# Oil and Natural Gas Pipelines: Role of the U.S. Army Corps of Engineers

> Briefs, arguments, decisions, and more.

URL: https://www.frixlaw.com/law-library/documents/crs%3AR44880

## Record

- **Collection:** Congressional research report
- **Document type:** CRS Report
- **Published:** June 28, 2017
- **Citation:** R44880

## Text

Oil and Natural Gas Pipelines:
Role of the U.S. Army Corps of Engineers
name redacted
Specialist in Natural Resources Policy
name redacted
Analyst in Environmental Policy
name redacted
Analyst in Natural Resources Policy
name redacted
Specialist in Energy and Infrastructure Policy
June 28, 2017

Congressional Research Service
7-....
www.crs.gov
R44880

Oil and Natural Gas Pipelines: Role of the U.S. Army Corps of Engineers

Summary
Growth in North American crude oil and natural gas production has led to efforts to expand the
domestic oil and natural gas pipeline network. Pipeline developers are required to obtain
authorizations from the U.S. Army Corps of Engineers (Corps) before constructing certain
pipeline segments. Under the agency’s regulatory program, the Corps is responsible for
authorizing activities that may affect federally regulated waters and wetlands. Under its civil
works program, the agency is responsible for approving activities that cross or may affect Corpsmanaged lands and Corps water resource projects. The agency’s role with respect to pipelines can
be controversial and may raise policy issues for Congress. Congress has a long-standing interest
in pipeline development and the regulation of pipelines because of the role of pipelines in the
domestic energy markets.
Corps Regulation of Water Crossings. The Corps has regulatory responsibilities pursuant to
Section 404 of the Clean Water Act (33 U.S.C. §1344), under which the Corps authorizes
activities that may discharge dredge or fill material into waters of the United States, including
wetlands. The agency also has regulatory responsibilities pursuant to Section 10 of the Rivers and
Harbors Act of 1899 (33 U.S.C. §403), under which the Corps authorizes structures and work in
or affecting the course, condition, or capacity of navigable waters. Because most pipelines cross
or potentially affect U.S. waters and wetlands somewhere along their routes, pipeline developers
routinely are required to obtain Corps authorization for some pipeline segments. The Corps
authorizes most pipeline water crossings using a general permit—Nationwide Permit 12—for
utility-line activities in waters of the United States. A nationwide permit essentially preauthorizes
a group of activities similar in nature that are likely to have a minor effect on waters and wetlands
both individually and cumulatively.
Approvals Related to Corps Land and Corps Projects. A pipeline developer may need
permissions from the agency’s civil works program if a pipeline segment may affect or cross a
Corps water resource project and Corps-managed land. That is, the Corps would need to grant (1)
an easement, typically for a right-of-way, to cross federal land managed by the Corps or (2) a
consent to cross non-Corps land with a Corps real estate interest (typically a federal flood
easement over nonfederal land). Prior to the granting of the easement or consent, the Corps
generally must provide permission for the pipeline to alter the associated Corps water resource
project. The easement at a Corps project for the Dakota Access Pipeline to cross under the
Missouri River in North Dakota was particularly controversial.
Corps Actions Must Comply with Federal Statutes. In carrying out its regulatory and civil
works authorities, the Corps complies with applicable federal requirements. For example, the
Corps identifies and considers the environmental impacts of the agency’s proposed action (e.g.,
Corps permit of an activity affecting a wetland) pursuant to the National Environmental Policy
Act (NEPA; 42 U.S.C. §§4321 et seq.) and considers impacts on historic properties pursuant to
the National Historical Preservation Act (NHPA; 54 U.S.C. §306108).
Policy Issues. Various questions arise in policy debates on Corps’ actions related to pipelines:



How does the Corps determine the direct, indirect, and cumulative impacts of its
decisions to authorize activities in regulated waters or Corps-managed lands?
When the federal role in a pipeline is limited to approving activities at discrete
segments, to what extent should federal agencies influence siting and other
aspects of a pipeline?

Congressional Research Service

Oil and Natural Gas Pipelines: Role of the U.S. Army Corps of Engineers



How does the use of Corps general permits affect the agency’s review,
information available to stakeholders and the public, and compliance with
NHPA?

These questions reflect some of the basic debates and challenges that Congress and other
policymakers face regarding federal approvals associated with private infrastructure.

Congressional Research Service

Oil and Natural Gas Pipelines: Role of the U.S. Army Corps of Engineers

Contents
Introduction ..................................................................................................................................... 1
Overview of Federal Role in Pipelines ............................................................................................ 3
Corps Involvement in Pipelines ................................................................................................ 3
Regulatory Role .................................................................................................................. 4
Civil Works Role ................................................................................................................. 4
Illustration of Federal Agency Involvement in Approving Pipelines ........................................ 4
Corps Regulatory Program .............................................................................................................. 6
Individual Permits ..................................................................................................................... 7
General Permits ......................................................................................................................... 7
Nationwide Permit 12: Utility-Line Activities .................................................................... 9
General Conditions Required for NWP Authorization ............................................................ 10
Pre-construction Notification ............................................................................................ 12
Nationwide Permit 12: Issues Raised Regarding Current Approach and Use ......................... 13
Corps Civil Works Program .......................................................................................................... 14
Permission to Alter a Corps Project ........................................................................................ 14
Corps Easements or Consents for Pipelines ............................................................................ 16
Congressional Committee Notification ............................................................................. 16
Evaluation of Request and Conditions of Easement or Consent....................................... 17
Illustration of Corps Approval Processes for Pipelines at Corps Projects and Real
Estate .................................................................................................................................... 18
Compliance with Other Federal Statutes During Corps Civil Works Processes ..................... 20
Compliance with Federal Statutes ................................................................................................. 20
Agency-Specific Procedures of the Corps Regulatory Program ............................................. 22
Corps NEPA Procedures ................................................................................................... 22
Corps Procedures for Protecting Historic Properties ........................................................ 24
Policy Issues Raised by Corps’ Pipeline Roles and Decisions ...................................................... 27

Figures
Figure 1. Illustration of Federal Agency Involvement in Approving Pipelines ............................... 5
Figure 2. Major Steps in Corps Approval Processes for Pipeline Segments Crossing
Corps Projects and Real Estate Interests .................................................................................... 19

Tables
Table 1. Selected Federal Laws That Require Outside Agency Review ....................................... 20

Contacts
Author Contact Information .......................................................................................................... 28

Congressional Research Service

Oil and Natural Gas Pipelines: Role of the U.S. Army Corps of Engineers

Introduction
Growth in North American crude oil and natural gas production has resulted in efforts to expand
the domestic oil and natural gas pipeline network.1 Pipelines can be a cost-effective and
comparatively safe means of hydrocarbon transport. Pipelines and their routes also can be
controversial locally, regionally, or nationally. While many new or expanded pipelines have been
proposed and completed in recent years, other proposed pipelines have been unable to satisfy all
the requirements to obtain federal authorizations, have faced barriers among state regulatory
agencies, and have been the subject of litigation. Congress has a long-standing interest in pipeline
development and the regulation of pipelines because of the critical role of pipelines in the
domestic energy markets.2
Failure to construct pipelines may result in various potential effects, such as greater reliance on
road or rail transport and constraints on getting oil and natural gas resources to refineries, power
plants, and other consumers—all of which can create economic inefficiencies.3 Local interests
along proposed pipeline routes regularly have raised concerns about the local environmental and
other impacts of pipeline construction; they also have expressed concerns about the risks during
pipeline operations of accidents that could affect the environment and human health. In recent
years, stakeholders interested in reducing U.S. reliance on fossil fuels or promoting other energy
sources and energy conservation have brought greater public attention both to oil and natural gas
pipelines and to federal and state decisions related to new pipelines in particular. Some of these
pipeline opponents argue that pipelines may facilitate the use of oil and natural gas, thereby
indirectly contributing to the human health, welfare, and environmental effects of oil and natural
gas production and use. Pipeline proponents argue that the impacts of development and use of
natural gas may be less than impacts associated with other energy sources and that both oil and
natural gas pipelines contribute to the nation’s energy security and provide broad benefits to the
U.S. economy.
This report discusses how the U.S. Army Corps of Engineers (Corps) administers its
responsibilities related to certain pipeline segments that require Corps authorizations. The Corps
is one of many federal agencies with responsibilities that may relate to oil and natural gas
pipelines. Interest in federal approvals and requirements for pipelines relates to a broader policy
issue before Congress: What is the appropriate federal role in protecting the environment, public

1

References in this report to oil pipelines also apply to pipelines carrying refined products, such as gasoline or
kerosene.
2
Congressional hearings and proposed legislation reflect some of the recent congressional interest related to pipelines.
For example, the House Energy and Commerce Committee’s Subcommittee on Energy held a hearing, Legislation
Addressing Pipeline and Hydropower Infrastructure Modernization, on May 3, 2017
(https://energycommerce.house.gov/hearings-and-votes/hearings/legislation-addressing-pipeline-and-hydropowerinfrastructure), and the Senate Energy and Natural Resources Committee held a hearing, Oversight Hearing on Oil and
Gas Pipeline Infrastructure, on June 14, 2016 (https://www.energy.senate.gov/public/index.cfm/2016/6/hearing-toexamine-oil-and-gas-pipeline-infrastructure-and-the-economic-safety-environmental-permitting-construction-andmaintenance-considerations-associated-with-that-infrastructure). During the 115th Congress, H.R. 2649 would change
the Federal Energy Regulatory Commission’s review process for natural gas pipelines. During the 114th Congress, S.
3498 proposed altering the requirements for actions by the U.S. Army Corps of Engineers (Corps) related to some oil
and natural gas pipelines and Section 1115 of H.R. 8, as passed by the House, would have required the establishment of
national energy security corridors for natural gas pipelines on federal land.
3
For example, for natural gas produced as part of oil production, transportation constraints potentially may contribute
to flaring or venting of unmarketable natural gas.

Congressional Research Service

1

Oil and Natural Gas Pipelines: Role of the U.S. Army Corps of Engineers

health, national economy, and domestic energy security when reviewing and authorizing activities
associated with private development of energy-sector or other infrastructure?
The role of the Corps in authorizing oil and natural gas pipelines is limited to (1) the agency’s
regulatory authorities for authorizing activities affecting regulated water bodies and wetlands and
activities that alter or obstruct navigable waters and (2) its civil works authorities, including
allowing a pipeline to cross a Corps water resource project and related lands. Because most
pipelines cross regulated water bodies, the Corps must authorize the activities at those crossings
before construction at those locations can commence. Because the Corps has no broad authority
related to pipelines along their entire domestic routes, the agency’s analyses to support its
authorization decisions are scoped to focus on the application of Corps authorities to specific
pipeline segments.
Controversy regarding the Dakota Access Pipeline (DAPL), a crude oil pipeline from North
Dakota to Illinois, focused attention on the Corps’ authorizations and approvals. This attention to
the Corps may continue, given the renewed efforts for the international Keystone XL,4 proposed
domestic pipelines, and related litigation.
This report provides an overview of the agency’s role with respect to oil and natural gas pipelines.
Because the Corps’ pipeline-related decisions can be controversial, the report also introduces
some of the issues raised.5 After an overview of the Corps and the broader federal role in
approving private oil and natural gas pipelines, the remainder of the report discusses







how the Corps’ regulatory responsibilities apply where pipelines cross water
bodies and wetlands (i.e., Corps regulatory program);
how the Corps’ civil works authorities may apply if a pipeline may alter or affect
a Corps water resource project or may cross Corps-managed land (i.e., Corps
civil works program);
how the Corps complies with various federal statutes as it arrives at pipelinerelated decisions, including the environmental documentation requirements of the
National Environmental Policy Act (NEPA) and the historic preservation
requirements of the National Historic Preservation Act (NHPA);6 and
how the agency’s role in pipelines raises or illustrates various policy issues for
decisionmakers.

