Navy Constellation (FFG-62) and FF(X) Class
Frigate Programs: Background and Issues for
Congress
Updated January 20, 2026

Congressional Research Service
https://crsreports.congress.gov
R44972

SUMMARY

Navy Constellation (FFG-62) and FF(X) Class
Frigate Programs: Background and Issues for
Congress

R44972
January 20, 2026
Ronald O'Rourke
Specialist in Naval Affairs

Constellation (FFG-62) class program. The Navy began procuring Constellation (FFG-62)
class frigates in FY2020. Prior to November 2025, Navy plans called for procuring a total of at
least 20. Six were procured through FY2025, including one per year in FY2020-FY2023, two in
FY2024, and none in FY2025. The Navy’s proposed FY2026 budget did not request the procurement of any additional FFG62s.
FFG-62s are being built by Fincantieri/Marinette Marine (F/MM) of Marinette, WI. The FFG-62 design is derived from the
design of an Italian-French frigate. Subsequent to the Navy’s April 2020 contract award to F/MM for designing and building
up to 10 FFG-62s, the program fell years behind schedule due in large part to delays in completing the FFG-62 design. In
June 2025, Secretary of Defense Pete Hegseth (who is using “Secretary of War” as a “secondary title” under Executive Order
14347 dated September 5, 2025) indicated that the FFG-62 program was being reviewed as one of several “difficult
decisions” to be made by the Department of Defense (DOD) (which is “using a secondary Department of War designation”
under Executive Order 14347) during a review of its acquisition programs.
Announced FF(X) program. In a series of announcements from November 25 to December 19, 2025, the Navy stated that it
wants to restructure its frigate acquisition effort by (1) truncating the FFG-62 program to no more than two ships and (2)
initiating a new program to procure a different class Navy frigates, called FF(X)s, whose design would be based on that of
the National Security Cutter (NSC), a frigate-like ship that has been built for the Coast Guard by Huntington Ingalls
Industries/Ingalls Shipbuilding (HII/Ingalls) of Pascagoula, MS.
Under the Navy’s desired new approach, the third through sixth FFG-62s (which have not begun construction) would be
cancelled; the first two FFG-62s (construction of which is underway) would remain under review; the first FF(X) would be
awarded to HII/Ingalls on a sole-source basis and be launched (i.e., put into the water for the final stages of its construction)
by 2028; and one or more additional U.S. shipyards would later be brought into the FF(X) program to expand the FF(X)
production rate and compete with HII/Ingalls for future ships in the program. The Navy envisages building a notional total of
50 to 65 FF(X)s.
In announcing its desired new approach for acquiring frigates, Secretary of the Navy John Phelan stated that “the
Constellation-class frigate was canceled because, candidly, it didn’t make sense anymore to build it. It was 80% of the cost of
a [larger DDG-51 class] destroyer and 60% of the capability. You might as well build destroyers.” The continuation, for now
at least, of construction work on the first two FFG-62s reportedly is intended to support F/MM in the near term, while
policymakers assess how F/MM’s shipbuilding capability could be used over the longer run. As of November 25, 2025, the
first ship in the FFG-62 program was reportedly about 12% complete.
An issue for Congress is whether to approve, reject, or modify the Navy’s desired approach for restructuring its frigate
acquisition effort. Decisions that Congress makes on this issue could substantially affect U.S. Navy capabilities and funding
requirements, and the U.S. shipbuilding industrial base.

Congressional Research Service

Navy Constellation (FFG-62) and FF(X) Class Frigate Programs

Contents
Introduction ..................................................................................................................................... 1
Constellation (FFG-62) Class Program ..................................................................................... 1
Announced FF(X) Program....................................................................................................... 1
Issue for Congress ..................................................................................................................... 2
Background ..................................................................................................................................... 2
Navy’s Force of Small Surface Combatants (SSCs) ................................................................. 2
SSCs in General .................................................................................................................. 2
SSC Force-Level Goal ........................................................................................................ 3
SSC Force at Start of FY2026 ............................................................................................ 3
U.S. Navy Frigates in General .................................................................................................. 3
FFG-62 Class Program .............................................................................................................. 4
Program Name .................................................................................................................... 4
Ship Design and Capabilities .............................................................................................. 5
Procurement Quantities and Procurement Cost .................................................................. 6
Acquisition Strategy............................................................................................................ 7
Home Port for Initial Ships in Class ..................................................................................11
Delay in Delivery of First Ship ..........................................................................................11
Issues for Congress Prior to Navy’s November 2025 Announcement .............................. 14
Navy’s Desired Approach for Restructuring Frigate Acquisition............................................ 14
Overview ........................................................................................................................... 14
Navy News Release of December 19, 2025 ...................................................................... 15
National Security Cutter (NSC) Design ............................................................................ 15
Naval Variants of NSC Design Proposed in Past Years by HII/Ingalls ............................. 16
FF(X) Frigate .................................................................................................................... 16
Issues for Congress Regarding Navy’s Desired Approach for Frigate Acquisition ....................... 19
Adequacy of Information Provided to Congress ..................................................................... 19
General Approach Regarding Frigate Acquisition .................................................................. 19
Overview of Four General Approaches ............................................................................ 19
Potential Oversight Questions for Congress ..................................................................... 22
New Frigate Design................................................................................................................. 22
Potential Design Options .................................................................................................. 23
Potential Oversight Questions for Congress ..................................................................... 27
Sole-Source or Competitive Contract Award for First Ship .................................................... 29
Potential Participation of Foreign Shipyards .......................................................................... 29
Unexpended FFG-62 Procurement Funds ............................................................................... 32
Near-Term Support for F/MM ................................................................................................. 32

Figures
Figure 1. Oliver Hazard Perry (FFG-7) Class Frigate ..................................................................... 4
Figure 2. Constellation (FFG-62) Class Frigate .............................................................................. 5
Figure 3. FFG-62 Design Compared to FREMM Design ............................................................... 9
Figure 4. National Security Cutter................................................................................................. 17
Figure 5. Rendering of FF(X) Design ........................................................................................... 18
Figure 6. Rendering and Selected Details of FF(X) Design .......................................................... 18

Congressional Research Service

Navy Constellation (FFG-62) and FF(X) Class Frigate Programs

Figure 7. Multi-Mission Surface Combatant (MMSC) ................................................................. 25
Figure 8. Mogami-Class Frigate .................................................................................................... 25
Figure 9. Daegu-Class Frigate ....................................................................................................... 26
Figure 10. Álvaro de Bazán-class F100 Frigate ............................................................................ 27

Tables
Table 1. Programmed and Actual Annual FFG-62 Procurement Quantities.................................... 7

Appendixes
Appendix A. Issues for Congress Prior to Navy’s November 2025 Announcement ..................... 34
Appendix B. Guaranty vs. Warranty in Construction Contract ..................................................... 40

Contacts
Author Information........................................................................................................................ 42

Congressional Research Service

Navy Constellation (FFG-62) and FF(X) Class Frigate Programs

Introduction
This report provides background information and discusses potential oversight issues for
Congress regarding the Navy’s effort to acquire new frigates, including Constellation (FFG-62)
class frigates and a type of frigate proposed by the Navy called the FF(X).

Constellation (FFG-62) Class Program
The Navy began procuring Constellation (FFG-62) class frigates in FY2020. Prior to November
2025, Navy plans called for procuring a total of at least 20. Six were procured through FY2025,
including one per year in FY2020-FY2023, two in FY2024, and none in FY2025. The Navy’s
proposed FY2026 budget did not request the procurement of any additional FFG-62s.
FFG-62s are being built by Fincantieri/Marinette Marine (F/MM) of Marinette, WI. The FFG-62
design is derived from the design of an Italian-French frigate. Subsequent to the Navy’s April
2020 contract award to F/MM for designing and building FFG-62s, the program fell years behind
schedule due in large part to delays in completing the FFG-62 design. In June 2025, Secretary of
Defense Pete Hegseth (who is using “Secretary of War” as a “secondary title” under Executive
Order 14347 dated September 5, 2025) indicated that the FFG-62 program was being reviewed as
one of several “difficult decisions” to be made by the Department of Defense (DOD) (which is
“using a secondary Department of War designation” under Executive Order 14347) during a
review of its acquisition programs.1

Announced FF(X) Program
In a series of announcements from November 25 to December 19, 2025, the Navy stated that it
wants to restructure its frigate acquisition effort by (1) truncating the FFG-62 program to no more
than two ships and (2) initiating a new program to procure a different class Navy frigates, called
FF(X)s, whose design would be based on that of the National Security Cutter (NSC), a frigatelike ship that has been built for the Coast Guard by Huntington Ingalls Industries/Ingalls
Shipbuilding (HII/Ingalls) of Pascagoula, MS.
Under the Navy’s desired new approach, the third through sixth FFG-62s (which have not begun
construction) would be cancelled; the first two FFG-62s (construction of which is underway)
would remain under review; the first FF(X) would be awarded to HII/Ingalls on a sole-source
basis and be launched (i.e., put into the water for the final stages of its construction) by 2028; and
one or more additional U.S. shipyards would later be brought into the FF(X) program to expand
the FF(X) production rate and compete with HII/Ingalls for future ships in the program.2 The
Navy envisages building a notional total of 50 to 65 FF(X)s.

1 Tony Bertuca, “Hegseth Indicates Frigate Program Is on the Chopping Block,” Inside Defense, June 12, 2025.
2 See, for example, U.S. Navy, “Navy Announces New Small Surface Combatant,” press release dated December 19,

2025; Huntington Ingalls Industries, “HII to Build Small Surface Combatants for US Navy,” news release dated
December 19, 2025; Justin Katz, “Navy Announces New Frigate Class, Taps HII to Build Off National Security
Cutter,” Breaking Defense, December 19, 2025; Sam LaGrone, “SECNAV: New Frigate will be Based on National
Security Cutter, First FF(X) to be Built at Ingalls,” USNI News, December 19 2025; Joseph Trevithick, “This Will Be
The Navy’s New FF(X) Frigate,” The War Zone, December 19, 2025; Joseph Trevithick, “U.S. Navy Now Wants A
New Frigate And Fast,” Breaking Defense, December 12, 2025; Justin Katz, “Navy Wants New Frigate in 2028, Says
Service’s Acquisition Head,” Breaking Defense, December 10, 2025; Rich Abott, “Navy “Golden Fleet” Plan To
Include Another Frigate, LSM To Avoid Change Orders,” Defense Daily, December 9, 2025; Mike Glenn, “Navy
(continued...)

Congressional Research Service

1

Navy Constellation (FFG-62) and FF(X) Class Frigate Programs

In announcing its desired new approach for acquiring frigates, Secretary of the Navy John Phelan
stated that “the Constellation-class frigate was canceled because, candidly, it didn’t make sense
anymore to build it. It was 80% of the cost of a [larger DDG-51 class] destroyer3 and 60% of the
capability. You might as well build destroyers.” 4 The continuation, for now at least, of
construction work on the first two FFG-62s reportedly is intended to support F/MM in the near
term, while policymakers assess how F/MM’s shipbuilding capability could be used over the
longer run. 5 As of November 25, 2025, the first ship in the FFG-62 program was reportedly about
12% complete.6

Issue for Congress
An issue for Congress is whether to approve, reject, or modify the Navy’s desired approach for
restructuring its frigate acquisition effort. Decisions that Congress makes on this issue could
substantially affect U.S. Navy capabilities and funding requirements, and the U.S. shipbuilding
industrial base.

Background
Navy’s Force of Small Surface Combatants (SSCs)
SSCs in General
In discussing its force-level goals and 30-year shipbuilding plans, the Navy organizes its surface
combatants into large surface combatants (LSCs), meaning the Navy’s cruisers and destroyers,
and small surface combatants (SSCs), meaning the Navy’s frigates, Littoral Combat Ships
(LCSs), mine warfare ships, and patrol craft.7 SSCs are smaller, less capable in some respects,
and individually less expensive to procure, operate, and support than LSCs. SSCs can operate in
conjunction with LSCs and other Navy ships, particularly in higher-threat operating
environments, or independently, particularly in lower-threat operating environments.

Secretary Announces New Frigate Program after Canceling Future Constellation-Class Warships,” Washington Times,
December 9, 2025; Lauren C. Williams, “And Just Like That, the Navy’s Frigate Program Is Back On—Sort Of,”
Defense One, December 8, 2025; Tom Kington, “US Navy Nixes Constellation Frigate Program after Two Ships HalfBuilt,” Defense News, November 26, 2025; Rich Abott, “Navy Cancels Constellation-Class Frigate, Will Only Retain
Two Under Construction,” Defense Daily, November 25, 2025; Anthony Capaccio, “Navy Cuts Orders for Frigate
Trump Once Touted as ‘Beautiful,’” Bloomberg, November 25, 2025; Drew FitzGerald and Lara Seligman, “Navy
Scraps Plans for Troubled Warship Design,” Wall Street Journal, November 25, 2025; Sam LaGrone, “Navy Cancels
Constellation-class Frigate Program, Considering New Small Surface Combatants,” USNI News, November 25, 2025.
3 For more on the DDG-51 class destroyer program, see CRS Report RL32109, Navy DDG-51 and DDG-1000
Destroyer Programs: Background and Issues for Congress, by Ronald O'Rourke.
4 See, for example, Mike Glenn, “Navy Wants New Frigate in 2028, Says Service’s Acquisition Head,” Washington
Times, December 10, 2025; Rich Abott, “Navy “Golden Fleet” Plan To Include Another Frigate, LSM To Avoid
Change Orders,” Defense Daily, December 9, 2025; Joseph Trevithick, “U.S. Navy Now Wants A New Frigate And
Fast,” The War Zone, December 12, 2025.
5 Sam LaGrone, “Navy Cancels Constellation-class Frigate Program, Considering New Small Surface Combatants,”
USNI News, November 25, 2025.
6 Sam LaGrone, “Navy Cancels Constellation-class Frigate Program, Considering New Small Surface Combatants,”
USNI News, November 25, 2025.
7 See, for example, CRS Report RL32665, Navy Force Structure and Shipbuilding Plans: Background and Issues for
Congress, by Ronald O'Rourke.

