Energy and Water Development:
FY2008 Appropriations
name redacted, Coordinator
Specialist in Energy Policy
January 31, 2008

Congressional Research Service
7-....
www.crs.gov
RL34009

CRS Report for Congress
Prepared for Members and Committees of Congress

Energy and Water Development: FY2008 Appropriations

Summary
The Energy and Water Development appropriations bill provides funding for civil works projects
of the Army Corps of Engineers (Corps), the Department of the Interior’s Bureau of Reclamation
(BOR), the Department of Energy (DOE), and a number of independent agencies.
Key budgetary issues involving these programs include
•

the distribution of Army Corps of Engineers appropriations across the agency’s
authorized construction and maintenance activities (Title I);

•

support of major ecosystem restoration initiatives, such as Florida Everglades
(Title I) and California “Bay-Delta” (CALFED) (Title II);

•

funding for the proposed national nuclear waste repository at Yucca Mountain,
Nevada, and proposals to store nuclear spent fuel temporarily (Title III: Nuclear
Waste Disposal); and

•

the Administration’s proposed Global Nuclear Energy Partnership to supply
plutonium-based fuel to other nations (Title III: Nuclear Energy).

The FY2008 Energy and Water Development bill was enacted as Division C of the Consolidated
Appropriations Act for FY2008 (P.L. 110-161). The omnibus funding measure was passed by
Congress December 19, 2007, and signed by the President December 26, 2007. The act provides
$31.4659 billion for Energy and Water programs, about $1 billion below the FY2007
appropriation and about $500 million above the Administration’s request.
The House Appropriations Committee reported out its FY2008 Energy and Water Development
Appropriations bill, H.R. 2641 (H.Rept. 110-185), on June 6, 2007. The bill as reported did not
contain indications of funding for specific projects. On June 20 the bill was debated on the House
floor, but was not voted on pending submission by the Appropriations Committee of a supplement
specifying funding for individual projects. That supplement was voted by the committee July 12,
and the House approved the bill July 17, 2007.
The Senate Subcommittee on Energy and Water Development Appropriations approved its
version of the bill on June 26, and the full Senate Appropriations Committee approved it June 28,
2007 (S. 1751, S.Rept. 110-127).

Congressional Research Service

Energy and Water Development: FY2008 Appropriations

Contents
Most Recent Developments.........................................................................................................1
Status..........................................................................................................................................1
Overview ....................................................................................................................................1
Title I: Army Corps of Engineers.................................................................................................3
Key Policy Issues—Corps of Engineers ................................................................................3
Project Backlog and Agency Priorities.............................................................................3
Everglades ......................................................................................................................6
Hurricane Katrina Repairs and Coastal Louisiana Restoration .........................................6
Title II: Department of the Interior ..............................................................................................6
Central Utah Project and Bureau of Reclamation: Budget In Brief .........................................7
Key Policy Issues—Bureau of Reclamation...........................................................................8
Background ....................................................................................................................8
CALFED ........................................................................................................................9
Loan Guarantee Program.................................................................................................9
Security ..........................................................................................................................9
Water 2025.................................................................................................................... 10
General Provisions ........................................................................................................ 10
Title III: Department of Energy ................................................................................................. 10
Key Policy Issues—Department of Energy.......................................................................... 12
Energy Efficiency and Renewable Energy ..................................................................... 13
Electricity Delivery and Energy Reliability ................................................................... 14
Nuclear Energy ............................................................................................................. 15
Fossil Energy Research, Development, and Demonstration............................................ 20
Strategic Petroleum Reserve.......................................................................................... 22
Science ......................................................................................................................... 23
Nuclear Waste Disposal................................................................................................. 25
Loan Guarantees ........................................................................................................... 26
Nuclear Weapons Stockpile Stewardship ....................................................................... 26
Nonproliferation and National Security Programs.......................................................... 37
Environmental Management.......................................................................................... 40
Power Marketing Administrations ................................................................................. 47
Title IV: Independent Agencies.................................................................................................. 48
Key Policy Issues—Independent Agencies .......................................................................... 49
Nuclear Regulatory Commission................................................................................... 49
For Additional Reading ............................................................................................................. 50
CRS Products...................................................................................................................... 50

Tables
Table 1. Status of Energy and Water Development Appropriations, FY2008 ................................1
Table 2. Energy and Water Development Appropriations, FY2001 to FY2008 .............................2
Table 3. Energy and Water Development Appropriations Summary .............................................2

Congressional Research Service

Energy and Water Development: FY2008 Appropriations

Table 4. Energy and Water Development Appropriations Title I: Army Corps of
Engineers .................................................................................................................................3
Table 5. Energy and Water Development Appropriations Title II: Central Utah Project
Completion Account ................................................................................................................7
Table 6. Energy and Water Development Appropriations Title II: Bureau of Reclamation ...........7
Table 7. Energy and Water Development Appropriations Title III: Department of Energy ......... 11
Table 8. Energy Efficiency and Renewable Energy Programs .................................................... 14
Table 9. Fossil Energy Research and Development Programs .................................................... 20
Table 10. Energy Policy Act of 2005 Title IV Authorization....................................................... 22
Table 11. Funding for Weapons Activities.................................................................................. 27
Table 12. NNSA Future Years Nuclear Security Program........................................................... 27
Table 13. DOE Defense Nuclear Nonproliferation Programs ..................................................... 38
Table 14. Environmental Management Program Appropriations ................................................ 43
Table 15. Office of Legacy Management Appropriations ........................................................... 47
Table 16. Energy and Water Development Appropriations Title IV: Independent
Agencies ................................................................................................................................ 48

Contacts
Author Contact Information ...................................................................................................... 51
Key Policy Staff........................................................................................................................ 51

Congressional Research Service

Energy and Water Development: FY2008 Appropriations

Most Recent Developments
The FY2008 Energy and Water Development bill was enacted as Division C of the Consolidated
Appropriations Act for FY2008 (P.L. 110-161). The omnibus funding measure was passed by
Congress December 19, 2007, and signed by the President December 26, 2007. The act provides
$31.4659 billion for Energy and Water programs, about $1 billion below the FY2007
appropriation and about $500 million above the Administration’s request.
The Bush Administration’s FY2008 budget request was released in February 2007. The House
Appropriations Committee reported out its FY2008 Energy and Water Development
Appropriations bill, H.R. 2641, on June 6, 2007. The bill as reported did not contain indications
of funding for specific projects. On June 20 the bill was debated on the House floor, but was not
voted on pending submission by the Appropriations Committee of a supplement specifying
funding for individual projects. That supplement was voted out by the committee July 12, and the
House approved the bill July 17, 2007.
The Senate Subcommittee on Energy and Water Development Appropriations approved its
version of the bill, S. 1751, on June 26, and the full Senate Appropriations Committee approved it
June 28.
Energy and Water Development programs were funded for FY2007 in the Revised Continuing
Appropriations Resolution, 2007 (H.J.Res. 20, P.L. 110-5). On March 16, 2007, the Department
of Energy (DOE) submitted its “operating plan” to Congress, detailing funding for individual
programs not specifically identified in P.L. 110-5.

Status
Table 1. Status of Energy and Water Development Appropriations, FY2008
Subcommittee
Markup
House

Senate

5/30/07

6/26/07

Final
Approval

House
Report

House
Passage

Senate
Report

Senate
Passage

Conf.
Report

House

Senate

H.Rept.
110-185

7/17/07

S.Rept.
110-127

None

None

12/19/07

12/18/07

Public
Law
P.L.
110-161

Overview
The Energy and Water Development bill includes funding for civil works projects of the U.S.
Army Corps of Engineers (Corps), the Department of the Interior’s Central Utah Project (CUP)
and Bureau of Reclamation (BOR), the Department of Energy (DOE), and a number of
independent agencies, including the Nuclear Regulatory Commission (NRC) and the Appalachian
Regional Commission (ARC).

Congressional Research Service

1

Energy and Water Development: FY2008 Appropriations

Table 2 includes budget totals for energy and water development appropriations enacted for
FY2001 to FY2008.
Table 2. Energy and Water Development Appropriations, FY2001 to FY2008
(budget authority in billions of current dollars)
FY01

FY02

FY03

FY04

FY05

FY06

FY07

FY08

23.9

25.2

26.1

26.7

30.2a

36.7b

29.4

31.5

Note: Figures represent current dollars, exclude permanent budget authorities, and reflect rescissions.
a.

For FY2005 and later, total includes DOE programs formerly funded in the Interior and Related Agencies
appropriations bill and transferred to the Energy and Water Development appropriations bill.

b.

Includes $6.6 billion in emergency funding for the Corps of Engineers.

Table 3 lists totals for each of the bill’s four titles. It also lists several “scorekeeping” adjustments
of accounts within the four titles, reflecting various expenditures or sources of revenue besides
appropriated funds. These adjustments affect the total amount appropriated in the bill but are not
included in the totals of the individual titles. Amounts listed in this report are derived from the
Administration’s FY2008 Congressional Budget Requests, from H.Rept. 110-185, to accompany
H.R. 2641, from the S.Rept. 110-127, to accompany S. 1751, and from the explanatory statement
for the FY2008 Consolidated Appropriations Act (H.R. 2764, P.L. 110-161).
Table 3. Energy and Water Development Appropriations Summary
($ millions)
Title

FY2007

FY2008
Request

House

Senate

Final

Title I: Corps of Engineers

$5,340.2

$4,871.0

$5,584.4

$5,448.1

$5,587.1

Title II: CUP & BOR

1,054.7

1,001.4

1,065.4

1,144.3

1,150.9

Title III: Department of Energy

24,228.2

24,762.7

25,243.1

25,896.9

24,446.6

Title IV: Independent Agencies

306.0

251.5

237.8

301.0

281.3

30,794.1

30,863.6

32,130.7

32,790.2

31,465.9

(44.0)

(51.6)

(51.6)

(51.6)

NA

Colorado River Basins, WAPA

(23.0)

(23.0)

(23.0)

(23.0)

NA

Uranium Fund

(446.0)

(463.0)

(463.0)

(463.0)

NA

Excess Fees FERC

(19.2)

(17.5)

(17.5)

(17.5)

NA

30,294.9

30,308.5

31,575.6

32,235.1

NA

E&W Subtotal
Scorekeeping Adjustments
Undistributed Pay Raise

33.0

Title II
Central Valley
Title III

E&W Total

Source: Administration FY2008 budget request; H.Rept. 110-185; S.Rept. 110-127. Consolidated
Appropriations Act, 2008, P.L. 110-161.
Note: Details may not add to totals due to rounding. Includes the across-the board rescission (Sec. 312). NA:
Not available.

Congressional Research Service

2

Energy and Water Development: FY2008 Appropriations

Tables 4 through 16 provide budget details for Title I (Corps of Engineers), Title II (Department
of the Interior), Title III (Department of Energy), and Title IV (independent agencies) for
FY2005-FY2006.

Title I: Army Corps of Engineers
P.L. 110-161 provided $5.587 billion for the U.S. Army Corps of Engineers; it was an increase
over the Administration’s budget request of $4.871 billion and 5% above the FY2007
appropriations (not including supplemental funds) of $5.340 billion. The omnibus funding
measure rescinded a total of $4.9 million of prior appropriations for the Corps.
Funding for the Corps’ civil works program is often a contentious issue between the
Administration and Congress, with final appropriations typically providing more funding than
requested, regardless of which political party controls the White House and Congress. Generally
around 85% of the appropriations for the agency is directed to specific projects. Often Congress
will direct funding to projects not included in the Administration’s request.
Table 4. Energy and Water Development Appropriations
Title I: Army Corps of Engineers
($ millions)
FY2007

FY2008
Request

Housea

Senate
Comm.

Final

Investigations and Planning

$162.9

$90.0

$120.0

$172.1

$167.2

Construction

2,336.5

1,523.0

2,004.2

2,059.5

2,289.3

396.6

260.0

278.0

375.0

2,243.6

1,975.1

2,471.0

2,655.2

2,292.0

387.4

Regulatory

159.3

180.0

180.0

180.0

180.0

General Expenses

167.2

177.0

171.0

175.0

175.0

FUSRAPb

138.7

130.0

130.0

140.0

140.0

Flood Control and Coastal Emergencies

—

40.0

40.0

50.0

0.0

Office of the Asst. Secretary of the Army

4.0

—

6.0

4.5

4.5

5,340.2

4,871.0

5,584.4

5,448.1

5,587.1

Program

Mississippi River & Tributaries
Operation and Maintenance (O&M)

Total Title I

Sources: FY2008 Budget Request; Army Corps of Engineers Civil Works: FY2007 Work Plan (March 19, 2007);
H.Rept. 110-185; S.Rept. 110-127.
a.

These figures account for rescissions.

b.

“Formerly Utilized Sites Remedial Action Program.”

