la
APPENDIX A
UNITED STATES COURT OF APPEALS,
FIFTH CIRCUIT.
No. 73-2765.
Hayes INTERNATIONAL Corporation, Plaintiff-Appellant,
v.

Dr. Joun L. McLveas, Secretary of the Air Force,
Defendant-A ppellee.

Tur Borrna Company, Intervenor-Appellec.
March 6, 1975.

Appeal from the United States District Court for the
Northern District of Alabama.

Before Turrie, Coreman and Arnsworts, Circuit Judges.
Turtie, Circuit Judge:

This case involves a suit by an unsuccessful bidder for
a Government contract to have the contract awarded to
a competitor set aside as being in violation of the regu-
lations of the Department of Defense governing conflicts
of interest in Federal procurement, § 1-113.2 and Appendix
G of the Armed Services Procurement Regulations
(ASPR), 32 C.F.R. §1-113.2 and Part 141 (1971). The

132 C.F.R. § 1-113.2 (1971) Organizational Conflicts of Interest
provides that:

‘“(a) Appendix G—Rules for the Avoidance of Organiza-
tional Conflicts of Interest sets out some of the more essential
policy considerations of the Department of Defense with
respect to relationships with nonfederal institutions. Specific-
ally, Appendix G describes examples of various organizational
conflicts of interest which might come into being, and rules for
avoidance of such conflicts: and it provides that action must be
taken to avoid placing a contractor in a position where his
judgment might be biased or where he would have an unfair
competitive advantage within the scope and intent of the rules.

2a

successful bidder, the Boeing Company, joined the suit as
defendant-intervenor.

However, the Appendix cannot of itself impose any obligations
on the contractor: such obligations must be imposed by a con-
tract clause designed to carry out the intent of the Appendix.
Furthermore, potential contractors must be advised in the
solicitation as to the extent of applicability of the rules, and
must be given an opportunity to negotiate on the terms of the
clause and its application.

(b)(1) The contracting officer is responsible for applying the
rules in the Appendix to contracts under his cognizance and
shall determine whether such proposed procurement is subject
to the Appendix... .’’

The general provisions of 32 C.F.R. § 1-113.2 further provide for
procedures by which the contracting officer may determine whether
a potential conflict of interest exists, and the method by which he is
to deal with that potential conflict. It concludes:

‘*(e) The contracting officer shall not impose restrictions
under the Appendix in follow-on procurements on any
prospective contractor in the absence of a specific contractual
agreement with that contractor.”’

Appendix G of the Armed Services Procurement Regulations
states four rules for the avoidance of organizational conflicts of
interest. In the Preamble to those rules the regulation states
‘*Tw]here the Department of Defense does contract for research and
development work, as it must for the bulk of that work, its choice of
a contractor should be based primarily upon two considerations :

‘(1) Getting the job done effectively and efficiently, with due
regard to the long-term strength of the Nation’s scientific and
technical resources, and

(2) Avoiding assignments of work which would create inherent
conflicts of interest.’ ’’

Appendix G then sets out four specific rules on possible organiza-
tional conflicts of interest which state general prohibitions which
are explained and illustrated by specific examples. The rules are
said not to be meant to be viewed as all-inclusive.

**There will undoubtedly oceur cases which are not resolved
by these rules. As the Bell Report [Bureau of the Budget,
Report to the President on Government Contracting for Re-
search and Development, Sen.Doe.No. 94, 87 Cong., Second
Sess. (1962)] said ‘[Conflict of Interest] arises in several

3a

The district court originally issued a preliminary in-
junction enjoining the Secretary of the Air Force from

forms—not all of which are by any means yet fully under-
stood.’ In order to assist in deciding what, if any, prohibition
should be applied in such instances, the two basic principles of
this Code—(1) preventing conflicting roles which might bias a
contractor’s judgment, and (2) preventing unfair competitive
-advantage—should be paramount. The following rules and
examples are not all-inclusive but merely attempt to achieve
these two goals in a variety of situations. The ultimate test
should always be: Is the contractor placed in a position where
his judgment may be biased, or where he has an unfair com-
petitive advantage? If so, corrective action must be taken in
accordance wth the rules below.’’

The first three of the rules apply specifically when a contractor
agrees to provide Systems Engineering and Technical Director
(SE/TD) for a system, without at the same time assuming overall
contractual responsibility for its development. The terms ‘‘Sys-
tems Engineering’’ and ‘‘Technical Direction’’ are defined within
the rule, and are said to be terms of art relating to military pro-
curement. The last of the four rules applies to situations where a
contractor obtains data in which a competitor has proprietary
rights, and the use of that proprietary data is accordingly limited.

Part 141 of 32 C.F.R. was deleted effective November 5, 1971.
See 36 F.R. 21339 (1971). Despite this deletion, 32 C.F.R. § 113.2
continues to refer to Part 141 as containing the operative rules
governing avoidance of organizational conflicts of interest. The
text of former Part 141 of 32 C.F.R. remains as Appendix G of the
Armed Services Procurement Regulations. At the request of this
Court, counsel for all parties were invited to comment on the con-
tinued legal effect of Appendix G, following its deletion from the
C.F.R. There is no doubt that both the sustaining engineering con-
tracts awarded to Boeing, and the IRAN/Modification contract
awarded to Boeing in 1971 were awarded prior to the deletion of
Part 141 and hence the deletion would have no immediate effect on
the subject matter of this suit. Both counsel for the plaintiff and
the Government have submitted supplemental papers to this Court
to the effect. that the deletion of Part 141 was due to inadvertence,
and that the Air Force has continued to view Appendix G as being
of continued legal effect. Naturally this Court is not prepared to
make findings of fact on this matter. We note that the deletion of
Part 141 creates confusion as to the continued legal effect of the
Rules for Avoidance of Organizational Conflicts of Interest.

4a

taking any action pursuant to the contract awarded to
Boeing; this Court on October 14, 1971, issued an order
without opinion granting the Secretary of the Air Force’s
motion for a stay pending appeal. The plaintiff, Hayes
International Corporation, then moved the district court
to vacate the preliminary injunction and the matter pro-
ceeded to trial. Hayes stated that the reason it was
requesting that its original preliminary injunction be va-
cated was that it was in the ‘‘best interest of all the
parties that this case proceed as quickly as possible to a
judgment on the merits’’ inasmuch as the challenged con-
tract was then scheduled to extend for as long as five years.

The case was tried without a jury. The trial court found
that Boeing did not enjoy an unfair competitive advantage
over Hayes, nor was it guilty of a conflict of interest which
might have biased its judgment and accordingly held that
the contract was valid. The plaintiff brings this appeal.
We affirm.

I.
Facts

The facts of this case are largely undisputed. While the
expert witnesses at trial differed as to their view of the
applicability of the organizational conflict of interest regu-
lations, and to the extent of Boeing’s actual advantage over
other bidders seeking the contract in question, the case
largely involves the legal issue of the extent to which the
Armed Services Procurement Regulations apply to the
facts of this case.

In March, 1971, the Secretary of the Air Force, acting
through the United States Department of the Air Force,
Air Force Logistics Command, Headquarters Oklahoma
City Air Materiel Area, Tinker Air Force Base, issued
‘‘Requests for Proposals’’ for the procurement of services
to perform the ‘‘inspection and repair as necessary’’
(IRAN), modifications and other related work on the world-

BAL RRM ESR AO PST

da

wide Air Force Fleet of KC-135 Aerial Refueling Tankers.
The Requests were issued pursuant to the authority dele-
gated to the Secretary in 10 U.S.C. § 2304(a) (10) (1970).
Pursuant to the Request, on June 23, 1971, the Secretary
awarded contract No. F34601-71-C-3366 to the Boeing Com-
pany, to take effect on July 2, 1971. Hayes International,
the plaintiff in this suit, was one of the two unsuccessful
bidders for this contract.”

Contract 3366 was awarded to Boeing by the Air Force
in the amount of $12,294,894.16 for the first year of per-
formance. The contract was designated to extend over a
five-year period for substantially similar maintenance and
repair work, based upon options available to the Govern-
ment to make periodic work assignments. The five-year
contract was thus valued at approximately $60,000,000.

The KC-135 is an aircraft originally manufactured by
Boeing, and is used by the Air Force as a tanker for sup-
plying fuel in mid-air to other aircraft.2. The IRAN/Modi-
fication contract, as contracts of this sort are referred to
in the industry, provided for three classes of work to be
performed. The successful bidder was first to perform
periodic inspections of each aircraft. The proposal sub-
mitted by each of the bidders described the procedures
the bidder would follow on each aircraft and offered a per
unit price for this work. Secondly the bidder agreed to
perform such modifications as prescribed by the Air Force.
Modifications might be performed only on individual air-

? McDonnell-Douglas Aircraft Corporation was the third bidder
for IRAN/Modification contract 3366.

3The 135 family of aircraft are the military equivalent of the
Boeing 707 commercial aircraft. The KC designation describes a
particular kind of 135 aircraft, and the IRAN/Modification con-
tract in question applied only to that specifie class of 135 aircraft.
Other Boeing built 135 aircraft include: the C-135 cargo plane, the
EC-135 electronics cargo plane, the RC-135 reconnaissance cargo
plane, and the W-135 weather plane.

6a

craft, as each suffered individual wear and fatigue fol-
lowing use, or as modifications might be prescribed for
each aircraft in the KC-135 fleet. No estimate of total
costs was possible because at the time the proposal was
submitted it was not known how many aircraft would
need modification, or precisely what modifications would
be required. The third part of the work contracted for
by the Air Force under contract 3366 was unscheduled
maintenance at the time the IRAN work was being per-
formed. Following the inspection of each aircraft there
might be a variety of different types of repairs which needed
to be performed. Each bid set out a formula by which
payment could be estimated. This entails largely a desig-
nation of a set fee per man hour of work. Using this
formula, the Air Force would be able to estimate the total
costs of any particular repair on any given number of
aircraft.

Hayes International had been awarded a similar contract
for the forty months preceding the issuance of the Boeing
contract, but lost the 1971 contract for its bid was several
million dollars higher than that submitted by Boeing.

For a number of years before contract 3366 was awarded
Boeing had been under contract to the Air Force to supply
sustaining engineering and related support services for the
KC-135 fleet. Pursuant to these contracts Boeing had made
specific recommendations as to what maintenance and modi-
fications were required on the entire fleet of more than
700 KC-135 aircraft. Boeing continues to operate under
these sustaining engineering and related support services
contracts. These were awarded to Boeing on a “sole
source’’ basis without competition or open bidding,‘ as

*10 U.S.C. § 2304(4) provides for the letting of contracts follow-
ing formal advertising for bids. The section also sets out a number
of exceptions to this requirement of formally advertising for com-
petitive bids, including where the contract is for property or serv-
ices for which ‘‘it is impracticable to obtain competition,’’ -10
U.S.C. § 2304(a) (10).

POR PRN AS SO SEIT ELLIE CLE EGG i

cs PO”

7a

was customary in awarding sustaining engineering con-
tracts to the original manufacturer of a given aircraft.’

