# Petition for Writ of Certiorari — Boeing Co., The v. United States, (2009) (No. 1302)

> Briefs, arguments, decisions, and more.

URL: https://www.frixlaw.com/law-library/documents/brief%3Amicro_IA43085015_0591%3A02

## Record

- **Collection:** Supreme Court brief
- **Document type:** Petition for Writ of Certiorari
- **Published:** January 1, 2009

## Text

Supreme Court, U.S.
FILED

ie. 091302 APR 23 200
OFFICE OF THE CLERK
Bn Whe
Joupreme Court of the Anited tates
*

THE BOEING COMPANY,

Petitioner,

v.
UNITED STATES OF AMERICA,
Respondent.

S

On Petition For A Writ Of Certiorari
To The United States Court Of Appeals
For The Federal Circuit

.

PETITION FOR A WRIT OF CERTIORARI
AND APPENDIX VOLUME I

+
J. MICHAEL LUTTIG CHARLES .J. COOPER
Executive Vice President Counsel of Record
& General Counsel MICHAEL W. KIRK
GRANT M. DIXTON HOWARD C. NIELSON, JR.
LYNDA GUILD SIMPSON DAVID LEHN
Tue BOEING COMPANY COOPER AND KIRK, PLLC
100 North Riverside 1523 New Hampshire Ave., N.W.
Chicago, IL 60606 Washington, D.C. 20036
(312) 544-2800 (202) 220-9600

(202) 220-9601 (fax)
ccooper@cooperkirk.com

Counsel for

April 23, 2010 The Boeing Company

COCKLE LAW BRIEF PRINTING CO (800) 225-6964
OR CALL COLLECT (402) 342-2831

QUESTIONS PRESENTED

1. Whether the Due Process Clause of the Fifth
Amendment permits an appellate court to adopt a
new legal rule, inconsistent with its own prior ruling
in the same case, and then apply it retroactively to
the record established in the trial court pursuant to
the prior ruling, without remanding to afford the
parties the opportunity to prove their case under the
new rule.

2. Whether the Due Process Clause of the Fifth
Amendment perinits the Government to maintain a
claim while simultaneously asserting the state se-
crets privilege to bar presentation of a prima facie
valid defense to that claim.

3. Whether the Government may te:minate a
government contract for default on the ground that a
contractor has failed to make adequate progress
toward timely completion of that contract where the
Government has not set a valid deadline for com-
pleting the contract.

ii
LIST OF PARTIES

Pursuant to Rule 14.1(b) and Rule 29.6, the fol-
lowing list identifies all the parties to the proceeding
before the United States Court of Appeals for the
Federal Circuit:

McDonnell Douglas Corporation, appellant below,
was a wholly owned subsidiary of The Boeing Com-
pany prior to January 1, 2010. On January 1, 2010,
McDonnell Douglas Corporation was merged into The
Boeing Company, which brings this petition for a writ
of certiorari as the corporate successor to McDonnell
Douglas Corporation. The following publicly held
companies own ten percent or more of the out-
standing stock of The Boeing Company: State Street
Corporation and its subsidiary State Street Bank and
Trust Company as the trustee of The Boeing Com-
pany Employee Savings Plan Master Trust; Evercore
Trust Company, N.A. as the investment manager of
The Boeing Company Employee Savings Plan Master
Trust.

General Dynamics Corporation, appellant below,
has no parent corporation. No publicly held company
owns ten percent or more of the stock of General
Dynamics Corporation.

The United States.

ill

TABLE OF CONTENTS
Page
LE vi
OPINIONS AND ORDERS BELOW.................... 1
a csidusinweninaters 1
CONSTITUTIONAL AND REGULATORY PRO-

_ 2
EEE 2
STATEMENT OF THE CASE.........................2000 6

ss cccncsccedsucosececevesees 6

B. Performance and Termination................... 6

C. The First Round of Litigation ................... 9

DD. The Second Round of Litigation................ 10

E. The Third Round of Litigation .................. 14

REASONS FOR GRANTING THE PETITION.... 18

I. The Federal Circuit’s Adoption and Ap-
plication of a New Legal Rule without
Remanding Violates Due Process and
Conflicts with this Court’s Precedents
and the Decisions of Other Circuits. ........ 18

A. The Federal Circuit’s Refusal to Re-
mand Conflicts with This Court’s
a EE Se a ee ee 19

B. The Court of Appeals’ Refusal to Re-
mand Creates a Conflict with Other
Circuits. ........ Ts atin 21

iV

TABLE OF CONTENTS — Continued
Page

C. The Federal Circuit’s Immediate Ap-
plication of Its New Test Prevents
Contractors from Presenting Newly
Relevant Argument and Evidence....... 23

Il. The Federal Circuit’s Rule Permitting the
Government to Prosecute a Claim While
Asserting the State Secrets Privilege to
Foreclose a Valid Defense to That Claim
Violates Due Process and Conflicts with
the Decisions of this Court and of Other
eee 28

A. The Federal Circuit’s State Secrets
Analysis Deprives Defendants of Due
Process in Conflict with This Court’s
aa eeenueeie 29

B. The Federal Circuit’s State Secrets
Analysis Conflicts with the Decisions
ry eds 33

Ill. The Federal Circuit’s New Ad Hoc Rule
for Default Terminations Will Destabilize
An Important Area of the Law................... 34

1) _______ RIN See er RED RE nt ene ATS FERS ena RA ONES 40

TABLE OF CONTENTS — Continued

Page
Appendix Documents
Volume I
McDonnell Douglas Corporation v. United States
(“MDC 14”), 567 F.3d 1340 (Fed. Cir. 2009)........... la

McDonnell Douglas Corporation v. United States
(“MDC 12”), 323 F.3d 1006 (Fed. Cir. 2003)......... 37a

McDonnell Douglas Corporation v. United States
(“MDC 10”), 182 F.3d 1319 (Fed. Cir. 1999)......... 74a

McDonnell Douglas Corporation v. United States
(“MDC 13”), 76 Fed. Cl. 385 (Ct. Cl. 2007).....106a

Volume II

McDonnell Douglas Corporation v. United States
(“MDC 11”), 50 Fed. Cl. 311 (Ct. Cl. 2001)......... 258a

McDonnell Douglas Corporation v. United States
(“MDC 9”), 40 Fed. Cl. 529 (Ct. Cl. 1998)............. 299a

McDonnell Douglas Corporation v. United States
(“MDC 5”), 37 Fed. Cl. 270 (Ct. Cl. 1996)........... 369a

McDonnell Douglas Corporation v. United States
(“MDC 4”), 35 Fed. Cl. 358 (Ct. Cl. 1996)............. 4lla

McDonnell Douglas Corporation v. United States,
Nos. 2007-5111, 5131 (Nov. 24, 2009)......-..-.-0-.... 462a

TABLE OF AUTHORITIES
Page
CASES
Aero Mayflower Transit Co. v. ICC, 699 F.2d

I, a seineieinaianen 23
Al-Haramain Islamic Found., Inc. v. Bush, 507

AG BEDS (BE Cae. BOOT). ccccccccccccsccccccsccscccesessseces 4, 29
American Sheet Metal Corp., 99-1 BCA 430,329

iia iaenttaldaealdiclaliitatianhinsiiid 37
Arar v. Ashcroft, 585 F.3d 559 (2d Cir. 2009) .............. 4
AST Anlagen-Und Sanierungstechnik GmbH,

04-1 BCA 932,558 (ASBCA 2004)..................ccceee eee 37
Austin v. United States, 509 U.S. 602 (1993) ............ 32
Bareford v. General Dynamics Corp., 973 F.2d

I salen 29, 33
Boute v. City of Colombia, 378 U.S. 347 (1964)......... 19
Bowman Transp., Inc. v. Arkansas-Best Freight

i ig ee es Be CR ictcinicinieninittntstnnnnnnincss 19
Boyd v. United States, 116 U.S. 616 (1886),

overruled in part on other grounds, 425 U.S.

EEE) SaRRSUPE REI Pcs eee oor 32
Brinkerhoff-Faris Trust & Sav. Co. v. Hill, 281

| | SEE ee eee aa nae ao Na 21
Brinley v. Commissioner, IRS, 782 F.2d 1326

ASEM ip rannede ero Urer EO naar tone eT UO 22

Darwin Constr. Co. v. United States, 811 F.2d
Sea

vil

TABLE OF AUTHORITIES — Continued

Page
De Vito v. United States, 413 F.2d 1147 (Ct. Cl.
aed 36
Decker & Co. v. West, 76 F.3d 1573 (Fed. Cir.
RITTER es Aarne RT ELE Le. BENIN RRS EE 20, 32, 36
Divecon Servs., LP, 04-2 BCA 432,656 (GSBCA
ESTEE Ate MSN EE rch vee Be ee ae EEE BE ee 37
El-Masri v. United States, 479 F.3d 296 (4th
i, IO ee En oO See earls 4, 34
Fisher v. United States, 425 U.S. 391 (1976)............. 32
Gonzales v. United States, 348 U.S. 407 (1955)......... 19
Harlan Bell Coal Co. v. Lemar, 904 F.2d 1042
I 22

Hatch v. FERC, 654 F.2d 825 (D.C. Cir. 1981) ....21, 22
Hepting v. AT&T’ Corp., 439 F. Supp. 2d 974

ES ESR a ED One: 29
Hertz Corp. v. Friend, 1308. Ct. 1181 (2010)............ 19
Ideal Elec. Sec. Co. v. International Fid. Ins.

Co., 129 F.3d 143 (D.C. Cir. 1997) ..............ee ee 33
In re United States, 872 F.2d 4172 (D.C. Cir.

EEE DS ae TR LENE DEES AERO EE sees a nde 29, 33
Jones v. Flowers, 547 U.S. 220 (2006)......................4. 20
Kasza v. Browner, 133 F.3d 1159 (9th Cir. 1998) ...... 34
King v. United States, 37 Ct. Cl. 428 (1902).............. 36

Lachance v. Erickson, 522 U.S. 262 (1998)................ 19

TABLE OF AUTHORITIES — Continued

Page
Lanzen Fabricating, Jnc., 93-3 BCA 426,079
I a caasunsumieunbisiad 37
Lindsey v. Normet, 405 U.S. 56 (1972)....................... 32
Lisbon Contractors, Inc. v. United States, 828
Feed CO Cs CAR. BIT) cccesitctscecccesceveroccccsesees passim
Logan v. Zimmerman Brush Co., 455 U.S. 422
SP UIIITITT iciscleccsieiaiacectasuahsipsccioetlamsiniaaeenadanmaslinadiissiueaiaeininenaaiemees 19, 32
Lyons v. Johnson, 415 F.2d 540 (9th Cir. 1969).........33
Malone v. United States, 849 F.2d 1441 (Fed.
I a eee iiamioeaia Yy
Marx v. Director, OWCP, 870 F.2d 114 (3d Cir.
Scie ccc haadiciabisceditentseile mlacinibadegliusenenianedienmaniieiiinies 22
McDonnell Douglas Corporation v. United States
(“MDC 14”), 567 F.3d 1340 (Fed. Cir. 2009) ..... passim

McDonnell Douglas Corporation v. United States
(“MDC 12”), 323 F.3d 1006 (Fed. Cir. 2003) ..... passim

McDonnell Douglas Corporation v. United States

(“MDC 10”), 182 F.3d 1319 (Fed. Cir. 1999) ............... 1
McDonnell Douglas Corporation v. United States
(“MDC 13”), 76 Fed. Cl. 385 (Ct. Cl. 2007)...........0..... ]
McDonnell Douglas Corporation v. United States
(“MDC 11”), 50 Fed. Cl. 311 (Ct. Cl. 2001).................. I
McDonnell Douglas Corporation v. United States
(“MDC 9”), 40 Fed. Cl. 529 (Ct. Cl. 1998)................... 1

McDonnell Douglas Corporation v. United States
(“MDC 5”), 37 Fed. Cl. 270 (Ct. Cl. 1996)...........0....... |

ix

TABLE OF AUTHORITIES — Continued

Page
McDonnell Douglas Corporation v. United States

(“MDC 4”), 35 Fed. Cl. 358 (Ct. Cl. 1996) ............0...... 1
Millipore Corp. v. Travelers Indem. Co., 115

ee es Ls soeuuvepmeaiininesasoen ss 22
Mohamed v. Jeppesen Dataplan, Inc., 579 F.3d

943, en banc granted, 586 F.3d 1108 (9th Cir.

FREI RE RSE SS REED, SHS lire Cee oS aor eT 4
Molerio v. FBI, 749 F.2d 815 (D.C. Cir. 1984)......29, 33, 34
Motorola Computer Sys., Inc., 87-3 BCA 420,032

ER ET Ae
M.V.I. Precision Machining, Ltd., 91-2 BCA

| FS RS ie i eae 37
Noriega v. Pastrana, 1305. Ct. 1002 (2010)................5
One 1958 Plymouth Sedan v. Pennsylvania,

te NY eI sin’ sasdcueseieessesedsncnesdaaseceeiacens 20, 32
Peabody Coal Co. v. Ferguson, 140 F.3d 634 (6th

RRR Fa PS Se Ee eileen me ia nape oe ae ORE 22
Rahman v. Chertoff, 530 F.3d 622 (7th Cir.

RR ae Tage ESE ES INES REN SIN D9 Sc 4
Singh v. INS, 213 F.3d 1050 (9th Cir. 2000).............. 22
Technocratica, 06-2 BCA 433,316 (ASBCA 2006)....... 37
Technocratica, 94-2 BCA 426,606 (ASBCA 1993)....... 37
Tenenbaum v. Simonini, 372 b.3d 776 (6th Cir.

