# Petition for Writ of Certiorari — United States v. Urban Plumbing & Heating Co.

> Briefs, arguments, decisions, and more.

URL: https://www.frixlaw.com/law-library/documents/brief%3Amicro_IA40385604_1547%3A1

## Record

- **Collection:** Supreme Court brief
- **Document type:** Petition for Writ of Certiorari
- **Published:** January 1, 1970
- **Citation:** 398 U.S. 958

## Text

INDEX

one ions presented bbe hia ey ha aduk wn ao Masts Cae tke
"i te involyed EE RHEE SOS ays Toe * 6

CITATIONS

Woy Products Corporation v. United Siates,
Me. 0 GOB. sb. socks ews cen
Automatic Radio Mfg. Hazeltine Re-
ee, 176 F. 2d op, “aiceed. 339 U.S.
E pal United States, 404 F. 2d 975______-_-
Bennett v. Mahon, 180 F. 2d 224, certiorari
denied, 339 U.S. 980___......-----_.-_--

Bolander v. United States, 186 Ct. Cl. 398_-__-
Centre Manufacturing Co. v. United States, 183
Ch 0: 116, 302 F.9d 220... 2-222. 225.
D. & L. Construction Co. v. United States, 185
Ct. Cl. 736, 402 F. 2d 990____..-...._--
Dean Construction Co. v. United States, Ct.
Cl. No. 95-67 (decided June 20, 1969) ____
Gill v. S.H.B. Corporation, 322 Mich. 700, 34
Te BO. bb Gonwe ccc tncedsudoeeua
— Mill v. United States, 271 U. .
ce Hellenis Lines Lid v. Louis Dreyfus Corp., 372
PE TD. . FF eee Pe eee ce —

>

ditions mt said contract as

remain unchanged and in full force and effect.
This Supplemental Agreement is entered into
pursuant to the authority of basic contract.

23. Appellant continued to work through the winter,
with attendant problems. There were interferences
from the severe weather and the operation of the

. While there was some rearrangement
of the interim schedules, the work was substantially
completed on 30 June 1962.

%4. An audit conducted by the Air Force after com-
pletion shows a cost to the appellant of $567,680.22.
This is $79,905.22 in excess of the final contract price.

25. The original claims consisted of the allegations
of delay and interference detailed in the foregoing
findings, and several smaller claims founded on par-
ticular alleged changes. Several of the smaller claims
were abandoned at the hearing, and none of the others

were supported by adequate proof to warrant specific
findings.

OPpixion

The first question presented is whether or not the
coal seales, combustion air coils, and ash removal
equipment initially offered by the appellant was im-
properly rejected by the respondent. Appellant argues

——_

that this equipment met the “intent” if not the de
tailed requirements of the specifications. It says thet
the details of fabrication and operation given wer
unduly restrictive and in violation of the provisions
of the Armed Services Procurement Regulation 1.
lating to description by “‘brand name or equal.” }j
says that respondent would accept only the named
brands, thus should have specified them alone. We cay
assume that every allegation made by the appellant
is correct, but still find that the equipment was prop.
erly rejected.

Prior to award of a contract, prospective bidders,
suppliers, or even interested taxpayers may object to
restrictive specifications which unnecessarily restriet
competition. These objections may be, and frequently
are, made to the contracting officer, his superiors, or
to the General Accounting Office. When the restric.
tions are found to be more stringent than the needs
of the service dictate, the specifications are amended.
But a bidder may not remain silent during the bid.
ding period, then after receipt of award of the
contract contend that he has the right to furnish some
thing less expensive and not meeting the requirements
of the specifications. To allow such would be equally
damaging to the competitive bidding system with u-
duly restrictive specifications. Many of the specified
details may have been unnecessary. Others were
clearly desirable for this particular application, and
some of these details were not met by the offered
equipment. The Richardson Scales, Brod and Me
Clung Coils and the Durabilt equipment clearly did
not meet the requirements of the contract and were
properly rejected.

The appellant was the innocent victim of represen-

ae ee, ee a ee tn F&F ewe TE S&H T

i

tations by its prospective suppliers that their equip-
ments would meet the specified requirements. We
have no reason to believe they were not acting in good
faith. But this would not entitle appellant to recover
its losses from the Government. Under the most lib-
eral view it could, at most, receive a time extension,
and this the appellant got.

The respondent did unreasonably delay acting upon
these submittals. The contract gave appellant only 10

tion on the Durabilt submittal until 29 August, par-
ticularly since it had already been decided to reject it.

Appellant argues that by insisting upon changing
the word “costs” to the word “price” in Supplemental
Agreement No. 1, it avoided agreeing that the contract
consideration would not be increased as the result of
the extended contract performance time. This is not a
reasonable construction of the provision which states,
“This Supplemental Agreement neither increases or
[sie] decreases contract price.” The other provisions
of the agreement reschedule performance. We think
it clear that the quoted sentence stated an agreement
that the contract price would not be changed by
reason of performance under the new schedule. The
appellant’s losses were directly attributable to such
performance.