5 Defendant’s Exhibit No. 2 introduced and received into evi-
dence at trial shows the 74 IRAN/Modification contracts in effect
during FY ’72 and the first quarter of FY ’73 which had been
let by one of the five Air Materiel Areas. These 1RAN/Modifica-
tion contracts were for maintenance on many different types of air-
craft. Of the 74 IRAN/Modification programs, 51 involved air-
craft for which the original manufacturer had obtained engineer-
ing support contracts which the evidence showed were similar to
the sustaining engineering and related support services contracts
Boeing held for the KC-135. In 16 of the 74 IRAN/Modification
programs, the original manufacturer had obtained the IRAN/Modi-
fication contract. Of these 16, 11 held or had held engineering serv-
ice contracts. Five manufacturers who obtained IRAN/Modification
contracts had not previously held engineering support contracts.
Thus 40 IRAN/Modification contracts were awarded to a contrac-
tor other than the original manufacturer, despite the manufac-
turer’s engineering services contracts.

During FY ’72 and the first quarter of FY ’°73 Hayes Interna-
tional, the plaintiff in this suit, had successfully competed against
the original manufacturer holding an engineering support contract
for 3 IRAN/Modification contracts—contracts for the C-130, the
C-123 and the B-57 (during the first quarter of FY °73). Hayes
International on five occasions during the period covered by De-
fendant’s Exhibit 2 had competed for IRAN/Modification con-
tracts where the original manufacturer did not hold sustaining
engineering contracts.

The record shows that manufacturers routinely bid on TRAN/
Modification contracts for aircraft which they had originally pro-
duced ; experts in the field of Air Force procurement testified that
they knew of no instance where a manufacturer had been prohibited
from competing for an IRAN/Modification contract, and further
testified that the Air Force routinely entered into engineering sup-
port service contracts with original manufacturers similar to that
which Boeing held for the KC-135. Finally the record showed that
a manufacturer could obtain substantially greater profit on-per- °
forming IRAN/Modification contracts than it could performing
sustaining engineering services.

Defendant’s Exhibit No. 2 shows that original manufacturers
routinely obtain engineering support service contracts. However,
the 74 IRAN/Modification programs in effect during the five

8a

The trial court found that Boeing’s relationship under
the sustaining engineering and related support services
contracts was essentially as the ‘‘engineering arm’’ of the
Air Force for the KC-135 fleet.

Among its findings of fact, the trial court found: (1) as
the contractor responsible for sustaining engineering for
the KC-135 fleet, Boeing proposed a number of different
modifications and improvements in the KC-135 design;
(2) Boeing as part of its duties under the sustaining en-
gineering contracts conducted a series of tests, evaluating
fatigue stress, and other factors which affect the durability
and usefulness of each aircraft; and (3) Boeing was thus
privy to technical data it generated as well as that pro-
vided by the Air Force. It was undisputed that Boeing
was responsible for recommending to the Air Force what
priority should be placed on any particular set of repairs.

The repairs and modifications which Boeing recommended
to the Air Force comprised in part the work the IRAN/
Modification contractor would perform. Boeing was thus
in a position to recommend changes and modifications to
aircraft which would enhance the value of the TIRAN/Modi-
fication contract it subsequently was awarded.

Hayes argues as a consequence of Boeing’s sustaining
engineering contracts it violated those D.O.D. regulations
outlawing organizational conflicts of interest—both because
in its dual role as both technical advisor and IRAN/Modif-
cation contractor Boeing was in a position to recommend
work which it eventually performed, thereby raising the
possibility of unneeded repairs being recommended to in-

quarters included in the exhibit show that such engineering sup-
port service contracts do not provide such a competitive advantage
in bidding for TRAN/Modification contracts that manufacturers
with sustaining engineering contracts were able to obtain a signifi-
eant number of IRAN/Modification contracts. Thus the relation-
ship between prior engineering support service contracts and sub-
sequent bidding on IRAN/Modification contracts is uncertain.

AMG OPIN LOTS: *, SRNR
va ES Sa, PO et CEN Pe ve CaM RES AIR IS ij

9a

crease its own profits, and in addition because Boeing’s
competitive position was superior to all others bidding for
the IRAN/Modification contract. This latter facet of its
alleged violation of D.O.D. procurement regulations was
due to Boeing’s acknowledged superior opportunity to ob-
tain and assess information—thereby enabling it to know
with greater assurance what types of modifications and re-
pairs would be performed under the IRAN/Modification
contract. Because it alone knew what modifications could
be expected, something which no other competitor knew with
equal certainty,® Hayes alleges Boeing could submit a
lower bid for work all bidders knew was to be performed,
and recoup its profits on the additional work assignments
it alone knew would be forthcoming.

At trial Hayes proved that Boeing recommended three
specific sets of modifications which had the effect of greatly
increasing the value of the IRAN/Modification contract it
obtained, information which neither of its competitors pos-
sessed at the time of bidding. These three sets of repairs

® Hayes International, as the IRAN/ Modification contractor from
1968 to 1971, was aware generally of structural problems in the
aerial boom and the wing for which Boeing recommended modifica-
tions. At trial it was shown that Hayes participated in meetings at
which these problems were discussed, but Hayes did not receive the
same information which Boeing used in recommending modifica-
tions and repairs, and the trial court found that Boeing had access
to confidential and vital information its competitors lacked.

Thus while the evidence showed that Boeing had access to infor-
mation which enabled it to predict with far more certainty what
modifications could be expected during the term of contract 3366, at
the same time all bidders knew that many modifications could be
expected. During the 40 months during which Hayes had held an
IRAN/Modification contract on the KC-135, over 153 modifications
were added to the contract enormously increasing its value. This
was not unusual, and the record shows that the initial predicted
value of a contract was almost always smaller than the ultimate
value the contract was to reach after many modifications were made
to it.

10a

involved alterations to the aerial boom,’ and two sets of
wing modifications. One of the wing modifications is actually
being performed by Boeing under its IRAN/Modification
contract as is the aerial boom modification but the most
substantial sepair, Wing Fatigue Package V (which was
valued as being in excess of $200,000,000) was awarded to
Boeing subsequent to the filing of this litigation on a sole
source basis. Beyond these specific instances of advance
knowledge of modifications to be performed, Hayes argues
that Bocing’s general responsibility for proposing modifi-
cations and repairs which were to be performed under the
IRAN/Modification agreement constitutes the type of or-

7 The aerial boom is the nozzle by which fuel is transferred in
mid-air from the KC-135 tanker to other aircraft. The alterations
in it which Boeing performs under its IRAN/ Modification contract
have an estimated cost of $2,000,000.

8 The two sets of wing modifications were issued in the form of so-
called ‘‘Wing Fatigue packages,’’ both of which Boeing performed.
Wing Fatigue Package IV was issued to Boeing under the IRAN/
Modification contract 3366. Wing Fatigue Package V involved far
more extensive changes in the wings of every KC-135 aircraft, and
at a unit price of $313,934.00 amounts to a total cost for a modifica-
tion of the entire fleet of over $200,000,000. This modification was
later issued to Boeing under a separate contract, No. F34601-72-C-
4213-PZ,0003, as opposed to being assigned to Boeing under its
IRAN/Modification contract.

Hayes at oral argument and in what it styled a ‘“Supplemental
Statement’’ in effect expanded its requested relief to include an
injunction against the continued operation of this second contract.
The Government argues, in our view correctly, that the second re-
quested injunction constituted a new issue raised on appeal, and
that under cases such as Cliff Food Stores v. Kroger, Inc., 417 F.2d
203, 208 n. 3 (5th Cir. 1969) ; Poston v. Caraker, 378 F.2d 439 (5th
Cir. 1967) ; Humble Oil & Refining Co. v. Martin, 298 F.2d 163 (5th
Cir. 1961), such a new issue cannot be raised at this time on appeal.
It is not necessary to specifically consider the problem vigorously
argued by the parties in supplemental papers whether an injune-
tion could properly issue against this second contract, however,
inasmuch as we affirm the trial court’s denial of the permanent
injunction requested to enjoin enforcement of contract 3366.

lla

ganizational conflict of interest which is barred by 32 C.F.R.
§ 1-113.2 and Part 141 (1971).

The district court found that while Boeing had access to
vital information concerning the KC-135 fleet it also found
that the Air Force evaluated all recommendations made by
Boeing, and that Boeing was not in a position to make final
decisions on its own recommendations for modifications and
repairs. The district court further found that Boeing was
only one source of ideas for improvement, although it did
not specify what sources other than those within the Air
Force itself affected work specifications and modifications
for the KC-135.

The district court found that the Air Force has made a
practice of awarding sustaining engineering services con-
tracts substantially identical to those with Boeing with the
manufacturers of several other aircraft in its inventory.
Some of these manufacturers have subsequently competed
for IRAN/Modification contracts on the aircraft they were
supplying with sustaining engineering services—at times
being successful, and at times unsuccessful in bidding for
the modifications which they in part pronosed. “he court
noted that Hayes itself had competed occasionally against
the holder of a sustaining engineering contract—winning
some IRAN/Modification contracts, and losing others. The
court found that one such example was the C-130 Lockheed
built aircraft, in which competition Hayes was successful;
the court noted that subsequent to the granting of contract
3366, Hayes and Boeing also competed for work on the
KC-135 A aircraft, where the contract was awarded ulti-
mately to LTV Corporation.

The district court concluded that ‘‘Service Engineering
Contracts with the Air Force do not result in the contrac-
tor being in a conflicting role which might bias its judg-
ment nor do such contracts result in the contractor obtain-
ing an unfair competitive advantage in bidding on future
contracts for work on the aircraft involved.’’ The court

12a

further found that the award of contract 3366 was ‘‘not
contrary to public policy and the public interest in main-
taining the integrity of the procurement system.’’ The
court made no specific finding as to the applicability of 32
C.F.R. § 1-113.2 and Part 141 to sustaining engineering con-
tracts, but appears to have assumed if an actual conflict of
interest was shown, or if it could be proven that Boeing
enjoyed a superior competitive position due to its sustain-
ing engineering contract, the resulting contract might be
voidable.

II.
STANDING

The district court found that Hayes had standing to chal-
lenge the award of contract 3366. We agree.

The Secretary of the Air Force is required to follow
procedures and practices prescribed by Congress in making
procurement contracts. Foremost among these statutes is
the Armed Services Procurement Act, 10 U.S.C. §§ 2301-
9314 and it was under the authority of this Act that the
contract in question was let. Contract 3366 was awarded
following ‘‘Requests for Proposals’’ which is a procure-
ment procedure available to the Secretary under 10 U.S.C.
§ 2304(a) (10) by which he had authority to by-pass formal
competitive bidding if it is impracticable to obtain compe-
tition.

Congressional limitations on discretionary awards of
procurement contracts have been held to be enacted for the
benefit of the public, not disappointed bidders, American
Smelting & Refining Co. v. United States, 259 U.S. 75, 42
S.Ct. 420, 66 L.Ed. 833 (1922); United States v. New York

® See also, the Federal Property and Administrative Services Act,
41 U.S.C. §§ 251-260 (1970) ; Armed Services Procurement Regu-
lations, 32 C.F.R. Parts 1-39 (1972); and Federal Procurement
Regulations, 41 C.F.R. § 1-1.000 et seq. (1972).

joy PETE MTT ITAL Te NE IT TE ENTE IM ST

13a

& Porto Rico S. 8S. Co., 239 U.S. 88, 36 S.Ct. 41, 60 L.Ed. 161
(1915), and accordingly under the ‘‘legal interest’’ theory
of standing, Tennessee Electric Power Co. v. Tennessee
Valley Authority, 306 U.S. 118, 59 S.Ct. 366, 83 L.Ed. 548
(1939) ; Alabama Power Co. v. Ickes, 302 U.S. 464, 58 S.Ct.
300, 82 L.Ed. 374 (1938) ; Massachusetts v. Mellon, 262 U.S.
447, 43 S.Ct. 597, 67 L.Ed. 1078 (1923), it was thought until
recently that no litigable rights are conferred on unsuccess-
ful bidders by the statutory standards. Thus they were
thought to lack standing to seek to remedy even a blatant
irregularity in the procurement procedures followed by a
Government agency. The leading case for this view is Per-
kins v. Lukens Steel Co., 310 U.S. 113, 60 S.Ct. 869, 84 L.Ed.
1108 (1940), and the Government urges us to follow it as
controlling precedent.