Congressional Research Service

2

Navy Constellation (FFG-62) and FF(X) Class Frigate Programs

SSC Force-Level Goal
The Navy’s FY2025 30-year (FY2025-FY2054) shipbuilding plan calls for a future Navy of 381
manned battle force ships, including 73 SSCs, of which 15 are to be LCSs capable of conducting
mine warfare operations, plus 58 “FFG / FFG Flt II” ships, meaning 58 frigates and frigates built
to a modified (i.e., Flight II) design.8 Under its FY2025 budget submission, the Navy wanted to
maintain a force of 25 (rather than 15) LCSs. This could imply a total of 48 (rather than 58)
frigates.
The Navy reportedly has prepared a new ship force-level objective, referred to as the Golden
Fleet, to succeed the 381-ship objective. The composition of this new force-level objective,
including the number of frigates and other SSCs, had not been announced as of late December
2025.9

SSC Force at Start of FY2026
The Navy’s force of SSCs at the start of FY26 consisted of 32 ships, including no frigates, 28
LCSs, and 4 mine warfare ships. The Navy has been retiring its mine warfare ships as LCSs
(some of which are to serve as replacement mine countermeasures ships) have entered service.
The figure of 32 ships equates to about 44% of the 73-ship force-level goal for SSCs discussed in
the previous section.

U.S. Navy Frigates in General
As mentioned earlier SSCs (including frigates) can operate in conjunction with LSCs (i.e.,
cruisers and destroyers), particularly in higher-threat operating environments, or independently,
particularly in lower-threat operating environments. U.S. Navy frigates perform many of the same
peacetime and wartime missions as U.S. Navy cruisers and destroyers, but are equipped with
fewer weapons, less-capable radars and other systems, and less engineering redundancy and
survivability than cruisers and destroyers.10
The most recent class of frigates operated by the Navy was the Oliver Hazard Perry (FFG-7) class
(Figure 1). A total of 51 FFG-7s were procured between FY1973 and FY1984. The ships were

8 U.S. Navy, Report to Congress on the Annual Long-Range Plan for Construction of Naval Vessels for Fiscal Year

2025, March 2024, Table 1 on page 4, column entitled “June 2023 BFSAR [Battle Force Ship Assessment and
Requirement] Report.
9 See, for example, Rich Abott, “Navy ‘Golden Fleet’ Plan To Include Another Frigate, LSM To Avoid Change
Orders,” Defense Daily, December 9, 2025.
10 Compared to cruisers and destroyers, frigates can be a more cost-effective way to perform missions that do not
require the use of a higher-cost cruiser or destroyer. In the past, the Navy’s combined force of higher-capability,
higher-cost cruisers and destroyers and lower-capability, lower-cost frigates has been referred to as an example of a socalled high-low force mix. High-low mixes have been used by the Navy and the other military services in recent
decades as a means of balancing desires for individual platform capability against desires for platform numbers in a
context of varied missions and finite resources.
Peacetime missions performed by frigates can include, among other things, engagement with allied and partner navies,
maritime security operations (such as anti-piracy operations), and humanitarian assistance and disaster response
(HA/DR) operations. Intended wartime operations of frigates include escorting (i.e., protecting) military supply and
transport ships and civilian cargo ships that are moving through potentially dangerous waters. In support of intended
wartime operations, frigates are designed to conduct anti-air warfare (AAW—aka air defense) operations, anti-surface
warfare (ASuW) operations (meaning operations against enemy surface ships and craft), and antisubmarine warfare
(ASW) operations. U.S. Navy frigates are designed to operate in larger Navy formations or as solitary ships. Operations
as solitary ships can include the peacetime operations mentioned above.

Congressional Research Service

3

Navy Constellation (FFG-62) and FF(X) Class Frigate Programs

built by three shipyards,11 entered service between 1977 and 1989, and were decommissioned
between 1994 and 2015. In their final configuration, FFG-7s were about 455 feet long and had
full load displacements of roughly 3,900 tons to 4,100 tons. (By comparison, the Navy’s Arleigh
Burke [DDG-51] class destroyers are about 510 feet long and have full load displacements of
roughly 9,700 tons.12) Following their decommissioning, a number of FFG-7s, like certain other
decommissioned U.S. Navy ships, were transferred to the navies of U.S. allied and partner
countries.
Figure 1. Oliver Hazard Perry (FFG-7) Class Frigate

Source: Photograph accompanying Dave Werner, “Fighting Forward: Last Oliver Perry Class Frigate
Deployment,” Navy Live, January 5, 2015, accessed September 21, 2017, at http://navylive.dodlive.mil/2015/01/05/
fighting-forward-last-oliver-perry-class-frigate-deployment/.

FFG-62 Class Program
Program Name
The FFG-62 program was earlier known as the FFG(X) program.13 On October 7, 2020, the Navy
announced that the first ship in the class, FFG-62, would be named Constellation, in honor of the
11 The three shipyards were Bath Iron Works (BIW) of Bath, ME (now referred to as General Dynamics/Bath Iron

Works or GD/BIW), Todd Shipyards of Seattle, WA, and Todd Shipyards of San Pedro, CA. Todd Shipyards of Seattle
was acquired in 2011 by Vigor Shipyards. (See, for example, “Vigor Shipyards,” Wikipedia, edited January 22, 2024.)
Todd Shipyards of San Pedro was closed in 1989 following the completion of its FFG-7 construction work. (See, for
example, “Todd Pacific Shipyards, Los Angeles Division,” Wikipedia, edited January 26, 2023.)
12 This is the displacement for the current (Flight III) version of the DDG-51 design.
13 In the designation FFG(X), FF meant frigate, G meant guided-missile ship (indicating a ship equipped with an areadefense anti-air warfare [AAW] system), and (X) indicated that the specific design of the ship had not yet been
determined. FFG(X) thus meant a guided-missile frigate whose specific design had not yet been determined.
The designation FF, with two Fs, means frigate in the same way that the designation BB, with two Bs, means
battleship, the designation DD, with two Ds, means destroyer, and the designation SS, with two Ss, means submarine.
FF is sometimes translated less accurately as fast frigate. FFs, however, are not particularly fast by the standards of
U.S. Navy surface combatants—their maximum sustained speed, for example, is generally lower than that of U.S. Navy
aircraft carriers, cruisers, and destroyers. In addition, there is no such thing in the U.S. Navy as a slow frigate.
Some U.S. Navy surface combatants are equipped with a point-defense AAW system, meaning a short-range AAW
system that is designed to protect the ship itself. Other U.S. Navy surface combatants are equipped with an area(continued...)

Congressional Research Service

4

Navy Constellation (FFG-62) and FF(X) Class Frigate Programs

first U.S. Navy ships authorized by Congress in 1794—the six heavy frigates United States,
Constellation, Constitution, Chesapeake, Congress, and President. FFG(X)s henceforth became
known as Constellation (FFG-62) class ships.

Ship Design and Capabilities
FFG-62s (Figure 2) are intended to be multimission small surface combatants capable of
conducting anti-air warfare (AAW), anti-surface warfare (ASuW), antisubmarine warfare (ASW),
and electromagnetic warfare (EMW) operations. They are to be capable of operating in both blue
water (i.e., mid-ocean) and littoral (i.e., near-shore) areas, and capable of operating either
independently (when that is appropriate for their assigned missions) or as part of larger Navy
formations.
Figure 2. Constellation (FFG-62) Class Frigate
Artist’s rendering of F/MM design

Source: Illustration accompanying Alistair MacDonald and Gordon Lubold, “The Warship That Shows Why the
U.S. Navy Is Falling Behind China,” Wall Street Journal, March 20, 2025. The caption to the photograph credits the
photograph to Fincantieri/Marinette Marine.

The FFG-62 design is based on the design of the Italian-French FREMM (Fregata Europea MultiMissione) frigate, a ship that has been built in two variants, one for the Italian navy and one for
the French navy. The FREMM design, in other words, served as what is known as the “parent”
design for the FFG-62 design. The use of a parent design for the FFG-62 program is discussed
further in the section below on the FFG-62 program’s acquisition strategy.
At the time of the FFG-62 contract award (see below), the FFG-62 was described as having an
estimated full load displacement of about 7,300 or 7,400 tons. As design work on the FFG-62
continued, the ship’s estimated full load displacement grew by several hundred tons, to a figure

defense AAW system, meaning a longer-range AAW system that is designed to protect not only the ship itself, but
other ships in the area as well. U.S. Navy surface combatants equipped with an area-defense AAW system are referred
to as guided-missile ships and have a “G” in their designation.

Congressional Research Service

5

Navy Constellation (FFG-62) and FF(X) Class Frigate Programs

much closer to 8,000 tons. (As noted earlier, by comparison, the Navy’s newest DDG-51 class
destroyers have full load displacements of roughly 9,700 tons.)

Procurement Quantities and Procurement Cost
Total Procurement Quantity
Until November 2025, the Navy wanted to procure at least 20 FFG-62s. Navy budget documents,
including the FY2025 budget-justification book for Navy’s shipbuilding account, described the
FFG-62 program as a 20-ship program.
As discussed earlier, the Navy’s FY2025 30-year (FY2025-FY2054) shipbuilding plan calls for a
future Navy of 381 manned battle force ships, including 58 “FFG / FFG Flt II” ships, meaning 58
frigates and frigates built to a modified (i.e., Flight II) design.14 The reference to a Flight II design
might be interpreted as referring to a modified (i.e., Flight II) version of the FFG-62 design. Such
an interpretation would imply a combination of 20 (or more) FFG-62s built to the original (i.e.,
Flight I) FFG-62 design plus 38 (or fewer) additional FFG-62s built to a modified (i.e., Flight II)
FFG-62 design.
As also discussed earlier, under its FY2025 budget submission, the Navy wants to maintain a
force of 25 (rather than 15) LCSs. This could imply a total of 48 (rather than 58) frigates. As also
mentioned earlier, The Navy reportedly has prepared a new ship force-level objective, referred to
as the Golden Fleet, to succeed the 381-ship objective. The composition of this new force-level
objective, including the number of frigates and other SSCs, had not been announced as of late
December 2025.

Annual Procurement Quantities
Table 1 shows programmed annual procurement quantities for the FFG-62 program under the
Navy’s budget submissions for FY2020 through FY2026, along with actual procurement
quantities for FY2020 through FY2025.

Procurement Cost
Under the Navy’s FY2026 budget submission, FFG-62s generally had budgeted procurement
costs of roughly $1.2 billion to $1.3 billion each. The lead ship in the program had a higher
estimated procurement cost ($1,499.3 million, or about $1.5 billion) than the follow-on ships
because it is at the top of the production learning curve for the class, and because the lead ship’s
procurement cost incorporates much of the detailed design/nonrecurring engineering (DD/NRE)
costs for the class. (It is a traditional Navy budgeting practice to attach most or all of the
DD/NRE costs for a new ship class to the procurement cost of the lead ship in the class.) As
discussed in Appendix A, one potential oversight issue for Congress for the FFG-62 program has
been the potential for cost growth (i.e., the potential for FFG-62 procurement costs to increase
above figures shown in the Navy’s FY2026 budget submission).

14 U.S. Navy, Report to Congress on the Annual Long-Range Plan for Construction of Naval Vessels for Fiscal Year

2025, March 2024, Table 1 on page 4, column entitled “June 2023 BFSAR [Battle Force Ship Assessment and
Requirement] Report.

Congressional Research Service

6

Navy Constellation (FFG-62) and FF(X) Class Frigate Programs

Table 1. Programmed and Actual Annual FFG-62 Procurement Quantities
FY20

FY21

FY22

FY23

FY24

FY25

FY26

FY27

FY28

FY29

1

2

2

2

2

1

1

2

2

3

Dec. 9, 2020, document

1

3

3

4

4

FY22 budget submission

1

n/a

n/a

n/a

n/a

1

2

1

2

1

2

1

2

1

2

1

2

1

2

1

0

n/a

n/a

n/a

Programmed
FY20 budget submission
FY21 budget submission

FY23 budget submission
FY24 budget submission
FY25 budget submission
FY26 budget submission
Actual

1

1

1

1

2

n/a

0

Sources: Table prepared by CRS based on Navy’s FY2020-FY2026 budget submissions; December 9, 2020,
long-range Navy shipbuilding document; and enacted National Defense Authorization Acts (NDAAs) and DOD
Appropriations Acts for FY2020 and subsequent years.
Notes: n/a means not available. DOD’s FY2022 budget submission was a single-year budget that did not contain
line-item details for subsequent fiscal years.