4

For more on Keystone XL, see CRS Insight IN10678, Keystone XL Pipeline: Development Issues, by (name re
dacted) . On May 30, 2017, the developer of the proposed Keystone XL pipeline submitted to the Corps preconstruction notifications (PCNs) for Nationwide Permit 12 (NWP 12). The submittals covered 182 regulated water
crossings in South Dakota, 194 crossings in Montana, and 212 crossings in Nebraska. These Keystone PCNs (with
some information withheld) are available at http://www.nwo.usace.army.mil/Missions/Dam-and-Lake-Projects/PCN/.
For more on NWP 12 and PCNs, see “Corps Regulatory Program.”
5
Tribal treaty and tribal trust responsibilities, including issues of tribal consultation, have been part of the legal
challenges related to the Corps’ actions in relation to the Dakota Access Pipeline (DAPL). Some of the policy issues
raised include the following: How does the Corps evaluate the impacts of its decisions on tribal treaty rights, and how
does the agency act on specific trust responsibilities or comply with more general trust duties? Because this CRS report
is about the role of the Corps in pipelines generally and not about DAPL or tribal issues specifically, the report does not
address tribal treaty and tribal trust responsibilities in detail. Although requirements to consult with tribes may exist in
law or regulation, how tribal consultation is performed is largely a function of policy.
6
National Environmental Policy Act (NEPA; 42 U.S.C. §§4321 et seq.); National Historic Preservation Act (NHPA; 54
U.S.C. §306108).

Congressional Research Service

2

Oil and Natural Gas Pipelines: Role of the U.S. Army Corps of Engineers

Overview of Federal Role in Pipelines
Siting, construction, and operation of oil and natural gas pipelines may be subject to a number of
local, state, tribal, and federal requirements.7 Whether the entire pipeline will require federal
agency authorization generally depends on the commodity the pipeline would transport and
whether it would cross state lines.8 Specifically, the siting, construction, and operation of
interstate natural gas pipelines must be authorized by the Federal Energy Regulatory Commission
(FERC), in accordance with requirements established under Section 7(c) of the Natural Gas Act
of 1938;9 in contrast, domestic oil pipelines and intrastate natural gas pipelines are not subject to
a similar federal authorization for their entire routes.
Federal pipeline safety standards also could affect pipeline siting, construction, operation, and
maintenance. The Department of Transportation’s Pipeline and Hazardous Materials Safety
Administration (PHMSA) is the principal federal agency charged with ensuring the safe interstate
movement of natural gas and hazardous liquids, including crude oil. Congress tasked the
Department of Transportation, working through PHMSA, with regulating key aspects of interstate
pipeline safety, including design, construction, operation and maintenance, and spill response
planning. For more information on the Department of Transportation’s safety program, see CRS
Report R44201, DOT’s Federal Pipeline Safety Program: Background and Key Issues for
Congress, by (name redacted) , and see the box later in this report titled “PHMSA Pipeline
Safety Regulation and Corps Permit Conditions Related to Safety.”
Specific aspects or activities associated with pipelines may be subject to federal agency approval.
For example, separate federal agency authorization (in the form of a permit or other approval)
may be required if the proposed pipeline, in whole or in part, would cross federal land or
potentially would affect an environmental, natural, or cultural resource protected under federal
law. As discussed below, the involvement of the Corps in pipelines generally is limited to those
pipeline segments that would cross Corps-managed federal land (hereinafter referred to as Corps
land) or a Corps-managed federal flood easement on nonfederal land and to those pipeline
activities that may affect or cross waters and wetlands regulated by the agency.

Corps Involvement in Pipelines
Although the Corps has no authority to approve pipelines, certain pipeline segments and their
construction may require Corps authorizations. Under the agency’s regulatory program, the Corps
is responsible for authorizing activities that could affect federally regulated waters and wetlands.
Under its civil works program, the agency is responsible for approving activities that cross or
affect Corps lands and projects.
7

See CRS Report R44432, Pipeline Transportation of Natural Gas and Crude Oil: Federal and State Regulatory
Authority, by (name redacted) .
8
This report focuses on the Corps’ roles in authorizing domestic oil and natural gas pipelines because the majority of
crude oil and natural gas pipelines in the United States do not cross an international border. Oil and natural gas
pipelines that would cross the border with Canada or Mexico require Presidential Permits for border-crossing facilities,
in addition to Corps and other permits required for domestic pipelines. For information about Presidential Permits, see
CRS Report R44140, Presidential Permit Review for Cross-Border Pipelines and Electric Transmission, by (name
redacted) and (name redacted), and CRS Report R43261, Presidential Permits for Border Crossing Energy Facilities,
by (name redacted) and (name redacted)
.
9
15 U.S.C. §171f. See CRS Report R43138, Interstate Natural Gas Pipelines: Process and Timing of FERC Permit
Application Review, by (name redacted) , and CRS Report R43261, Presidential Permits for Border Crossing Energy
Facilities, by (name redacted) and (name redacted)
.

Congressional Research Service

3

Oil and Natural Gas Pipelines: Role of the U.S. Army Corps of Engineers

Regulatory Role
A pipeline developer must have authorization from the Corps regulatory program (sometimes
referred to as its permit program) for any pipeline segment affecting or crossing Corps
jurisdictional water, in accordance with




Section 404 of the Clean Water Act,10 under which the Corps regulates the
discharge of dredged or fill material into waters of the United States, including
wetlands; and
Section 10 of the Rivers and Harbors Act of 1899,11 under which the Corps
regulates structures and/or work in or affecting the course, condition, or capacity
of navigable waters.

Because pipelines of any significant length will cross or otherwise may affect U.S. waters
somewhere along their routes, pipeline developers are routinely required to have authorization
from the Corps under Section 404 of the Clean Water Act (hereinafter Section 404) and/or under
Section 10 of the Rivers and Harbors Act (hereinafter Section 10). The Corps regulates all
activities affecting regulated waters; for pipelines, the Corps regulates activities whether the
pipeline is interstate or intrastate and whether the pipeline is transporting oil or natural gas.

Civil Works Role
A pipeline developer may need certain approvals from the civil works program of the Corps if the
proposed pipeline could affect a Corps water resource project or Corps land and real estate
interests.12 Corps land and other real estate interests (e.g., private lands with a federal flood or
other flowage easement) typically were acquired as part of a water resource project. For pipelines
to cross below, on, or above Corps land and non-Corps land with a Corps real estate interest, the
agency generally will decide on granting both



a Corps permission to alter a Corps civil works project; and
a Corps easement to cross Corps land or a consent to cross non-Corps land with a
Corps real estate interest.

Illustration of Federal Agency Involvement in Approving Pipelines
Figure 1 illustrates pipeline segments over which the Corps may have some role, specifically
segments that would cross Section 404 Corps-regulated waters and wetlands or Section 10 Corpsregulated waters (and therefore would involve a role for the agency’s regulatory program) and
Corps land (and therefore would involve a role for the agency’s civil works program). Figure 1
also illustrates FERC involvement in authorizing the siting and construction of interstate natural
gas pipelines; no federal agency has a similar role for domestic interstate or intrastate oil
pipelines or for intrastate natural gas pipelines. Stakeholders with an interest in pipeline
construction sometimes have focused on the role of the Corps in pipeline-related approvals when
10

33 U.S.C. §1344. For a discussion of waters regulated under the Clean Water Act, see CRS Report R44585,
Evolution of the Meaning of “Waters of the United States” in the Clean Water Act, by (name redacted)
.
11
33 U.S.C. §403.
12
Most Corps civil works projects and lands are associated with infrastructure the agency built to improve navigation
and flood control and to restore aquatic ecosystems. For more on the Corps civil works program and its evolution, see
the appendix of CRS Report R41243, Army Corps of Engineers: Water Resource Authorizations, Appropriations, and
Activities, by (name redacted) and (name redacted) .

Congressional Research Service

4

Oil and Natural Gas Pipelines: Role of the U.S. Army Corps of Engineers

no other federal agency has authority to approve the entire pipeline, which primarily is the case
for domestic pipelines transporting crude oil. In the case of the DAPL to transport crude oil, the
pipeline route selected crossed Corps-regulated waters and Corps land at Corps water resource
projects. For more on the DAPL, see the box “Why Was the Corps the Main Federal Agency
Involved in the DAPL Debate?”
Figure 1. Illustration of Federal Agency Involvement in Approving Pipelines
(federal roles for different types and different routes of oil and natural gas pipelines)

Source: Congressional Research Service (CRS).
Notes: Corps land refers to Corps-managed federal land. FERC = Federal Energy Regulatory Commission. The
Department of Transportation’s Pipeline and Hazardous Materials Safety Administration (PHMSA), which is not
included in this figure, also has primary authority to regulate key aspects of interstate pipeline safety.
International pipelines may have additional federal entities and pipeline segments that are subject to federal
review, approval, or regulation. FERC does not authorize either interstate oil pipelines or intrastate oil pipelines;
the role of the Corps is the same for interstate and intrastate oil pipelines.

Why Was the Corps the Main Federal Agency Involved in the DAPL Debate?
The Dakota Access Pipeline (DAPL) is a 1,170-mile pipeline system to transport oil from North Dakota to Illinois.
The U.S. Army Corps of Engineers (Corps) became the most prominent federal agency in the DAPL debate in part
because other agencies had minimal involvement, given that DAPL is an interstate oil pipeline. Because DAPL
domestically transports crude oil, no federal agency has authority over its entire route or the entire construction
project. Instead, the four states that the pipeline traverses had primary authority for approving the pipeline’s route.

Congressional Research Service

5

Oil and Natural Gas Pipelines: Role of the U.S. Army Corps of Engineers

The Corps was involved only in approving pipeline segments that overlapped with Corps authorities; that is, the
agency’s jurisdiction was over 37 miles of DAPL’s length. The Corps was involved in DAPL because


the construction of the pipeline required that the Corps authorize activities in regulated waters and wetlands at
202 separate water crossings and



the route selected for DAPL required that the pipeline developer obtain Corps easements and related agency
permissions to cross Corps-managed federal land at the agency’s congressionally authorized water resource
projects on the Missouri River, as well as the consent of the Corps to cross Corps flood easements on
nonfederal land.
The pipeline developer used a Corps-promulgated nationwide permit—Nationwide Permit 12 for utility-line activities
(NWP 12)—as the mechanism to obtain the agency’s authorization for the 202 water crossings. Given the use of
NWP 12, there was no DAPL-specific National Environmental Policy Act (NEPA) environmental documentation
required for the Corps’ verifications of the 202 water crossings.
The easement and related permission for the pipeline to cross under the Missouri River in North Dakota at the
Corps-managed Lake Oahe project and lands received intense public attention, in part because the crossing is 0.55
miles upstream from the Standing Rock Sioux reservation and 73 miles north of the Cheyenne River reservation.
DAPL began transporting crude oil on June 1, 2017.
Some litigation related to DAPL continues in the courts. Much of the litigation relates to the agency’s compliance with
NEPA with respect to the permission and easement decisions at Lake Oahe. A number of these legal challenges
initially were rejected. However, in Standing Rock Sioux Tribe v. U.S. Army Corps of Engineers, No. 16-1534 (D.D.C. June
14, 2017), the U.S. District Court for the District of Columbia found that “[a]lthough the Corps substantially
complied with NEPA in many areas, the Court agrees that it did not adequately consider the impacts of an oil spill on
fishing rights, hunting rights, or environmental justice, or the degree to which the pipeline’s effects are likely to be
highly controversial.”
The court reserved judgement on other claims and did not immediately provide for relief, noting the “serious
consequences” of vacating the agency’s approval now that the pipeline is in operation. The court instead scheduled a
new round of briefing on the issue of relief.

Corps Regulatory Program
The Corps is responsible for authorizing activities that may affect waters over which it has
jurisdiction under Section 404 or Section 10. The agency performs this work as part of its
regulatory program. The types of projects that may cause impacts to regulated waters vary widely,
including navigation, coal mining, riverbank stabilization, and transportation projects. One
category of activities is a water or wetland crossing by a utility line, which includes oil and
natural gas pipelines.
The Corps’ regulatory authorities are limited by statute to activities affecting waters and wetlands
regulated pursuant to the Section 404 and Section 10 authorities.13 That is, the agency’s
regulatory jurisdiction does not extend to a pipeline’s entire route; it is limited to the crossings of
regulated waters, as shown in Figure 1. Therefore, the Corps generally does not regulate the
largest components of pipeline projects because it does not have regulatory jurisdiction over
portions of the pipeline that cross upland areas.14
13

A discussion of the waters regulated under Section 404 and how those are defined is beyond the scope of this report.
For information on that policy issue, see CRS In Focus IF10125, Overview of the Army Corps and EPA’s Rule to
Define “Waters of the United States” (WOTUS) and Recent Developments, by (name redacted)
.
14
In other words, the agency’s authorities federalize (i.e., make the private action subject to federal authorization or
approval) only the portions of the pipeline associated with regulated water crossings. For a project such as an oil
pipeline, in which only discrete segments are federalized, the Corps is described as having a “small federal handle”
based on the analogue that the pipeline is the pan and the federal role is limited to a small handle. For more on this
concept, see box titled “Geographic Limits of Corps Environmental Reviews.” For example, in the case of the Flanagan
South pipeline to transport crude oil from Illinois to Oklahoma, the pipeline segments that were subject to the agency’s
(continued...)