While Perkins has not been expressly overruled by the
Supreme Court, ' the ‘‘legal interest’’ test for standing has

10 See, however, Scanwell Laboratories, Inc. v. Shaffer, 137 U.S.
App.D.C. 371, 424 F.2d 859 (1970) where the court notes several
significant legislative enactments which arguably have the effect of
legislatively overruling Perkins. Foremost is the passage in 1946 of
the Administrative Procedure Act which provides that ‘‘[a] person
suffering legal wrong because of agency action, or adversely affect-
ed or aggrieved by agency action within the meaning of a relevant
statute, is entitled to judicial relief thereof.’’ The Supreme Court
has held that this passage was meant to broaden the concept of
standing in the area of judicial review of administrative actions,
Abbott Laboratories v. Gardner, 387 U.S. 136, 140, 87 S.Ct. 1507,
18 L.Ed.2d 681 (1967).

Until Scanwell federal courts have, with few exceptions, followed
the Perkins rationale that an unsuccessful bidder for a Govern-
ment contract has no standing to complain. Edelman vy. Federal
Housing Administration, 382 F.2d 594 (2d Cir. 1967); United
States v. Gray Line Water Tours of Charleston, 311 F.2d 779 (4th
Cir. 1962); Friend v. Lee, 95 U.S.App.D.C. 224, 221 F.2d 96
(1965).

Scanwell has not been expressly rejected by any Courts of
Appeals which have considered it, and two courts have expressly
adopted its reasoning. Merriam v. Kunzig, 476 F.2d 1233 (3d Cir.

l4a

largely been abandoned. See Sierra Club v. Morton, 405
U.S. 727, 92 S.Ct. 1361, 31 L.Ed.2d 636 (1972) ; Data Proc-
essing Service v. Camp, 397 U.S. 150, 90 S.Ct. 827, 25 L.Ed.
2d 184 (1970) ; Barlow v. Collins, 397 U.S. 159, 90 S.Ct. 832,
25 L.Ed.2d 192 (1970) ; Flast v. Cohen, 392 U.S. 83, 88 8.Ct.
1942, 20 L.Ed.2d 947 (1967). While the Supreme Court has
recognized that earlier cases did establish that standing
would be denied ‘‘unless the right invaded is a legal right,
—one of property, one arising out of contract, one protected
against tortious invasion, or one founded on a statute which
confers a privilege,’’ Tennessee Electric Power Co. v.
T.V.A., 306 U.S. at 137-38, 59 S.Ct. at 369, in Data Proces-
sing Service v. Camp, supra, the Court stated unambigu-
ously that ‘‘the ‘legal interest’ test goes to the merits. The
question of standing is different. It concerns, apart from
the ‘case’ or ‘controversy’ test, the question whether the
interest sought to be protected by the complainant is argu-
ably within the zone of interests to be protected or regu-
lated by the statute or constitutional guarantee in ques-
tion.’’

Where, as here, the plaintiff cannot rely on any specific
statute authorizing judicial review of administrative de-
cision-making, the question of standing hinges on whether
the party has alleged such a ‘‘personal stake in the outcome
of the controversy,’’ Baker v. Carr, 369 U.S. 186, 204, 82

1973) ; William F. Wilke, Inc. v. Department of the Army, 485
F.2d 180 (4th Cir. 1973). This Court in Allen M. Campbell Co. v.
Lloyd Wood Construction Co., 446 F.2d 261, 264 n. 5 (5th Cir.
1971) acknowledged that the question of standing for unsuccessful
bidders was viewed as an open one, and this Court has subsequently
referred approvingly to Scanwell, without adopting it. See Ray
Baillie Trash Hauling, Ine. v. Kleppe, 477 F.2d 696, 704 n. 8 (5th
Cir. 1973).

See generally, Pierson, Standing to Seek Judicial Review of
Government Contracts: Its Origins, Rationale and Effect on the
Procurement Process, 12 B.C.Ind. and Comm.L.Rev. 1 (1970) ;
Comment, Government Contract Bid Protest: Judicial Review and
the Role of the Court of Claims, 39 U.Chi.L.Rev. 814 (1972).

1lda

S.Ct. 691, 703, 7 L.Ed.2d 663 (1962) as to guarantee that
‘‘the dispute sought to be adjudicated will be presented in
an adversary context and in a form historically viewed as
capable of judicial resolution.’’ Flast v. Cohen, 392 U.S. at
101, 88 S.Ct. at 1953. As the Supreme Court noted in Sierra
Club v. Morton, ‘‘{w]here, however, Congress has author-
ized public officials to perform certain functions according
to law, and has provided by statute for judicial review of
those actions under certain circumstances, the inquiry as to
standing must begin with a determination of whether the
statute in question authorizes review at the behest of the
plaintiff.’’ 405 U.S. at 732, 92 S.Ct. at 1365. Recognizing
that ‘‘[c|learly the momentum of recent Supreme Court
decisions is in the direction of finding standing whenever
‘the plaintiff alleges that the challenged action has caused
him injury in fact, economic or otherwise’ and that ‘the in-
terest sought to be protected by the complainant is argu-
ably within a zone of interests to be protected or regulated
by the statute or constitutional guarantee in question.’ ’’
Allen Campbell Co. General Contractors, Ine. v. Lloyd
Wood Construction Co., 446 F.2d 261, 264 n. 5 (Sth Cir.
1971), we believe these are the two tests the plaintiff must
meet in order to establish standing to sue."

11 A third requirement is sometimes added that ‘‘there must be
no ‘clear and convincing’ indication of a legislative intent to with-
hold judicial review.’’ Ballerina Pen Co. v. Kunzig, 140 U.S.App.
D.C. 98, 433 F.2d 1204, 1207 (1970) ; see also Blackhawk Heating
and Plumbing Co. v. Driver, 140 U.S.App.D.C. 31, 433 F.2d 1137
(1970) ; Constructores Civiles De Centro America, S.A. (CON-
CICA) v. Hannah, 148 U.S.App.D.C. 159, 459 F.2d 1183 (1972).
As the D.C. Cireuit recognized in Ballerina Pen, supra, 433 F.2d
at 1207 n. 6, this reviewability test for standing has also been
treated as a separate and distinct issue, Data Processing Service,
Ine. v. Camp, 397 U.S. at 156, 90 S.Ct. 827; Abbott Laboratories
v. Gardner, 387 U.S. 136, 140, 87 S.Ct. 1507, 18 L.Ed.2d 681 (1967).
The distinction between the two methods of dealing with the ques-
tion of the scope of judicial review is murky and we choose to treat
the issues separately.

16a

A. Injury in Fact.

Unlike the type of delicate question which arises when a
plaintiff alleges an injury of a non-economic nature to in-
terests which are widely shared, see, e.g., Sierra Club v.
Morton, supra; United States v. Students Challenging
Regulatory Procedures (S.C.R.A.P.), 412 U.S. 669, 93 S.Ct.
2405, 37 L.Ed.2d 254 (1973), the economic injury suffered
by a losing bidder in seeking a government procurement
contract is manifest. No serious doubt exists that Hayes
International suffered economic loss by virtue of its inabil-
ity to obtain the contract at issue in this case.

B. The Zone of Interest.

Early cases which applied the ‘‘legal interest’’ test of
standing also made the general finding that government
procurement statutes were ‘‘not intended to be a bestowal
of litigable righis upon those desirous of selling to the Gov-
ernment...’’ Perkins v. Lukens Steel Co., 310 U.S. at 127,
60 S.Ct. at 877; American Smelting & Refining Co. v. United
States, supra; Goldberg v. Daniels, 231 U.S. 218, 34 S.Ct.
84; 58 L.Ed. 191 (1913) ; Edelman v. Federal Housing Ad-
ministration, 382 F.2d 594, 597 (2d Cir. 1967) ; United States
vy. Gray Line Water Tours of Charleston, 311 F.2d 779 ( 4th
Cir. 1962). These authorities do not, however, directly
answer the question whether the interests of a disappointed
bidder fall within the zone of interests arguably protected
by a statute or regulation, for even if the plaintiff is unable
to assert a violation of a legal right which the court may
remedy, ‘‘once review is properly invoked, that person may
argue the public interest in support of his claim that the
agency has failed to comply with its statutory mandate.’’
Sierra Club v. Morton, 405 U.S. at 737, 92 S.Ct. at 1367. It
was indeed largely on this premise that a disappointed
bidder is uniquely suited to assert a public interest in the
Government’s compliance with relevant statutes regulating
procurement that led the D.C. Circuit to hold a losing bid-

l7a

der has standing to contest an arguably illegal Government
contract—despite the fact it may not necessarily be able to
assert a ‘‘legal right’’ to the contract. Scanwell Labora-
tories, Inc. v. Shaffer, 137 U.S.App.D.C, 371, 424 F.2d 859
(1970).

Here we believe the interests of competitors are at least
arguably within the zone of interests protected by the De-
partment of Defense regulations or organizational conflicts
of interest. Those regulations, under which this suit was
brought, 32 C.F.R. § 1-113.2 and Part 141 (1971), set out
rules which are intended to achieve two different but related
goals: avoiding those conflicts of interest which bias a con-
tractor’s judgment, and avoiding situations where one con-
tractor has an unfair competitive advantage over another.
It seems probable that this latter goal is at least in part
designed to protect the interests of competitors who are
unable to obtain government contracts due to the superior
competitive position of the successful bidder, whose com-
petitive advantage is the result of its prior confidential
relationship with the Government.

References to the goal of avoiding unfair competitive ad-
vantages for a contractor in a privileged position with the
Government frequently occur in the legislative reports and
hearings preceding drafting of the organizational conflicts
of interest procurement regulation. See, e.g., Organization
and Management of Missile Programs, H.R.Rep. No. 112,
86th Cong., Ist Sess., 88, 92, 95 (1959); House Comm. on
Gov’t Operations Avoiding Conflicts of Interests in Defense
Contracting and Employment, H.R.Rep. No. 917, 88th
Cong., Ist Sess., 4, 52 (1963). While these references draw
no formal distinction between the Government’s interest in
free competition, and the interest of a competitor—these
cited passages do express a broad concern that unfair com-
petition may result, and the regulation subsequently drafted
seems sufficiently broad to incorporate both the Govern-
ment’s interest in lower prices and higher quality through

18a

free competition, as well as the industry’s interest in maxi-
mizing the opportunity for each competitor to bid on an
equal footing.

C. Effect on Future Procurement.

While the Government urges this Court to dismiss the
suit on authority of Perkins v. Lukens Steel, supra, and thus
affirm the requirement that a formal legal interest must be
found before a party has standing to challenge the grant of
a Government contract, the Government also proposed
larger grounds for refusing to review procurement decisions
of the sort involved in this case.’ These concerns are both
serious and important, and we do not feel we can ignore
them. While we ultimately deny the relief the plaintiff re-
quests, we do not do so on the basis that Hayes lacks stand-
ing to raise the issues presented, and we recognize we may
thus occasion other challenges to Government procurement
which necessarily will have effects on the manner in which
the Government conducts military procurement.

