# Appendix — Beazer East, Inc. v. Mead Corp.

> Briefs, arguments, decisions, and more.

URL: https://www.frixlaw.com/law-library/documents/brief%3Amicro_IA40386016_0375%3A2

## Record

- **Collection:** Supreme Court brief
- **Document type:** Appendix
- **Published:** January 1, 2006
- **Citation:** 546 U.S. 1091

## Text

10a

through December 31, 1999, were recoverable CERCLA
response costs. In August 2002 the District Court issued a
thorough opinion largely rejecting Mead’s challenges to
Beazer’s costs. The court determined that Beazer had incurred
recoverable response costs of $4,805,137.60 through the end
of 1999 and entered judgment against Mead for 67.5% of this
amoumt, or $ 3,243,467.80. Pursuant to the parties’
stipulation, in September 2002, the Court further ordered
Mead to pay pre-judgment interest in the amount of
$1 ,538,164.03. Finally, in October 2002, the District Court
entered a declaratory judgment requiring Mead to pay 67.5%
of Beazer’s ongoing response costs associated with
implementing the AOC. The order also provided a framework
for resolution of disputes over the necessity and NCP-
consistency of such costs.

Mead timely appealed these orders. In December 2002,
we assigned the case for mediation pursuant to the Third
Circuit's Appellate Mediation Program, L.A.R. 33. The
parties strenuously dispute what transpired at the February
26, 2003, mediation session. Beazer claims that the parties
reached an oral agreement while Mead claims that the
tentative agreement reached at mediation was conditioned on
further management approval which was ultimately denied. In
May 2003, Beazer moved this Court to enforce the alleged
oral settlement and dismiss Mead’s appeal with prejudice. The
motion was referred to this panel and we decide it here along
with Mead’s appeals.

III .Jurisdiction

The District Court had jurisdiction over this case under 42
U.S.C. § 9613(b), which vests exclusive jurisdiction of
CERCLA claims in the federal courts, as well as under 28
U.S.C. §§ 1331 and 1332. Horsehead Industries, Inc. v.

lla

Paramount Communications, Inc., 258 F.3d 132, 140 (3d
Cir. 2001); Beazer 1, 34 F.3d at 210. We have appellate
jurisdiction over the appeal from the District Court's final
orders described above pursuant to 28 U.S.C. § 1291.
Horsehead Industries, 258 F.3d at 140. Finally, we have
original jurisdiction over Beazer’s motion to enforce the
alleged settlement agreement. See Fed. R. App. Pro. 33
(“The court may, as a result of the [mediation], enter an order
controlling the course of the proceedings or implementing any
settlement agreement.”). See aiso Herrnreiter v. Chi. Hous.
Auth. , 281 F.3d 634, 637 (7th Cir. 2002).

V. Discussion
A. Enforcement of the alleged oral settlement.

Beazer’s motion to specifically enforce the alleged oral
settlement reached at the appellate mediation and to dismiss
this appeal with prejudice must be rejected. Both Local
Appellate Rule (LAR) 33.5 and sound judicial policy compel
the conclusion that parties to an appellate mediation session
are not bound by anything short of a written settlement. Any
otlier rule would seriously undermine the efficacy of the
Appellate Mediation Program by compromising the
confidentiality of settlement negotiations.‘

* Federal Rule of Appellate Procedure 33 gives appellate courts the
power to order settlement conferences and to “implement{]} any
s>ttlement agreement” reached as a result of such conferences. Fed.
R. App. P. 33. The Third Circuit has established an Appellate
Mediation Program to implement this general directive. Local
Appellate Rule 33.0. The program is subject to the rules and
procedures provided in the Local Appellate Rules. /d.

12a

Beazer requests enforcement of the alleged oral settlement
but admits that there are genuine factual disputes regarding
whether the parties actually reached an agreement.’ Mead
correctly argues that we cannot resolve these disputes without
violating the confidentiality rule, LAR 33.S(c). With
exceptions not relevant here, Rule 33.5( The court agrees with Mead as to two particular costs placed in
this category by Dr; Ball. It is well settled that RCRA does not in
itself provide for the recovery of past costs incurred in the
treatment, storage and disposal of hazardous wastes. See Meghrig
vy. KFC Western, Inc., 516 U.S. 479, 484 (1996). Consequently,
recovery is appropriate under a RCRA-based program only where
recovery of the claimed costs is warranted under CERCLA. Id. at
487-88. The $6,000.00 post-closure application fee paid to ADEM
reflects a purely administrative RCRA cost and the cost itself lacks
any potential to contribute to the characterization of the site or the
evaluation of potential remedial measures. Thus, it will be

89a

Mead’s contention that its CERCLA liability was
extinguished by Beazer’s submission of a risk assessment to
the environmental agencies on March 3, 1997, also is
Unavailing. At the completion of Phase I and II of the RFI
Beazer submitted a risk assessment to ADEM as an appendix
to its report on those phases. The risk assessment was

excluded.

In addition, Beazer agreed that a deduction is appropriate for
the costs of installing and monitoring the wells for one of the post-
closure units because one unit was created exclusively by Beazer’s
operations at the site. Beazer deducted $365,299.00 from its
Claimed costs as reflective of installing and monitoring four RCRA
ground wells at a hypothetical RCRA regulated unit. This
calculation was made based on the estimated costs which would
have been required by the K060 regulated unit at the site.
Testimony from Beazer’s environmental project manager indicated
that the unit had five wells associated with it, not four. Based On
Beazer’s average cost for each of the four wells, an additional
deduction of $91,324.75 is appropriate.

The remaining costs placed in the “C-1” category by Dr. Ball
are recoverable. Dr. Ball reviewed Beazer’s invoices to determine
whether on their face the invoices reflected activities that “were
referenced in the risk assessment or were reasonably necessary to
produce the risk assessment.” TT of February 5, 2002 (Ball) at 94;
see also id. at 95. If the invoice did not demonstrate its purpose in
this process, Dr. Ball placed it in “C-1.” Id. at 95. This approach
is contrary to the substantial compliance standard mandated by the
1990 NCP. Furthermore, the court has reviewed the remaining
invoices in this category and is satisfied that they reflect monitoring
and data-gathering activities that are essential to characterizing and
understanding the site as a whole in conjunction with assessing the
nature of the release, understanding its potential risks and
evaluating feasible remedial measures.

90a

prepared by Beazer’s contractor, Ogden, and provided in
pertinent part:

Estimated non-cancer risks resulting from potential
exposures to site related constituents are all below the
U.S. EPA’s target Hazard Index of 1.0, for all
receptors in all media at all exposure areas. Similarly
all estimated excess lifetime cancer risks are within the
U.S. EPA’s target risk range of 1 x 10° (1 in
1,000,000) and 1 x 10° (1 in 10,000).

Defendant’s Exhibit M-14 at p. ES-2. Mead notes that “the
entire Ogden risk assessment is extremely conservative” and
expressly indicates that conservative assumptions have been
employed in developing it. Mead’s Post-Trial Brief in Support
Of Judgment (Document 341) at 21 (citing Defendant's
Exhibit M-14 at p. 7-1). Mead further contends that the risk
assessment has been accepted by ADEM because it has
approved Beazer’s report on the Phase I & II RFI activities
and has not indicated any disagreement with the risk
assessment.‘

Based on the above, Mead argues that “the primary focus
of CERCLA and the NCP is the elimination of unacceptable
risk to human health and the environment” and because a
determination of no unace “table risk has been made through
Beazer’s risk assessment, no further action would be required
under CERCLA. From Mead’s perspective all activities at
the site subsequent to the submission of the risk assessment

* Mead bolsters this argument by asserting that “from the CERCLA
perspective, Beazer is the ‘lead agency’” and as a result a
determination has been made that no further remedial action within
the meaning of CERCLA will be necessary at the site.

9la

were undertaken to comply with the regulatory requirements
of RCRA and any costs Beazer incurred after that date “were
‘on its own nickel’ because the costs would no longer be
necessary costs of response pursuant to CERCLA, since they
no longer were incurred in response to a threat to human
health or the environment.” Id. at 21. Because the risk
assessment purportedly established that no further action was
required under CERCLA, Mead contends that all costs
incurred after May 3, 1997, are not recoverable response
costs.

Mead’s contention that the risk assessment extinguished its
liability under CCRCLA is specious. First, while Beazer is
“the lead agency” under various provisions of the NCP, the
determination of whether further corrective measures and/or
additional activities leading to remediation of the site will be
required under the AOC is a determination that remains with
the environmental agencies. No provision of the AOC
explicitly or implicitly grants Beazer the authority to decide
that its obligations to perform a corrective measure study and
implement any remedies selected by the agencies have been
extinguished by its assessment of the risk posed by the site.

Second, ADEM’s letter of August 24, 2000 - indicating
the draft Phase I & II RFI and groundwater assessment reports
prepared by Beazer’s contractor have been “approved” -
cannot be read to support Mead’s contention that the
conclusions advanced in the risk assessment have been
accepted by ADEM and therefore no further response actions
or remedial measures under CERCLA will be necessary. See
Defendant's Exhibit M-15. The letter merely indicates that
the reports have been approved, which can only be understood
to mean that Beazer has fulfilled the requirements of the work
plan governing Phase I & Il investigation activities and
developed a risk assessment. See TT of February 6, 2002

92a

(Vandeven) at 56. In other words, the letter simply means
that Beazer met the requirements of Phase I and Phase II of
the RIF work plan and has developed the risk assessment as
required by the terms of the AOC-id- And ADEM’s intent
to further investigate and characterize the potential migration
of hazardous substances before substantively approving the
risk assessment and moving to the corrective measures
component of the AOC is evident by the reference in the letter
to the “Phase III RFI work plan” under negotiation between
ADEM and Beazer. It also is evident that the need for the
Phase III work arose as a result of areas of concern generated
from the submitted reports. Defendant's Exhibit M-15; TT of
February 6, 2002 (Vandeven) at 55-56; TT of February 5,
2002 (Vandeven) at 7, 29-30.

Third, it is a well-accepted premise that the risk
assessment is only one step in the CERCLA decision-making
process. See Rebuttal Expert Report of October 2000 at pp.
13-14; TT of February 6, 2002 at 28-31. It is merely one
piece of information that will be used by the environmental
agencies along with all other available information in making
their own assessment of the acceptable and unacceptable risks
that remain at the site. Id.

The author of the Ogden risk assessment, Dr. Magee, also
expressed the same view. In conjunction with questioning
regarding Ogden’s decisions to include or exclude particular
chemicals in a risk assessment presented to an environmental
agency, Dr. Magee provided the following insight as to how
a risk assessment is prepared and presented:

As is typical in the work that I do for clients, I view
my job to put a realistic defensible risk assessment on
the table first time through that’s consistent with the
law and the regulations and the guidance but that

93a

wears the client’s hat rather than the agency’s hat
because I’m working for the client.

We know full well that the agency may often, and
usually does, disagree with many of the assumptions
and approaches that we take. So that the numbers of
this report, which is the favorable report to start the
negotiation with the agency, concludes simply that
nothing has to be done anywhere.

But I don’t believe for a minute that nothing will
have to be done anywhere. Because I believe that
they’re going to say, up in the ponds, you have shown
that if a trespasser gets in there and touches some of
the sediment, it won’t hurt them. But you didn’t say a
darn thing about the ecology, the ecological receptors.

Or you assume that if trespassers get on the site
and contact the average of all the soil across one or
two areas, that there won’t be a problem. But you
didn’t consider that they might go preferentially to this
very small, what we would call, hot spot; what would
be the answer if they went just there?

On groundwater, you assume no use of the
groundwater directly beneath the site. While we
might, all agree that it’s unlikely that someone would
drop a well there and make that their drinking water,
they could use the water for industrial process water.
Again, not atypical of any site, the negotiation that
goes on between the PRP and the agency is just that,
and we haven't seen how they responded to this yet.

So from my general experience on sites that have
these kinds of chemicals in them at these levels, I am

94a

sure that some remediation will be required. And it
will be my job then, if I’m asked to continue working
on it, to focus it in and make it be reasonable and cost
effective, selective removal in just this area, capping
and so forth.

Deposition testimony of Dr. Magee at pp. 48-50. In other
words, the initial risk assessment submitted by Beazer is
anticipated to be a mere first step in the bargaining process
between the EPA/ADEM and Beazer with regard to what
additional response/remediation activities will be required at
the site. Absent written notice from the EPA/ADEM
indicating Beazer has complied with all of its obligations
under the AOC, there is no factual or legal basis for this court
to conclude that subsequent response and remediation
activities at the site will fall outside the “necessary” and
“consistency” requirements of CERCLA.

Furthermore, to extrapolate the proposition that no
unacceptable risk remains at the site and therefore no further
remedial measures will be required from the siatements made
in the risk assessment fails to acknowledge the role of the
EPA in evaluating the information generated from agency-
directed investigations. Ogden’s risk assessment did not
purport to render a conclusion on whether the site continues
to present an acceptable or unacceptable risk. The assessment
merely advances an objective proposition regarding general,
site-wide estimated non-cancer and excess lifetime cancer
risks. The assessment is based upon numerous assumptions
about the hazardous substances present, the likely pathways of
exposure, the likely receptors and future expected land and
water use. It docs not purport to address the need or lack
thereof for future remedial action.