Congressional Research Service

6

Oil and Natural Gas Pipelines: Role of the U.S. Army Corps of Engineers

Authorizations pursuant to the Corps regulatory authorities fall under two categories of permits—
individual permits and general permits. Actions authorized through general permits represented
almost 94% of the Corps’ 53,825 regulatory actions in FY2016.15

Individual Permits
Activities that may or are expected to have significant adverse impacts on regulated waters
require individual permits. The Corps (or states that have been delegated the authority to
administer Section 404 permits)16 can process individual permits as standard individual permits or
through an abbreviated process known as a Letter of Permission procedure (which can vary by
state).17 Each standard individual permit is subject to public notice, public interest review, public
hearing, activity-specific environmental documentation, and case-by-case evaluation (including
an evaluation of alternatives), so these permits typically require more time than general permits
before an activity is authorized.18 Public notification is not required for individual permits
processed using Letters of Permission procedures.

General Permits
The Corps issues general permits for activities that are similar in nature and that are expected to
have minimal adverse effect on waters and wetlands both individually and cumulatively.19
General permits essentially preauthorize a group of similar activities on a programmatic level.
(...continued)
regulatory jurisdiction were 2.3% of the total length of the pipeline. (See U.S. Army Corps of Engineers, Decision
Document Nationwide Permit 12, January 6, 2017, at http://www.usace.army.mil/Portals/2/docs/civilworks/nwp/2017/
NWP_12_2017_final_Dec2016.pdf?ver=2017-01-06-125514-797. Hereinafter referred to as NWP 12 Decision
Document.)
15
That is, of the Corps’ 53,825 regulatory actions in FY2016, 60% (32,475 actions) and 34% (18,066 actions) were
pursuant to the nationwide permits (NWPs) and the regional/state general permits, respectively. These figures were
calculated using data in Appendix B of U.S. Army Corps of Engineers, FY2016 Regulatory Annual Report for Section
1006(2)(e) of WRRDA, at http://www.usace.army.mil/Portals/2/docs/civilworks/regulatory/section214/
fy16_WRDA214_annual_report.pdf?ver=2017-03-27-075105-620. Figures do not include authorization of actions that
do not require reporting to the Corps. An estimate of the total actions under the nationwide permits (including the
actions that are not required to be reported) is around 61,500 (U.S. Army Corps of Engineers, Regulatory Impact
Analysis for the Proposed 2017 Nationwide Permits, May 18, 2016, p. B-2. Hereinafter referred to as 2016 NWP
Regulatory Impact Analysis).
16
The Clean Water Act was amended in 1977 to allow for state administration of individual and general permits (33
U.S.C. §1344). In this report, for simplicity the Corps generally is identified as the entity responsible for administering
the permit requirements of Section 404.
17
Letters of Permission can be used only for activities specified in 33 C.F.R. §325.2(e)(1). For example, Letters of
Permission for Section 404 compliance are limited to activities for which the water quality certification (pursuant to
Section 401 of the Clean Water Act) is waived and, if appropriate, the Coastal Zone Management Act consistency
concurrence is obtained or presumed. For information on state or tribal water quality certification and state coastal zone
management consistency, see “Compliance with Federal Statutes” later in this report.
18
According to the Corps, the agency’s mean number of days for evaluating complete applications for standard
individual permits and for Letters of Permission are 211 days and 110 days, respectively (2016 NWP Regulatory
Impact Analysis, p. B-2). If additional information is needed from an applicant to complete an application, the
permitting process may take longer. The mean number of days from the initial application (which may or may not
represent a complete application) to the Corps decision is 291 days for standard individual permits and 140 days for
Letters of Permission (ibid., p.10). No data on permit-processing time are available for oil and natural gas pipelinerelated individual permits. For information on processing times for some general permits, see footnote 41.
19
33 U.S.C. §1344(e). The Clean Water Act does not establish how the Corps is to determine whether or not an impact
is minimal or the degree of certainty required to support such a determination; however, the statute does indicate
(continued...)

Congressional Research Service

7

Oil and Natural Gas Pipelines: Role of the U.S. Army Corps of Engineers

The Corps uses general permits to minimize the permit processing burden of its regulatory
program on both itself and applicants. General permits authorize applicants to proceed without
the more time-consuming need to obtain standard individual permits in advance. The lower
processing burden of general permits creates an incentive for applicants to reduce the impacts of
their activities on regulated waters and wetlands in order to qualify for a general permit.
During the process required for the Corps to issue a general permit, the general permit is subject
to public notice, public interest review, public hearing, and environmental documentation; the
specific actions undertaken pursuant to the general permit do not go through these steps. The
Corps issues a range of general permits, including




Nationwide permits (NWPs), which cover a wide range of activities—such as
aids to navigation, minor dredging, and bank stabilization.20 There are 52 NWPs
in force. Regional conditions also can be applied to NWPs.
Other general permits that apply in a single state or regionally. Programmatic
permits are built on an existing state, local, or other federal agency program and
are designed to avoid duplication between the existing program and Corps
efforts.21 Regional permits are a type of general permit issued by a division or
district engineer at the Corps.22

Nationwide and other general permits are issued for five-year terms; the permits automatically
expire and become null and void (and cannot be extended) if they are not modified or reissued
within five years of their effective date.23 The current NWPs took effect on March 19, 2017, for a
five-year period.24
Pipeline activities that require Corps authorization and that are similar in nature with minimal
environmental impacts (e.g., minor stream crossings) may qualify for a general permit. It
typically would be NWP 12 (which is discussed in more detail in “Nationwide Permit 12: UtilityLine Activities,” below), unless a state or regional general permit applies. To qualify for NWP
authorization, proposals must meet a number of general conditions (GCs). (See section titled
“General Conditions Required for NWP Authorization” for more information).
Many activities covered by NWPs can proceed without advance notification to the Corps,
whereas other activities that can be pursued under an NWP require that the applicant submit a
pre-construction notification (PCN) and obtain a verification by the Corps for use of that NWP. A
PCN is a request submitted by the applicant to the Corps to confirm (i.e., verify) whether or not a
particular activity is authorized by general permits. If the activity does not require the permittee to
submit a PCN, the permittee determines if the activity qualifies for an NWP. Therefore, the Corps
(...continued)
criteria applicable to Section 404 permits, including categories of impacts (33 U.S.C. §1344(b)).
20
For more on nationwide permits, see CRS Report 97-223, The Army Corps of Engineers’ Nationwide Permits
Program: Issues and Regulatory Developments, by (name redacted) and (name redacted) .
21
For example, there is a state programmatic general permit (SPGP) for Pennsylvania that allows for the issuance of
general permits on a statewide basis that work in conjunction with a Pennsylvania regulatory program that protects the
environment in a manner equivalent to the Corps regulatory program.
22
An assessment of the suite of regional and state general permits and how they relate to pipelines is beyond the scope
of this report.
23
Most standard individual permits also expire after five years and must be reissued or renewed, if the activity that they
authorize is of a continuing nature.
24
U.S. Army Corps of Engineers, “Issuance and Reissuance of Nationwide Permits, Final Rule” 82 Federal Register
1860, January 6, 2017.

Congressional Research Service

8

Oil and Natural Gas Pipelines: Role of the U.S. Army Corps of Engineers

reviews the activities for which it receives a PCN but does not conduct a review of all the
individual activities potentially authorized by an NWP. (See section titled “Pre-construction
Notification” for more on PCNs.)
If a pipeline-related crossing does not meet the conditions of a general permit or qualify for a
general permit as determined by statute and regulation, the Corps district may use its
discretionary authority to require use of the individual permit process. The Atlantic Sunrise
natural gas pipeline is an example of a pipeline for which the Corps reviewed the application as a
standard individual permit because the proposed activity would exceed the wetland loss threshold
of the applicable general permit.25

Nationwide Permit 12: Utility-Line Activities
One of the nationwide permits—NWP 12—is used to authorize utility-line activities, including
the construction, maintenance, or repair of utility lines in waters of the United States. The permit
defines a utility line as any pipe or pipeline for the transportation of any gaseous, liquid,
liquescent, or slurry substance—including oil or natural gas—for any purpose and any cable, line,
or wire for the transmission for any purpose of electrical energy, telephone, and telegraph
messages and radio and television communication.26 NWP 12 can be used only if the activity
(e.g., a water crossing) does not result in the loss of more than 0.5 acres of waters of the United
States.
Certain activities under NWP 12 require an approved PCN before the activity authorized by that
permit may commence. An NWP 12 permit applicant must submit a PCN based on various
thresholds and criteria—for example, when a Section 10 permit is required, when mechanized
land clearing in forested wetlands is required for the right-of-way, or when discharges are
expected to cause the loss of more than 0.1 acres of waters of the United States, among other
thresholds and criteria.27 For NWP 12 specifically, the Corps requires that PCNs include
information on other water crossings for the linear project (e.g., the pipeline) that will use NWP
12 that do not require PCNs.
The Corps estimates that NWP 12 is used on average approximately 11,500 times per year on a
national basis, affecting approximately 1,700 acres of U.S. waters, including wetlands regulated
under the Clean Water Act.28 The total includes about 9,000 uses per year for activities that
involve submitting a PCN to the Corps and about 2,500 uses for activities that do not require a
PCN.29
Individual NWP 12 verifications do not require NEPA documentation, nor do they require an
opportunity for public comment.30 The public comment opportunity occurs during the rulemaking
procedure for the NWP itself, not with each verification or use of the permit.31

25

The applicable general permit would have been a Pennsylvania-specific general permit (see footnote 21). For more
information on Atlantic Sunrise, see U.S. Army Corps of Engineers, Public Notice, March 31, 2017, at
http://www.nab.usace.army.mil/Missions/Regulatory/Public-Notices/Public-Notice-View/Article/1136707/pn17-15williams-gas-pipeline-atlantic-sunrise-project-2014-00475/.
26
NWP 12 Decision Document, p. 1.
27
Ibid., p. 43.
28
Ibid., p. 70.
29
Ibid.
30
Ibid., p. 20.
31
During the NWP rulemaking, the Corps may consult with tribes. Generally this consultation is to determine regional
(continued...)

Congressional Research Service

9

Oil and Natural Gas Pipelines: Role of the U.S. Army Corps of Engineers

Whereas for some pipelines Corps regulatory information is publicly available through Corps
districts, FERC dockets,32 or court documents, no nationally aggregated data are available on
NWP 12 use that is specifically about oil and natural gas pipelines. The 11,500 NWP 12
authorizations cited are not specific to pipelines; the figure includes all utility-line activities.
Furthermore, although NWP 12 covers a large majority of utility-line activities, some pipeline
activities may not qualify for NWP 12 and may require individual permits. The publicly available
database that the Corps maintains on individual permits is not designed to track which individual
permits are related to oil and gas pipelines,33 and no publicly available database is available that
tracks each verification for NWP 12 activities related to pipelines specifically or utility lines more
broadly.

General Conditions Required for NWP Authorization
By statute, activities that have the potential to result in more than minimal individual and
cumulative adverse effects on the aquatic environment cannot be authorized by NWPs, including
NWP 12.34 To ensure that individual activities do not exceed that level of impact, each NWP
rulemaking includes general conditions (GCs) that a permittee must comply with, as applicable.35
The NWPs reissued in 2017 detail 32 GCs that apply to any activity using an NWP for its
authorization, including the following:



Navigation (GC 1). No activity may cause more than minimal adverse effects on
navigation.
Water Supply Intakes (GC 7). No activity may occur in the proximity of a
public water supply intake, except where the activity is for the repair or
improvement of public water supply intake structures or adjacent bank
stabilization.