ERAN AL ee 2 EE REE Ao ae Ce 34

United States v. James Daniel Good Real Prop.,
Ue, IN isis icconsssssceserenss'cscnsslecencaces 20, 33

X

TABLE OF AUTHORITIES — Continued

Page

United States v. Reynolds, 345 U.S. 1

SEN IN oisdikdisiiuindusiatiitendiicentidadandsdsuamiisininanbains 11, 29, 30, 31
United States v. Winstar Corp., 518 U.S. 839

RRA RAS I UE AAR AT Sa eae eRe Se ON EC) 39
Universal Fiberglass Corp. v. United States, 537

ee Ss SIE STEED tesdciniicitchinantcapiaciniinentdinnimeebsnsien 38
Upwest Corp., 01-2 BCA 931,474 (PSBCA 2001) ...... 37
Wilner v. NSA, 592 F.3d 60 (2d Cir. 2009)... 4
Zuckerbraun v. General Dynamics Corp., 935

Pe Os WE noc 33
OTHER
| GS REESE eee ase a eee PRR ARS oe 2
a ee I niiisiichinbsicinsindioneristuanbeddeininchentesanebeeucis 9
Federal Acquisition Regulation (48 C.F.R.)

a Sa EE SN ce a 32
Federal Acquisition Regulation (48 C.F.R.)

| __REER ASIN Esaea eS oR EEN RS eo NE OD 10
Federal Acquisition Regulation (48 C.F.R.)

REE Ea ee a 36
Federal Acquisition Regulation (48 C.F-R.)

iis Sal aalachicd sneidadidipsodeneetvinesnennns 8
Federal Acquisition Regulation (48 C.F.R.)

§ 52.249-9( a 111) (1984)...............ccccccccscereees 2, 8, 35

Federal Acquisition Regulation (48 C.F.R.)
FC Rea LEI De SO a oe 10

TABLE OF AUTHORITIES — Continued
Page

U.S. Government Accountability Office, GAO-09-
326SP, Defense Acquisitions: Assessments of Se-
lected Weapon Programs 4 (Mar. 2, 2009)......... 35, 36

Donna Miles, Tanker Solicitation Seeks Fair
Competition, Best Value, American Forces
OS EWEN, OR. BG, BPI ccc ecesécccoscceccscccccesceseseses 35

Barack Obama, Memorandum for the Heads of
Executive Departments and Agencies, Mar. 4,
SE NES SCS GES SEA tr es ie an 35

1

PETITION FOR A WRIT OF CERTIORARI

The Boeing Company, as corporate successor to
the McDonnell Douglas Corporation (“McDonnell
Douglas”), respectfully petitions for a writ of certio-
rari to review the judgment of the United States
Court of Appeals for the Federal Circuit.

e

OPINIONS AND ORDERS BELOW

The opinions of the Federal Circuit (App. 74a-
105a, 37a-73a, la-36a) are reported at 182 F.3d 1319,
323 F.3d 1006, and 567 F.3d 1340. That court’s order
denying McDonnell Douglas’ combined petition for
rehearing and rehearing en banc (App. 462a) is
unreported. Pertinent opinions of the United States
Court of Federal Claims (App. 4lla-46la, 369a-410a,
299a-368a, 258a-298a, 106a-257a) are reported at 35
Fed. Cl. 358, 37 Fed. Cl. 270, 40 Fed. Cl. 529, 50 Fed.
Cl. 311, and 76 Fed. Cl. 385.'

.

JURISDICTION

The Federal Circuit entered final judyment on
June 2, 2009, and denied McDonnell Douglas’ timely
petition for rehearing and rehearing en banc on

' References to the appendix included with this petition are
designated as “App. .” References to the joint appendix filed
with the Federal Circuit are designated as “JA .

2

November 24, 2009. App. la-36a, 462a. On January
22, 2010, and March 12, 2010, the Chief Justice
extended the deadline for filing this petition for a writ
of certiorari, first to March 24, 2010, and then to
April 23, 2010. Docket No. 09A-678. The jurisdiction
of this Court is invoked under 28 U.S.C. § 1254(1).

+

CONSTITUTIONAI. AND
REGULATORY PROVISIONS INVOLVED

The Fifth Amendment to the United States Con-
stitution provides in pertinent part: “No person shall
... be deprived of life, liberty, or property, without
due process of law... .”

Section 52.249-9(a)(1)(ii) of the Federal Acquisi-
tion Regulations, 48 C.F_R. § 52.249-9(a)(1)(1i) (1984),
states: “The Government may ... , by written Notice
of Default to the Contractor, terminate this contract
in whole or in part if the Contractor fails to ...
|plrosecute the work so as to endanger performance of
this contract.”

¢

INTRODUCTION

This case arises from the Government's 1991
default termination of its contract with McDonnell
Douglas and General Dynamics (“Contractors”) to
design and build the A-12 “stealth” aircraft. Over the
course of almost two decades of litigation, the Federal

3

Circuit has twice denied Contractors due process,
created multiple circuit splits, and thrown previously
settled law in a critical area of government contracts
jurisprudence into complete disarray. If allowed to
stand, the court’s rulings may well unjustly deprive
Contractors of billions of dollars. This Court’s review
is necessary to settle these important legal issues and
to resolve these conflicts among the circuits.

First, the Federal Circuit denied Contractors the
most elemental feature of due process: fair notice of
the governing legal standard and an opportunity to
prove their case in the trial court under that stan-
dard. After initially directing the trial court to apply
its clear, long-standing rule for evaluating default
terminations — a rule it expressly prescribed as the
“controlling standard” in this very case — the Federal
Circuit, upon next review, sua sponte embraced an
entirely different, “ad hoc” approach materially indis-
tinguishable from one it had expressly rejected in its
previous decision. Without remanding, the Federal
Circuit then adjudicated Contractors’ rights itself,
applying its newly minted test to the pre-existing
record, even though the case had been litigated under
the very different rule it had previously mandated.
The Federal Circuit’s ruling conflicts with the deci-
sions of this Court and other circuits and introduces
substantial uncertainty regarding the principles of
due process governing appellate adjudication. Fur-
thermore, the grave miscarriage of justice worked by
the appellate process in this case manifestly warrants
the exercise of this Court’s supervisory authority.

4

Indeed, in view of the Federal Circuit’s patent error,
summary reversal of this ruling is warranted.

Second, the Federal Circuit earlier worked an
equally grave violation of Contractors’ due process
rights in this case by allowing the Government to
press its claim for default termination while simul-
taneously upholding the Government’s assertion of
the state secrets privilege to bar Contractors from
asserting a valid defense to that claim. In addition to
conflicting with bedrock principles of due process
embraced by this Court’s precedents, the Federal
Circuit’s ruling creates a conflict among the circuits
on the effect of the Government’s invocation of the
state secrets privilege. This case thus presents an
important question regarding the accommodation of
fundamental due process concerns with the needs of
national security. Moreover, it comes to this Court at
a time when the state secrets privilege is being as-
serted with growing frequency, and the need for
clarity and uniformity on its scope and impact could
not be more compelling.” And because this case pre-
sents the issue in the less politically charged context
of a government contract dispute, it offers a rare op-
portunity to provide clarity in a vital area of the law

* See, e.g., Wilner v. NSA, 592 F.3d 60, 77 n.8 (2d Cir. 2009);
Arar v. Ashcroft, 585 F.3d 559 (2d Cir. 2009); Mohamed v.
Jeppesen Dataplan, Inc., 579 F.3d 943, en banc granted, 586 F.3d
1108 (9th Cir. 2009); Rahman v. Chertoff, 530 F.3d 622, 624-25
(7th Cir. 2008); Al-Haramain Islamic Found., Inc. v. Bush, 507
F.3d 1190 (9th Cir. 2007); El-Masri v. United States, 479 F.3d
296 (4th Cir. 2007).

5

“in a manner that is insulated from the pressures of
the moment.” Noriega v. Pastrana, 130 S. Ct. 1002
(2010) (Thomas, J., joined by Scalia, J., dissenting from
denial of petition for writ of certiorari) (quotation
marks omitted). This Court should take that oppor-
tunity.

Finally, the Federal Circuit’s new ad hoc ap-
proach for reviewing government default ter:mina-
tions of fixed-price contracts represents a_ stark
change in settled law, upon which public contractors
have long relied in calculating the risks of doing busi-
ness with the United States. The new approach is
flawed and unworkable and will breed uncertainty
and arbitrary outcomes at a time when the Govern-
ment has publicly renewed its interest in fixed-price
contracting. Indeed, the court’s new approach may
produce an unexpected and grossly unjust multi-
billion dollar forfeiture in this case alone. And
because it is highly unlikely that any other Circuit
will address the issue of government contracts law
presented here, the issue is ripe for review by this
Court at this time.*

* Petitioner agrees that the additional issues presented by
General Dynamics Corporation in its petition for a writ of cer-
tiorari also warrant this Court’s attention, Petition for Writ of
Certiorari, The Boeing Company v. United States, No. (April
23, 2010), and joins General Dynamics’ request that the Court
review those issues, which equally affect both Petitioners.

6

STATEMENT OF THE CASE
A. The A-12 Contract

In 1988, Contractors entered into a fixed-price
research-and-development contract with the United
States Navy to develop the “A-12 Avenger,” a state-of-
the-art carrier-based “stealth” attack aircraft. App.
39a. The contract required Contractors first to devel-
op a design for the aircraft acceptable to the Navy,
and then to manufacture eight test aircraft of in-
creasing complexity, with the first to be delivered in
June 1990 and the remaining seven to be delivered on
specified dates thereafter. App. 4a. The eighth test
aircraft was to be a fully operational prototype. App.
260a. The A-12 contract also gave the Navy options to
purchase four production lots of aircraft. App. 5a. The
Navy exercised its first option (“Lot I”) in May 1990
for six production aircraft, which were to be delivered
between June 1991 and May 1992. App. 5a. The
contract also provided for six phases of testing by
Contractors, to be completed by April 1993, as well as
contractor support for additional Navy testing and
training until June 1996. App. 4a-5a, 119a.

B. Performance and Termination

Performance commenced in January 1988. From
the beginning, Contractors’ progress was hampered
because the Air Force refused to share classified
information and stealth technology from other pro-
grams, contrary to the mutual expectations and under-
standing of Contractors and the Navy. See, e.g., App.

7

393a & n.9. Further, as the Navy well understood,
deviations from schedule and specifications are all
but inevitable in research-and-development programs
like this one, which seek to advance the state of the
art. See, e.g., App. 124a, 117a-48a; JA 15,623, 16,541,
71,217; 48 C.F-R. § 35.002.

Accordingly, the Navy and Contractors agreed
early on to address technical issues as they arose,
rather than attempt to adhere rigidly to contract
schedule and specifications. App. 5a; JA 2,279-80. By
1989, the Navy knew that the original schedule for
delivery of the eight test aircraft would not be
achieved and that the aircraft would exceed the origi-
nally specified weight. See, e.g., JA 2,269-70, 18,936;
App. 447a.

In June 1990, Contractors projected that first
flight would be delayed unuil between July and Sep-
tember 1991, and that there would be a correspond-
ing slippage of twelve to fourteen months for the
remaining contract work. Although Contractors thus
missed the milestone for delivering the first test
aircraft, the Navy took no action to terminate the
contract. App. 5a. To the contrary, on August 17 the
Navy unilaterally issued a contract modification,
called “P00046,” as “a first step” toward establishing
a more realistic contract completion schedule. See JA
2,368. This modification set a new schedule for de-
livering the eight test planes, but did not address the
schedule for subsequent stages of perforinance. App.
6a. Because the original schedule for the subsequent
perforinance was irreconcilable with (and therefore

8

displaced by) PO0046, there was no longer any bind-
ing completion date for the entire contract. App. 16a,
3la, 110a-lla, 243a-44a. The Navy and Contractors
intended to negotiate a new schedule for the remainder
of the contract effort after they agreed on the A-12
design. See, e.g., JA 1,067-68, 2,360-61, 2,368, 71,088.

Contractors continued to perform, at a cost to
them of $120-150 million per month. App. 7a. During
the fall of 1990, the parties resolved all outstanding
design issues. App. 125a-30a. Among other things, the
Navy accepted Contractors’ modified weight projec-
tions. App. 288a. Concluding that “technical concerns
had been addressed and resolved to its satisfaction|[,]
[t]he Navy accepted plaintiffs’ design for the A-12 in
November 1990.” App. 130a.

Rather than re-establish a reasonable completion
schedule, as the parties had intended, however, the
Navy abruptly issued a cure notice in December 1990
and, on January 7, 1991, terminated the contract for
default pursuant to Federal Acquisition Regulation
(“FAR”) 52.249-9(a)(1)(ii). That provision authorized
termination for default if Contractors “failled] to .. .
[p}rosecute the work so as to endanger performance of
this contract.” 48 C.F.R. § 52.249-9(a)(1)Gii) (1984);
App. 8a-9a.* As grounds, the Navy asserted Contractors’

* The Government also invoked FAR 52.249-8(a)(1)(ii), the
analogous regulation governing the production option exercised
by the Government. As relevant here, there is no material differ-
ence between these two provisions.

9

projected failure to meet (1) the interim P00046
schedule, (2) the original Lot 1 production schedule
(though displaced by P00046, see App. 16a, 243a), and
(3) original design requirements — particularly,
weight requirements — even though the Navy had
accepted a modified design just weeks before (see App.
129a-30a & n.11). JA 18,297.

Based on this claimed default, the Navy not only
refused to reimburse Contractors for more than $1.2
billion in out-of-pocket costs incurred before ter:nina-
tion, it also demanded that Contractors return ap-
proximately $1.35 billion in allegedly unliquidated
progress payments. App. 9a-10a. To date, approximately
$1.5 billion in interest has accrued on the principal
balance claimed by the Government.

C. The First Round of Litigation

In June 1991, Contractors sought review of the
Navy’s decision in the Court of Federal Claims under
the Contract Disputes Act, 41 U.S.C. § 609(a). Al-
though that statute required Contractors to initiate
this action, they are the plaintiffs in name only. “[A]
government decision to terminate a contractor for
default is a government claim,” Malone v. United
States, 849 F.2d 1441, 1443 (Fed. Cir. 1988), and the
Government, accordingly, had the burden of proving
that its default termination, and a potential multi-
billion dollar penalty, were justified, Lisbon Contrac-
tors, Inc. v. United States, 828 F.2d 759, 764 (Fed. Cir.
1987). Contractors argued that the Government could

10

not satisfy its burden and that the termination should
therefore be converted into one for the convenience of
the Government. See FAR 49.401(b), 52.249-9(g). Con-
tractors also sought their unreimbursed costs in-
curred in performing the contract.