Key Policy Issues—Corps of Engineers
Project Backlog and Agency Priorities
The policy debate on how to structure the Corps’ budget and priorities is ongoing. The Corps civil
works program has been criticized by some observers as an agglomeration of projects with no

Congressional Research Service

3

Energy and Water Development: FY2008 Appropriations

underlying design. These observers see the Corps’ backlog of authorized activities as an example
of this lack of focus. Prior to enactment of the $23 billion authorization bill for the agency known
as the Water Resources Development Act (WRDA) in November 2007, estimates of the backlog’s
size had varied from $11 billion to more than $60 billion, depending on which projects are
included. Although some observers view the backlog as nothing more than a Corps “to do” list,
others are concerned that projects face construction delays and related cost overruns as available
appropriations are spread across an increasing portfolio of projects.
The Corps’ backlog of authorized projects and concerns about the fiscal planning and
management of the agency’s portfolio contribute to support for performance-based criteria for
structuring the agency’s budget and for concentrated appropriations on a small set of priority
projects. Others also express concerns about the agency’s fiscal planning and management, yet
reject both the use of performance-based criteria that have been proposed and the focus on 6 to 10
priority projects. These critics argue that the criteria used are too simplistic and that basing the
Corps’ budget on performance criteria does not produce an integrated multiyear program for the
agency. They also argue that the focus on priority projects has resulted in a disproportionate
amount of the agency’s budget being concentrated on a few projects, resulting in less investment
in other authorized, cost-beneficial projects and in those regions of the country that do not have
priority projects.

Performance-Based Budgeting
One way recent Administration requests have tried to address the backlog of Corps projects has
been the application of a performance-based budgeting approach for determining which projects
to include in its requests for construction and maintenance funds; the performance measures were
based on their economic and environmental returns and protection of human safety. The
construction projects selected for funding were chosen largely on their having either a high ratio
of benefits to costs, or, for environmental projects, a high cost-effectiveness. The FY2008 budget
request continued the Administration’s movement toward presenting the agency’s budget
according to “business lines” (e.g., navigation, flood control, recreation, hydropower). For
example, of the $4.871 billion budget request, $2.009 billion (41%) is for commercial navigation,
$1.384 billion (28%) is for flood and coastal storm damage reduction, and $274 million (6%) and
$110 million (2%) are for the agency’s relatively new roles in aquatic ecosystem restoration and
environmental stewardship, respectively. The agency’s regulatory responsibilities represent $180
million, 4% of the agency’s budget.
Although little of the debate about performance-based budgeting is reflected in the omnibus
report language, the earlier House and Senate reports illustrated differing opinions about how best
to manage the Corps’ budget. H.Rept. 110-185 generally supported the Administration
performance-based budgeting approach; it states: “While the Committee agrees in large part with
the prioritization of projects, it does not believe the level of funding provided by the
Administration is sufficient to meet the needs of the Nation.” In contrast, the Senate
Appropriations Committee report stated: “From the Committee’s perspective, the Corps’ budget
seems to be developed exactly in the opposite manner that it should be.” It then echoes the House
by stating “the country needs to invest more heavily in its water resources.” The Senate
Appropriations Committee report criticized the Administration’s focus on a small number of
projects, and its lack of support for projects at the different stages of development (e.g.,
planning). It also questioned the effect that focusing on a few projects would have on the ability
and interest in partnering with the Corps of the local project sponsors for the Corps’ other
authorized, but unbudgeted, projects and studies.

Congressional Research Service

4

Energy and Water Development: FY2008 Appropriations

Priority Projects and New Starts
To address the backlog of authorized Corps activities, the Administration’s request limited the
number of new activities started to only two planning activities and one maintenance assessment.
The President’s request would fund construction projects that could be completed in FY2008 and
six projects considered by the Administration to be priorities, similar to the President’s FY2007,
FY2006, and FY2005 requests.
Although little of the debate about new starts is reflected in the omnibus report language, the
earlier House and Senate reports illustrated differing opinions about how best to manage the
Corps’ budget. H.Rept. 110-185 expressed general support for the Administration’s no new start
policy as applied to the FY2008 budget for the Corps. The exception noted by the Committee is
that it “will consider funding for the major rehabilitation” at specific locks on the Ohio and
Mississippi River systems because it “does not view the rehabilitation of existing infrastructure as
a new construction start ... but rather a necessity.” The Senate Appropriations Committee
recommended a limited number of new construction starts. Numerous construction projects that
were not included in the President’s request were included among the projects funded in the
omnibus report language.

Financial Management and O&M Budgeting
Unlike previous budget requests, the FY2007 and FY2008 requests did not specify the amount
that individual Corps projects would receive for O&M. Instead, the Administration’s recent
requests divide the country into 21 regions and specify O&M funding for each region for six
different categories of activities—commercial navigation, flood and coastal storm damage
reduction, environment, hydropower, recreation, and water supply. The Corps has provided
estimates of how much individual projects are expected to receive; however, these estimates are
not part of the agency’s formal budget request and budget justification package. This budgeting
approach appears to allow the agency flexibility to move money across projects within the region
as O&M needs arise, without being subject to many of the reprogramming restrictions put into
place with the agency’s FY2006 appropriations. Some project stakeholders are likely to be
uncomfortable as a result of the decreased certainty in the O&M funding available for particular
projects under this regional O&M budgeting approach.
Although little of the debate about new starts is reflected in the omnibus report language, the
earlier House and Senate reports illustrated differing opinions about how best to manage the
Corps’ budget. H.Rept. 110-185 was critical of how the Administration developed its request for
each of the 21 regions, and it adopts the regional approach to O&M funding by specifying an
O&M funding level for each region. The Senate Appropriations Committee recommended
rejecting the regional budgeting for O&M, arguing that this budgeting tactic serves no real
purpose other than circumventing reprogramming guidance and that Corps projects (not regions)
are authorized by Congress. The omnibus report language did not adopt the O&M regions.
Instead it directed the Corps to prepare integrated O&M budgets for four regions—the Ohio
River, the Great Lakes, the Texas coast, and the California coast.
The omnibus report language also provided direction to the Corps on reprogramming of funds,
five-year budget plans, budget submission materials, and the use of multi-year continuing
contracts.

Congressional Research Service

5

Energy and Water Development: FY2008 Appropriations

Everglades
The Corps plays a significant coordination role in the restoration of the Central and Southern
Florida ecosystem. The agency received $131 million for FY2008 Everglades restoration
activities in the omnibus report language. The FY2008 budget request was for $162 million,
down from the $164 million requested and provided for FY2007.
The FY2008 funds consist of Central and Southern Florida Project ($82 million, down from the
$91 million requested), Kissimmee River Restoration Project ($31 million, down from the $33
million requested), Everglades and South Florida Restoration Projects ($8 million, up from the $4
million requested), and Modified Water Deliveries Project ($10 million, down from the $35
million requested). FY2006 was the first year that funds for the Mod Waters project were
included in the Corps budget request and enacted appropriations; previously, the project was
funded solely through Department of the Interior appropriations. The omnibus report language
noted appropriators’ concerns regarding the changing design of the Mod Waters project. The
report directs the Corps to submit to the Appropriations Committees its plan for completion of
Mod Waters, and it provides direction to Interior regarding its funding of the project. (For more
information, see CRS Report RS21331, Everglades Restoration: Modified Water Deliveries
Project, by (name redacted).)
In addition to funding for Corps activities through Energy and Water Development
appropriations, federal activities in the Everglades are funded through Department of the Interior
appropriations bills. Concerns regarding the level of appropriations and progress in the restoration
effort are discussed in CRS Report RS20702, South Florida Ecosystem Restoration and the
Comprehensive Everglades Restoration Plan, by (name redacted) and (name redacted).

Hurricane Katrina Repairs and Coastal Louisiana Restoration
The Corps is responsible for much of the repair and fortification of the hurricane protection
system of coastal Louisiana, particularly in the greater New Orleans area; to date, most of the
Corps’ work on the region’s hurricane protection system has been funded through emergency
supplemental appropriations, not through the annual appropriations process. The Corps has
received more than $7 billion in emergency supplemental funds for flood protection and water
resources repair and recovery work. The vast majority of the enacted and requested supplemental
appropriations for the region are for structural hurricane defenses; coastal wetlands restoration
activities by the Corps have received less than $200 million of the enacted Katrina appropriations.
The 110th Congress enacted emergency supplemental legislation with an additional $1.64 billion
for the Corps, largely to continue repairs and accelerate completion of flood and storm damage
reduction projects in the New Orleans and south Louisiana area. Previously appropriated funds
were insufficient to complete these activities because of increased costs, improved data on costs,
and other factors.

Title II: Department of the Interior
The Department of the Interior requested that Congress provide an increase in funding for the
Central Utah Project (CUP) Completion Account and a reduction for the Bureau of Reclamation
(BOR) for FY2008. The total approved by P.L. 110-161 for Title II funding is $1.1509 billion—
$149.5 million above the President’s request.

Congressional Research Service

6

Energy and Water Development: FY2008 Appropriations

Table 5. Energy and Water Development Appropriations
Title II: Central Utah Project Completion Account
($ millions)
FY2007

FY2008
Request

House

Senate
Comm.

P.L.
110-161

Central Utah Project Construction

$31.4

$40.4

$40.4

$40.4

$40.4

Mitigation and Conservation Activities

0.9

1.0

1.0

1.0

1.0

Oversight & Administration

1.7

1.6

1.6

1.6

1.6

34.0

43.0

43.0

43.0

43.0

Program

Total, Central Utah Project

Source: Central Utah Project Completion Act, FY2008 Budget Justification. H.Rept. 110-185; S.Rept. 110-127.,
P.L. 110-161.

Table 6. Energy and Water Development Appropriations
Title II: Bureau of Reclamation
($ millions)
FY2007

FY2008
Request

House

Senate
Comm.

P.L.
110-161

$874.7

$816.2

$871.2

$950.1

$949.9

Policy & Administration

57.3

58.8

58.8

58.8

58.8

CVP Restoration Fund (CVPRF)a

52.1

59.1

59.1

51.6

59.1

Legislative Proposal—SJRRFb

—

(7.5)

(7.5)

0.0

0.0

Calif. Bay-Delta (CALFED)

36.6

31.8

40.8

40.8

40.1

1,020.7

958.4

1,022.4

1,101.3

1,107.9

CVP Collectionsa

(43.9)

(51.6)

(51.6)

(51.6)

(51.6)

Net Current Authority

976.8

906.8

970.8

1,049.7

1,056.3

1,054.7

1,001.4

1,065.4

1,144.3

1,150.9

Program
Water and Related Resources

Gross Current Authority

Total, Title II

Source: Bureau of Reclamation FY2008 Budget Justification. H.Rept. 110-185; S.Rept. 110-127,P.L. 110-161.
a.

In its request, BOR lists CVP Collections as an “offset.” Congress does not follow this procedure.

b.

FY2008 reflects a legislative proposal to redirect $7.5 million collected from Friant Division water users to
the new San Joaquin River Restoration Fund.

Central Utah Project and Bureau of Reclamation: Budget In Brief
The Administration requested $43.0 million for the CUP Completion Account for FY2008 (Table
5). The FY2008 request for BOR totaled $958.4 million in gross current budget authority. This
amount is $62.3 million less than enacted for FY2007. The FY2008 request included “offsets” of
$51.6 million for the Central Valley Project (CVP) Restoration Fund, yielding a “net” current
authority of $906.8 million for BOR. The total budget request for Title II funding, Central Utah
Project and Bureau of Reclamation, was $1.0014 billion.
BOR’s single largest account, Water and Related Resources, encompasses the agency’s traditional
programs and projects, including construction, operations and maintenance, the Dam Safety
Program, Water and Energy Management Development, and Fish and Wildlife Management and

Congressional Research Service

7

Energy and Water Development: FY2008 Appropriations

Development, among others. The Administration requested $816.2 million for the Water and
Related Resources Account for FY2008 (Table 6). This amount is $58.5 million (6.7%) less than
enacted for FY2007.
The House Appropriations Committee recommended funding at the amount reflected in the
President’s Budget for CUP (Table 5), Policy and Administration, and the CVP (Table 6). The
Committee recommended increases of $55 million for Water and Related Resources and $9
million for CALFED (Table 6). The Committee initially made no recommendations for specific
water projects within Water and Related Resources, indicating that it would consider individual
project allocations after further analysis. The Committee’s final recommendation for Water and
Related Resources matched the President’s request for facilities and operations and maintenance
(O&M). The additional funding recommended by the Committee was on the Resource
Management side of the Water and Related Resources budget.
The Senate Appropriations Committee recommended funding at the amount reflected in the
President’s Budget for the CUP and Policy and Administration. Recommended funding for Water
and Related Resources is $134 million more than the President’s request and $79 million more
than the level recommended by the House. The CALFED recommendation, an increase of $9
million over the President’s request, matches the House. The Committee provided $7.5 million
less funding for the CVP Restoration Fund, indicating that the Administration’s proposed San
Joaquin River Restoration Fund (which was included as an offset) was not yet authorized.
The House and Senate agreed on final appropriations for the BOR that were close to the levels
recommended by one or both chambers previously. Policy and Administration remains unchanged
from the President’s request at $58.8 million. The CVP Restoration Fund remains at the level
requested by the President, $59.1 million. However $7.5 million that the Administration and
House intended for the proposed San Joaquin River Restoration Fund (SJRRF) was reallocated to
other CVP Restoration Fund programs because the SJRRF was not authorized. Water and Related
Resources and CALFED are both funded at levels similar to those passed by the Senate: $949.9
and $40.1 respectively. The total approved by P.L. 110-161 for Title II funding is $1.1509
billion—$149.5 million above the President’s request.