(...continued)
conditions that may apply to one or more NWPs and to require PCNs for proposed activities in a geographic region that
have the potential to cause more than minimal adverse effects on tribal rights, protected tribal resources, or tribal lands.
According to 82 Federal Register 1953, January 6, 2017, during the 2007, 2012, and 2017 NWP rulemakings, “Corps
Headquarters issued memoranda to its division and district offices that requested that Corps districts consult with tribes
on the NWPs to develop regional conditions, coordination procedures, and other measures to ensure that the NWPs
have no more than minimal adverse effects on tribal trust resources and tribal rights.”
32
In 2007, the Corps adopted a regulatory guidance letter on its permit process for proposed natural gas projects,
including interstate natural gas pipelines; the letter indicates that the Corps will provide a copy of its verification letters
to the Federal Energy Regulatory Commission (Letter from Major General Don T. Riley, Director of Civil Works,
Corps Regulatory Guidance Letter, September 19, 2007).
33
A national database of Corps individual permits is available at http://corpsmapu.usace.army.mil/cm_apex/f?p=
340:1:0::NO. The database includes individual permits; it is searchable by Corps regulatory office, month, and year.
Available data fields include the name of the applicant and project name (which may reference the type of project);
there is no database field for the type of project (e.g., pipeline).
34
33 U.S.C. §1344(e).
35
Although noncompliance with the general conditions (GCs) can be the basis for enforcement action, courts have held
that the Corps need not undertake a searching examination of compliance with each GC prior to issuing an NWP
verification (Mobile Baykeeper, Inc. v. U.S. Army Corps of Engineers, 2014 WL 5307850 (S.D. Ala. October 16,
2014)). According to 82 Federal Register 1952, January 6, 2017, “District engineers monitor the use of the NWPs in
specific geographic regions, to ensure that the use of the NWPs does not result in more than minimal cumulative
adverse environmental effects, which includes adverse effects to tribal rights, protected tribal resources, and tribal
lands.”

Congressional Research Service

10

Oil and Natural Gas Pipelines: Role of the U.S. Army Corps of Engineers















Management of Water Flows (GC 9). To the maximum extent practicable, the
pre-construction course, condition, capacity, and location of water flows must be
maintained.
Proper Maintenance (GC 14). Any authorized structure or fill shall be properly
maintained, including maintenance to ensure public safety and compliance with
applicable NWP GCs, as well as any activity-specific conditions added by the
district engineer to an NWP authorization.36 (For information on how pipeline
safety is addressed and how it relates to GC 14, see box titled “PHMSA Pipeline
Safety Regulation and Corps Permit Conditions Related to Safety.”)
Tribal Rights (GC 17). No NWP activity may cause more than minimal adverse
effects on tribal rights (including treaty rights), protected tribal resources, or
tribal lands.37
Endangered Species (GC 18). No activity may be authorized if it is likely to
directly or indirectly jeopardize the continued existence of a threatened or
endangered species or a species proposed for such designation, as identified
under the federal Endangered Species Act (ESA),38 or if it will directly or
indirectly destroy or adversely modify the critical habitat of such species.
Historic Properties (GC 20). In cases where the district engineer determines that
the permitted activity may affect properties listed, or eligible for listing, in the
National Register of Historic Places, no activity may be authorized until the
requirements of Section 106 of NHPA have been satisfied. Section 106 requires
federal agencies to take into account the effect of their undertakings on any
historic property.
Mitigation (GC 23). The district engineer must consider specific factors when
determining appropriate and practicable mitigation measures to ensure that any
adverse effects on the aquatic environment are minimal (e.g., to the maximum
extent practicable, the activity must be designed and constructed to avoid and
minimize temporary and permanent adverse effects, at the project site, to waters
of the United States).
Water Quality (GC 25). The permittee must obtain an individual water quality
certification or waiver for discharges authorized by the NWP if the state or
authorized tribe has not previously certified compliance of the NWP with Section
401 of the Clean Water Act.39

36

NWP 12 Decision Document (p. 24) states:
General condition 14, proper maintenance, requires NWP activities to be maintained to ensure
public safety. For NWP 12 activities, this includes maintaining the utility line so that it does not
leak. The Corps does not regulate the operation and maintenance of pipelines, if those activities do
not include activities that require [Department of the Army] authorization. As discussed above,
there are other federal agencies that have legal responsibility for addressing the operation of
pipelines and responding to leaks or spills that may occur. Concerns regarding pipeline leaks or
spills should be brought to the attention of those federal agencies.
37
According to 82 Federal Register 1953, January 6, 2017, “If a tribe has concerns with how a Corps district is
implementing these NWPs, the tribe should raise those concerns to the district. Disagreements concerning
interpretation of treaties may need to be resolved by other parties.”
38
16 U.S.C. §1536.
39
33 C.F.R. §330.4 contains the regulations for implementing Section 401 of the Clean Water Act.

Congressional Research Service

11

Oil and Natural Gas Pipelines: Role of the U.S. Army Corps of Engineers



Pre-construction Notification (GC 32). The permittee is required to provide a
PCN as specified in each NWP.

Unlike with individual permits, activities in regulated waters can be conducted pursuant to NWPs
without an evaluation of alternatives to those activities (e.g., a water crossing proposed by a
pipeline developer can be authorized under the NWP without the Corps evaluating alternative
crossing locations).40 For verification under an NWP, GC 18 and GC 20 may require the use of
the NWP to be reviewed if the activity may adversely affect federally listed endangered or
threatened species or historic properties. For more on NWP and ESA compliance, see box
“Nationwide Permits and Endangered Species Act Compliance.” For more on historic properties
compliance, see this report’s section titled “Corps Procedures for Protecting Historic Properties.”
PHMSA Pipeline Safety Regulation and Corps Permit Conditions Related to Safety
The Pipeline and Hazardous Materials Safety Administration (PHMSA) largely determines the minimum federal
requirements for interstate pipelines. PHMSA regulations are largely how pipeline safety is addressed in pipeline
design, construction, and maintenance. PHMSA also is responsible for reviewing oil spill response plans (known as
facility response plans) for oil pipelines that might spill oil into navigable waters or on the shoreline. PHMSA reviews
and approves these plans consistent with 33 U.S.C. §1321. Key elements of a facility response plan are, among other
things, a worst-case discharge calculation and location (49 C.F.R. §194) and identification of environmentally and
economically sensitive areas.
Regarding siting of pipelines, PHMSA identifies high consequence areas (HCAs) to reduce the consequences of an
inadvertent release from pipelines. HCAs for natural gas transmission focus solely on populated areas. For hazardous
liquid pipelines, such as oil pipelines, the HCAs are identified based on populated areas, drinking water sources, and
unusually sensitive ecological resources. PHMSA’s Office of Pipeline Safety identifies and maps HCAs for hazardous
liquids because of their complexity, while operators of natural gas pipelines use an equation to calculate a radius of
potential impact and then compare the area of potential impact to populated areas. Pipeline segments in the presence
of HCAs may require extra integrity protection to reduce risk.
Regarding the scope of the treatment of pipeline safety within the agency’s regulatory program, the Corps has stated:
We do not have the authority to regulate the operation of oil and gas pipelines, and we do not have the
authority to address spills or leaks from oil and gas pipelines. ... There are other federal laws that address the
operation of pipelines and spills and leaks of substances from pipelines. Those laws are administered by other
federal agencies. (U.S. Army Corps of Engineers, Decision Document Nationwide Permit 12, January 6, 2017,
p. 1884.)

Instead, when the Corps provides authorization for activities regulated under Section 404 and Section 10, the agency
generally requires that the authorized structures be properly maintained to ensure public safety. For example, under
Nationwide Permit 12, General Condition 14 on proper maintenance requires that any authorized structure be
maintained so that it does not leak.

Pre-construction Notification
GC 32 specifies that the permittee is required to submit a PCN to the Corps pursuant to the
applicable NWP; it also establishes the information required for inclusion in the PCN and the
timing of the agency’s review of the PCN. When a PCN is submitted, the Corps has 30 days to
determine whether a PCN is complete. The Corps district engineer has 45 days to review a
complete notification under most NWPs, including NWP 12, unless the proposed activity requires
an ESA Section 7 consultation and/or NHPA Section 106 consultation.41 If no ESA or NHPA
40

40 C.F.R. §230.7(b)(1).
NWP 12 Decision Document, p. 10. According to the Corps, the agency’s mean number of days for evaluating
complete applications for verifications pursuant to the NWPs that require PCNs is 41 days (2016 NWP Regulatory
Impact Analysis, p. 10). If additional information is needed in order to complete an application, the permitting process
may take more time. The mean number of days from the initial notification with a PCN under an NWP (which may or
may not represent a complete application) to the Corps decision is 86 days (ibid., p.10). No data on permit-processing
(continued...)
41

Congressional Research Service

12

Oil and Natural Gas Pipelines: Role of the U.S. Army Corps of Engineers

consultation is required, the proposed work generally may not proceed without written
confirmation from the district engineer; however, if no decision is issued during the 45-day
review period, the permittee may presume that the activity qualifies for the NWP.42 If ESA or
NHPA consultation is required, the proposed work may not begin before receiving a written NWP
verification. PCNs and their verifications are not required to be published, nor must a public
comment opportunity be provided during the review period. The public may not be aware that a
PCN has been submitted to the Corps.
Nationwide Permits and Endangered Species Act Compliance
Section 7 of the Endangered Species Act (ESA) requires federal agencies to consult with the Department of the
Interior’s Fish and Wildlife Service or the National Marine Fisheries Service, as appropriate, to determine whether an
activity an agency might authorize “may affect” a species listed or proposed for listing as threatened or endangered
under ESA. The Corps does not engage in Section 7 consultation on rulemaking for the nationwide permits (NWPs)
because it relies on General Condition 18 and other NWP procedures, such as regional conditions, to ensure that
the NWPs are not likely to jeopardize any threatened or endangered species or harm critical habitat. Consequently,
the Corps may have to ensure ESA compliance for specific NWP verifications. A Corps document indicates that the
agency conducted 1,402 formal consultations and 9,302 informal consultations for specific activities under the NWP
pursuant to Section 7 of the ESA during the period March 19, 2012, to September 30, 2016 (U.S. Army Corps of
Engineers, Decision Document Nationwide Permit 12, January 6, 2017, p. 65). No consultation statistics specific to NWP
12 are available. According to the same Corps document (p. 66), “If the biological opinion concludes that the
proposed activity is likely to jeopardize the continued existence of listed species or adversely modify or destroy
critical habitat, the proposed activity cannot be authorized by NWP and the district engineer will instruct the
applicant to apply for an individual permit.” For more on what is a Section 7 consultation, see CRS Report RL31654,
The Endangered Species Act: A Primer, by (name redacted) and (name reda cted)
.

Nationwide Permit 12: Issues Raised Regarding Current Approach
and Use
As noted, the majority of oil and natural gas pipeline activities subject to the Corps regulatory
program are authorized via NWP 12. Some stakeholders have criticized the Corps for relying on
NWP 12 to authorize pipeline-related activities. A primary concern is that the NWP process does
not allow for a separate environmental review of each activity or set of activities for a pipeline
project proceeding under NWP 12. The agency’s position is that, if applicable general conditions
and limits for using the NWP are met, the environmental impacts would be minimal.
The Corps has developed the general conditions for the use of NWP 12 to establish compliance
with federal laws related to species, historic properties, and environmental impacts. Some critics
contend that permittees that are not required to submit PCNs make their own determinations
about project-specific conditions without Corps review.
Another criticism relates to the scope of environmental impacts considered for projects under
NWP 12. NWPs can be used only for a “single and complete project” that will cause only
minimal adverse environmental effects, individually or cumulatively.43 The Corps defines a single
(...continued)
times are available for NWP 12 or for oil and natural gas pipeline-related verifications pursuant to NWP 12. As noted,
these data are for the mean; information on the full distribution of evaluation days and application days is not available.
42
According to the NWP 12 Decision Document (p. 11), “If the district engineer determines after reviewing the PCN
that the cumulative adverse environmental effects are more than minimal, after considering a mitigation proposal
provided by the project proponents, he or she will exercise discretionary authority and require an individual permit.”
43
33 C.F.R. §330.2(i).

