# Opposition Brief — Acmat Corp. v. School District of Philadelphia

> Briefs, arguments, decisions, and more.

URL: https://www.frixlaw.com/law-library/documents/brief%3Amicro_IA40385020_2864%3A2

## Record

- **Collection:** Supreme Court brief
- **Document type:** Opposition Brief
- **Published:** January 1, 1991
- **Citation:** 498 U.S. 1024

## Text

Petition No. 90-499

IN THE

SUPREME COURT OF THE UNITED

October Term, 1990

ACMAT CORPORATION,
Petitioner,

v.

SCHOOL DISTRICT OF PHILADELPHIA,
Respondent.

RESPONDENT’S BRIEF IN OPPOSITION TO
PETITION FOR A WRIT OF CERTIORARI
TO THE UNITED STATES COURT OF
APPEALS FOR THE THIRD CIRCUIT

André L. Dennis
John J. Murphy, III
STRADLEY, RONON, STEVENS

& YOUNG
2600 One Commerce Square
Philadelphia, Pennsylvania 19103
(215) 564-8034

Counsel of Record and
Attorneys for Respondent

PACKARD PRESS / LEGAL DIVISION, 1617 JFK BOULEVARD, PHILA, PA. 19103 (215) 563-9000

BEST AVAILABLE COPY” jam

anes a
fhe sigh be ae a S
Be:
ume
+ an

JOSEPH F. SPANIO
JR.
LERK JR

TABLE OF CONTENTS

COUNTER-STATEMENT OF THE CASE ............
PMP em ss

A.

THE DISTRICT COURT DID NOT DEPRIVE
ACMAT OF ITS PROCEDURAL DUE PROCESS
PUNE ENS Cob cben ceewenebageteasductdevesece

. THE DISTRICT COURT CORRECTLY INTER-

PRETED THE CONTRACT DOCUMENTS......

. THE DISTRICT COURT PROPERLY ENTERED

SUMMARY JUDGMENT ON ACMAT’S BREACH
OF CONTRACT CLAIMS. ..............2.cceeee

. THE DISTRICT COURT DID NOT DECIDE IM-

PROPERLY DISPUTED ISSUES OF MATERIAL
PREG 2 keveees SP TT ee PCIe TINT CO TTT ETT

. THE DISTRICT COURT PROPERLY DISMISSED

ACMAT’S CLAIMS FOR DELAY DAMAGES. ....

BASED UPON THE JUROKS’ ANSWERS TO SPE-
CIAL INTERROGATORIES, THE DISTRICT
COURT PROPERLY ENTERED JUDGMENT
FOR THE SCHOOL DISTRICT ON ACMATS
CLAIM FOR CONTRACT RETAINAGES........

. THE DISTRICT COURT PROPERLY DIS-

MISSED ACMAT’S QUANTUM MERUIT
ECA Sapbvetkan eee beueebeeeeanbecrcnccce

10

13

14

15

16

RE Ship sh 00k o ean 040550 cd abde es thnnen eases R.A.

THE SCHOOL DISTRICT OF PHILADELPHIA'S

MOTION FOR SUMMARY JUDGMENT....... R.

A. 1

TABLE OF CONTENTS — (Continued)

Page

ACMATS ANSWER TO THE SCHOOL DIS-
TRICTS MOTION FOR SUMMARY JUDG-
MENT... vcscccccccwscctcnsstccaceésesenseos R.A. 30

ACMATS MEMORANDUM OF LAW IN SUP-
PORT OF ITS MOTION FOR REARGUMENT. R.A. 68

LAS OMS te

TABLE OF AUTHORITIES

Cases: Page
Commonwealth v. Mitchell's Structural Steel Painting Co.,
18 Pa. Commw. 591, 336 A.2d 913 (1975) .......... 12
Commonwealth v. Seagram's Distiller’s Corp., 379 Pa. 411,
PR I BERL aa dni tedeicdcccccccccecss i7
Derry Twp. School Dist. v. Suburban Roofing Co., 102 Pa.
Commw. 54, 517 A.2d 225 (1986). .............. 17, 18
Dick Corp. v. State Public School Bidg. Auth., 27 Pa.
Commw. 498, 365 A.2d 663 (1976). ................ 14
F.D. Rich Co. v. Wilmington Housing Auth., 392 F.2d 841
Se I ie CEU Ee Rick Ca Wbeebs kcdekeccccccs 15
Goodwin v. Elkins & Co., 730 F.2d 99 (3d Cir. 1984), cert.
I, Se es BP ovo iccccccncccccccces 9
Hutchinson v. So. Central Bell Tel. Co., 815 F.2d 1058 (Sth
GUIS Wa Roba umhedewn be be ca de codecotsececs 8
John F. Harkins Co. v. School Dist. of Phila., 313 Pa.
Super. 425, 460 A.2d 260 (1983)... ................ 9
Keene Corp. v. Internat Fidelity Ins. Co., 736 F.2d 388
RES a a 8
Layne & Bowler Corp. vo. Western Well Works, Inc., 261
i ehh nauk end ceneh su eeensseceee 6

Nether Providence Twp. School Auth. v. Thomas M.
Durkin & Sons, Inc., 505 Pa. 42, 476 A.2d 904

Appeal of Sykesville Boro., 91 Pa. Super. 335 (1927) ..... 17

Teodori v. Penn Hill School Dist. Auth., 413 Pa. 127, 196
ETE SR aca ecnsncepevccssoncceeences 10, il

United Contractors v. United States, 368 F.2d 585 (Ct. Cl.
ee EL ee ccceckdnecceetecccses 13

United States v. Spearin, 248 U.S. 132, 39 S.Ct. 59, 63
ss omni casees 13

TABLE OF AUTHORITIES — (Continued)

Statutes: Page

0 Pia ic Mm GIBB, «06 kinds i vecceccusatdosseis 8, 18

OUT OTTI TTT eTER eh OL 6

oe Fe Fk OR TVIITTE Tiree eed Le 9

DD. .Bey SOE ND SED ox sewpaccctcsvsvesdevwnctes 14
iv

Sh A ti.

RE Ao RN ae NS AS CO ECL BER 5s -

Petition No. 90-499

IN THE

SUPREME COURT OF THE UNITED STATES

October Term, 1990

ACMAT CORPORATION,

v.

SCHOOL DISTRICT OF PHILADELPHIA,

Respondent.

RESPONDENT'S BRIEF IN OPPOSITION TO
PETITION FOR A WRIT OF CERTIORARI
TO THE UNITED STATES COURT OF
APPEALS FOR THE THIRD CIRCUIT

COUNTER-STATEMENT OF THE CASE

A. Prior Proceedings

This is an action by Acmat Corporation (“Acmat”) to recover
damages for alleged extra work Acmat contends it performed in
connection with three asbestos removal contracts with the
School District of Philadelphia (“School District”). Acmat com-
menced this action by Summons and Complaint in the United
States District Court for the Eastern District of Pennsylvania on
December 9, 1985. The Complaint set forth claims for breach of

toppel and under the Racketeer Influenced Corrupt Organiza-

tions Act.!