Key Policy Issues—Bureau of Reclamation
Background
Most of the large dams and water diversion structures in the West were built by, or with the
assistance of, the Bureau of Reclamation. Whereas the Army Corps of Engineers built hundreds
of flood control and navigation projects, BOR’s mission was to develop water supplies, primarily
for irrigation to reclaim arid lands in the West. Today, BOR manages hundreds of dams and
diversion projects, including more than 300 storage reservoirs in 17 western states. These projects
provide water to approximately 10 million acres of farmland and 31 million people. BOR is the
largest wholesale supplier of water in the 17 western states and the second-largest hydroelectric
power producer in the nation. BOR facilities also provide substantial flood control, recreation,
and fish and wildlife benefits. At the same time, operations of BOR facilities are often
controversial, particularly for their effect on sensitive fish and wildlife species and conflicts
among competing water users.

Congressional Research Service

8

Energy and Water Development: FY2008 Appropriations

CALFED
The Administration requested $31.8 million for the California Bay-Delta Restoration Account
(Bay-Delta, or CALFED) for FY2008 (Table 6). The bulk of the requested funds were targeted at
three main program areas, including the environmental water account, the storage program, and
conveyance. The remainder of the request was allocated for science, water quality, planning and
management, and ecosystem restoration.
The House Appropriations Committee recommended that all programs within CALFED be
funded at the level in the FY2008 budget request, except for a $1 million reduction in Planning
and Management. The Committee also recommended $5 million each for Water Use Efficiency
and Delta Levees, which were not in the President’s Budget. The Committee indicated that
funding for Delta Levees is to be transferred to the Corps of Engineers. The recommended $10
million addition and $1 million reduction result in a recommended net increase of $9 million over
the President’s request.
The Senate Appropriations Committee approved funding at the amount recommended by the
House Appropriations Committee. The final appropriations level agreed to by both chambers is
$40.1 million for CALFED. (For more information on CALFED, see CRS Report RL31975,
CALFED Bay-Delta Program: Overview of Institutional and Water Use Issues, by (name redac
ted) and (name redacted).)

Loan Guarantee Program
BOR requested $1 million in FY2008 to establish a loan guarantee program. Reclamation is
establishing this program to guarantee private loans to water districts that have responsibility for
funding O&M or rehabilitation costs on Reclamation facilities. Because the federal government
retains title to these projects, it may be difficult for water users to secure loans from private
lenders. The House and Senate Appropriations Committees recommended funding this program at
the level requested.

Security
Under BOR’s Water and Related Resources account, the Administration requested $35.5 million
for site security for FY2008, a decrease of $4.1 million compared with that enacted for FY2007.
The bulk of the request is for facility operations/security. Funding covers activities such as
administration of the security program (e.g., surveillance and law enforcement), antiterrorism
activities, and physical emergency security upgrades. (For more information, see CRS Report
RL32189, Terrorism and Security Issues Facing the Water Infrastructure Sector, by (name re
dacted).)
The FY2008 request assumed that annual costs for guard and patrol activities would be treated as
project O&M costs, and hence would be reimbursable based on project cost allocations. These
costs were estimated to be $18.9 million in FY2008, of which $11.6 million would be in up-front
funding from power customers and $7.3 million would be appropriated funds which are
reimbursed by irrigation, municipal, and industrial users and other customers. BOR would
continue to treat facility fortification and antiterrorism management-related expenses as
nonreimbursable.

Congressional Research Service

9

Energy and Water Development: FY2008 Appropriations

The House and Senate Appropriations Committees both recommended funding this program at
the level requested, and the final appropriation was $35.0 million.

Water 2025
This program, part of the Water and Related resources account, is intended to reduce water use
conflicts by increasing certainty, diversity, and flexibility of water supplies. In 2008, BOR plans
to focus program resources on areas where water conflicts exist currently or are likely to develop
in the future. The 2008 budget request for this program is $11.0 million, a decrease of $3.5
million from FY2007. The House Appropriations Committee did not include funding for Water
2025, citing a lack of authorization for the program (however, see General Provisions below for
Water 2025 authorization). The Senate Appropriations Committee recommended $14 million for
Water 2025, indicating that funds above the President’s $11 million request are intended to
provide for efficiency and water improvements related to the Middle Rio Grande Conservancy
District. Ultimately, $5.9 million was agreed upon by both chambers.

General Provisions
Final appropriations language includes a number of general provisions authorizing approximately
$66 million in Nevada for water projects such as dam removal, fish passage, municipal water
treatment, and watershed inventory (§208). Section 210 authorizes two water reuse projects: the
Inland Empire and Cucamonga Valley in California. A total of $30 million is authorized for these
projects. An additional $20 million is authorized for the Southern California Desert Region
Integrated Water and Economic Sustainability Program (§214).
Though no funding is specified, §204 authorizes the Secretary of the Interior, acting through the
Commissioner of Reclamation, to fund grants at a 50% cost share aiding irrigation or water
districts and states in their planning, design, and construction of projects to conserve water or
improve water use efficiency. This language appears to authorize the BOR’s Water 2025 program.

Title III: Department of Energy
The Energy and Water Development bill since FY2005 has funded all DOE’s programs. Major
DOE activities historically funded by the Energy and Water bill include research and
development on renewable energy and nuclear power, general science, environmental cleanup,
and nuclear weapons programs, and now includes programs for fossil fuels, energy efficiency, the
Strategic Petroleum Reserve, and energy statistics, which formerly had been included in the
Interior and Related Agencies appropriations bill.

Congressional Research Service

10

Energy and Water Development: FY2008 Appropriations

Table 7. Energy and Water Development Appropriations
Title III: Department of Energy
($ millions)
FY2007

FY2008
Request

House

Senate

Conf.

$1,474.3

$1,236.2

$1,873.8

$1,715.6

$1,722.4

Electricity Delivery & Energy Reliability

137.0

114.9

134.2

169.4

138.6

Nuclear Energy

482.2

801.7

759.2

719.6

961.7

Environment, Safety, Healtha

27.8

—

—

—

—

Legacy Management

33.2

35.1

—

35.1

33.9

2,154.5

2,187.9

2,767.2

2,639.7

2,856.5

592.6

566.8

708.8

808.1

742.8

Clean Coal Technology (Deferral)

—

(58.0)

(58.0)

(58.0)

(58.0)

Naval Petrol. & Oil Shale Reserves

21.3

17.3

17.3

21.3

20.3

Strategic Petroleum Reserve

164.4

331.6

163.5

163.5

186.8

Northeast Home Heating Oil Reserve

5.0

5.3

5.3

12.8

12.3

Energy Information Administration

90.7

105.1

105.1

105.1

95.5

Non-Defense Environmental Cleanup

349.7

180.9

286.0

195.4

182.3

Uranium Decontamination and
Decommissioning Fund

556.6

573.5

618.8

573.5

622.2

High Energy Physics

751.8

782.2

782.2

789.2

688.0

Nuclear Physics

422.8

471.3

471.3

471.3

433.0

1,250.3

1,498.5

1,498.5

1,512.3

1,270.0

Bio. & Env. R&D

483.5

531.9

581.9

605.8

544.0

Fusion

319.0

427.9

427.9

427.9

287.0

Advanced Scientific Computing

283.4

340.2

340.2

334.9

351.0

Other

292.2

351.5

417.7

361.5

450.3

Adjustments

(5.6)

(5.6)

(5.6)

(5.6)

(5.6)

Total, Science

3,797.3

4,397.9

4,514.1

4,497.3

4,017.7

Program
Energy Supply & Conservation
Energy Efficiency & Renewables

Total, Energy Supply & Conservation
Fossil Energy R&D

Sciencea

Basic Energy Sciences

Nuclear Waste Disposal

99.2

202.5

202.5

202.5

187.3

Environment, Safety, Healthb

—

—

31.8

—

—

Departmental Admin. (net)

153.8

148.6

143.0

146.8

148.4

Office of Inspector General

41.8

48.4

47.7

47.7

46.1

—

8.4

—

8.4

4.5

Innovative Technology Loan Guarantee

Congressional Research Service

11

Energy and Water Development: FY2008 Appropriations

Program

FY2007

FY2008
Request

House

Senate

Conf.

National Nuclear Security Administration (NNSA)
Weapons

6,275.6

6,511.3

5,879.1

6,489.0

6,297.5

Nuclear Nonproliferation

1,818.3

1,672.6

1,683.7

1,872.6

1,336.9

Naval Reactors

781.8

808.2

808.2

808.2

774.7

Office of Administrator

340.3

394.7

415.9

394.7

402.2

Total, NNSA

9,216.0

9,386.8

8,786.9

9,564.5

8,811.2

Defense Environmental Cleanup

5,731.8

5,363.9

5,766.6

5,690.4

5,349.4

Other Defense Activities

636.3

764.0

604.3

765.5

754.4

Defense Nuclear Waste Disposal

346.5

292.0

292.0

242.0

199.2

15,930.6

15,806.8

15,449.8

16,262.4

15,114.1

Southeastern

5.6

6.5

6.5

6.5

6.4

Southwestern

30.0

30.4

30.4

30.4

30.2

Western

232.3

201.0

201.0

231.0

228.9

2.7

2.5

2.5

2.5

2.5

Total, PMAs

270.6

240.4

240.4

270.4

267.9

FERC
(revenues)

221.9
(221.9)

255.4
(255.4)

255.4
(255.4)

255.4
(255.4)

258.1
(258.1)

24,228.2

24,762.7

25,243.1

25,896.9

24,446.6

Total, Defense Activities
Power Marketing Administrations (PMA)

Falcon & Armistad O&M

Total, Title III

Sources: DOE FY2008 Congressional Budget Request, February 2007; H.Rept. 110-185; S.Rept. 110-127.
Consolidated Appropriations Act, 2008, P.L. 110-161.
a.

Figures in italic for the Office of Science have been adjusted by CRS for the across-the board rescission
(Sec. 312) but not for a specific rescission of $44.6 million in prior-year funds.

b.

Environment, Safety and Health moved from Energy Supply and Conservation for FY2008.

The Administration’s FY2008 request for DOE programs was $24.7627 billion, compared with
$24.2282 billion appropriated for FY2007. The final omnibus act provides $24.4466 billion, $218
million above FY2007 but $316 million below the request. The FY2008 total reflects an acrossthe-board rescission on all DOE programs imposed by Section 312 of Title III, Division C of the
act. Section 312 requires all funding levels in the explanatory statement to be reduced by 1.6% of
earmarked funds and 0.91% for all other funding. Summary tables at the end of the explanatory
statement reflect the Section 312 rescission, but the detailed tables do not. DOE is required to
submit a report to the Appropriations Committees within 30 days with detailed numbers reflecting
the rescission.

Key Policy Issues—Department of Energy
DOE administers a wide variety of programs with different functions and missions. In the
following pages, the programs are described and major issues are identified, in approximately the
order in which they appear in the budget tables in Table 7.

Congressional Research Service

12

Energy and Water Development: FY2008 Appropriations

Energy Efficiency and Renewable Energy
The omnibus appropriations act provides $1,722.4 million for DOE’s Office of Energy Efficiency
and Renewable Energy (EERE) for FY2008, which is $486.2 million more than the request and
$248.1 million more than the FY2007 appropriation. Table 8 shows the FY2008 funding amounts
by program. Relative to FY2007, the FY2008 appropriation provides key increases of $25.0
million for Vehicles, $22.7 for Weatherization, $17.5 million for Hydrogen, $14.8 million for
Geothermal, $9.9 million for Water (Marine and Hydrokinetic) technologies, and $9.1 million for
Solar. The FY2008 appropriation also includes $30.9 million less for Facilities. This reduction
does not affect the level of funding for facilities operations; instead, it reflects a reduced level of
spending on construction of new buildings. The main cuts in FY2008 are $9.5 million less for
International Renewables (which terminates the program) and $5.4 million less for State Grants.
As Table 8 shows, DOE’s FY2008 request sought $1,236.2 million for the EERE programs. The
Administration’s Advanced Energy Initiative (AEI, part of the American Competitiveness
Initiative) “aims to reduce America’s dependence on imported energy sources.” The AEI includes
hydrogen, biofuels, and solar energy initiatives that are supported by programs in EERE. The
Hydrogen Initiative aims to “facilitate a decision by industry to commercialize hydrogen
infrastructure and fuel cell vehicles by 2015.”1The Biofuels Initiative seeks to develop
transportation fuels, such as cellulosic ethanol. The Solar America Initiative’s goals are to cut the
cost of photovoltaics (PV) technology, increase its commercial use, and displace natural gas use
for electric power generation. The President’s 2007 State of the Union address set out a goal to
reduce gasoline use by 20% and to increase the production of “alternative” fuels, including
cellulosic ethanol, to 35 billion gallons by 2017. To support the AEI and those fuels goals, the
FY2008 EERE budget request proposed significant increases for the Biofuels, Hydrogen, and
Solar programs. 2 At hearings on the FY2008 DOE budget request, concerns were raised about
DOE’s proposed termination of the Geothermal and Hydropower programs. 3 The House approved
$1,873.8 million and the Senate Appropriations Committee approved $1,715.6 million for
FY2008 EERE programs.
The House Committee report includes several policy directives to EERE. First, on page 59, it
directs DOE to quantify and track the progress and impact of the investments in the EERE
portfolio and brief the Committee annually on the return on investment for each of the accounts.
Second, on page 60, the report directs DOE to implement an aggressive program that focuses on
using Historically Black Colleges and Universities and Hispanic Serving Institutions to deepen
the recruiting pool of diverse scientific and technical staff available to support the growing
renewable energy marketplace. Third, on page 65, within funding available for the State Energy
Program, the Committee directs DOE to implement section 140 of the Energy Policy Act of 2005
to support state-wide pilot programs that encourage reduced electricity and natural gas use.
The report of the Senate Appropriations Committee directs DOE to draw from available funds to
study and report on five special topics. First, on page 131, DOE is directed to conduct a study on
“the feasibility of increasing consumption of ethanol-blended gasoline with levels of ethanol
blends between 10%-25%, including a study of production and infrastructure constraints on
1

U.S. Executive Office of the President, Budget of the United States Government, Fiscal Year 2007, Appendix, p. 390.
Also see DOE, FY2007 Congressional Budget Request: Budget Highlights, p. 41.
2
The Energy Independence and Security Act (P.L. 110-140, H.R. 6) also addressed those goals.
3
Secretary Bodman’s Senate testimony is available at http://energy.senate.gov/public/_files/BodmanTestimony.pdf.