Congressional Research Service

13

Oil and Natural Gas Pipelines: Role of the U.S. Army Corps of Engineers

and complete project as a portion of a total project that includes all crossings of a single water
body at a specific location.44 Thus, NWP 12 can be used multiple times for a single pipeline with
numerous water crossings if each crossing does not result in the loss of greater than 0.5 acres of
waters of the United States. Therefore, the “project” that is subject to Corps authorization is not
the entire pipeline but rather the discrete segments that cross waters subject to the agency’s
regulatory jurisdiction. Critics say that such segmenting of a pipeline when NWPs are used fails
to account for cumulative effects. Legal challenges to the use of NWPs along these lines of
argument have been largely unsuccessful.45

Corps Civil Works Program
If a proposed nonfederal pipeline of any type or other nonfederal activity would cross or
otherwise use federal lands, the developer generally is required to obtain the appropriate real
estate interest (e.g., an easement providing a right-of-way for the pipeline) from the federal
agency authorized to administer that land. The Corps owns 7.6 million acres of land and manages
another 4.1 million acres, often through federal flowage easements on nonfederal, frequently
private, land.46 The Corps is responsible for these lands because they are part of Corps civil works
projects. The agency’s inventory of civil works projects includes 702 dams and associated
reservoirs and 14,500 miles of Corps-constructed levees. A pipeline developer also is required to
obtain the agency’s permission prior to altering or otherwise affecting the operations of a Corps
civil works project.
For requests to have pipelines cross below, on, or above Corps land and non-Corps land with a
Corps real estate interest, the Corps generally will decide on whether or not to grant both a
permission to alter a Corps civil works project and an easement to cross Corps land or a consent
to cross non-Corps land with a Corps real estate interest.

Permission to Alter a Corps Project
Corps authority to allow alterations to its projects derives from Section 14 of the Rivers and
Harbors Act of 1899, also known as Section 408 based on its codification at 33 U.S.C. §408. This
provision states that the Secretary of the Army may “grant permission for the alteration or
permanent occupation or use of any of the aforementioned public works when in the judgment of
the Secretary such occupation or use will not be injurious to the public interest and will not
impair the usefulness of such work” (emphasis added).
44

According to 82 Federal Register 2007, January 6, 2017, “For linear projects crossing a single or multiple
waterbodies several times at separate and distant locations, each crossing is considered a single and complete project
for purposes of NWP authorization.”
45
See, for example, Sierra Club v. United States Army Corps of Eng'rs, 990 F. Supp. 2d 9 (D.D.C. 2013) related to the
Flanagan South oil pipeline; Mobile Baykeeper, Inc. v. U.S. Army Corps of Engineers, 2014 WL 5307850 (S.D. Ala.
October 16, 2014) related to the use of NWP 12 for 12 water-crossing authorizations for a 41-mile pipeline transporting
oil from Alabama to Mississippi; and Sierra Club v. Bostick, 787 F.3d 1043 (10th Cir. 2015) related to the 485-mile
Gulf Coast Pipeline to transport oil with more than 2,000 regulated crossings authorized using NWP 12. A dissent in an
earlier opinion in the Sierra Club v. Bostick litigation contrasts with the previously noted opinions, in that it attributed
significance to the absence of a Corps NEPA document for the cumulative impacts of the more than 2,000 NWP 12
verifications (Sierra Club v. Bostick, No. 12-6201, 539 Fed. Appx. 885, 896, 2013 U.S. App. LEXIS 20667, 2013 WL
5539633, at *9 (10th Cir. Oct. 9, 2013)).
46
U.S. Army Corps of Engineers, Information Paper: Civil Works Program Statistics, March 20, 2013. Flowage
easement land is non-Corps-owned land on which the Corps has acquired certain perpetual rights, including the right to
flood the land.

Congressional Research Service

14

Oil and Natural Gas Pipelines: Role of the U.S. Army Corps of Engineers

A Section 408 permission is required for all alterations to Corps projects, not only alterations by
pipelines.47 For pipelines over 24 inches (24″) in diameter, the Corps conducts a technical review
of the proposed pipeline’s effects on Corps projects pursuant to Engineer Circular (EC) 1165-2216, Policy and Procedural Guidance for Processing Requests to Alter US Army Corps of
Engineers Civil Works Projects Pursuant to 33 USC 408.48 For more details on the technical
review conducted for deciding to grant, grant with conditions, or deny a Section 408 permission,
see the box “Section 408 Permissions: Guidance Since 2015 and Congressional Action.” For
smaller pipelines and other encroachments of a more routine or minimal nature, the Corps
complies with Section 408 by following the process established in Chapter 17, “Non-Recreation
Outgrant Policy,” of Engineer Regulation (ER) 1130-2-550, Recreation Operations and
Maintenance Policies.49

Section 408 Permissions: Guidance Since 2015 and Congressional Action
In 2015, the Corps released new regulations for how the agency would process requests for Section 408
permissions—Engineer Circular (EC) 1165-2-216. The regulations require the Corps to review (1) whether granting
the 408 permission would impair the usefulness of the specific Corps project and (2) whether the proposed alteration
to the Corps project would be injurious to the public interest based on probable, including cumulative, impacts. EC
1165-2-216 states:
Evaluation of the probable impacts that the proposed alteration to the [Corps] project may have on
the public interest requires a careful weighing of all those factors that are relevant in each particular
case. The benefits that reasonably may be expected to accrue from the proposal must be compared
against its reasonably foreseeable detriments. The decision whether to approve an alteration will be
determined by the consideration of whether benefits are commensurate with risks.
EC 1165-2-216 also states:
Factors that may be relevant to the public interest depend upon the type of [Corps] project being
altered and may include, but are not limited to, such things as conservation, economic development,
historic properties, cultural resources, environmental impacts, water supply, water quality, flood
hazards, floodplains, residual risk, induced damages, navigation, shore erosion or accretion, and
recreation. This evaluation should consider information received from the interested parties,
including tribes, agencies, and the public.
As part of the technical review, the Corps complies with other federal statutes, such as the National Environmental
Policy Act (NEPA), and provides public notice of the opportunity for public input. As part of the technical review and
accompanying documents for NEPA compliance, the Corps considers reasonable feasible alternatives. In practice, the
alternatives considered are generally limited to (1) the proposed alteration in place and (2) the proposed alteration
not in place. According to EC 1165-2-216, examination of alternatives not proposed by the applicant should be

47

The Corps received 1,437 applications (also referred to as requests) in FY2016 for Section 408 permissions. There is
no available information on how many of these requests were related to oil and natural gas pipelines (Email from U.S
Army Corps of Engineers staff to Congressional Research Service, November 10, 2016). The Corps processed a total of
847 requests in FY2016; of these, the Corps approved 755 and denied 42, and 52 requests were withdrawn (ibid.).
There are no data on how often the Corps used environmental assessments or the more-detailed environmental impact
statements as part of its NEPA compliance for the agency’s Section 408 permission reviews (ibid.). No data on
processing times for Section 408 permissions are publicly available.
48
U.S. Army Corps of Engineers, Policy and Procedural Guidance for Processing Requests to Alter US Army Corps of
Engineers Civil Works Projects Pursuant to 33 USC 408, Engineer Circular (EC) 1165-2-216, September 30, 2015
(June 21, 2016, update), at http://www.publications.usace.army.mil/Portals/76/Publications/EngineerCirculars/
EC_1165-2-216.pdf?ver=2016-09-01-111054-827.
49
U.S. Army Corps of Engineers, Recreation Operations and Maintenance Policies, Engineer Regulation (ER) 1130-2550, October 1, 1999, at http://www.publications.usace.army.mil/Portals/76/Publications/EngineerRegulations/
ER_1130-2-550.pdf?ver=2014-05-06-112352-670. EC 1165-2-216 states that easements and other approved uses of
federal lands by nonfederal entities issued pursuant to ER 110-2-550, Chapter 17 meet “the intent of Section 408.”

Congressional Research Service

15

Oil and Natural Gas Pipelines: Role of the U.S. Army Corps of Engineers

evaluated only to the extent necessary to allow a complete and objective evaluation of the public interest and an
informed decision regarding the permission. At the end of the Section 408 process, the Corps chooses to provide or
deny permission for the alteration to the Corps project; the Corps also can attach conditions to its Section 408
permission, including conditions that should be applied to the easement or consent.
EC 1165-2-216 (as drafted in 2015 and updated in 2016) provided some time frames for specific steps within the
agency’s review process; it did not specify guidance on or requirements for a timeline for completing the entire
permission process. EC 1165-2-216 also did not specify that the Corps needed to identify an application as complete
or incomplete. Instead, it indicated that Corps district would work with the applicant to determine the level of detail
necessary to make a decision for a particular request and that the Corps district may request additional information
from the applicant during the agency’s review.
The 114th Congress addressed the agency’s Section 408 permission process in legislation enacted in December 2016.
Specifically, Section 1156 of P.L. 114-322 amended the Section 408 authority to require the Corps to


indicate whether the application is complete within 30 days of receiving the application,



decide on the Section 408 permission or provide a schedule of when the decision would be made within 90 days
of receiving a complete application, and



coordinate its NEPA review of an activity requiring a Section 408 permission with other NEPA reviews related
to that activity (including any review under the agency’s regulatory authorities or led by another agency).



Section 1156 also allowed the Corps to accept and expend funds received from nonfederal public and private
entities to evaluate an alteration or permanent occupation or use of a work built by the United States. In June
2017, the Corps released its implementation guidance for Section 1156. The guidance indicates that EC 1165-2216, which is set to expire on September 30, 2017, is in the process of being revised to include lessons learned
and to implement the changes made in statute in 2016 and 2014 (Section 1007 of P.L. 113-121).
Sources: U.S. Army Corps of Engineers, Policy and Procedural Guidance for Processing Requests to Alter US Army Corps of
Engineers Civil Works Projects Pursuant to 33 USC 408, EC 1165-2-216, September 30, 2015 (updated June 21, 2016);
U.S. Army Corps of Engineers, Implementation Guidance for Section 1007 of the Water Resources Reform and
Development Act of 2014 (WRRDA 2014), Expediting Approval of Modifications and Alterations of Projects by Non-Federal
Interests and Section 1156 of the Water Resources Development Act of 2016 (WRDA 2016), Structures and Facilities
Constructed by Secretary, Memorandum for Distribution, June 2, 2017.

Corps Easements or Consents for Pipelines
Federal agencies, including the Corps, may grant an easement for oil and natural gas pipelines to
cross federal land in accordance with the provisions of Section 28 of the Mineral Leasing Act
(MLA).50 The Corps also can consent to a pipeline crossing non-Corps lands with a Corps real
estate interest (e.g., flowage easement) using a broad, military-wide real estate authority.51
If a Section 408 permission is needed, the easement or consent is contingent upon the granting of
the Section 408 permission.

Congressional Committee Notification
Since 1973, the MLA requires that two congressional authorizing committees—the House Natural
Resources Committee and the Senate Energy and Natural Resources Committee—be notified if
the developer of an oil or natural gas pipeline with a diameter of 24″ or greater is requesting to
cross federal land.52 The Corps also must notify the committees if it intends to grant an easement

50

30 U.S.C. §185.
10 U.S.C. §2668. Corps consents do not grant a right or interest in a property.
52
30 U.S.C. §185(w)(2). The Secretary of the Interior or the head of the federal agency appropriate for the land being
crossed is required to perform this notification. The remainder of this section of the report discusses these requirements
and the related policies of the Corps for Corps-managed, federal lands.
51

Congressional Research Service

16

Oil and Natural Gas Pipelines: Role of the U.S. Army Corps of Engineers

and must provide “detailed findings as to the terms and conditions” to be imposed on the
applicant.53
The MLA is not more specific about what the contents of these notifications, nor does it provide
guidance about when an agency may grant the rights-of-way application in relation to the
committee notification.54 The Corps released a policy guidance memorandum in 2008 for
easements of pipelines that are 24″ or larger.55 The policy direction therein regarding
congressional notification and the granting of the rights-of-way states: “If the Committee does not
provide an affirmative response, [the Corps] District will wait 14 days following Committee
notification before execution of the easement.”56 The Administration can waive this policy-based
waiting period.