Following the completion of discovery, the School District
filed a Motion for Summary Judgment on each of Acmat’s claims
on August 15, 1988. (R.A. 1).* The School District advanced the
following positions in support of its motion: (1) Acmat was
prohibited from recovering on any contractual or quasi-
contractual claims for additional work because Acmat failed to
obtain the approval of the School Board for the alleged extra
work, as required under its contracts and under the provisions of
the Pennsylvania Public School Code; (2) Acmat was precluded
from recovering delay damages under the terms of its contract;
(3) Acmat was barred from contesting the Schoo! Board’s deter-
mination on labor and materials expended in the two instances
where the School Board did approve additional work; and (4)
Acmat was responsible under its contracts for ascertaining the
full scope of its work and had a contractual obligation to perform
the work it claimed it was unaware of when it submitted its bids.

Acmat conceded in its response to the motion that as a
general rule it would not be able to obtain payment for alleged
extra work in the absence of School Board approval. (R.A. 33).
However, Acmat argued that an exception existed in those
“instances dealing with situations where time is of the essence
and the delay in waiting for School Board approval would be
detrimental to the citizens of the Commonwealth.” (R.A. 34).
Acmat also contended it was entitled to pursue its claim since (1)
equitable adjustment was “mandated” under the contracts; (2)
the extra work arose from “unforeseen conditions”; and (3) a

1. Acmat’s negligence and Racketeer Influenced and Corrupt Organiza-
tions Act (“RICO”) claims were voluntarily dismissed with prejudice. Acmat's
punitive damages and two fraud counts were withdrawn without prejudice. A
single fraud count was later reinstated by Acmat.

2. “R.A.” refers to the sequentially numbered pages of Respondent's
Appendix attached hereto.

Ue i

3

factual dispute existed which precluded enforcement of the “no
damage for delay” clause. (R.A. 45, 39, 55).

The District Court issued a 22-page Order in response to
the School District's motion on December 21, 1988. (App. C 5a-
24a).2 The District Court found that Acmat’s contract and
quasi-contract claims were barred as a matter of law under the
provisions of the Pennsylvania Public School Code due to the
absence of School Board approval of the alleged extra work.
Acmat’s fraud claim was dismissed for failure to state a claim.
The District Court also determined that a provision of the
contract relating to an equitable adjustment was likewise subject
to the provision in the contracts requiring Board approval of all
changes in contract scope and price. In response to the unfore-
seen conditions argument of Acmat, the District Court ruled
that Acmat did not comply with the procedures set forth in the
contract requiring School Board approval of any change in the
scope of work or contract price occasioned by the discovery of
conditions not allegedly reasonably anticipated and that Acmat
was bound by its contractual responsibility to ascertain the
nature and location of the work. Acmat’s Gaim for delay damages
was rejected by the Court because it was barred by the specific
language of the written contracts.‘ (App. C at Sa-24a).

More than six months after the entry of the Court’s Order
of December 21, 1988, Acmat moved for reargument of the
District Court's earlier order granting partial summary judg-
ment to the School District. (R.A. 68). In addition to reiterating
Acmat’s prior position that there were unforeseen conditions

3. Appendices A through J are attached to Acmat’s Petition and are
numbered sequentially from la through 245a.

4. After making these rulings, the District Court, nevertheless, pro-
ceeded to determine on an item-by-item basis whether Acmat was entitled to
receive damages for individual items of alleged extra work and the amount
thereof. At the conclusion cf the order, the District Court determined that
Acmat was entitled to a total credit of $203,723.79 against the School District's
counterclaim. Due to adjustments, this amount was later reduced to
$132,420.70. The District Court's decision to award damages to Acmat,
notwithstanding the lack of School Board approvel, is the subject of the School
District's Cross-Petition for a Writ of Certiorari.

and materials. (R.A. 86).

The jury trial on the School District's counterclaim against
Acmat took place from July 7 to July 14, 1989. In accordance
with the jury's answers to special interrogatories, the District

1989, in favor of the School District in the amount of $23,480.92
on the School District’s Counterclaim for delay damages and in
the amount of $16,975.42 on the School District’s claims for
contract-completion costs. (App. F at 97a). In the same Judg-
ment, the District Court entered judgment in favor of the
School District and against Acmat on Acmat’s claim for payment
of contract balances in the amount of $150,909.14, and deducted
the jury award in favor of the School District from the court's
earlier summary judgment award to Acmat for a net award to
Acmat of $91,964.40. (Id.)

Acmat did not file any post-trial motion for a new trial or
judgment notwithstanding the verdict. Post-trial motions filed
by the School District were denied. Acmat filed an appeal to the
United States Court of Appeals for the Third Circuit, and the
School District, thereafter, filed a cross-appeal. The Court of

;
i
3
:

conditions which can affect the work or the cost thereof.” (App.
E at 88a). Acmat further acknowledged that any failure on its
part to ascertain the extent of its work under the contracts would

not relieve it of “responsibility for successfully performing the
work without additional expense to the School District.” (fd.,

stances, including those instances where such delays were
caused by acts or neglect of the School District. (App. E at 92a).
Instead, Acmat agreed in each of its contracts that it could seek
extensions of time to complete its contracts as a result of any
delays on the job sites. (Id. ).

6

where a contractor [Acmat] claimed it discovered site conditions
differing from those shown in the contract drawings and speci-
fications. (Id.).

The School District and Acmat agreed, with Board ap-
proval, to a single written change order for the work at the
Fairhill School. The Board did not approve, nor did the School
District ever issue, any change orders with respect to work at
the Lincoln School. The parties agreed, with Board approval, to
a single written change order at the Rush School. No other
change orders or requests for additional compensation were
approved by the School Board.

Acmat failed to complete its work at the three work sites
within the time required under its contracts with the School
District. The total fixed price for all three contracts was
$2,001,283. Acmat, however, subsequently sought nearly
$6,000,000 for alleged contract extras.

REASONS FOR DENYING THE PETITION

This case involves nothing more than a garden variety
contract dispute between an asbestos-removal contractor and a
property owner which is limited solely to issues of Pennsylvania
law. As such, this case does not satisfy even remotely the
standards which would support review on a Writ of Certiorari.

A review on a Writ of Certiorari is not a matter of right, but
of judicial discretion. The rules of this Court provide that a
Petition for a Writ of Certiorari will be granted “only when there
are special and important reasons therefor.” Sup. Ct. R. 10. This
Court has explained certiorari should be granted only “in cases
involving principles the settlement of which is of importance to
the public as distinguished from that of the parties, and in cases
where there is a real and embarrassing conflict of opinion and
authority between the Circuits.” Layne & Bowler Corp. v.
Western Well Works, Inc., 261 U.S. 387, 393 (1923).