After several years of litigation, the trial court
held that the default termination could not be sus-
tained because it had been pretextual, and the con-
tracting officer had not exercised reasoned discretion
in invoking this draconian remedy. App. 343a-44a.
That court also expressly rejected the Government’s
arguments that Contractors had repudiated the
contract or otherwise failed to give adequate assur-
ances of performance. App. 458a-6la. The court
awarded Contractors $1.2 billion in unreimbursed
costs, plus interest. App. 367a-68a.

The Federal Circuit reversed, holding that “be-
cause the terimination for default was predicated on
contract-related issues, it was within the discretion of
the government.” App. 75a-76a. The court remanded
for determination of whether the Government could
prove that Contractors were in default. App. 104a-O5a.

D. The Second Round of Litigation

On remand, the trial court sustained the default
termination based solely on its finding that Contrac-
tors would not have met the December 1991 “first
flight” milestone set by P00046. App. 255a-75a. That
court rejected all other grounds for default termi-
nation the Government alleged including that

1]

Contractors could not meet weight and other
specifications, that Contractors’ financial condition
threatened performance, and (once again) that
Contractors failed to give adequate assurances of
performance. See, e.g., App. 264a-65a.

That court also rejected Contractors’ “superior
knowledge” defense, which was premised on the Gov-
ernment’s “duty to disclose critical inforimation to a
contractor that is necessary to prevent the contractor
from unknowingly pursuing a ruinous course of ac-
tion,” App. 96a (quotation marks omitted). The court
fuund that this duty extended to the Air Force’s
extensive knowledge of stealth technology, and Con-
tractors argued that they could have used that supe-
rior knowledge to avoid the extensive, duplicative,
and time-consuming efforts they expended to solve
technical problems in designing the A-12. App. 38la.
82a & nn.6-7; see also App. 137a n.16 (Deputy
Assistant Secretary of Defense for Procurement
“relented” in her opposition to “putting the A-12 out
for bids on a fixed-price contract ... only with
assurance that the Government would share its
stealth technology with the contractors. Otherwise,
she predicted, it cannot be done.”).

The Government, however, invoked the state
secrets privilege to block discovery relating to its
superior knowledge. App. 383a-86a. That privilege
applies if “there is a reasonable danger that compulsion
of the evidence will expose military matters which, in
the interest of national security, should not be
divulged.” United States v. Reynolds, 345 U.S. 1, 10

12

(1953). The trial court found that Contractors could
“present a prima facie case based on A-12 program
inforsnation alone.” App. 394a-95a, 402a; see also App.
293a-94a. But the court sustained the privilege and
rejected the defense because, it concluded, the
“superior knowledge issues in this case cannot be
litigated safely.” App. 292a-93a.

In its 2003 decision (“MDC 12”), the Federal Cir-
cult vacated the judyment in favor of the Government
and remanded. The appellate court “reaffirinled] . . .
that the test ... adopted in Lishon [Contractors, Inc.
v. United States, 828 F.2d 759 (Fed. Cir. 1987)], as
further explained in this opinion, controls the review
of default ter:mination for failure to make progress.”
App. 58a. Specifically prescribing Lisbon as “the
controlling standard” in this case, App. 72a-73a, the
court held that the Government — which “bore the
burden of proof in justifying a default termination” —
must show “‘reasonable belief on the part of the
contracting officer that there was no reasonable
likelihood that the contractor could perform the entire
contract effort within the time remaining for contract
performance,” App. 52a (quoting Lishon, 828 F.2d at
765) (emphasis added).

The Federal Circuit further held that, under Lis-
bon, the trial court’s finding that Contractors would
not have met P00046's first flight date in December
1991 was “insufficient to sustain a default termina
tion in this case.” App. 47a. It vacated the trial court's
ruling that the default terinination was justified and
remanded for further proceedings “because the

13

Court of Federal Claims did not apply the controlling
standard under Lisbon to this case.” App. 72a. The
court specifically directed that “on remand, once the
Court of Federal Claims determines the performance
required by the contract and the contract completion
date, it can then decide ... whether the government
has met its burden” of justifying the default termina-
tion under Lisbon. App. 57a (emphasis added); see
also App. 56a (“the Court of Federal Claims will first
have to decide the actual performance that the con-
tract requires and the amount of time remaining for
performance”) (emphasis added). For, as the court ex-
plained, “[uJnless the contracting officer had deter-
mined the entire effort required under the contract
and the time left to complete the contract, it would be
difficult, if not impossible, for him to resolve whether
‘there was no reasonable likelihood that the con-
tractor could perforin the entire contract effort within
the time remaining for contract performance.” App.
56a (quoting Lisbon, 828 F.2d at 766) (emphasis
altered).

Turning to the superior knowledge defense, App.
39a-42a, 58a-72a, the Federal Circuit rejected Contrac-
tors’ argument that the Government could not, consis-
tent with due process, both continue to assert its claim
for default termination and also invoke the state
secrets privilege to foreclose Contractors’ superior
knowledge defense to that claim. App. 69a-70a.
Asserting that Contractors had “conflate[d] rules
governing criminal and civil proceedings,” the court
concluded that the trial court had not erred in

14

barring Contractors’ defense while allowing the
Government’s claim to proceed. App. 69a.

E. The Third Round of Litigation

On remand, the trial court specifically deter-
mined that “(t]he contract had no completion date at
termination, seemingly leaving the court without a
basis for finding a reasonable belief on the part of the
contracting officer that the contractors would not
complete the work on time.” App. 243a-44a. Under
Lisbon’s plain language, and MDC 12’s even plainer,
repeated remand instructions quoted above, the
Government could not prove that Contractors had
failed to make sufficient progress toward timely
completing the entire contract effort if there was no
valid completion date. App. 109a-lla. Rather than
vacate the default termination, however, the trial
court turned again to the interim, partial PO0046
schedule and used it as a “yardstick” for measuring
performance under Lisbon; it concluded that the “trial
record supplies reasons that a contracting officer
might have deemed himself insecure if he were
considering the period of performance identified as the
‘yardstick.’” App. 21la (emphasis added).

Given that the P00046 yardstick “use[d] a con-
tract period before the ultimate completion date” and
addressed only one of more than 80 contract line
items, the court had to acknowledge that its analysis
showed only that “the contractors were behind sched-
ule at termination according to a self-contained series

15

of milestones, not in relation to the entire contract,”
App. 206a (emphasis added), as Lisbon and MDC 12
required. Indeed, the trial court openly acknowledged
that its analysis could not be squared with the MDC
12 mandate if that mandate’s words were construed
“to mean exactly what they appear to mean.” App.
256a n.92. The court thus defied the Federal Circuit’s
specific remand instructions; readopted its prior, re-
jected analysis; and conceded as much. App. 196a.

In its decision in 2009 (“MDC 14”), the Federal
Circuit agreed “that the contract, as modified by
P00046, does not provide a definite contract comple-
tion date.” App. 16a, 3la. Under the Lisbon-MDC 12
rule, therefore, it should have reversed the trial court’s
decision sustaining default termination. Instead, the
Federal Circuit affirmed, candidly acknowledging that
it was now adopting an analysis that “may appear
different from the one [it had] previously instructed
the trial court to perforin.” App. 30a n.4. That court
invoked supposed authority under the law of the case
doctrine to justify its acknowledged “depart[ure]”
from MDC 12. Id. Whereas MDC 12 identified Lisbon
as the “controlling standard,” under which the trial
court must determine “the performance required by
the contract and the contract completion date” as a
prerequisite to sustaining the default termination,
App. 57a, MDC 14 ruled that “because the modified
A-12 contract does not contain a fixed completion
date, a Lisbon analysis cannot be strictly applied,”
App. 3la; see also App. 17a (refusing to “apply the
Lisbon test literally”).

16

Instead, MDC 14 created a new “ad hoc, factual
inquiry,” requiring a terinination for default to be up-
held, even absent a contract completion date, if the
Government shows that, in light of “all relevant cir-
cumstances,” “the contracting officer was reasonably
justified in feeling insecure about the contractors’ rate
of progress.” App. 22a, 29a (emphasis added). The
court held that “[o]nce the Government has met this
burden of proving that timely perforinance is beyond
the contractors’ reach, the contractors have the bur-
den of going forward to prove either that they were
making progress such that timely completion of the
contract was not endangered or that there was ex-
cusable delay.” App. 3la. The court thus not only
shifted to Contractors the burden of proof on what
had been the ultimate question under the Lisbon-
MDC 12 rule — whether “timely completion of the
contract” is endangered — but also removed altogether
the only objective metric — a completion date — by
which that inquiry could be answered.

Attempting to justify its abrupt repudiation of
the Lisbon-MDC 12 rule, the Federal Circuit invoked
what it characterized as “the unique facts of this case
and the disadvantage [the court] faced [in MDC 12]
when deciding the case without the benefit of suffi-
cient fact findings from the trial court.” In particular,
the court lamented that MDC 12’s “specific instruc-
tion” for the trial court to determine “the contract
completion date ... , if read literally, turns out to be
difficult to apply.” App. 15a (emphasis added).

MDC 12, however, had already considered the
“unique facts of this case.” That court was fully aware

17

of the parties’ “differing views of the contract comple-
tion date,” including Contractors’ position “that no
such date existed.” App. 56a.” But MDC 12 never
suggested that Lisbon would not apply absent a
completion date; on the contrary, it specifically noted
that “it would be difficult, if not impossible,” for the
Government to carry its burden of justifying the
default termination absent such a date. Jd. Further-
more, MDC 12 had squarely rejected the Govern-
ment’s arguments then: (i) that “the circumstances
in this case are so different that [the court] should
not seek guidance from precedent” such as Lisbon;
(ii) that default termination should therefore be as-
sessed solely by looking “at the contractors’ conduct
in context, in all the facts and circumstances,” and
(iii) that default termination “was appropriate here
given the Contractors’ admitted inability to meet an
interim contract milestone, the alleged impossibility
for the aircraft design to meet contract specifications,
and the Contractors’ request for a restructuring of the
agreement.” App. 50a; JA 90,075-76 (oral argument).
Yet, MDC 14 later invoked these same essential argu-
ments in upholding the default termination. MDC 14
thus embraced an analysis materially indistinguish-
able from that expressly rejected by MDC 12.

Despite the crucial differences in proof between
its new ad hoc approach and the clear rule it discarded,
the Federal Circuit, incredibly, did not remand to

* As discussed below, lack of a completion date at termi-
nation hardly rendered this case “nique” or the Lisbon analysis
“difficult to apply.” See infra, Part III.

18

require the Government to meet its new burden or to
afford Contractors a chance to rebut’ the
Government’s showing, to present defenses under the
new standard, or to meet the burden the court had
newly shifted to them. Rather, the court applied its
new test to the record formed under the funda-
mentally different Lisbon-MDC 12 rule. Thus, the
court sustained the default termination because it
believed, based on its own interpretation of the facts,
that the Government “was justifiably insecure about
the contract’s timely completion” and because Con-
tractors neither proffered “record evidence to show
... that they could have completed the contract on
any date” nor argued on appeal “that their failure to
make progress could be excused.” App. 30a (emphasis
added). Of course, Contractors had had neither
reason nor opportunity to make either showing.

¢

REASONS FOR GRAN'TING THE PETITION

I. The Federal Circuit’s Adoption and Ap-
plication of a New Legal Rule without
Remanding Violates Due Process and
Conflicts with this Court’s Precedents
and the Decisions of Other Circuits.

In MDC 12, the Federal Circuit clearly directed
that this case be litigated and decided under the
Lisbon rule. As this Court’s precedents and the deci-
sions of other circuits make clear, once the appellate
court changed the applicable legal standard, the Due
Process Clause entitled Contractors, as a matter of

19

basic fairness, to a remand so they could present
argument and evidence made newly relevant by the
Federal Circuit’s about-face. Had they been afforded
that opportunity, Contractors almost certainly would
have prevailed.

A. The Federal Circuit’s Refusal to Re-
mand Conflicts with This Court’s
Precedent.

“tT Jhe Due Process Clauses protect civil litigants
who seek recourse in the courts, either as defendants
hoping to protect their property or as plaintiffs at-
tempting to redress yrievances.” Logan v. Zimmer-
man Brush Co., 455 U.S. 422, 429 (1982). Due process
manifestly requires “notice and a meaningful oppor-
tunity to be heard.” Lachance v. Erickson, 522 U.S.
262, 266 (1998). More specifically, a “party is entitled,
of course, to know the issues on which decision will
turn.” Bowman Transp., Inc. v. Arkansas-Best Freight
Sys., Inc., 419 U.S. 281, 289 n.4 (1974). Consequently,
when a court “overrules a consistent line of ... deci-
sions with the retroactive effect of denying a litigant
a hearing in a pending case, it thereby deprives him
of due process of law.” Bouie v. City of Colombia, 378
U.S. 347, 354 (1964); see also Gonzales v. United
States, 348 U.S. 407, 414 & n.5 (1955).

It follows that a court must remand when it
announces a rule different from the one under which
the case has been litigated. This principle is so funda-
mentally obvious that courts ordinarily apply it as a
matter of course. For example, in Hertz Corp. uv.

20

Friend, this Court recently adopted a jurisdictional
test for identifying a corporation’s principal place of
business that differed materially from the standard
under which the parties had litigated the case. 130
S. Ct. 1181, 1186-87, 1191-94 (2010). Even though the
plaintiffs had not previously challenged the defen-
dant’s declaration relating to its principal place of
business, this Court vacated the decision below and
remanded to afford the respondents “a fair opportu-
nity to litigate their case in light of [its] holding.” Jd.
at 1195.