95a

Guidance documents from the EPA indicate clearly that
mere objective findings reflecting the presence of hazardous
wastes within an acceptable target range does not mean that a
CERCLA-quality remedial measure will not subsequently be
required by the EPA at the site. In a memorandum providing
guidance on the use of a risk assessment in the CERCLA
decision-making process, the EPA has emphasized that a
finding within the agency’s acceptable target range will not
eliminate the agency’s discretion to require further remedial
action based on other pertinent factors. EPA’s Office of Solid
Waste and Emergency Response advises that “the EPA uses
the general 10(-4) to 10(-6) risk range as a ‘target range’
within which the Agency strives to manage risks as part of a
Superfund clean-up,” but further emphasizes:

(a) A risk manager may also decide that a baseline risk
level less than 10“ is unacceptable due to-site specific-
reasons and that remedial action is warranted [and
similarly} EPA may determine that risks less than | x
10% are not sufficiently protective and warrant
remedial action.

(b) Other chemical-specific ARARS [applicable
regulations and applicable requirements] may also be
used to determine whether a site warrants remediation.

(c) The upper boundary of the risk range is not a
discreet line at 1 x 10*....

Role of the Baseline Risk Assessment in the Superfund
Remedy Selection Decisions, EPA Office of Selid Waste and
Emergency Response (OSWER), 1991, Base 9355.3-30; see
also Rebuttal Expert Report by Jay Vandeven at pp. 12-13;
TT of February 6, 2002 (Vandeven) at 30-31.

96a

The AOC incorporates the EPA’s authority to evaluate as
a whole all risks presented by the site. All of Beazer’s work
under the AOC is submitted for agency review. The EPA and
ADEM retain the express right to require additional
investigation, characterization; monitoring or remedial action
whenever in the agencies’ judgment the data submitted by
Beazer requires such measures and the EPA reserves the right
to select and require the implementation of corrective
measures. See, e.g., AOC at pp. 7-8. The EPA and ADEM
have not substantively approved the Ogden risk assessment or
released Beazer from any further obligations under the AOC;
to the contrary, they have required additional RFI work
pertaining to deep and off-site groundwater flow. Under these
circumstances Mead’s contention that the Ogden risk
assessment eliminated any further basis for cost recovery
under CERCLA lacks sufficient evidentiary support and
Beazer’s post March 7, 1997, response costs are recoverable
to the extent they are not otherwise precluded by the court’s

-—_——Tulings.

Mead’s assertion that Beazer engaged in inefficient and
excessive sampling at the site, thereby rendering a substantial
portion of the data collected “unnecessary” for the purposes
of assessing risk and selecting a remedial action, also is
without merit. Mead argues that in accordance with the NCP,
“(t]he purpose of the remedial investigation (“RI”) is to
collect data necessary to characterize adequately the site for
the purpose of developing and evaluating effective remedial
alternatives.” 42 C.F.R. §300.430(d). It then notes that a
number of the samples collected during Phases I & II of the
RFI were not used by Ogden in formulating the risk
assessment. It reasons “that the risk assessment is the
essential document for identifying and evaluating effective
remedial alternatives and therefore “only those data necessary
to support a risk assessment for the Woodward Coke Site are

97a

recoverable under the NCP.” Mead’s Post-Trial Brief in
Support of Judgment at p. 23.

Mead reduces its “unnecessary” sampling arguments to a
set of mathematical formulas. The total number of samples
made available to Ogden for formulating the risk assessment
was 662. Ogden used a maximum number of 368
investigative samples in evaluating the mediums of concern
(soil, groundwater, sediment and surface water) and thus from
Mead’s perspective a total of 294 samples were not used in
calculating the risk. Mead’s expert then tabulated the
estimated cost of gathering the 662 samples and subtracted
44% from this total (i.e., 294/662 equals .44).

As a further refinement of this requested reduction Mead
notes that while 368 samples represent the maximum number
used by Ogden for an individual contaminant of concern, in
certain of the medium of concern Ogden used far fewer
samples to calculate the risk. For example, to calculate the
risk for some contaminants of concern in the soil, Ogden
needed only 34 samples and for others Ogden used the
maximum number of samples available, 93. From these
premises Mead reasons:

Thus, although Ogden used the additional data, they
were clearly not necessary to complete the risk
assessment, as the minimum number was used for
many of the [contaminants of concern]. In aggregate,
the minimum number of samples used by Ogden is
166, as opposed to the maximum aggregate of 368.

Therefore, as further refinement of the percentage
listed above, the investigation and laboratory costs that
are not recoverable under CERCLA and the NCP

98a

equal approximately 74% - (662 minus 167)/662 - of
the total sampling related costs claimed by Beazer.

The deduction from Beazer’s costs that should be
made if one looks solely at the data used in the risk
assessment is $1 ,154,018.67 (44% of $2,622,769.71 -
the “total E/F costs” ...; if the deduction is based
upon the efficient data needs (that is the number of
samples-which would have satisfied the risk
assessment needs) the deduction is $1 ,964,976.07 ....
Mead is willing to “split the difference” with Beazer
between the deduction based upon the “inefficient”
risk assessment number and the deduction based upon
the efficient risk assessment number; thus, the
deduction Mead proposes for this item is
$1,559,497.37 ($1,964,978 + $1,154,018 =
$3,118,994 +2).

Id. at 25-26. In other words, Mead advocates that only the
minimum amount of data samples needed to formulate the risk
assessment, as calculated after the fact, can be found to be
necessary costs of response incurred consistent with the NCP.

Mead’s mathematical efficiency arguments are flawed on
many levels. First, the court already has considered and
rejected Mead’s contention that Beazer engaged in inefficient
and/or ineffective methods of gathering and processing the
information used in characterizing the site. In the previous
phase of the litigation Mead argued that there was evidence of
“over testing” by Beazer in that it did more testing under
RCRA than would have been “necessary” under CERCLA,
pointing to purported over sampling during Phase II of the
RFI work plan as an example. See Findings of Fact and
Conclusions of Law of November 24, 1999 at p. 52. Mead
also challenged Beazer’s methods of sampling as inefficient

99a

and lacking quality control. Id. After considering these
matters, the court rejected Mead’s challenges on the grounds
that there was nothing “suspect” in the manner in which
Beazer proceeded with its sampling programs under Phase I
& Il of the RFI and Dr. Ball’s criticisms merely reflected “the
type of difference in professional opinion referred to by the
USEPA in guidance documents, and which is to be expected
from site to site.” Id. at 53.

The court explained that identifying the most efficient
approach to investigating a site under CERCLA was not
grounds for excluding additional costs as unnecessary because
such a rigid approach “leaves no room for the accepted notion
that professional judgment might vary from site to site.” Id.
at 54, 74. It then made the following finding:

54. Dr. Ball’s criticisms of the manner in which the
site was addressed under RCRA do not suffice to
establish that any of the actions taken are inconsistent
with the national contingency plan. The manner in
which a site is addressed under RCRA or CERCLA
differs from site to site, and a certain amount of
professional style (for lack of a better word) or
judgment is inherent in the system. Dr. Ball has
established only that he would have conducted the site
inspection and remediation differently: he has not
established that anything actually done at the site was
inconsistent with the NCP.

Id. at p. 78, 454. Indeed, the court rejected the proposition
that efficiency arguments based upon hindsight are a proper
means of identifying necessary costs of response incurred
consistent with the NCP. The court opined:

100a

15. Recovery of costs pursuant to CERCLA requires
that actions taken be “consistent with” the NCP. There
is no requirement that the actions be no more than are
necessary. There is no authority for viewing the
consistency of actions taken in hindsight, i.e., by
arguing that certain actions may not have been
necessary. In short, there is no requirement that a
remedial investigation [be] “perfect” before costs
expended will be found to be consistent with the
“NCP” and, therefore, recoverable in a CERCLA
action.

16. Mead, through the testimony of Dr. Ball, seems to
assert that any action which would not be forced upon
a PRP under CERCLA would not be “consistent” with
the NCP. The court disagrees. Again, the NCP vests
discretion in individual professionals involved in the
investigation and remediation of a particular site to
select from a range of options. There is no support in
the law for Dr. Ball’s hypothesis, and the expert
testimony offered by Beazer concerning the practices
in the field is entirely to the contrary.

Id. at p. 98, 44 15, 16. Thus, the court already has ruled that
the necessity and consistency requirements under CERCLA
are not limited to the minimal means of investigating and

characterizing the risk posed by a site as measured with
hindsight.

Second, Mead’s attempt to reduce the necessity and
consistency requirements of CERCLA to encompass only
those tasks undertaken to gather data directly used in
formulating a risk assessment reflects a_ significant
misapprehension of the CERCLA decision-making process
and the information needed to perform that process efficiently

10la

and effectively. The applicabie regulation does indicate that
“the purpose of the remedial investigation is to collect data
necessary to adequately characterize the site for the purpose
of developing and evaluating effective remedial alternatives.”
42 C.F.R. §300.430(d). But, it does not follow from that
proposition that only the gathering of the data actually used to
support a risk assessment constitutes recoverable costs under
the NCP.

The AOC obligated Beazer to collect data to characterize
the site, delineate the nature and extent of the contamination
present, and perform a baseline risk assessment. Beazer has
gathered the data to characterize the site and published a draft
Phase I & II RFI report. All of the data collected was used in
formulating the RFI report, and the risk assessment was but
one component part of that report. Rebuttal Expert Report of
Jay Vandeven at p. 23. ADEM reviewed the report and
mandated additional investigation above and beyond the data
collected during the first two phases of the RFI investigation
prior to requiring Beazer to undertake the process of
completing a corrective measures study. Thus, the steps
Beazer has been required to take in implementing the AOC
demonstrate clearly that collecting the data necessary to
evaluate remedial alternatives effectively encompasses far
more than a “private party’s formulation of a risk
assessment.”

> A review of the persuasive expert testimony of record more than
adequately supports this proposition. As Jay Vandeven highlighted
in his rebuttal expert report:

Data collected during the course of an investigation have
many purposes and uses. These data are used to develop
conceptual models of the site, to delineate the nature and
extent of contamination, to evaluate groundwater flow and

102a

Third Beazer’s obligation to perform the RFI Phase III

contaminant transport, to document site conditions for
evaluation of remedial alternatives, and to assess risk. The
risk assessment, which is only one component of the RFI,
does use all. the data available in a qualitative manner and
a subset of the data in a quantitative manner to evaluate
exposure pathways and calculate an excess lifetime cancer
risk and hazard index. All of the information from the
various phases of the RFI, including the risk assessment,
when complete, will be considered by ADEM when they
ultimately select a remedy at the site.

Rebuttal Expert Report of Jay Vandeven at p. 22. At trial he
reiterated the multifaceted use of data in conducting an initial
CERCLA or RCRA investigation, emphasizing that the basic
objectives under both RCRA and CERCLA are to characterize the
nature and extent of the contamination at the site and then to
develop remedies to address the risk posed to human health and the
environment. TT of February 6, 2002 (Vandeven) at 8.

Dr. Magee, the vice president and principal toxicologist of
Ogden Environmental and chief architect of the risk assessment,
similarly emphasized the multi-purposes for collecting data during
the course of a CERCLA site investigation. He repeatedly
emphasized that the entire data selection and evaluation process
leading to the formulation of a risk assessment has a bearing on and
informs the decision-making process concerning the assumptions
underlying the risk assessment and the selection of the data used to
formulate the assessment. Deposition Testimony of Dr. Magee
(Document 331) at pp. 25-30. For example, all of the groundwater
samples were entered into a database and initially considered before
strategic decisions were made “about what to put in the first report
to send off to the State and EPA.” Thus, while all the groundwater-
data was evaluated, only a few samples actually were quantitatively
used from very specific locations as a result of a “strategic decision
as to how to treat a very complex subject.” Id. at 36-37.

103a

work after the completion and submission of the risk
assessment as well as its compilation of conceptual models
such as the site conceptual model for groundwater flow
further demonstrate the breadth of data and information
needed by the environmental agencies to move toward the
development of alternative remedial measures. The
environmental agencies decision to conduct further
gruundwater testing and analysis before completing the RFI
process demonstrates quite clearly that the selective process
employed in formulating the risk assessment might prove to
be too narrowly confined and the use of data not contained in
the risk assessment might be required in the environmental
agencies’ subsequent evaluation and decision-making process.
The use of this vast array of information in the decision-
making process in itself demonstrates the inappropriateness of
confining the CERCLA’s cost recovery mechanisms to the
minimal amount of data necessary to conduct a risk
assessment is determined with the benefit of hindsight.

It follows that limiting the recovery of response costs to
only the data used in a private party’s formulation of a risk
assessment thus would inappropriately eliminate the costs of
some of the data actually used to assess and characterize a
release or threaten release, formulate various assumptions
employed in the risk assessment, and effectively evaluate
feasible remedial alternatives. It likewise would create an
improper motive for private parties to minimize the amount of
data made available for an environmental agency’s decision-
making process from sources other than the risk assessment
and/or incorporate extraneous data into the risk assessments.