Acquisition Strategy
Number of Builders
The Navy’s baseline plan for the FFG-62 program envisaged using a single builder at any one
time to build FFG-62s, but Navy officials also spoke about the option of bringing a second
shipyard into the program at some point, particularly if annual procurement rates for FFG-62s
rose above two ships per year.15

Parent-Design Approach
As noted earlier, FFG-62s are to be built to a modified version of an existing ship design—an
approach, called the parent-design approach, that in theory can reduce design time, design cost,
15 See, for example, U.S. Navy, Report to Congress on the Annual Long-Range Plan for Construction of Naval Vessels

for Fiscal Year 2025, March 2024, p. 13.
On November 15, 2024, the Navy released a Sources Sought Request for Information (RFI) “to identify qualified U.S.
surface combatant Shipbuilders as sources for future design and/or follow-on construction of the Constellation Class
Frigate,” inviting “all U.S. surface combatant shipbuilding sources who are interested in the FFG 62 Class ships, to
submit written information sufficient to demonstrate their ability to fulfill the Government requirements.” Responses to
the RFI were due by November 22, 2024. (“FFG 62 Constellation Class Frigate Program, Sources Sought / Request for
Information,” published November 15, 2024, at https://sam.gov/opp/5df8c0d9f5da4805a080e066928011f2/view. See
also Justin Katz, “State of Play: Industry Readying for Second Chance at US Navy’s Frigate Program,” Breaking
Defense, December 20, 2024.)
In December 2024, a Navy official reportedly stated that having a mature design for the FFG-62 program—something
that the Navy reportedly anticipated having by May 2025—“will form the basis of a potential follow-on contract
competition [i.e., a potential competition to select a second shipyard] anticipated in” FY2027. (Mallory Shelbourne and
Sam LaGrone, “Navy: Constellation Frigate Design Will be Ready in May, Second Yard Could Come in FY 2027,”
USNI News, December 13, 2024. See also Nick Wilson, “Navy Punting LSM Award Due to Pricier-than-Expected
Bids,” Defense Daily, December 11, 2024, which reports on both the Navy’s Medium Landing Ship (LSM) program
and the FFG-62 program.)

Congressional Research Service

7

Navy Constellation (FFG-62) and FF(X) Class Frigate Programs

and cost, schedule, and technical risk in building the ship. Industry teams competing for the FFG62 were required to show that their bid was based on a parent design. The Coast Guard and the
Navy are currently using the parent-design approach for the Coast Guard’s Polar Security Cutter
(PSC) (i.e., heavy polar icebreaker) program16 and the Navy’s medium landing ship (LSM)
program.17 The parent-design approach has also been used in the past for other Navy and Coast
Guard ships, including Navy mine warfare ships18 and the Coast Guard’s new Fast Response
Cutters (FRCs).19
Some observers have questioned the value of using parent designs in military shipbuilding
programs. A 2015 journal article, for example, states
The U.S. Navy has experimented with many approaches to design and build its ships. Using
an existing design as the “parent” design, also referred to as “modified-repeat” design, is
on its face an attractive option. Many acquisition executives, program managers and some
ship design engineers believe that a design based on a parent has fewer technical risks than
a new “clean sheet of paper” design and therefore the time and cost to design and build it
will be reduced. They assume early in the ship acquisition program that “the design is
mature” and because of that fewer problems will be encountered in completing the design
and savings will thus be accrued. Yet, a number of naval ships based on a parent design
have in fact experienced unanticipated cost and schedule growth during construction as
well as technical problems during their in-service life. The authors will examine some of
these ship designs which were based on an existing design and/or prototypes and highlight
the fallacies of such beliefs and assumptions.20

Figure 3 shows a U.S. Navy briefing slide summarizing what the U.S. Navy says are the
“primary differences between the FFG 62 Class [design] and the FREMM Parent design.” The
Navy states that the design differences “were proposed by [the shipbuilding firm] Fincantieri and
incorporated [into Fincantieri’s proposed design for the FFG-62] prior to [the Navy’s] contract
award [for the FFG-62 program to Fincantieri].”21 An August 4, 2021, press report states
The Navy has chosen to elongate and widen the hull of its next-generation Constellationclass frigate relative to the [FREMM] parent design, but the officer overseeing its
production says the internal layout will largely remain the same.
“The Italians did a very good job in the design of the internal spaces, and the flow of a lot
of those spaces,” Capt. Kevin Smith, program manager for the Constellation class, told
attendees at the Sea Air Space exposition on Monday [August 2]. “You could say we
bought a bigger house, [but] from a modeling and simulation perspective, it’s exactly the
same.”…

16 For more on the PSC program, including the parent-design approach, see CRS Report RL34391, Coast Guard Polar

Security Cutter (Polar Icebreaker) Program: Background and Issues for Congress, by Ronald O'Rourke.
17 For more on the LSM program, see CRS Report R46374, Navy Medium Landing Ship (LSM) Program: Background
and Issues for Congress, by Ronald O'Rourke.
18 The Navy’s Osprey (MCM-51) class mine warfare ships are an enlarged version of the Italian Lerici-class mine
warfare ships.
19 The FRC design is based on a Dutch patrol boat design, the Damen Stan Patrol Boat 4708.
20 Robert G. Keane Jr. and Barry F. Tibbitts, “The Fallacy of Using a Parent Design: ‘The Design Is Mature,’”
Transactions (Society of Naval Architects and Marine Engineers [SNAME]), 2015, No. 1 (January): 91-104, with
additional discussion from the authors and other commentators on pages 105-122. The quoted passage appears at the
start of the article, on page 91, where it forms part of an abstract or summary for the article.
21 Source: Navy information paper dated August 18, 2021, on differences between FFG-62 design and FREMM parent
design, provided to CRS and the Congressional Budget Office (CBO) by Navy Office of Legislative Affairs on August
27, 2021.

Congressional Research Service

8

Navy Constellation (FFG-62) and FF(X) Class Frigate Programs

While some changes are to be expected to meet the Navy’s needs, enlarging the hullform
itself has the potential to change where components in the ship must be placed, as well as
the overall cost.
Asked about how possible changes in the ship’s hull could affect the internal design, Smith
said Fincantieri Marinette Marine, the Constellation’s prime contractor, worked with Naval
Surface Warfare Center Carderock to develop a scale model of the ship and that most
elements will stay true to the parent design. He cited the bridge and propulsion plant as
areas where the Navy has not made any significant changes to the layout.22

Figure 3. FFG-62 Design Compared to FREMM Design

Source: Navy briefing slide provided to CRS and Congressional Budget Office (CBO) by Navy Office of
Legislative Affairs, August 27, 2021, with accompanying Navy information paper dated August 18, 2021.

An April 2, 2024, press report states: “At one point the Constellation design shared about 85
percent commonality with the original FREMM design, but the alterations have brought that
commonality down to under 15 percent, a person familiar with the changes told USNI News.”23 If
the FFG-62 design shares less than 15% commonality with the FREMM design, then some

22 Justin Katz, “Navy Says Constellation Hull Change Won’t Affect Internal Design,” Breaking Defense, August 4,

2021.
23 Mallory Shelbourne and Sam LaGrone, “Constellation Frigate Delivery Delayed 3 Years, Says Navy,” USNI News,
April 2 (updated April 3), 2024.

Congressional Research Service

9

Navy Constellation (FFG-62) and FF(X) Class Frigate Programs

observers might characterize the FFG-62 program as having moved over time toward what might
be termed a parent design in name only (PDINO) design approach.24
A Navy official commenting on the FFG-62 program in February 2025 reportedly stated that “[it]
turns out modifying someone else’s design is a lot harder than it seems,” and that “sometimes,
you’re just better off designing a new ship.”25 Another Navy official, also commenting on the
FFG-62 program in February 2025, reportedly stated that “I’ll be brutally honest, I don’t think
people truly understood what it meant to adapt a parent design to Navy requirements.”26

No New Technologies or Systems
As a measure for reducing cost, schedule, and technical risk in the FFG-62 program, the Navy
envisaged developing no new technologies or systems for FFG-62s—the ships are to use systems
and technologies that already exist or are already being developed for use in other programs.

Legislation Regarding U.S. Content Requirements for FFG-62 Components
Section 856 of the FY2020 National Defense Authorization Act (S. 1790/P.L. 116-92 of
December 20, 2019) states
SEC. 856. APPLICATION OF LIMITATION ON PROCUREMENT OF GOODS
OTHER THAN UNITED STATES GOODS TO THE FFG–FRIGATE PROGRAM.
Notwithstanding any other provision of law, amounts authorized to carry out the FFG–
Frigate Program may be used to award a new contract that provides for the acquisition of
the following components regardless of whether those components are manufactured in the
United States:
(1) Auxiliary equipment (including pumps) for shipboard services.
(2) Propulsion equipment (including engines, reduction gears, and propellers).
(3) Shipboard cranes.
(4) Spreaders for shipboard cranes.

Section 8097(b) of the FY2024 DOD Appropriations Act (Division A of H.R. 2882/P.L. 118-47 of
March 23, 2024) states
SEC. 8097….
(b) None of the funds provided in this Act for the FFG(X) Frigate program shall be used to
award a new contract that provides for the acquisition of the following components unless
those components are manufactured in the United States: Air circuit breakers;
gyrocompasses; electronic navigation chart systems; steering controls; pumps; propulsion
and machinery control systems; totally enclosed lifeboats; auxiliary equipment pumps;
shipboard cranes; auxiliary chill water systems; and propulsion propellers: Provided, That
the Secretary of the Navy shall incorporate United States manufactured propulsion engines

24 The phrase parent design in name only (with the resulting acronym PDINO) is only one possible shorthand way of

referring to the situation. One possible way to pronounce the acronym PDINO would be pa-DEE-no.
25 Former Assistant Secretary of the Navy (Research, Development, and Acquisition), as quoted in John Grady,
“Navy’s Plan for Frigate Parent Design Caused Delays, Former Acquisition Chief Says,” USNI News, February 19,
2025.
26 Captain Andy Gold, program manager for the FFG-62 program within Program Executive Office (PEO) Unmanned
and Small Combatants, as quoted in Rich Abott, “Frigate Manager Says Design To Finish This Year, Delays Because
Parent Design Mods Not Understood,” Defense Daily, January 15, 2025.

Congressional Research Service

10

Navy Constellation (FFG-62) and FF(X) Class Frigate Programs

and propulsion reduction gears into the FFG(X) Frigate program beginning not later than
with the eleventh ship of the program.

Provisions similar to Section 8097(b) have been included in annual DOD appropriations acts
since the FY2020 DOD appropriations act.

Competition and Contract Award
Four industry teams competed for the FFG-62 program. On April 30, 2020, the Navy announced
that it had awarded the FFG-62 contract to the team led by Fincantieri/Marinette Marine (F/MM)
of Marinette, WI. F/MM was awarded a fixed-price incentive (firm target) contract for Detail
Design and Construction (DD&C) for up to 10 FFG-62s—the lead ship plus nine option ships.
The other three industry teams reportedly competing for the program were led by Austal USA of
Mobile, AL; General Dynamics/Bath Iron Works (GD/BIW) of Bath, ME; and Huntington Ingalls
Industries/Ingalls Shipbuilding (HII/Ingalls) of Pascagoula, MS.
As noted earlier, industry teams competing for the FFG-62 were required to show that their bid
was based on a parent design. The team led by F/MM based its bid on the Italian-French FREMM
frigate. The team led by Austal based its bid on Independence (LCS-2) class Littoral Combat
(LCS) design (a design that Austal was building for the U.S. Navy).27 The team led by GD/BIW
based its bid on the Spanish Navantia F100 frigate design. At the time of the competition, the
team led by HII/Ingalls did not publicly disclose its parent design.28 December 2025 press reports
stated that HII now acknowledges that its parent design was the NSC design.29

Home Port for Initial Ships in Class
A June 2, 2021, Navy press release stated that “Naval Station Everett30 was designated as the
Navy’s future homeport for the initial ships” in the FFG-62 program, serving as “the homeport for
12 Constellation-class Frigates, with a future Navy homeport decision planned for the following
ships.”31

Delay in Delivery of First Ship
Subsequent to the April 2020 contract award, the FFG-62 program fell years behind schedule due
in large part to delays in completing the ship’s design. The Navy’s submission for the FY2020
budget—the budget that requested the procurement of the first ship in the program—estimated
that the first ship would be delivered in July 2026. On April 2, 2024, as part of an announcement
of significant delays to several Navy shipbuilding programs caused by shipbuilder workforce
challenges, supply chain issues, and other causes, the Navy announced that the estimated delay in
the delivery of the first FFG-62 had grown to 36 months. The Navy’s FY2026 budget estimated
that the ship would be delivered in April 2029, a delay of 33 months from the July 2026 date
shown in the FY2020 budget submission. As mentioned earlier, as of November 2025, the first
ship in the program reportedly was about 12% complete.

27 For more on the LCS program, see CRS Report RL33741, Navy Littoral Combat Ship (LCS) Program: Background

and Issues for Congress, by Ronald O'Rourke.
28 See page 2 and Table 2 (on page 9) of the April 17, 2020, update of this CRS report.
29 Joseph Trevithick, “U.S. Navy Now Wants A New Frigate And Fast,” The War Zone, December 12, 20205.
30 Naval Station Everett is located in Everett, WA, which is on Puget Sound north of Seattle.
31 U.S. Navy, “Naval Station Everett Future Homeport for New Constellation Class Frigates,” press release dated June
2, 2021.