Evaluation of Request and Conditions of Easement or Consent
To decide on easements and consents, the Corps follows Chapter 8 of ER 405-1-12, Real Estate
Handbook,57 and Army Regulation (AR) 405-80, Management of Title and Granting Use of Real
Property.58 ER 405-1-12 requires that the Corps find that “the proposed easement will not be
inconsistent with the authorized purposes of the Federal installation or project.”59
According to ER 405-1-12, site-specific environmental, cultural, and operational requirements
may be added to the easement or consent; also, the Corps is to impose any special requirements
for safe operation of a pipeline or related facilities.60 For example, according to the Corps, the
Lake Oahe easement for DAPL “contains 36 conditions that are intended to further mitigate risk
of rupture at the Lake Oahe crossing,” including specific coatings to prevent corrosion, corrosion
53

Ibid.
In 1990, P.L. 101-475 removed a requirement for a waiting period following congressional notification (emphasis
added):
The Secretary or agency head shall notify the House and Senate Committees on Interior and Insular
Affairs promptly upon receipt of an application for a right-of-way for a pipeline twenty-four inches
or more in diameter, and no right-of-way for such a pipeline shall be granted until sixty days (not
counting days on which the House of Representatives or the Senate has adjourned for more than
three days) after a notice of intention to grant the right-of-way, together with the Secretary’s or
agency head’s detailed findings as to terms and conditions he proposes to impose, has been
submitted to such committees, unless each committee by resolution waives the waiting period.
H. Rpt. 101-833 and S. Rpt. 101-471 provide information on the congressional discussion surrounding these changes.
The congressional notification and waiting period had been added in 1973, as part of the amendments to the Minerals
Leasing Act (30 U.S.C. §185(w)(2)) made in legislation.
55
Letter from Scott L. Whiteford, Acting Director of Real Estate, Corps Real Estate Policy Guidance Letter No. 27,
October 29, 2008. Hereinafter Corps Real Estate Policy Guidance Letter No. 27.
56
Corps Real Estate Policy Guidance Letter No. 27 also states that “If the pipeline only crosses an area held in less than
fee, such as an easement, then the [Corps] District will follow the process to consent to the fuel-carrying pipeline. No
notice to Congress is required for a Consent.”
57
U.S. Army Corps of Engineers, Real Estate Handbook, Engineer Regulation (ER) 405-1-12, Washington, DC,
September 30, 1994.
58
These guidance documents do not specify a time frame within which the Corps is to complete its process for granting
or denying a request for an easement or consent. Department of the Army, Management of Title and Granting Use of
Real Property, Army Regulation 405-80, Washington, DC, October 10, 1997, at http://usahec.contentdm.oclc.org/cdm/
ref/collection/p16635coll11/id/1556/.
59
According to ER 405-1-12, the district engineer of the Corps district in which the pipeline easement application is
being reviewed will provide notice and a public hearing where appropriate; however, no further hearings are required if
the pipeline proposal has been scrutinized through NEPA procedures or other hearings held by federal or state agencies.
60
ER 405-1-12, pp. 8-110 and 8-113.
54

Congressional Research Service

17

Oil and Natural Gas Pipelines: Role of the U.S. Army Corps of Engineers

surveys after installation, more stringent enforcement of the pipeline’s oil spill facility response
plan, mainline valve and automatic shutdown requirements, and measures for initial and ongoing
leak and crack detection.61
If the Corps finds that the pipeline is not inconsistent with the authorized purposes of the Corps
project and its lands, the Corps signs a real estate instrument that grants the easement.62 If the
pipeline crosses lands administered by the Corps and at least one other federal agency, the
Secretary of the Interior is authorized, after consultation with the agencies involved, to grant or to
deny the easement.63 Each agency head remains responsible for administering and enforcing the
easements, as they involve lands under the agency head’s jurisdiction.

Illustration of Corps Approval Processes for Pipelines at Corps
Projects and Real Estate
Figure 2 illustrates the relationship between the Section 408 permission, the real estate or consent
process, and the MLA congressional notification requirements for proposed pipelines. The
Section 408 permission process is shown in the grey boxes on the left side of Figure 2. The
process to grant or deny the easement or consent is shown in the tan boxes on the right side of
Figure 2. The MLA notification requirements are shown in the green boxes in Figure 2.

61

U.S. Army Corps of Engineers’ Opposition to Standing Rock Sioux Tribe’s Motion for Partial Summary Judgment
and Cross Motion for Partial Summary Judgment at 9, Standing Rock Sioux Tribe v. U.S. Army Corps of Engineers,
No. 16-1534 (D.D.C. filed July 27, 2016), ECF No. 172.
62
According to ER 405-1-12, the Assistant Secretary of the Army for Installations, Energy, and Environment executes
easements for pipelines 24 inches in diameter or larger. The use of not inconsistent (rather than a determination of
consistency) reflects the language used in the underlying authority at 33 U.S.C. §408.
63
For example, the Bureau of Land Management (BLM) on behalf of the Secretary of the Interior renewed in 2011 the
easement for the natural gas pipeline owned by the Northern Border Pipeline Company to cross the same Corps lands
on the Missouri River as DAPL; the renewal also included easements to cross U.S. Forest Service and BLM lands.

Congressional Research Service

18

Oil and Natural Gas Pipelines: Role of the U.S. Army Corps of Engineers

Figure 2. Major Steps in Corps Approval Processes
for Pipeline Segments Crossing Corps Projects and Real Estate Interests

Source: CRS.
Notes: Corps land refers to Corps-managed federal land. House NR = House Natural Resources Committee;
Senate ENR = Senate Energy and Natural Resources Committee. Information within parentheses refers to the
U.S. Code (U.S.C.) for the guiding statutory authority or to Corps documents, including Engineer Circulars (EC),
Engineer Regulations (ER), and Army Regulations (AR).

Congressional Research Service

19

Oil and Natural Gas Pipelines: Role of the U.S. Army Corps of Engineers

Compliance with Other Federal Statutes During Corps Civil
Works Processes
As part of the process of granting an easement or consent, the Corps must comply with federal
statutes. The Corps typically evaluates this compliance as part of its NEPA documentation. For a
request that requires both a Section 408 permission and an easement or consent by the Corps, the
NEPA document is produced as part of the technical review for the Section 408 permission. As
part of the technical review process, the Corps documents and demonstrates that it has gathered
relevant information from the pipeline developer and that it has analyzed that and any additional
information necessary to determine what federal requirements may apply to the Corps’ actions.
During that process, the Corps determines the resources potentially affected by granting the
permission and easement or consent, and it determines whether the impacts to those resources
would trigger actions necessary for compliance with other federal laws, such as Section 106 of
NHPA and Section 7 of ESA, among others.64

Compliance with Federal Statutes
As previously noted, Corps regulatory actions and civil works actions may be subject to other
federal statutes, such as NEPA, NHPA, and ESA.65 Part of the compliance may include
consultation or input from other entities. Table 1 lists selected federal laws that, if applicable to a
Corps pipeline-related action, may require the Corps to consult with relevant state or tribal
entities or with other federal agencies. Most requirements listed in the table are limited to actions
taken by federal agencies. For example, an oil pipeline constructed on private land that does not
require a federal agency approval (e.g., a pipeline that does not cross Corps jurisdictional waters
or federal lands) would not be subject to NEPA or NHPA.
Table 1. Selected Federal Laws That Require Outside Agency Review
(additional laws often applicable to activities authorized by the Corps)
Law/Requirement

Description/Agency Consultation Requirement

National Environmental
Policy Act
(NEPA; 42 U.S.C.
§§4321 et seq.)

Requires federal agencies to identify and consider the potential impacts of their
proposed actions (e.g., a proposed rulemaking or an applicant’s request to approve a
specific project) and to inform the public of those impacts before making a final
decision whether to proceed with the action. When preparing the necessary NEPA
analysis, the Corps (the lead agency) must request comments and other assistance
from any other federal agencies (cooperating agencies) that have jurisdiction by law or
special expertise with respect to any environmental impact involved in a proposal.
Cooperating agencies may include state and tribal agencies.

Section 106 of the
National Historic
Preservation Act, as
amended
(NHPA; 54 U.S.C.
§306108)

Requires federal agencies to take into account the effects that activities they may
authorize are likely to have on historic properties listed in, or eligible for listing in, the
National Register of Historic Places. Agencies must consult with state historic
preservation officers (SHPOs) and tribal historic preservation officers (THPOs) and,
for certain proposed activities, the Advisory Council on Historic Preservation.

64

The Corps also may be required to or may follow policies that result in the agency taking steps to address tribal
treaties and tribal trust responsibilities; however, as discussed in footnote 5, these tribal topics are largely not within the
scope of this report.
65
Although executive orders, regulations, and executive branch policies also may result in the Corps taking certain
actions, the discussion herein is limited primarily to requirements associated with statute.

Congressional Research Service

20

Oil and Natural Gas Pipelines: Role of the U.S. Army Corps of Engineers

Law/Requirement

Description/Agency Consultation Requirement

Section 7 of the
Endangered Species
Act, as amended
(ESA; 16 U.S.C. §1536)

Requires federal agencies to consult with the Department of the Interior’s Fish and
Wildlife Service or the National Marine Fisheries Service, as appropriate, to determine
whether an activity that a federal agency may authorize “may affect” a species listed or
proposed for listing as threatened or endangered under ESA. No activity may be
authorized by the Corps that is likely to jeopardize the continued existence of such a
species or to destroy or adversely modify its critical habitat. After the consultation,
the Corps may add special conditions to its permit or approval to ensure that the
activity does not jeopardize endangered or threatened species or destroy or adversely
modify critical habitat.

Section 401 of the
Clean Water Act, as
amended
(33 U.S.C. §1341)

Requires a permit applicant to obtain a water quality certification from the U.S.
Environmental Protection Agency or an authorized state or tribal agency if the activity
subject to permitting may result in the discharge of a pollutant into waters of the
United States. The certification specifies any conditions the permittee must meet to
ensure compliance with applicable effluent limitations and water quality standards. No
nationwide permit or other Corps permit can be authorized until the activity receives
a water quality certification from the authorized agency within a reasonable period of
time (which shall not exceed one year) or the agency waives certification.a

Coastal Zone
Management Act of
1972, as amended
(CZMA, 33 U.S.C
§1456)

If the proposed activity is located or would affect the coastal zone of a state with a
coastal zone management program approved by the Secretary of Commerce, Section
307(c) of the CZMA, as amended, requires that the applicant must furnish a
consistency concurrence that the proposed project is in compliance with the state’s
approved coastal zone management program. The state’s concurrence with the
applicant’s certification should be obtained prior to the issuance of the Corps permit.b

Source: CRS.
a. Under the nationwide permits (NWPs), the Corps district engineer may issue a provisional verification for
an activity that requires a Section 401 certification, but the activity is not authorized until the Section 401
water quality certification or waiver is obtained.
b. Under the NWPs, the Corps district engineer may issue a provisional verification for an activity that
requires CZMA consistency, but the activity is not authorized until the CZMA consistency concurrence or
the presumption of concurrence is obtained.

As shown in Table 1, federal licenses and approvals, such as Corps individual permits, generally
are conditioned on the permittee obtaining a state or tribal water quality certification pursuant to
Section 401 of the Clean Water Act and a state or tribal consistency concurrence pursuant to the
Coastal Zone Management Act.66 For the NWPs, compliance with Section 401 of the Clean Water
Act is accomplished by satisfying GC 25. The state or tribe can certify all activities authorized by
an NWP or require that verifications of certain activities under an NWP obtain state or water
quality certification. The state or tribe can approve, deny, or condition its certification. Although
the Corps is not part of the process for the permittee to obtain a state or tribal water quality
certification, the denial of a water quality certification can affect the Corps’ regulatory
authorizations for pipelines. For example, the developer of the Northern Access Pipeline to
transport natural gas from Pennsylvania to New York has planned on using the NWP 12 for 276
wetland and 192 stream crossings. In April 2017, the New York State Department of
Environmental Conservation (NYSDEC) denied the state water quality certification pursuant for
the April 2016 application for the 94-mile pipeline.67 Until the pipeline developer complies with
66

For the NWPs, Coastal Zone Management Act of 1972, as amended (CZMA, 33 U.S.C §1456) compliance is
pursued through GC 26 on coastal zone management. The state can provide a consistency concurrence to all activities
authorized by an NWP or require that verifications of certain activities under an NWP obtain a consistency
concurrence. The state can approve, deny, or condition its concurrence.
67
For the notice and explanation of the state’s denial of this water quality certification, see letter from John Ferguson,
(continued...)

Congressional Research Service

21

Oil and Natural Gas Pipelines: Role of the U.S. Army Corps of Engineers

Section 401 of the Clean Water Act, the Corps will be unable to allow the permittee to proceed in
New York under NWP 12 because of the permit’s GC 25 on water quality. Individual permits also
require state water quality certification. The pipeline developer can address the concerns that led
to the NYSDEC denial and submit a new application to NYSDEC for a state water quality
certification or pursue a public hearing within 30 days of the denial consistent with New York
regulations.68 A detailed discussion of how state approvals, and the state water quality
certification in particular, may affect federal approvals for pipelines is beyond the scope of this
report.
The remainder of this section addresses two agency-specific procedures that the Corps has
adopted for its regulatory program: NEPA procedures and historic properties procedures.