Mead’s contention that recoverable response costs should
be limited to the actual and/or minimal amount of data needed
to complete the risk assessment effectively was considered and
resolved during the preceding phase of this litigation. Mead

104a

has advanced no authority or reason for reexamining this
aspect of the prior litigation. But even assuming arquendo
that there is some ground for reexamining the prior findings
and rulings, the record adequately demonstrates that the entire
sampling undertaken to investigate and characterize the site
constitutes a necessary cost of response incurred consistent
with the NCP. Accordingly, Mead’s mathematical efficiency
arguments cannot be accepted by the Court.

The parties dispute whether Beazer is entitled to
prejudgment interest on its recoverable response costs, and if
so, when any such interest began to accrue. Beazer contends
prejudgment interest properly is recoverable in a contribution
proceeding and asserts it has met all statutory requirements
governing a private party's entitlement to it. Mead contends
that prejudgment interest is not available in a contribution
action and even if it is, Beazer has not demonstrated
entitlement to it.

A private party is entitled to prejudgment interest on
recoverable response costs ina CERCLA contribution action.
Mead’s argument that only the government has the right to
prejudgment interest is unpersuasive. The courts that have
considered whether prejudgment interest is available in a
private party contribution action have concluded that the
contribution provisions of 42 U.S.C. §9613 (f) incorporate the
prejudgment interest provisions of 42 U.S.C. §9607(a)(4), and
thus prejudgment interest is available in a contribution action.
See, e.g., Bancamerica Commercial Corp. v. Mosher Steel of
Kansas, Inc., 100 F.3d 792, 799 (10th Cir. 1996) (“We hold
prejudgment interest should be granted in §113(f) actions in
the same fashion as it ts granted in §107 actions.”); Boeing

Co. v. Cascade Corp., 920 F. Supp. 1121, 1132, 1140 (D.
Ore. 1996) (awarding prejudgment interest in §113(f)

contribution action); Dow Chemical Co. v. Sinclair Oil Corp.,

10Sa

3 F.Supp.2d 1252, 1254(D.Wyo. 1998) (prejudgment interest
recoverable in private party contribution action); Browning-

Ferris Industries v. Ter Maat, No. 92 C 20259, 1996 WL
67216 at *4 - *5 (N.D.Il. Feb. 16, 1996) (same).

In holding that prejudgment interest is available in a
private party contribution action, the courts have reasoned that
although a cost apportionment action must be brought
pursuant to §9613(f), that section does not in itself create,
independent rights for establishing liability. Instead, §9613(f)
simply confirms a responsible person’s rights under §9607 to
obtain a proportional recovery from other potentially
responsible persons. See Bancamerica, 100 F. 3d at 800.
Thus, because CERCLA’s contribution provision is only a
mechanism for apportioning established CERCLA-defined
costs, by necessity it incorporates the elements and measures
of liability set forth in §9607. Id. (collecting cases). The
United States Court of Appeals for the Third Circuit similarly
has recognized that §113(f) of CERCLA incorporates the
liability provisions of §107. See New Castle County, 111
F.3d at 1122 (“[S]ection 113 does not in itself create any new
liabilities; rather, it confirms the right of a [PRP] under
section 107 to obtain contribution from other [PRPs].”).

And because the purpose of CERCLA’s contribution
provision is to apportion equitably §107 response costs among
responsible parties, the courts generally have recognized that
the failure to grant prejudgment interest on contribution
awards would result in inequitable apportionment, i.e., the
parties that paid more than their fair share in complying with
government mandates would lose the time value of the money
they spent on behalf of other responsible persons.
Disallowing prejudgment interest under such circumstances
would frustrate CERCLA’s incentive for prompt, voluntary
cleanup action by private parties under government oversight.

106a

As the Bancamerica court recognized, “[iJndeed, it would
create a perverse incentive for responsible parties to delay
involvement in cleanups, because as they delay, they gain the
time value of funds they should be investing in the cleanup.”

Bancamerica, 100 F.3d at 801.

CERCLA provides that prejudgment interest begins to
“accrue from the latter of (1) the date payment of a specified
amount is demanded in writing or (ii) the date of the
expenditure concerned “ 42 U.S.C. §6907(a)(4). “The statute
plainly requires a written demand for specified response costs
as a prerequisite to an award of prejudgment interest.”
Matter of Bell Petroleum Services, Inc., 3 F.3d 889, 908 (Sth
Cir. 1993). To satisfy these requirements a party must make
a written demand for payment of specific response costs that
have been incurred. Notices that do not satisfy both
requirements are insufficient. Id. see also The Dow Chemical

Co. v. Sinclair Oil Corp., 3 F.Supp.2d 1252, 1253 (D. Wyo.
1998) (“Courts have fleshed out this seemingly clear statutory

language by assuming (1) that both demand and expenditure
are required (despite the disjunctive), and (2) that the demand
must be made by the party seeking the interest.”) (citations
omitted)). For example, a notice from the EPA simply
advising a potentially responsible party that it is considered to
be responsible for response costs and/or informing the party
of an unspecified demand for future reimbursement are
insufficient. Id. In contrast, the filing of a complaint seeking
the recovery of incurred response costs satisfies the statutory
requirement even if it does not specify an exact amount. In
Matter of Bell Petroleum Services, Inc., 3 F.3d at 908
(“Although the complaint does not specify an exact amount,
we conclude that it constitutes a sufficient written demand for
payment.”); Bancamerica, 100 F.3d at 108 (complaint
indicating party had incurred response costs “in excess of $1
million” and seeking reimbursement and interest triggered the

107a

right to prejudgment, interest from the date the complaint was
filed); Dow Chemical Co., 3 F.Supp.2d at 1254 (complaint
along with simultaneously filed computation of damages
indicating expenditures in excess of a specified amount
constituted a sufficient written demand).

Beazer’s letter of September 18, 1986, failed to satisfy the
statutory requirements for prejudgment interest. The letter
merely advised Mead of ongoing investigations by the EPA
and ADEM, noted the possibility that corrective action might
be required at specific locations within the site and invited
Mead to participate in negotiations with the environmenial
agencies pursuant to an agreed upon method of sharing costs.
The letter thus was not a written demand requesting payment
for a specified amount of incurred response costs. Mead’s
follow-up letters fall short of the mark for the same reasons.

Beazer’s amended complaint constituted the first demand
that satisfied the statutory requirements for prejudgment
interest. Beazer’s June 14, 1991, amended complaint was in
writing, demanded contribution for incurred response costs in
excess of $180,000.00, and provided Mead with notice that
Beazer would be seeking recovery for all future response costs
incurred in cleaning up the site. See Amended Complaint
(Document 15) at 44 32, 35. Accordingly, Beazer is entitled
to prejudgment interest from June 14, 1991, forward with
regard to the recoverable response costs incurred prior to that
date and prejudgment interest from the date Beazer paid any
subsequently incurred response costs.°

° Mead’s contention that the accrual of prejudgment interest should
be tolled until Beazer served its cost documents on Mead pursuant
to the case management order of April 5, 2000, is unconvincing.
The amended complaint provided Mead with notice that Beazer was
seeking contribution for recoverable costs of response that had been

108a

Based on the above, the court calculates Beazer’s response
costs for activities through December 31, 1999, as follows:

Submitted Invoices: $4,993 488.00
Less Resampling Costs (55,984.76)
Less D-I Invoices (35,041.09)
Less Post-Closure Application Fee (6,000.00)
Less Additional Well Deduction (91,324.75)
Total Costs $4 805,137.60
Mead's Share @ 67.5% $3,243 ,467.80

Accordingly, the court will enter judgment in Beazer's favor
and against Mead in the amount of $3,243,467.80. The
award will be subject to the addition of prejudgment interest
as calculated in accordance with the court's rulings. Counsel
for the parties will be directed to stipulate to the applicable
prejudgment interest within a reasonable period of time.

An appropriate order will follow.’

and would be incurred at the site. The statutory prerequisites were
thus satisfied at that point and abse a prevailing defense an award
of prejudgment interest as specified above is warranted under the
circumstances.

” At the pretrial conferences in January and February of this year
both parties indicated Beazer’s obligations under the AOC would
likely be ongoing for years. Mead indicated that any remedial
measures may take decades to complete. Both counsel implied that
this action would have to remain open in order to provide the
parties with an appropriate forum for resolving any subsequent
disputes.

109a

/s/
Gustave Diamond
United States District Judge

From the court’s perspective the destruction of the plant and the
ongoing supervision of Beazer’s implementation of the AOC by the
environmental agencies indicate that any future response costs can
be allocated in accordance with the comprehensive disposition of
Mead’s challenges set forth above. Accordingly, the court believes
that the entry of a declaratory judgment on Mead’s liability for
Beazer’s future response and remediation costs consistent with the
court's findings and rulings to date would provide Beazer with
appropriate and complete relief. Congress provided for declaratory
relief under CERCLA to ensure that a responsible party’s
established liability would not have to be relitigated. CERCLA

provides in pertinent part:

In any such action ... the court shall enter a declaratory
judgment on liability for response costs or damages that
will be binding on any subsequem action or actions to
recover future response costs or damages.

42 U.S.C. §961%g)(2). The mere possibility that future costs are
somewhat speculative does not present a “bar to a present
declaration of liability.” Kelley v. E.1. du Pont De Nemours &
Co., 17 F.3d 836, 844 (6th Cir. 1994) (quoting United States v.
Fairchild industries, inc., 766 F.Supp. 405, 415 (D.Md. 1991)).

In light of the above, the parties will be directed to show cause
why a declaration binding Mead to pay all incurred and future costs
of implementing the AOC in accordance with the court's findings
and rulings will not provide the parties with adequate relief under
the circumstances.

110a

Mark D. Shepard, Esq.
D. Matthew Jamison III, Esq.

Melissa L. Evans, Esq.

Babst, Calland, Clements & Zomnir
Two Gateway Center, Eighth Floor
Pittsburgh, PA 15222

George P. Faines, Esq.

John H. Bingler Jr., Esq.
Thorp, Reed & Armstrong
One Oxford Centre, 14" Floor
Pittsburgh, PA 15219-2402

Alan M. Wiseman, Esq.
Thomas A. Isaacson, Esq.
Howrey & Simon

299 Pennsylvania Avenue, N.W.
Washington, D.C. 20004-2402

Van Carson, Esq.

Charles R. McElwee, II, Esq.
Squire, Sanders & Dempsey
127 Public Square

4900 Key Tower

Cleveland, OH 44114-1304

John E. Frey, Esq.

Wildman, Harrold, Allen & Dixon
225 West Wacker Drive

30" Floor

Chicago, IL 60606-1225

llla

IN THE UNITED STATES DISTRICT COURT
FOR THE WESTERN DISTRICT OF
PENNSYLVANIA
Civil Action No. 91-408

[Filed March 7, 2000]

BEAZER EAST, INC.,
Plaintiff,

Vv.

THE MEAD CORPORATION,
Defendant,

Vv.

KOPPERS INDUSTRIES, INC.,
Third-Party Defendant.

ee

~~

1i2a
MEMORANDUM AND ORDER OF COURT

DIAMOND, D.J.

Beazer East, Inc. (“Beazer”) commenced this action under
the Comprehensive Environmental Response, Compensation
and Liability Act (“CERCLA”) seeking contribution for
expenses that have been and will in the future be incurred in
cleaning up the Woodward Coke Plant, an industrial site near
Dolomite, Alabama. Coke used in the steelmaking industry
has been produced at the site since 1911. Beazer seeks
recovery against the Mead Corporation (“Mead”) as a prior
owner and operator of the site from 1911 to 1974. Mead
asserted a counterclaim against Beazer as prior owner and
operator of the site (1974 to 1988) and joined the current
owner and operator of the site, Koppers Industries, Inc.
(“KII"). Presently before the court are KII and Mead’s
objections to the Magistrate Judge’s report of November 24,
1999, (Document No. 303), recommending equitable
allocation percentages for each party. After de novo review
of the record, together with the (1) proposed findings of fact
and conclusions of law, (2) comprehensive allocation briefs,
(3) recommendations for equitable allocation set forth in the
report, and (4) objections to the report and responses thereto,
the report and recommendation will be adapted by the court
as modified hereiw. and further proceedings will be ordered
accordingly.

Following the United States Court of Appeals for the
Third Circuit's remand of December 9, 1994, this action was
referred to the Magistrate Judge on December 22, 1994, for
further proceedings consistent with the Third Circuit's opinion
at Beazer East, Inc. v. Mead Corp., 34 F.3d 206 (3d Cir.
1994), cert. denied, 514 U.S. 1065 (1995). After the
resolution of several pretrial matters, this court entered a

113a

memorandum order on July 9, 1996, grantine in part and
denying in part Mead’s motion for partial summary judgment.
The order further provided:

It further appearing that a determination of the
eyuitable factors to be considered in the parties’ claims
for contribution [has] not yet been [made] and that a
report and recommendation identifying such
appropriate factors as well as setting forth a
comprehensive allocation of Beazer’s clean-up costs
among the parties is appropriate at this juncture, IT IS
ORDERED that a scheduling conference shall be held
before the Magistrate Judge wherein timeframes shall
be established for (1) proposing the equitable factors
to be considered under §9613(f), (2) submitting briefs
in support of an allocation of Beazer’s clean-up costs
among the parties, and, after a hearing if necessary,
(3) the submission of a report addressing the same.