In its seminal opinion of Scanwell Laboratories, Ine. v.
Shaffer, supra, the D.C. Circuit Court took note that there

12The Supreme Court in Perkins expressly referred to the
possible effects on the procurement process as contributing to its
holding that an unsuccessful bidder lacked standing to sue.

‘Courts should not, where Congress has not done so, subject
purchasing agencies . . . to the delays necessarily incident to
judicial scrutiny at the instance of potential sellers .... A
like restraint applied to purchasing by private business would
be widely condemned as an intolerable business handicap. It
is, as both Congress and the courts have always recognized,
essential to the even and expeditious functioning of Govern-
ment that the administration of the purchasing machinery be
unhampered.’’ 310 U.S. at 130, 60 S.Ct. at 878.

See also, Lind v. Staats, 289 F.Supp. 182, 186 (N.D.Cal. 1968)
for a strong statement of the possible harm resulting from interfer-
ence with essential Government procurement. See also discussion
M. Steinthal and Co. v. Seamans, 147 U.S.App.D.C. 221, 455 F.2d
1289, 1300 (1971).

LL OL LTE NEL LONI SE OTR IE PPE AGE A RA NEE SEEN = i.

19a

were justifiable concerns that judicial review of procure-
ment decisions may have a disastrous effect on the efficient
operation of Government procurement. In matters such
as the one before us in this case, where the procurement de-
cision touches on weapons systems which may have a vital
impact on national defense, the courts must be wary of in-
truding into areas where they have neither special compe-
tence nor the ability to act expeditiously.* Despite these
concerns, we feel we must follow the line of authority which
began with Scanwell.

There is now a substantial body of case law in the D.C.
Circuit which by now almost routinely applies Scanwell
and grants judicial review of procurement decisions. See
e.g., P.A.M. News Corp. v. Hardin, 142 U.S.App.D.C. 227,
440 F.2d 255 (1971); National Automatic Laundry and
Cleaning Council v. Shultz, 143 U.S.App.D.C. 274, 443 F.2d
689 (1971) ; Blackhawk Heating and Plumbing Co. v. Driver,
140 U.S.App. D.C. 31, 433 F.2d 1137 (1970); Ballerina Pen
Co. v. Kunzig, 140 U.S.App.D.C. 98, 433 F.2d 1204 (1970),
cert denied 401 U.S. 950, 91 S.Ct. 1186, 28 L.Ed.2d 234

13 Our decision in Allen M. Campbell Co. v. Lloyd Wood Con-
struction Co., 446 F.2d 261 (5th Cir. 1971) demonstrates the type
of inefficiency which may be occasioned by judicial review of pro-
curement decisions. In that case the district court originally
entered an injunction restraining the Air Force from entering into
a contract for the construction of housing when the plaintiff con-
tended that the bidder to whom the contract was to be awarded was
ineligible because it was not a ‘‘small business’’ within the mean-
ing of the relevant statute. 318 F.Supp. 1167 (N.D.Ala. 1970). The
Air Force because it determined that the housing was urgently
needed, complied with the injunction and awarded the contract to
the plaintiff. On appeal, this Court determined that the Air Force’s
original determination was reasonable, and that the injunction had
been erroneously granted. Subsequently, the Court of Claims
ordered the Government to pay damages to the original successful
bidder flowing from the Air Force’s obedience to the district court’s
order. 467 F.2d 931, 199 Ct.Cl. 515 (1972). As a consequence of
this litigation, the Government was in effect required to pay two
different bidders for the same work.

20a

(1971) ; M. Steinthal and Co. v. Seamans, 147 U.S.App.D.C.
221, 455 F.2d 1289 (1971); Wheelabrator Corp. v. Chafee,
147 U.S.App.D.C. 238, 455 F.2d 1306 (1971); Kentron
Hawaii, Ltd. v. Warner 156 U.S.App.D.C. 274, 480 F.2d
1166 (1973). As that Court observed in M. Steinthal and
Co., supra, the administration of suits involving military
procurement has not been without its problems—frivolous
suits are occasionally filed, and not infrequently the delay
occasioned by judicial review has a harmful effect on the
smooth and efficient operation of military procurement.
Procurement decisions are frequently complex and involve
factual issues courts are ill-equipped to settle. Obviously
many procurement decisions involve delicate questions of
policy which are better left to the expertise of an executive
agency to answer.

At least in part the problem has been to develop proper
standards in determining when a discretionary injunction
should issue. Many different factors are necessarily taken
into account in making a decision of this sort, and the
experience in the D.C. Cireuit has shown that the grant of
an injunction which has the effect of delaying possibly vital
procurement may have grave effects on the national inter-
est. Among the various factors which have been expressly
recognized as proper to take into account in determining
whether an injunction should issue are: (1) the importance
to national defense of the item to be procured;* (2) the
availability of alternative remedies, either in the Court of
Claims “ or a bid protest claim to the General Accounting

14 Ray Baillie Trash Hauling, Inc. v. Kleppe, 477 F.2d 696 (5th
Cir. 1973).

15 VW. Steinthal and Co., supra, 455 F.2d at 1302. The damages
available in the Court of Claims are normally limited to those costs
associated with preparation of the losing bid. See Keco Industries,
Ine. v. United States, 428 F.2d 1233, 192 Ct.Cl. 773 (1970) ; Robert
F. Simmons and Associates v. United States, 360 F.2d 962, 175 Ct.
Cl. 510 (1966) ; Heyer Products Co. v. United States, 140 F.Supp.
409, 135 Ct.Cl. 63 (1956) and 177 F.Supp. 251, 147 Ct.Cl. 256
(1959).

ie. .

OLMIS A IO TOTES miamssme comes seo b

2la

Office ;° and (3) the substantial likelihood that statutory
standards were in fact violated.” Further the plaintiff has
been held to bear a heavy burden of proving that a pro-
curement officer’s decision was genuinely arbitrary and un-
reasonable.’ We agree that there is a ‘‘strong public inter-
est in avoiding disruptions in procurement, and for with-
holding judicial interjection unless it clearly appears that
the case calls for an assertion of an overriding public in-
terest [at] ‘in having the agencies follow the regulations
which control government contracting.’’’ M. Steinthal
and Co., supra, 455 F.2d at 1300. At the same time, we do
not believe that denying review altogether is the proper
way to temper judicial discretion in granting injunctions
which may have harmful effects on military and Govern-
ment procurement.

16 Wheelabrator Corp. v. Chafee, 147 U.S.App.D.C. 238, 455 F.2d
1306, 1313 (1971). See 4 C.F.R. Part 20 for the bid protest pro-
cedures issued by the Comptroller General, and see generally,
Cibinie and Lasken, The Comptroller General and Government Con-
tracts, 38 Geo.Was.L.Rev. 349 (1970).

T As the D.C. Circuit specifically noted in M. Steinthal and Co.,
supra, 495 F.2d at 1301, the federal courts must pay particular
respect to what might be fairly called the ‘‘common law of govern-
ment procurement’’—the body of rulings determinations emanating
from executive officials and the uniquely situated appeals determi-
nations of the Comptroller General and quasi-judicial boards such
as the boards of contract appeals in many of the various procure-
ment agencies. Thus the deference normally owed an agency’s
interpretation of its own authorizing statutes and regulations may
in some cases induce a federal court in its sound equity diseretion
to withhold issuance of the preliminary injunction if the ageney ean
demonstrate the likelihood that its procurement decisions followed
accepted agency practice.

8 Kentron Hawaii, Ltd. v. Warner, 156 U.S.App.D.C. 274, 480
F.2d 1166 (1973) ; M. Steinthal and Co., supra, 455 F.2d at 1301;
Continental Business Enterprises, Ine. v. United States, 452 F.2d
1016, 196 Ct.Cl. 627 (1971) ; Keco Industries, Inc., supra, 428 F.2d
at 1240.

22a

III.
REVIEWABILITY

The Administrative Procedure Act, 5 U.S.C. § 701(a)
provides that the provisions of the Act authorizing judicial
review apply ‘‘except to the extent that—(1) statutes pre-
clude judicial review; or (2) agency action is committed to
agency discretion by law.’? The Supreme Court has held
that there is virtually a presumption in favor of judicial re-
view, Abbott Laboratories v. Gardner, 387 U.S. 136, 140, 37
S.Ct. 1507, 18 L.Ed.2d 681 (1967) unless a contrary pur-
pose is fairly discernible in the statutory scheme. Data
Processing Service v. Camp, 397 U.S. 150, 157, 90 S.Ct. 827,
25 L.Ed.2d 184 (1970). Agency action is normally found to
be non-reviewable ‘‘only upon a showing of ‘clear and con-
vincing evidence’ of a contrary legislative intent.’’ Abbott
Laboratories v. Gardner, 387 U.S. at 141, 87 S.Ct. at 1511.

32 C.F.R. § 1-113.2 and Part 141 do not expressly pre-
clude judicial review, but neither do they mandate it.
Clearly the absence of statutory language expressly author-
izing judicial review is insufficient to offset the presumption
that administrative action is reviewable. ‘‘Indeed, judicial
review of such administrative action is the rule, and nonre-
viewability an exception which must be demonstrated.’’
Barlow v. Collins, 397 U.S. 159, 166, 90 S.Ct. 832, 838, 25
L.Ed.2d 192 (1970). However, ‘‘[a] clear command of
the statute will preclude review; and such a command of the
statute may be inferred from its purpose.’’ Id. at 167, 90
S.Ct. at 838.

The Government points to those provisions of the regula-
tions which provide that ‘‘[a]ny of the prohibitions
imposed by these rules may be waived by an Assistant
Secretary of a military department or the Director of a
defense agency if he determines that a failure to waive the
prohibition will be prejudicial to the best interests of the
Government,’’ 32 C.F.R. Part 141 (1971) as well as the
repeated statement that ‘‘[a]ll prospective contractors will

PB RIA ROLLS OI ILL T LOM LEE LD LOI LI SOLE IE *

23a

be advised of the applicability of the rules by a notice in
solicitations and by a clause in resulting contracts,’’ Id.,
and ‘‘[t]he contracting officer shall not impose restrictions
under the Appendix in follow-on procurements on any
prospective contractor in the absence of a specific contrac-
tual agreement with that contractor,’’ 32 C.F.R. § 1-113.2(c)
and argue that taken together they amount to such a ‘‘clear
command’’ that the regulations are meant to be applied only
at the discretion of the agency.

That part of Appendix G which provides for ‘‘Review
and Waiver’’ seems to us to grant substantial discretion
to procurement officers. Indeed, Hayes concedes that the
Air Force could have made the decision to waive the appli-
cation of the Rules on Avoidance of Organizational Con-
flicts of Interests. Implicitly the plaintiff also concedes
that were such a decision made, it likely would be unre-
viewable as it would be one of those ‘‘rare instances where
‘statutes are drawn in such broad terms that in a given
case there is no law to apply.’’’ Citizens to Preserve
Overton Park v. Volpe, 401 U.S. 402, 410, 91 S.Ct. 814, 821,
28 L.Ed.2d 136 (1971). We do not pass on that question,
however, as such a waiver decision was not made in this
ease. Rather, the Air Force has determined that the Rules
on Avoidance of Organizational Conflicts of Interest are
never applicable to the type of engineering contracts which
Boeing held prior to the grant of IRAN/Modification con-
tract 3366. In our view, this construction of the regulations
is a decision other than a specific decision to waive the
application of the rules in a particular instance, having
made the decision that a failure to do so would be ‘‘preju-
dicial to the best interests of the Government.’’