Rule 10 of the Supreme Court Rules sets forth certain
situations in which the Court will consider exercising its discre-
tion to review on a Writ of Certiorari. None of these standards
even remotely applies here. This case does not involve a split

lS a ag gs Cina GAS ES Pt si OAR

7

between the circuit courts on an important legal issue. More
importantly, Acmat voluntarily dismissed its RICO claim and,
therefore, has not pursued any claim under federal law against
the School District. This case does not involve a situation where
a United States court of appeals has decided a federal question
in conflict with a state court of last resort or where a United
States court of appeals has decided an important question of
federal law which was not then, but should be, settled by this
Court. Finally, this case does not involve a situation where a
court of appeals has sanctioned an action by a District Court
which has “departed from the accepted and usual course of
judicial proceedings” contemplated by Rule 10, supra. As
explained more fully below, there was more than an adequate
legal and factual basis to support the actions of the District
Court.
Acmat asks this Court merely to interpret provisions in
asbestos-removal contracts and to interpret provisions of Penn-
sylvania law governing public school contracts in a fashion which
has already been rejected by the District Court and the Court of
Appeals. Acmat has failed to present any compelling basis for a
review of these state law questions. Furthermore, many of the
arguments Acmat has made to this Court and the Court of
Appeals were never presented in a timely fashion to the District
Court at the time it adjudicated the claims between the parties
and are, therefore, beyond this Court’s scope of review.

A. The District Court Did Not Deprive Acmat Of Its Proce-
dural Due Process Rights.

In ruling on the School District’s Motion for Summary
Judgment, the District Court held that the great majority of
Acmat’s claims against the School District were barred as a
matter of law because Acmat had failed to obtain approval in
advance for this alleged extra work from the School Board, as

under the terms of its contracts and under the provi-
sions of §5-508 of the Pennsylvania School Code. (App. C at 5a).

5. The Pennsylvania School Code of 1949 provides, in pertinent part,
that:

8

The District Court, however, determined that Acmat was
entitled to additional compensation with respect to a limited
number of claims for additional work and determined the
amount of additional compensation Acmat was entitled to based
on the record before the Court. Acmat now complains that this
aspect of the summary judgment Order was improper and that it
should have been afforded a hearing to present further evidence
concerning its alleged damages.

Significantly, Acmat did not contend at the time it re-
sponded to the School District’s Motion for Summary Judgment
that Paragraph 14(b) of the contracts between Acmat and the
School District, making the School District the final arbiter of
Acmat’s cost of labor and materials, violated public policy or
Acmat’s due process rights. (R.A. 30). Acmat first raised this due
process argument in an untimely motion for reargument of the
District Court’s order granting, in part, the School District's
Motion for Summary Judgment. The District Court denied
Acmat’s motion for reargument because it concluded that Acmat
had raised nothing which could not have been raised by Acmat
when it filed its response to the Motion for Summary Judgment.
(App. D at 5la-52a). The District Court’s refusal to consider
these new arguments on a motion for reconsideration was well
founded. See Hutchinson v. So. Central Bell Tel. Co., 815 F.2d
1058 (5th Cir. 1987) (“a party who presents his case on one
theory and loses should not, in the absence of good reason, be
permitted to have a second chance for the presentation of a new
rationale”); Keene Corp. v. International Fidelity Ins. Co. 736
F.2d. 388, 393 (7th Cir. 1984) (a party cannot raise new legal
theories in a motion for reconsideration or on appeal).

NOTES (Continued)
[t]he affirmative vote of a majority of all the members of the board of
school directors in e very school district, duly recorded, showing how each
member voted, shall be required in order to take action on the following
subjects: . . . [c]reating or increasing any indebtedness . . . [e]ntering into
contracts of any kind . . . where the amount exceeds $100.00 . . . [failure
to comply with the provisions of this section shall render such acts of the
board of school directors void and unenforceable.

24 Pa. Stat. Ann. §5-508.

9

Even if Acmat had challenged the “final arbiter provision”
in its contracts in a timely fashion, any such challenge would be
without merit. Acmat’s reliance, for example, upon the case of
John F. Harkins Co. v. School Dist. of Phila., 313 Pa. Super.
425, 460 A.2d 260 (1983) is misplaced. Acmat cites Harkins for
the proposition that it was entitled to offer proof of additional
damages even where the School District was the final arbiter of
the contractor's net cost. However, Acmat did not submit any
proper evidence by affidavit in opposition to the School Dis-
trict’s Motion for Summary Judgment to demonstrate its costs
exceeded the amount approved by the Board.

Furthermore, Acmat’s reading of Harkins is incorrect.
Harkins involved the issue of whether a “total cost” method for
evaluating additional work performed under a contract was
appropriate. Reversing the trial court's use of the total cost
method and its decision in favor of Harkins, the Pennsylvania
Superior Court stated “[o]ur independent review of the record
persuades us that this was error. In the first place, the School
District was to be the final arbiter of the contractor's net costs.”
313 Pa. Super. at 434, 460 A.2d at 265. Thus, the final arbiter
clause was both enforceable and relied upon by the Superior
Court in its decision. Further, the Harkins case involved only an
evaluation of the “total cost” method. There is nothing in the
record here to demonstrate that the School District argued that
the final arbiter clause was binding and conclusive with respect
to its determination of damage.

Finally, the District Court and the United States Court of
Appeals for the Third Circuit are not bound by decisions of the
Pennsylvania Superior Court in interpreting Pennsylvania law.
Goodwin v. Elkins & Co., 730-F.2d 99 (3d Cir. 1984), cert.
denied, 105 S.Ct. 118 (1984). The only decisions they are bound
to follow in interpreting Pennsylvania law are the decisions of
the Pennsylvania Supreme Court. Id. As explained more fully
below, the Pennsylvania Supreme Court has refused to permit
contractors to recover against school districts in those instances
where base contract work or modifications have not been
formally approved in advance by school boards.

10

In short, Acmat has not been denied any procedural due
process rights under the terms of its contracts. Having freely
agreed to the provisions in its contracts and having offered
absolutely no proper evidence under Rule 56 of the Federal
Rules of Civil Procedure at the time the School District filed its
Motion for Summary Judgment, that the costs figures deter-
mined by the School District (and later approved by the court)
were improper, Acmat has absolutely no basis to contend its
procedural due process rights have been abridged.

B. The District Court Correctly Interpreted The Contract
Documents.

Acmat next argues that the District Court incorrectly
interpreted the “differing site conditions” provision in the
asbestos-removal contracts between Acmat and the School Dis-
trict. Once again, Acmat is merely asking this Court to serve as
the final arbiter of certain contract provisions which are to be

interpreted under Pennsylvania law. This issue does not provide
even remotely a “special and important” reason for this Court to
review this case on a Writ of Certiorari.