Memorandum Order of July 8, 1996 (Document No. 193). On
August 29, 1996, the Magistrate Judge entered an order
scheduling implementation of the July 8, 1996, directives.

On September 16, 1996, Mead filed an objection to the
Magistrate Judge’s order of August 29, 1996, contending that
the scheduling order was inconsistent with the grant of
authority set forth in the Magistrates Act, 28 U.S.C. §636,
because the identification of the equitable factors might
require the Magistrate Judge to make credibility assessments
regarding the testimony of fact and expert witnesses and thus
the hearing essentially constituted a trial of the parties dispute
without Mead’s assent. On April 30, 1997, this court
overruled Mead’s objection and denied Mead’s supplemental
motion to stay further proceedings on the grounds that the
identification of the equitable factors was not a dispositive

114a

undertaking in itself, particularly in light of the Magistrate
Judge’s requirement to issue a report and recommendation to
which Mead could file timely objections. The court
additionally noted that given the complex nature of the
dispute, the court’s ability to evaluate any specific objections
to the report in a concrete context would conserve judicial
resources.

The Magistrate Judge held a hearing on May 6, 1997,
through May 21, 1997.' The parties introduced approximately
1300 exhibits contained in more than 47 ring binders and
called 14 witnesses. On November 24, 1999, the Magistrate
Judge issued a report recommending proposed findings of fact
and conclusions of law. The parties filed their respective
objections and responses thereto, with the final pleading being
filed on December 28, 1999. The report and KII and Mead’s
objections were forwarded to this court for consideration on
January 4, 2000.’

KII objects to the first recommendation made by the
Magistrate Judge: “that KII be deemed a [responsible party],
and that it be considered such as the court fashions the
ultimate allocation in this matter.” Report of November 24,

' The heating consumed twelve days and has been transcribed in its
entirety. See Document Nos. 276-77, 284 and 286-97.

? On December 18, 1997, the Magistrate Judge issued a report
recommending that KII’s motion for judgment on the pleadings be
denied and this court entered a memorandum order that same day
denying the motion. Also, the Magistrate Judge issued a
memorandum and order on June 16, 1999, ruling on the parties’
evidentiary objections made during the hearing. The parties do not
contest the Magistrate Judge’s June 16, 1999, memorandum and
order.

11Sa

1999 (Document No. 303) at p.4. KII objects for the reasons
set forth in its motion for judgment on the pleadings as to
Count | of Mead's amended third-party complaint and
emphasizes that it should not be part of an equitable allocation
in this litigation because Beazer is the party seeking an
equitable allocation of its response costs against Mead, and
thus the only relevant inquiry should be the percentage of
Beazer’s response costs to be allocated to Mead. This
objection is misplaced for a number of reasons. First, as
noted in the memorandum and order of September 8, 1995,
granting defendant's motion for leave to serve a third-party
complaint on KII, KII statutorily is a responsible person under
42 U.S.C. §9706 and the Third Circuit specifically noted that
upon remand “the trial court will have to revisit the parties’
contribution claims and correspondingly apportion liability for
the attendant CERCLA response costs.” Beazer East, 34 F.3d
at 219 n.10 (emphasis added). Joinder of KII to Mead’s
counterclaim was proper under these Circumstances pursuant
to Fed.R.Civ. P. 13h) and 20 as well as for the reasons set
forth in the Magistrate Judge's report of February 21, 1995.
In addition, as a reading of the Magistrate Judge’s Novermber
24, 1999, report as a whole makes clear, a fair assessment of
plaintiff and defendant's equitable shares of the response costs
necessarily involves consideration of factors bearing on KII's
current ownership and operation of the site and the value
bestowed upon KII by the ultimate remediation, as well as
other poter tial benefits which may inure to the site owner.
These are factors which courts repeatedly have recognized as
potentially relevant equitable factors in a 42 U.S.C. §9316(f)
analysis. See, ¢.g., Hatco v. W.R. Grace & Co., 836 F.Supp.
1049, 1084 (D.N.J. 1993) (“the financial benefit derived from
remediation is a factor that must be considered in determining
the equitable contribution of each party to the remediation of
the site”), vacated and remanded on other grounds, 59 F.3d
400 (3d Cir. 1995); Weyerhaeuser Co. v. Koppers Co., 771

1 16a

F.Supp. 1420, 1427 (D.Md. 1991) (recognizing benefit
remediation bestows on ultimate owner of environmentally
safe property) (citing in support BCW Associates, Lid. v.

Occidental Chemical Corp., 1988 WL 102641 (E.D.Pa. Sept.
29, 1988)).’

KII's objection that an allocation of 2.5% to it is (1)
inconsistent with CERCLA’s underlying “polluter pays”
policy and (2) not based on any volumetric or statistical
analysis likewise is unavailing. Although the “polluter pays”
policy is an important guide post in analyzing CERCLA
matters, §9613(f) assigns to the court the obligation of
determining in any particular case the appropriate equitable
factors to be considered in the allocation process. The fact
that the percentage assigned to KII is not based on principles
which are typically employed in assessing the responsibility of
parties who have contributed substantially to the
environmental conditions requiring remediation does not
restrict the court’s identification and evaluation of the case-

* These authorities likewise demonstrate the lack of merit in the
first prong of KII's second objection, which challenges the
conclusion that after remediation KII will “own property which is
more valuable than it was pre-remediation.” In the context of this
case the conclusion is well supported by Ar. Graham's evaluation
and testimony. The other prong of KII's second objection likewise
is without merit. The Magistrate Judge merely recognized that KI
would have an opportunity to recoup ary costs imposed upon it
through the further sales of coke (as a cost » € doing business spread
out over time). He also acknowledged, that the remediation would
not permit KII to reap unanticipated profits due to the overall
effects of environmental regulation/remediation on the domestic
coke market. KII's prediction that it will be unable to recoup such
costs through future sales does not climinate its general opportunity
to do so as recognized by the Magistrate Judge.

117a

specific factors to be used in making a comprehensive
equitable allocation among the parties. See Discussion of
Court’s Discretion, infra, at pp.8-9.

With one exception, Mead’s objections also are
unavailing. Mead’s core objections are threefold: the
Magistrate Judge erred (1) by failing to assign a greater
percentage to Beazer based upon Beazer’s pre-sale connection
to and knowledge of the site and its willingness to bear the
risks of various environmental costs in the future; (2) in
assessing the weight to be given to the parties’
expert/historical fact witnesses and discounting certain
aspects, of Mead’s evidence bearing on Beazer and Mead’s
contributions to the condition of the site and the attendant
response/remediation costs of those contributions; and (3) in
failing to assign responsibility for Beazer’s history of
noncooperation, delay and non-compliance with regulatory
agencies and the potential dual purposes of some of the
monitoring and corrective actions taken or to be taken at the
site.

“Congress enacted CERCLA, a complex piece of
legislation ... to force polluters to pay for costs associated
with remedying their pollution.” Beazer East, 34 F.3d at 219
(quoting United States v. Alcan Aluminum Corp., 964 F.2d
252, 258 (3d Cir. 1992)). CERCLA is a remedial statute
which is to be construed liberally to effectuate its goals and
one of its principal concerns is assuring that those who are
responsible for environmental conditions hear the costs of
remedying those conditions. Id. (citing, Inter alia, B.F.
Goodrich v. Murtha, 958 F.2d 1192, 1197 (2™ Cir. 1992)).
Generally, CERCLA initially imposes strict liability on
potentialiy responsible parties. The liability is joint and
several with regard to response or remediation costs incurred
by the United States or innocent third parties. New Castle

118a

County v. Halliburton NUS Corp., 111 F.3d 1116, 1120-21
(3d Cir. 1997). With limited exception, a potentially
responsible party who has incurred costs associated with
hazardous waste clean-up and site remediation may recoup
that portion of its expenditures which exceed its fair share of
the overall liability through the contribution and equitable
apportion mechanism engrafted into CERCLA by the
Superfund Amendments and Re-authorization Act, 42 U.S.C.
§9613(f).

Section 9613(f) provides that any person may seek
“contribution from any other person who is liable or
potentially liable under section 9607(a) of this title ....” 42
U.S.C. §9613(f) (1). The Third Circuit has held that the term
“contribution” as used in §9613 (f) refers to a claim “by and
between jointly and severally liable parties for an appropriate
division of the payment one of them has been compelled to
make. “ In re Matter of Reading Co., 115 F.3d 1111, 1120

(3d Cir. 1997) (quoting Akzo Coatings, lnc, v. Aigner Corp..
30 F.3d 761, 764 (7th Cir. 1994)). A primary consideration

in allocating such costs is the concept of relative fault.
Envi IT ion S ENSCO, Inc...
969 F.2d 503, 508-09 (7th Cir. 1992) (“courts should
equitably allocate casts of clean-up according to the relative
culpability of the parties rather than an automatic equal shares
rule”); United States v. Monsanto Co., 858 F.2d 160, 173
n.29 (4th Cir. 1988), ceri. denied, 490 U.S. 1106 (1989)
(“the language of CERCLA’s new contribution provisions
reveals Congress’ concern that the relative culpability of each
responsible party be considered in determining the
proportionate share of costs each must bear”).

Section 9613(f) provides that “the court may allocate
response costs among liable parties using such equitable
factors as the court determines are appropriate.” 42 U.S.C.

119a

$9613 (f); Halliburton NUS Corp., 111 F.3d at 1121; Gould,
Inc. v. A&M Battery & Tire Service, 987 F.Supp. 353, 367
(M.D.Pa. 1997). Factors which appropriately are considered
include the relative fault of the parties, whether the parties
have contractually allocated responsibility for the cleanup
costs, and the “Gore factors.” Kerr-McGee Chemical Corp.
y. Lefton Iron & Metal Co,, 14 F.3d 321, 326 (7th Cir.
1994); United States v. Colorado & Eastern Railroad Co.. 50
F.3d 1530, 1536 n.5 (10th Cir. 1995).* In any given case “a
court may consider several factors, a few factors, or only one-
determining factor, ... depending on the totality of the
circumstances presented to the court.” Colorado & Eastern,
50 F.3d at 1536 (quoting Environmental Transportation
Systems, Inc. v. ENSCO, Inc., 969 F.2d 503, 509 (7th Cir.
1992)); AL. Tech Specialty Steel Corp. v. Allegheny

International Credit Corp., 104 F.3d 601, 608 (3d Cir. 1997)
(it is within the court's discretion to rely on a single factor).

* 4. The “Gore factors” are a non-exclusive list of relevant factors
proposed by then Senator Albert Gore:

(i) The ability of the parties to demonstrate that their
contribution to a discharge, release or disposal of a hazardous
waste can be distinguished,

(it) The amount of the hazardous waste involved,
(iii) The degree of toxicity of the hazardous waste,

(iv) The degree of involvement by the parties in the generation,
transportation, treatment, storage or disposal of the hazardous
waste ,

(v) The degree of care exercised by the parties, taking into
account the characteristics of the hazardous waste, and

(vi) The degree of cooperation by the parties with the federal,
state, or local officials to prevent any harm to the public health
or the environment.

120a

The parties devoted considerable effort and resources in
thoroughly developing the record on their respective positions
regarding the factors which should command this court's
attention and the Magistrate Judge's November 24, 1999,
report identifies the appropriate equitable factors to be
considered in this case. Mead contends that although the
Magistrate Judge correctly found or concluded that

“Reasonable parties negotiating the sale of an industrial
site in Alabama in 1974 would expect that the seller would
not be held liable for any future environmental costs”
(Finding of Fact 65);

“Beazer performed a full inspection of the Woodward
Plant prior to its purchase, and was well aware of the
environmental condition of the site” (Finding of Fact 68);

“The parties in fact intended that Mead be able to ‘walk
away’ from the site, i.e. that Mead would not indemnify
Beazer for any future costs at the site for any reason,
including environmental response costs” (Finding of Fact
66);

“Beazer was in at least as good a position as was Mead,
and was probably in a more informed position to assess the
potential environmental problems at the site at the time of
the 1974 sale” (Finding of Fact 67);

“Beazer purchased the property from Mead pursuant to
the doctrine of caveat emptor and with full knowledge of
the contamination, or potential contamination, on site”
(Conclusion of Law 27);

“Beazer purchased the property ‘as is’ and with
knowledge that the property had been contaminated by its

12la

decades of use as a coking facility. Beazer also had
intimate knowledge of the site in terms of the manner and
extent of the contamination on site” (Conclusion of Law
28); and

“Mead is entitled to a reduction in its ‘polluter pays’
allocation due to its reasonable expectation, and Beazer’s
intent, to accept responsibility for all environmental
regulation at the site ‘post-sale’” (Conclusion of Law 29);

the Magistrate Judge failed to give proper weight to the intent
of the parties and seriously understated the significance of
these (and related) factors when he assigned only 15% to them
in the allocation process. Mead further argues:

[iJn effect, the Magistrate Judge assigned 12.5% of the
liability to post-sale factors (10% to Beazer and 2.5%
to KIT) and 87.5% to pre-sale factors. In allocating
the pre-sale liability, he assigned more than 70% to
Mead because of its contamination but only 15% to
Beazer for its agreement to bear the costs associated
with its obligation to remediate that same pre-sale
contamination. Given Mead’s historic role more than
four times the weight assigned to Beazer’s agreement
to bear the costs of those historic practices is neither
equitable nor just.