Congressional Research Service

13

Energy and Water Development: FY2008 Appropriations

increasing consumption.” Second, on page 131, the Committee requests that DOE prepare
updates on the National Biofuels Action Plan and deliver the final plan by the end of January
2008. Third, on pages 131-132, the Committee recommends that DOE report on its planned
procedure for holding a reverse auction for cellulosic biofuels grants, as directed by the Energy
Policy Act of 2005 (§942). Fourth, on page 134, the Committee directs DOE to study methods of
increasing the fuel efficiency of alternative fueled vehicles by improving their ability to use E-85
(85% ethanol) fuel. Fifth, on page 138, under the Electricity Program, the Committee encourages
DOE to identify the potential for distributed energy equipment to provide energy savings and
reduce transmission line losses. DOE is directed to focus the study on commercial potential.

Electricity Delivery and Energy Reliability
The FY2008 request included $114.9 million for the Office of Electricity Delivery and Energy
Reliability (OE). The House approved $134.2 million and the Senate Appropriations Committee
approved $169.4 million. The omnibus law provides $138.7 million. The Senate Committee
report directs OE to increase energy storage efforts in support of intermittent wind and solar
power production and to increase support for deployment of distributed generation equipment.
Table 8. Energy Efficiency and Renewable Energy Programs
($ millions)
FY2006

FY2007

FY2008
Request

FY2008
House

FY2008
SAppC

FY2008
Conf.

$153.5

$193.6

$213.0

$194.6

228.0

211.1

Biomass & Biorefinery Systems

89.8

199.7

179.3

250.0

244.0

198.2

Solar Energy

81.8

159.4

148.3

200.0

180.0

168.5

—Photovoltaics

58.8

—

137.3

149.0

145.3

136.7

Wind Energy

38.3

49.3

40.1

57.5

57.5

49.5

Geothermal Technology

22.8

5.0

0.0

44.3

25.0

19.8

Water Power (Hydro/Ocean)

0.5

0.0

0.0

22.0

10.0

9.9

Subtotal, Renew. & Hydrogen

386.6

606.9

580.6

768.4

744.5

657.0

Vehicle Technologies

178.4

188.0

176.1

235.4

230.0

213.0

Building Technologies

68.2

104.3

86.5

146.5

137.0

109.0

Industrial Technologies

55.9

56.6

46.0

57.0

57.0

64.4

Federal Energy Management

19.0

19.5

16.8

27.0

23.0

19.8

Subtotal, Efficiency R&D

321.4

368.4

325.4

465.9

447.0

406.2

Facilities & Infrastructure

26.1

107.0

7.0

195.7

7.0

76.2

Program Management

115.2

110.2

118.3

128.9

118.3

114.9

R&D Subtotal

849.2

1,192.6

1,031.3

1,558.9

1,316.8

1,254.3

—Weatherization Grants

242.6

204.6

144.0

245.6

240.6

227.2

—State Energy Grants

36.1

58.8

45.5

49.5

55.0

44.1

Program
Hydrogen Technologies

Federal Assistance

Congressional Research Service

14

Energy and Water Development: FY2008 Appropriations

Program

FY2006

FY2007

FY2008
Request

FY2008
House

FY2008
SAppC

FY2008
Conf.

—Renewables Deployment

38.2

18.4

15.4

19.9

12.0

10.9

—Cong.-Directed Assistancea

—

0.0

0.0

—

91.2

185.9

Federal Assistance Subtotal

316.9

281.7

204.9

314.9

398.8

468.1

Total Appropriation, EE & RE

1,166.1

1,474.3

1,236.2

1,873.8

1,715.6

1,722.4

158.2

137.0

114.9

134.2

169.4

138.7

Office of Electricity Delivery & Energy
Reliability (OE)b

Sources: DOE FY2007 Operating Plan; H.Rept. 110-185; S.Rept. 110-127; Joint Explanatory Statement on the
Consolidated Appropriations Act of 2007 (Cong. Record, Dec. 17, 2007, p. 15587 and p. H15940).
a.

In FY2006, there was $159.0 million in congressionally-directed funds spread over EERE accounts. For
FY2008, the House approved (H.Rept. 110-185, part 2) $104.3 million for congressionally-directed
assistance to be taken from available funds.

b.

The Distributed Energy Program was moved from EERE to OE in FY2006.

Nuclear Energy
For nuclear energy research and development—including advanced reactors, fuel cycle
technology, nuclear hydrogen production, and infrastructure support—DOE received $1.037
billion for FY2008. That amount is substantially higher than the FY2007 funding level and the
Administration’s request, but it includes large transfers from other accounts and eliminates most
of the Administration’s proposed increase for the Advanced Fuel Cycle Initiative (AFCI). The
higher AFCI funding would have allowed DOE to continue developing a demonstration plant for
extracting plutonium and uranium from spent nuclear fuel, as part of the Administration’s Global
Nuclear Energy Partnership (GNEP). The nuclear energy program is run by DOE’s Office of
Nuclear Energy, Science, and Technology.
DOE requested $801.7 million for FY2008, nearly 30% above the FY2007 funding level. The
request would have boosted funding for AFCI from $167.5 million in FY2007 to $395.0 million
in FY2008. The omnibus appropriation holds AFCI to $181 million and shifts the mixed-oxide
(MOX) fuel program—totaling $281 million—to the nuclear energy program from the nuclear
nonproliferation program. That brings the nuclear energy total to $970.5 million ($961.7 million
with the rescission), about 20% above the request. An additional $75.9 million provided in the
Other Defense Activities account brings the Office of Nuclear Energy’s total spending level to
$1.046 billion ($1.037 billion with the rescission).
Overall, the House had provided a funding level of $835.2 million for nuclear energy, including
$74.9 million from the Other Defense Activities account and $167.8 million transferred for the
MOX program. The Senate Appropriations Committee had recommended $795.5 million for
nuclear energy, including $75.9 million from Other Defense Activities, while opposing the MOX
funding transfer.
According to DOE’s FY2008 budget justification, the nuclear energy R&D program is intended
“to secure nuclear energy as a viable, long-term commercial energy option, providing diversity in
the energy supply.” However, opponents have criticized DOE’s nuclear research program as
providing wasteful subsidies to an industry that they believe should be phased out as
unacceptably hazardous and economically uncompetitive.

Congressional Research Service

15

Energy and Water Development: FY2008 Appropriations

Under the Administration’s GNEP initiative, plutonium partially separated from the highly
radioactive spent fuel from nuclear reactors would be recycled into new fuel to expand the future
supply of nuclear fuel and potentially reduce the amount of radioactive waste to be disposed of in
a permanent repository. Under the initial concept for GNEP, the United States and other advanced
nuclear nations would lease new fuel to other nations that agreed to forgo uranium enrichment,
spent fuel recycling (also called reprocessing), and other fuel cycle facilities that could be used to
produce nuclear weapons materials. The leased fuel would then be returned to supplier nations for
reprocessing. Solidified high-level reprocessing waste would be sent back to the nation that had
used the leased fuel, along with supplies of fresh nuclear fuel. However, a GNEP Statement of
Principles signed by the United States and 15 other countries on September 16, 2007, preserves
the right of all participants to develop fuel cycle facilities while encouraging the establishment of
a “viable alternative to acquisition of sensitive fuel cycle technologies.”4
Although GNEP is largely conceptual at this point, DOE issued a Spent Nuclear Fuel Recycling
Program Plan in May 2006 that provided a general schedule for a GNEP Technology
Demonstration Program (TDP),5 which would develop the necessary technologies to achieve
GNEP’s goals. According to the Program Plan, the first phase of the TDP, running through
FY2006, consisted of “program definition and development” and acceleration of AFCI. Phase 2,
running through FY2008, was to focus on the design of technology demonstration facilities,
which then were to begin operating during Phase 3, from FY2008 to FY2020. The National
Academy of Sciences in October 2007 strongly criticized DOE’s “aggressive” deployment
schedule for GNEP and recommended that the program instead focus on research and
development.6
Nuclear critics oppose GNEP’s emphasis on spent fuel reprocessing, which they see as a weapons
proliferation risk, even if weapons-useable plutonium is not completely separated from other
spent fuel elements, as envisioned by the Administration. “As the research of DOE scientists
makes clear, the reprocessing technologies under consideration would still produce a material that
is not radioactive enough to deter theft, and that could be used to make nuclear weapons,”
according to the Union of Concerned Scientists.7
The omnibus appropriation cuts the Administration’s GNEP request to $181 million, including
$30 million for upgrades to existing facilities. The remaining $151 million is for research,
development, and design activities, with no funds for constructing facilities for technology
demonstration or commercialization. The GNEP budget totals, as well as the remaining nuclear
program numbers cited below, do not reflect the 0.91% across-the-board DOE rescission.

Nuclear Power 2010
President Bush’s specific mention of “clean, safe nuclear power” in his 2007 State of the Union
address reiterated the Administration’s interest in encouraging construction of new commercial
reactors—for which there have been no U.S. orders since 1978. DOE’s efforts to restart the
4
5

See GNEP website at http://www.gnep.energy.gov.
DOE, Spent Nuclear Fuel Recycling Plan, Report to Congress, May 2006.

6

National Academy of Sciences, Review of DOE’s Nuclear Energy Research and Development Program,
prepublication draft, October 2007.
7
Union of Concerned Scientists, U.S. Nuclear Fuel Reprocessing Initiative,
http://www.ucsusa.org/global_security/nuclear_terrorism/US_Nuclear_Fuel_Reprocessing_Initiative.html.

Congressional Research Service

16

Energy and Water Development: FY2008 Appropriations

nuclear construction pipeline have been focused on the Nuclear Power 2010 Program, which will
pay up to half of the nuclear industry’s costs of seeking regulatory approval for new reactor sites,
applying for new reactor licenses, and preparing detailed plant designs. The Nuclear Power 2010
Program, which includes the Standby Support Program authorized by the Energy Policy Act of
2005 (P.L. 109-58) to pay for regulatory delays, is intended to encourage near-term orders for
advanced versions of existing commercial nuclear plants.
Two industry consortia are receiving DOE assistance over the next several years to design and
license new nuclear power plants. DOE awarded the first funding to the consortia in 2004. DOE
requested $114.0 million for Nuclear Power 2010 for FY2008, more than 40% above the FY2007
funding level of $80.3 million. The omnibus act provided a $21.0 million increase from the
budget request, as recommended by the Senate Appropriations Committee, for a total of $135.0
million. The funding increase is intended to accelerate progress on the new reactor licenses. The
House had approved flat funding for the program, contending that funds should not be provided
for reactor design work.
The nuclear license applications under the Nuclear Power 2010 program are intended to test the
“one-step” licensing process established by the Energy Policy Act of 1992 (P.L. 102-486). Under
the process, NRC may grant a combined construction permit and operating license (COL) that
allows a completed plant to begin operation if all construction criteria have been met. Even if the
licenses are granted by NRC, the industry consortia funded by DOE have not committed to
building new reactors. The following two consortia are receiving COL assistance under the
Nuclear Power 2010 program:
•

A consortium led by Dominion Resources that is preparing a COL for an
advanced General Electric reactor. The proposed reactor would be located at
Dominion’s existing North Anna plant in Virginia, where the company received
an NRC early-site permit with DOE assistance. Dominion Energy submitted a
COL application for a new unit at North Anna on November 27, 2007.