Moreover, Acmat’s argument is simply incorrect. Acmat’s
attempt to recover under the differing site conditions clause fails
for three reasons. First, the final sentence of Paragraph 14(c) of
the contracts provides that any increase or decrease of cost shall
be adjusted in the manner provided in the contract for adjust-
ment as to change. (App. E at 91a). This provision clearly relates
back to the provision requiring School Board approval for
contract modifications. Second, Acmat relies incorrectly upon
the case of Teodori v. Penn Hill School Dist. Auth., 413 Pa. 127,
196 A.2d 306 (1964), for the proposition that a differing site
condition clause is not modified by a “changes and alterations”
clause requiring formal approval of all contract changes. Teodori
involved a dispute as to whether a “changes and alterations
section requiring a written order or differing provisions clause”
governed the dispute. Id. The case did not involve a provision
present in the contracts between Acmat and the School District
relating to Board approval of changes to the contract or contract

eR a ee et ne ee ee ee Ee Le Ee eT ec a

Said

Pee ee Te Pee a ee ne eed

SA Sn EN ely pg AF ON LMS ge Pa aS Ud ths

ll

price. Further, the contract language in Teodori is materially
different from the contract language in the present case. In
Teodori, the parties followed the contractually mandated steps.
Here, Acmat was required to provide proper notice to the
School District of the alleged differing conditions pursuant to
Paragraph 14(c). If that had been done, the School District was
to investigate, and if it found materially differing conditions, it
was to make changes in the drawings and/or specifications as it
found necessary. Even if Acmat had gotten to the point where
change in drawings and specifications was necessary, it required
Board approval under Paragraph 14(a). Paragraph 14(a) expressly
provides that the School District may, subject to Board ap-
proval, make changes in the drawings and/or specifications in
the contract.

Furthermore, the court in Teodori specifically found that
the differing conditions included work in the original contract,
and no physical changes or alterations in the contract documents
were necessary. 413 Pa. at 132-33, 196 A.2d at 309. By contrast,
Acmat sought payment in this action for extra work that it
contended was not within the provisions of its original contracts.

Third, Acmat cannot recover under the “differing condi-
tions” clause is that it failed to conduct an inspection of the
building site prior to submitting its bid to determine the full
scope of the work at the project. Acmat expressly agreed in its
contract that it was responsible for inspecting the site and
acknowledged it would be responsible for all charges and costs
resulting from its failure to verify the conditions at the site.

6. In moving for summary judgment, the School District presented
extensive evidence concerning Acmat's failure to inspect the building site
before it submitted its bids. The School District, for example, submitted
deposition testimony from Acmat’s own job foteman that the extent of
overspray at the Rush School was readily apparent as soon as Acmat began
moving the ceiling tiles on the first floor. The School District also submitted
deposition testimony that Acmat typically performs an inspection before
submitting its bids for asbestos removal contracts, and that these inspections
include removal of ceiling tiles. In response, Acmat merely submitted an
affidavit which was not based on personal knowledge and did not include any
statement that Acmat was prevented by any action of ‘he School District from

making a proper inspection.

12

(App. E at 88a). Further, each contract provided that Acmat was
responsible for ascertaining the nature and location of the
working conditions which could affect the work, and that any
failure to do so would not relieve Acmat from the “responsibility
for successfully performing the work without additional expense
to the School District.” (Id., emphasis added). Under Pennsy]-
vania law, once a public contractor assumes responsibility for
being aware of the conditions it will encounter on the site, its
duty cannot be excused simply because its visual inspection was
inadequate. Commw. v. Mitchell’s Structural Steel Painting
Co., 18 Pa. Commw. 591, 336 A.2d 913 (1975).

The Pennsylvania Supreme Court expressly rejected the
argument Acmat now makes in Nether Providence Twp. School
Auth. v. Thomas M. Durkin & Sons, Inc., 505 Pa. 42, 476 A.2d
904 (1984). In Durkin, a school authority entered into an
agreement with a contractor to construct a new high school for a
fixed price. After construction began, the contractor noticed
discrepancies between the site plan topography contour lines
and the actual topographical conditions. As a result, the contrac-
tor was required to clear additional ground at the job site.

Before the job was completed, the parties disputed who
would bear the cost of the additional work which had to be
performed. Like Acmat, the contractor in Durkin was obligated
to examine the site, ascertain the nature and location of the work
and the general local conditions which would affect the work or
cost thereof. Id., at 46, 476 A.2d at 906. The contractor sought
to recover for the extra work due to actual site conditions which
differed from the contract documents and site plan provided by
the School District. The Court denied the claim since the School
Board had never approved the extra work.

The District Court here properly rejected Acmat’s attempt
to impose the cost of differing site conditions on the School
District due to Acmat’s failure to inspect the building site before
it submitted its bids. The District Court stated that Acmat's
failure to “ascertain what was entailed in performing the con-
tracted work could not be visited upon the School District but

‘ill

eer an

— “in Athen sth, lth
.

13

would be the contractor’s responsibility for successfully perform-
ing ... without additional expense to the School District.”
(App. C at 8a). The court concluded that:

[tlo permit a contractor to claim belatedly it could not
discover the scope of the work through a pre-bid inspec-
tion, and without more, to collect for work not approved as
an extra, would nullify the contract provisions controlling
bidding and performance and undermine the fiscal author-
ity and responsibility of the public contracting body.

(Id.). The District Court’s reasoning is entirely consistent with
the holding and spirit of the Pennsylvania Supreme Court in
Durkin, which explained, “[w]e have always rigidly imposed
strict standards on contractors who deal with public bodies to
prevent the unwarranted plundering of public funds. . . .” 505
Pa. at 48-49, 476 A.2d at 907.

Acmat’s reliance upon the decisions in United States v.
Spearin, 248 U.S. 132, 39 S.Ct. 59, 63 L.Ed. 166 (1918) and
United Contractors v. United States, 368 F.2d 585 (Ct. Cl. 1966)
is misplaced. Neither of these cases involves interpretations of

Pennsylvania law and its strict requirements concerning Board
approval in advance of all contract work or modifications.

C. The District Court Properly Entered Summary Judgment
on Acmat’s Breach of Contract Claims

The District Court properly granted the School District's
summary judgment motion on Acmat’s breach of contract
claims. Relying upon the Pennsylvania Supreme Court's deci-
sion in Durkin, the District Court held that Acmat had failed to
obtain the necessary approval from the School Board for its
claims for alleged extra work, as required under the provisions of
the Pennsylvania Public School Code and the provisions of its
contracts with the School District. Well after the entry of
summary judgment on behalf of the School District, Acmat
argued for the first time that certain claims were beyond the
scope of its contracts with the School District and were,
therefore, entitled to adjudication under common law princi-
ples. (R.A. 88). Specifically, Acmat contended it had performed

14

“protest work”, which was somehow separately compensible as
a breach of contract, the requirement of Board approval not-
withstanding. This issue was raised for the first time by Acmat in
its untimely motion for reargument.’ As the School District has
pointed out, Acmat was not permitted to raise these claims
belatedly in an effort to set aside the entry of summary
judgment. Further, Acmat is prohibited from recovering for
“protest work” because it continued to perform its contract
without obtaining School Board approval. See Dick Corp. v.
State Public School Bldg. Auth., 27 Pa. Commw. 498, 365 A.2d
663 (1976) (rather than proceeding with extra work without
written authorization, contractor may refuse to perform it until
it receives the contractually required written authorization).