The appellant next contends that the supplemental
agreement was without consideration, thus not bind-

64

ing upon it. The appellant was actually in default at
the time the supplemental agreement was made, The
parties were jointly responsible for the delay in de
livery of the equipment, the appellant because it of.
fered equipment which did not meet the contractual
requirements, and the respondent because it delayed
too long in rejecting it. We are unable to apportion
the causes of delay for the evidence is directed to.
ward the time lapse between submittal and action
thereon. A time extension is properly computed upon
how long the work is delayed, not how long the de.
laying causes continue in existence. We know when
the approved equipment was delivered, but not when
it would have been delivered but for the respondent's
delay in rejecting the unsuitable equipment. In any
event, the appellant was not entitled to a time exten.
sion adequate to permit completion of the work,
The receipt of such time in the modification was a
valuable consideration.

Appellant’s final argument is that the supplemental
agreement was signed by it under duress. In order
to constitute economic duress, there must be something
present other than threatened financial disaster.
DuPuy v. United States, 67 Ct. Cl. 348, 381 (1929).
Where the contracting officer threatens default termi-
nation, and the contractor is actually in default, the
contracting officer was threatening to do only what he
had the right to do. This is not duress. Commonwealth
Engineering Company of Ohio v. United States, 48
Ct. Cl. 330 (1960), cert. denied 364 U.S, 820. In the
instant case the appellant was in default for the com-
pletion date was 18 days past when the modification
was signed. At least as to the coal thaw shed only 3
days of the delay was excusable. The contracting of-
ficer offered 69 days time extension because of the
delay in approvals. This would not have permitted

BLEED THROUGH POOR COPY

or Tra wr iB SPS SET SB ABP SS SB

~o we | © OH oe 8 Ts SF Oo

65

completion, but we cannot find that it was not as
much as was due for excusable cause.

The appeal is denied.
Dated: 30 December 1966.

Harris J. ANDREWS, Jr.,
Member of Division No. 3,
Armed Services Board of Contract Appeals.
I concur.
Hvuou B. ArcHer,

Acting Vice Chairman, Armed Services Board
of Contract Appeals, and Member of Division
No. 3.

Rosert J. O’Connor,

Member of Division No. 3, Armed Services
Board of Contract Appeals, did not par-
ticipate.

Armep Services Boarp or Contract APPEALS
ASBCA No. 9831

Appeal of
Ursan PLUMBING AND HeEatine Co.

Under Contract No. AF 65(503)-1505

Appearances for the Appellant: Warde H. Erwin,
Esq., Portland, Oregon.

Appearances for the Respondent: Colonel David C.
Yeoman, USAF, Chief Trial Attorney; Major Eugene
M. Solimine, USAF, Trial Attorney.

On Morton For RECONSIDERATION

The appellant has moved for rehearing and redeter-
mination of certain of the Board’s findings set out in

COPY BOUND CLOGE IN CENTER

66

its opinion of 30 December 1966, which denied the
appeal.

The first allegation of error is that the member of
the Board who conducted a portion of the hearing dig
not participate in the decision. This member retired
soon after the hearing, and was not a member of the
Board at the time this case was ready for decision,
The Board has held many times that preparation of
the opinion by a member who did not preside at the
hearing is not error. Buckeye Union Casualty Co,
ASBCA No. 6770 (On Reconsideration), 1962 BCA
P 3309, and cases cited therein. See also Racine Screw
Company v. United States, 156 Ct. Cls. 256 (1962).

The remaining allegations of error present nothing
which was not fully considered by the Board in reach-
ing its decision.

The Motion for Reconsideration is denied.

Dated 8 February 1967.

Harris J. ANDREWS, JR.,
Member of Division No. 3,
Armed Services Board of Contract Appeals.

I concur:

Huou B. ARcHER,

Acting Vice Chairman, Armed Services Board of
Contract Appeals and Member of Division No.
3.

Wu11aM T. Grirrirn,

Lt. Colonel, USAF, Member of Division No. 3,
Armed Services Board of Contract Appeals,
did not participate in the determination of this
decision.

I certify that the foregoing is a true copy of the de-
cision and opinion of the Armed Services Board of
Contract Appeals in ASBCA No. 9831, Appeal of
Urban Plumbing and Heating Co., On Motion for

BLEED THROUGH POOR COPY

67

Reconsideration, rendered in conformance with the
Board’s Charter.
Dated

GerorceE L. HAWKES,
Recorder, Armed Services Board of
Contract Appeals.

U.S. GOVERNMENT PRINTING OFFICE: 1969

---

Source: Frix Law Library, https://www.frixlaw.com/law-library/documents/brief%3Amicro_IA40385604_1547%3A1. Public record. Not legal advice.