•

A consortium called NuStart Energy Development, including Exelon and several
other major nuclear utilities, which announced on September 22, 2005, that it
would seek a COL for two Westinghouse reactors at the site of TVA’s
uncompleted Bellefonte nuclear plant in Alabama and for a General Electric
design at the Grand Gulf plant in Mississippi. The Nuclear Power 2010 Program
is providing funding for review and approval of the Bellefonte COL, which was
submitted to NRC on October 30, 2007.

The Nuclear Power 2010 Program also helped three utilities seek NRC Early Site Permits (ESPs)
for potential new reactors in Illinois, Mississippi, and Virginia. NRC issued the first of these on
March 15, 2007, to Exelon Generating Company for a potential new reactor at the company’s
Clinton, Illinois, nuclear plant. Under Nuclear Power 2010, DOE paid half the $15 million cost of
the Clinton ESP. NRC authorized a second ESP on March 27, 2007, for the Grand Gulf site in
Mississippi, and a third, for the North Anna site in Virginia, on November 20, 2007. The holders
of those ESPs will not have to revisit site-related issues if they seek licenses for new reactors at
those locations during the next 20 years.

Generation IV
Advanced commercial reactor technologies that are not yet close to deployment are the focus of
DOE’s Generation IV Nuclear Energy Systems Initiative, for which $36.1 million was requested

Congressional Research Service

17

Energy and Water Development: FY2008 Appropriations

for FY2008—about the same as the FY2007 funding level. The omnibus measure nearly tripled
the request to $116.0 million, with $74 million devoted to the Next Generation Nuclear Plant
(NGNP). At least $38 million of the NGNP funding is to be spent for developing a conceptual
design and baseline cost estimate, and $36 million is for NRC pre-licensing activities. Under
DOE’s current plans, NGNP will use Very High Temperature Reactor (VHTR) technology, which
features helium as a coolant and coated-particle fuel that can withstand temperatures up to 1,600
degrees Celsius.
The Energy Policy Act of 2005 authorizes $1.25 billion through FY2015 for NGNP development
and construction (Title VI, Subtitle C). The authorization requires that NGNP be based on
research conducted by the Generation IV program and be capable of producing electricity,
hydrogen, or both. Phase I research on the NGNP is to continue until 2011, when a decision will
be made on moving to the Phase II design and construction stage, according to the FY2008 DOE
budget justification.
In conjunction with the GNEP Technology Demonstration Program, the Generation IV Program
will also focus on developing a sodium-cooled fast reactor (SFR). Existing U.S. commercial
nuclear reactors use water to slow down, or “moderate,” the neutrons released by the fission
process (splitting of nuclei). The relatively slow (thermal) neutrons are highly efficient in causing
fission in certain isotopes of heavy elements, such as uranium 235 and plutonium 239.8 Therefore,
fewer of those isotopes are needed in nuclear fuel to sustain a nuclear chain reaction (in which
neutrons released by fissioned nuclei then induce fission in other nuclei, and so forth). The
downside is that thermal neutrons cannot efficiently induce fission in more than a few specific
isotopes.
In contrast, “fast” neutrons, which have not been moderated, are less effective in inducing fission
than thermal neutrons but can induce fission in a much wider range of isotopes, including all
major plutonium isotopes. Therefore, nuclear fuel for a fast reactor must have a higher proportion
of fissionable isotopes than a thermal reactor to sustain a chain reaction, but a larger number of
different isotopes can constitute that fissionable proportion.
A fast reactor’s ability to fission most heavy radioactive isotopes, called “transuranics” (TRU),
makes it theoretically possible to repeatedly separate those materials from spent fuel and feed
them back into the reactor until they are entirely fissioned. In a thermal reactor, the buildup of
non-fissile isotopes sharply limits the number of such separation cycles before the recycled fuel
can no longer sustain a nuclear chain reaction.
“Given the benefits of continuous recycling, at this time GNEP-TDP is focused on the
development of fast reactor technologies, recognizing that fast reactor operating experience is
much more limited than thermal reactor operating experience, and that fast burn reactor fuels, or
transmutation fuels, are not fully developed,” according to the DOE Program Plan.9
The House Appropriations Committee report directed DOE to make the gas-cooled NGNP a
higher priority than fast reactors for GNEP and begin a competitive solicitation for a commercial
demonstration plant at the Idaho National Laboratory. The Senate panel also emphasized gascooled reactors in the Generation IV program.
8
9

Isotopes are atoms of the same chemical element but with different numbers of neutrons in their nuclei.
Spent Nuclear Fuel Recycling Program Plan, p. 8.

Congressional Research Service

18

Energy and Water Development: FY2008 Appropriations

The Generation IV program is also monitoring international research on lead-cooled fast reactors,
gas-cooled fast reactors, and supercritical water-cooled reactors, according to the FY2008 budget
justification.

Fuel Cycle Research and Facilities
The omnibus act places the Advanced Fuel Cycle Initiative within the new category of Fuel Cycle
Research and Facilities, along with Mixed-Oxide Fuel Fabrication, which was transferred from
the nuclear nonproliferation account (described in a separate section of this report). Funding for
the new category totals $462.3 million.
The FY2008 funding request of $395 million for AFCI, the primary component of GNEP, was
more than double the FY2007 funding level of $167.5 million, which in turn was more than
double the FY2006 appropriation. The omnibus act reduced AFCI to $181.0 million, as discussed
above. According to the DOE budget justification, AFCI will develop and demonstrate nuclear
fuel cycles that could reduce the long-term hazard of spent nuclear fuel and recover additional
energy. Such technologies would involve separation of plutonium, uranium, and other long-lived
radioactive materials from spent fuel for reuse in a nuclear reactor or for transmutation in a
particle accelerator. Much of the program’s research will focus on a separations technology called
UREX+, in which uranium and other elements are chemically removed from dissolved spent fuel,
leaving a mixture of plutonium and other highly radioactive elements. Proponents believe the
process is proliferation-resistant, because further purification would be required to make the
plutonium useable for weapons and because its high radioactivity would make it difficult to divert
or work with.
FY2008 funding was also to have been used for conceptual design work on an Advanced Fuel
Cycle Facility (AFCF) to provide an engineering-scale demonstration of AFCI technologies,
according to the budget justification. At the same time, industry design teams were to complete
conceptual designs for nuclear fuel recycling demonstration facilities to be used for GNEP.
However, the omnibus measure specifically rejected funding for development of AFCF in
FY2008.
Removing uranium from spent fuel would eliminate most of the volume of spent nuclear fuel that
would otherwise require disposal in a deep geologic repository, which DOE is developing at
Yucca Mountain, Nevada. The UREX+ process also could reduce the heat generated by nuclear
waste—the major limit on the repository’s capacity—by removing cesium and strontium for
separate storage and decay over several hundred years. Plutonium and other long-lived elements
would be fissioned in accelerators or fast reactors (such as the type under development by the
Generation IV program) to reduce the long-term hazard of nuclear waste. Even if technically
feasible, however, the economic viability of such waste processing has yet to be determined, and
it still faces significant opposition on nuclear nonproliferation grounds.

Nuclear Hydrogen Initiative
In support of President Bush’s program to develop hydrogen-fueled vehicles, DOE is requesting
$22.6 million in FY2008 for the Nuclear Hydrogen Initiative, about 10% above the FY2007
funding level but below the FY2006 appropriation. The omnibus measure provides $10 million
for the program. The House had provided flat funding for the program, and the Senate Committee
had approved the full request. According to DOE’s FY2008 budget justification, the program will

Congressional Research Service

19

Energy and Water Development: FY2008 Appropriations

continue laboratory-scale experiments to allow selection by 2011 of a hydrogen-production
technology for pilot-scale demonstration by 2013.

Fossil Energy Research, Development, and Demonstration
The Bush Administration requested $566.8 million in the FY2008 omnibus act for Fossil Energy
Research and Development (see Table 9). This is about 20.7% more than the $469.7 million
requested in FY2007. (Final funding under the FY2007 Operating Plan showed spending of
$592.6 million). Major funding categories and amounts in the FY2008 request include the
President’s Coal Research Initiative (Clean Coal Power Initiative, $73 million; FutureGen, $108
million; and Fuels and Power Systems, $245.6 million), Program Direction ($130 million), Fossil
Energy Environmental Restoration ($9.6 million), and Special Recruitment Programs ($0.7
million). Coal and coal-related activities accounted for more than 75% of the FY2008 Fossil
Energy R&D budget request.
The FY2007 funding bill (P.L. 110-5) as enacted deferred $257million in unobligated Clean Coal
Technology balances to FY2008. The FY2008 omnibus act transfers $166 million to the Fossil
Energy Research and Development account in FY2008, and recommends the deferral of $149
million in Clean Coal Technology balances until FY2009 (as proposed by the Senate and not the
rescission of balances proposed by the House). The FY2008 act provides $750 million for Fossil
Energy Research and Development (an across-the-board rescission of 0.91% reduces this to
$742.8 million). Under that heading, $70 million is marked for the Clean Coal Power Initiative
($3 million below request); $75 million for FutureGen ($33 million below request due to unused
prior-year funds); $352.9 million for Fuels and Power Systems ($107.3 million above request);
$20 million for Natural Gas Technologies; $5 million for Petroleum-Oil Technologies; $150
million for Program Direction; $13 million for Plant and Capital Equipment; $0.7 million for
Special Recruitment Programs; $5 million for Cooperative Research and Development; and $48.9
million for congressionally directed projects.
Table 9. Fossil Energy Research and Development Programs
($ millions)
Clean Coal Technology

FY2007
Op. Plan

Def. unobligated bal., FY2007

257.0

Def. unobligated bal., FY2008

-257.0

FY2008
Request

FY2008
House

FY2008
S.Cmte.

FY2008
Appropriations

257.0

257.0

257.0

257.0

Def. unobligated bal., FY2009

-149.0

Rescission, uncommitted bal.

—

-149.0

-149.0

-149.0

Transfer to Clean Coal Pwr. Init.

—

-58.0

—

-73.0

-70.0

Transfer to FutureGen

—

-108.0

-108.0

-88.0

-75.0

Transfer to Fuels & Power Sys.

-58.0

Transfer to Fossil Energy R&D

-5.0

Transfer to Carbon
Sequestration
Total

Congressional Research Service

-21.0

-58.0
—

-58.0

-58.0

-58.0

-58.0

20

Energy and Water Development: FY2008 Appropriations

FY2007
Op. Plan

FY2008
Request

FY2008
House

FY2008
S.Cmte.

FY2008
Appropriations

Clean Coal Power Initiative

60.4

73.0

73.0

88.0

70.0

FutureGen

54.0

108.0

108.0

88.0

75.0

Fossil Energy R & D

Fuels & Power Systems
Innovations for existing plants

36.4

Advanced IGCC

54.0

Advanced turbines

24.0

Carbon sequestration

120.0

Fuels

25.0

Fuel Cell

56.0

Advanced research

37.5

Subtotal

311.3

245.6

375.6

374.0

352.9

Natural Gas Technologies

12.0

—

12.0

20.0

20.0

Petroleum-Oil Technologies

2.7

—

2.7

10.0

5.0

129.8

130.0

127.0

150.0

150.0

Program Direction
Plant & Capital Equipment
Fossil Energy Env. Restoration

—
9.7

Special Recruitment Program

9.6

13.0
9.6

16.6

9.6

0.7

0.7

Congressionally Directed

48.0

Other

12.7

0.7

07

61.6

Total

592.6

566.8

708.8

808.1

750.0a

Sources: DOE FY2007 Operating Plan; DOE FY2008 Budget Request; H.Rept. 110-185; S.Rept. 110-127;
Congressional Record, December 17, 2007.
a.

does not reflect a 0.91% across-the-board rescission.

The Clean Coal Power Initiative is intended to demonstrate advanced clean coal-based power
generation technologies on a commercial scale capable of achieving 45% thermal efficiency. The
FutureGen project will partner with industry to build the advanced coal-based Integrated
Gasification Combined Cycle (IGCC) plant that can produce electricity at 45%-50% efficiency at
a capital cost of $1,000/kilowatt (in 2003 dollars) and can integrate CO2 separation, capture, and
sequestration. The FutureGen Industrial Alliance, Inc., has selected Mattoon, Illinois, as the plant
site. The Fuels program is a key component of the Hydrogen Fuel Initiative and will provide the
hydrogen production supporting R&D for the FutureGen project. The Fossil Energy
Environmental Restoration program remediates the National Energy Technology Laboratory at
the Morgantown, WV; Pittsburgh, PA; Tulsa, OK; Fairbanks, AK; and Albany, OR, sites.
The Energy Policy Act of 2005 (P.L. 109-58, Title IV) authorizes the annual appropriation of
$200 million in FY2006 through FY2014 for the Clean Coal Power Initiative (see Table 10). Of
the funds made available, 70% (i.e., $140 million annually) are to be used only in funding coalbased gasification technologies: combined cycle, fuel cell, coproduction, hybrid, and advanced
technologies capable of producing concentrated carbon monoxide—technologies aimed at
FutureGen. The Coal and Related Technologies Program is authorized $611 million in FY2007,
$626 million in FY2008, and $641 million in FY2009, in addition to programs for research,

Congressional Research Service

21

Energy and Water Development: FY2008 Appropriations

development, demonstration, and commercial application of coal-based power generation through
gasification, advanced combustion, and turbines for synthesis gas derived from coal.
Table 10. Energy Policy Act of 2005 Title IV Authorization
($ millions)
EPAct Authorization

FY06

FY07

FY08

FY09

FY10

FY11

FY12

FY13

FY14

Clean Coal Power

200

200

200

200

200

200

200

200

200

FutureGen related

140

140

140

140

140

140

140

140

140

611

626

641

Fossil Energy

Source: DOE FY2008 Budget Request.