These bedrock principles of due process apply
with special force here, for it is well-established that
default termination is “a drastic sanction,” Lisbon,
828 F.2d at 765 (citation omitted), indeed, “a species
of forfeiture,” Decker & Co. v. West, 76 F.3d 1573,
1580 (Fed. Cir. 1996). As this Court has repeatedly
emphasized, the Due Process Clause is vitally im-
portant in the forfeiture context. See, e.g., Jones v.
Flowers, 547 U.S. 220 (2006); United States v. James
Daniel Good Real Prop., 510 U.S. 43, 52, 62 (1993);
see also One 1958 Plymouth Sedan v. Pennsylvania,
380 U.S. 693, 700 (1965) (“forfeiture proceeding is
quasi-criminal in character”).

Furthermore, MDC 12 had specifically mandated
that Contractors’ challenge to the default termination
be litigated under the Lisbon-MDC 12 rule. Accord-
ingly, MDC 14’s failure to remand after announcing
its new approach was particularly egregious. Because
Contractors never had a meaningful opportunity to
adduce evidence and argument mad2 relevant by

21

MDC 14’s new approach, that decision denied them
due process of law. See Brinkerhoff-Faris Trust & Sav.
Co. v. Hill, 281 U.S. 673, 677 (1930).

B. The Court of Appeals’ Refusal to Re-
mand Creates a Conflict with Other
Circuits.

Consistent with this Court’s decisions, many cir-
cuits have held that the Due Process Clause requires
remand when an appellate court announces a new
controlling rule, to permit a party to present its case
under the new rule. The decision below therefore cre-
ates a conflict among the circuits on an important
issue relating to the fundamental procedural fairness
of litigation in the federal courts.

Thus, in Hatch v. FERC, after the parties liti-
gated before the ALJ under one standard, the Federal
Energy Regulatory Commission on appeal denied
petitioner’s claim by “adoptling] a stricter interpre-
tation of [the relevant statutory provision] than had
heretofore prevailed.” 654 F.2d 825, 830 (D.C. Cir.
1981). The D.C. Circuit observed that “when ... the
change [in the controlling standard] is a qualitative
one in the nature of the burden of proof so that ad-
ditional facts of a different kind may now be relevant
for the first time, litigants must have a meaningful
opportunity to submit conforming proof.” Id. at 835.
The court accordingly ruled that due process required
the Commission to allow the petitioner “to submit any

22

additional relevant evidence . .. he may have in order
to meet the new standard.” Jd. at 837.

Similarly, in Harlan Bell Coal Co. v. Lemar, an
employer initially submitted to the ALJ sufficient
evidence to defeat an employee’s benefits claim under
the then-controlling standard. 904 F.2d 1042, 1044
(6th Cir. 1990). After the ALJ had closed the record,
however, the Sixth Circuit reinterpreted that stan-
dard in another case. Jd. at 1044-45. On appeal the
Board applied the new standard to the extant record,
finding the employer’s evidence inadequate. Id. at
1045. The Sixth Circuit reversed because the em-
ployer had “been effectively deprived of the opportu-
nity to rebut evidence now supporting issues that did
not exist at the time of its ALJ hearing.” Jd. at 1049.
Explaining that the employer’s “night to a hearing
encompasses not only the right to present evidence,
but also the right to rebut the [employee’s] claims .. .
under the correct legal standards,” the court ruled
that “due process considerations” required that the
employer “must be granted an opportunity to present
evidence directed at the [newly adopted] standards as
such evidence is necessary to the full presentation of
{the employer’s] defense.” Jd.; see also, e.g., Peabody
Coal Co. v. Ferguson, 140 F.3d 634, 637 (6th Cir.
1998); Singh v. INS, 213 F.3d 1050, 1054 (9th Cir.
2000); Millipore Corp. v. Travelers Indem. Co., 115
F.3d 21, 33-34 (1st Cir. 1997); Marx v. Director,
OWCP, 870 F.2d 114, 121 (3d Cir. 1989); Brinley v.
Commissioner, IRS, 782 F.2d 1326, 1336 (5th Cir.

23

1986); Aero Mayflower Transit Co. v. ICC, 699 F.2d
938, 942 (7th Cir. 1983).

C. The Federal Circuit’s Immediate Ap-
plication of Its New Test Prevents
Contractors from Presenting Newly
Relevant Argument and Evidence.

Relying on MDC 12’s clear mandate, Contractors
maintained in the trial court and on appeal that de-
fault termination was improper because “the contract
had no completion date for the ‘entire contract effort’
at termination, leaving no possibility that the con-
tracting officer reasonably concluded the contractors
would not complete the work on time.” App. 234a,
242a-46a, 15a-16a. So clear was the MDC 12 mandate
that Contrac-tors had no reason to anticipate MDC
14’s adoption of a new, ad hoc approach closely
resembling one MDC 12 had rejected, \et alone
attempt to show that the Government could not meet
its burden under that new approach. Nor could they
reasonably have foreseen the need to proffer “record
evidence to show ... that they could have completed
the contract on any date,” or to argue on appeal “that
their failure to make progress could be excused,” App.
30a-3la, for these issues arise under the then-
controlling Lisbon-MDC 12 rule only if the Govern-
ment first proves a binding date for completing the
entire contract. Certainly Contractors could not have
anticipated that the Government’s failure to carry
its burden under Lisbon-MDC 12 would require

24

Contractors to prove that they were making adequate
progress toward a nonexistent completion date.

Had the Federal Circuit remanded the case after
altering the governing standard, Contractors almost
certainly would have prevailed. Instead, the appellate
court drew its own factual conclusions out of a gar-
gantuan record, making findings directly contrary to
those of the trial court — seemingly, without even
realizing that it had done so. In concluding that “the
contracting officer was reasonably justified in feeling
insecure about the Contractors’ rate of progress,” App.
29a (emphasis added), MDC 14 relied on (1) Con-
tractors’ projected failure to meet the P00046 delivery
schedule for the first eight test aircraft, (2) supposed
concerns about Contractors’ financial ability to per-
forin the contract, and (3) Contractors’ statements
made while negotiating for an equitable contract
restructuring and resisting unwarranted attempts to
hold them to waived or superseded milestones and
specifications. App. 25a-29a. Although the trial court
had found, based on these matters, that Contractors
might not have met the interim milestones imposed by
P00046, that court had expressly disclaimed the con-
clusion that they endangered timely performance of
the entire contract. See, e.g., App. 206a, 212a-13a. On
the contrary, that court found:

¢ the contracting officer was “not par-
ticularly concerned” about the projected “fail-
ure to meet the [P00046) delivery schedule.”
App. 218a n.73;

25

¢ the Navy saw a projected nine-month
delay in first flight as “realistic and ac-
ceptable,” App. 18la n.44, 276a-77a n.11;

¢ Contractors’ “financial condition was
not endangering performance of the A-12
contract,” App. 28la-82a;

* “lelvidence at trial established that
plaintiffs’ financial ability was not a concern”
of the contracting officer, App. 282a;

¢ “(tjJhe contractors’ requests to re-
structure the contract were not declarations
of financial inability or unwillingness to per-
form,” App. 225a;

¢ the contracting officer “did not be-
lieve that the contractors would not per-
form,” App. 283a;

¢ the senior Defense Department offi-
cial spearheading the A-12 contract termina-
tion “had no concern that the contractors
were incompetent or otherwise unable to
handle the A-12 contract,” App 171la n.35;
and

¢ the contractors “were committed to
performing the A-12 contract until the date
of termination,” App. 227a.

These undisturbed findings, amply supported by
the evidentiary record, alone appear to preclude a
finding under MDC 14 that “the contracting officer
was reasonably justified in feeling insecure about the
Contractors’ rate of progress.” App. 20a (emphasis
added). Had they been afforded an opportunity on

26

remand, Contractors could have further negated any
such conclusion by tailoring their arguments and
evidence to the new, ad hoc approach. They could also
have established both “that they were making pro-
gress such that timely completion of the contract was
not endangered,” and “that there was excusable
delay,” either of which would have provided a

complete defense to default termination under MDC
14’s new approach. App. 30a.

While it is unclear what might constitute “timely
completion” of the entire contract absent a valid com-
pletion date, Contractors could have proved that they
would have met any reasonable completion schedule.
In late 1990, Contractors and the Government had
similar internal projections of the entire schedule
leading to contract completion. JA 26,307; 92,112-13.
These internal schedules, which were satisfactory to
the Government, would have extended all milestones
by roughly the same amount of time that PO00046 had
extended delivery milestones for the first eight test
aircraft. Jd. At termination, Contractors were on
track to meet the later milestones these schedules
projected. Indeed, the Navy itself estimated just
before termination that the flight test program had a
reserve of more than 40 aircraft months, as long as
first flight occurred by the fourth quarter of 1992,
which was a conservative projection at the time of
termination. JA 26,6348; App. 178a n.44” Further,

* The Federal Circuit noted that Contractors projected test-
ing and evaluation to be completed 27 months after the orivinal
contract specified. App. 26a. The original testing-and-evaluation

(Continued on following page)

27

Contractors could have shown that the Government
caused much of the delay early on by directing
Contractors to focus on weight reduction rather than
schedule compliance. App. 447a.

In short, Contractors almost certainly would have
prevailed if given the opportunity to prove their case
under MDC 14’s new ad hoc test. Bedrock principles
of due process thus required the court to remand for
further proceedings. Indeed, so glaring is the Federal
Circuit’s departure from fundamental canons of due
process set forth in this Court’s controlling precedents
that summary reversal, with a remand to the trial
court for further proceedings, may be warranted as
ax! alternative to plenary review.

milestone did not, however, survive P00046’s extension of the
earlier milestones on which it depended, cf. App. 15a-16a, and
Contractors’ projection closely aligned with P00046, which
extended by up to 25 months the delivery milestones for the first
eight test airplanes. See JA 15,657. Had the parties believed the
extra two-month delay was significant, Contractors easily could
have compressed the lengthy contract testing period, as
evidenced by the ample flight-test program reserve.

28

il. The Federal Circuit’s Rule Permitting the
Government to Prosecute a Claim While
Asserting the State Secrets Privilege to
Foreclose a Valid Defense to That Claim
Violates Due Process and Conflicts with
the Decisions of this Court and of Other
Circuits.

Fundamental fairness does not permit the Gov-
ernment to assert a multi-billion-dollar claim against
a defendant while refusing to disclose secret informa-
tion that would dei. at that claim. Here, the Govern-
ment asserted a default ter:mination claim and then
invoked the state secrets privilege to bar Contractors
from proving their prima facie valid superior knowl-
edge defense to that claim. By allowing the default
terinination claim to proceed, MDC 12 violated ele-
mental due process and created a conflict with this
Court’s decisions and those of every other circuit that
has addressed the issue.

Tellingly, the Government has embraced these
due process principles when the shoe is on the other
foot and it is attempting to defend against a claim.
Indeed, earlier in this very case, the Government
insisted that, if the court converted the termination
for default to one for convenience, Contractors’ claim
for contractual payments should nonetheless be de-
nied because a potential government defense to that
claim would depend upon privileged state secrets.
The Government argued: “As a matter of law, ‘if the
privilege deprives the defendant of information that
would otherwise give the defendant a valid defense to

29

the claim, then the Court may grant summary judg-
ment to the defendant.’” Def.’s Br. Regarding Effect of
State Secrets and Mot. for Reconsideration 11 n.2
(Mar. 28, 2001) (quoting Bareford v. General Dynam-
ics Corp., 973 F.2d 1138, 1141 (5th Cir. 1992)); see
also App. 373a-80a, 394-98a. The Government has
repeatedly taken the same position in other cases.
See, e.g., Al-Haramain Islamic Found., Inc. v. Bush,
507 F.3d 1190, 1197 (9th Cir. 2007); Hepting v. AT&T
Corp., 439 F. Supp. 2d 974, 985-86 (N.D. Cal. 2006);
In re United States, 872 F.2d 472, 477 (D.C. Cir. 1989);
Molerio v. FBI, 749 F.2d 815, 819 (D.C. Cir. 1984).

This is exactly Contractors’ position: their prima
facie valid defense to the Government’s default termi-
nation claim cannot be litigated because the Govern-
ment asserted the state secrets privilege. Private
parties defending against a Government claim are
entitled to at least the same due process protections
as the Government. Indeed, it is especially unfair to
permit the Government to use the state secrets
privilege both offensively and defensively in the same
case, always to Contractors’ disadvantage.

A. The Federal Circuit’s State Secrets
Analysis Deprives Defendants of Due
Process in Conflict with This Court’s
Precedents.

Invoking this Court’s decision in United States
v. Reynolds, 345 U.S. 1 (1953), and circuit court
decisions following it, the Federal Circuit ruled that

30

Contractors were precluded from asserting their su-
perior knowledge defense to the Government’s default
terinination claim because, “when a properly invoked
claim of State Secrets privilege undercuts a civil
litigant’s opportunity to prove its case, the interests
favoring protection of the state secret always prevail.”
App. 66a-69a, 71a. But Contractors did not dispute
that genuine state secrets must always be protected;
rather, they argued that permitting the privilege to
preclude their prima facie valid defense requires, as a
matter of due process, dismissal of the Government’s
default termination claim. The Due Process Clause
will not permit the Government both to assert a claim
and then to ensure its own victory by asserting the
privilege to preclude its opponent from raising a valid
defense.

In Reynolds, the plaintiffs sued the Government
in tort and sought disclosure of a classified report
withheld under the state secrets privilege. 345 U.S. at
3-5. Upholding the Government’s assertion of privi-
lege, the Court distinguished a criminal defendant
from a civil plaintiff asserting a claim for monetary
relief against the Government: “[I]n the criminal
field, ... the Government can invoke its evidentiary
privileges only at the price of letting the defendant go
free,” for “it is unconscionable to allow [the Govern-
ment] to undertake prosecution and then invoke its
governmental privileges to deprive the accused of
anything which might be materia! to his defense.” Jd.
at 12. But this “rationale has no application,” the
Court held, “in a civil forum where the Government is

31

not the moving party, but is a defendant only on
terias to which it has consented.” Jd.