Congressional Research Service

11

Navy Constellation (FFG-62) and FF(X) Class Frigate Programs

A June 2025 Government Accountability Office (GAO) report—the 2025 edition of an annual
GAO report on selected DOD acquisition programs—stated the following regarding schedule
delay and other aspects of the FFG-62 program:
Program Performance
Since our last assessment, the program continued to face challenges completing its
functional design, which is needed to demonstrate design stability. More than 2 years after
beginning lead ship construction, this persistent lack of design stability stalled construction
of the lead ship and poses the same risk to initial follow-on ships. The Navy currently plans
to deliver the lead frigate in April 2029—3 years later than the original contracted delivery
date. The Navy and shipbuilder continue to revise basic design documents, including the
ship’s general arrangement drawings—the design drawings that all other design aspects are
based on—and structural components of the ship. This approach is inconsistent with
shipbuilding leading practices, which call for completion of basic and functional design
activities prior to construction start.
Further, in response to a recommendation we made in our May 2024 report, the program
restructured its functional design metrics to more closely align with actual design progress.
As a result, the program concluded that its functional design progress is significantly less
than the 92 percent complete it reported in August 2023. As of December 2024, the
program reported that the functional design was 70 percent complete, as measured with the
restructured design metrics. Although program officials expect to achieve a stable basic
and functional design by late spring 2025, the program has yet to achieve its planned rate
of design progress to meet this goal.
The frigate design is further complicated by unanticipated weight growth. In October 2024,
the Navy reported 759 metric tons of weight growth from initial estimates—nearly a 13
percent increase—due in part to the underestimation of applying Navy technical
requirements to a foreign ship design. Navy personnel are working with the shipbuilder to
reduce the ship’s weight, but weight growth has only become more pronounced over the
last year as the program further developed the frigate design. We previously reported that
unplanned weight growth during ship construction can compromise ship capabilities, as
the fleet seeks to alter and improve initial capabilities over the planned decades-long
service life of the ship. Such alterations may leave frigates less combat capable, limit the
ability to add capabilities to address evolving threats, and reduce planned service lives.
Leading Product Development Practices
In May 2024, we reported that the frigate program employed a traditional, linear
development approach to acquisition, in contrast to leading companies’ use of iterative
design approaches centered on identifying a minimum viable product to quickly meet
users’ needs. We recommended that the Navy evaluate ways to incorporate these leading
practices into the frigate acquisition strategy prior to the acquisition of an 11th ship. The
Navy stated that it is taking steps to implement this recommendation.
Program officials stated that plans for a digital twin and digital thread will not be
incorporated into program documentation until 2025. Officials stated that they have
encountered challenges with the availability of data, cost of data environments, and finding
skilled personnel. Additionally, as we reported in January 2025, the program’s documents
contain general language about MOSA [modular open system approach] principles but do
not address planning elements for modularity.
Other Program Issues
As of November 2024, frigate program officials reported that the shipbuilder had submitted
a total of five requests for equitable adjustment, raising the potential of unbudgeted
program cost growth, depending on the outcome. Requests for equitable adjustment
provide a remedy payable only when unforeseen or unintended circumstances, such as

Congressional Research Service

12

Navy Constellation (FFG-62) and FF(X) Class Frigate Programs

government modification of the contract, cause an increase in contract performance costs.
The Navy deemed the total costs of the five requests as not suitable for public release.
According to program officials these requests relate to government change orders and
significant design changes from the frigate’s parent ship design.
Despite the unresolved issues identified above, the Navy has proceeded full steam ahead
with the frigate program, exercising options for the fifth and six ships in May 2024. Further,
in November 2024, the Navy requested information seeking shipbuilders to serve as a
second shipyard for constructing future frigates. In January 2025, the Navy began assessing
industry responses to inform future acquisition strategies.
Program Office Comments
We provided a draft of this assessment to the program office for review and comment. The
program office provided technical comments, which we incorporated where appropriate.
The program office stated that in early spring 2025, it anticipates completing design
products needed to support production. According to the program office, the Navy
increased its leadership and technical presence at the shipyard, including contracted
engineering support personnel. The program office further noted that it continues to work
with the shipbuilder on frigate weight reduction and identified potential weight savings to
regain service life allowance through a phased implementation across the first three ships.
According to the program office, the requests for equitable adjustment are currently under
Navy review. In April 2025, the office of DOD’s Director, Operational Testing and
Evaluation provided comments stating that the start date for the program’s operational test
should be reflected as the first quarter of fiscal year 2032.

A May 2024 Government Accountability Office (GAO) report on the FFG-62 program stated,
To reduce technical risk [in the FFG-62 program], the Navy and its shipbuilder [in
designing the FFG-62] modified an existing [Italian-French frigate] design to incorporate
[U.S.] Navy specifications and weapon systems. However, the Navy’s decision to begin
construction [of the first FFG-62] before the design was complete is inconsistent with
leading ship design practices and jeopardized this approach. Further, design instability has
caused weight growth. The figure shows the frigate’s 3D design—a component of design
stability—as incomplete over 1 year after construction began.

Delays in completing the ship design have created mounting construction delays. The Navy
acknowledges that the April 2026 delivery date, set in the contract at award, is
unachievable. The lead frigate is forecasted to be delivered 36 months later than initially
planned. The program office tracks and reports design progress, but its design stability
metric hinges largely on the quantity—rather than quality—of completed design
documents. This limits insight into whether the program’s schedule is achievable. If the
Navy begins construction on the second frigate without improving this metric, it risks

Congressional Research Service

13

Navy Constellation (FFG-62) and FF(X) Class Frigate Programs

repeating the same errors that resulted in construction disruptions and delays with the lead
frigate.
The frigate is using many mission systems already proven on Navy ships. However, the
Navy has yet to demonstrate two systems—the propulsion and machinery control systems.
A planned update to the frigate test plan—combined with the opportunity afforded by
schedule delays—could offer the Navy the chance to conduct land-based testing of these
two unproven systems. This testing would reduce the risk of discovering issues after the
ship is at sea.
The frigate is using a traditional, linear development approach for design and construction.
The Navy has historically experienced schedule delays, cost growth, or both in prior
shipbuilding programs using this approach. The Navy has incorporated elements of leading
practices into its acquisition strategy. However, further incorporating these practices in an
updated acquisition strategy could position the program, when contracting for future
frigates, to better respond to evolving mission needs.32

Issues for Congress Prior to Navy’s November 2025 Announcement
Potential oversight issues for Congress regarding the FFG-62 program as they existed prior to the
Navy’s November 2025 announcement about its desire to truncate the FFG-62 program and
initiate a program to start procuring FF(X)s are discussed in Appendix A. These issues include
the delay in the delivery of the first ship, the potential for cost growth in the FFG-62 program,
whether and when to introduce a second shipyard into the FFG-62 program, the number of
vertical launch system (VLS) tubes in the FFG-62 design, and technical risk in the FFG-62
program.

Navy’s Desired Approach for Restructuring Frigate Acquisition
Overview
As discussed earlier, in June 2025, Secretary of Defense Pete Hegseth indicated that the FFG-62
program was being reviewed as one of several “difficult decisions” to be made by the Department
of Defense (DOD) during a review of its acquisition programs. As also discussed earlier, in a
series of announcements from November 25 to December 19, 2025, the Navy stated that it wants
to restructure its frigate acquisition effort by (1) truncating the FFG-62 program to no more than
two ships and (2) initiating a new program to procure a different class Navy frigates, called
FF(X)s, whose design would be based on that of the National Security Cutter (NSC), a frigatelike ship that has been built for the Coast Guard by Huntington Ingalls Industries/Ingalls
Shipbuilding (HII/Ingalls) of Pascagoula, MS.
Under the Navy’s desired new approach, the third through sixth FFG-62s (which have not begun
construction) would be cancelled; the first two FFG-62s (construction of which is underway)
would remain under review; the first FF(X) would be awarded to HII/Ingalls on a sole-source
basis and be launched (i.e., put into the water for the final stages of its construction) by 2028; and
one or more additional U.S. shipyards would later be brought into the FF(X) program to expand
the FF(X) production rate, competing with HII/Ingalls for future ships in the program. As shown
in Figure 6, the Navy envisages building a notional total of 50 to 65 FF(X)s.
32 Government Accountability Office, Navy Frigate[:] Unstable Design Has Stalled Construction and Compromised

Delivery Schedules, GAO-24-106546, May 2024, highlights page. See also Richard Thomas, “Could US Navy’s
Constellation-Class Frigates Share Littoral Combat Ship Fate?,” Naval Technology, June 11, 2024; Joseph Trevithick,
“Navy’s New Constellation Class Frigate Is A Mess,” The War Zone, May 30, 2024.

Congressional Research Service

14

Navy Constellation (FFG-62) and FF(X) Class Frigate Programs

In announcing its desired new approach for acquiring frigates, Secretary of the Navy John Phelan
stated that “the Constellation-class frigate was canceled because, candidly, it didn’t make sense
anymore to build it. It was 80% of the cost of a [larger DDG-51 class] destroyer and 60% of the
capability. You might as well build destroyers.” The continuation, for now at least, of construction
work on the first two FFG-62s reportedly is intended to support F/MM in the near term, while
policymakers assess how F/MM’s shipbuilding capability could be used over the longer run. As
of November 25, 2025, the first ship in the FFG-62 program was reportedly about 12% complete.

Navy News Release of December 19, 2025
A December 19, 2025, Navy news release about its desire to initiate procurement of FF(X)s states
The Navy announced today its plan to introduce a new class of smaller combatant ships,
the FF(X), as a critical component of the Navy’s fleet of the future. The FF(X) will be a
smaller, more agile surface combatant designed to complement the fleet’s larger, multimission warships and enhance operational flexibility around the globe.
“To deliver at speed and scale, I’ve directed the acquisition of a new frigate class based on
HII’s Legend-Class National Security Cutter design: a proven, American-built ship that
has been protecting U.S. interests at home and abroad,” said John C. Phelan, Secretary of
the Navy. “President Trump and the Secretary of War have signed off on this as part of the
Golden Fleet. Our goal is clear: launch the first hull in the water in 2028. To expand
capacity and production across our maritime industrial base, we will acquire these ships
using a lead yard, and competitive follow-on strategy for multi-yard construction.
Shipyards will be measured against one outcome: delivering combat power to the Fleet as
fast as possible."
The FF(X) is a highly adaptable vessel. While its primary mission will be surface warfare,
its ability to carry modular payloads and command unmanned systems enables it to execute
a broad spectrum of operations, making it ready for the challenges of the modern maritime
environment.…
“Like the Medium Landing Ship [LSM], leveraging a complete design and production
baseline approach will allow the Navy and shipbuilders to reduce costs, schedule and
technical risk,” said Adm. Daryl Caudle, 34th Chief of Naval Operations. “We know this
Frigate design works, we know it operates with the Fleet, and most importantly, we know
how to build it now.”33

A December 19, 2025, press report quoted a “senior official” as stating: “We will initially solesource the lead ship to Ingalls, but we will move to competition as soon as possible.”34

National Security Cutter (NSC) Design
The NSC program is discussed in detail in a separate CRS report on Coast Guard cutter
acquisition programs.35 HII/Ingalls has built 10 NSCs for the Coast Guard; the first was
commissioned into service with the Coast Guard in August 2008, and the 10th was commissioned
into service with the Coast Guard in April 2024. Congress funded an 11th NSC in FY2018, but in

33 U.S. Navy, “Navy Announces New Small Surface Combatant,” press release dated December 19, 2025.
34 Sam LaGrone, “SECNAV: New Frigate will be Based on National Security Cutter, First FF(X) to be Built at

Ingalls,” USNI News, December 19, 2025.
35 CRS Report R42567, Coast Guard Cutter Procurement: Background and Issues for Congress, by Ronald O'Rourke.

Congressional Research Service

15

Navy Constellation (FFG-62) and FF(X) Class Frigate Programs

June 2025 it was reported that the Coast Guard and HII/Ingalls had agreed to cancel construction
of the ship,36 making the 10th NSC the final one to be built for the Coast Guard.
The NSC design (Figure 4) is substantially smaller than the FFG-62 design. As noted earlier, the
full load displacement of the FFG-62 design is close to 8,000 tons. By comparison, the NSC
design has a full load displacement of about 4,500 tons.37 Consistent with both its smaller size
and Coast Guard (rather than Navy) mission needs, the NSC is less heavily armed than the FFG62 design.