DOE had proposed terminating programs in Natural Gas Technology and Petroleum-Oil
Technology in FY2008. OMB rated both programs as ineffective based on its Program
Assessment Rating Tool. Nor had DOE requested funding for Plant and Capital Equipment or the
Cooperative Research and Development program (believing that research center sponsored work
can compete for Fossil Energy funding through the competitive solicitation process, DOE had not
requested funding in FY2007 or FY2008). Congress has reinstated the funding of these programs.

Strategic Petroleum Reserve
The Strategic Petroleum Reserve (SPR), authorized by the Energy Policy and Conservation Act
(P.L. 94-163) in 1975, consists of caverns formed out of naturally occurring salt domes in
Louisiana and Texas in which roughly 690 million barrels of crude oil are stored. Current
capacity is 727 million barrels; the SPR currently holds 690 million barrels. The purpose of the
SPR is to provide an emergency source of crude oil that may be tapped in the event of a
presidential finding that an interruption in oil supply, or an interruption threatening adverse
economic effects, warrants a drawdown from the reserve. A Northeast Heating Oil Reserve
(NHOR) was established during the Clinton Administration. NHOR houses 2 million barrels of
home heating oil in above-ground facilities in Connecticut, New Jersey, and Rhode Island.
Program costs for the SPR in recent years have been dedicated principally to maintaining SPR
facilities and keeping the SPR in readiness should it be needed. Any fill activity was
accomplished by accepting deliveries of royalty-in-kind (RIK) oil to the SPR in lieu of cash
royalties on offshore production being paid to the federal government. The Administration request
for FY2007 for the SPR was $155.4 million. DOE’s 2007 operating plan set FY2007 spending at
$169.4 million, including $5.0 million for the NHOR. The FY2008 request for the same activities
was $168.8 million. However, the request included an additional $168.1 million to launch the
Administration’s plan to expand the SPR to 1.5 billion barrels, for a total of $331.6 million. At
present, expansion of the Reserve is authorized to 1 billion barrels by the Energy Policy Act of
2005 (P.L. 109-58). The FY2008 request from the Administration was intended to achieve
capacity of 1 billion barrels by adding 115 million barrels of capacity at three existing sites and
establishing a new site, in Richton, Mississippi, where 160 million barrels of capacity would be
created. The FY2008 budget request indicated that the Administration would seek authority at a
later date to expand the SPR to 1.5 billion barrels, and that planned spending during FY2008
would be a start toward that goal.

Congressional Research Service

22

Energy and Water Development: FY2008 Appropriations

The proposal to raise spending significantly to expand the SPR was anticipated to be
controversial. In its report on the bill (H.Rept. 110-185), the House Committee on Appropriations
indicated that it did not support expansion of the SPR at this time, noting an estimate that it would
cost $10 billion for creating additional capacity and $55 billion to fill, and expansion would not
be completed until 2027. The Committee said the plans for the expansion lacked “analytical
clarity,” citing recommendations in a 2006 report from the Government Accountability Office
(GAO) that a new assessment be made of the optimal mix for the SPR of sweet and sour crudes,
as well as the appropriate size of the SPR. The Committee recommended $163.5 million for the
SPR program in FY2008, and approved the Administration request of $5.3 million for the NHOR.
The Senate Committee on Appropriations had the same reaction as the House committee. Citing
the same statistics as in the House report, the Senate committee also settled on a recommendation
of $163.5 million. The omnibus bill provides $188.5 million, an increase of $25 million, which is
directed to be spent to acquire land at a new site. The explanatory statement on the bill is explicit
that the Appropriations Committees do not support expansion of the SPR to 1.5 billion barrels.
Meanwhile, fill of the SPR with royalty-in-kind (RIK) oil continues to be controversial. Critics
argue that it is inadvisable to add oil to the SPR when markets are tight and prices are touching
inflation-adjusted historic highs, and that the additional oil adds little to U.S. energy security.
Supporters of RIK fill argue that the fill rate is too little to have a discernible impact on markets,
and that currently high product prices are sustained owing to factors other than crude supply,
which is more than ample at this time. Deliveries of RIK oil to the SPR totaled 4.3 million barrels
during FY2007. Deliveries of RIK oil during FY2008 are estimated at 19.1 million barrels.
Deliveries of roughly 15 million barrels are scheduled through July 2008.

Science
The DOE Office of Science conducts basic research in six program areas: basic energy sciences,
high-energy physics, biological and environmental research, nuclear physics, fusion energy
sciences, and advanced scientific computing research. Through these programs, DOE is the thirdlargest federal funder of basic research and the largest federal funder of research in the physical
sciences.10 For FY2008, DOE requested $4.398 billion for Science, an increase of 16% from the
FY2007 amount of $3.797 billion. This unusually large increase reflected the American
Competitiveness Initiative (ACI), which President Bush announced in his State of the Union
address on January 31, 2006. Over 10 years, the ACI would double the combined R&D funding
of the DOE Office of Science and two other agencies. The House provided $4.514 billion for
Science. The Senate committee recommended $4.497 billion. The final appropriation was $4.018
billion,11 which was $380 million less than the request but a 6% increase from FY2007.
The requested funding for the largest Office of Science program, basic energy sciences, was
$1.498 billion, a 20% increase from FY2007. Much of the requested increase was to expand
facility operating time, as called for by the House and Senate appropriations reports for FY2006.
The House provided the requested amount, and the Senate committee recommended a further
increase of $14 million. The final appropriation was $1.270 billion, less than the request by $229
10

Based on preliminary FY2006 data from Tables 29 and 22 of National Science Foundation, Division of Science
Resources Statistics, Federal Funds for Research and Development: Fiscal Years 2004-06, NSF 07-323 (June 2007).
11
Adjusted for the across-the board rescission (Sec. 312) but not for a specific rescission of $44.6 million in prior-year
funds.

Congressional Research Service

23

Energy and Water Development: FY2008 Appropriations

million but a 2% increase from FY2007. The explanatory statement did not explain how this
reduction relative to the request should be allocated to particular activities. In particular, it did not
mention the operating time issue. It did state that the final bill included “less funding than
requested for two projects where the start of major construction activity can be delayed,” but the
total request for construction in this program was only $121 million.
For high-energy physics, the request was $782 million, up 4% from FY2007. The budget
justification stated that the program’s “highest priority R&D effort is the development of the
proposed International Linear Collider (ILC).” The House provided the requested amount,
including the requested increase for the ILC. The House committee also emphasized its support
for the NASA/DOE Joint Dark Energy Mission (JDEM), for which it said “DOE has done its
part” but “NASA has failed to budget and program for launch services.” The Senate committee
also recommended the requested ILC funding, although as in previous years it expressed concern
that the ILC “will crowd out other valuable research”; it provided a $7 million increase to
“aggressively ramp up” JDEM and related activities. The final appropriation was $688 million,
$94 million less than the request and 8% down from FY2007. The final bill provided $15 million
for the ILC, $45 million less than the request; the explanatory statement directed DOE to proceed
with JDEM during FY2008, together with NASA, but if the two agencies cannot agree on a joint
approach, to provide no support for space science satellite missions in future years. The Fermi
National Accelerator Laboratory (Fermilab) received about $52 million less than requested, and
the Stanford Linear Accelerator Center (SLAC) received about $25 million less. The directors of
Fermilab and SLAC have announced plans to lay off 200 and 125 employees respectively.12
The request for biological and environmental research was $532 million, up 10%. The House
provided an increase of $30 million for biological research and an increase of $20 million for
climate change research. The Senate committee recommended an increase of $73 million, mostly
for congressionally directed projects. The final appropriation was $544 million, an increase of
$12 million. In past years, biological and environmental research has been the main location for
congressionally directed projects in the Science account. The explanatory statement for FY2008
grouped all such projects (for the entire Office of Science) in a separate category, for which it
provided $124 million.
For nuclear physics, the request was $471 million, up 11% from FY2007. As in the FY2007
request, no funds were included for construction of the Rare Isotope Accelerator (RIA), despite
direction in Section 981 of the Energy Policy Act of 2005 (P.L. 109-58) that construction of this
project must begin no later than the end of FY2008. A National Academies report on the RIA was
released in December 2006 and is available on the nuclear physics program’s website.13 The
House provided the requested amount and endorsed DOE’s decision to fund additional R&D
rather than build the RIA. The Senate committee recommended the requested amount and did not
mention the RIA. The final appropriation was $433 million, less than the request by $39 million
but 2% up from FY2007.
The request for fusion energy sciences was $428 million, up 34%. Almost the entire increase was
for the U.S. share of the International Thermonuclear Experimental Reactor (ITER), a fusion
12
Pier J. Oddone, director of Fermilab, presentation slides from an “all hands” meeting on December 20, 2007,
http://www.fnal.gov/pub/today/files/All_Hands_Meeting_122007.ppt; Persis S. Drell, director of SLAC, presentation
slides from an “all hands” meeting on January 7, 2008, http://today.slac.stanford.edu/misc/AllHands-010708.ppt.
13
National Research Council, Scientific Opportunities with a Rare-Isotope Facility in the United States, online at
http://www.sc.doe.gov/np/program/docs/RareIsotopeScienceAssessment.pdf.

Congressional Research Service

24

Energy and Water Development: FY2008 Appropriations

facility now under construction whose other participants include China, the European Union,
India, Japan, Russia, and South Korea. The House provided the requested amount, but rejected
the proposed creation of a new activity in high energy-density physics and instead redistributed
its requested $12 million among existing non-ITER activities. The Senate committee also
recommended the requested amount, but it supported the new program in high energy-density
physics and encouraged DOE to expand it in future years. The final appropriation was $287
million, less than the request by $141 million and 10% down from FY2007. The requested $150
million for U.S. contributions to ITER was not included, although $10 million for related R&D
was, and DOE was directed not to use reprogramming to restore ITER funding. According to
press reports, ITER officials expect no immediate impact on the project’s planned start in 2008,
but “what the other ITER partners now want from the United States is clarity” about its future
plans.14 Under an agreement signed in 2006, the U.S. share of ITER construction costs is 9.1%, or
an estimated $1.122 billion through FY2014.
The request for the smallest of the Office of Science research programs, advanced scientific
computing research, was $340 million, up 20% from FY2007. The House provided the requested
amount. The Senate committee recommended $335 million. The final appropriation was $351
million.
The request for laboratory infrastructure was $79 million, up from $42 million in FY2007. The
House provided $152 million: the bulk of this increase was to accelerate facility cleanup,
replacement, renovation, and upgrades at Pacific Northwest National Laboratory (PNNL). The
Senate committee recommended $89 million, expressed its continued support for the affected
PNNL facilities, and questioned why the budget request did not fund an agreement on those
facilities signed by DOE and the Department of Homeland Security in 2006. The final
appropriation was $65 million. It included $10 million less than the request for PNNL, but the
explanatory statement directed DOE to increase future funding for PNNL by $10 million to
restore the baseline.

Nuclear Waste Disposal
DOE’s Office of Civilian Radioactive Waste Management (OCRWM) is responsible for
developing a nuclear waste repository at Yucca Mountain, Nevada, for disposal of nuclear reactor
spent fuel and defense-related high-level radioactive waste.
The omnibus appropriations act provides $386.5 million in FY2008 for the nuclear waste
program (including the rescission), about $50 million below the FY2007 level and more than
$100 million below the Administration’s $494.5 million request. The funding cut may affect
OCRWM’s plans to submit the Yucca Mountain license application to the Nuclear Regulatory
Commission by June 30, 2008, and the current goal of opening the repository by 2017. The
House had approved the full request, while the Senate Appropriations panel had voted to hold the
program at $446.1 million, about the FY2007 level.
Funding for the program is provided under two appropriations accounts. The Administration
requested $202.5 million from the Nuclear Waste Fund, which holds fees paid by nuclear utilities.
An additional $292.0 million was requested in the Defense Nuclear Waste Disposal account,
14

Dennis Normile, “U.S. Wavers Again on ITER,” ScienceNOW Daily News, December 21, 2007
http://sciencenow.sciencemag.org/cgi/content/full/2007/1221/1.