Relying on this discussion in Reynolds, the Fed-
eral Circuit held that Contractors had “conflate[d]
rules governing criminal and civil proceedings, ele-
vating this civil contract dispute into the consti-
tutional territory of a criminal] prosecution.” App. 69a.
Concluding that “(t]he Contractors are not at jeop-
ardy from an attack on them by the government,” the
court ruled that due process did not foreclose the
Government from proceeding with its default termi-
nation claim, even as Contractors were barred from
presenting their prima facie valid superior knowledge
defense. App.70a.

In fact, however, this Court’s decisions in Rey-
nolds and other cases show that the Government’s
default ter:nination claim here must be denied. Con-
trary to the Federal Circuit’s decision, Contractors
are at jeopardy — from a staggering multi-billion
dollar forfeiture claim asserted against them by the
Government — and due process entitles them to
dismissal of that claim because the Government’s
invocation of the privilege bars them from raising a
valid defense.

Reynolds did not specifically address the situa-
tion here, where the Government is the moving party
asserting a civil penalty claim. But Reynolds’ ration-
ale concerning criminal defendants nonetheless plain-
ly applies: just as in the criminal context, it is clearly
unconscionable to allow the Government both to assert

32

a multi-billion dollar civil penalty claim against
Contractors and also to “invoke its governmental
privileges” to bar them from presenting a valid de-
fense to that claim.’

Indeed, other decisions of this Court unambigu-
ously hold that due process guarantees a civil de-
fendant “an opportunity to present every available
defense.” Lindsey v. Normet, 405 U.S. 56, 66 (1972);
see also Logan, 455 U.S. at 429. The underlying risk
in civil and criminal cases involving the state secrets
privilege is the same: if the Government can both
assert a claim and invoke the privilege to bar a
defense to that claim, it can distort the court’s fact-
finding process to its advantage. As this Court has
explained, “(t]he purpose of an adversary hearing is
to ensure the requisite neutrality that must inform
all governmental decision-making. That protection is
of particular importance here, where the Government

* Indeed, termination for default is a “species of forfeiture,”
Decker & Co., 76 F.3d at 1580, and settled law holds that a
“forfeiture proceeding is quasi-criminal in character.” One 1958
Plymouth Sedan, 380 U.S. at 700 (applying the Fourth
Amendment's exclusionary rule in forfeiture proceeding); see
also, e.g., Austin v. United States, 509 U.S. 602 (1993) (finding
that forfeiture constituted punishment for purposes of the Ex-
cessive Fines Clause of the Eighth Amendment); Boyd v. United
States, 116 U.S. 616 (1886) (applying the Self Incrimination
Clause of the Fifth Amendment in forfeiture proceeding)
(overruled in part on other grounds, Fisher v. United States, 425
U.S. 391 (1976)). And default termination can have other quasi-
criminal consequences as well, including debariuent from public
contracting. See FAR § 9.406-2(b)(1).

33

has a direct pecuniary interest in the outcome of the
proceeding.” James Daniel, 510 U.S. 55-56. The Fed-
eral Circuit’s state secrets ruling thus violates due
process and directly conflicts with this Court’s clear
precedents.

B. The Federal Circuit’s State Secrets
Analysis Conflicts with the Decisions
of Other Circuits.

Consistent with this Court’s civil due process
precedents, “[mJost courts that have discussed the
state secret privilege have adopted the position that,
if privileged information would establish a valid de-
fense, then the court ought to dismiss the plaintiffs’
case.” Bareford, 973 F.2d at 1143 (citing Zuckerbraun
v. General Dynamics Corp., 935 F.2d 544, 547 (2d Cir.
1991), In re United States, 872 F.2d at 476, 481 (D.C.
Cir. 1989), and Molerio, 749 F.2d at 821, 825).* In
Molerio, for example, the plaintiff claimed that the
FBI, its director, and its former personnel officer had
illegally refused to hire him. 749 F.2d at 819. Then-
Judge Scalia, writing for the court, held that two of
the counts were “properly dismissed” because the

* Moved by similar concerns about fairness, courts have
likewise not allowed civil plaintiffs to assert other types of
privileges to foreclose a valid defense. See, e.g., Ideal Elec. Sec.
Co. v. International Fid. Ins. Co., 129 F.3d 143, 151-52 (D.C. Cir.
1997) (attorney-client privilege); Lyons v. Johnson, 415 F.2d 540,
542 (Sth Cir. 1969) (Fifth Amendment privilege against self-
incrimination).

34

Government’s assertion of the state secrets privilege
with respect to evidence of “the genuine reason for
denial of employment” prevented the defendants from
asserting a “valid[] ... defense.” Jd. at 825-26. In-
deed, other than the Federal Circuit here, all of the
circuits addressing this issue have — often building on
Molerio — made clear that a civil claim should be
dismissed if the state secrets privilege forecloses a
valid defense. See also El-Masri v. United States, 479
F.3d 296, 309 (4th Cir. 2007); Tenenbaum v. Simonini,
372 F.3d 776, 777 (6th Cir. 2004); Kasza v. Browner,
133 F.3d 1159, 1166 (9th Cir. 1998). The point of these
cases is this: if the state secrets privilege requires a
defendant to lay down its shield, due process requires
the plaintiff to lay down its sword.

By embracing a contrary approach, the decision
below creates a conflict among the circuits on an im-
portant question regarding the accommodation of
fundamental due process concerns with the needs of
national security. This Court’s review is thus urgently
needed to correct the decision below and restore clar-
ity and uniformity in this critical area of the law.

Ill. The Federal Circuit’s New Ad Hoc Rule
for Default Terminations Will Destabilize
An Important Area of the Law.

The Federal Circuit’s new, ad hoc approach to
default terminations is unworkable, unfair to contrac-
tors, and potentially very costly to the Government.
It will have significant adverse consequences for the

35

Government’s extensive contracting programs. See
U.S. Government Accountability Office, GAO-09-
326SP, Defense Acquisitions: Assessments of Selected
Weapon Programs 4, 6 (Mar. 2, 2009) (“GAO Report” ].
The Government’s renewed emphasis on fixed-
price contracts, which are directly governed by FAR
§ 52.249-9 (at issue here) and analogous default
termination provisions, renders the Federal Circuit’s
novel interpretation especially momentous. See, e.g.,
Barack Obama, Memorandum for the Heads of Execu-
tive Departments and Agencies, Mar. 4, 2009; Donna
Miles, Tanker Solicitation Seeks Fair Competition,
Best Value, American Forces Press Service, Feb. 24,
2010. Because the Federal Circuit has exclusive
appellate jurisdiction of challenges to such terinina-
tions, the decision below effectively creates a national
rule implicating all future government contracts of
this kind. Clarifying the standard for terminating
such contracts is thus an issue of exceptional im-
portance that warrants this Court’s attention.

Given the special rules that already apply in this
area, the approach adopted below is unnecessary to
protect the Government’s interests and will create
perverse incentives for arbitrary governmental ac-
tion. Unlike a private party, the Government may
terminate a contract for convenience at any time and
for virtually any reason, without liability for breach,
simply by paying for work already perforined plus
limited settlement costs. But if the Government ter-
minates for default, it is not liable even for work the
contractor already has performed. On the contrary,

36

this “drastic” remedy may entitle the Government “to
the repayment of advance and progress payments”
that have not been liquidated. Decker & Co., 76 F.3d
at 1580; FAR § 49.402-2. Absent bad faith, the only
consequence to the Government if a court rules that
the “default decision represented an abuse of dis-
cretion” is that termination is converted “into one for
the convenience of the Government.” Darwin Constr.
Co. v. United States, 811 F.2d 593, 597 (Fed. Cir.
1987).

These rules incentivize the Government to ter-
minate for default and take its chances in subsequent
litigation. To temper the consequences of such a
“drastic sanction,” which effects a forfeiture of con-
tractors’ rights, courts have long insisted upon clear,
strict standards to guard against arbitrary default
terminations. See, e.g., De Vito v. United States, 413
F.2d 1147, 1153 (Ct. Cl. 1969); King v. United States,
37 Ct. Cl. 428, 436 (1902).

Lisbon and MDC 12 struck a “praymatic,” care-
fully calibrated “balance” between “the judicial aver-
sion to default terminations” and the Government’s
right “to receive that for which it contracted” by
adopting clear, fair rules for deter:mining when sched-
ule delays warrant the drastic sanction of default
termination. App. 50a-51la. In complex contracts where
delays are commonplace, see GAO Report 6, 10-11,
the requirement that default termination be based on
the contracting officer’s reasonable belief that there is
no reasonable likelihood that the contractors will
perform “the entire contract effort” by the “contract

37

completion date” provides a rule that is both work-
able and fair.

Contrary to the court’s assertions below, nothing
about the lack of a valid contract completion date
renders Lisbon “unworkable” or unsound. In fact,
without clear guidance for when a contract must be
completed, it is not only unreasonable, but also logic-
ally impossible to conclude that there is no reason-
able likelihood of timely completion. App. 55a. Nor
does the Government’s inability to meet its burden
under Lisbon without a valid completion date make
that decision “difficult to apply.” Indeed, the Boards of
Contract Appeals — “whose specialized expertise with
government contracts is entitled to respect,” App.
52a-53a n.2 — have had no difficulty applying Lisbon
to contracts lacking a “reasonable and_ specific
completion date,” repeatedly holding that in such
circumstances “the Government could not rationally
terminate for default for failure to make progress,
since there was no objective against which the
contractor’s progress could be judged.” Divecon Servs.,
LP, 04-2 BCA 932,656 at 161,634-35 (GSBCA 2004).”

* See Technocratica, 06-2 BCA 933,316 at 165,190 (ASBCA
2006); AST’ Anlagen-Und Sanierungstechnik GmbH, 04-1 BCA
132,558 at 161,043-44 (ASBCA 2004); Upwest Corp., 01-2 BCA
731,474 at 155,393 (PSBCA 2001); Amerwan Sheet Metal Corp.,
99-1 BCA 430,329 at 149,994-95 (GSBCA 1999): Technocratica,
94-2 BCA 926,606 at 132,370 (ASBCA 1993); Lanzen Fabricating,
Inc., 93-3 BCA 426,079 at 129,609 (ASBCA 1993); M.V.I.
Precision Machining, Ltd., 91-2 BCA 923,898 at 119,741 (ASBCA
1991); Motorola Computer Sys., Inc., 87-3 BCA 420,032 at
101,416 (ASBCA 1987).

38

Applying Lisbon in this way does not disadvan-
tage the Government. Unlike a private party, the
Government always possesses the power unilaterally
to impose a reasonable completion date against which
to measure a contractor’s progress. App. 60a. Re-
quiring the Government to impose a clear completion
date before penalizing a contractor for failing to make
progress toward timely completion is just what basic
fairness requires. further:more, courts have recog-
nized a narrow exception to the requirement for a
completion date in the exceptional case, unlike this
one, where a contractor is “making no progress at
all,” and the evidence shows that progress will never
resume. Universal Fiberglass Corp. v. United States,
537 F.2d 393, 397 (Ct. Cl. 1976). These rules, as well
as the government-friendly rules governing default and
convenience terminations discussed above, more than
suffice to protect the Government’s legitimate interests.

Unlike Lisbon, it is the ad hoc approach ordered
by the court below that is unworkable and unfair.
At best, the new approach is arbitrary and un-
predictable, turning on any conccivable subjective
circumstance, apparently including failure to meet
milestones and specifications that the Government
previously waived. Compare App. 25a-27a, with App.
60a-6la. At worst, the new approach is circular and
incoherent, requiring an ungrounded prediction of
whether “timely” performance is endangered, despite
the absence of an enforceable completion date.

By replacing the Lisbon test with this flawed ad
hoe approach, the decision below will increase the

39

Government's already substantial incentive to default
terminate, regardless of whether that remedy is jus-
tified. Moreover, the new approach reverses the Gov-
ernment’s incentive to forthrightly reset waived or
superseded schedules: while the Government cannot
prevail under Lisbon absent a valid completion date
(unless the contractor is making no progress whatso-
ever), the new approach holds the Government to a
less-demanding standard when there is no contract
completion date than when there is one. Without a
definite deadline, contractors will be unable to know
whether their progress is adequate, and courts will lack
an objective basis for judging the reasonableness of a
Government claim that it “feel/s/ insecure about the
contractors’ rate of progress.” App. 24a-3la (emphasis
added).

The result will be an inevitable decrease in pre-
dictability, with a concomitant increase in unwar-
ranted default ter:ninations and litigation disputing
them. And while the ruling below will inure to the
Government’s benefit here, over time it will most likely
harm the Government, as contractors either refuse to
enter fixed-price contracts or demand a preminm to
compensate for the heightened risk of arbitrary or
unjustified forfeitures. See United States v. Winstar
Corp., 518 U.S. 839, 913 (1996) (Breyer, J., concurring).

Contrary to the Federal Circuit's suggestion, see
App. 35a-36a, its decision will not be limited to the
facts of this case or rare cases. Schedule waivers and
realignments are typical of Government contracts,
especially complex R&D contracts such as this one.

40

And default terminations of contracts lacking a valid
completion date are not particularly unusual, either,
as indicated by the numerous Boards of Contract
Appeals cases cited above. Further, the frequency of
such default teriminations undoubtedly will increase
now that the Government’s incentive to re-establish a
valid completion schedule has been replaced with an
incentive to leave the completion date undefined.

¢

CONCLUSION

For the foregoing reasons, this petition for a writ
of certiorari should be granted. As an alternative to
plenary review, this Court may wish to consider sum
marily reversing the judyinent below, with instruc-
tions to remand the case to the trial court to afford
Contractors an opportunity to satisfy the Federal
Circuit’s new test for reviewing a default termination.

April 23, 2010 Respectfully submitted,
J. MICHAEL LuwiiG CHARLES J. COOPER
executive Vice President Counsel of Record

& General Counsel! MiIcHABL W. KikkK
GRANT M. DIXTON Howakb CC, NIELSON, Jk
LYNDA GUILD SIMPSON DAVID LEHN
THE BOEING COMPANY COOPER AND KIKK, PLLC
100 North Riverside 1523 New Hampshire Ave , N.W.
Chicago, IL 60606 Washington, D.C. 200386
($12) 544-2800 (202) 220-9600

(202) 220-9601 (fax)
ccooper@cooperkirk.com

Counsel for
The Boeing Company

la

MCDONNELL DOUGI.AS CORPORATION,
Plaintiff-Appellant, and GENERAT.
DYNAMICS CORPORATION,
Plaintiff-Appellant, v.