Naval Variants of NSC Design Proposed in Past Years by HII/Ingalls
HII/Ingalls since at least 2012 has marketed naval variants of the NSC design, which HII/Ingalls
has called patrol frigates, for potential export to other countries.38 Some observers have argued
that ships based on the NSC design should be procured for the U.S. Navy.39

FF(X) Frigate
Figure 5 and Figure 6 show Navy renderings of the FF(X) frigate based on the NSC design. The
renderings show some differences from the HII patrol frigate designs discussed in the previous
section.40 As shown in Figure 6, the FF(X) design has an estimated displacement of 4,750 tons.
The Navy’s decision to refer to the proposed new frigate for the U.S. Navy as the FF(X) rather
than the FFG(X) suggests that the ship will be equipped with a point-defense anti-air warfare
(AAW, aka air defense) system rather than an area-defense AAW system, as the “G” designation
in U.S. Navy surface combatants, meaning guided missile ship, is usually reserved for ships that
are equipped with an area-defense AAW system.41

36 Sam LaGrone, “Ingalls, Coast Guard Scrap 11th National Security Cutter Over Contract Impasse, Says HII,” USNI

News, June 5, 2025.
37 U.S. Coast Guard, “National Security Cutter,” accessed December 18, 2025, at https://www.dcms.uscg.mil/OurOrganization/Assistant-Commandant-for-Acquisitions-CG-9/Programs/Surface-Programs/National-Security-Cutter/.
38 See, for example, Sam LaGrone, “HII Targets Global Market with New Patrol Frigate,” Jane’s Defence Weekly,
January 13, 2012; Huntington Ingalls Industries, “Ingalls Shipbuilding Highlighting Patrol Frigate Derivative of
National Security Cutter at DIMDEX,” news release dated March 26, 2012; Mrityunjoy Mazumdar, “Patrol Frigate
Concepts from Huntington Ingalls Industries Gain Traction Internationally,” Defense Media Network, April 24, 2012;
Scott C. Truver, “Payloads over Platforms: Designing the ‘Flexible Frigate,’” Naval Engineers Journal, September
2013, pp. 31-38; “Ingalls Shipbuilding Highlights its Patrol Frigate at Sea-Air-Space 2014,” Navy Recognition, April 9,
2014; Huntington Ingalls Industries, “Ingalls Shipbuilding Sea Control Frigate,” YouTube, April 14, 2014, at
https://www.youtube.com/watch?v=5OJZ8eB_mPA&t=6s.
39 See, for example, Zachary Howitt, “It's Time for a ‘Sea-Control Frigate,’” U.S. Naval Institute Proceedings, April
2014; Dave Majumdar, “Huntington Ingalls Has a New Frigate that Could Give the U.S. Navy Some Impressive
Capabilities,” National Interest, January 11, 2017; Harold C. Hutchison, “The Coast Guard Could Have the Solution
for a Bigger US Navy,” We Are the Mighty, November 1, 2018.
40 For a discussion of some of these differences, see Joseph Trevithick, “This Will Be The Navy’s New FF(X) Frigate,”
The War Zone, December 19, 2025.
41 A point-defense AAW system has a range sufficient to defend the ship itself, but not other ships in the area. An areadefense AAW system has a longer range that is sufficient for defending not only the ship itself, but also other ships in
the area. In the U.S. Navy, ships capable of firing the Standard Missile interceptor, which is a longer-ranged AAW
interceptor, are considered to have an area-defense AAW system and have a G in their designation, while ships that
cannot fire the Standard Missile and employ shorter-ranged interceptors, such as the Evolved Sea Sparrow Missile
(ESSM) or Rolling Airframe Missile (RAM), are considered to have a point-defense AAW system and do not have a G
in their designation.

Congressional Research Service

16

Navy Constellation (FFG-62) and FF(X) Class Frigate Programs

Figure 4. National Security Cutter

Source: Cropped version of photograph accompanying Huntington Ingalls Industries, “Bertholf (WMSL 750)
Builder’s Trials,” March 22, 2019. The caption to the photograph states that it was taken on December 4, 2007.

A December 19, 2025, press article quotes a “senior official” as stating: “The [NSC] design
[with] little adaptation will meet the CNO’s [Chief of Naval Operations’] requirements for a small
surface combatant.”42 The article also states
The scaled-back requirements for the new ship class were born from a Navy-led review of
what the sea service needs in the short term to support lower-priority missions that tie up
more capable warships….
“They looked at what’s been going on in U.S. 5th Fleet and 4th Fleet as exemplar areas
where this platform would help take the load off of our destroyers so they could focus on
some of the higher-end missions,” a second senior official told USNI News.
One of the few changes the Navy intends to make to the NSC design is to construct a
platform above the open boat deck for containerized mission packages, the officials said.
For example, the Army and Lockheed Martin developed the MK-70 Typhon vertical launch
system within the dimensions of a 40-foot shipping container. The Navy is developing
more containerized packages that can be swapped from ship to ship.
“That’ll be something immediately on the first flight of ships that will be available,” the
first senior official told USNI News. “Those containers could do a host of missions. That’s
a core element of the future force design. Beyond that … things that are more intrusive to
install, like anti-submarine warfare equipment, would be something we would look to do
in the future.”43

42 Sam LaGrone, “SECNAV: New Frigate will be Based on National Security Cutter, First FF(X) to be Built at

Ingalls,” USNI News, December 19, 2025.
43 Sam LaGrone, “SECNAV: New Frigate will be Based on National Security Cutter, First FF(X) to be Built at
Ingalls,” USNI News, December 19, 2025.

Congressional Research Service

17

Navy Constellation (FFG-62) and FF(X) Class Frigate Programs

Figure 5. Rendering of FF(X) Design

Source: Cropped version of rendering accompanying Sam LaGrone, “SECNAV: New Frigate will be Based on
National Security Cutter, First FF(X) to be Built at Ingalls,” USNI News, December 19, 2025. The caption to the
rendering credits it to the U.S. Navy.

Figure 6. Rendering and Selected Details of FF(X) Design

Source: Cropped version of Navy briefing slide shown at Surface Navy Association Symposium, January 15,
2026, provided to CRS by Navy Office of Legislative Affairs, January 16, 2026.

Another December 19, 2025, press article states that the Navy has

Congressional Research Service

18

Navy Constellation (FFG-62) and FF(X) Class Frigate Programs

made clear that it expects the new frigate design to allow for the integration of new and
improved capabilities and functionality down the line.
“The [FF(X)] frigate will follow the same proven approach we’ve used with the Arleigh
Burke destroyers, building it smart from the start, then upgrading it in steps over time, as
the threat and technology evolve,” Chief of Naval Operations Adm. Daryl Caudle also said
in today’s video announcement.44

Issues for Congress Regarding Navy’s Desired
Approach for Frigate Acquisition
In considering whether to approve, reject, or modify the Navy’s desired approach for
restructuring its frigate acquisition effort, Congress may consider several potential oversight
issues, including but not necessarily limited to those discussed below.

Adequacy of Information Provided to Congress
One potential oversight issue for Congress is whether is whether Congress has adequate
information to assess the merits of the Navy’s desired new approach to frigate acquisition.
Information that could support congressional assessments includes information on
•

•
•

the formal analysis—such as an Analysis of Alternatives (AOA)—by which the
Navy determined that the most cost-effective approach to frigate acquisition
would be to truncate the FFG-62 program to no more than two ships and initiate
a new frigate procurement program based on the NSC design;
what steps, if any, in the DOD acquisition process were set aside to facilitate the
initiation of the FF(X) program in December 2025; and
the design features, capabilities, and estimated procurement and life-cycle
operation and support (O&S) costs of the FF(X) design, how the FF(X) design
(and thus FF(X) capabilities and costs) might evolve after procurement of the
first FF(X) or the first few FF(X)s, the numbers of FF(X)s that are to be procured
each year, and the schedule for introducing one or more additional shipyards into
the program.

General Approach Regarding Frigate Acquisition
Another potential oversight issue for Congress is what general approach to pursue regarding
frigate acquisition.

Overview of Four General Approaches
In a context of the existing FFG-62 program and a potential successor frigate program, notional
general approaches regarding frigate acquisition include but are not necessarily limited to the
following four possibilities:
•
•

End procurement of FFG-62s and do not initiate a successor frigate program.
End procurement of FFG-62s and initiate a successor frigate program (the Navy’s
desired approach).

44 Joseph Trevithick, “This Will Be The Navy’s New FF(X) Frigate,” The War Zone, December 19, 2025.

Congressional Research Service

19

Navy Constellation (FFG-62) and FF(X) Class Frigate Programs

•
•

Continue procurement of FFG-62s and do not initiate a successor frigate
program.
Continue procurement of FFG-62s and initiate an additional frigate program.

Below are brief discussions of each of these possible approaches.

End Procurement of FFG-62s and Do Not Initiate a Successor Frigate Program
Under this approach, which might be thought of as the “no frigates” approach, procurement of
FFG-62s would be truncated, and no successor frigate program would be initiated. Navy mission
needs that were to have been met by procuring frigates would instead be met by increasing
planned procurement and force levels of DDG-51 destroyers (i.e., ships larger than frigates)
and/or corvette-sized unmanned surface vessels (USVs) (i.e., ships smaller than frigates).45
Supporters of this approach could argue that ending procurement of frigates would ease Navy
shipbuilding program management workloads by reducing the number of shipbuilding programs
to be managed, and do so at a time when the Navy is facing challenges in executing its
shipbuilding programs. They could argue that this approach could increase production and lifecycle O&S economies of scale for DDG-51 destroyers and USVs.
Skeptics of this approach could question whether a combination of DDG-51s and USVs could
meet certain mission needs that were to have been met by procuring frigates, because the
capabilities of the Navy’s future USVs have not been fully defined and proven, and because
USVs, as unmanned ships, could be challenged in performing certain day-to-day, noncombat
missions that manned frigates would perform.46 They could argue that using destroyers to perform
missions that could be adequately performed by frigates would not be cost effective, given the
higher procurement and O&S costs of destroyers compared to frigates.

End Procurement of FFG-62s and Initiate a Successor Frigate Program
This is the Navy’s desired approach. Supporters of this approach could argue, as Secretary of the
Navy Phelan has, that the FFG-62 design is no longer cost-effective to pursue as a smaller and
individually less expensive complement to the DDG-51 design, because the FFG-62 design has
grown during the design process to more than 80% of the size of the DDG-51 design but would
provide less than 80% of a DDG-51’s capability, and that a successor frigate design could fare
better than the FFG-62 design in terms of cost and capability in relation to the cost and capability
of the DDG-51 design. They could argue that although limiting FFG-62 procurement to two ships
could increase per-ship FFG-62 O&S costs by reducing economies of scale for such costs, the
increase will not be onerous. They could argue that the Navy operates other numerically small
ship classes (including the three-ship Seawolf [SSN-21] class of attack submarines and the threeship Zumwalt [DDG-1000] class of destroyers), and that the issue of per-ship FFG-62 O&S costs
could be addressed by eventually selling the two FFG-62s to one or two allied or partner navies
that might need only one or two such ships to meet their own mission needs.
Skeptics of this approach could argue that the FFG-62 design is the design that the Navy
originally selected, following a rigorous source-selection process, as the one that could best meet
45 For more on the Navy’s program for procuring large USVs, see CRS Report R45757, Navy Large Unmanned Surface

and Undersea Vehicles: Background and Issues for Congress, by Ronald O'Rourke.
46 Potential examples of such missions include engagement with allied and partner navies, humanitarian
assistance/disaster response (HA/DR) operations, noncombatant evacuation operations (NEOs), maritime security
operations (such as anti-piracy operations), and operations with embarked Coast Guard law-enforcement detachments
for fisheries enforcement or interdiction of illegal migrants and illegal drug shipments.

Congressional Research Service

20

Navy Constellation (FFG-62) and FF(X) Class Frigate Programs

the Navy’s operational requirements for a frigate, and that a successor frigate design might fare
no better than the FFG-62 design in terms of cost and capability in relation to the cost and
capability of the DDG-51 design. They could argue that while there is less than a 20% difference
in the size of a 9,700-ton DDG-51 and an 8,000-ton FFG-62, Navy plans have called for shifting
destroyer procurement in the early 2030s from the DDG-51 design to a 14,500-ton nextgeneration destroyer design called the DDG(X),47 which would establish a larger difference in
size between the FFG-62 design and the design of the destroyer that the Navy would be
procuring. They could argue that design work on the FFG-62 is progressing toward completion;
that truncating FFG-62 procurement to two ships would provide a limited return on the
investment of time and funding that the Navy has expended to complete the FFG-62 design
(which needs to be completed to support the construction of the first two ships); that it would not
be optimal for the Navy to create another case, alongside cases such as the Seawolf and Zumwalt
classes, of paying elevated per-ship O&S costs for a numerically limited class of combatant ships;
and that there is no guarantee that the Navy would be able to find one or two allied or partner
navies willing to buy two FFG-62s unless their purchase price is set substantially below their
original procurement costs.

Continue Procurement of FFG-62s and Do Not Initiate a Successor Frigate
Program
Under this approach, which might be thought of as the “stay the course with the FFG-62
program” approach, the cancellation of the third through sixth FFG-62 would be treated as a
pause in FFG-62 procurement that would be intended to permit FFG-62 construction work to
catch up with the number of FFG-62s that have been procured, at which point procurement of
additional FFG-62s would resume, and a successor frigate program would not be initiated. A
pause in FFG-62 procurement could be viewed as similar in some respects to what occurred in the
earlier years of the Littoral Combat Ship (LCS) procurement program.48
Since this approach is essentially the obverse of the previous approach, notional arguments for
supporters and skeptics of this approach would essentially be the obverse of those outlined above
for the previous approach: Supporters of this approach could make arguments similar to those
outlined above for skeptics of the previous approach, while skeptics of this approach could make
arguments similar to those outlined above for supporters of the previous approach.

