IN THE
Puneet ofthe Hed State

ie oe

Nos.-#4#, 768, 769, and 776

Dramimea & Exproration Company, J. R.
) FRANKEL, ET AL., J. Ray McDerMort & Co., INO.,
© Due Superior On. Company, Petitioners,

Vv.

Power Commission, Pusiic Service CoMMIs-
siON OF THE State or NEw York, THE UNITED

inc Company, Respondents.

ON PETITIONS FOR WRITS OF CERTIORARI TO THE
UNITED STATES COURT OF APPEALS FOR
THE FIFTH CIRCUIT

BRIEF FOR PUBLIC SERVICE COMMISSION
OF THE STATE OF NEW YORK IN OPPOSITION

c QUESTION PRESENTED
“Where prior to completion of appeal proceedings

ehallenging the Federal Power Commission’s issuance
Va certificate of public convenience and necessity, a

tu gas producer commences service under the cer-
pai, which later is held invalid on the ground that
initial price thereunder is out of line, does the
A hission, on remand, have power to require refunds
ithe excess amounts collected by the producer under

p invalid certificate?

2

STATEMENT

By orders issued September 4, 1958 and August 10,
1959, the Federal Power Commission, over the objection
of the Public Service Commission of the State of New
York and other consumer interests, granted uncondi-
tional certificates to a substantial number of natural
gas producers, including the four petitioners here, au-
thorizing them to commence the sale of natural gas
from Louisiana fields at initial prices ranging from
21.4¢ to 23.8¢ per Mef. On appeal, the Commission’s
actions were reversed and the several cases remanded.'

In the meantime, however, and notwithstanding the
pendency of the appeals, the present petitioners com-
menced service under the unconditional certificates and
collected the high initial price that was the basis for
the legal attack on, and judicial invalidation of, the
certificates. Following hearings on remand, the Com-
mission determined that the maximum initial price at
which these sales should have been certificated was 20¢
per Mef, including 1.5¢ tax reimbursement where ap-
plicable, and, to give effect to this finding, it issued
new certificates at that level and directed petitioners to
refund all amounts in excess of 20¢ per Mcf which had
been collected under the original, judicially invalidated
certificates.

eee

1 Public Service Commission of New York v. F.P.C., 361 U.S. 195
(1959) ; United Gas Improvement Co. v. F.P.C., 283 F. 2d 817
(9th Cir. 1960), cert. denied, 365 U.S. 879, 881 (1961); Public
Service Commission of New York v. F.P.C., 287 F. 2d 146 (D.C.
Cir. 1960), cert. denied, 365 U.S. 880, 882 (1961); United Gas
Improvement Co. v. F.P.C., 287 F. 2d 159 (10th Cir. 1961) ; United
Gas Improvement Co. v. F.P.C., 290 F. 2d 133 (5th Cir. 1961),
cert. denied, 368 U.S. 823 (1961) ; United Gas Improvement Co. v.
F.P.C., 290 F. 2d 147 (5th Cir. 1961), cert. denied, 366 U.S. 965
(1961).

3

On appeal by petitioners and other producers, the
Court of Appeals for the Fifth Circuit, though revers-
ing other aspects of the Commission’s order,’ held that,
on remand, the Commission had power to require re-
funds of ‘‘the fruits obtained [by petitioners] under
an invalid, that is illegal, order.”’ Callery Properties,
Ine. Vv. F.P.C., 335 F.2d 1004 at 1019.

ARGUMENT

Although, for the reasons stated in its own petition
for a writ of certiorari (O.T. 1964, No. 678, filed
November 12, 1964), the Public Service Commission
of the State of New York believes that the decision be-
low urgently requires review and, indeed, summary
reversal by this Court, it does not believe that the nar-
row aspect of the decision below presented by peti-
tioners in Nos. 714, 768, 769, and 776 merits certiorari.

1. The issue raised by petitioners was rightly decided
below.

a. The Commission’s determination to require re-
funds of excess amounts was eminently correct, and
was, in fact, required by this Court’s landmark deci-
sion in Atlantic Refining Co. v. Public Service Com-
mission of New York (Catco), 360 U.S. 378 (1959),
in which the Commission’s unconditional certification
of a 21.4¢ Louisiana sale was struck down precisely
because it would permit the producers to retain, with-
out refund obligation, an out-of-line price during the
“nigh interminable” period between initial certifica-

® The court’s action in reversing the Commission is the subject
of pending petitions for certiorari in F.P.C. v. Callery Properties,
Inc., 0.T. 1964, No. 756; Public Service Commission of New York
v. Oallery Properties, Inc., O.T. 1964, No. 678; United Gas Im-
provement Co. v. Callery Properties, Inc., 0.T. 1964, No. 671.