UNITED STATES, Defendant-Appellee.

2007-5111, 2007-5131

UNITED STATES COURT OF APPEATS
FOR THE FEDERAT. CIRCUIT

567 F.3d 1340; 2009 U.S. App. LEXIS 11716
June 2, 2009, Decided

COUNSEL: Charles J. Cooper, Cooper & Kirk,
PLLC, of Washington, DC, argued for plaintiff-appel-
lant. McDonnell Douglas Corporation. With him on
the brief were Michael W. Kirk, Howard C. Nielson,
Jr. and D. John Sauer. Of counsel on the brief were
Caryl A. Potter, III, and Elizabeth A. Ferrell, Sonnen-
schein, Nath & Rosenthal, LLP, of Washington, DC;
and J. Michael Luttig, The Boeing Company, of
Chicago, Illinois.

Donald B. Verrilli, Jr., Jenner & Block, LLP, of Wash-
ington, DC, argued for plaintiff-appellant General
Dynamics Corporation. With him on the brief were
David A. Churchill; and Linda L. Listrom, of Chicago,
Illinois.

Bryant G. Snee, Deputy Director, Commercial Liti-
gation Branch, Civil Division, United States De-
partment of Justice, of Washington, DC, argued for
defendant-appellee. With him on the brief were
Jeanne KE. Davidson, Director, and Patricia M.

2a

McCarthy, Assistant Director. Of counsel was Kirk T.
Manhardt, Deputy Director. Of counsel on the brief
were Wendell A. Kjos and Mark A. Romano, Office of
the General Counsel, United States Department of
the Navy, of Arlington, Virginia.

Gregory A. Smith, Cooley Godward Kronish LLP, of
Reston, VA, for amicus curiae National Defense In-
dustrial Association. With him on the brief was David
E. Fletcher, of Washington, DC. Of counsel on the
brief was Ralph C. Nash, Jr., George Washington
University Law School, of Washington, DC.

JUDGES: Before MICHEL, Chief Judge, MOORE,
Circuit Judge, and HUFF,* District Judge.

OPINION BY: MICHEL

OPINION
MICHEL, Chief Judge.

This case arises from the government’s default
terinination in 1991 of a contract between the United
States Navy (“the government”) and two contractors,
McDonnell Douglas Corporation (“MDC”) and Gen-
eral Dynamics Corporation (“GD”) (collectively “con-
tractors”) to develop a carrier-based stealth aircraft,
the A-12 Avenger. The contractors challenge the

* Honorable Marilyn L. Huff, District Judge, United States
District Court for the Southern District of California, sitting by
designation.

3a

judgment of the Court of Federal Claims in favor of
the government. McDonnell Douglas Corp. v. United
States, 76 Fed. Cl. 385 (2007) (“McDonnell Douglas
XIII”). We heard oral argument on December 3, 2008.
Because the overall evidence of record supports a
conclusion that the government was justified in
terminating the contract for default, we affirin.

I. BACKGROUND

This American version of Jarndyce and Jarndyce
has entered its eighteenth year of litigation. The de-
tailed facts have been repeated many times pre-
viously. See, e.g., McDonnell Douglas XIII; McDonnell
Douglas Corp. v. United States, 323 F.3d 1006 (Fed.
Cir. 2003) (“McDonnell Douglas XII”); McDonnell
Douglas Corp. v. United States, 50 Fed. Cl. 311 (2001)
(“McDonnell Douglas XI”); and McDonnell Douglas
Corp. v. United States, 182 F.3d 1319 (Fed. Cir. 1999)
(“McDonnell Douglas X”). As we are writing what
necessarily will become “McDonnell Douglas XIV,” we
will only provide a summary of relevant facts here.

A. The A-12 contract

In January 1988, the Navy awarded the contrac-
tors a fixed-price research and development contract
for the A-12 stealth aircraft. The full-scale engineer-
ing and development (“FSD”) contract was structured
as an incrementally funded, fixed-price incentive
contract with a ceiling price of $4,777,330,294. The con-
tract incorporated by reference Federal Acquisition

4a

Regulation (FAR) 52.249-9 Default provision (Fixed-
Price Research and Development), which provides in
relevant part:

(a1) The Government may ... by
written Notice of Default to the Contractor,
terminate this contract in whole or in part if
the Contractor fails to —

(ii) Prosecute the work so as to en-
danger perforinance of this contract (but see
paragraph (a)(2) of this clause);

(2) The Government’s right to termi-
nate this contract under subdivisions (a)(1)(ii)
and (iii) of this clause may be exercised if the
Contractor does not cure such failure within
10 days (or more, if authorized in writing by
the Contracting Officer) after receipt of the
notice from the Contracting Officer speci-
fying the failure.

48 C.F.R. § 52.249-9 (1984).

Under the contract, the contractors were to de-
sign, manufacture, and test eight A-12 prototypes ac-
cording to a specified schedule, with the first aircraft
to be delivered in June 1990 (the “first flight” date)
and the remaining seven to be delivered monthly
through January 1991. The contractors were to con-
clude their testing of the aircraft by April 1993, the
completion time of the Navy’s technical evaluation
program (“[T'CHEVAL”). The contractors would also

5a

support the Navy’s evaluation of the aircraft and
further provide training support for three years after
delivering training equipment to the Navy in June
1993. In addition, the contract gave the Navy the
option to purchase four production lots of aircraft. In
May 1990, the Navy exercised its option on Lot I for
six aircraft to be delivered between June 1991 and
May 1992.

B. Modification of the A-12 contract

From the start, the contractors encountered diffi-
culties in performing the contract, including meeting
the contract schedule and keeping the aircraft weight
within specifications. McDonnell Douglas XII, 323
F.3d at 1011. Two weeks before the first flight date,
the contractors reported to the Navy that the pro-
jected first flight date would be July-September 1991,
instead of June 1990 as originally agreed, and the
remainder of the contract work would be delayed a
corresponding twelve to fourteen months. They also
predicted that the cost of completing the contract
would exceed the ceiling price so substantially that it
would be “unacceptable” to the contractors. The con-
tractors asserted that a fundamental problem with
the FSD contract was its fixed-price structure and
proposed that the contract be modified.

At the end of June 1990, the contractors missed
the first flight date. The Navy did not terininate
the contract. Instead, the contracting officer sent a
letter to the contractors in July, expressing “serious

6a

concern” regarding the deficient performance under
the contract. He warned that the contractors’ failure
to meet the first flight date “could jeopardize perfor-
mance of the entire [contract] effort.” He also asked
for the contractors’ plan to meet the rest of the origi-
nal schedule as well as their proposal for contract
revision.

As the parties failed to reach an agreement, on
August 17, 1990, the Navy unilaterally issued a con-
tract modification, P00046, which revised the proto-
type aircraft delivery dates but left Lot I and later
milestones intact. The delivery schedules are:

Aircraft Original P00046 Modified
Number Delivery Date Delivery Date
Prototype 1 June 1990 December 1991
2 July 1990 February 1992
3 August 1990 June 1992

4 September 1990 August 1992

5 October 1990 September 1992
6 November 1990 November 1992
7 December 1990 December 1992
8

|

9

January 1991 February 1993

Lot I June 1991
10 August 1991
ll October 1991
12 December 1991
13 March 1992

14 May 1992

7a

C. Performance after contract modification

After the contract modification, more problems
arose concerning the performance of the contract.
During the months leading to terinination, the con-
tractors’ internal schedules showed that they would
not meet the P00046 modified first flight date in
December 1991. McDonnell Douglas XIII, 76 Fed. Cl.
at 401. Instead, they projected three more months’
delay with the first flight date in March 1992. By
December 1990, the contractors’ “confidence in the
March 1992 flight date [was further] reduced.” They
believed that such a date was achievable “only after
significant changes.”

At the same time, the contractors continued oper-
ations, spending $120-150 million of their own money
every month. McDonnell Douglas XIII, 76 Fed. Cl. at
427. In November 1990, the contractors submitted a
formal request to the Navy to restru: ture the contract
as a cost-reimbursement type contract. McDonnell
Douglas X, 182 F.3d at 1322.

D. The termination

The contractors’ continued difficulties in perforin-
ing the contract led the Department of Defense and
the Navy to question the viability of the project. On
Friday, December 14, 1990, then-Secretary of Defense
Dick Cheney directed the Secretary of the Navy to
show cause by January 4, 1991, why the A-12
program should not be terminated.

8a

The following Monday, December 17, the Navy
issued a cure notice to the contractors, stating that
the government considered the contractors’ perfor-
mance under the contract “unsatisfactory.” In par-
ticular, the cure notice stated that the contractors
had “failed to fabricate parts sufficient to permit final
assembly in time to meet the schedule for delivery,”
and had “failed to meet specification requirements.”
The letter asserted that “these conditions [were] en-
dangering performance of [the] contract,” and that
unless these conditions were cured by January 2,
1991, the government might terminate the contract
for default.

In the following days, high-level meetings oc-
curred between the responsible government person-
nel and the contractors. McDonnell Douglas X, 182
F.3d at 1323. During these meetings, the contractors
asserted that they could not “get there if [they didn’t]
change the contract,” and that it “got to get reformed
to a cost type contract or [they could not] do it.” When
asked by the government if they could “correct defi-
ciencies to provide an aircraft that meets the require-
ments,” the contractors replied that “all deficiencies
cannot be corrected. ... Mother [NJature won’t allow
correction of all defects. We'll do the best we can and
the Navy has to decide if that’s good enough.”

On January 2, 1991, in responding to the cure
notice, the contractors admitted that they would “not
meet delivery schedules or certain specifi :tions of
the original contract, or the revised FSU delivery
schedule.” However, they denied that they were in

Ya

default because, in their view, the delivery schedules
were invalid. They asserted that “the furdamental
factual assumptions of the original contract, with
respect to schedule and achievability of certain speci-
fication requirements, were gravely mistaken,” and
therefore, “the schedules and certain other specifi-
cation requirements, such as weight, were impossible
to satisfy.” The contractors concluded that “[iJn these
circumstances, there [was] not an _ enforceable
schedule or specifications against which to measure
their performance.” They further declared that com-
pliance with the government’s demand to cure by
January 2, 1991 was “unachievable.”

However, the contractors stated that they were
“fully committed to the success of the [A-12] Program.”
They again submitted their proposal to restructure
the contract to a cost reimbursement contract. In ex-
change for that restructuring, the contractors wou'd
absorb a $1.5 billion fixed loss and would waive their
claims for equitable adjustment.

On January 7, 1991, Rear Admiral William
Morris, the contracting officer at the time, issued a
terinination letter to the contractors stating that the
government was terminating the A-12 contract due to
the contractors’ default. A few weeks later, the Navy
sent a letter to the contractors demanding the return
of approximately $1.35 billion in unliquidated pro-
gress payinents under the terminated contract.
McDonnell Douglas X, 182 F.3d at 1324.

10a

Il. LITIGATION HISTORY
A. The first round

In June 1991, the contractors sought relief in the
Court of Federal Claims under the Contract Disputes
Act, 41 U.S.C. § 609(a), requesting that the court: (1)
grant the contractors’ equitable adjustment claims,
(2) convert the government’s termination for default
into a termination for convenience, (3) deny the gov-
ernment’s demand for return of progress payments,
(4) award the contractors costs and a reasonable
profit under the contract, (5) award the contractors
settlement expenses, and (6) award damages for
breach of contract.

After several years of litigation, the Court ov
Federal Claims ruled that the government’s default
termination was invalid. McDonnell Douglas Corp.
v. United States, 35 Fed. Cl. 358, 368-71 (1996)
(“McDonnell Douglas IV”). It found that the con-
tracting officer failed to exercise “reasoned discretion”
before the default termination because Secretary
Cheney’s actions effectively forced the Navy to
terminate the A-12 contract for default. Jd. at 369-71.
Therefore, it vacated the government’s termination
for default and converted it into a termination for
convenience. Jd. at 361. The court ultimately denied
the government’s claim for return of $1.35 billion in
unliquidated progress payments, and entered judg-
ment of approximately $1.2 billion in favor of the
contractors. McDonnell Douglas Corp. v. United

lla

States, 40 Fed. Cl. 529, 555-56 (1998) (“McDonnell
Douglas IX”).

On appeal, we reversed, holding that because the
termination for default was related to the contractors’
performance, it was within the discretion of the
government. McDonnell Douglas X, 182 F.3d at 1321.
We remanded the case for the trial court to determine
whether the default termination was justified. /d.

B. The second round

After a six-week trial on remand, the Court of
Federal Claims ruled in favor of the government.
McDonnell Douglas XI, 50 Fed. Cl. at 319. The court
sustained the default termination based solely on the
contractors’ failure to meet the December 1991 first
flight date. Jd. at 315-19. It declined to base its de-
termination of justified default on the contractors’
alleged financial inability to perform the contract,
anticipatory repudiation, and failure to comply with
weight and other specification requirements. Jd. at
319-24. The court also rejected the contractors’ argu-
ments that the unilateral schedule was unreasunable
and therefore unenforceable, or, if enforceable then
the Navy waived the unilateral schedule and first
flight date of December 1991; that the contract was
commercially impossible to perform; and that the
Navy had to disclose its alleged superior knowledge
despite the assertion of the state secrets privilege. /d.
at 324-26. The court then entered judyinent in favor
of the government. /d. at 326.

12a

On appeal, we affirined the trial court’s de-
termination that the unilateral schedule imposed by
the government was enforceable and not waived, that
the Military and State Secrets privilege precluded
litigation of the contractors’ “superior knowledge”
claim, and that the government’s claim for progress
payments was not at issue in the case. McDonnell
Douglas XII, 323 F.3d at 1018-24. However, we held
that the trial court misapplied the controlling
standard in determining whether the default
termination was justified. Jd. at 1012-14. Therefore,
we again vacated and remanded. /d.