D. The District Court Did Not Decide Improperly Disputed
Issues of Material Fact.

Acmat takes issue with various legal and factual findings by
the District Court at the time it ruled upon the School District's
Motion for Summary Judgment. Acmat believes, for example,
that the District Court should have characterized certain work as
base contract work rather than extra work. Acmat also believes
there were disputed issues of fact as to whether or not Acmat
conducted a reasonable pre-bid site inspection.

Once again, these efforts to reargue the evidence do not
even remotely qualify as “special and important reasons” to
require the issuance of a Writ of Certiorari. Furthermore,
Acmat is simply incorrect. Acmat does not point to even a single
example of how the District Court improperly determined that
certain work was base contract work, as opposed to “extra work.”
Acmat’s second argument, that there were disputed issues of
material fact as to the adequacy of Acmat’s pre-bid inspection, is
equally unfounded. As the School District has previously
pointed out, Acmat failed to submit any proper evidence when
the District Court decided the Motion for Summary Judgment

7. Local Rule 20(g) of the Rules of the United States District Court for
the Eastern District of Pennsylvania requires that a motion for reargument or
reconsideration be filed within ten days of the order or decree concerned.

—— ee el

15

to establish it conducted an adequate pre-bid inspection. It was
not until many months after the Motion for Summary Judgment
was decided that Acmat, in its motion for reargument, at-
tempted to submit evidence for the first time concerning the
adequacy of its pre-bid inspection. This evidence was properly
disregarded by the District Court, since it could and should
have been submitted by Acmat at the time it opposed the School
District's original Motion for Summary Judgment.

In short, Acmat’s arguments concerning disputed issues of
material fact provide no compelling basis for a Writ of Certiorari
and, furthermore, were never properly before the District
Court.

E. The District Court Properly Dismissed Acmat’s Claims for
Delay Damages.

Acmat agreed in each of its contracts with the School
District that it would not seek to recover damages if it were
delayed in concluding its work under the three asbestos removal
contracts.* This clause prohibits Acmat from seeking damages
from the School District even if it was delayed by acts of the
employees or agents of the School District. This is merely one
more instance where Acmat is asking this Court to interpret
contractual issues under Pennsylvania law.

Contract provisions which prohibit damages for delay are
“now universally accepted as valid.” F.D. Rich Co. v. Wilming-
ton Housing Authority, 392 F.2d 841, 843 (3d Cir. 1968). Acmat,
however, now claims the School District caused delays by

8. Each of Anmat’s equecments with the Scheel Distuict contains the

following delay damages provision
eee ie leah ba caiehilban tthe ih be iaeaen of

resulting from any of the aforesaid causes. (App. E at 92a, emphasis
added).

16

interfering with the prosecution of its work. This is simply
another instance where Acmat is now making a conclusory
argument which was not properly supported by affidavit or other
competent evidence at the time the District Court decided the
School District’s motion. Acmat presented no competent evi-
dence to suggest, much less prove, that the School District had
deliberately delayed Acmat in the prosecution of its work.
Under the circumstances, the District Court properly entered
judgment in favor of the School District on Acmat’s claim for

delay damages.

F. Based Upon The Jurors’ Answers To Special Interrogato-
ries, The District Court Properly Entered Judgment For
The School District On Acmat’s Claim Fer Contract Retain-

The School District retained contract balances from Acmat
because Acmat failed to provide copies of dump tickets evidenc-
ing the proper disposal of asbestos-contaminated materials. The
contracts between Acmat and the School District provided in no
less than three different sections that Acmat had to dispose of
asbestos-contaminated materials removed from the schools in an
approved landfill certified to receive hazardous waste, obtain
signed dump tickets from the landfill and submit the dump
tickets with its final payment requisition.

The School District produced overwhelming evidence at
the counterclaim trial that the dump tickets had not been
provided to it by Acmat. The jurors, by answers to special
interrogatories, concluded that Acmat did not prove that it
supplied to the School District all the asbestos site dump tickets
in compliance with the contract specifications and conditions.

The District Court, therefore, entered judgment against Acmat
and in favor of the School District on Acmat’s claim for the

contract balances.

Acmat now contends that the District Court erred by not
instructing the jury that the failure to provide dump tickets was
an immaterial breach of the contracts. This argument is without
merit for several reasons. First, it is self-evident that proof of

nti sa ee ee

School District on Acmat’s claim for contract retainages.

contractaal eiee when:the seuetremante of @ publie statete
have not been satisfied. See Commw. v. Seagram's Distiller’s
Corp., 379 Pa. 411, 108 A.2d 184 (1954) (rejecting contractor's
quantum meruit claim where contractor failed to comply with
statutory requirements); Appeal of Sykesville Boro., 91 Pa.
Super. 335 (1927) (rejecting contractor's quasi-contractual claims
against school district where required approval was not
obtained).

The decision in Derry Twp. School Dist. v. Suburban
Roofing Co., 102 Pa. Commonw. 54, 517 A.2d 225 (1986) does
not relieve Acmat of its obligation to obtain prior Board ap-
proval. Acmat seeks to recover for extra work, for which it never
obtained Board approval. Derry did not involve a claim for extra
work. The expansive reading of Derry advanced by Acmat would

9. Not surprisingly, Acmat did not include its points for charge in either
its appendix to its Appeal to the United States Court of Appeals for the Third
Circuit or its appendix to its Petition for a Writ of Certiorari.

18

make Derry wholly inconsistent with the decision of the Penn-
sylvania Supreme Court in Durkin, supra, since many claims for
extra work invariably involve a dispute between the contractor
and the owner over each party's responsibilities under the

Derry did not apply to the facts of this case.!®

CONCLUSION

For all of the foregoing reasons, it is respectfully requested
that Acmat Corporation’s Petition for a Writ of Certiorari be
denied.

Respectfully submitted,

André L. Dennis
John J. Murphy, III
STRADLEY, RONON, STEVENS
& YOUNG
2600 One Commerce Square
Philadelphia, Pennsylvania 19103
(215) 564-8034
Counsel of Record and
Attomeys for Respondent
Dated: October 22, 1990

10. In fact, the Commonwealth Court in Derry reaffirmed that Durkin

prohibited a contractor from recovering compensation for extra work per-
formed under a change order which was never approved by the School Board

in accordance with contract requirements.

EEO —— ‘a

RESPONDENT'S
APPENDIX

“a
a
=)

>

R.A.1

IN THE UNITED STATES DISTRICT COURT
FOR THE EASTERN DISTRICT OF PENNSYLVANIA

ACMAT CORPORATION : CIVIL ACTION
Plaintiff:

vo.