A large, highly sophisticated purchaser such as
Beazer must bear the consequences of its decision to
assume these liabilities. Yet, the Magistrate Judge
virtually absolved Beazer of its considered decision to
assume these costs. In a free market economy, the
parties to arms-length corporate transactions must
accept both the rewards and the risks of their

122a

decisions. CERCLA did not alter that fundamental
premise.

Mead’s Objections (Document No. 305) at p. 8. Mead asserts
that a higher percentage is appropriate here, particularly
where Beazer’s pre-sale involvement with and knowledge of
considered as a single, overlapping factor in order to avoid
Possible “double counting.” Se« Conclusion of Law 31.

The court agrees that 15% understates the various factors
which are combined in Conclusion of Law 31. Accordingly,
the court will exercise its discretion and increase the
percentage to 20%. In addition, because Beazer did not assert
a claim for contribution against KII and the court finds that
2.5% appropriately represents KII's proportional share solely
as to Mead’s equitable allocation, the court will amend
Conclusion of Law 33 to provide:

The final equitable allocation amounts in this case are:
Mead (90% of the waste, minus 2.5% for KII's share
and minus 20% shifted to Beazer due to all
circumstances surrounding the 1974 sale) - 67.5%;
Beazer - 32.5%.

As modified the above allocation strikes an appropriate
equitable balance between the factors surrounding the 1974
sale of the site to Beazer, Beazer and KII’s ownership and
ongoing operation of the site since 1974, the factors pertaining
to each party's contributions to the current condition of the
site, and the remaining equitable factors, identified in the
report. Mead's general contention that these factors warrant
an even greater percentage being assigned to Beazer is
unpersuasive for the reasons noted in the report and addressed
below.

123a

Mead’s specific contention that the Magistrate Judge
misread the import of Beazer East is without merit. The Third
Circuit examined the various provisions of the asset purchase
agreement, determined that it contained contradictory
provisions and recognizec that although the parties did
contemplate a division of specific environmental obligations,
they did not legally effectuate a transfer of the stringent
obligations and requirements which CERCLA ultimately
imposed on Beazer. The court’s refusal to construe the
agreement as effectuating an indemnity agreement governing
“CERCLA response costs leaves both Beazer and Mead
responsible for their fair share of the clean-up costs associated
with the coke plant,” a result which reinforces CERCLA
policy. Beazer East, 34 F.3d at 219. Against this backdrop
the Magistrate Judge aptly observed that the context of the
appeal did not foreclose Mead’s ability to establish (1) the
parties’ factual intent to create a sweeping transfer of
environmental liability and (2) the impact any such failed
attempt should have on the matter at hand. Report at pp. 6-
11. The various contractual provisions of the asset purchase
agreement and the attendant circumstances surrounding the
sale of the Woodward Coke plant have been carefully
considered from an equitable perspective and, after placing
those factors within the comext of CERCLA’s primary policy
and fundamental principles, the court finds that 20% is the
appropriate weight to be assigned to them. Furthermore,
Alcan-Toyo America v. Northern Illinois Gas, 881 F.Supp.
342 (N.D.Ill. 1995), does provide persuasive support for
assigning this weight to the factors of caveat emptor, Beazer’s
purchase of the property “as is” and with full knowledge of its
condition, and Beazer’s intent to accept responsibility at the
site for environmental regulation, because Alcan-Toyo
emphasizes the importance of similar factors where a
sophisticated purchaser acquired environmentally
contaminated property prior to the enactment of CERCLA and

124a

a significant portion of the contamination had been placed on
the site by the previous owner. In the instant action an even
higher percentage has been assigned to Beazer in arriving at
a fair and equitable assessment of the similar factors. Under
all of the circumstances Mead’s contention that the
contractual/condition of-the-site factors should warrant an
even greater percentage of the total allocation is unavailing.

Mead’s attempt to rehash all of the arguments advanced as
to why its witnesses’ testimony and proposed assessments
should be elevated over Beazer’s is misplaced. The
substantive strengths and weaknesses of the witnesses’
testimony/opinions are thoroughly examined and explained in
the report, and while Mead’s reasons to disagree with the
evaluations are apparent, the record does not warrant the
substantial shift in emphasis advocated by Mead.

Mead’s numerous objections contending that the
Magistrate Judge erred in evaluating whether in general

* The review and assessment of the testimony in this manner and the
expressed merit-based reasons for adopting certain portions of the
witnesses’ testimony and opinions also renders moot Mead’ s
objection that the allocation hearing/report and recommendation
transcends the boundaries of the Magistrates Act. It similarly
reveals the lack of merit in Mead’s insistence that a trial de novo
with live witness presentations be conducted before this court on the
same issues presented to the Magistrate Judge in order for the court
to judge for itself the credibility of witnesses. The report assigns
relative weight on such factors as the methodology employed, the
thoroughness of the expert’s analysis, the number of potential
relevant factors considered, the internal consistency of the
testimony and assessments made, and so forth. It does not discredit
any testimony on the basis of the demeanor or character of the
witness.

125a

various investigation costs and actions to be taken at the site
under the Resource, Conservation and Recovery Act
(“RCRA”) constitute recoverable costs under CERCLA are
curious. It was Mead’s expert, Dr. Ball, who squarely raised
the issue of whether various investigation costs, monitoring
activities and projected remediation costs should be considered
as an equitable allocation factor to Beazer’s detriment.
Mead’s contentions in this regard were thoroughly developed
by Dr. Bali in both his testimony and expert report. Beazer
presented substantial expert testimony through (A) Dr. Harris
and Mr. Vandeven of ENVIRON Corporation and (B) Dr.
Jones to counter Dr. Ball's opinions and assessments, much
of which pertained to whether the corrective actions being
undertaken pursuant to the current RCRA action program are
substantially similar to the investigation and remediation
guidelines of CERCLA and the hypothetical program that
would have been developed thereunder. These experts also
referenced memoranda by the EPA expressing that agency's
view that acceptable investigation/remedial action under the
RCRA should be presumed to be acceptable and meet the
standards of CERCLA and vice versa. Dr. Ball’s methodology
also raised the issue of whether an assessment of recoverable
costs should be influenced substantially by his proposed on-
site operable units (as opposed to addressing the costs for the
entire site). The evidence of record demonstrated that while
Dr. Ball’s proposal was one way of assessing the need for and
conducting the incremental steps toward obtaining regulatory
compliance, the record in its entirety fell far short of
demonstrating that the method pursued by Beazer (prior to
and later at the insistence of the EPA) involved undertakings
which were wasteful, duplicative or otherwise beyond the
realm of actions necessary to respond to the threatened release
of hazardous wastes and consistent with the National
Contingency Plan. Mead’s evidence failed to warrant a
finding that Beazer’s costs in general were not recoverable in

126a

a CERCLA contribution proceeding. The Magistrate Judge
correctly observed that recoverable costs are not limited to
those believed to be the least necessary in the range of
acceptable professional judgments regarding investigation and
remediation action. The record has been developed thoroughly
with regard to these general contentions and proposed findings
of fret 51 through 55 (pertaining to the shortcomings of Dr.
B4dt’s testimony and opinions) are well supported. To the
extent these matters may preclude Mead from objecting to
specific costs yet to be identified, any such consequences are
a natural outcome of the issues Mead chose to raise.

Finally, the Magistrate Judge did not ignore or fail to
consider Mead’s contention that Beazer engaged in a course
of non-cooperation and non-compliance which contributed to
the costs sought to be allocated among the parties. The
testimony and opinions of Dr. Harris and Mr. Vanderview of
ENVIRON Corporation and Dr. Jones clearly established that
Beazer did not create the need for additional action by its
chosen course of investigation. Their testimony also made
clear that given the nature of site and the substances created
in the coking process, the twenty-three solid waste
management units identified in the EPA’s RCRA Facility
Assessment of May 1988 and the three regulated hazardous
waste units would have required the same
investigation/remediation actions in any event. The Magistrate
Judge considered similar contentions in assessing Dr. Ball’s
opinions and conclusions. It readily is apparent that the record
did not support the proposition that any such alleged conduct
increased the overall costs at issue. Mead’s objections on
these various points suffer from similar shortcomings in that
they fail to demonstrate that the referenced factors had any
impact which should factor into the equitable apportionment
analysis at hand. In addition, even assuming that some
undettakings may coincidently serve a dual purpose for

127a

Beazer, this factor in itself does not make such undertakings
unnecessary for proper monitoring and remediation of the
site.

The parties agree that Beazer and the EPA are parties to
a 1991 administrative order on consent issued under the
RCRA and that an investigation of the site has been
undertaken by Beazer in accordance with that administrative
order. See Joint Stipulations (Document No. 270) at $47).
Various investigations and monitoring reports also have been
completed and submitted to the EPA and its state counterpart.
Id. at 51 & 52. The parties further agree:

Some of the costs which Beazer has incurred to date
pursuant to the RCRA order at Woodward Coke are
recoverable response costs which are necessary and
incurred consistent with the National Contingency
Plan.

Id. at 55. In light of this stipulation, the parties elected to
present their materials on a comprehensive allocation formula
and did not seek to have the Magistrite Judge determine
whether any specific costs incurred to date by Beazor are
recoverable, reserving the question of the recoverability of
specific costs until a later phase of the allocation proceeding.
See Report at p.17, n.6 (citing Transcript of May 13,1997
(Document 292) at pp. 24-25). Meads general contention that
substantial portions of the undertakings aimed at complying
with the RCRA and the 1991 admin‘strative order on consent
are not recoverable costs under CERCLA has been resolved
sufficiently in the report’s assessment of Dr. Ball’s opinions
and recommendations. Beyond this general dispute the parties
have not indicated in the record their remaining disputes, if
any, regarding the recoverability of any specific costs
incurred or to be incurred in cleaning up the site.

128a

Accordingly, the court will schedule a status conference to
ascertain the appropriate procedure for resolving this
remaining aspect of the litigation.

For the reasons set forth above, KII’s objections will be
overruled and Mead’s objections will be granted in part and
denied in part. The Magistrate Judge’s report and
recommendation of November 24, 1999, as modified herein
will be adopted as the findings of fact and conclusions of law
of the court. In light of the above, the following, order is

appropriate.
ORDER

AND NOW, this 7" day of March, 2000, for the reasons
set forth in the above memorandum, IT IS ORDERED that
Koppers Industries, Inc.’s objections to the report and
recommendation of November 24, 1999, be, and the same
hereby are, overruled and the Mead Corporation’s objections
be, and the same hereby are, granted in part and denied in
part as reflected in the memorandum. The report as modified
in the memorandum is adopted as the findings of fact and
conclusions of law of the court. The final costs found
recoverable in this action shall be allocated as follows: The
Mead Corporation - 67.5%; and Beazer East, Inc. - 32.5%.

IT FURTHER IS ORDERED that a status conference be,
and the same hereby is, scheduled before this member, of the
court for Tuesday, March 21, 2000, at 10:30 a.m., in
Courtroom No. 2, Eighth Floor, United States Post Office and
Courthouse, Pittsburgh, Pennsylvania. Trial counsel must be
present. The parties shall be prepared to report to the court in
detail on the settlement posture of the case. Counsel shall have
their clients present at the conference or immediately available
for consultation. In the event the parties are unable to resolve

129a

the remaining aspects of this litigation, the parties shall be
prepared to discuss the most efficient procedures for
identifying and resolving their remaining disagreements.

/s/
Gustave Diamond
United States District Judge

ce: Honorable Kenneth J. Benson
Chief, U.S. Magistrate Judge

Robert A. King, Esq.

Kenneth R. Bruce, Esq.

Albert Bates, Jr., [V, Esq.

Timothy C. Wolfson, Esq.

Babst, Calland, Clements & Zomnir, P.C.
Two Gateway Center

Eighth Floor Pittsburgh, PA 15222

John J. Bingler, Jr., Esq.
George P. Faines, Esq.
Thorp, Reed & Armstrong
One Riverfront Center
Pittsburgh, PA 15222

Alan M. Wiseman, Esq.

Thomas A. Isaacson, Esq.
Howrey & Simon

1299 Pennsylvania Avenue, N.W.
Washington, D.C. 20004-2402

130a

Van Carson, Esq.

Charles R. McElwee, II, Esq.
Squire, Sanders & Dempsey
127 Public Square

4900 Society Center
Cleveland, OH 44114-1304

John E. Frey, Esq.

Wildman, Harrold, Allen & Dixon
225 West Wacker Drive, 30th Floor
Chicago, IL 60606-1225

l3la

IN THE UNITED STATES DISTRICT COURT
FOR THE WESTERN DISTRICT
OF PENNSYLVANIA
Civil Action No. 91-408

[Dated November 24, 1999]

BEAZER EAST, INC. ,
Plaintiff,

Vv.

THE MEAD CORPORATION,
Defendant,

Vv.