Agency-Specific Procedures of the Corps Regulatory Program
The Corps regulations implementing the agency’s regulatory program include procedures to
implement NEPA and to provide for the protection of historic properties.69 Those procedures
reveal the agency’s interpretation of the limits to its jurisdiction; that is, the procedures reflect that
the Corps interprets its regulatory authorities under Section 404 and Section 10 as not extending
to private actions upland of regulated waters.

Corps NEPA Procedures
NEPA requires federal agencies to identify and consider the environmental impacts of an action
before a final decision is made about that action. Regulations implementing NEPA were
promulgated by the Council on Environmental Quality (CEQ).70 Those regulations identify
federal actions subject to NEPA to include those over which a federal agency has some control or
responsibility.71 Each federal agency was required to adopt the CEQ regulations, supplement
them as necessary to include procedures relevant to that agency’s authority, and ensure that those
(...continued)
Chief Permit Administrator, New York State Department of Environmental Conservation, to National Fuel Gas Supply
Corporation and Empire Pipeline, Inc., April 7, 2017, at http://www.dec.ny.gov/docs/permits_ej_operations_pdf/
northaccesspipe42017.pdf. In 2016, the New York State Department of Environmental Conservation (NYSDEC) also
denied the state water quality certification for the Constitution Pipeline (John Ferguson, Chief Permit Administrator,
New York State Department of Environmental Conservation, to Constitution Pipeline Company, LLC, April 22, 2016,
at http://www.dec.ny.gov/docs/administration_pdf/constitutionwc42016.pdf). In 2017, NYSDEC established a special
condition for the use of the NWP 12 during its five-year term from 2017 to 2022 in the state; the condition is
Utility Line activities that cross multiple waterbodies or cross the same waterbody at multiple
locations, while viewed as multiple ‘single and complete’ projects for the purposes of the
Nationwide Permit program, will be considered by the Department as a single project for all
crossings for the entire length of the project in New York State for the purpose of obtaining Water
Quality Certification from New York State and determining the disturbance threshold of 300 linear
feet or ¼ acre.
(Letter from Kent P. Sanders, Deputy Chief Permit Administrator, New York State Department of Environmental
Conservation, to Stephan A. Ryba, Chief Regulatory Branch, U.S. Army Corps of Engineers, March 7, 2017, at
http://www.dec.ny.gov/docs/permits_ej_operations_pdf/wqcnwp2017.pdf.)
68
Each state develops its own processes for addressing appeals related to denials or required conditions of state water
quality certifications.
69
33 C.F.R. Part 325.
70
See Council on Environmental Quality, “Regulations for Implementing the Procedural Provisions of the National
Environmental Policy Act,” in 40 C.F.R. Parts 1500-1508 (43 Federal Register 55990, November 28, 1978).
71
See 40 C.F.R. §1508.18.

Congressional Research Service

22

Oil and Natural Gas Pipelines: Role of the U.S. Army Corps of Engineers

procedures implementing NEPA are integrated into the agency’s broader decisionmaking
procedures.72 The Corps adopted and supplemented the CEQ regulations in its own Procedures
for Implementing NEPA.73 Further, the Corps provides additional procedural guidance for
preparing and processing NEPA documents for regulatory actions in Appendix B to the
regulations implementing its regulatory program.74
Under NEPA, a project known to have a significant impact on the environment requires the
preparation of an environmental impact statement (EIS). When impacts are uncertain, an
environmental assessment (EA) is prepared to determine if an EIS is needed or a finding of no
significant impacts (FONSI) may be issued. The Corps has identified “regulatory actions” (i.e.,
issuance of a permit) among the actions that normally require an EA but not necessarily an EIS.75
The Corps does not require NEPA review for individual NWP verifications.76 Instead, to date, the
federal action subject to NEPA has been issuance of NWP 12. During the public rulemaking for
each of these five-year permits, NEPA compliance has involved preparation of an EA that resulted
in Corps issuance of a final decision document (its version of a FONSI).77 The Corps EA/decision
document for NWP 12 has been prepared, in part, to identify conditions that must be met to
ensure that authorization via an NWP is appropriate. Part of the process to develop the decision
document is the identification of general conditions to ensure that activities related to a single and
complete project will have minimal adverse environmental effects (i.e., no significant impacts
that would require the preparation of an EIS).
Understanding the scope of Corps NEPA reviews is useful in recognizing how far upland the
Corps will evaluate the impacts of a larger project (e.g., a pipeline that extends beyond Corpsregulated waters). As noted, under NEPA, the Corps is required to evaluate the impacts of an
action over which it has control and responsibility. Depending on the details of the activity
subject to Corps approval, the agency’s interpretation of the extent of its control and
responsibility over a proposed action will dictate the geographic area over which environmental
impacts are evaluated (i.e., how far upland from regulated waters the agency will review the
impacts of a larger project).78 For a discussion of the geographic limits of Corps environmental
reviews for pipelines, see the box titled “Geographic Limits of Corps Environmental Reviews.”

72

See directives included in 40 C.F.R. §§1505.1 and 1507.3.
33 C.F.R. Part 230.
74
Specifically, “NEPA Implementation Procedures for the Regulatory Program” in Appendix B to 33 C.F.R. Part 325.
75
33 C.F.R. §230.7(a).
76
82 Federal Register 1861, January 6, 2017.
77
All “2017 Nationwide Permit Final Decision Documents” are available at http://www.usace.army.mil/Missions/
Civil-Works/Regulatory-Program-and-Permits/Nationwide-Permits/2017_NWP_FinalDD/.
78
See requirements applicable to “scope of analysis” associated with an “EA/FONSI document” in 33 C.F.R. Part 325,
Appendix B(7)(b). Specifically, see the typical factors to be considered in determining whether sufficient control and
responsibility exists in Appendix B(7)(b)(2), including the discussion of the extent of federal control and
responsibility—“Federal control and responsibility will include the portions of the project beyond the limits of Corps
jurisdiction where the cumulative Federal involvement of the Corps and other Federal agencies is sufficient to grant
legal control over such additional portions of the project”—and examples in Appendix B(7)(b)(3), such as “[f]or those
regulated activities that comprise merely a link in a transportation or utility transmission project, the scope of analysis
should address the Federal action, i.e., the specific activity requiring a DA [Department of Army] permit and any other
portion of the project that is within the control or responsibility of the Corps of Engineers (or other Federal agencies).”
73

Congressional Research Service

23

Oil and Natural Gas Pipelines: Role of the U.S. Army Corps of Engineers

Geographic Limits of Corps Environmental Reviews
Whether an entire pipeline or activities associated with segments of a pipeline are subject to federal authorization or
approval shapes how a federal agency scopes its environmental review. This is sometimes referred to as the extent to
which the project is federalized, particularly for purposes of complying with the National Environmental Policy Act
(NEPA). Some of the controversy over the actions of the Corps related to pipelines stems from the limits of the
agency’s authorities. When an agency has a limited role in a private action the federal authority is sometimes
characterized as a small federal handle. That term refers to the limits of federal authority related to projects that are
largely nonfederal but become partially federalized because some aspect of the project is subject to a federal permit
or approval. In contrast, as previously noted, the Federal Energy Regulatory Commission (FERC) is authorized to
approve interstate natural gas pipelines; therefore, in its evaluation, FERC must identify and consider the impacts of
the entire pipeline.
A privately funded linear project, such as an oil pipeline, built largely on nonfederal land is an example of a project
with a small federal handle for the Corps. For example, the Corps interprets its permitting authority under Section
404 of the Clean Water Act and Section 10 of the Rivers and Harbors Act of 1899 to mean that it is required to
evaluate the environmental impacts of only those activities associated with the geographically discrete segments of the
pipeline related to regulated waters and wetlands. Generally, the review by the Corps does not encompass private
activity outside the scope of the sum of the geographically limited federal authorizations. A 2015 court decision
related to Flanagan South oil pipeline’s more than 2,000 water crossings authorized under NWP 12—Sierra Club v.
U. S. Army Corps of Engineers, 803 F.3d 31, 34 (D.C. Cir. 2015)—stated:
We hold that the federal government was not required to conduct NEPA analysis of the entirety of the
Flanagan South pipeline, including portions not subject to federal control or permitting. The agencies’
respective regulatory actions—in the form of easements, Clean Water Act verifications, and authorization
to harm or kill members of endangered species without incurring liability under the Endangered Species Act
(ESA)—were limited to discrete geographic segments of the pipeline comprising less than five percent of its
overall length. As explained below, the agencies were required to conduct NEPA analysis of the foreseeable
direct and indirect effects of those regulatory actions. However, on the facts of this case, the agencies were
not obligated also to analyze the impact of the construction and operation of the entire pipeline.

Corps Procedures for Protecting Historic Properties
The Corps established “Procedures for the Protection of Historic Properties” in Appendix C to its
regulations applicable to Department of the Army permits.79 The Corps follows Appendix C to
fulfill the procedural requirements set forth in NHPA, other applicable historic preservation laws,
and presidential directives as they relate to the Corps regulatory program.
Section 106 of NHPA provides that federal agencies, prior to expending federal funds or granting
a license to any undertaking over which they have direct or indirect jurisdiction, must “take into
account the effect of [the] undertaking on any historic property.”80 If historic properties might be
79

33 C.F.R. Part 325, Appendix C; also see U.S. Army Corps of Engineers, “Revised Interim Guidance for
Implementing Appendix C of 33 C.F.R. Part 325 with the Revised Advisory Council on Historic Preservation
Regulations at 36 C.F.R. Part 800,” April 25, 2005, at http://www.usace.army.mil/Portals/2/docs/civilworks/regulatory/
techbio/InterimGuidance_25apr05.pdf; and U.S. Army Corps of Engineers, “Clarification of Revised Interim Guidance
for Implementing Appendix C of 33 C.F.R. Part 325 with the Revised Advisory Council on Historic Preservation
Regulations at 36 C.F.R. Part 800 Dated 25 April 2005,” January 31, 2007, at http://www.usace.army.mil/Portals/2/
docs/civilworks/regulatory/inter_guide2007.pdf. The Corps uses its own procedures for the regulatory program, rather
than the standard procedures for complying with Section 106, which are established in Subpart B of the Advisory
Council on Historical Preservation (ACHP) Section 106 regulations (36 C.F.R. Part 800). See footnote 81 for more
information.
80
P.L. 89-665, as amended; 54 U.S.C. §306108. The law defines a historic property as “any prehistoric or historic
district, site, building, structure, or object included on, or eligible for inclusion on, the National Register [of Historic
Places], including artifacts, records, and material remains relating to the district, site, building, structure, or object” (54
U.S.C. §300308). The Section 106 regulations promulgated by ACHP add to this definition by stating that “[t]he term
includes properties of traditional religious and cultural importance to an Indian tribe or Native Hawaiian organization
and that meet the National Register criteria” (36 C.F.R. §800.16(l)(1)).