Specifically, we stated that a default te: mination
did not require “absolute impossibility of performance
or a contractor’s complete repudiation or abandon-
ment.” /d. at 1015. On the other hand, the govern-
ment cannot justify u default termination “based
solely on a contractor’s concerns about meeting a con-
tractual schedule milestone or specification require-
ments.” Jd. Instead, the government must establish
by a preponderance of the evidence of a “reasonable
belief on the part of the contracting officer that there
was no reasonable likelihood that the contractor
could perform the entire contract effort within the
time remaining for contract performance.” /d. at
1016. (citing Lisbon Contractors, Inc. v. United States,
828 F.2d 759, 765 (Fed. Cir. 1987)).

l3a

C. The third round

On remand, the Court of Federal Claims stated
as follows:

The case turns on whether the Circuit's
remand meant for the clauses, “entire con-
tract effort” and “contract completion date”
to mean exactly what they appear to mean —
the contractors’ expansive view; or whether
the remand permits our use of a more com-
pact yardstick — coinciding with the Govern-
ment’s restricted view. The Government did
not establish a contract closing date and the
contracting officer did not conduct a Lishon
analysis pnor to termination.

McDonnell Douglas XIII, 76 Fed. Cl. at 437 n.92. The
court concluded that the government could not “pre-
vail if the law requireld] an enforceable contract
completion date at termination,” but went on to state
that the government’s “burden of proof [did] not
necessarily require the Government to provide a
completion date for the entire contract effort.” Jd. at
388.

Based on its understanding that we “implied in
this case that a court may choose a reasonable period
of performance Lo use as uw measure of progress on the
contract,” id. at 420, the court found that the Navy’s
unilateral modification, POUO46, was a yardstick that
“enable[d] the court to consider the contractors’ pro-
gress in light of factors that are probative of their
ability and willingness to perforin,” id. at 389. Using
P00046 as the yardstick and considering “all of the

14a

relevant facts and testimony,” id. at 421, including
mitigating factors for the contractors, the court con-
cluded that the overall evidence of record supported
a conclusion that the government was justified in
tersninating the contract for failure to make progress,
id. at 430.

In addition, the trial court stated that the judg-
ment in the case mooted the government's alternative
argument that the contractors did not provide
adequate assurances to the contracting officer after
receiving the notice to cure. Jd. at 434.

The contractors timely appealed. We have juris-
diction pursuant to 28 USC. § 1295(a)(3).

Wl. DISCUSSION
A. Standard of review

Whether the government is justified in terminat
ing a contract for default is a question of law based on
factual underpinnings. McDonnell Douglas X, 182
F.3d at 1325. We review issues of law de novo, with-
out deference to the trial court. McDonnell Douplas
XII, 3823 F.3d at 1012 (citation omitted). However, we
will not disturb the trial court’s factual findings, such
us its evaluation of evidence of default, unless they
are clearly erroneous. /d.

15a

B. Analysis

1. Termination for failure to make progress
in the absence of a contract completion
date

In McDonnell Douglas XII, we quoted the
language from Lisbon in toto and directed the Court
of Federal Claims to determine “the perforimance
required by the contract’ and the contract completion
date.” 323 F.3d at 1018 (emphasis added, footnote
added). We acknowledge that this specific instruction,
if read literally, turns out to be difficult to apply. This
is largely due to the unique facts of this case and the
disadvantage we faced last time when deciding the
case without the benefit of sufficient fact findings
from the trial court. See id. at 1014.

The difficulty in strictly applying the Lisbon test
lies in the critical fact that P00046 revised the pro-
totype aircraft delivery dates but left Lot I delivery

‘ Generally, obligations arising from the exercise of an
option are part of a new contract only when the option was the
principal subject matter of the bargain, i.e., an option contract.
Alliant Techsystems, Inc. v. United States, 178 F.3d 1260, 1275
(Fed. Cir. 1999) (citing 3 Eric Mills Holmes, Corbin on Contracts
§ 11.1 (1996)). In this case, because the option to purchase Lot |
production aircraft is not the principal subject matter of the
original bargain, it is properly considered as part of the original
A-12 contract between the contractors and the government.
Thus, “the performance required by the contract” includes the
design, manufacturing, and testing of the eight prototype planes
under the FSD contract, the manufacturing and testing of the
six Lot I production aircraft, and other testing and supporting of
the project.

l6a

dates unchanged. As such, there is an overlap be-
tween the modified delivery schedule for the eight
prototype aircraft and the original delivery schedule
for the Lot I production aircraft. See Delivery Sched-
ules, supra. The government insists that the Lot I
schedule remains in effect because that portion of the
original contract was not modified by P00046. How-
ever, “[t]he A-12 contract was designed as a long-term
research and development effort, structured so that
each period of performance built upon preceding
work.” McDonnell Douglas XIII, 76 Fed. Cl. at 432.
Because the eighth test plane would serve as the
prototype for the Lot I aircraft, the contractors could
not have delivered Lot I aircraft according to the
original schedule as that would require delivering the
production aircraft prior to the prototype planes.
Therefore, we agree with the Court of Federal Claims
that the “[a]pplication of the contract in [the] manner
[advocated by the government] would be nonsensical.”
McDonnell Douglas XIII, 76 Fed. Cl. at 432. It follows
that the contract, as modified by P00046, does not
provide a definite contract completion date.” Id. at
401.

* The contractors offered legal principles, such as judicial
estoppel and waiver, to support this point. We do not believe it is
necessary to reach those arguments. Whether the contract has a
completion date is a question of fact. Common sense in this case
dictates the conclusion that “(t]he overlapping schedule offered
by the Government as a basis for assessing default is unrea-
sonable and likely unenforceable.” McDonnell Douglas XIII, 76
Fed. Cl. at 432.

17a

The contractors would have us apply the Lisbon
test literally and hold that the absence of a contract
completion date per se precludes the government from
ever justifiably terminating a contract for failure to
make progress. We cannot adopt such a broad cate-
gorical rule. The propriety of such a default terimi-
nation, even though ultimately a question of law, is a
fact-sensitive inquiry. The Lisbon test requires the
contracting officer’s reasonable belief that there was
no reasonable likelihood of timely completion. Lisbon,
828 F.2d at 765. Therefore, it is inevitable that some
case-by-case adjudication is required.

To be sure, just as the prior panel did, we re-
affirm that the test forinulated in Lisbon is a correct
standard for determining whether a default termi-
nation for failure to make progress is justified. How-
ever, this test was announced in view of the specific
facts presented in that case, where there was a
definite contract completion date. Lisbon, 828 F.2d at
761, 762. It did not address the situation where, as in
the present case, the contract does not specify a fixed
completion date. See United States v. Alaska S.S. Co.,
253 U.S. 113, 116, 40 S.Ct. 448, 64 L.Ed. 808 (1920)
(stating that a court “will deterinine only actual
matters in controversy essential to the decision of the
particular case before it,” and that it “is not em-
powered to decide .. . abstract propositions ... which
cannot affect the result as to the thing in issue in the
case before it”). As such, the Lisbon standard could
not be literally applied in every default termination
for failure to make progress case.

18a

We are confident that Lisbon does not, as the
contractors argue, foreclose a court’s review of a de-
fault te::nination for failure to make progress merely
because of an unascertainable contract completion
date. This is evident from Lisbon itself, in which the
court approved the Claims Court’s citation and
interpretation of Universal Fiberglass Corp. v. United
States, 210 Ct. Cl. 206, 537 F.2d 393, 397 (1976).
Lisbon, 828 F.2d at 765.

Universal Fiberglass involved a supply and
service contract for more than 12,000 mail delivery
trucks. 537 F.2d at 394. The contractor in that case
repeatedly failed to meet the installment delivery
schedule, even after several extensions of time. /d. at
394-95. It closed down almost all of the production
lines and laid off most of its labor force. Jd. at 395.
Meanwhile, a government audit showed that the
contractor was insolvent. Jd. Time and again, the
government asked the contractor to furnish its pro-
posed revised delivery schedule, but to no avail. /d.
The government issued a Preliminary Notice of
Default and gave the contractor ten days to cure all of
its defaults. Jd. at 396. After the contractors waived
its rights to the full ten-day notice period, the gov-
ernment promptly terminated the contract for failure
to make progress. /d.

* Universal Fiberglass was also cited with approval by the
previous two panels in deciding the present case. See McDonnell
Douglas X, 182 F.3d at 1328; McDonnell Douglas X/JI, 323 F.3d
at 1015.

19a

The Court of Claims held that the contract was
properly terminated for failure to make progress. Jd.
The court found that in the absence of a delivery
schedule, i.e., the contract completion date, the “cure
notice” served the purpose of advising the contractor
when the time for default has been reached. Jd. at
398. The court reasoned:

The contractor had already been asked
to submit a new delivery schedule and had
not done so. Nor had the contracting officer
learned, from the contractor or any other
source, any information to lead him to be-
lieve that deliveries would or could ever be
resumed. In such circumstances, a unilateral
delivery schedule prescribed by him would
have been an exercise in futility, except for
forensic purposes, should we be so foolish as
to give the absence of such a schedule any
lega’ significance or weight.

Id.

We realize that the facts in Universal Fiberglass
are not exactly the same as in the present case. First,
the difficulties in designing and manufacturing
stealth aircraft are incomparable tu those in making
small three-wheeled mail delivery trucks. More
importantly, as the contractors correctly point out, in
Universal Fiberglass, the contractor “was making no
progress at all, had never manufactured a vehicle
under the new specifications it had agreed to, did not
have the necessary parts and could not obtain them
and had allowed its labor force to wither away.” Jd. at

20a

398. In contrast, in the present case, “[dJespite de-
lays, the contractors continued operations. They were
spending $120 to $150 million of their own money
every month. They were committed to perfor: ming
the A-12 contract until the date of termination.”

McDonnell Douglas XIII, 76 Fed. Cl. at 427.

However, the contractors’ commitment to per-
forming the contract was not without conditions.
Starting from as early as June 1990, the ccitractors
had asserted that “the A-12 contractual schedule
[was] not achievable and need[ed] to be changed.”
They also predicted that the cost of completing the
contract would exceed the ceiling price so sub-
stantially that it would be “unacceptable” to the con-
tractors. Insisting that the A-12 project could not “be
accomplished under a fixed price type contract with-
out [solving] the financial, schedule and specification
problems,” the contractors proposed that the contract
be modified. The contractors maintained this position
throughout their performance of the A-12 contract.

After missing the original first flight date, “[tJhe
contractors were working to an aggressive schedule,
but they would not sign up for one.” McDonnell
Douglas XIII, 76 Fed. Cl. at 399. Because the con-
tractors rejected the government’s proposal of a bi-
lateral modification of the contract, the government
imposed the unilateral modification of the delivery
schedule for the prototype airplanes, P00046, “as a
first step in achieving the overall delivery schedule.”

McDonnell Douglas XIII, 76 Fed. Cl. at 400.

2la

P00046 extended the first flight date from June
1990 to December 1991. The contractors’ projected
delivery date, however, further slipped away. “Six
months prior to termination, the contractors projected
a twelve to fourteen-month delay in first flight [June-
August 1991]. By termination, the contractors’ ex-
pectations extended first flight to March 1992.”
McDonnell Douglas XIII, 76 Fed. Cl. at 422. In fact,
by December 1990, the contractors’ confidence in even
the March 1992 flight date was reduced. They
believed that such a date was achievable “only after
significant changes.” As the trial court found, “Navy
officials ... could not predict when the contractors
would deliver first flight.” McDonnell Douglas XIII,
76 Fed. Cl. at 401.

As the contractors themselves emphasize, “one
cannot test an aircraft before it has been built, nor
build a production airplane before developing its
prototype.” Therefore, without the timely delivery of
the prototype airplanes, there would be no basis for
the government to prescribe a new delivery schedule
for Lot I aircraft. In this sense, similar to the Court of
Claim’s opinion in Universal Fiberglass, we believe
requiring the contracting officer to artificially reset
the contract completion date would have been “super-
erogatory,” “except for forensic purposes.” See Uni-
versal Fiberglass, 210 Ct. Cl. at 217, 5387 F.2d 393.
Therefore, we agree with the trial court that this case
is similar to Universal Fiberglass in that

a schedule is not necessary because
the cure notice supplants the schedule and

22a

serves a similar function. The cure notice
lets a contractor know that even if per-
formance or delivery is not yet due, the
contracting officer believes the contractor
may not be making sufficient progress to
complete the contract on time. The burden is
then on the contractor to advise the Gov-
ernment how it will complete the project on
time, according to contract requirements.

Id. at 419.

One could analogize the per se rule advocated by
the contractors to an injunction against the govern-
ment. In granting or denying an injunction, a court
follows traditional equitable principles and “balances
the conveniences of the parties and possible injuries
to them” to arrive at a “nice adjustment and recon-
ciliation” between the competing claims. Weinberger
v. Romero-Barcelo, 456 U.S. 305, 312, 102 S.Ct. 1798,
72 L.Ed.2d 91 (1982). When a government contract is
terminated, there are two interests at issue — the
contractor’s interest in holding the government to its
obligation to carry out the contract, and the govern-
ment’s interest in not wasting taxpayer dollars. The
contractors in this case, however, would have us en-
join the government from ever terminating a contract
for failure to make progress based on a single factor —
the contract lacks a set completion date. We reject
such a per se rule because it serves only the con-
tractors’ interest. Instead, we favor an ad hoc, factual
inquiry that allows careful examination and weighing
of all relevant circumstances. See McDonnell Douglas

23a

XII, 323 F.3d at 1014 (stating that “[iJn determining
whether a default terrnination was justified, a court
must review the evidence and circumstances sur-
rounding the termination, and that assessment in-
volves a consideration of factual and evidentiary
issues”).