KOPPERS INDUSTRIES, INC.,
Third-Party Defendant,

ed

JUDGE GUSTAVE DIAMOND
MAGISTRATE JUDGE BENSON

132a

PROPOSED FINDINGS OF FACT AND
CONCLUSIONS OF LAW

1. Procedural History.

This is an action commenced by Beazer East,
Incorporated, (Beazer) seeking contribution from The Mead
Corporation (Mead), for present and future expenses that have
been and will be incurred in the clean-up of an industrial site
near Dolomite, Alabama, referred to as the “Woodward Coke
Plant”. The sole claim remaining from the initial complaint is
a claim for contribution under to the Comprehensive
Environmental Response, Compensation and Liability Act, as
amended (CERCLA), 42 U.S.C. §9607. There is also a third-
party claim for contribution which is asserted by Mead against
the present owner of the Woodward Coke Plant, Koppers
Industries, Inc. (KIN).

The procedural history of this case is long and tortured,
and need not be recounted in full here, except for more recem
events. The court has determined that Mead is a potentially
responsible party (PRP) under CERCLA, and, hence, liability
has been established pursuant to that statute. Beazer is also a
PRP, having owned and operated the site from 1974 through
1988, and having already expended funds for investigation
and remediation at the site. Finally, there is no dispute that
KII, as the present owner and operator of the facility, and of
about half of the land in question, is also a PRP. 42 U.S.C.
§9607(a). There is, however, dispute concerning whether KIl
should be assigned a separate allocable share of clean-up
costs. This question will be addressed preliminary to
proceediag with the proposed findings of fact and conciusions
of law drawn from the hearing in this matter.

133a
A. Is Koppers a party to this allocation?

Beazer maintains that the sole question to be answered in
this proceeding concerns Mead’s allocable share. This is so,
in Beazer’s view, since Beazer may only seek through this
contribution action to have Mead found responsible for
Mead’s equitable share of the response costs. See, Pinal Creek
Group v. Newmont Min. Corp., 118 F.3d 1298 (9th Cir.
1997), cert. denied 118 S.Ct. 2340 (1998) (contribution
liability limited to a potentially responsible party's (PRP)
equitable share). Beazer also points to an agreement it has
with KII pursuant to which Beazer is responsible for all costs
incurred by KII with respect to environmental liabilities at the
site. (Indeed, Beazer and KII have been represented jointly in
this proceeding.) Thus, in Beazer's view, this is truly a two-
party proceeding, since whatever percentage of the response
costs is attributed to Mead, the remaining costs will be borne
by Beazer in any event.

Mead responds that any agreement between KII and
Beaz t is not properly before the court. What is at issue, in
Mead’s view, is the responsibility of all PRPs for the response
costs in this matter. Thus, since KII is a PRP, its
responsibility for contribution should be litigated in this
proceeding, and, indeed, must be litigated in order to properly
determine the allocable shares of Beazer and Mead.

A PRP may seek contribution from another PRP pursuant
to §9613(f). A PRP may make a claim for contribution for
either costs already incurred, or for costs to be incurred in the
future. In fact, Beazer seeks contribution for both expenses
already incurred, and for future expenses. Here, Mead has
made a claim for contribution under §9613(f) against KII.
Mead, as a PRP, is entitled to make such a claim, regardless

134a

of the fact that it has not, to date, incurred any response
costs. '

This court has already held, in ruling upon the motion to
dismiss Mead’s third party complaint, that consideration of
the allocable share o* all PRPs, including KII, is necessary. It
is not persuaded by Beazer’s argument that this conclusion
should change.

While it is true that an agreement exists between Beazer
and KII, this will result only in KII’s share of the response
costs, whatever that is found to be (and it is at least possible
that the share may be 0%), being ultimately paid by Beazer.
In any event, the court cannot properly pass upon Mead’s
allocable share without considering the responsibility of all
PRPs for the contamination at the Woodward Plant. Thus, the
first recommendation offered to the court is that KI] be
deemed a PRP, and that it be considered such as the court
fashions the ultimate allocation in this matter.

B. The court’s obligations.

This writer’s responsibilities with respect to the nexi step
to be taken in this matter were explained by Judge Diamond
in his order of July 8, 1996:

It further appearing that a determination of the
equitable factors to be considered in the parties’ claims
for contribution have not yet been determined and that
a report and recommendation identifying such

' That Mead will be assessed some portion of the response costs

is a foregone conclusion. The parties here merely dispute the extent
of Mead’s contribution.

135a

appropriate factors as well as setting forth a
comprehensive allocation of Beazer’s clean-up costs
among the parties is appropriate at this juncture, IT IS
ORDERED that a scheduling conference shall be held
before the magistrate judge wherein time frames shall
be established for (1) proposing the equitable factors
to be considered under §9613(f), (2) submitting briefs
in support of an allocation of Beazer’s clean-up costs
among the parties and, after a hearing if necessary, (3)
the submission of a report addressing same.

(Docket #193 at 3). A scheduling order was entered on
August 29, 1996 (Docket #201). Proposed equitable allocation
factors were filed by the parties (Docket #s 202, 203, 204).
Comprehensive allocation briefs, with appendices, were also
filed by the parties (Docket #s 227-229 and 231-235), as were
supplemental, reply and surreply allocation briefs and
appendices (Docket #s 236, 237, 238, 239 and 240). The
parties then submitted proposed findings of fact and
conclusions of law (Docket #s 247, 260). Expert reports and
rebuttal expert reports were filed at various times (Docket #s
207, 208, 216, 218, 219, 224).

A hearing was held in this matter over a period of twelve
days, beginning on May 6, 1997, and ending on May 21,
1997 (Docket #272). During that hearing, the parties
introduced more than forty-seven ring binders of exhibits, as
well as numerous demonstrative exhibits, along with the
testimony of fourteen witnesses. Although some of the
exhibits were adit = into evidence, rulings on others were
withheld pending —e submission of final exhibit lists by each
party and any objections thereto.

‘. On June 12, 1997, Beazer and KII filed a joint, final
exhibit list (Docket #274), referencing 748 separate exhibits.

136a

Of these, 700 were offered into evidence. Mead filed
objections to the admission of all or portions of 133 of the
exhibits offered by Beazer and KII (Docket #278). Mead also
provided a final exhibit list which sought admission of 493
separate exhibits (Docket #279). Beazer and KII objected to
the admission of all or part of 5 of these exhibits. Both
parties’ objections to the other’s exhibit list were filed on June
27, 1997.’ Many of the exhibits offered by Mead, and two of
those offered byBeazer and KII, were admitted into evidence
during the hearing (Docket #272). Rulings on the admissibility
of the 138 exhibits (or portions thereof) to which objections
were raised post-hearing were made in an order filed on July
21, 1997 (Docket #282).

The parties also filed designations and cross-designations
from numerous depositions, which fill six additional ring
binders. Objections to the designations and cross-designations
of each party were filed on June 5 and 12, 1997 (Docket #s
273 and 275). These objections often proceeded line-by-line
through the deposition excerpts. Mead’s objections are more
than 50 pages in length, and Beazer’s a relatively svelte 19
pages. Again, rulings on the objections to the specific
designations were made and entered in the record on June 15,
1999 (Docket #302). Thus, after great pains, the record has
been finalized.

* The undersigned represented to the parties that a report and
recommendation would be forthcoming by June 30, 1997.
Obviously, having received the final submissions of the parties on
June 27, 1997, and with a multitude of evidentiary rulings to be
made, the projected dated became somewhat unrealistic. The delay
in making these rulings has, for other reasons which are the court’s
responsibility alone, stretched on far beyond what it ought. For this
the court offers its apologies.

137a

C. The Third Circuit’s Opinion.

The court is not writing upon a clean slate in this case.
Hence, prior to setting forth proposed findings of fact and
conclusions of law, it will first be nevessary to review the
opinion accompanying the order of remand in this matter.

This matter was remanded from the Court of Appeals,
which reversed this court’s entry of summary judgment in
favor of Mead. Summary judgment was granted on the basis
of the indemnification provision contained in the 1974 Asset
Purchase Agreement (APA) between Mead and Beazer. The
parties now contest, and the court must decide, what impact
the appellate court’s ruling has upon the allocation
proceeding.

Beazer takes the position tha: the opinion of the Court of
Appeals prevents consideration of the APA’s indemnification
provision as a factor in equitable allocation. Mead, on the
other hand, asserts that the Court of Appeals’ decision was
addressed to the marrower issue of whether the
indemnification provision in the agreement was legally
sufficient to transfer liability. Mead argues further that the
present inquiry is whether the parties intended to transfer such
liabilities, a question not addressed by the Court of Appeals,
not whether they actually succeeded in so doing under
Alabama law, the question which was answered by the court.
Mead asserts that the record establishes the parties’ intention
to have a legally enforceable indemnification agreement, and
that this should be considered by the ourt in making an
equitable allocation between the parties.

Having thus framed the issue before the court, a careful
reading of the opinion of the Court of Appeals is in order.

138a

Early ip its opinion, the Court of Appeals framed the issue
before it as follows:

Thus, Beazer could have lawfully agreed to
indemnify Mead for its CERCLA liability or,
conversely, Mead could have lawfully agreed to
indemnify Beazer. The issue is whether either did so.

34 F.3d at 211. As framed by the Court of Appeals, then, the
issue on appeal was whether either party “lawfully” agreed to
indemnify the other. After determining that Alabama law
should apply to the construction and effect of the contract
provisions, the court refined its statement of the issue as
follows:

We conclude that Alabama law requires a plain
. _and unambiguous expression of intent to cover the cost
of the liability in question. Using this standard, we
now consider whether Paragraph 4(c) unambiguously
expresses Beazer’s intent to indemnify
Mead against CERCLA liability.

34 F.3d at 217. The court went on to hold that the language
in question was subject to more than one reasonable
interpretation, i.e., it could mean that the parties intended
indemnification for all liabilities, including CERCLA, or it
could mean that the parties intended to encompass a lesser
range of liabilities, not including CERCLA liability. The court
concluded: “Under applicable principles of Alabama law, the
parties failed to express the intent to indemnify with the
requisite clarity. We hold, therefore, that Paragraph 4(c) is
not specific enough to impose on Beazer a duty to indemnify
Mead for their CERCLA response costs.” 34 F.3d at 218.

139a

Accordingly, the Court of Appeals did not rule, as Beazer
would have it, that no indemnity was intended by the parties.
The Court of Appeals held instead that the expression of the
parties’ intent contained in the contract was not possessed of
“the requisite clarity” to permit a conclusion concerning that
intent as a matter of law.

Viewed in this fashion, there is no inherent inconsistency
in the ruling made on appeal and a decision by this court that,
as a matter of equity, the parties’ intentions concerning
indemnity, to the extent they can be divined from both the
document and any other evidence offered by the parties,
should be considered in equitable allocation. If, as Mead
argues, parol evidence plainly establishes that the parties
intended a sweeping indemnity provision, a decision by this
court to consider this fact in equitable allocation would not be
inconsistent with the ruling made by the Court of Appeals.
This is so since the Court of Appeals was not faced with this
question and, hence, did not rule upon it. The question the
appellate court decided was a legal one addressed to the
sufficiency of the contract language, under applicable state
law, to transfer all environmental liability for the site. Here,
the court is faced with making a factual determination
concerning the parties’ actual intent. It will then be the court’s
duty to determine what effect, if any, the parties’ intent should
have upon the equitable allocation of response costs between
the parties.

Other courts have drawn similar distinctions between the
legal sufficiency of an indemnity provision, and the
consideration of the intent of the parties in an equitable
allocation of response costs. In Kerr-McGee Chemical Corp.
v. Lefton Iron & Metal Co., 14 F.3d 321 (7th Cir. 1994), the
Court of Appeals for the Seventh Circuit found that a
contractual indemnity agreement, entered into in 1972 before

140a

the passage of CERCLA, was sufficient to shift the
responsibility for CERCLA response costs. In this respect, the
Seventh Circuit reversed the lower court's finding. Prior to
reaching this question, however, the appellate court found
error in the district court failing to consider the indemnity
agreement in the context of allocation, even though it had
concluded that the indemnity agreement was insufficient to
shift responsibility for CERCLA response costs.

Since the district court did not believe the
indemnification agreement applied to the cleanup costs
at issue, the court ignored the agreement when
allocating responsibility for cleanup costs. This was an
error. Although contractual arrangements between
parties are not necessarily determinative of statutory
liability, Lefton’s intent to indemnify Kerr-McGee
should be considered in the allocation of cleanup costs.
In determining the relative contribution of the parties,
courts must look to the “totality of circumstances.”
Environmental Transportation Systems, 969 F.2d
[503,] at 509 [(7th Cir. 1992)]. That Lefton - with
knowledge of the creosote on site - agreed that it took
the property “as is” and would assume all future
liabilities resulting from that pollution is certainly a
significant circumstance. The fact that Kerr-McGee’s
predecessor Moss-American was the source of most of
the pollution at the site may also weigh in the court’s
analysis; this, however, is not reason to ignore other
relevant considerations.

14 F.3d at 326.

The same analysis applies here. The Court of Appeals for
the Third Circuit has, in this case, determined that the
indemnification agreement is not legally sufficient to shift

14la

responsibility for Mead’s CERCLA costs to Beazer.
Nonetheless, if Mead can establish that there was an intent to
make such an agreement, but that the intent was not realized,
then that would be a factor worthy of consideration.