Such a construction of the regulations ‘‘does not signifi-
cantly engage the agency’s expertise,’’ Barlow v. Collins,
397 U.S. at 166, 90 S.Ct. at 837, for ‘‘Courts are as expert
as administrators in matters of statutory construction.’
Kast Oakland-Fruitvale Planning Council v. Rumsfeld, 471

24a

F.2d 524, 529 (9th Cir. 1972). See Barlow v. Collins, 397
U.S. at 166, 90 S.Ct. 832.”

Thus the issue in this case comes down to the relatively
straightforward one of the extent to which the Department
of Defense rules on avoidance of organizational conflicts of
interest were meant to apply to the type of engineering con-
tracts which Boeing held for the KC-135. The decision that
Boeing’s sustaining engineering and related support serv-
ices contracts did not come within the purview of the rules
was not made on the basis of the ‘‘best interests of the
Government,’”’ rather the record shows it was made on the
basis of a construction of the language of the regulations,
and the legislative history surrounding the drafting of the
rules. Such matters are eminently fit for judicial review,
and while naturally an agency’s interpretation of its own
regulations is subject to substantial deference,” this does
not amount to unreviewable discretion within the meaning
of §701(a) of the Administrative Procedure Act.”

19 An analogous question would be the extent to which an agency
has discretion to construe its own authorizing legislation to deter-
mine the extent to which its decisions are to be unreviewable. In
such eases, normally the initial inquiry as to the construction of an
agency’s authorizing legislation is held to be a matter proper for
judicial review, even if ultimately the decision is that the agency
has unreviewable discretion under that legislation. See East Oak-
jand-Fruitvale Planning Council v. Rumsfeld, supra; Fletcher v.
Housing Authority of Louisville, 491 F.2d 793 (6th Cir. 1974).
Similarly, ‘‘ ‘[w]here the only or principal dispute relates to the
meaning of the statutory term’. . . [the controversy] presents
issues on which courts, and not [administrators], are relatively
more expert.’’ Barlow v. Collins, 397 U.S. at 90 166 S.Ct. at 837,
citing Hardin v. Kentucky Utilities Co., 390 U.S. 1, 14, 88 S.Ct.
651, 19 L.Ed.2d 787 (Harlan, J., dissenting).

20 See generally, 4 K. C. Davis, Administrative Law Treatise,
§ 30.12 (1958).

21'The Government and Boeing argue that by the terms of 32
C.F.R. § 1-113.2 and Part 141, the failure of the government to
include provisions in Boeing’s sustaining engineering contracts
barring future bidding on IRAN/Modification contracts should

8 PERLE LTE GIG pL SEILER EL ISAT ER ee i hb

25a

IV.

APPLICABILITY OF THE DEPARTMENT OF DE-

FENSE RULES ON AVOIDANCE OF ORGANIZATION-

AL CONFLICTS OF INTERESTS TO ENGINEERING
SUPPORT CONTRACTS

As the Government has had to rely increasingly on the
use of private contractors to perform tasks which might
previously have been performed by Government employees,
the problem of reconciling the private interests of independ-
ent contractors with the public mission they are called upon
to perform has resulted in substantial legislative concern
about conflicts of interest. The problem has been particu-
larly acute concerning use of individual Government em-
ployees who have some interest in private concerns, and
both the legislation and the literature concerning this ques-
tion of so-called ‘‘individual conflicts of interest’’ have
been extensive.”” Such ‘‘individual conflicts of interest’’

preclude retroactive application of the Rules on Organizational
Conflicts of Interest. We note without passing on the question
that other procurement regulations have been held to be self-
enforcing despite the failure to include them in specific contracts,
see, e.g., G. L. Christian and Associates v. United States, 312 F.2d
418, 160 Ct.Cl. 1 (1963). Further the Comptroller General has
recently decided that the failure to include such a ban in a prior
contract need not bar an application of restrictions similar to
those of 32 C.F.R. Part 141, if such a restriction is made con-
sistent with 10 U.S.C. §2304(g¢) which requires solicitation of
proposals ‘‘from the maximum number of qualified sources consist-
ent with the nature and requirements of the supplies or services
to be procured.’’ Decision of the Comptroller General, B-181448
of October 15, 1974. See OGC Newsletter, Office of the General
Counsel, Dept. of the Navy, Vol. 21, No. 4 (12/16/74).

22 See 18 U.S.C. §§ 201-219 (1964). See generally, Manning,
Federal Conflict of Interest Law (1964) ; Perkins, The New Federal
Conflict of Interests Law, 76 Harv.L.Rev. 1113 (1963) ; Petrowitz,
Conflict of Interests in Federal Procurement, 29 Law and Contemp.
Prob. 196 (1964) ; Pasley, Individual Conflicts of Interest (Brief-
ing Paper No. 64-4, Federal Publications, Inc.) (1964).

26a

have been defined as ‘‘the clash, or appearance of a clash,
between a Government official’s interest in performing his
official duties and his interests in his private—and espe-
cially his private economic—affairs.’’ Association of the
Bar of the City of New York, Conflict of Interests in Fed-
eral Service, 3 (1960). Here the statutory restrictions
are relatively clear, and well understood. The same cannot
be said of ‘‘organizational conflicts of interest’? which
have been described by one of the leading scholars in the
field as a ‘‘more mysterious, arcane subject, on which much
less has been published and about which very little that
is definitive can yet be said.’’ Pasley, Organizational Con-
flicts of Interests in Government Contracts, 1967 Wis.L.
Rev. 5, 6.

‘Organizational conflicts of interest,’? unlike ones con-
cerning individual employees, normally do not arise in most
aspects of public service. Rather they have been described
as ‘‘essentially creatures of federal government contract
law and policy, more specifically of research and develop-
ment contracting and of complex space age technology.’’
Pasley, Id.

32 C.F.R. §1-113.2 and Part 141 were drafted to deal
with what a series of Congressional hearings and reports
identified as the continuing problem of organizational con-
flicts of interest in aerospace procurement.” At trial the

23 See for his account of the development of the D.O.D. regula-
tions, Pasley, Organizational Conflicts of Interest in Government
Contracts, 1967 Wis.L.Rev. 5, 6 et seq. See also House Committee
on Government Operations, Organization and Management of
Missile Programs, H.R.Rep.No.1121, 86th Cong., Ist Sess. (1959) ;
House Committee on Government Operations, Air Force Ballistic
Management (Formation of Aerospace Corporation), H.R.Rep.No.
324, 87th Cong., 1st Sess. (1961); U.S. Bureau of the Budget, Re-
port to the President on Government Contracting for Research and
Development, S.Doc.No.94, 87th Cong., 2nd Sess. (1962); House
Committee on Government Operations, Avoiding Conflicts of In-
terest in Defense Contracting and Employment, H.R.Rep.No.917,

27a

Government introduced witnesses who either participated
in the drafting of the regulations in question, or who sub-
sequently were responsible for applying them in military
procurement contracts, who testified that the rules were
intended to apply to situations where a highly specialized
contractor engaged in what was called ‘‘systems engineer-
ing’’ and ‘‘technical direction.’’** ‘‘Systems engineer-
ing’’ is defined by 32 C.F.R. Part 141 to include ‘‘a com-
bination of substantially all the following activities: de-
termination of specifications, identification and solution of
interfaces between parts of the system, development of
test requirements or plans and evaluation of test data,
and supervision of design work.’’ The term ‘‘technical
direction’’ is similarly defined to include ‘‘a combination
of substantially all the following activities: preparation of
work statements for contractors, determination of para-
maters, direction of contractors’ operations, and resolu-
tion of technical controversies.’’ While some of these
technical terms seem so conceptually broad as to include
some, although certainly not all, of Boeing’s responsibilities
under its sustaining engineering contracts, Government
witnesses at trial testified that the type of post-production
engineering which Boeing was expected to perform under

88th Cong., Ist Sess. (1963); Hearings Before the Sub-Committee
of the House Committee on Government Operations, Organization
and Management of Missile Programs, 86th Cong., 2nd_ Sess.
(1960) ; Hearings Before a Sub-Committee of the House Commit-
tee on Government Operations, Systems Development and Man-
agement, 85th Cong., Ist Sess. (1963).

*4 Among the other equally ambiguous generic terms used to
describe similar functions are: ‘‘systems analysis and engineering
and technical monitoring and direction,’’ Staff of Sub-Committee
for Special Investigations of the House Committee on Armed
Services, 89th Cong., Ist Sess., The Aero Space Corporation 7
(Comm.Print. 1965) or, more generally, ‘‘ Planning, technical, ana-
lytical, or other consulting services.’’ Proposed Atomic Energy
Commission, ‘Statement of General Policy for the Avoidance of
Organizational Conflicts of Interest,’’ 31 F.R. 2699, 2700 (1966).

28a

its sustaining engineering contracts was qualitatively dif-
ferent from the kind of engineering effort described by the
terms ‘‘systems engineering’’ and ‘*technical direction.”’
Typically this latter type of engineering was said to involve
development of new systems, and the coordination of the
contributions of a number of sub-contractors in an effort
to speed research, development and production.

The Government relies not only upon what individuals
who participated in the drafting of the regulations sug-
gested was the intent behind the language used within the
regulation, but also refers to the specific instances of sys-
tems engineering and technical direction which had been
identified by Congressional committees investigating
organizational conflicts of interest as creating a problem
which required a solution.”

Expert Government witnesses testified that there were
fundamental differences between the type of engineering
responsibilities involved in developing a new weapon sys-
tem, and that which are involved in performing mainten-
ance engineering on an existing system. These witnesses

25 The prototype of such a contractor was the Ramo-Wooldridge
Corporation, later known as the Thompson-Ramo- Wooldridge Cor-
poration, later responsible for the separate incorporation of Space
Technology Laboratories, a wholly-owned subsidiary of Thompson-
Ramo. The history of these corporations, and their role in develop-
ing the ballistic missile system for the Air Force are extensively
reported in two House of Representative’s reports, H.R.Rep.No.
1121, and H.R.Rep.No.324, supra, note 23. Ramo-Wooldridge
was responsible for the coordination of sub-contracting in the de-
velopment of the ballistic missile system—and as such had enor-
mous influence in making decisions about what equipment and
services should be acquired by the Government. It seems plain
to us that if what Ramo-Wooldridge was performing in the late
‘50s is what the terms ‘‘systems engineering’’ and ‘‘technical
direction’? were meant to describe, then Boeing’s sustaining engi-
neering contracts bear no meaningful relationship to the type of
engineering responsibilities vested by the Air Force in the Ramo-
Wooldridge Corporation.

LORE RPSL IB NOONE NTS, 8 URN Lop RIC Noe IM ETS \.

29a

testified that contracts led by the Logistics Command
simply were not ‘‘system engineering’’ or ‘‘technical direc-
tion’’ contracts within the meaning of the regulations.
Sustaining engineering was identified as resembling ‘‘fix-
it’’ engineering although the precise conceptual differences
between such ‘‘fix-it’’ engineering and the ‘‘very sophisti-
cated type of technical management’’ which was said to be
involved in systems engineering and technical direction
were left largely unarticulated.