Continue Procurement of FFG-62s and Initiate an Additional Frigate Program
Under this approach, which might be thought of as the “procure two frigate classes” approach, the
cancellation of the third through sixth FFG-62 would be treated as a pause in FFG-62
procurement, followed by a resumption in FFG-62 procurement at a later point, and an additional
frigate program would be initiated, with ships in this additional program being procured in
parallel with procurement of FFG-62s. Under this approach, the builder or builders of FFG-62s
and the builder or builders of the second type of frigate could compete for contracts to build
47 For more information on the DDG(X) program, see CRS In Focus IF11679, Navy DDG(X) Next-Generation

Destroyer Program: Background and Issues for Congress, by Ronald O'Rourke.
48 The earlier years of the LCS procurement program included the cancellation of two LCSs funded in FY2006, another
two LCSs funded in FY2007, and an LCS funded in FY2008, followed by procurement of additional LCSs through
FY2019. For notations of the cancelled LCSs, see note 1 to the second table in the Appendix entitled “Size of the Navy
and Navy Shipbuilding Rate” in CRS Report RL32665, Navy Force Structure and Shipbuilding Plans: Background and
Issues for Congress, by Ronald O'Rourke; and the note to Table 1 (on page 3) of the December 17, 2019, update (the
final update) to CRS Report RL33741, Navy Littoral Combat Ship (LCS) Program: Background and Issues for
Congress, by Ronald O'Rourke.

Congressional Research Service

21

Navy Constellation (FFG-62) and FF(X) Class Frigate Programs

frigates for the Navy. This approach would be broadly similar to the one the Navy employed for
the LCS program, under which two different LCS designs were built at two shipyards, with each
shipyard building one of the designs, and the Navy had the option of using competition between
the two shipyards in determining who would build the later ships in the program.
Supporters of this approach could argue that that the FFG-62 design is the design that the Navy
originally selected, following a rigorous source-selection process, as the one that could best meet
the Navy’s operational requirements for a frigate,49 but that a second frigate design might be
smaller and individually less expensive to procure and operate than the FFG-62 design,
permitting it to serve, within the Navy’s frigate force, as a less-expensive complement to the
Navy’s FFG-62s.
Skeptics of this approach could argue that it would increase Navy shipbuilding program
management workloads by increasing the number of shipbuilding programs to be managed, and
do so at a time when the Navy is facing challenges in executing its shipbuilding programs. They
could also argue that building two types of frigates would reduce frigate production and life-cycle
O&S economies of scale by dividing frigate acquisition into two programs, and that the reduced
economies of scale could, other things held equal, increase per-ship production and life-cycle
O&S costs for Navy frigates.

Potential Oversight Questions for Congress
Potential oversight questions for Congress regarding what general approach to pursue regarding
frigate acquisition include the following:
•

•
•
•

What is the analytical basis for the Navy’s desire to pursue the second general
approach outlined above? What formal analysis—such as an Analysis of
Alternatives (AOA)—did the Navy perform to evaluate the four general
approaches outlined above (and perhaps other potential approaches)? What were
the findings of this analysis? Has the Navy transmitted this analysis to Congress?
How fully and cost effectively could a combination of DDG-51s and USVs
perform the missions that the Navy intends to perform with frigates?
What are the potential impacts on per-ship FFG-62 life-cycle O&S costs of
truncating FFG-62 procurement to no more than two ships?
What are the potential impacts on per-ship frigate procurement and life-cycle
O&S costs of building two types of frigates (FFG-62s and a second type)?

New Frigate Design
If the second or fourth general approach outlined in the previous section is pursued, and a new
frigate design is consequently to be procured, a follow-on potential oversight issue for Congress
would be whether the Navy’s desired design—an FF(X) based on the NSC design—is the most
cost-effective new design to procure.
49 They could also argue, as skeptics of the second approach (i.e., the Navy’s desired approach) could argue, that design

work on the FFG-62 is progressing toward completion; that truncating FFG-62 procurement to two ships would provide
a limited return on the investment of time and funding that the Navy has expended to complete the FFG-62 design
(which needs to be completed to support the construction of the first two ships); that it would not be optimal for the
Navy to create another case, alongside cases such as the Seawolf and Zumwalt classes, of paying elevated per-ship
O&S costs for a numerically limited class; and that there is no guarantee that the Navy would be able to find one or two
allied or partner navies willing to buy two FFG-62s unless their purchase price is set substantially below their original
procurement costs.

Congressional Research Service

22

Navy Constellation (FFG-62) and FF(X) Class Frigate Programs

Potential Design Options
Potential options for a new frigate design include but are not necessarily limited to the following:
•

•
•

the Multi-Mission Surface Combatant (MMSC), a variant of the LCS-1 class
design with a displacement of more than 3,900 tons,50 four of which F/MM is
building for the Royal Saudi Navy (Figure 7);51
a 4,750-ton frigate variant of the NSC design (the Navy’s desired choice);
a reduced-cost, more lightly armed variant of the DDG-51 design whose installed
systems would be less like those of a destroyer and more like those of a frigate—
an option broadly similar to options for lower-cost DDG-51 variants that the
Navy studied in 199152 and to the Navy’s 31 Spruance (DD-963) class destroyers
in their original configuration;53

50 Source for displacement figure of more than 3,900 tons: Program Executive Office Unmanned and Small

Combatants (PEO USC) Public Affairs, “Navy Cuts Steel on First Multi-Mission Surface Combatant Ship for Saudi
Arabia,” Naval Sea Systems Command, November 18, 2019, which cites a figure of more than 4,000 metric tons,
which equates to more than 3,936 long tons.
51 For more on the MMSC, see, for example, “The First MMSC-1 Frigate Built by Fincantieri in the United States for
the Royal Saudi Navy Was Launched,” Zona Militar, December 29, 2025; Richard Scott, “First Saudi MMSC launched
by Fincantieri in Wisconsin,” Naval News, December 24, 2025; Chris Cavas, “First Look: Fincantieri Marine Group
Production Includes US Navy’s Frigate, LCS and Saudi Combatants,” Naval News, February 2, 2024; “Multi-Mission
Surface Combatant (MMSC),” Naval Technology, July 31, 2020; Sam LaGrone, “Lockheed Awarded $1.96B
Construction Contract for Four Saudi Frigates,” USNI News, December 20, 2019; Paul McLeary, “Saudis Save
Wisconsin Shipbuilder: Fills Gap Between LCS & Frigates At Marinette,” Breaking Defense, January 17, 2019;
Defense Security Cooperation Agency (DSCA), “Kingdom of Saudi Arabia - Multi-Mission Surface Combatant
(MMSC) Ships,” news release, October 20, 2015.
52 The Navy’s 1991 study was called the destroyer variant (DDV) study (or studies). A 1994 journal article about the
DDV study states
The Destroyer Variant (DDV) studies were initiated in mid-1991 by OPNAV [the office of the
Chief of Naval Operations] to evaluate a variety of potential follow-on destroyer designs covering
the spectrum from a non-AEGIS low-end reference [design] ([designated] DDV 1) to a [DDG-51]
Flight III lookalike [design] with a 40-foot [hull] plug [i.e., a 40-foot increase in hull length] as a
high-end reference [design] ([designated] DDV H).… The acquisition cost of DDV 1 was estimated
to be 53 percent of DDV H, while the other non-AEGIS variant costs were between 70 and 87
percent of DDV H.
(Robert J. Scott and Kevin E. Moak, “Studies of Helicopter Capable DDG 51 Variants,” Naval
Engineers Journal, September 1994, p. 34.)
For additional mentions of the DDV study, see Donald L. Ewing, et al., “A Surface Combatant for the 21st Century:
DDG 51 Flight IIA,” Naval Engineers Journal, May 1995, p. 218; George A. Huchting, “Lean and Mean Warship
Design,” U.S. Naval Institute Proceedings, October 1994; Department of the Navy, Department of the Navy 1992
Posture Statement, A Report by The Honorable H. Lawrence Garrett, III, Secretary of the Navy, Admiral Frank B.
Kelso, II, United States Navy, Chief of Naval Operations, and General Carl E. Mundy, Jr., United States Marine Corps,
Commandant of the Marine Corps on the Posture and the Fiscal Year 1993 Budget of the United States Navy and The
United States Marine Corps, February-March 1992, p. 25; John F. Morton, “The U.S. Navy in 1991,” U.S. Naval
Institute Proceedings, May 1992; R. K. U. Kihune, “Message for the Fleet Sailor,” Surface Warfare,
September/October 1991, p. 1.
For blog entries in more recent years that discuss different potential options for a reduced-cost DDG-51 variant, see
Craig Hooper, “Time To Consider A Low-End “Littoral Operations Variant” DDG-51?,” Next Navy, April 22, 2014;
Mike Burleson, “Flight III: Building a Better Burke,” New Wars, March 1, 2010.
53 Thirty-one Spruance-class ships were procured for the Navy from FY1970 through FY1978; the ships entered service
in 1975-1983 and were decommissioned in 1998-2005. CRS testimony to the Seapower and Projections Forces
subcommittee of the House Armed Services Committee in October 2013 discussed the Spruance-class design, stating
that it
(continued...)

Congressional Research Service

23

Navy Constellation (FFG-62) and FF(X) Class Frigate Programs

•

•
•

Japan’s 5,400-ton54 Mogami-class frigate design (Figure 8), or the more heavily
armed 6,100-ton55 variant of that design that Australia is procuring for its navy,
with the first three to be built in Japan and the final eight to be built in
Australia;56
South Korea’s 3,600-ton Daegu-class frigate design (Figure 9),57 or a variant of
that design; and
European frigate designs or variants of such designs, including but not limited to
the 6,400-ton Spanish F100 frigate design (which was a proposed parent design
in the original FFG-62 competition) (Figure 10),58 the newer the Spanish F110
frigate design,59 the Spanish Alfa 3000, 4000, and 5000 frigate designs,60 the UK

was criticized as being underarmed for its size—for having something like a frigate’s worth of
combat systems on a destroyer hull. The criticism arose in part from a Navy decision to make the
ship more affordable to procure: The ship was originally designed with both a full-capability ASW
[antisubmarine warfare] system and a full-capability AAW [anti-air warfare, aka air defense]
system (which, in those pre-Aegis days, was the digital Tartar/SM-2 system). To reduce the ship’s
procurement cost, the Navy decided that the most important mission need to be met by the ship was
ASW. Accordingly, the ship’s full-capability ASW system was retained while its AAW system was
de-scoped to a less-capable and less-expensive point-defense system. While this contributed to
criticism that the ship was underarmed for its size, a decision to retain the full-capability AAW
system might well have led to a different criticism—that the ship was insufficiently affordable for
the shipbuilding budgets of the day. The de-scoping of the ship’s AAW system, as it turned out, left
the ship with ample growth margin, which the Navy years later used to install a 61-cell vertical
launch system (VLS) on 24 of the 31 DD-963s, giving those ships an additional mission of acting
as Tomahawk strike platforms—a mission not originally contemplated for the ships, and one that
contributed to the ship’s cost effectiveness in their later years of service.
(Statement of Ronald O’Rourke, Specialist in Naval Affairs, Congressional Research Service,
before the House Armed Services Committee, Subcommittee on Seapower and Projection Forces,
on The Navy’s FY2014 30-Year Shipbuilding Plan, October 23, 2013, p. 10.)
54 Source for figure of 5,400 tons: Joseph Trevithick, “Japan’s Futuristic Mogami Frigate Will Be Australia’s Next
Warship,” The War Zone, August 4, 2025, which cites a figure of 5,500 metric tons, which equates to 5,413 long tons.
55 Source for figure of 6,100 tons: Joseph Trevithick, “Japan’s Futuristic Mogami Frigate Will Be Australia’s Next
Warship,” The War Zone, August 4, 2025, which cites a figure of 6,200 metric tons, which equates to 6,102 long tons.
56 For additional discussion of the Mogami-class design and Australia’s decision to acquire 11 Mogami-variant ships,
see, for example, “Mogami-Class Frigate,” Wikipedia, edited December 25, 2025, accessed January 1, 2025; Moyuru
Tanaka, “The Mogami: Advancing Australia-Japan Defense Cooperation,” Center for Strategic and International
Studies (CSIS), November 21, 2025; Iku Tsujihiro and Masashi Murano, “Japan and Australia’s Mogami Gamble: A
New Role in a Taiwan Strait Contingency,” Hudson Institute, September 23, 2025; Joseph Trevithick, “Japan’s
Futuristic Mogami Frigate Will Be Australia’s Next Warship,” The War Zone, August 4, 2025; Oliver Parken, “Japan’s
Futuristic Mogami Frigates: Everything You Need To Know,” The War Zone, November 17, 2023; Eric Wertheim,
“Japan’s Multimission Mogami-class Frigates,” U.S. Naval Institute Proceedings, September 2023.
57 For more on the Daegu-class design, see “Daegu-Class Frigate,” Wikipedia, edited December 27, 2025, accessed
January 1, 2026; Eric Wertheim, “South Korea’s Future Experimental Frigates,” U.S. Naval Institute Proceedings,
October 2025; Jamie Chang, “South Korea Commissions Final Daegu-class FFX Batch II Frigate,” Naval News,
October 24, 2023; “FFX-II (Daegu Class) Multi-Role Frigates,” Naval Technology, September 5, 2016.
58 For more on the F100 design, see Navantia, “F-100,” undated, accessed January 1, 2026; “Álvaro de Bazán-Class
Frigate,” Wikipedia, edited December 12, 2025, accessed January 1, 2026; Brandon J. Weichert, “Here’s How Spain Is
Keeping Its F100 Frigates Relevant Through 2045,” National Interest, December 15 2025; Ben Werner, “Spanish
Shipbuilder Navantia Showcases F-100 Frigate Design,” USNI News, January 22, 2019.
59 For more on the F110 design, see “F110-Class Frigate,” Wikipedia, edited December 16, 2025, accessed January 1,
2026; Navantia, “F-110,” undated, accessed January 1, 2026; Xavier Vavasseur, “Spain’s Navantia Proposing Two
New Frigate Designs to the Hellenic Navy,” Naval News, December 4, 2021.
60 For more on the Alfa 3000, 4000, and 5000 frigate designs, see Navantia, Alfa 4000,” undated, accessed January 1,
2026; Alex Luck, “Navantia Presents Revised Alfa 4000 Light Frigate And Smart LPD Concept At Indo Pacific 2025,”
(continued...)