Congressional Research Service

25

Energy and Water Development: FY2008 Appropriations

which pays for disposal of high-level waste from the nuclear weapons program in the planned
Yucca Mountain repository. The omnibus measure provides $187.3 million from the Nuclear
Waste Fund and $199.2 million under the Defense Nuclear Waste Disposal account (with both
figures reflecting the rescission).
The Nuclear Waste Policy Act of 1982 (NWPA, P.L. 97-425), as amended, names Yucca
Mountain as the sole candidate site for a national geologic repository. Congress passed an
approval resolution in July 2002 (H.J.Res. 87, P.L. 107-200) that authorized the Yucca Mountain
project to proceed to the licensing phase.
NWPA required DOE to begin taking waste from nuclear plant sites by January 31, 1998. Nuclear
utilities, upset over DOE’s failure to meet that deadline, have won two federal court decisions
upholding the department’s obligation to meet the deadline and to compensate utilities for any
resulting damages. Utilities have also won several cases in the U.S. Court of Federal Claims.
DOE estimates that liability payments will total $7 billion if Yucca Mountain begins receiving
waste by 2017 and $11 billion if the repository’s opening is delayed until 2020.15 (For more
information, see CRS Report RL33461, Civilian Nuclear Waste Disposal, by (name redacted).)

Loan Guarantees
Congress established the DOE Innovative Technology Loan Guarantee Program in the Energy
Policy Act of 2005. The act authorized loan guarantees for energy projects using “new or
significantly improved technologies” to reduce greenhouse gas emissions.
The omnibus act allows DOE to guarantee repayment of up to $38.5 billion in loans for energy
projects during FY2008 and FY2009. Of that amount, $18.5 billion is for nuclear power plants,
$6 billion for coal projects that incorporate carbon capture and sequestration, $2 billion for
advanced coal gasification, $10 billion for renewable energy and energy efficiency projects, and
$2 billion for uranium enrichment and other “front end” nuclear fuel cycle facilities. DOE must
submit an implementation plan to the House and Senate Appropriations Committees at least 45
days before issuing the loan guarantees.
In the FY2008 request, the Administration sought $9 billion in loan guarantee authority
(including $2 billion previously requested for FY2007). The House approved $7 billion in loan
guarantees for FY2008, allocating $2 billion for coal, $4 billion for biofuels, and $1 billion for
electric transmission and renewable power systems, specifically omitting the Administration’s
mention of nuclear power. The Senate Appropriations Committee’s version of the bill did not cap
the loan guarantee level or specify eligible technologies.

Nuclear Weapons Stockpile Stewardship
Congress established the Stockpile Stewardship Program in the FY1994 National Defense
Authorization Act (P.L. 103-160) “to ensure the preservation of the core intellectual and technical
competencies of the United States in nuclear weapons.” The program is operated by the National
Nuclear Security Administration (NNSA), a semiautonomous agency within DOE that Congress
15

Statement of Edward F. Sproat III, Director of the Office of Civilian Radioactive Waste Management, Before the
House Budget Committee, October 4, 2007.

Congressional Research Service

26

Energy and Water Development: FY2008 Appropriations

established in the FY2000 National Defense Authorization Act (P.L. 106-65, Title XXXII). It
seeks to maintain the safety and reliability of the U.S. nuclear stockpile.
Stockpile stewardship consists of all activities in NNSA’s Weapons Activities account. The three
main elements of stockpile stewardship, described below, are Directed Stockpile Work (DSW),
Campaigns, and Readiness in Technical Base and Facilities (RTBF). Table 11 presents funding
for these elements. NNSA manages two programs outside of Weapons Activities: Defense
Nuclear Nonproliferation, discussed later in this report, and Naval Reactors.
Most stewardship activities take place at the nuclear weapons complex, which consists of three
laboratories (Los Alamos National Laboratory, NM; Lawrence Livermore National Laboratory,
CA; and Sandia National Laboratories, NM and CA); four production sites (Kansas City Plant,
MO; Pantex Plant, TX; Savannah River Site, SC; and Y-12 Plant, TN); and the Nevada Test Site.
NNSA manages and sets policy for the complex; contractors to NNSA operate the eight sites.
Table 11. Funding for Weapons Activities
($ millions)
FY2007
Operating Plan

FY2008
Request

House

Senate
Approps. Cmte.

Consolidated
Approps. Act

DSW

$1,425.7

$1,447.2

$1,336.6

$1,409.5

$1,413.9

Campaigns

1,979.0

1,866.2

1,725.2

1,933.2

1,890.7

RTBF

1,613.2

1,662.1

1,479.6

1,659.2

1,652.1

Othera

1,257.7

1,535.7

1,337.7

1,487.1

1,398.9

Total

6,275.6

6,511.3

5,879.1

6,489.0

6,355.6

Program

Sources: DOE FY2008 Congressional Budget Request, vol. 1 (NNSA), p. 59; U.S. Department of Energy, FY
2007 Operating Plan by Appropriation, March 16, 2007, pp. 15-21; U.S. Congress. House. Committee on
Appropriations. Energy and Water Development Appropriations Bill, 2008, 110th Congress, 1st Session, H.Rept. 110185, pp. 136-140; U.S. Congress. Senate. Committee on Appropriations. Energy and Water Appropriations Bill,
2008, 110th Congress, 1st Session, S.Rept. 110-127, pp. 193-198; and U.S. Congress. House. Committee on Rules.
Text of the House Amendments to Senate Amendment to H.R. 2764—State, Foreign Operations, and Related Programs
Appropriations Act, 2008 (Consolidated Appropriations Act, 2008). Joint Explanatory Statement to Accompany
Consolidated Appropriations Amendment, Division C—Energy and Water, pp. 58e-58h.
Notes: Does not reflect applicable rescissions. Details may not add to totals due to rounding. DSW, Directed
Stockpile Work; RTBF, Readiness in Technical Base and Facilities.
a.

Includes Secure Transportation Asset, Nuclear Weapons Incident Response, Facilities and Infrastructure
Recapitalization Program, Environmental Projects and Operations, Safeguards and Security, and several
adjustments.

The FY2008 request document includes data from NNSA’s Future Years Nuclear Security
Program (FYNSP), which projects the budget and components through FY2012 (see Table 12).
Table 12. NNSA Future Years Nuclear Security Program
($ millions)
FY2008

FY2009

FY2010

FY2011

FY2012

DSW

$1,447.2

$1,483.4

$1,520.5

$1,558.5

$1,597.5

Campaigns

1,866.2

1,916.6

1,941.1

1,933.7

1,942.0

Congressional Research Service

27

Energy and Water Development: FY2008 Appropriations

FY2008

FY2009

FY2010

FY2011

FY2012

RTBF

1,662.1

1,698.4

1,765.5

1,862.7

1,952.6

Othera

1,535.7

1,606.6

1,677.0

1,756.0

1,831.9

Total

6,511.3

6,705.0

6,904.0

7,111.0

7,324.0

Source: DOE FY2008 Congressional Budget Request, vol. 1 (NNSA), pp. 59, 60.
Note: Does not reflect applicable rescissions. Details may not add to totals because of rounding.
a.

Includes Secure Transportation Asset, Nuclear Weapons Incident Response, Facilities and Infrastructure
Recapitalization Program, Environmental Projects and Operations, Safeguards and Security, and several
adjustments.

Nuclear Weapons Complex Reconfiguration
In testimony before the House Appropriations Committee’s Energy and Water Subcommittee in
March 2004, the Secretary of Energy agreed to conduct a review of reconfiguring the nuclear
weapons complex (the “Complex”). The committee’s FY2005 energy and water report contained
a requirement for that study. The committee was concerned about high costs, the security of
fissile material distributed among many sites, and the size and age of the Complex. A task force
of the Secretary of Energy Advisory Board released its final report in October 2005. It
recommended a Consolidated Nuclear Production Center (CNPC) that would make nuclear
components (such as those of uranium or plutonium) and would assemble and dismantle nuclear
weapons. It recommended consolidating uranium and plutonium, and probably closing several
current sites. The House Appropriations Committee, in its FY2007 report, supported the task
force’s recommendations and rejected NNSA’s “Complex 2030” plan to modernize the Complex
with less consolidation. The committee recommended $100.0 million “for transition planning, site
selection, and preliminary design and development for a consolidated nuclear production site for
reliable replacement warheads and stockpile support.” The bill as passed by the House provided
this sum. NNSA had not requested funds for this purpose. The Senate Appropriations Committee
did not recommend funds for this purpose, and the DOE FY2007 operating plan did not include
such funds. For FY2008, NNSA did not request funds for CNPC, but did request funds
throughout its proposed budget for upgrading and consolidating the Complex. In January 2007, it
submitted a report to Congress on its plan for transforming the Complex. This plan included
evaluation of CNPC in a draft Supplement to the Stockpile Stewardship and Management
Programmatic Environmental Impact Statement for Complex 2030.
The House Appropriations Committee, in its FY2008 report, expressed extreme displeasure with
the Administration’s rationale for the nuclear weapons program and with NNSA’s plan for the
Complex. It stated that the Reliable Replacement Warhead program (RRW, discussed below) and
Complex 2030 “are being proposed in a policy vacuum without any Administration statement on
the national security environment that the future nuclear deterrent is designed to address.”
Accordingly, “The Committee believes it is premature to proceed with further development of the
RRW or a significant nuclear complex modernization plan, until a three-part planning sequence is
completed.” This sequence has three elements: “a comprehensive nuclear defense and
nonproliferation strategy”; a detailed description translating that strategy into a “specific nuclear
stockpile”; and “a comprehensive, long-term expenditure plan, from FY2008 through FY2030....”
“The Committee views completion of this three-part planning sequence as a necessary condition
before considering additional funding for Complex 2030 and RRW activities.” It noted its “strong
reservations” on Complex 2030 and stated that “NNSA continues to pursue a policy of rebuilding

Congressional Research Service

28

Energy and Water Development: FY2008 Appropriations

and modernizing the entire complex in situ without any thought given to a sensible strategy for
long-term efficiency and consolidation.”
The Senate Appropriations Committee expressed concern with NNSA’s plans for the Complex. It
felt that there was an inadequate linkage between warheads, the Complex, and strategy.
“Congress should have a more vigorous analysis and debate of our national strategic defense
policy prior to deciding whether to continue or terminate RRW development.” Further,
The Committee rejects the Department’s premature deployment of the NNSA Complex 2030
consolidation effort. This plan was based on the adoption and deployment of the Reliable
Replacement Warhead systems. The Government Accountability Office found this proposal
to be lacking critical details about the size and military mission of the RRW system, which
of course would dictate the size and makeup of the future stockpile including the necessity
for a new pit manufacturing capability.

The committee also expressed concern about “sustaining the science capability at the
laboratories.” It directed DOE to provide (1) a comprehensive, long-term strategy for
computation at the labs and (2) an R&D plan “that addresses unresolved physics and materials
questions.”
The joint explanatory statement accompanying the consolidated appropriations bill said, “The
Congress agrees to the direction contained in the House and Senate reports requiring the
Administration ... to develop and submit to the Congress a comprehensive nuclear weapons
strategy for the 21st century.”
On December 18, 2007, NNSA announced its plans for the Complex, called Nuclear Weapons
Complex Transformation. This plan, to be more fully described in a draft supplemental
programmatic environmental impact statement to be released in January 2008, would retain
existing sites, reduce the weapons program footprint by as much as one-third, close or transfer
from weapons activities about 600 structures, reduce the number of weapons workers by 20-30%,
dismantle weapons more rapidly, and build several major new facilities, such as a Uranium
Processing Facility at Y-12 Plant, a Weapons Surveillance Facility at Pantex Plant, and a
Chemistry and Metallurgy Research Replacement Nuclear Facility at Los Alamos National
Laboratory.16

Directed Stockpile Work (DSW)
This program involves work directly on nuclear weapons in the stockpile, such as monitoring
their condition; maintaining them through repairs, refurbishment, life extension, and
modifications; R&D in support of specific warheads; and dismantlement. The FY2008 DSW
request would support life extension programs for the B61 gravity bomb and the W76 warhead
for Trident II submarine-launched ballistic missiles. It would fund surveillance and maintenance
for eight warhead types, dismantlement and disposition of retired warheads and components, and
16
U.S. Department of Energy. National Nuclear Security Administration. “NNSA Releases Draft Plan to Transform
Nuclear Weapons Complex.” Press release, December 18, 2007, at
http://www.nnsa.doe.gov/docs/newsreleases/2007/PR_2007-12-18_NA-07-64.htm; National Nuclear Security
Administration, “Nuclear Weapons Complex Transformation,” with links to plans for each site, at
http://www.nnsa.doe.gov/complextransformation.htm; and Walter Pincus, “Administration Plans to Shrink U.S.
Nuclear Arms Program,” Washington Post, December 19, 2007, p. 1.