The plaintiff produced no evidence as to the intent of
the draftsman of 32 C.F.R. § 1-113.2 and Part 141, nor any
evidence as to how the terms ‘‘system engineering’’ and
‘*technical direction’’ are viewed by specialists in military
procurement. Rather Hayes simply says that to read the
language of the regulation is enough, that the words are
so clear no extrinsic evidence is required. However, it
only requires a single attempt to read and understand the
cabalistic jargon of the regulations to conclude that the
words cannot stand alone.

We do not feel that the plaintiff has offset the weight
we attach to the administrative interpretation of the regu-
lations and to the intent attributed to the draftsman of the
regulation by participants in the drafting process. One
such participant in the drafting process, then a special as-
sistant to the Secretary of Defense, has described the pro-
blems the regulations were designed to solve. Yarmolin-
sky, Organizational Conflicts of Interest, 24 Fed.B.J. 309
(1964). He describes the development of ‘‘systems en-
gineering and technical direction’’ as responding to a need
which arose ‘‘because weapons systems had become so
complex that the job of fitting together separate systems,
sub-systems, and sub-sub-systems, turned out to be at least
as important as the job of producing component elements.
Contractors were needed to perform what came to be called
systems engineering and technical direction, which amount-
ed to giving the contractor a very large say in what the
ultimate customer—the Government— was going to buy.’’

* eee ae Re

30a

We are thus unable to read 32 C.F.R. §1-113.2 and Part
141 so broadly as to encompass all engineering tasks as-
signed by contract by the military. Such a reading is in-
consistent with the background to the drafting of the re-
gulation, and has never been the interpretation placed upon
it by the agencies responsible for military procurement.
In our view, the limited reading placed on the regulations
by the various procurement agencies is consistent with the
legislative materials which prompted the drafting of the
regulation originally, and with the attempted solution of
the specific problem those legislative hearings and reports
documented.

We thus conclude that the Air Force’s administrative
interpretation of 32 C.F.R. $1-113.2 and Part 141 is a per-
missible interpretation, and we do not disturb it.”

Accordingly, we affirm the judgment of the trial court.

26 The plaintiff proposes an alternative basis on which it seeks to
have contract 3366 voided. Relying on what it identifies as the
rationale of United States v. Mississippi Valley Generating Co., 364
U.S. 520, 81 S.Ct. 294, 5 L.Ed.2d 268 (1961), the plaintiff proposes
that a general publie policy against conflicts of interests is suffi-
ciently strong to justify voiding a contract which arguably is
tainted by such a conflict of interest. We feel we must decline the
invitation to develop such a novel ‘‘federal common-law of Gov-
ernment procurement,’’ premised upon what a court can be per-
suaded is desirable procurement policy.

No authority is cited for this dramatie use of federal equity
power save the Mississippi Valley Generating case, and it is ad-
mittedly distinguishable on the grounds that it involved the vio-
lation of a penal conflict of interest statute, and thus did not
require a decison to void a Government contract premised solely
on the court’s intuitive sense of what is desirable public policy.
The penal statute in question, 18 U.S.C. § 434 was said to be given
its ‘‘fair meaning in accord with the evident intent of Congress,”’
364 U.S. at 550, 81 S.Ct. at 309, and the Supreme Court by its
own terms did nothing more than construe that intent. We find
nothing in the case which authorizes so broad a use of discretionary
power as to justify creating new and novel limitations on military
procurement.

|

VESPA TE LPT FILO BE LS

3la
APPENDIX B

IN THE UNITED STATES DISTRICT COURT FOR THE NORTHERN
DISTRICT OF ALABAMA, SOUTHERN DIVISION

Crviz Action No. 71-831-A

Hayes INTERNATIONAL Corporation, Plaintiff
v.

Dr. Rosert C. Szamans, Jr., Secretary of the
Air Force, Defendant

Tue Bortne Company, a Corporation, Intervenor

Order of Dismissal

In conformity with the Findings of Fact and Conclusions
of Law entered contemporaneously herewith,

It is Orperep, Apsupcep and Drcreep by the Court that
plaintiff is not entitled to the relief for which it prays;
that this action be and the same is hereby dismissed; and
that the costs of court incurred herein be and the same
are hereby taxed against plaintiff.

Done this 30th day of April, 1973.

/s/ Seymour H. Lynne
Senior Judge

32a

IN THE UNITED STATES DISTRICT COURT FOR THE NORTHERN
DISTRICT OF ALABAMA, SOUTHERN DIVISION

Civiz Action No. 71-831-S

Haves InTeRNATIONAL Corporation, Plaintiff
v.

Dr. Rosert C. Szamans, Jr., Secretary of the
Air Force, Defendant

Tue Borrnca Company, a Corporation, Intervemor

This cause, coming on to be heard, was submitted upon
the alternative prayers of plaintiff for a permanent in-
junction or a declaratory judgment upon the pleadings and
the proof. After full consideration thereof, aided by the
memoranda and oral arguments of able counsel, the Court
proceeds to make and enter the following findings of fact
and conclusions of law:

FINDINGS OF FACT

(1) On or about March 29, 1971, defendant, acting
through the United States Department of the Air Force,
Air Force Logistics Command, Headquarters Oklahoma
City Air Materiel Area, Tinker Air Force Base, Okla-
homa, 73145, issued Request for Proposals (RFP) No.
F34601-71-R-1488 for the procurement of certain services
to perform the ‘‘inspection and repair as necessary’’
(IRAN), modifications (otherwise known as Technical Or-
der compliance) and other related services on the world-
wide Air Force fleet of KC-135 aerial refueling tankers.
The RFP was issued pursuant to the authority delegated
to the defendant in 10 U.S.C. § 2304(a)(10) (1970), and
requested proposals to be submitted by offerors on or be-
fore 4:30 p.m., Central Standard Time, May 17, 1971.
The date for receipt of proposals was later extended to
June 4, 1971.

33a

(2) Pursuant to the Request for Proposals, on June 23,
1971, defendant awarded Contract No. F34601-71-C-3366
to The Boeing Company (hereinafter ‘‘Boeing’’), effec-
tive July 2, 1971, in the amount of $12,294,894.16 for the
first year of performance. The provisions of the RFP
and of the resulting contract anticipated delivery by the
Air Force of KC-135 aircraft to Boeing for IRAN/Modi-
fication work beginning on or about October 12, 1971.

(3) At the time of the solicitation of the Request for
Proposals, plaintiff, Hayes International Corporation, was
performing similar IRAN/Modification services for the
Air Force on the KC-135 fleet under Contract No.
F'34601-68-C-3607, and had been doing so since March, 1968.

(4) Such contract contemplated a five-year period of
substantially similar work requirements based upon annual
options available to the Government.

(5) Plaintiff initiated an inquiry to the Air Force be-
cause of the inconsistency between the face amount of the
contract and a newspaper report of the potential value
of the contract to Boeing. The purpose of the inquiry
was to ascertain the nature and extent of other contracts
prevailing between Boeing and the Air Force which also
concerned the KC-135 fleet. On the basis of a review of
such other contracts supplied to plaintiff by the Air Force
pursuant to the Freedom of Information Act, plaintiff
concluded that:

(a) Boeing held a privileged relationship with the
Air Force as the only contractor providing engineering
services and recommendations on maintenance require-
ments and modifications which should be performed
on KC-135 aircraft;

(b) that privileged relationship was of such a nature
that Boeing alone, among the offerors for Contract
No. F34601-71-C-3366, had superior knowledge and
information concerning pending modifications to the

34a

KC-135 fleet that would result in work requirement
changes and additions to IRAN/Modification Contract
No. F34601-71-C-3366; and, therefore,

(c) the competition for Contract No. F34601-71-C-
3366 was unfair and Boeing had an unfair competitive
advantage over all other offerors;

(d) a conflict of interest existed between Boeing’s
performance of sustaining engineering services for the
Air Force on the KC-135 fleet and the performance of
IRAN/Modification services under Contract No.
F34601-71-C-3366 ; and

(e) Boeing’s judgments and engineering decisions
made under its KC-135 service contracts with the Air
Force would be biased in favor of maintenance require-
ments and modifications which Boeing would perform
and receive the economic benefit of as the IRAN /Modi-
fication contractor under Contract No. F34601-71-C-
3366.

(6) On July 15, 1971, plaintiff submitted various ques-
tions to the Air Force concerning the bidding and award
of Contract No. F34601-71-C-3366, and particularly con-
cerning the unfair competitive advantage which Boeing
enjoyed in the alleged ‘‘Competition’’ for the contract.
Additionally, plaintiff pursued its administrative remedies,
to the extent they existed, by consulting with and bring-
ing the questions of unfair competition, conflict of interest,
and bias to the personal attention of, among others, the
then Assistant Secretary of the Air Force, Philip N.
Whittaker. All such inquiries were to no avail.

(7) At all times pertinent to this litigation, specifically
prior to, at the time of, and after the award of Contract
No. F34601-71-C-3366 to Boeing for IRAN/Modification
services on the KC-135 fleet, Boeing and the Air Force
were parties to a_ series of contracts whereunder Boeing
furnished the Air Force sustaining engineering and re-

PARE LEP ELE YAEL CLIO POLLEN BELO EIDE LY LID ME EERE RE LINES OIE OES E EE NL HORI MD. AP

™

35a

lated support services on the worldwide Air Force KO-135
fleet. Pursuant to these contracts, Boeing advised and
recommended to the Air Force what specific maintenance
and modification requirements were to be performed on
the entire Air Force fleet of more than 700 KC-135 air-
craft. Boeing continues to operate under such contracts
and to provide these services for the Air Force on the
KC-135 fleet at this time. The contracts include Nos.
F'34601-71-C-0799; F34601-72-C-1782; F34601-72-C-2039;
¥34601-71-D-2291; and ¥34601-71-A-1408, all as amended,
modified, superseded, or replaced by substantially similar
contracts.

(8) All of the KC-135 sustaining engineering and re-
lated support services contracts referenced in the prior
numbered finding were awarded to Boeing by the Air
Force on a ‘‘sole source’’ basis without competition or
open bidding.

(9) During the early part of the 1950’s, Boeing devel-
oped a prototype jet transport aircraft, which was pri-
vately financed, and subsequently developed a tanker air-
craft for use by the Air Force from this prototype. The
Air Force has procured 732 of these aircraft from Boeing,
having an inventory value of $1,692,134,780.00. This air-
craft, known as the KC-135A, has the mission of provid-
ing worldwide aerial refueling support for all ‘First
Line’’ bombers, fighters, tactical and special mission air-
craft (reconnaissance and weather configuration).

(10) Pursuant to the KC-135 sustaining engineering and
related support services contracts, Boeing functions as the
engineering arm of the Air Force for the KC-135 fleet.
Because of the information provided to Boeing by the Air
Force to perform under such contracts, Boeing had access
to vital information concerning the KC-135 fleet.

(11) As with all its aircraft, the Air Force has the
responsibility of assuring that the KC-135A aircraft are

36a

properly maintained and ready to fulfill critical National
Defense mission requirements. This maintenance work
may be done in Air Force facilities or it may be contracted
out to private contractors. During the first ten years of
operation, modification and maintenance work on the KC-
135A aircraft was performed primarily in Air Force facili-
ties. By December of 1967, other Air Force work had led
the Air Force to conclude that the modification and main-
tenance work on the KC-135A aircraft should be con-
tracted out. In January, 1968, proposals were received
from five contractors including plaintiff and Boeing.