SCHOOL DISTRICT OF PHILADELPHIA :
Defendant : No. 85-7067

MOTION FOR SUMMARY JUDGMENT OF THE
SCHOOL DISTRICT OF PHILADELPHIA

The School District of Philadelphia hereby moves the Court
pursuant to Rule 56 of the Federal Rules of Civil Procedure for
the entry of judgment on its behalf with respect to each and
every claim asserted by Acmat Corporation in its Amended
Complaint. The School District of Philadelphia is entitled to the
entry of judgment on its behalf because there is no genuine issue
as to any material fact and because the School District is entitled
to judgment as a matter of law under the provisions of the
Pennsylvania Public School Code and under the provisions of its
contracts with Acmat Corporation. The School District relies
upon the memorandum of law which accompanies this motion as
well as the attached Affidavit of Herman Mattleman, Esquire,
President of the Board of Education of the School District of
Philadelphia.

André L’ Dennis

John J. Murphy, III

Paul D. Shaffner

STRADLEY, RONON, STEVENS
& YOUNG

2600 One Commerce Square

Philadelphia, PA 19103-7098

(215) 564-8000

Attorneys for Defendant
The School District of Philadelphia

R.A.2

MEMORANDUM OF LAW OF THE SCHOOL DISTRICT
OF PHILADELPHIA IN SUPPORT OF MOTION FOR
SUMMARY JUDGMENT

IN THE UNITED STATES DISTRICT COURT
FOR THE EASTERN DISTRICT OF PENNSYLVANIA

ACMAT CORPORATION ' : CIVIL ACTION
Plaintiff :

oD.

SCHOOL DISTRICT OF PHILADELPHIA :
Defendant : NO. 85-7067

MEMORANDUM OF LAW OF THE SCHOOL DISTRICT
OF PHILADELPHIA IN SUPPORT OF MOTION FOR
SUMMARY JUDGMENT

I. INTRODUCTION

Acmat Corporation (“Acmat”) has filed claims against the
School District of Philadelphia (the “School District”) seeking
additional compensation under three separate written agree-
ments for the removal of asbestos at Fairhill Elementary School,
Lincoln Senior High School and Rush Middle Schooi in Phila-
delphia, Pennsylvania. The School District not only denies that
Acmat is entitled to any additional compensation but insists it is
entitled to substantial credits for work Acmat did not have to
perform under the three agreements. In addition, the School
District has asserted a counterclaim against Acmat and seeks in
excess of $400,000 due to Acmat’s failure to complete the
contracts within the time required in the agreements and to
complete all labor and provide all materials called for in each of
the agreements.

The School District now moves for summary judgment on
its behalf pursuant to Rule 56 of the Federal Rules of Civil
Procedure because there is no genuine issue as to any material
fact and because the School District is entitled to judgment in its

,

R.A.3

favor as a matter of law under the terms of its contracts with
Acmat and the provisions of the Pennsylvania Public School
Code.

The terms of Acmat’s three contracts with the School
District are not in dispute.! The first of the three contracts is
B-137 (“Fairhill Contract”) under date of April 16, 1984 for the
fixed price of $446,000. (Exhibit No. 1) The School District, with
School Board approval, and Acmat subsequently agreed on June
26, 1984 to a price change on the Fairhill Contract in the amount
of $18,000 and a change in specifications known as the “Work
Practices Supplement”. (Exhibit No. 2). The School District
agreed to no other change in price on the Fairhill Contract.
(Mattleman Aff. at 993-4).

The second contract is B-163 (“Lincoln Contract”) under
date of June 11, 1984, in the fixed amount of $223,000. (Exhibit
No. 3) The provisions in the Work Practices Supplement were a
part of the specifications for the Lincoln Contract. No change
order was issued by the School District with respect to this
contract. Id. |

The third contract is B-216 (“Rush Contract”) under date of
June 11, 1984, relating to the second floor of the Rush School in
the fixed amount of $595,000. (Exhibit No. 4) Provisions of the
Work Practices Supplement were also part of the specifications
for the Rush Contract. Under date of October 30, 1984, the
School District and Acmat entered into a Supplemental Agree-
ment B-43 to the Rush Contract. (Exhibit No. 5) The Supple-
mental Agreement, with School Board approval, added the first
floor of the Rush School to Acmat’s contract for an additional
$656,000. On April 29, 1985, the School District, with School
Board approval, and Acmat agreed to Change Order No. 1 in the
amount of $63,282.89 for extra labor, material and equipment
necessary to wet wipe items in closets and cabinets required
because of the presence of asbestos. (Exhibit No. 6) No other

1. Copies of each contract, supplemental agreement and change order
have been separately bound and submitted to this Court previously as Exhibits
of the School District's Response to the Statement of Claim of Acmat Pursuant
to Order of April 23, 1986. The exhibit numbers used in this memorandum
conform to the exhibit numbers in that submission.

R.A.4

change order was issued by the School District with respect to
this contract. (Mattleman Aff. at {__).

‘Acmat agreed in each of these contracts with the School
District that it would be solely responsible for “ascertaining the
nature and location of the work and the general and local
conditions which can affect the work or the cost thereof.”
(Fairhill Contract, General Conditions at {9(a); Lincoln Con-
tract, General Conditions at {7(a); Rush Contract, General
Conditions at {7(a)). Acmat further acknowledged that any
failure on its part to ascertain the effect of its work under the
contracts would not relieve it from “responsibility for success-
fully performing the work without additional expense to the
School District.” Id. (Emphasis added).

Acmat further agreed it would not be entitled to recover
delay damages from the School District under any circum-
stances, including those instances where such delays are caused
by acts or neglect of the School District. (Fairhill Contract,
General Conditions at 417(c); Lincoln Contract, General Con-
ditions at 915(c); Rush Contract, General Conditions at 415(c)).

The asbestos removal contracts further provide that the
School District may, subject to the approval of the School
Board, make changes in the contracts. Each of the agreements,
however, expressly cautions that verbal instructions given by
any officer, agent or employee of the Board which depart from
the contract documents shall not be binding upon the Board.
(Fairhill Contract, General Conditions at 416; Lincoln Contract,
General Conditions at 414; Rush Contract, General Conditions
at 14).

The total fixed price for all three contracts was
$2,001,283.00. Acmat, however, now seeks somewhere be-
tween $5 Million and $6 Million in damages from the School
District for alleged contract extras and modifications.?

2. Even at this late stage in the litigation, the precise amount of Acmat's
claimed damages is unknown. Acmat has yet to provide either the School
District or the Court with a final calculation of the damages it claims it incurred
in connection with its work at the three schools. Acmat has attached to its
pretrial memorandum a portion of a report by Kellogg Corporation which
purports to set forth a “preliminary estimate of damages” incurred by Acmat on

R.A.5

The School District relies upon seven basic legal grounds in
support of this motion:

(1) All of Acmat’s claims for additional work must be
rejected since Acmat failed to obtain the approval of the
School Board for this alleged extra work as required under
its contracts with the School District and under the provi-
sions of the Pennsylvania Public School Code;

(2) Acmat’s contracts with the School District and the
case law provide that verbal requests by School District
representatives shall not be binding upon the Board.