In fact, in our 2003 opinion, we provided the
same guida: ce, stating that to determine whether a
default termination is justified, “the trial court should
focus on the events, actions, and communications
leading to the default decision in ascertaining
whether the contracting officer had a reasonable
belief that there was no reasonable likelihood of
timely completion.” McDonnell Douglas XII, 323 F.3d
at 1017. Of course, in some cases, it is possible that a
conclusion drawn from a comparison of the entire
contract effort and the time remaining for contract
performance is so clear that it becomes dispositive.
See Lisbon, 828 F.2d at 765. However, in cases such
as the present one, where such a comparison is
inapplicable, the court must examine other factors,
including the contractor’s failure to meet progress
milestones, its problems with subcontractors and
suppliers, its financial situation, and its performance
history. See McDonnell Douglas XII, 323 F.3d at 1017.
Only after analyzing the totality of the circumstances
can a court determine whether a contractor failed to
“(plrosecute the work so as to endanger performance”
of the contract. See 48 C.F.R. § 52.249-9.

24a

2. Default termination of the A-12 contract

It is true that the A-12 contract, as modified by
F00046, lacks a definite contract completion date.
E owever, this single factor, even though important, is
insufficient to support the contractors’ contention that
the government cannot sustain the default termina-
tion. A court must also take into account other
relevant facts and testimony in deciding whether the
default termination was justified.

In Lisbon, we held that the government bears the
burden of justifying the propriety of a default
termination. 828 F.2d at 765. We also stated that “the
contracting officer’s termination decision [must] be
based on tangible, direct evidence reflecting the im-
pairment of timely completion.” McDonnell Douglas
XII, 323 F.3d at 1016 (citing Lisbon, 828 F.2d at 766).
The direct evidence includes the contractors’ “state-
ments that they could not meet the contract specifi-
cations, the contract delivery schedule, nor complete
performance at the specified contract price.” Jd. at
1013 (quoting McDonnell Douglas X, 182 F.3d at
1332). The direct evidence also includes the “con-
tracting officer’s testimony and contemporaneous
documents.” /d. at 1016. The Court of Federal Claims
made detailed factual findings based on the evidence.
McDonnell Douglas XIII, 76 Fed. Cl. at 422-30. After
reviewing the record, we see no clear error. Therefore,
we only highlight a few important aspects here.

25a

a. Contractors’ performance history and
failure to meet progress milestones

The contractors missed several milestones under
the origina] contract, the most significant of which, of
course, is the June 1990 first flight date. They also
missed the July 1990 delivery date for the second
prototype airplane. More tellingly, after the govern-
ment unilaterally modified the contract through
P00046, and in fact, in their response to the cure
notice, the contractors unequivocally stated that they
would not meet the revised delivery schedule for the
eight prototype airplanes. Instead, they projected
that the first flight date would be in March 1992,
three months after the date imposed in P00046. By
December 1990, the contractors were only “50%” con-
fident in this date, believing it was achievable “only
after significant changes.”

The contractors and the amicus curiae argue that
if we uphold the default termination here, the gov-
ernment may terminate for failure to make progress
a contract for any minor slippage in meeting any
insignificant interim milestone. This is an exaggera-
tion. First of all, due to the sequential “building
block” structure of the A-12 contract, delivery of the
prototype airplanes is not just any milestone. It is
certainly not an insignificant milestone. Quite to the
contrary, it is clearly one of the most important mile-
stones in the entire contract. This is because, as the
contractors admit, “one cannot test an aircraft before
it has been built, nor build a production airplane
before developing its prototype.”

26a

Second, the delay in the delivery schedule is
hardly just a minor slippage. The A-12 contract
provided the June 1990 first flight date. In other
words, it provided the contractors thirty months from
the contract award time (January 1988) to deliver the
first prototype plane. P00046, in extending the first
flight date to December 1991, gave the contractors 60
percent more time to reach this significant milestone.
Yet, the contractors, even though at first predicting
that they would, concluded that they could not meet
this schedule. In fact, they were not even sure if they
could deliver in March 1992. According to the con-
tractors’ own estimate, even assuming they could
meet the March 1992 first flight date, they would not
complete the design, manufacturing, and testing of
the aircraft until July 1995, two years and three
months after the Apnml 1993 TCHEVAL deadline
specified in the original contract.

More importantly, we are not upholding the
default termination “based solely on a contractor’s
concerns about meeting a contractual schedule
milestone.” McDonnell Douglas XII, 323 F.3d at 1015
(citing Lisbon, 828 F.2d at 765). As we explained
above, the contractors’ failure to meet progress mile-
stones is one factor to he considered in the totality-of-
the-circnmstances analysis. In this respect, we agree
with the trial court that

[mjissed milestones “indicate a pattern
of nonperformance and delay which should
not be ignored. Although not justifications
for default in themselves, they provide a

27a

context for understanding and evaluating
plaintiff’s continued problems.” Such infor-
mation should be relevant if we consider
whether a reasonable contracting officer
might reasonably have been concerned about
[the contractors’] ability to complete the
contract on time.

McDonnell Douglas X11, 76 Fed. Cl. at 426 (quoting
Universal Fiberglass, 537 ¥.2d at 397).

b. Contractors’ financial situation

Another piece of relevant inforimation we con-
sider when reviewing a default termination is the
contractors’ financial situation. “Ihe cost to complete
a contract — more particularly, the inability of a con-
tractor to perform a contract at the specified contract
price ... [is a] fundamental element | of government
contracts and [is] related to contract perforinance; as
such, [it is] highly relevant to the question of default.”
McDonnell Douglas X, 182 F.3d at 1328.

The A-12 contract as initially awarded had a
target contract price of $ 4,379,219,436 and a ceiling
price of $ 4,777,330,294. In June 1990, the contrac-
tors proposed that the fixed-price contract be modi-
fied because the cost of completing the contract would
exceed the ceiling price so substantially that it would
be “unacceptable” to the contractors.

The contractors repeatedly insisted on restruc-
turing the contract from a fixed-price contract to a
cost-reimbursement type contract. Even during the

28u

high-level negotiation meetings following the govern-
ment’s issuance of the cure notice, Mr. John
McDonnell, the CKO of MDC, asserted that the
contractors “can’t pet there if we don’t change the
contract,” and that the contract “has pot to yet
reformed to a cost type contract or we cannot do it.”
In their January 2, 1991, written response to the cure
notice, the contractors again submitted their proposal
to restructure the contract to a cost reimbursement
contract. In exchange for that restructuring, the con
tractors would absorb a $1.5 billion fixed loss and
would waive their claims for equitable adjustment.
The sizeable concession the contractors were willing
to make further illustrates the grave inadequacy of

the contract price.

Of course, the difficulty in the contractors’ finan
cial situation, in and of itself, may not be sufficient
to justify the default termination. See McDonnell
Douglas XI, 50 Fed. Cl. at 320-21 (ruling that the
contractors’ financial condition “was not endangering
performance of the A-12 contract”). However, in this
case, “inadequate financing is not collateral | because}
it pervades the entire contract.” Universal Fiberglass,
210 Ct. Cl. at 216. Indeed, in the months leading
to the termination, the contractors were spending
$120-150 million of their own money every month.
McDonnell Douplas XIII, 76 Fed. Cl. at 427. Captain
Lawrence Elberfeld, the Navy's A-12 Program Man-
ager, testified that the cost to complete the A 12
contract would be so “unthinkably” over the fixed-
price ceiling that the contractors’ internal “worst case

29a

estimate could bankrupt both corporations.” /d. at
429.

More importantly, Captain Elberfeld testified
that the cost overruns jeopardized the contractors’
performance because the contractor engaged in “cost
cutting efforts like reducing staff, eliminating over-
time, quick fixes that address and would remedy a
cash flow situation.” Jd. at 428. For example, around
the time when the contractors missed the original
first flight date, they removed 110 people from the A-
12 program. /d. Captain Elberfeld concluded that the
contractors’ cost cutting efforts to avoid bankruptcy
led to “more corner-culting and more incomplete ef-
fort and basically a longer process to get a product
that may not be the product that we desire or need
for the Navy.” /d. at 429.

ce. Conclusion

In summary, the government offered the con-
tracting officer’s testimony, the contractors’ state-
ments, and contemporary documents as direct evidence.
The evidence, such as the contractors’ performance
history (e.g., the failure to meet several milestones,
including the significant first flight), coupled with the
contractors’ dire financial difficulty, which negatively
impacted their performance under the contract,
shows that the contracting officer was reasonably
justified in feeling insecure about the contractors’
rate of progress. Therefore, the government has

30a

satisfied its burden to justify the default te:r:ni-
nation.*

Once the government has met this burden of
proving that timely performance is beyond the
contractors’ reach, the contractors have the burden of
going forward to prove either that they were making
progress such that timely completion of the contract
was not endangered or that there was excusable
delay. See Appeal of Mich. Joint Sealing, Inc., ASBCA
No. 41477, 93-3 BCA 26,011 (Apr. 26, 1993). On
appeal, the contractors assert no affirmative defense.
They proffer no record evidence to show, without con-
tract restructuring, that they could have completed
the contract on any date. Certain arguments, such as
waiver, are presented to support their proposition
that, at termination, the A-12 contract lacked an
enforceable completion date. Even if these arguments
could be interpreted as the contractors’ defenses, we
have already addressed them elsewhere in this
opinion. In conclusion, because the government was
justifiably insecure about the contract’s timely com-
pletion and the contractors do not argue that their

* Our current analysis may appear different from the one
we previously instructed the trial court to perform, specifically,
to determine the contract completion date. See McDonnell
Douglas XII, 323 F.3d at 1018. We believe that this is warranted
as under the law of the case doctrine, “it is not improper for a
court to depart from a prior holding if convinced that it is clearly
erroneous and would work a manifest injustice.” Arizona v.
California, 460 U.S. 605, 619, 103 S. Ct. 1382, 75 L. Ed. 2d 318
(U.S. 1983).

3la

failure to make progress could be excused, we sustain
the default termination of the A-12 contract.

3. Default termination without contracting
officer’s Lisbon analysis

The contractors and the amicus curiae also assert
that we cannot uphold the default termination be-
cause the contracting officer, Admiral Morris, did not
conduct the Lisbon analysis before the termination.
They base this argument on the trial court’s finding
that “Admiral Morris did not determine the entire
effort required and the time left to complete that con-
tract effort prior to termination.” McDonnell Douglas
XIII, 76 Fed. Cl. at 424 n.72; see also id. at 437 n.92
(concluding “the contracting officer did not conduct a
Lisbon analysis prior to termination”). This argument
is unpersuasive.

First of all, as we have stated earlier, because the
modified A-12 contract does not contain a fixed
completion date, a Lisbon analysis cannot be strictly
applied. Second, we previously stated that “the gov-
ernment is not required to establish that the con-
tracting officer conducted the analysis necessary to
sustain a default under the alternative theory.”
Empire Energy Mgmt. Sys. v. Roche, 362 F.3d 1343,
1357 (Fed. Cir. 2004); see also Christopher Vill., L.P. v.
United States, 360 F.3d 1319, 1337 (Fed. Cir. 2004)
(“This court sustains a default termination if justified
by circumstances at the time of termination, regard-
less of whether the Government originally removed

32a

the contractor for another reason.” (quoting Kelso v.
Kirk Bros. Mech. Contractors, Inc., 16 F.3d 1173, 1175
(Fed. Cir. 1994))).

The contractors and the amicus curiae attempt to
distinguish the present case from Empire Energy. The
amicus curiae emphasizes that there is a “critical
distinction between failure to make progress as the
asserted basis for default at the time of termination,
and failure to make progress as an alternative basis
for default, proven at trial, that supports an other-
wise unsustainable termination for failure to timely
deliver.” We discern no such distinction. In fact, the
amicus’s contention is illogical-it would have us, on
the one hand, uphold a default termination for failure
to make progress when the contracting officer never
even contemplated, much less evaluated, such a
basis; while at the same time, reject another default
termination for failure to make progress even though
the contracting officer explicitly asserted such a
basis.

More importantly, we are less concerned about
the label of the contracting officer’s action so long as,
in fulfilling his duty, the contracting officer exercised
reasoned judyiment and did not act arbitrarily. After
reviewing the record, we believe that the contractors
are not victims of arbitrary government action.
Admiral Morris testified that concerns about the A-12
Program “increased [and] the risks increased” in the
fall of 1990. Jd. at 424 n.70. The trial court found that

33a

lals the end of 1990 approached, |Ad-
miral Morris] was concerned that substantial
development on the aircraft had yet to occur.
He testified “[t]he contractors were indi-
cating that they were experiencing an over-
run that they could not absorb. Cost was
obviously a factor and their failure to
fabricate components, their failure to meet
schedule were clearly impacting cost.”

Id. at 423-24.

Admiral Morris also testified that in the weeks
leading to termination, the contractors “indicated
that they would not be able to meet the delivery
schedule that was currently in the contract. And they
would not be able to perforin the contract without
extraordinary relief or additional funding for the
contract.” Jd. at 424 (alterations omitted). He ex-
plained: “I didn’t know at that particular time when
in fact they would be able, if ever, to achieve
performance of the contract and I was hearing ‘we
will not’ or ‘we could not.’” Jd. (alterations omitted).

On December 17, 1990, Admiral Morris issued a
cure notice, warning the contractors that their per-
formance was “unsatisfactory” and the defect condi-
tions were “endangering performance” of the contract.
He explained that “[t]lhe purpose of the cure notice
was to advise the contractors they were failing to
make progress.” McDonnell Douglas XIIl, 76 Fed. Cl.
at 402. He testified that he “had been extremely
concerned with the communications coming in from
the contractors that unless extraordinary relief were

34a

provided, unless the contract were restructured into a
cost-type contract, that they could not or would not
perform, and that belief existed certainly on De-
cember 17th.”

Admiral Morris considered the problems of cost
overruns to be a “real issue.” McDonnell Douglas
XIII, 76 Fed. Cl. at 404. Even though he made an
effort to resolve the issue “within the context of the
contract” without restructuring the contract, “the
contractors were insisting upon Public Law 85-804
extraordinary relief.”” Even in their January 2, 1991,
written response to the cure notice, the co

[Text truncated at 120,000 characters. The full text is on the page linked above.]

---