(12) The 1968 procurement of maintenance and modifica-
tion work on the KC-135A aircraft, known as TRAN/Modi-
fication work was contracted to plaintiff, Hayes Interna-
tional Corporation, since it was determined to be the
lowest, responsive proposer on the 1968 procurement. This
contract was extended through exercise of options through
the first 90 days of fiscal year 1972, and was numbered
F34601-68-C-3607.

(13) Following essentially the same procedures as in
1968, the Air Force again requested proposals for a new
modification and maintenance work contract on the
KC-135A aircraft by Request for Proposal issued March
29, 1971. In response to this RFP, three bids were sub-
mitted, proposals from Hayes International Corporation,
The Boeing Company, and McDonnell-Douglas Company.
As a result of this competition, The Boeing Company was
awarded the IRAN/Modification Contract F34601-71-C-
3366 because it was the lowest, responsive, responsible
proposer. The Boeing Company’s proposal was several
million dollars lower than was _plaintiff’s. McDonnell-
Douglas, who was the other bidder on this procurement,
submitted a manpower estimate which was approximately
one million (1,000,000) man-hours less than the Hayes es-
timate and was more comparable to the man-hours estimate
presented by Boeing.

ok ol a al al ER ENE BYNES,

37a

(14) The modification work called for by the contract
at issue here originates when changes or improvements
are recommended. The manufacturer of the KC-135A air-
craft, a highly sophisticated technological system, is one
source of ideas for improvement. Once a change or im-
provement is proposed, the Air Force screens the proposals
before it actually makes the decision to incorporate any
change. These procedures include all improvement ideas
furnished to the Air Force’s Engineer Services Division.
If considered sound, they are subsequently transmitted to
the systems manager of the KC-135A aircraft system.
This individual is responsible for determining that further
required review procedures are followed prior to any
recommended change being accepted for use on the
KC-135A aircraft. Configuration Control Boards may give
additional technical and engineering evaluation as to the
basic improvement. If these boards, composed of techni-
cians and engineers experienced and authoritative in the
military aircraft field, conclude that the specific improve-
ment should be incorporated into the aircraft, the systems
manager is then responsible for directing the idea to its
final stage, to see that it is incorporated into the aircraft,
and that all technical manuals are accordingly modified
or updated. The final decision regarding the making of
any modification is made by the Air Force.

(15) After a modification is approved by the Air Force,
a Technical Order (TO) is prepared which involves setting
out the technical terms so that installation service can
be performed. The function of a Technical Order is to
finally relate every step as simply as possible so that
qualified personnel can understand how to do the job at
the field level.

(16) Technical Orders are also prepared so that per-
sonnel will have detailed instructions for performance
of maintenance work (IRAN). If, in the course of tear-
ing down or disassembling an aircraft or system or equip-
ment therein and inspecting it, it is determined that re-

38a

pairs are necessary, such repairs are made. The inspec-
tions and repairs are made in compliance with the IRAN
work statement in the IRAN/Modification contract, which
work statement is prepared solely by the Government.
Technical Orders for maintenance of the KC-135A aircraft
were basically established at the time of acquisition of the
aireraft. The manufacturer of the aircraft, Boeing, does
assist necessarily in preparation of changed Technical
Orders for performance of maintenance work but, as with
other Technical Orders, each Technical Order is analyzed
by the Air Force at the time it is implemented. The changes
in Technical Orders at this time are few and inconsequen-
tial compared to the entire body of basic TO’s related to
IRAN.

(17) At the time offers were solicited on the first con-
tract for modification and maintenance work on the
KC-135A aircraft in 1968, none of the potential contractors
complained or alleged that Boeing was precluded from
bidding on the contract due to bias or unfair competitive
advantage. Likewise, the contracting officer was never
presented with any questions of biased judgment or un-
fair competitive advantage relating to Boeing’s eligibility
in the competition for contract F34601-71-C-3366 either
before award or immediately subsequent thereto. If plain-
tiff had ever lodged any formal complaint and set forth
its reasons for excluding Boeing as a competitor, the Con-
tracting Officer would have been required, under his re-
view authority, to render a final decision and submit same
through channels to the Assistant Secretary of the Air
Fe-ece (I&L) for decision. No such action was ever
initiated or requested by Hayes. No protest was made to
the Comptroller General of the United States.

(18) The Air Force has engineering services contracts
substantially identical to those with Boeing for the
KC-135A (F34601-71-C-0799, F3460i-71-A-1408, F34601-67-
('-0419, etc.) with the manufacturers of several other air-

ee ee i ae oe 2 Oe Bie eee

39a

eraft in its inventory. Certain of these same manufac-
turers have competed for IRAN/Modification contracts on
the aircraft involved and have been successful in some
competitions and unsuccessful in others. Hayes has com-
peted for some of these same contracts and has been sue-
cessful in certain competitions against these aircraft man-
ufacturers who have engineering services contracts on the
aircraft involved. One instance of such success was with
relation to the C-130 Lockheed-built aircraft, which com-
petition took place after that for contract F34601-71-C-3366.
Hayes also competed for work on the KC-135A aircraft
after award of F34601-71-C-3366, which competition was
won by LTV Corporation.

(19) Service engineering contracts with the Air Force
do not result in the contractor being in a conflicting role
which might bias its judgment nor do such contracts result
in the contractor attaining an unfair competitive advan-
tage in bidding on future contracts for work on the air-
craft involved.

(20) In bidding upon and being awarded Contract No.
F'34601-71-C-3366, Boeing

(a) was not involved in conflicting roles which might
bias a contractor’s judgment; and

(b) did not have an unfair competitive advantage.

(21) The bid of the Boeing Company under the sub-
ject RFP was not materially unbalanced as to price and
does not reflect superior knowledge and inside information
available to Boeing by virtue of its engineering services
contracts with the Air Force for the KC-135 which was un-
available to other offerors.

(22) The award of Contract F34601-71-C-3366 was not
contrary to public policy and the public interest in main-
taining the integrity of the procurement system.

40a

CONCLUSIONS OF LAW

(1) This Court has jurisdiction of the subject matter of
this action for declaratory judgment and injunctive relief
and the parties pursuant to 28 U.S.C. §§ 1331, 1361, 2201
and 2202 (1964); and Section 10 of the Administrative
Procedure Act [5 U.S.C. §702 (1970)]. There is now
existing between the parties an actual and justifiable con-
troversy.

(2) The award of Contract No. F34601-71-C-3366 to
Boeing has not resulted in an inherent and illegal conflict
of interest with respect to Boeing by virtue of its contracts
(F34601-71-C-0799 and related contracts) with the Air
Force for sustaining engineering and other related service
work on the KC-135A aircraft. Such award was not arbi-
trary and capricious, and not contrary to public policy and
the public interest in maintaining the integrity of the pro-
curement system, and not contrary to the applicable law.

(3) The plaintiff (Hayes International Corp.) has failed
to establish the award of Contract No. F34601-71-C-3366
by the Department of the Air Force to the Boeing Com-
pany was improper because of the existence of any un-
fair competitive advantage.

(4) The application for permanent injunction or, in the
alternative, for a declaratory judgment, should be denied.

An order of dismissal will be entered in accordance with
the foregoing findings and conclusions.

Done this 30th day of April, 1973.

/s/ Seymour H. Lynne
Senior Judge

4la
APPENDIX C

Armed Services Procurement Regulation
1—113.2 Organizational Conflicts of Interest.

(a) Appendix G—Rules for the Avoidance of Organiza-
tional Conflicts of Interest sets out some of the more
essential policy considerations of the Department of De-
fense with respect to relationships with non-Federal
institutions. Specifically, Appendix G describes examples
of various organizational conflicts of interest which might
come into being, and rules for avoidance of such conflicts;
and it provides that action must be taken to avoid placing
a contractor in a position where his judgment might be
biased or where he would have an unfair competitive ad-
vantage within the scope and intent of the rules. However,
the Appendix cannot of itself impose any obligations on the
contractor; such obligations must be imposed by a contract
clause designed to carry out the intent of the Appendix.
Furthermore, potential contractors must be advised in the
solicitation as to the extent of applicability of the rules,
and must be given an opportunity to negotiate on the terms
of the clause and its application.

(b)(1) The contracting officer is responsible for applying
the rules in the Appendix to contracts under his cognizance
and shall determine whether each proposed procurement
is subject to the Appendix.

(2) If the contracting officer initially determines with
respect to a particular procurement that a potential conflict
of interest exists, he shall, before issuing the solicitation,
prepare a written analysis, including a statement as to
which of the four rules (or other conflict of interest not
stated in the rules) he considers applicable, and a recom-
mended solicitation notice and clause designed to avoid the
organizational conflict of interest. A standard form of
solicitation notice or clause is not prescribed in this Regu-
lation since such notices and clauses must be especially

42a

adapted to apply the principle of the rules to the specific
facts of each contractual situation. The clause shall spell
out the specifie extent of any future restrictions on the
contractor. The restrictions of the proposed clause shall
also have a specific time period of effectiveness. As a
general rule, the time effectiveness of any clause which ex-
cludes the contractor from participation in subsequent pro-
curement shall have a fixed term of reasonable duration as
appropriate, except that where Rule 1 of Appendix G is
involved the exclusion shall be permanent. A fixed term
of reasonable duration is measured by the time required
to avoid the circumstance of unfair competitive advantage.
This is variable; for example, it may run to the date of
award of the first production contract or for a stated period
of time. (See Rules 2 and 3 of Appendix G.) In no event
shall an exclusion be stated in the clause without a specific
date, or an event certain, terminating the effectiveness of
the exclusion except where Rule 1 is involved.

(3) The contracting officer shall include the determina-
tion, together with the written analysis, in the negotiation
file or record. The approved solicitation notice and pro-
posed clause shall then be included in the solicitation,
together with a clear statement that the proposed clause
and the application of the Appendix are subject to negotia-
tion.

(4) In no ease shall the clause included in a solicitation
or in a contract (including letter contracts) pursuant to
this paragraph 1—113.2 defer the determination of the
application of the Appendix to a time after the contract
has been awarded.

(5) Where a contract contemplates a Rule 4 situation, it
is incumbent on the contracting officer to assure himself
that the agreement called for by Rule 4 is in fact executed,
and that copies thereof are made available to the Govern-
ment.

43a

(c) The contracting officer shall not impose restrictions
under the Appendix in follow-on procurements on any
prospective contractor in the absence of a specifie con-
tractual agreement with that contractor. If, during the
effective period of any restriction, procurement responsi-
bility for the system or item involved is transferred from
the procuring activity which imposed the restriction that
activity shall notify the transferee of the restriction and
send it a copy of the contract under which it was imposed.

(d) The Departments shall maintain, in accordance with
Departmental procedures, and for an appropriate period of
time as determined by the circumstances, a record of all
solicitation notices and all clauses incorporated in contracts
pursuant to this paragraph 1—113.2.

44a

APPENDIX G
Avoidance of Organizational Conflicts of Interest

I. PREAMBLE

The Report to the President on Government Contracting
for Research and Development (generally known as the
Bell Report) states that ‘‘today about 80% of Federal ex-
penditures for research and development are made through
non-Federal institutions’’ and that ‘‘there is no doubt that
the Government must continue to rely on the private sector
for the major share of the scientific and technical work
which it requires.”’