(3) Acmat is prohibited from recovering against the
School District under any quasi-contractual theory of re-
covery since it has failed to comply with the provisions of
the Pennsylvania School Code and its contracts with the
School District;

(4) Acmat'’s fraud claim against the School District must
be dismissed as a matter of law since Acmat is attempting to
superimpose a tort theory on what is essentially a contrac-
tual cause of action and because Acmat has failed to
establish that it reasonably relied upon any alleged misrep-
resentations by representatives of the School District;

(5) Acmat is precluded from seeking to recover delay
damages against the School District under the terms of its
contracts even in those instances where such delays may be
attributable to acts or neglect on the part of the School
District;

The School District of Philadelphia is a separate and
independent School District administered, operated and man-
aged by the Board of Education in accordance with state and
local laws. The Pennsylvania Public School Code of 1949

the three projects in the amount of $5,387,670. Following the submission of
this motion, the School District will seek a conference with the Court or will
file a motion seeking to compel Acmat to respond to the School District's
discovery requests and provide it with a final accounting of the damages it
claims it is entitled to under the three contracts.

R.A.6

provides, in pertinent part, that: “[t]he affirmative vote of a
majority of all the members of the Board of School Directors in
every school district, duly recorded, showing how each member
voted, shall be required in order to take action on the following
subjects”:

. .. Entering into contracts of any kind, including contracts
for the purchase of fuel or any supplies, where the amount
involved exceeds One Hundred Dollars ($100.00) ....
Failure to comply with the provisions of this section shall
render such acts of the board of school directors void and
unenforceable.

24 Pa. Stat. Ann. §5-508. Each of Acmat’s contracts with the
School District provide that they are entered into subject to the
provisions of the Pennsylvania School Code of 1949.

The plaintiff bears the burden of establishing both the
validity of the underlying contract as well as approval of the
contract by a majority of Board members. Rudolph v. Albert
Gallatin School District, 60 Pa. Commw. 456, 431 A.2d 1171
(1981). Without a proper resolution, an action against the School
District is precluded.

The Pennsylvania courts have insisted that contractors
comply with the requirements of the School Code. In Framlau,
supra., the Court declined to enforce settlement terms agreed
to by the president of the Philadelphia School Board and its
attorney because the School Board declined to approve the
Agreement as required under Section 5-508 of the School Code.
Despite the apparent harshness of the result, the Court rea-
soned:

One who contracts with the School District must, at his own
peril, know the extent of the power of the School District's
officers in making the contract . . . [and] know that the
Board of Directors may repudiate any contract provisiun to
which it is assented. . . It is the general rule that where
formal action is necessary to bind the School District, such
a requirement must be met in order to predicate liability.
In the absence of a compliance with the applicable statutory

R.A.7

provisions pertaining to the motive by which a board of
school directors may make a contract, no enforceable
contract will result.

Id. at 627-28.

Modifications to a school district contract likewise require
approval by a majority of Board members. Matevish v. Ramey
Borough School District, 167 Pa. Super. 313, 74 A.2d 797
(1950). In Matevish, the Court rejected a claim by a transpor-
tation company that the secretary of a School Board had orally
modified the requirements of a contract for the busing of
students. The Court concluded that modification of the contract
required the approval of the School Board in compliance with
the same Public School Code provisions which applied to the
formation of the original contract. Absent compliance with the
provisions of the School Code, the Court concluded that no
liability could be imposed upon the School District for any
alleged. modifications to the contract.

2. Contract Requirements.

Acmat’s contracts with the School District, like the School
Code, provide that any modifications to the contract must be
approved by the School Board:

[t]he School District may, . . . , subject to approval of the
Boerd . . . make changes in the drawings and/or specifica-
tions of this contract if within its general scope, such
changes to be made in writing. If such changes cause an
increase or decrease in the contractor's cost of, or time
required for, performance of the contract, an equitable
adjustment shall be made and the contractor notified in
writing accordingly, any such change in the contract price
being subject to the approval of the Board.

General Condition 916(a) (emphasis added). Each contract also
expressly cautions that “[v]erbal instruction given by any of the
officers, agents, or employees of the Board which depart from
the contract document shall not be binding upon the Board.
General Condition $16(d). Thus, Acmat clearly agreed that: (1)

R.A.8

any modifications to the contract were required to be in writing;
(2) any modifications were subject to the approval of the Board;
(3) any change in the contract price was subject to the approval
of the Board; and (4) verbal instructions which departed from the
contract document were not binding upon the Board.

It is well recognized under Pennsylvania Law that strict
compliance with the contractual provisions in a public service
contract is necessary to support a claim under a contract for extra
work or material. Nether Providence Township School Authority
v. Thomas M. Durkin & Sons, Inc., 505 Pa. 42, 476 A.2d 904
(1984). In Nether Providence, a School Authority entered into an
agreement with a contractor to construct a new high school for
the Authority for a fixed price. After construction began, the
contractor noticed discrepancies between the site plan topogra-
phy contour lines and the actual topographical conditions. As a
result, the contractor was required to clear additional ground at
the job site.

Before the job was completed, the parties disputed who
would bear the cost of the additional work which had to be
performed. The School Authority’s President authorized the
School Authority's secretary to write to the contractor to ac-
knowledge the dispute and recommend that the contractor
continue the work with resolution of the disagreement at a later
time. After the job was completed, the contractor submitted a
claim to the School Authority for the extra work claiming that he
had been induced to perform the work by the letter authorized
by the School Authority’s President. When the School Authority
rejected the contractor's claim, the contractor brought an action
against the School Authority seeking compensation for the extra
work.

Recognizing the long line of Pennsylvania cases requiring
strict adherence to the provisions of public contracts, the
Pennsylvania Supreme Court rejected these claims for addi-
tional compensation. The Court noted that the contract obli-
gated the contractor to determine the amount of cut and fill
needed to complete the job and to inspect the work site in order
to verify conditions and assess the work which was required to
be performed. The contract also provided that “no change in the

| —

R.A.9

contract shall be made without the written approval of the
Board.” The Court, therefore, declined to allow the contractor
to recover since written approval of the Board was never
obtained. In so concluding, the Court stated:

[w]e have always rigidly imposed strict standards on
contractors who deal with public bodies to prevent the
unwarranted plundering of public funds, to uphold the
integrity of the bidding process, and we see no reason to
change our long-established precedents today. We reiterate
that public agreements can be altered only by the same
formal municipal action that created them or express rati-
fication by resolution of the public body.