Also, even if no such intent is established, the fact that the
sale was made “as is” and that The Tar Plant is also undergoing a site-wide facility investigation
pursuant to the Resource Conservation and Recovery Act (RCRA)
which is not the subject of this lawsuit (Docket #287 at 61).

145a

19. In 1975, the coal washery was shut down (Beazer
thereaiter . chased “pre-washed” coal).

20. In 1977, the in-ground decanter tanks were replaced,
and a new ammonia stil! was installed.

21. In 1978, a wastewater treatment plant was built and
put into operation.

22. By 1980, tar decanter sludge, one of the toxic wastes
produced duriag the coking process (designated under RCRA
as K087), was recycled into the coke ovens and “rebaked.”
This was accomplished by mixing tar decanter sludge with
coal on the open ground.

23. Sometime before 1986, a concrete pad was installed,
and the mixing of coal tar sludge with coal was done on the
pad. On May 26, 1986, a hopper was installed for the mixing
of KO87 coal tar sludge so that tt could be recycled into the
ovens without any leaching into the soil.

24. Beginning in November, 1985, lime was no longer
used for the ammonia still, and was replaced by liquid caustic.

—

nt

25. KII upgraded the wastewater treatment plant in 1989,
and installed additional cooling towers. KI] also upgraded the
surface water containment system.

26. KII installed a benzene emissions capturing system in
1991.

27. The by-product coking process involves placing coal
in an oven and heating the coal, in the absence of air, to
extremely high temperatures. The coal is “baked” for between
16 and 36 hours. During this process, the “by-products”

146a

associated with coal are removed. A by-product plant captures
these excess products as steam, and, through various
processes, captures the constituents which include tar,
benzene, natural gas, and other useful products.

28. During the course of the coking process, including the
by-products recovery process, various waste products are
produced. The specific types of waste are, however, not
relevant to the court’s allocation since the parties have
stipulated to the following facts:

a. The types of contaminants generated during the
operations at Woodward Coke were similar for Mead,
Beazer and KII.

b. The unique production wastes generated by Mead
were associated with the light oil refining process, and the
production wastes unique to Beazer’s and KII’s operations
were associated with the waste water treatment plant.

c. The wastewater treatment plant solids generated
from coke plant production after 1974 were no more toxic
than the coke plant production wastes unique to the pre-
1974 operations.

d. with respect to wastewaters, the wastewater
treatment plant effluent is no more toxic than the untreated
wastewaters that had historically been discharged into the
Coke Plant lake or Opossum Creek.

(Docket #270, stipulations of fact 56-59).

29. Beazer has conducted remediation at three sites, on the
Plant property pursuant to §3008(h) of the Resource

147a

Conservation and Recovery Act (RCRA), 42 U.S.C.
§6928(h).

30. After discussions with State (Alabama Department of
Environmental Matters, or “ADEM”) and federal (United
States Environmental Protection Agency, or “USEPA”)
regulatory bodies in 1985 and 1986, Beazer agreed to close
three areas of the Plant which were designated by USEPA and
ADEM as Hazardous Waste Management Units (HWMU’s).

31. There are now three HWMU’s which are subject to
RCRA’s “post-closure” requirements. These units are
designated as Solid Waste Management Units (SWMU’s):
Unlined K060 waste pile (SWMU 1); Unlined KO87 (coal tar
sludge) waste pile (SWMU2); and Unlined KO87 (against coal
tar sludge) waste pile (SWMU 3).

32. Beazer has conducted groundwater monitoring and
reporting associated with the three RCRA units since 1986 in
accordance with its obligations arising from its agreement
with regulatory agencies.

33. Beazer and USEPA are the only named parties to a
1991 Administrative Order on Consent pursuant to which
Beazer has conducted an investigation of the Plant site.

34. Anapproved RCRA Facility Investigation (RFI) Work
Plan was submitted to USEPA by Keystone Environmental
Services on behalf of Beazer in September, 1991.

35. The RFI field effort was begun in February, 1992, and
completed in August, 1996.

148a

36. Beazer submitted its Draft Phase I and II RFI and
Groundwater Assessment Report to USEPA and ADEM on
March 6, 1997.

37. In addition to the RFI requirements of the RCRA
Order, the Draft RFI Report addresses ADEM’s requirements
to complete a Groundwater Quality Assessment as well as the
groundwater data requirements associated with post-closure
permitting.

38. At least some of the costs which Beazer has incurred
pursuant to the RCRA Order at Woodward Coke are
recoverable response costs which were necessary and were

incurred consistent with the National Contingency Plan
(NCP).°

B. Contested facts.

The following is a summary of the testimony given at the
hearing in this matter. Proposed findings of fact follow each
witness’ testimony.

WITNESSES

Mitchell Brourman

Mr. Brourman is the environmental manager for Beazer
East, Inc., 2 company with which he has been employed since

6

Based upon this stipulation, which is actually as much a
conclusion of law as a stipulation of fact, the parties do not, at this
time, seek to determine whether any specific cost incurred to date
by Beazer is recoverable. Instead, the parties agree that the question
of the recoverability of specific costs will be left to a later phase of
this proceeding.” (Docket #292 at 24-25).

149a

1991 (Docket #286 at 72). He has a master’s degree in
hydrogeology, and has previous employment experience as a
hydrogeologist. Hydrogeology is a field in which the fate,
transport, movement and occurrence of groundwater and
groundwater systems are studied (/d., at 76).

Mr. Brourman’s position involved his participation in field
projects prior to 1995. Since that time, he has been given
greater authority over administrative matters, purchasing and
liaison activities with respect to environmental field projects
(/d., at 81). Mr. Brourman’s duties with respect to the
Woodward Facility include: fiscal responsibilities;
participation in the decision to hire consultants; reviewing
invoices; insuring compliance with applicable environmental
regulations and orders; acting as liaison between Beazer and
ADEM; and technical guidance to the company consisting of
assisting in review of compliance procedures and specific
expertise in groundwater remediation (/d., at 82-84). He has
had personal involvement in Beazer operations at the Toledo
coke plant, the St. Paul coke plant and the Kearney Seaboard
coke plant (/d., at 84-85).

Mr. Brourman’s initial involvement at Woodward was as
a project manager during field investigation activities in 1992
(Id. at 86). He has visited the plant on about six occasions
during his tenure at Beazer (/d., at 87).

Mr. Brourman had “intimate review responsibilities” for
the RFI which was submitted to USEPA and ADEM (id., at
92). He identified the “Part A” permit application which was
filed for the Woodward Facility pursuant to RCRA regulations
on November 19, 1980 (/d., at 12; Plaintiff's Exhibit 346).
The permit application identifies two wastes which are
generated and stored on site, KO60 (ammonia still lime
sludge) and KO87 (tar decanter sludge) (/d., at 13). The

150a

application shows the former being stored in an equalization
tank which is part of the wasie water treatment plant, and the
latter located in an area by the north landfill (/d.). These were
identified as “RCRA regulated units” which are areas that are
subject to RCRA permitting requirements for storage,
treatment or disposal of hazardous waste (/d., at 15).

Beazer was notified by the EPA for the first time in 1985
or 1986 that the historic treatment and disposal of hazardous
waste at the Woodward site was a concern under RCRA, as
opposed to present practices, such as the operating RCRA
units already identified at that time (/d., at 17-21; Plaintiff's
Exhibit 369, a letter from USEPA dated March 13, 1986).
This came as a result of the enactment of the HSWA
amendments to RCRA which address historic disposal
practices (/d., at 22).

Beazer notified Mead on September 18, 1986, that
historical waste disposal practices may be the subject of a
RCRA §3008(h) corrective action order (/d., at 23; Plaintiff's
Exhibit 382). Mead responded to the letter by denying
responsibility for the questioned waste disposal practices (/d.,
at 24). The responsive letter from Mead references the Asset
Purchase Agreement, and states Mead’s position that Beazer
has assumed all liability for “solid waste matters” (Docket
#288 at 2-4; Defendant's Exhibit 1).

On March 22, 1988, Beazer notified Mead that a USEPA
contractor was about to conduct a facility assessment of the
Woodward Plant (Plaintiff's Exhibit 405). That assessment
was conducted on April 11 and 12, 1988 (/d., at 27). The
assessment report was prepared in May, 1988, by A.T.
Kearney, Inc. (Plaintiff's Exhibit 406). The report reflects the
result of a visual site inspection and the identification of “solid
waste management units” (SWMUs) and “areas of concern”

ISla

(AOCs). The former are areas in which hazardous waste is
presently being stored, and the latter are areas suspected to
have been used for historical waste disposal practices (/d., at
29). The report identified 39 solid waste management units
(SWMUs), including the three RCRA regulated units
identified in the Part A application (/d., at 30). Four AOCs
were identified.

In October, 1990, Beazer received a proposed consent
order pursuant to §3008(h) from the EPA (Plaintiff's Exhibit
425). On November 28, 1990, Beazer notified Mead of this
proposed order, and invited Mead to participate in the
negotiation of a final order on consent (Plaintiff's Exhibit
427). Mead did not participate (/d. , at 32).

After negotiation with USEPA, Beazer, through Keystone
Environmental Resources, Inc., submitted a RCRA facility
investigation work plan (/d. , at 37; Plaintiff's Exhibit 1325).
The work plan was designed to address the 39 SWMUs and
4 AOCs, but focused on the entire site for investigational
purposes (/d., at 38). The reasons for this approach are set
forth in the work plan:

EPA identified a number of Solid Waste Management
Units (SWMUs) and Areas of Concern (AOCs) at the
facility in a RCRA Facility Assessment Report (A.T.
Kearney, 1988). Due to the size of plant, the close
proximity of SWMUs and AOCs, and the impussible
task of defining the potential release from each
individual unit, potential releases from the entire site
will be investigated rather than investigating the
potential release from each SWMU or AOC
individually.

152a

(Plaintiff's Exhibit 1325 at I-2; Plaintiff's D-3). The same
document identifies the “specific objectives of the RFI” as
follows:

@ Augment data previously collected at the site;

@ Identify and define the nature and extent of

constituents that may have been released from
SWMuUs and AOCs at the site;

®@ Identify potential migration pathways;

@ Define the potential for migration of constituents at the
site;

® Identify the potential environmental impact and
potential risk to human health and the environment;

@ Gather necessary data to support the evaluation and
selection of corrective measures alternative, if
necessary.

(/d., at 39-40; Plaintiff's Exhibit 1325 at I-2).

Mr. Brourman had some hands-on involvement in the site
investigation that followed, and helped prepare the RFI report
which was submitted to USEPA and ADEM in March, 1997
(Id., at 41; Plaintiff's Exhibit 1338). In that document, the
reasons for choosing the whole-site approach are repeated, as
are the goals of the RFI. Those goals are slightly restated as
follows:

153a

1. Characterize the nature and extent of constituents of
interest (COIs) within and beyond the facility
boundary;

2. Determine and characterize the sources of COIs;

3. Define and characterize the potential pathways of
constituents migration;

4. Identify and characterize actual and potential human
and environmental receptors and assess the potential
risks posed to such receptors; and

5. Gather the data necessary to support the development,
evaluation, and selection of corrective measures
alternatives, as necessary.

(Id.) Phase I of the field work began in 1992. USEPA
required a second phase of field work, which began in 1995
(Id., at 46-47).

Mr. Brourman described in some detail the investigative
efforts actually performed. The details of that investigation are
not relevant to this report. At the time of his testimony,
however, Beazer had expended over $4.3 million during the
RFI portion of the investigation, and remediation was
expected to begin in September, 1997, and last for 2 to 3
years (/d., at 55-56). The amount does not include the three
RCRA regulated units (/d., at 64).

Mr. Brourman conceded that it is at least possible that no
remediation will be necessary at the site (Docket #288 at 8-9).

On cross-examination, Mr. Brourman noted that some
limited resampling was required with respect to the Phase I

154a

sampling program due to “problems with the quality control
aspects of the sampling at the laboratory.” (/d., at 9-10). No
additional charge was included for this resampling, since the
subcontractor was held responsible for providing quality
work, and was not paid additional compensation for
performing the resampling (/d., at 19). Further, costs
associated with wells installed to monitor the RCRA regulated
units are not included in the investigational costs sought by
Beazer in this action, although information from those wells
has been used in the preparation of the RFI (Docket #288 at
65-66).

Landfills 1 and 2 are not identified as either primary or
secondary areas of interest in the RFI report (/d., at 11). A
significant amount of investigative work was done with
respect to the landfills, however, including cross-section

sampling (/d., at 13).
Wayne M. Grip

Mr. Grip is the co-founder of Aero-Data Corporation,
which is an entity specializing in “aerial mapping and
environmental studies using aerial photography and historic
maps.” (Docket #207, Tab 5 at 1). He has previously testified
as ain expert in photogrammetry and photo interpretation (/d. ,
at 2-5). He was qualified in this case as an expert in aerial
photogrammetry and aerial photographic interpretation
(Docket #288 at 92). Mr. Grip was asked by Beazer to study
historical aerial photography of the Woodward site and
identify “the generic or the typical environmental types of
features that have resulted or typically do result in
contamination of a site.” (/d., at 93). He was also asked to
perform, and did perform, calculations concerning the volume
of wastes in two on-site landfills relying upon aerial

155a

photographs of the site from different historic dates (/d.). He
did this through terrain modeling and photogrammetry.