In such contracting, it is the policy of the Department of
Defense that the contractor should be given the maximum
responsibility and authority for the performance of as-
signed tasks, and these tasks be of such a nature, even
when they are part of a major system, as to be self-con-
tained from a management point of view. The Report
further states that there are certain essential management
functions in the research and development area that must be
retained within Government. For instance, the integra-
tion and coordination of the separate parts of a large wea-
pons system contract involving several major contractors
would, as a general rule, be handled by Government agen-
cies. To achieve this integration and coordination, how-
ever, special arrangements are sometimes needed such as
are made with nonprofit organizations and industrial or-
ganizations. In this case, the Government must be able to
establish rules for its relationships with the nonprofit or
industrial organizations which may be stricter than those
normally employed with prime contractors. All prospective
contractors will be advised of the applicability of the rules
by a notice in solicitations and by a clause in resulting con-
tracts.

Where the Department of Defense does contract for
research and development work, as it must for the bulk of

45a

that work, its choice of a contractor should be based pri-
marily upon two considerations:

‘*(1) Getting the job done effectively and efficiently, with
due regard to the long-term strength of the
Nation’s scientific and technical resources, and

**(2) Avoiding assignments of work which would create
inherent conflicts of interest.’’

The Report points out that while there are advantages
and disadvantages to the various types of organizations
within the private sector (universities, private nonprofit
organizations and industrial corporations), these types of
organizations should not ‘‘be given areas of monopoly on
different kinds of work,’’ or be permitted to develop a
privileged relationship to the Department of Defense.

In connection with the second criterion, the Report pro-
poses that each department develop a ‘‘Code of Conduct’’
for organizations in the research and development field.
These rules have been developed in accordance with that
instruction.

It should be borne in mind that the pragmatic test for
the selection of a contractor for a particular research and
development contract covers both profit and nonprofit or-
ganizations, including those created largely or wholly with
Government funds. But the rules do not deal with the
criteria for the creation of additional Government-spon-
sored nonprofit organizations in this category. It is the
policy of the Department of Defense that such organiza-
tions are created only under extraordinary circumstances,
when private resources are not available to accomplish a
necessary objective beyond the scope of in-house capabil-
ities. Their termination is governed by the organic
statutes of the individual organizations. These rules
should make it even less likely that any additional Gov-
ernment-financed nonprofit organizations need be created.

46a

While these organizations are in existence they will be
treated by the Department on arms length basis, as the
rules prescribe.

Il. Ruies

The following rules state general prohibitions which are
then explained and illustrated by specific examples. There
will undoubtedly occur cases which are not resolved by these
rules. As the Bell Report said, ‘‘(Conflict of Interest]
arises in several forms—not all of which are by any means
yet fully understood.”’ In order to assist in deciding what,
if any, prohibitions should be applied in such instances,
the two basic principles of this code—(1) preventing con-
flicting roles which might bias a contractor’s judgment,
and (2) preventing unfair competitive advantage—should
be paramount. The following rules and examples are not
all inclusive but merely attempt to achieve these two goals
in a variety of situations. The ultimate test should always
be: Is the contractor placed in a position where his judg-
ment may be biased, or where he has an unfair competitive
advantage? If so, corrective action must be taken in ac-
cordance with the rules below.

As used in these rules, ‘‘contractor’’ means the person
under contract to the Department of Defense to perform
the work described in each rule, and its affiliates; ‘‘system”’
means system, subsystem, project or item. The term
‘‘systems engineering”’ includes a combination of sub-
stantially all the following activities: determination of
specifications, identification and solutions of interfaces
between parts of the system, development of test require-
ments or plans and evaluation of test data, and supervision
of design work. The term ‘‘technical direction’’ includes a
combination of substantially all the following activities:
preparation of work statements for contractors, determina-
tion of parameters, direction of contractors’ operations,
and resolution of technical controversies.

47a

1. If a contractor agrees to provide systems engineering
and technical direction (SE/TD) for a system, without at
the same time assuming over-all contractual responsibility
for: (a) development, or (b) integration, assembly and
checkout (IAC), or (c) production of the system, then that
contractor shall not later be allowed to supply the system
or any major components thereof, or to be a subcontractor
or consultant to a supplier of the system or any major
components thereof.

Explanation: The SE/TD contractor occupies a highly
influential and responsible position as an agent of the De-
partment of Defense both in determining basic concepts
of a system and in supervising their execution by other
contractors. To assure the objectivity of its services and
hence a more soundly planned system, the SE/TD contrac-
tor must not be in a position to make decisions which
could favor its own products. Furthermore, it would be
inconsistent with the managerial responsibility of an SE/
TD contractor for it to be concurrently one of the compo-
nent suppliers.

Example A: Company A agrees to provide SE/TD for -
the Navy on the power plant for a group of submarines
(i.e., turbine, drive shafts, props, ete.). Company A shall
not be allowed to supply any power plant components.
Company A can, however, supply components of the sub-
marine unrelated to the power plant (e.g., fire control, navi-
gation, ete.). In this example, the system is the power
plant, not the submarine, and the ban on the supply of
components is coterminous with the system only.

Example B: Company A is the SE/TD contractor for
system X. After some progress, but prior to completion,
the system is cancelled. Later, system Y is developed to
achieve the same purposes as system X, but in a funda-
mentally different fashion. Company B is the SE/TD con-
tractor for system Y. Company A may bid to produce
system Y or its components.

48a

2. If a contractor agrees to prepare and furnish com-
plete specifications covering nondevelopmental items to be
used in competitive procurement, that contractor shall not
be allowed to furnish such items, either as a prime or sub-
contractor, for a reasonable period of time including, at
least, the initial procurement. This rule shall not apply to:

a. Contractors who furnish at Government request spe-
cifications or data with respect to the product they fur-
nished, even though the specifications or data may have
been paid for separately or in the price of the product.

b. Situations where one or more contractors acting as
industry representatives assist Department of Defense
agencies in preparing, refining or coordinating specifica-
tions, regardless of source, which assistance is supervised
and controlled by Government representatives.

c. Contracts for developmental or prototype items.

Explanation: If a single contractor is engaged by the
Government to draft complete specifications for nondevel-
opmental equipment, he should be eliminated for a reason-
able time from competition for production based on the
specifications. This should be done in order to avoid a
situation where he could draft specifications which would
favor his own products or capabilities. In this way the
Government can be assured of getting unbiased advice as to
the content of its specifications and can avoid allegations of
favoritism in the award of production contracts.

In development work it is normal to select firms which
have done the most advanced work in the field. It is to be
expected that these firms will design and develop around
their own prior knowledge. Development contractors can
frequently start production earlier and more knowledgeably
than firms which did not participate in the development,
and this affects the time and quality of production, both
of which are important to the Department of Defense. In
many instances the Government may have financed such

49a

development. Thus, the development contractor may have
an unavoidable advantage which is not considered unfair
and no prohibition should be imposed.

In instances of cooperation between industry and De-
partment of Defense agencies to prepare, refine or coordi-
nate specifications, there is continuous participation and
supervision by Government representatives and, usually,
more than one contractor concerned. In these cireumstan-
ces Government supervision prevents the establishment of
specifications oriented to favor a given contractor’s prod-
ucts or capabilities.

Example A: Company A prepares updated Government
specifications for a standard refrigerator to be procured
competitively. Company A shall not be allowed for a rea-
sonable period of time to compete for supply of the re-
frigerator.

Example B: Company A designs or develops a new
electronic equipment and, as a result of the design or de-
velopment, prepares specifications. Company A may sup-
ply the electronics equipment.

Example C: XYZ Tool Company and/or KLM Machinery
Company representing the American Tool Institute work
under the supervision and control of Government repre-
sentatives to refine specifications or to clarify the require-
ments of a specific procurement. These companies may sup-
ply the item.

3. If a single contractor, other than a company which
has participated in the development or design of a system,
agrees to assist the Department of Defense or a contractor
of the Department of Defense in the preparation of a state-
ment of work, or agrees to provide material leading direct-
ly, predictably, and without delay to a statement of work,
to be used in the competitive procurement of a system or
services, that contractor shall not be allowed to supply
the services, or the system or major components thereof,

50a

unless he is the sole source. The content of a statement of
work shall not be considered predictable if more than one
contractor is involved in the preparation of material lead-
ing to it.

Explanation: The various services related to a statement
of work to be used in a competitive procurement should
normally be performed by the Department of Defense.
However, when it is necessary to seek the assistance of
contractors, they may often be in a position to favor their
own products or capabilities. To overcome this possibility
of bias, such contractors are to be prohibited from sup-
plying a system or services procured on the basis of work
statements growing out of their services.

No prohibitions are imposed on development contractors
for the reasons given in the explanation to Rule 2.

Example A: Company A receives a contract to define the
detailed performance characteristics the Department of
Defense will require for the purchase of rocket fuels. A
has not developed the particular fuels. At the time the con-
tract is awarded, it is clear to both parties that the perform-
ance characteristics arrived at will be used by the Depart-
ment of Defense to choose competitively a contractor to
develop or produce the fuels. Company A shall not be
permitted to bid on this procurement.

Example B: Company A receives a contract to prepare
a detailed plan for the procurement of services aimed at the
advanced scientific and engineering training of Department
of Defense personnel. It suggests a curriculum which the
Department of Defense endorses and incorporates in
requests for proposals to various institutions to establish
and conduct such training. Company A shall not be per-
mitted to bid on this procurement.

Example C: Company A prepares a feasibility study of
a new weapons system without proposing in detail the

bE dail be an tg ees Re ea) a i eo dr hl te: pow

5la

characteristics of a possible final device. It may bid to
produce the system or components thereof.

4. If a contractor agrees to conduct studies or provide
advice concerning a system, which work requires access to
proprietary data of other companies, the contractor must
agree with such companies to protect such data from un-
authorized use or disclosure so long as it remains pro-
prietary. In addition, the contractor shall not be permitted
to utilize the data in supplying the system, or components
thereof, procured, either by formal advertising or negotia-
tion, as a direct result of that study or advice, or in per-
forming for the Department of Defense additional studies
in the same field which are obtained competitively.

Explanation: Proprietary data is information considered
so valuable by its owners that it is held secret by them and
their licensees. Where a contractor must obtain such data
from others for purposes of the study, and can obtain it by
the leverage of the Department of Defense contract, he
will gain an advantage over other companies unless there
are restrictions upon his use of the data. Such restrictions
are necessary both to protect the data, and to encourage
companies to furnish it to contractors for the necessary
performance of the Department of Defense contract. The
rule is not intended to protect proprietary data furnished
voluntarily by companies without limitations as to use, or
data which falls into the public domain.

Example A: Company A is selected to study the use of
lasers in military communications. The Department of
Defense will request that firms doing research in the field
make proprietary data available to A. In order to receive
the contract, A must agree with such firms to protect any
proprietary data it obtains, so long as it remains pro-
prietary, and shall not be permitted to utilize the data in
supplying any lasers to the Department of Defense.
Furthermore, while A could not receive a competitively
awarded contract to perform additional studies of lasers

I 85 8.28 CLE ON NOONE EE PONG IORI REY NTT

52a

using such data, it may receive a sole source contract for
such studies.

Review and Waiver

The contracting officer is responsible for applying these
rules to contracts under his cognizance. If the prospective
contractor disagrees with his decision, the contracting
officer shall report his decision, and the contentions of the
contractor, through channels to an Assistant Secretary of
a Military Department or the Director of a Defense Agency
for decision.

Any of the prohibitions imposed by these rules may be
waived by an Assistant Secretary of a Military Department
or the Director of a Defense Agency if he determines that
a failure to waive the prohibition will be prejudicial to the
best interests of the Government.

---