Congressional Research Service

24

Navy Constellation (FFG-62) and FF(X) Class Frigate Programs

Type 26 and Type 31 frigate designs,61 and the German MEKO 200 and MEKO
400 frigate designs.62
Figure 7. Multi-Mission Surface Combatant (MMSC)

Source: Cropped version of photograph accompanying “The First MMSC-1 Frigate Built by Fincantieri in the
United States for the Royal Saudi Navy Was Launched,” Zona Militar, December 29, 2025. A watermark on the
photograph with both Arabic and English writing states, in its English portion, “Ministry of Defense.”

Figure 8. Mogami-Class Frigate

Source: Cropped version of photograph accompanying Eric Wertheim, “Japan’s Multimission Mogami-class
Frigates,” U.S. Naval Institute Proceedings, September 2023. The caption to the photograph credits the
photograph to Arjun Sarup.

Naval News, November 11, 2025; Alex Luck, “Navantia Unveils Three New Warships Including Tier-2 Corvette,”
Naval News, August 11, 2023; Xavier Vavasseur, “Spain’s Navantia Proposing Two New Frigate Designs to the
Hellenic Navy,” Naval News, December 4, 2021.
61 For more on the Type 26 and Type 31 frigate designs, see “Type 26 Frigate,” Wikipedia, edited December 14, 2025,
accessed January 1, 2026; “Type 31 Frigate,” edited December 31 2025, accessed January 1, 2026.
62 For more on the MEKO 200 and MEKO 400 frigate designs, see TKMS, “MEKO A-200,” undated, accessed January
1, 2026; “MEKO 200,” Wikipedia, edited December 31, 2025, accessed January 1, 2026; TKMS, “MEKO A-400
AMD,” undated, accessed January 1, 2026.
For press reports discussing some of potential options listed here, see Joseph Trevithick, “U.S. Navy Now Wants A
New Frigate And Fast,” The War Zone, December 12, 2025; Joseph Trevithick, “Japan’s Futuristic Mogami Frigate
Will Be Australia’s Next Warship,” The War Zone, August 4, 2025.

Congressional Research Service

25

Navy Constellation (FFG-62) and FF(X) Class Frigate Programs

Figure 9. Daegu-Class Frigate

Source: Photograph accompanying “Daegu class (FFG-II) Guided Missile Frigate,” Seaforces, undated, accessed
January 1, 2026. The caption to the photograph credits the photograph to “Republic of Korea Armed Forces/
CC.”

General observations that might be made about the above-listed options for a new frigate design
include but are not necessarily limited to the following:
•

•
•

•

•

•

These potential design options are varied in ship sizes, capabilities, estimated or
known procurement and life-cycle O&S costs, program-execution risks (i.e.,
risks of cost growth, schedule slippage, or technical challenges), and potential
implications for the U.S. shipbuilding industrial base.
The foreign designs might not meet certain U.S. Navy design standards, such as
those relating to ship survivability.
The three listed U.S. designs—the MMSC, the frigate variant of the NSC design,
and the reduced-cost, more lightly armed variant of the DDG-51 design—could
benefit from production and life-cycle O&S economies of scale with the existing
Navy and Coast Guard ships from which they would be derived (the Navy’s
LCS-1 class, the Coast Guard’s NSCs, and the Navy’s DDG-51s, respectively).
Compared with building a U.S. design in one or more U.S. shipyards, some of
the foreign designs, if built in foreign shipyards, might have lower unit
procurement costs due in part to lower labor costs in foreign shipyards compared
with labor costs in U.S. shipyards,
Compared with the U.S. designs, the foreign designs might offer less potential for
creating life-cycle O&S economies of scale in conjunction with existing U.S.
Navy and Coast Guard ships due to differences from existing U.S. Navy and
Coast Guard ships regarding installed systems and components.
The supply chains for supporting the foreign designs could reside at least
partially, and perhaps to a large degree, in the countries where the designs were
developed, which could pose risks during conflicts for supporting U.S. Navy

Congressional Research Service

26

Navy Constellation (FFG-62) and FF(X) Class Frigate Programs

ships built to a foreign design, unless investment is made to establish a U.S.based supply chain for the ships.
Figure 10. Álvaro de Bazán-class F100 Frigate

Source: Photograph accompanying Defence24, “Navantia Showcasing Its Miecznik Proposal in Warsaw. Aegis
offered for Poland,” Defence24.com, December 15, 2021. The caption to the photograph credits the photograph
to “NATO Maritime Group 2 via US Navy.”

Potential Oversight Questions for Congress
Potential oversight questions for Congress regarding options for a new frigate design include the
following:
•

•

•

What is the analytical basis for the Navy’s selection of a frigate variant of the
NSC design as the new frigate design? What formal analysis—such as an
Analysis of Alternatives (AOA)—did the Navy perform to evaluate the design
options listed above (and perhaps other options)? What were the findings of this
analysis? Has the Navy transmitted this analysis to Congress?
As noted earlier, Secretary of the Navy Phelan has stated that the FFG-62 design
would have a cost 80% of that of a destroyer while providing 60% of the
capability of a destroyer. What are the corresponding percentage figures for a
frigate variant of the NSC design and for the other above-listed design options?
As noted earlier, the frigate variant of the NSC design, according to a senior
official, reportedly will meet the CNO’s requirements for a small surface
combatant. As also noted earlier, the frigate variant of the NSC design will be
smaller than the FFG-62 design, and might thus be less heavily armed than the
FFG-62 design. Are the CNO’s requirements for a small surface combatant the

Congressional Research Service

27

Navy Constellation (FFG-62) and FF(X) Class Frigate Programs

same as the requirements that were used earlier in originally selecting the FFG62 design? If so, then was the FFG-62 design excessively large and expensive for
meeting those requirements? If the CNO’s requirements for a small surface
combatant are not the same as those that were used earlier in originally selecting
the FFG-62 design, how were the CNO’s requirements determined, and have they
been set forth in a formal requirements document?
A December 22, 2025, blog entry states the following regarding the comparative capabilities of
the FFG-62 design and the proposed NSC-based FF(X) design:
The U.S. Navy has confirmed to TWZ [The War Zone] that the armament package for its
first “flight” of its new FF(X) frigates will not include a built-in Vertical Launch System
(VLS).…
A lack of any type of VLS on the FF(X) design is a glaring omission that can only raise
questions about the operational utility and flexibility of the ships. At the same time, the
new frigates will be able to carry modular payloads, including containerized missile
launchers, on their sterns. The Navy also has an explicit plan to employ the FF(X)s as
“motherships” for uncrewed surface vessels (USV), likely offering a distributed arsenal, as
well as additional sensors, for the frigates to leverage during operations….
“The initial flight of FF(X) will have a 57mm gun, 2 x 30mm guns, a Mk 49 Rolling
Airframe Missile [launcher], various countermeasures, and a flight deck from which to
launch helicopters and unmanned systems. Aft of the flight deck, there will be a flexible
weapons system, which can accommodate containerized payloads (Counter-UAS [counterunmanned aerial systems], other missiles),” a Navy spokesperson told TWZ today. “Much
like the successful DDG-51 [Arleigh Burke class destroyer] program, we are building this
in flights. The frigate will be upgraded over successive flights to evolve and has the space
reservations needed to improve capability over time.”…
Overall, the Mk 41 VLS requirement was central to the FFG(X) program that led to the
Constellation class design. This was viewed as a key element of righting the wrongs of the
Navy’s chronically underperforming Littoral Combat Ship (LCS) program. The
Independence class and Freedom class LCSs both lack a VLS array. In addition, it’s worth
remembering here that HII’s losing FFG(X) bid was notably a Patrol Frigate concept
derived from the National Security Cutter that featured a VLS….
Integrating a VLS into future flights of FF(X) frigates is certainly an option, but one that
could be complex and costly if the design is not configured to accommodate one to begin
with….
Installing missile launchers on the FF(X)’s fantail would give the ships a boost in firepower
in the absence of an integrated VLS array. Renderings so far have shown what look to be
launchers for up to 16 Naval Strike Missiles (NSM) installed in that position.… There also
looks to be space there for a least one containerized Mk 70 Payload Delivery Systems
(PDS), another capability the Navy is already acquiring. Each Mk 70 contains a four-cell
launcher derived from the Mk 41 VLS, and similarly capable of firing a variety of weapons,
including SM-6 multi-purpose missiles and Tomahawk land-attack cruise missiles….
“The FF(X) will be designed to command groups of unmanned vessels, acting as a sort of
‘mothership,’ providing the commander tailored force packages based upon the weapons
and sensors fielded on those unmanned craft,” a Navy spokesperson also told TWZ today.
In this way, an FF(X) could still call upon a deeper and more flexible array of weapon
options without having to have a VLS integrated directly onto the ship. The uncrewed
platforms would also be able to operate across a much broader area than any single crewed
frigate and present a different risk calculus for operating in higher-risk environments. All
of this would expand the overall reach of the combined force and present targeting
challenges for opponents. But there are also substantial development and operational risks

Congressional Research Service

28

Navy Constellation (FFG-62) and FF(X) Class Frigate Programs

with this kind of arrangement. As it sits, this kind of autonomous vessel and manned vessel
teaming is still in development. Operationally, leaving the ship without, or with very
limited, area defense capability is at odds with many future threat scenarios….
Even with all this in mind, the lack of a VLS still raises significant questions about the
FF(X) plans, especially about the ability of the ships to operate more independently. This
has been a key issue for the Navy’s existing LCS fleets, and one that the Constellation class
was supposed to help address….
… While expanded [FF(X)] variants in the future [that are equipped] with VLS arrays and
more exquisite combat systems seem like a real possibility, when it comes to installed
armament, America’s next frigate is set to be just as lightly armed as the LCS that came
before it.63

Sole-Source or Competitive Contract Award for First Ship
Another potential oversight issue for Congress is whether a contract to build the first ship of a
new frigate design should be awarded on a sole-source basis or competitive basis. As noted
earlier, a December 19, 2025, press report quoted a “senior official” as stating: “We will initially
sole-source the lead ship to Ingalls, but we will move to competition as soon as possible.”64 A
potential alternative to a sole-source award for the first ship would be for the government to
purchase the data rights to the selected frigate design (if the government does not already own the
data rights) and hold a competition among multiple shipbuilders to build the first ship to that
design.
Supporters of a sole-source award could argue that it will help reduce the construction timeline
for the first ship, and that it is uncertain that holding a competition would have a meaningful
impact on reducing contract price. Supporters of a competitive award could argue that a solesource award would deprive the Navy of an opportunity to use competitive leverage to minimize
the contract price, and that having that leverage would be more important than the additional time
needed to hold a competition. Potential questions for Congress include the following:
•

•

What analysis did the Navy perform to evaluate the question of whether to
employ a sole-source approach or a competitive approach for awarding the
contract to build the first ship of a new frigate design, and what were the findings
of this analysis in terms of factors such as contract price and first-ship
construction timeline?
When would a second shipyard be brought into the effort to build a new frigate
design?

Potential Participation of Foreign Shipyards
Another potential oversight issue for Congress is whether foreign shipyards should play a role in
building frigates for the U.S. Navy. Such a role could involve building either entire frigates or
frigate ship sections (sometimes called ship modules or ship blocks) that would be transported to
a final-assembly shipyard in the United States. Building ships sections in one yard for
transportation to a final assembly yard would be a form of what is referred to as distributed

63 Joseph Trevithick, “Navy’s New Frigate Will Not Have A Vertical Launch System For Missiles,” The War Zone,

December 22, 2025.
64 Sam LaGrone, “SECNAV: New Frigate will be Based on National Security Cutter, First FF(X) to be Built at
Ingalls,” USNI News, December 19, 2025.