4

tion and the ultimate conclusion of a rate investiga-
tion. Here, where there has been a ‘‘nigh intermina-
ble’’ delay of four to five years between initial, invalid
certification and lawful certification on remand, the
producers nevertheless urge that, as a matter of law,
they cannot be required to refund the excess amounts
collected during this period. Acceptance of the pro-
ducer position, however, would result in ‘‘a windfall
for the natural gas company 9d a consequent squall
for the consumers,’’ 360 U.S. «. 390, thereby frustrat-
ing the

‘“‘overriding intent of the Congress to give full

gig My coverage to the consumer as to price.”
U.S. at 389.

b. Not only are refunds necessary to meet the sub-
stantive requirements of the Act, as spelled out by this
Court in Catco, supra, but they are necessary, as a
remedial measure, to carry out the purpose of the re-
versal of the original, unlawful certificates and to as-
sure that the petitioners in the earlier appeals will be
made whole.

e. Wholly aside from the Commission’s power on
remand to correct the errors laid bare by the earlier
appeals, the express conditioning power conferred by
Section 7(e) of the Natural Gas Act’ provides ample
authority for the Commission to condition its issuance
of the new certificates upon the applicants’ refunding
all excess amounts collected under the invalid certifi-
cates. See F.P.C. v. Hunt, 376 U.S. 515 at 521 (1964).

$< he “‘ommission shall have the power to attach to the issu-
ance of the certificate and to the exercise of the rights granted there-
under such reasonable terms and conditions as the public con-
venience and necessity may require.’’

d. In electing to commence service at a time. when
. the validity of their certificates was under attack, the
present petitioners necessarily assumed the risk that
the certificates might be rendered invalid. See Vir-
ginia Petrolewm Jobbers Ass’n v. F'.P.C., 259 F.2d 921
at 927 (D.C. Cir. 1958). The producer contention that
the consumer representatives, the successful petition-
ers in the earlier appeals, either could have or should
have obtained a stay of the invalid certificates pending
appeal is devoid of merit; no stay was available pre-
cisely because those petitioners, if successful, could be
made whole through refunds on remand, Id., 259 F.2d
at 925-27.

2. There is no conflict between the decision below
(insofar as it sustains the Commission’s power to or-
der refunds) and the decision of any other circuit or
of this Court.

Although petitioners correctly cite Montana-Dakota
Utilities Co. v. Northwestern Public Service Co., 341
U.S. 246 (1951), and related cases* for the proposition
that the Commission has no power, under Section 5 of
the Act, to require refunds of excess amounts collected
under a rate which has assumed finality, they overlook
the fact that, as noted by the Commission at the very
outset of these remanded proceedings (27 FPO 482 at
483, R. 411):

[The] unconditional certificate orders under Sec-
tion 7 were erroneously issued in the first place
and as a result of the invocation of Section 19 have
never assumed finality.’’

- *TIM_E. v. United States, 359 U.S. 464 (1959) ; F.P.C. v.. Hope
Natural Gas Co., 320 U.S. 591 (1944); Hope Natural Gas Co: ¥.
FP.C., 134 F. 2d 287 (4th Cir. 1948). ;

6

Absent finality, of course, the filed-rate doctrine of
Montana-Dakota has no applicability. See, ¢.g., Pub-
lic Service Commission of New York v. F.P.C., 329
F.2d 242 at 249 (D.C. Cir. 1964), cert. denied sub nom.
Prado Oil & Gas Co. v. F.P.C., 377 U.S. 963 (1964)
Pan American Petroleum Corp. v. Kansas-Nebraska
Natural Gas Co., 297 F.2d 561 (8th Cir. 1962), cert.
denied, 370 U.S. 937; Cities Service Gas Co. v. Colum-
bian Fuel Corp., 52 Del. 262, 155 A.2d 879 (1959).

CONCLUSION
In sustaining the Commission’s power to order re-
funds of excess amounts, the decision below was emi-
nently correct and presents no conflict with the deci-
sion of any other circuit. Accordingly, the petitions
for a writ of certiorari should be denied.

Respectfully submitted,

Kent H. Brown, Counsel
55 Elk Street
Albany, New York

Morton L. Smons
1815 H Street, N. W.

Washington, D. C.
Attorneys for Respondent
January 11, 1965

5 The arguments now presented by Ocean Drilling, petitioner in
No. 714, are virtually identical with the arguments unsuccessfully

by Prado Oil & Gas Co. last term. See Prado Oil & Gas
Co. v. F.P.C., 0.T. 1963, No. 987, petition pp. 8-10.

---