Congressional Research Service

29

Energy and Water Development: FY2008 Appropriations

management and technology work linked to multiple warhead types or to no specific warhead
type. It also included funds for the Reliable Replacement Warhead (RRW) program.
RRW originated as a funded program in the FY2005 Consolidated Appropriations Act, P.L. 108447, which included $9.0 million for the program and described it as a “program to improve the
reliability, longevity, and certifiability of existing weapons and their components.” For FY2006,
Congress appropriated $24.8 million. The FY2007 operating plan included $35.8 million, and the
FY2008 request is $88.8 million. Outyear projections are FY2009, $99.8 million; FY2010,
$109.2 million; FY2011, $167.4 million; and FY2012, $179.9 million. (See CRS Report
RL32929, The Reliable Replacement Warhead Program: Background and Current Developments,
by Jonathan Medalia, and CRS Report RL33748, Nuclear Warheads: The Reliable Replacement
Warhead Program and the Life Extension Program, by Jonathan Medalia.)
Although RRW is a small part of the NNSA budget, the House Appropriations Committee, in its
FY2006 report, viewed it as enabling large changes, such as transitioning the Complex “from a
large, expensive Cold War relic into a smaller, more efficient modern complex” and allowing
“long-term savings by phasing out the multiple redundant Cold War warhead designs that require
maintaining multiple obsolete production technologies.” The Senate Appropriations Committee
stated that the recommended funding increase for RRW is “to accelerate the planning,
development and design for a comprehensive RRW strategy that improves the reliability,
longevity and certifiability of existing weapons and their components.” The conference report
emphasized that RRW “must stay within the military requirements of the existing deployed
stockpile” and “must stay within the design parameters validated by past nuclear tests.” P.L. 109163, the FY2006 National Defense Authorization Act, section 3111, set seven objectives for the
RRW program, including “[t]o increase the reliability, safety, and security of the United States
nuclear weapons stockpile” and “[t]o further reduce the likelihood of the resumption of
underground nuclear weapons testing.”
For FY2007, the Administration requested $27.7 million for RRW. The House Appropriations
Committee linked RRW with a restructured, smaller, and consolidated nuclear weapons complex:
“The Committee supports the RRW, but only if it is part of a larger package of more
comprehensive weapons complex reforms.” It recommended $52.7 million for RRW but
restricted use of the additional $25.0 million until NNSA delivered an infrastructure plan to
Congress. The committee also directed NNSA to have the JASON Defense Advisory Group
conduct a peer review of competing RRW designs and to analyze the premise of RRW—that a
new warhead can be designed and deployed without nuclear testing. The bill as passed by the
House left these provisions unchanged.
Also under DSW, the committee (1) reduced the $232.7 million request for warhead life
extension programs by $80.0 million, directed NNSA to terminate the life extension program for
the W80 warhead for cruise missiles, and used the funds to support weapons complex
transformation, and (2) increased funding for warhead dismantlement from $75.0 million to
$105.0 million to accelerate that activity. The bill as passed by the House left these provisions
unchanged.
The Senate Appropriations Committee supported RRW. It found, “The directors of Los Alamos,
Sandia and Livermore National Labs and the Commander, U.S. Strategic Command share the
belief that maintaining incremental modifications to the existing and highly optimized legacy
systems [i.e., life extension programs (LEPs) of warheads now in the stockpile] is not
sustainable.” It “urges the NNSA to accelerate the transition to a responsive infrastructure and to

Congressional Research Service

30

Energy and Water Development: FY2008 Appropriations

proceed expeditiously with the RRW design.” It noted that DOD and the Nuclear Weapons
Council no longer support the W80 LEP, and provided $10.0 million for a design competition for
a second RRW in lieu of W80 LEP activities. It recommended $62.7 million for RRW and
reducing funds for warhead dismantlement to $35.0 million, preferring to ensure that facilities for
disassembling pits and for fabricating mixed-oxide fuel will be built before providing full
funding. DOE’s FY2007 operating plan included $35.8 million for RRW, $264.4 million for Life
Extension Programs, and $75.0 million for weapons dismantlement and disposition.
NNSA requested $88.8 million for RRW for FY2008. (The Navy requested an additional $30.0
million for RRW; those funds are in the defense appropriations bill and are not discussed here.)
NNSA had planned to use the FY2008 RRW funds mainly to develop a detailed cost, scope, and
schedule baseline for RRW. Other DSW funds requested for FY2008 include $238.7 million for
Life Extension Programs, $346.7 million for Stockpile Systems, $52.3 million for Weapons
Dismantlement and Disposition, and $720.8 million for Stockpile Services. The latter category
includes, for example, funds for production support, safety, and other work supporting multiple
warhead types or otherwise not linked to one specific warhead.
The House Appropriations Committee expressed extreme dissatisfaction with the RRW program.
Its FY2008 report stated, “The Committee finds the RRW program the DoD and NNSA have
pursued at the direction of Congress goes far beyond the scope and purpose of the original
congressional language and intent.... The Committee is unconvinced that pursuing the RRW
design competition to a production phase is necessary at this time.” Further,
A particularly troubling issue for the Committee related to the RRW proposal is the
contradictory U.S. policy position of demanding other nations give up their nuclear
ambitions while the U.S. aggressively pursues a program to build new nuclear warheads. The
Administration needs to develop a policy rationale that explains why the RRW program is
not contradictory and does not undermine our international nuclear nonproliferation goals.

As noted above, the committee felt it necessary to have the planning sequence described earlier
before continuing RRW design activities; accordingly, it recommended providing no funds for
RRW for FY2008.
The committee recommended providing $1,336.6 million for DSW, a reduction of $110.6 million
from the request. This reflects reductions of $88.8 million for RRW, $27.4 million for Stockpile
Systems because of the termination of W80 warhead activities, and $115.5 million for Stockpile
Services, and an increase of $121.0 million for weapons dismantlement and disposition.
Regarding the latter category, the committee stated that DOE “must view dismantlement as a
priority in and of itself, rather than as a workload leveling function to fill-in for down times in the
life extension workload at Pantex.” The committee also recommended transferring NNSA’s
activity to build a Pit Disassembly and Conversion Facility from the Office of Defense Nuclear
Nonproliferation to the Office of Defense Programs, and directed DOE to begin the siting process
to build the facility at Pantex Plant (TX) rather than at Savannah River Site (SC) to avoid security
risks in transporting pits from Texas to South Carolina.
The Senate Appropriations Committee provided $66.0 million for NNSA for RRW in order to
complete Phase 2A. As noted earlier, it made clear that it was not committed to proceeding with
Phase 3 but wanted “a more vigorous analysis and debate” first. It wanted more information to
help with this decision, such as characteristics of the future stockpile, the possible effects of RRW
on U.S. nuclear nonproliferation efforts, and comparative costs of RRW vs. LEP. “It will be
incumbent upon NNSA to provide specific details as to how many RRW weapons will be

Congressional Research Service

31

Energy and Water Development: FY2008 Appropriations

manufactured, how the Department of Defense intends to integrate the system into the stockpile
and how many weapons from the existing deterrent can be retired.” While it recommended funds
to continue Phase 2A work on the first RRW type, it barred the use of funds for initial research on
a second RRW type. In other areas of DSW, the committee recommended a net reduction of $37.7
million ($22.8 million from RRW, and $14.9 million, the entire amount requested, from
“responsive infrastructure,” a management program to support decisions on the Complex). It
expressed concern with cost growth in the W76 LEP and commended DOE for recent efforts to
increase the rate at which it dismantled nuclear warheads.
The consolidated appropriations bill eliminated NNSA funds for RRW. The explanatory statement
said, “Congress believes a new strategic nuclear deterrent mission assessment for the 21st century
is required to define the associated stockpile requirements and determine the scope of the
weapons complex modernization plans.” The largest change under DSW was to increase funding
for weapons dismantlement and disposition from $52.3 million requested to $135.9 million. The
bill also provided funds for the Pit Disassembly and Conversion Facility at Savannah River Site
rather than at Pantex.

Campaigns
These are “multi-year, multi-functional efforts” that “provide specialized scientific knowledge
and technical support to the directed stockpile work on the nuclear weapons stockpile.” The
FY2008 request includes six Campaigns, each with multiple components: Science, Engineering,
Inertial Confinement Fusion and High Yield, Advanced Simulation and Computing, Pit
Manufacturing and Certification, and Readiness. Many items within Campaigns have significance
for policy decisions. As one example, the Science Campaign’s goals include improving the ability
to assess warhead performance without nuclear testing, improving readiness to conduct tests
should the need arise, and maintaining the scientific infrastructure of the nuclear weapons
laboratories. Campaigns also fund some large experimental facilities, such as the National
Ignition Facility at Lawrence Livermore National Laboratory, the Dual-Axis Radiographic
Hydrotest Facility at Los Alamos National Laboratory, and the Microsystems and Engineering
Sciences Applications Complex at Sandia National Laboratories.
NNSA’s proposal to build a Modern Pit Facility (MPF) had been controversial for years. A pit is
the fissile core of a nuclear weapon that is used to trigger a thermonuclear explosion. The United
States has been unable to manufacture pits that can be certified for use in the stockpile since
1989. Los Alamos has a small-scale pit manufacturing facility, called TA-55; NNSA’s plan is that
TA-55 would be able to manufacture 10 pits per year by the end of FY2007 and 30-50 RRW pits
per year by FY2012, but NNSA saw that capacity as insufficient to maintain the stockpile and
favored building MPF, with a capacity of perhaps 125 pits per year. H.R. 2419, the FY2006
Energy and Water Development Appropriations Bill, as passed by the House, eliminated MPF
funds until “capacity requirements tied to the long-term stockpile size are determined” and “until
the long-term strategy for the physical infrastructure of the weapons complex has incorporated
the Reliable Replacement Warhead strategy.” The bill as passed by the Senate provided the
amount requested for MPF, $7.7 million. The appropriation bill, as passed, provided no funds for
MPF. Conferees on the energy and water bill directed NNSA to focus instead on improving
manufacturing capability at TA-55. NNSA requested no funds for MPF for FY2007 and instead
planned to increase capacity at TA-55. It requested $237.6 million for the Pit Manufacturing and
Certification campaign for FY2007; H.R. 5427 as passed by the House provided that amount, and
the Senate Appropriations Committee recommended that amount. The FY2007 operating plan
included $242.4 million for this campaign, and the FY2008 request is $281.2 million. NNSA

Congressional Research Service

32

Energy and Water Development: FY2008 Appropriations

envisions a new pit manufacturing facility able to deliver 125 pits per year to the stockpile by
2022 as part of Complex 2030.17
The House Appropriations Committee recommended providing $150.0 million for pit
manufacturing and certification for FY2008, a reduction of $131.2 million on grounds that the
request has funds in multiple lines “that assume a preferred future programmatic approach” that
“ensures unnecessary expenditures and lack of accountability.” It linked pit funding to the
strategic plan discussed above:
The Committee will not continue to fund activities that are not part of a clearly articulated
facilities strategy. Until the Committee receives a new nuclear weapons strategic plan that
addresses the future requirements for plutonium production, including specifically how
plutonium facilities factor into supporting the future stockpile, the Committee will not
support funding activities that assume a modernization-in-place strategy for the current
nuclear weapons complex.
The Committee recommendation includes no funds for the consolidated plutonium center
proposal.

The Senate Appropriations Committee recommended $256.3 million for pit manufacturing for
FY2008, a reduction of $24.9 million. It “does not endorse the consolidated plutonium center and
has not provided any funding for this activity” because DOD “has been unable to articulate a
coherent policy and pit requirement for the stockpile.”
The consolidated appropriations bill provided $215.8 million for pit manufacturing and
certification. It provided no funds for the consolidated plutonium center. According to the
explanatory statement,
Until a modern nuclear weapons strategy, including required pit production capacity defined
by nuclear stockpile requirements, is developed, the NNSA is directed to constrain the outyear planning for plutonium operations to a pit production capacity no greater than 80 pits
per year. The NNSA Administrator is directed to provide quarterly reports to the Committees
on Appropriations on pit production, with the first report due on April 1, 2008.

The appropriate test readiness posture—the time between a presidential order to resume testing
and the conduct of the test—has been contentious. The posture was set at 24 to 36 months after
the Cold War, but NNSA and others expressed concern that it had become 36 months or more.
The Administration and Congress sought to shorten it, but there was a dispute over how much.
NNSA and the Armed Services Committees favored an 18-month posture on grounds that it
would take that long to prepare a test but that any testing should not be delayed beyond that time.
The Appropriations Committees favored a 24-month posture, seeing an 18-month posture as
provocative and more costly. The FY2006 appropriation was $19.8 million. In its FY2007
request, NNSA stated that it achieved a 24-month readiness posture in FY2005 and planned to
maintain that posture at least through FY2011. It stated that the posture is 18 months “under
current law” but that it “has thus far been limited to 24 months by Congressional funding.” The
FY2007 test readiness request was $14.8 million, and NNSA’s operating plan included $14.6
million.
17
U.S. Department of Energy. National Nuclear Security Administration. Office of Defense Programs. Complex 2030:
An Infrastructure Planning Scenario for a Nuclear Weapons Complex Able to Meet the Threats of the 21st Century,
DOE/NA-0013, October 2006, p. 11.

Congressional Research Service

33

Energy and Water Development: FY2008 Appropriations

For FY2008, NNSA requested no funds for test readiness, but plans to request funds for FY2009.
The House provided $20.0 million for test readiness to restore funding to this activity and keep

[Text truncated at 120,000 characters. The full text is on the page linked above.]

---