Mr. Grip’s testimony was certainly the most
technologically assisted presentation in this case. He provided
the court with photographs which had been modified to be
viewed in three dimensions; he provided historic photographs
as well as historic maps. During his testimony, he utilized a
high resolution projection system attached to a computer
which generated digital photographs (/d., at 94).

The first step in Mr. Grip’s work was to obtain any and all
historic aerial photographs of the site in question, as well as
maps of the area (/d., at 98). He noted that he is, in such
cases, often dealing with second or third generation film, in
the sense that he is obtaining not the original negative film
used, but a copy made from a positive produced from the
original negative. This results in some loss of resolution (/d.).

The film which is obtained is then “photo-indexed”
whereby the center of each photograph is plotted on a map of
the area. A set of similarly sized prints of the photographs is
then made, and each is scaled, oriented and cropped in the
same manner, so that one may flip from one historic
photograph to the next and compare the same area or feature
in one to the same area or feature in another (/d.). “Stereo”
prints are then developed, which are prints of the same or of
overlapping areas of the map. The difference in distance from
the lens for each photograph provides a means by which the
height of objects pictured may be derived, and by which
terrain maps may be made (/d., at 101-02).

Once all of the information is obtained, it is transferred to
a stereoplotter which, in Mr. Grip’s words, “can zoom in
very, very closely into the aerial photography and allow the

156a

operator to see it in full stereo with very good resolution.”
(/d., at 106). “Stereo pairs” of photographs are obtained, that
is, pictures of the same features or area are made from
overlapping photographs. The overlap in the photographs
means that the same area has been photographed from two
slightly different angles. This difference in “parallax” offers
the photointerpreter the ability to use a mirror stereoscope,
with both pictures underneath it, to see a three-dimensional
image (/d., at 111-12).

The writer does not wish to oversimplify the process by
which photogrammetry is accomplished. The court is satisfied
that methods of producing terrain maps from historic
photographs were proper and that representations of the site
in the three maps prepared by Mr. Grip are as accurate as the
process permits.

The three terrain or contour maps presented by Mr. Grip
are for the years 1948, 1971 and 1993 (/d., at 124; Plaintiff's
Exhibit 1100, pages entitled “Contour Map of Landfill
Areas”) (it must be remembered that these dates are dictated
not simply by historic dates which may have meaning in the
context of this litigation, but also by the availability and
quality of aerial photography of the site). The witness also
testified that he mapped the terrain from a series of
photographs taken in 1940 (/d., at 124-25). On each of the
three maps, Mr. Grip has identified “landfill” areas. These
are areas which other testimony and evidence of record, as
well as Mr. Grip’s photo interpretation, identify as being the
areas where wastes from the plant site were disposed. Mr.
Grip, using stereo pairs for each of those dates, calculated the
volumes of the landfill areas identified on the maps of the site
for each date (/d.). From these calculations he reaches the
conclusion that 79% of the total volume of waste placed in the

1S7a

two landfills between 1940 and 1993 was placed there prior
to 1971 (Plaintiff's Exhibit 1100).

Mr. Grip was asked to explain the methods by which he
checked the accuracy of his computations. With respect to
horizontal accuracy, he used a method of overlapping the
photographs in areas with fixed features, such as buildings,
and producing an exhibit which showed in different colors the
outlines of such features, and showed how closely they
matched from photograph to photograph (Tr. 126; Plaintiff's
Exhibit D-7). The exhibit is called a “composite planimetric
map” (/d., at 127).

With respect to the vertical accuracy of his measurements,
Mr. Grip again explained the manner in which he obtained the
volume of the landfills for his starting date of 1940:

. . . basically I used the 1948 stereo photography
with the mirror stereoscope, and I measured the height
above surrounding terrain of the southern landfill at
multiple locations by comparing it with the height of
small vehicles in the parking lot. Aad in this way I
was able to derive an average thickness for the landfill
as it existed already in 1948.

And I repeated that process for the 1940 date and
earlier date, subtracted the 1940 thickness from the
‘48 thickness, and arrived at the increase in thickness
of the landfill for that period. So this thickness times
the surface area of the landfill equals the increase in
volume for that period... .

***

158a

Then for the 1948 to 1971 percent, as I described
earlier, | used the TIN derived from the ‘48 contour
map and the TIN derived from the ‘71 contour map
and calculated the added volume to the southern
landfill between the two dates using the terrain
modeling software.

(Id., at 128).

Mr. Grip testified that he concluded, based upon his
calculations, that 227,294 cubic yards of material were placed
on the landfills on site between 1940 and 1993, and that
46,877 yards of materials were placed on those landfills after
1974 (Tr. 183-84).

Mr. Grip was also asked to interpret photographs and the
images which appeared thereon historically. The witness
described the conclusions he drew concerning the site from
his interpretation of several photographs. In comparing aerial
photographs From 1940 and 1945, he noticed an increase in
height in the area of the northern landfill (/ © , at 136-37). He
also compared ihe condition of trenches, a sump, turbid water
beyond an earthen dam, and fluid flowing in channels from a
cooling pond (/d., at 137; Plaintiff's Exhibit 1100,
photographs of 11/17/40 and 8/28/45). He also identified
areas on which dark materials are stockpiled.

The next photograph is dated 1/15/48. Mr. Grip again
identified material stockpiles which are changing in shape
fromm previous photographs, and an increase in the volume of
the southern landfill (/d., at 138). He identifies a “braided
stream ‘ effect where water from the plant is entering the plant
lake, indicating the presence of sediment and particles in the
water settling out into the lake. He also notes a “plume” in the

159a

lake indicating the presence of something, such as an oil slick
or particles in the water (/d., at 138-39).

Similar interpretative work was done with respect to
photographs dated 3/31/51, 1/9/56, 11/2/60, 3/66, 2/21/70,
1/27/71, 4/29/73, 1/9/76, 3/15/78, 12/18/82, 12/29/85,
3/5/90 and 3/29/93 (Plaintiff's Exhibit 1100, section entitled
“Interpreted Images of the Woodward Coke Plant from
11/17/40 through 3/29/93). Mr. “rip then furnished a
summary of his conclusions from the interpretation of the
photographs listed above:

LANDFILLS

@ Southern Landfill - The Southern Landfill is visible
and active in the photography of 11/17/40. By
12/1/75, the landfill is inactive.

@ Northern Landfill - The Northern Landfill is first seen
in the photography of 3/7/52. By 8/28/85, vegetation
is returning within this inactive landfill area.

® Third Landfill - A third landfilling operation is visible
in the photography of 11/17/40. This landfill is
inactive by 8/28/45.

WATER BODIES

Prior to 1974, surface runoff from the stockpiles on the
western side of the Site and discharges from the coke plant
flowed directly into Pond | with little or no evidence of
treatment. Plumes were detected in the surface water of
Pond 1 and a large mud flat area grew in the northern
portion of the pond over time. These features evidence the
ongoing discharges from the plant area to the north.
Plumes were much less noticeable in Pond | after 1/9/76.

160a

After 1974, significant changes were made to the existing
ponds, and new ponds were constructed. The new ponds
received some of the discharges that formerly flowed into
Pond | and appeared to be used as settling basins. Pond 2
which is also called the “cooling pond” was filled in and
the area converted to a parking lot by 10/8/78.

TRENCHES

Trenches are visible in the photography from 11/17/40
through 2/24/81. Fluids and solids were detected in these
trenches on most dates. The trenches are somewhat
smailer in surface area after 2/22/73 and are no longer
visible after 2/24/81. The trenches were used for the
disposal of waste materials. Most, if not all, of the
disposal occurred prior to 1974.

DARK STAINING

Dark staining was mapped in the photography on

numerous dates, both before and after 1974, in the

southern portion of the processing area. Drainage in this

area flowed toward Pond | and Pond 5. It is my opinion

that the dark staining results from ongoing leakage or

spills from the area of the nearby pump houses or tanks.’

(/d., section entitled “Summary of Conclusions”; Plaintiff's
Exhibit D-9; Docket #288 at 171-177). In making this report,
Mr. Grip relied upon 8 maps of the area and 48 separate
photographs of the site (Docket #207, Tab 5, Attachment A).

” It should be noted that, during the hearing on this matter, the
court sustained an objection to Mr. Grip's testimony that the dark
Staining was caused by a spill of liquid (Docket #288, at 145-148).
The undersigned later noted that Mr. Grip could properly testify
that the dark stain is consistent with a spilled liquid or liquid on the
ground from some source (/d., at 162).

l6la

On cross-examination, Mr. Grip conceded that while he is
a member of the American Society for Photogrammetry and
Remote Sensing (ASPRS), he is not certified by that entity
(Docket #288 at 185-86). Mr. Grip did not visit the
Woodward Coke Plant, nor did he personally take aerial
photos of the site (Docket #289 at 2).

Mr. Grip also conceded that there is a subjective element
involved in photo interpretation (/d., at 6). There is also a
subjective element in photogrammetry, and a margin of error
inherent therein (/d., at 6-7).

When conducting photogrammetry, it is better to have the
original film to work from. If the original film is not
available, then a second generation contact film print, rather
than a paper print, would be preferable (Docket #289 at 22-
23). As noted earlier, each generation of reprints results in a
loss of resolution. Further, film prints have less inherent loss
of resolution than would a paper print.

Mr. Grip explained the manner in which he determined
the vertical precision of his photogrammetry, i.e., how he
determined the precision of the measurements of depth which
he used in calculating the volume of he landfills on varying
dates. He did this by measuring certain “control points” thirty
times through using the stereoplotter and determining the
standard deviation of those measurements (Docket #289 at
31). He used as control points the rooftop of a building or
other feature which would not change in elevation over time
(/d., at 32).

162a

Gabriel Lucisano*®

Mr. Lucisano was retained by Mead to review Mr. Grip’s
expert report, with particular attention to the volume
calculations contained therein (Docket #293 at 25). Mr.
Lucisano is Manager of Photogrammetry and Environmental
Services for IntraSearch, Inc. (/d., at 12). He has 20 years
experience in photogrammetry, and is a Certified
Photogrammetrist as recognized by the ASPRS (Docket #216,
Tab D). He has participated personally in over 300 projects,
including 47 ‘hich involved volumetric mapping (/d.).
IntraSearch was founded in 1951, and has an extensive
historical aerial photography library (Dockei #293 at 15). Mr.
Lucisano has personally performed approximately 15,000
hours of photo interpretation and has been involved in about
50 historical aerial photography projects, ard about 50
projects, both current historical, involving volume calculations
(/d., at 17).

Mr. Lucisano was offered and found qualified as an expert
in the field of mapping sciences, and in particular of all
aspects of photo interpretation and photogrammetry (/d., at
24-25).

Mr. Lucisano stresses in his report that aerial
photography, and in particular historical aerial photography,

* Mr. Lucisano testified during Mead’s case-in-chief. Although his
testimony is several witnesses removed from Mr. Grip’s, Mr.
Lucisano’s testimony is addressed specifically to Mr. Grip’s report
and conclusions. Hence, Mr. Lucisano’s testimony is summarized
in this report immediately following the summary of Mr. Grip’s
reports and testimony. The undersigned will group other witnesses
in like fashion where appropriate in an attempt to make this report
more useful to and convenient for the court.

163a

is not an exact science (/d.). Under the best of circumstances,
using state-of-the-art equipment and proper procedures with
new photography, computations within plus or minus 1 % of
actual conditions may be attained. In his opinion,
interpretation of historical photographs without control
measures such as surveyed ground control cannot approach
the level of accuracy claimed by Mr. Grip.

Generally accepted industry standards for photogrammetry
set forth maximum flying heights for photographs, maximum
photo enlargement ratios and surveyed ground control. None
of these elements is present with respect to the historical
photography which Mr. Grip used in this case. Thus, in Mr.
Lucisano’s view, the following questions are left unanswered
by the Grip report:

Quadrangle maps used to “scale” and “orient a work
print” are only accurate horizontally within 50 feet,
and vertically within 10 feet.

Camera accuracy as measured by focal length and lens
distortion is unknown.

Mapping should be done with only the original copy
negative, as each generation of reprints and copies
diminishes accuracy.

The earliest photograph available from which volume
calculations are made does not give information
concerning Virgin ground conditions (i.e., whether the
material seen is filling a ditch, or covering a rock).

(Docket #216, Tab D). Mr. Lucisano opines that the
photographs relied upon by Mr. Grip have expected errors in
elevation measurements of between 2 and 5 feet, depending

164a

upon the height at which the photograph was taken, in Mr.
Lucisano's view, the volumes reported by Mr. Grip could be
inaccurate by as much as 50%. Mr. Lucisano testified that, in
his view, Mr. Grip’s report “lacked

[Text truncated at 120,000 characters. The full text is on the page linked above.]

---

Source: Frix Law Library, https://www.frixlaw.com/law-library/documents/brief%3Amicro_IA40386016_0375%3A2. Public record. Not legal advice.