Congressional Research Service

29

Navy Constellation (FFG-62) and FF(X) Class Frigate Programs

production or federated shipbuilding. The Navy currently uses distributed production/federated
shipbuilding for its Virginia- and Columbia-class submarine construction programs.65
As discussed at length in another CRS report, U.S. Navy shipbuilding programs in some cases are
being slowed or limited by U.S. shipbuilding industrial base capacity constraints.66 Concerns over
this situation are heightened by the pace of China’s naval shipbuilding effort.67 President Trump,68
some other U.S. officials,69 and other observers70 have suggested or advocated using foreign
shipyards—particularly shipyards in South Korea and/or Japan—to build ships for the U.S. Navy,
at least as a stop-gap measure until U.S. shipbuilding capacity constraints can be alleviated. Other
observers oppose proposals for using foreign shipyards to build ships for the U.S. Navy.71
10 U.S.C. 8679 prohibits the construction of vessels for U.S. Armed Forces, or the major
components of the hull or the superstructures of such vessels, in foreign shipyards. The statute
includes a presidential waiver for the national security interest. The phrase major component of
65 For further discussion, see CRS Report RL32418, Navy Virginia-Class Submarine Program and AUKUS Submarine

(Pillar 1) Project: Background and Issues for Congress, by Ronald O'Rourke.
66 CRS Report RL32665, Navy Force Structure and Shipbuilding Plans: Background and Issues for Congress, by
Ronald O'Rourke.
67 For more on China’s naval shipbuilding effort, see CRS Report RL33153, China Naval Modernization: Implications
for U.S. Navy Capabilities—Background and Issues for Congress, by Ronald O'Rourke.
68 See, for example, Howard Altman, “Trump Considering Buying Foreign Ships To Make Up Gap With China,” The
War Zone, April 11, 2025; Song Sang-ho, “Trump Says U.S. May Buy ‘Top-Of-The-Line’ Ships from ‘Close’
Countries,” Yonhap, April 11, 2025; Oh Sam-Gwon, “Korean Shipbuilders Gear Up as Trump Suggests U.S. May Buy
Warships,” Korea JoongAng Daily, April 11, 2025; Tom Sharpe, “Trump Plans to Rebuild the US Navy in Korean
Shipyards. We Already Know This Works Well,” Telegraph (UK), January 9, 2025; Morgan Phillips, “Trump
Threatens to Tap Allies for Military Shipbuilding if US Can't Produce,” Fox News, January 7, 2025; Joe Gould,
“Trump Hints Pentagon Could Lean on Allies to Build Warships,” Politico Pro, January 6, 2025.
69 See, for example, Daryl Caudle, “Winning the Long Game: Sustaining Sea Power as Our Enduring Advantage,”
Defense News, December 18, 2025, in which the author—the Chief of Naval Operations—states (emphasis added):
“Until American [ship]yards fully recover from workforce shortages, supply chain fragility and lack of automation, we
are exploring responsible cooperation with allied shipbuilders in places like South Korea and Japan to bridge near-term
gaps in maintenance, repair and production.” See also “U.S. Navy Looks to Korean and Japanese Shipyards to Address
Submarine and Destroyer Delays,” Army Recognition, November 26, 2025; Kim Hyun-soo, “Arms Agency, U.S. Navy
Discuss Cooperation on Naval Shipbuilding, MRO,” Yonhap, August 8, 2025.
70 See, for example, Jennifer Hlad, “Can Partner Nations Help Solve the Navy’s Shipbuilding Woes?” Defense One,
November 24, 2025; Maritime Executive, “South Korean Yards Want to Build U.S. Navy Ships in Korea,” Maritime
Executive, November 16, 2025; Jihoon Yu, “ROK–U.S. Shipbuilding Cooperation Matters for Maritime Power,” Real
Clear World, December 17, 2025; Juliana Liu, “South Korea Is the Answer to America’s Naval Problem,” Bloomberg,
December 4, 2025; Brad Lendon, Gawon Bae, Yoonjung Seo, Mike Valerio, and Charlie Miller, “US Navy
Shipbuilding Is ‘a Mess.’ South Korean companies Think They Can Help Fix It,” CNN, updated October 20, 2025;
William Hawkins, “Trade Is Not What Matters Most,” U.S. Naval Institute Proceedings, July 2025; Namyeon Kwon,
“Don’t Miss the Boat: Considerations for U.S.-South Korea Maritime Cooperation,” Center for Strategic and
International Studies (CSIS), June 12, 2025; Steve Forbes, “Making Our Navy Supreme Again,” Forbes, May 27,
2025; Arjun Akwei and Jinwan Park, “Trump Wants More Ships? Korea Stands Ready to Help Build Them,” The Hill,
May 8, 2025; Miyeon Oh and Michael Cecire, “Why the United States, South Korea, and Japan Must Cooperate on
Shipbuilding,” RAND, May 6, 2025; “South Korea Offers to Build Five Aegis Destroyers per Year to Help the US
Counter China at Sea,” Army Recognition, April 11, 2025; Fatima Bahtić, “Facing New Realities amid Rising Costs:
Could Future US Navy Warships Be Built at Foreign Shipyards?” NavalToday.com, February 17, 2025; Peter Suciu,
“The 21st Century U.S. Navy Might Be Built in South Korea,” National Interest, January 9, 2025; Brian T. Di Mascio,
“Foreign Shipyards Can Help the U.S. Navy Build Its Fleet,” U.S. Naval Institute Proceedings, October 2024; Douglas
Robb, “Japan, South Korea and the US Should Mirror AUKUS for Destroyers,” Defense News, October 5, 2023; Brad
Lendon, “These May Be the World’s Best Warships. And They’re Not American,” CNN, June 3, 2023.
71 See, for example, Rebecca Grant, “6 Reasons to Say ‘No Thanks’ to Building U.S. Navy Warships in South Korea,”
Real Clear Defense, July 30, 2025; Matthew Paxton, “Outsourcing the US Shipyard Industrial Base Will Outsource
American Sovereignty,” Breaking Defense, August 5, 2024; Shipbuilders Council of America, “‘We Stand Ready’ Ad
Campaign Shows American Shipbuilders Can Deliver the Fleet of the Future,” undated, accessed January 4, 2026.

Congressional Research Service

30

Navy Constellation (FFG-62) and FF(X) Class Frigate Programs

the hull can be viewed as including, among other things, ship sections. The full text of the statute
as of January 2, 2026, is as follows:
§8679. Construction of vessels in foreign shipyards: prohibition
(a) Prohibition.-Except as provided in subsection (b), no vessel to be constructed for any
of the armed forces, and no major component of the hull or superstructure of any such
vessel, may be constructed in a foreign shipyard.
(b) Presidential Waiver for National Security Interest. (1) The President may authorize
exceptions to the prohibition in subsection (a) when the President determines that it is in
the national security interest of the United States to do so.
(2) The President shall transmit notice to Congress of any such determination, and no
contract may be made pursuant to the exception authorized until the end of the 30-day
period beginning on the date on which the notice of the determination is received by
Congress.
(c) Exception for Inflatable Boats. An inflatable boat or a rigid inflatable boat, as defined
by the Secretary of the Navy, is not a vessel for the purpose of the restriction in
subsection (a).

In addition to 10 U.S.C. 8679, a recurring provision in the annual DOD Appropriations Act has
prohibited funds appropriated each year for the Navy’s shipbuilding account—the Shipbuilding
and Conversion, Navy (SCN) appropriation account—from being used to build naval vessels or
the major components of naval vessels in foreign shipyards or other foreign facilities. The
provision has not included a presidential waiver. The phrase major components can be viewed as
including, among other things, ship sections. The text of the provision, which appears in the
paragraph of the DOD appropriations act that makes appropriations for the SCN account, has
been as follows:
… Provided further, That none of the funds provided under this heading [i.e., the heading
for the SCN account] for the construction or conversion of any naval vessel to be
constructed in shipyards in the United States shall be expended in foreign facilities for the
construction of major components of such vessel: Provided further, That none of the funds
provided under this heading shall be used for the construction of any naval vessel in foreign
shipyards:…

Supporters of having foreign shipyards contribute to the construction of frigates for the U.S. Navy
could argue that the Navy’s force of 32 small surface combatants (SSCs) at the start of FY2026 is
less than half of the Navy’s 73-ship force-level goal for such ships; that in light of China’s naval
shipbuilding effort, closing this shortfall is a matter of some urgency; and that given the time
needed to alleviate constraints on U.S. shipbuilding capacity (particularly limits on numbers of
available workers and the productivity of recently hired workers), there are few apparent options
other than using foreign shipyards for quickly expanding the shipbuilding capacity engaged in
building ships for the U.S. Navy. They could argue that involving foreign shipyards in the frigatebuilding effort could be a stop-gap measure to be employed until U.S. shipbuilding capacity is
increased, and that for similar reasons, Finnish shipyards are being brought into the effort to build
new icebreakers for the U.S. Coast Guard.72 They could argue that foreign shipyards in some
cases have lower shipbuilding costs than U.S. shipyards, due in part to lower labor costs, and that
involving foreign shipyards in the U.S. Navy’s frigate-building effort could therefore reduce
frigate procurement costs for the U.S. Navy.
72 For more on programs to build new icebreakers for the U.S. Coast Guard, see CRS Report RL34391, Coast Guard

Polar Security Cutter (PSC) and Arctic Security Cutter (ASC) Icebreaker Programs: Background and Issues for
Congress, by Ronald O'Rourke.

Congressional Research Service

31

Navy Constellation (FFG-62) and FF(X) Class Frigate Programs

Skeptics of having foreign shipyards contribute to the construction of frigates for the U.S. Navy
could argue that the Navy can use destroyers and other forces to compensate for its current
shortfall in SSCs; that the Navy and industry are taking numerous steps to alleviate constraints on
U.S. shipbuilding capacity;73 that diverting some of the work involved in building frigates to
foreign shipyards could weaken the U.S. shipbuilding industrial base by depriving the U.S.
shipbuilding industry of work that would support efforts to alleviate those constraints; that
involving foreign shipyards in the frigate-building effort, even if described as a stop-gap measure,
could set a precedent for involving foreign shipyards in other U.S. Navy shipbuilding programs,
which could further weaken the U.S. shipbuilding industrial base; and that involving foreign
shipyards in the frigate-building effort could add to Navy shipbuilding program management
workloads, and do so at a time when the Navy is facing challenges in executing its shipbuilding
programs.

Unexpended FFG-62 Procurement Funds
Another potential oversight issue for Congress is whether unexpended funds for the FFG-62
program—particularly funds appropriated for procuring the third though sixth FFG-62s—should
be rescinded or reprogrammed to other uses, and if the latter, then what those other uses should
be. The Navy’s FY2026 budget submission shows that a total of about $7.7 billion was
appropriated for procurement of FFG-62s through FY2025, including about $5.0 billion for the
third through sixth ships in the program. Potential oversight issues for Congress include the
following:
•

•

How much FFG-62 procurement funding appropriated in FY2025 and prior years
has not been expended and would become available for other uses if the third
through sixth ships in the program were canceled? How much additional
unexpended procurement funding would become available for other uses if the
first and/or second ships in the program were also canceled?
What would be the most cost-effective uses of unexpected FFG-52 procurement
funding? What are the Navy’s proposed uses?

Near-Term Support for F/MM
Another potential oversight issue for Congress concerns how to support F/MM in the near term,
while policymakers assess how F/MM’s shipbuilding capability could be used over the longer
run. Under the Navy’s desired approach for frigate acquisition, construction of the first two FFG62s, which was underway as of November 2025, would continue but remain under review. As
discussed earlier, the continuation, for now at least, of construction work on the first two FFG-62s
reportedly is intended to support F/MM in the near term, while policymakers assess how F/MM’s
shipbuilding capability could be used over the longer run. Other options for supporting F/MM in
the near term—which could be pursued either in lieu of or in conjunction with continued
construction work on the first two FFG-62s—include but are not necessarily limited to the
following:
•

building for the U.S. Navy Multi-Mission Surface Combatants (MMSCs) that
would be in addition to the four MMSCs that F/MM is building for the Royal
Saudi Navy;

73 For more on these steps, see CRS Report RL32665, Navy Force Structure and Shipbuilding Plans: Background and

Issues for Congress, by Ronald O'Rourke.

Congressional Research Service

32

Navy Constellation (FFG-62) and FF(X) Class Frigate Programs

•

•

building ship sections of other kinds of Navy ships, including but not limited to
• DDG-51 ship sections, so as to increase the annual production rate of DDG51s, which is below the annual procurement rate for DDG-51s, leading to a
growing backlog of numbers of DDG-51s that have been procured but not
yet completed;74 and
• Virginia-class attack submarine sections, so as to help increase the annual
production rate of Virginia-class submarines, which is below the annual
procurement rate for Virginia-class submarines, leading to a growing backlog
of numbers of Virginia-class submarines that have been procured but not yet
completed; and
participating in other Navy shipbuilding programs, including but not necessarily
limited to those for building amphibious ships,75 medium landing ships (LSMs),76
or USVs.77

Continuing construction work on the first two FFG-62s would permit F/MM to fully use
materials and components that have been procured for those two ships, and produce two frigates
for the Navy, reducing the Navy’s shortfall of small surface combatants (SSCs) relative to its
stated force-level goal for SSCs. As discussed earlier in this report, a two-ship FFG-62 class
could have elevated per-ship life cycle O&S costs due to the limited O&S economies of scale for
a two-ship class. As also discussed earlier, the issue of elevated FFG-62 per-ship O&S costs could
be addressed by eventually selling the two FFG-62s to one or two allied or partner navies that
might need only one or two such ships to meet their own mission needs. Potential oversight
questions for Congress include the following:
•

•

•

Would continued construction of the first two FFG-62s in conjunction with
F/MM’s construction of MMSCs for the Royal Saudi Navy adequately support
F/MM in the near term, while policymakers assess how F/MM’s shipbuilding
capability could be used over the longer run?
What is the most cost-effective approach for supporting F/MM in the near term,
while policymakers assess how F/MM’s shipbuilding capability could be used

[Text truncated at 120,000 characters. The full text is on the page linked above.]

---