Congressional Research Service

24

Oil and Natural Gas Pipelines: Role of the U.S. Army Corps of Engineers

affected, the agency must consult with the state historic preservation officer or tribal historic
preservation officer, as applicable, about alternatives to avoid, minimize, or mitigate adverse
effects to those properties.81 The Advisory Council on Historical Preservation (ACHP), an
independent federal agency established under NHPA to promote and advise on historic
preservation,82 also may be involved in consultations under certain circumstances.83
Procedures for NHPA Section 106 compliance for the regulatory program of the Corps have been
the subject of disagreements with the ACHP and some other stakeholders. According to 2016
ACHP communications to the Corps, the ACHP has not accepted the Corps procedures as being
consistent with ACHP regulations.84 Some federal district courts have declined to apply the
agency’s procedures, on the bases of inconsistency with NHPA or non-approval by the ACHP;85
however, others have cited or applied the Corps procedures.86
The ACHP has objected particularly to the decision by the Corps to review each water crossing
by a linear project, such as a pipeline, as a separate undertaking.87 The ACHP regulations define
an “undertaking” as “a project, activity, or program funded in whole or in part under the direct or
indirect jurisdiction of a Federal agency, including those carried out by or on behalf of a Federal
agency; those carried out with Federal financial assistance; and those requiring a Federal permit,
license or approval.”88 The ACHP contends that this definition would in many cases require the
81

36 C.F.R. Part 800. These regulations implementing Section 106 are promulgated by the ACHP under 54 U.S.C.
§304108(a).
82
A description of the council’s duties is at 54 U.S.C. §304102.
83
NHPA Section 106 does not require an agency to ensure that adverse effects to historic properties are avoided; the
agency is required only to consult on potential alternatives. However, regulations implementing Section 106 (36 C.F.R.
§800.6) discuss potential ways to resolve situations in which adverse effects may occur, such as through a
memorandum of agreement among the agency and other stakeholders on a plan to minimize damage to the historic
property.
84
See, for example, letter from the ACHP to Jo-Ellen Darcy, Assistant Secretary of the Army for Civil Works, August
19, 2016, at http://www.achp.gov/docs/asadarcy.pdf. Under 36 C.F.R. §800.14, agencies are allowed to develop their
own procedures for complying with Section 106, but those procedures must be consistent with the ACHP’s regulations
and must be approved by the ACHP. More specifically, Subpart C of the regulations establishes five program
alternatives that federal agencies may use to meet their obligations under Section 106. One of these program
alternatives is the development of alternate procedures, whereby agencies may “develop procedures to implement
Section 106 and substitute them for all or part of” the ACHP rules, “if they are consistent with the Council’s
regulations” (36 C.F.R. §800.14(a)). The agency official must submit the proposed alternate procedures to the ACHP
for a 60-day review period; if the ACHP finds them to be “consistent” with the ACHP regulations, the alternate
procedures may be adopted in lieu of the standard regulations (36 C.F.R. §800.14(a)(2)).
85
See, for example, Sayler Park Vill. Council v. U.S. Army Corps of Eng’rs, 2002 U.S. Dist. LEXIS 26208, *23-24
(S.D. Ohio 2002) (finding that “the Corps Interim Guidance is inconsistent with the ACHP Interim Guidance and
irrelevant”); Comm. to Save Cleveland’s Huletts v. U.S. Army Corps of Eng’rs, 163 F. Supp. 2d 776, 792 (N.D. Ohio
2001) (holding that the Corps “cannot rely on its own regulations to define the scope of its notice obligations or to
define the ‘permit area’”). See also, for example, McGee v. U.S. Army Corps of Eng’rs, No. 3:11-CV-160-H, 2011
U.S. Dist. LEXIS 56652, at *16-17 (W.D. Ky. May 23, 2011) (recognizing “possibility of conflict” between the two
sets of regulations but finding no conflict under the circumstances).
86
See, for example, Standing Rock Sioux Tribe v. U.S. Army Corps of Eng’rs, 205 F. Supp. 3d 4 (D.D.C. 2016) (“[I]t
falls squarely within the expertise of the Corps, not the Advisory Council, to determine the scope of the effects of
construction activities at U.S. waterways.”); Abenaki Nation of Mississquoi v. Hughes, 805 F. Supp. 234, 251 (D. Vt.
1992) (“Procedurally the Corps is in technical violation.... However, this violation is not fatal, given the NHPA’s
permission that its regulations ‘may be implemented in a flexible manner.’”).
87
CRS personal communication with the ACHP, March 27, 2017; and ACHP, “Section 106 Reviews for United States
Army Corps of Engineers Permits and Undertakings with Small Federal Handles,” November 2015, at
http://www.achp.gov/docs/fapc.pdf.
88
36 C.F.R. §800.16(y).

Congressional Research Service

25

Oil and Natural Gas Pipelines: Role of the U.S. Army Corps of Engineers

Corps to conceive of the “undertaking” as broader than a single water crossing. The approach
used by the Corps, the ACHP states, “dismiss[es] the potential for effects to historic properties
that may be located within the broader project area of an undertaking when properly defined
under the Section 106 regulations.”89 The Corps maintains that its procedures for historic
properties in Appendix C satisfy the requirements of NHPA Section 106.90 The Corps explained
its interpretation of an undertaking related to pipelines as follows:
For oil pipelines and other utility lines, the activities that are subject to the Corps’
regulatory authorities and require DA [Department of Army] authorization are crossings
of jurisdictional waters and wetlands, as well as utility line substations, foundations for
overhead utility lines, and access roads, that involve discharges of dredged or fill material
into waters of the United States or structures or work in navigable waters of the United
States. Segments of an oil pipeline or other utility line in upland areas outside of the
Corps’ jurisdiction, or attendant features constructed in upland areas, do not require DA
authorization and therefore are not, for the purposes of the Corps’ compliance with
section 106 of the NHPA, “undertakings.” The Corps does not have direct or indirect
jurisdiction over pipeline segments in upland areas. The Corps does not regulate oil
pipelines, or other utility lines per se; we only regulate those components of oil pipelines
or other utility lines, that involve activities regulated under our authorities (i.e., section
404 of the Clean Water Act and section 10 of the Rivers and Harbors Act of 1899).91

The Corps indicates in this statement its position that the agency has neither direct nor indirect
jurisdiction over the entire pipeline and that its control does not extend to areas upland of
regulated waters.92 The essence of this interpretation was adopted by one district court, the U.S.
District Court for the District of South Dakota, in Standing Rock Sioux Tribe v. U.S. Army Corps
of Engineers.93 However, as noted above, other district courts have declined to apply other
elements of the agency’s procedures on the basis of inconsistency with NHPA or lack of approval
by the ACHP.94

89

Letter from the ACHP to Jo-Ellen Darcy, Assistant Secretary of the Army for Civil Works, August 19, 2016, at
http://www.achp.gov/docs/asadarcy.pdf. The ACHP did not specify in its letter whether the “broader project area”
would encompass an entire pipeline or a more broadly defined area around each water crossing.
90
See, for example, Federal Defendants’ Opposition to Plaintiff-Appellant’s Emergency Motion for Injunction Pending
Appeal at 9 and 10, Standing Rock Sioux Tribe v. U.S. Army Corps of Engineers, No. 16-5259 (D.D.C. Court of
Appeals filed September 14, 2016), ECF No. 1635700.
91
NWP 12 Decision Document, p. 18.
92
33 C.F.R. §325 Appendix C, in Section (2)(c), states:
The district engineer will take into account the effects, if any, of proposed undertakings on historic
properties both within and beyond the waters of the U.S. Pursuant to Section 110(f) of the NHPA,
the district engineer, where the undertaking that is the subject of a permit action may directly and
adversely affect any National Historic Landmark, shall, to the maximum extent possible, condition
any issued permit as may be necessary to minimize harm to such landmark (emphasis added).
Appendix C (5)(f) provides additional detail in this paragraph:
The Corps of Engineers’ responsibilities to seek eligibility determinations for potentially eligible
historic properties is limited to resources located within waters of the U. S. that are directly affected
by the undertaking. The Corps responsibilities to identify potentially eligible historic properties is
limited to resources located within the permit area that are directly affected by related upland
activities. The Corps is not responsible for identifying or assessing potentially eligible historic
properties outside the permit area, but will consider the effects of undertakings on any known
historic properties that may occur outside the permit area.
93
205 F. Supp. 3d 4, 30-32 (D.D.C. 2016).
94
See footnote 85 and accompanying text.

Congressional Research Service

26

Oil and Natural Gas Pipelines: Role of the U.S. Army Corps of Engineers

Separately, stakeholders have raised concerns about the Corps’ procedures whereby the permit
applicant, rather than the Corps itself, is responsible for identifying historic properties that may be
affected by a pipeline activity under an NWP. The ACHP regulations specify that “[i]t is the
statutory obligation of the Federal agency to fulfill the requirements of section 106,” including
identification of historic properties that may be affected by an undertaking.95 For pipeline
activities that occur under NWP 12, GC 20 provides that the Corps must initiate Section 106
review and consultation when an applicant identifies historic properties in a PCN.96 Once a PCN
is submitted, the activity cannot proceed until the Corps district engineer completes a site-specific
analysis and verifies either that the activity will not affect any eligible historic site or that the
consultations required by NHPA are complete. However, the Corps does not undertake the
analysis unless the project applicant raises the issue through a PCN. For pipeline activities that
require individual permits, by contrast, the Corps district engineer is responsible for identifying
historic properties that may be affected by the permitted activity and completing consultations as
necessary.

Policy Issues Raised by Corps’ Pipeline Roles
and Decisions
Growth in North American crude oil and natural gas production has led to efforts to expand the
domestic oil and natural gas pipeline network. Pipeline construction and operation may impact
the environment, human health, and welfare. The interest in expanding the domestic pipeline
network and the concerns about the local, regional, and national effects of pipeline construction
and operation have raised policy questions about how the Corps’ regulatory authorities and civil
works processes may influence the development and approval of pipelines and their routes. The
Corps is authorized as part of its regulatory program to regulate certain pipeline activities that
may affect certain waters and wetlands; it also is authorized to grant permissions, easements, and
consents for pipeline segments that cross Corps water resources projects and associated lands.
These Corps roles in pipelines are not without controversy. Some of the issues raised center on
the following policy questions:






Impacts. How does the Corps determine the geographic area for its evaluations
of impacts on the environment, historic properties and cultural resources,
communities, and specific population groups? How does the Corps evaluate
cumulative impacts?
Limits of Agency Authority. When a pipeline is largely a nonfederal
undertaking and the federal role is limited to discrete segments, to what extent
should the federal government shape siting and other aspects of the pipeline?
Risk and Safety. To what extent is the Corps authorized to address oil and
natural gas pipeline safety (e.g., risk of spills) as part of its regulatory
authorizations and civil works decisions? How are low-probability, highconsequence safety risks considered and addressed in the Corps’ decisionmaking
processes?

95

36 C.F.R. §800.2.
The permit applicant may seek the assistance of a state historic preservation officer or tribal historic preservation
officer and may consult the National Register of Historic Places to identify relevant properties that either are on the
register or may be eligible for listing.
96

Congressional Research Service

27

Oil and Natural Gas Pipelines: Role of the U.S. Army Corps of Engineers





Public Interest. How does the Corps arrive at and document its assessment of
public interest in its pipeline-related regulatory and civil works activities? That
is, how are anticipated costs and benefits (both monetized and non-monetized)
for one group weighed relative to costs and benefits for another group, and how
is the national public interest considered?
General Permits. How does the use of general permits (rather than individual
permits) for Corps-regulated pipeline segments affect the agency’s review of
proposed water crossings, the information available to stakeholders and the
public, and compliance with the requirements of NHPA?

An extensive discussion of each of these questions is beyond the scope of this report. Many of
these questions are not unique to pipelines or to the Corps; that is, many of them have been the
subject of past (and ongoing) court cases related to other Corps approvals or to similar actions by
other federal agencies. As Congress considers the Corps’ current and future roles and the federal
role in pipelines more broadly, these questions reflect some of the basic debates about federal
actions associated with private infrastructure.

Author Contact Information
(name redacted)
Specialist in Natural Resources Policy
[redacted]@crs.loc.gov
, 7-....

(name redacted)
Analyst in Natural Resources Policy
[redacted]@crs.loc.gov
, 7-....

(name redacted)
Analyst in Environmental Policy
[redacted]@crs.loc.gov
, 7-....

(name redacted)
Specialist in Energy and Infrastructure Policy
[redacted]@crs.loc.gov , 7-....

Acknowledgments
Prior to her retirement from CRS, (name redacted) ( former Senior Specialist in Environmental Policy)
made major contributions to this report, especially the discussion of the regulatory program of the Corps.
(name redacte d)
and (name redacted)
in the American Law Division of CRS also provided assistance to the
authors.

Congressional Research Service

28

EveryCRSReport.com
The Congressional Research Service (CRS) is a federal legislative branch agency, housed inside the
Library of Congress, charged with providing the United States Congress non-partisan advice on
issues that may come before Congress.
EveryCRSReport.com republishes CRS reports that are available to all Congressional staff. The
reports are not classified, and Members of Congress routinely make individual reports available to
the public.
Prior to our republication, we redacted names, phone numbers and email addresses of analysts
who produced the reports. We also added this page to the report. We have not intentionally made
any other changes to any report published on EveryCRSReport.com.
CRS reports, as a work of the United States government, are not subject to copyright protection in
the United States. Any CRS report may be reproduced and distributed in its entirety without
permission from CRS. However, as a CRS report may include copyrighted images or material from a
third party, you may need to obtain permission of the copyright holder if you wish to copy or
otherwise use copyrighted material.
Information in a CRS report should not be relied upon for purposes other than public
understanding of information that has been provided by CRS to members of Congress in
connection with CRS' institutional role.
EveryCRSReport.com is not a government website and is not affiliated with CRS. We do not claim
copyright on any CRS report we have republished.

---

Source: Frix Law Library, https://www.frixlaw.com/law-library/documents/crs%3AR44880. Public record. Not legal advice.