The Court in Nether Providence rejected the contractor's
claim that the School Authority had waived the requirement that
changes to the contract needed the approval of the Board. The
Court held that a provision in a public contract relating to the
manner in which changes to the contract can be made can be
waived only by formal written action of the Board or by express
ratification of the extra work by resolution of the Board. The
Court, therefore, held that a letter prepared by the School
District’s president and secretary was not the act of the full
board and that the formal written action vequirement for waiver
was not satisfied. The Court also observed that the Board had
never adopted a resolution ratifying the extra work.

The Supreme Court's decision in Nether Providence is
consistent with a long line of Pennsylvania cases which require
strict compliance with contractual provisions regarding extra
work in public contracts. In Morgan v. Johnstown, 306 Pa. 456,
160 A.696 (1931), written orders for the city engineer for alleged
extra work were required by the terms of the contract. The
Court held that, in the absence of a written order from the city
engineer, the contractor could not recover for alleged extra
work. Similarly, in Montgomery v. Philadelphia, 391 Pa. 607,
139 A.2d 347 (1958) the contract required the contractor to
obtain a written order from the city engineer before proceeding
with extra work. The Corrt refused to allow any recovery for
additional work absent the required approval and explained that

ee eeeeeEOOeeoe

R.A.10
authorization by a subordinate of the designated official would

Building
Authority, 27 Pa. Commw. 498 (1 rather than proceeding
wth aie wah then ealaneaeieaiee es
refuse to perform until it receives Sy seminar + a

B. Oral or Written Directives of School District Represen-
tatives Do Not Constitute School Board Approval.

4 Nor can Acmat point to a single instance where the School Board, by
formal resolution, waived adherence to the provision in its contracts requiring

| ' ones ,

R.A.11

this argument which have already been discussed at some length
above: (1) The School Code requires formal Board approval of
any contracts or modifications to contracts; (2) Acmat’s contracts
with the School District provide that all modifications to the
contract must be approved by the School Board; and (3) Acmat’s
contracts further provide that any verbal instructions by repre-
sentatives of the School District shall not be binding upon the

The Pennsylvania Courts have consistently rejected efforts
by contractors to circumvent the statutory or contractual re-
quirements on the basis of alleged oral or written directives. In
Morgan v. Johnstown, 306 Pa. 456, 160 A.696 (1931), the Court
held a contractor could not recover for extra work on the basis
that members of City Council had orally directed extra work be
done when the contract required a written order of the city
engineer. Similarly, in Montgomery v. Philadelphia, 301 Pa.
591, 139 A.2d 347 (1958), the Court held that when written
orders of the city engineer for extra work were required, the
contractor could not recover on the basis of authorization by
subordinates of the city engineer. Authorization for extra work
must be made in strict compliance with the contract provisions
or the contractor is barred from pursuing claims for additional
work.

"Individuals who contract with public bodies governed by
public statutes make agreements outside the parameters of the
statute at their own risk. Commonwealth v. Seagram Distillers
Corp., 378 Pa 411, 109 A.2d 184 (1954). The Court in
refused to enforce an oral agreement between Seagram and the
Board. The Board was required by statute to approve any such
contracts. The Court stated that it was the obligation of Seagram
to determine the extent of the authority of the Director of
Operations to bind the Board by an oral agreement since
“[p]ersons contracting with a governmental agency must, at
their peril, know the extent of the power of its officers making
the contract.” Id. at 417, 109 A.2d at 186. The Court held that
Seagram's oral agreement with the Board’s subordinates did not
constitute formal action by the Board and was, therefore,

invalid. See also Vona v. Redevelopment Authority of Delaware

esteem

R.A. 12

County, 109 Pa. Commw. 156, 530 A.2d 1018 (1087) (Plaintiff
acted at his peril when he performed additional work on the
basis of representations made by the Authority's counsel be-
cause counsel lacked proper authorization to enter into the
agreement).

C. Aemat Is Prohibited From Recovering Against The
School District Under Any Quasi-Contracrural Theory

Of Recovery.

In addition to its contract claims, Acmat has asserted
various quasi-contractual theories in ‘ts Amended Complaint.
Count VI sets forth a theory based upon quantum meruit, Count
VII sets forth a claim for unjust enrichment and Count XI sets
forth a claim based upon promissory estoppel.

By asserting these equitable claims, Aemat seeks to render
the requirement of approval in the School Code mean-
ingless and circumvent the requirements of its asbestos removal
contracts. The Pennsylvania courts have consistently rejected
quasi-contractual claims when the requirements of a public
statute have not been satisfied. In Commonwealth v. Seagrams
Distillers Corp., supra., the Court refused to permit Seagrams

be no quasi-contractual recovery. The Court further held that
“the doctrine of quasi-contract does not extend to benefits which
by there very nature cannot be surrendered, and the retention
of which is therefore involuntary.” Id. at 410, 100 A.Qd at 187.
The Court observed that where benefits conferred upon a public
body pursuant to an invalid contract, by their very nature,
cannot be surrendered, no implied obligation arises on the part
of the municipality to make compensatory payment. As a result,
Seagrams could not recover under any quasi-contractual theory
of recovery.

—————————————————————aaaaEEEE——————

District, 170 Pa. Super. 477, 87 A.2d 98 (1952) (Unless statutory
provisions are observed there could be no enforceable contract
entered into by a school board nor can a plaintiff recover on the
basis of quantum merwit).

Furthermore, a party may not recover on a quasi-

to comply with contractual provisions governing modifications to
the contract or extra work. In Montgomery v. Philadelphia, the
Court explained the rationale for this rule as follows:

Where a contractor has attempted to recover for either
additional work or work necessitated by a change in the
plans and specifications, all of the cases in this jurisdiction
have denied recovery where the contract prescribed a
procedure for the oval of such additional work,
and such edure has not been followed. The
reasons for the requirement of strict adherence to the
contractual provisions are obvious. Municipal construction
contracts, whose terms are in a large part governed by
statute, are designed to provide, from the initial bidding to

R.A.14

final completion, for as many reasonably foreseeable con-
tingencies as practicable, to forestall any possible collusion
between city officials and contractors and to protect public
funds against wanton dissipation.

391 Pa. at 616, 139 A.2d at 350. The court in Montgomery,
accordingly, denied any recovery, contractual or otherwise by
the part of the contractor.

Acmat’s auantum meruit theory is clearly barred because
Acmat failed to proceed in accordance with the requirements of
the School Code on its contracts with the School District.
Likewise, Acmat’s claim for unjust enrichment is barred since it

Acunat’s cleien for enjust entidiuant te leo bemed clace eny
“benefit” conferred on the School District, by its very nature,

R.A.15

D. Acmat May Not Recover Against the School District on a
Theory of Equitable Estoppel.

The provisions of the School Code and its contracts not-
withstanding, Acmat suggests it may recover against the School
District in the absence of School Board approval under a theory
of equitable estoppel. Acmat directs the Court's attention to the
case of Derry Township School District v. Suburban Roofing
Co., Inc., 102 Pa. Commw. 54, 517 A.2d 225 (1986). Acmat’s
reliance upon Derry is misplaced. If anything, Derry merely
re-affirms the commitment to the principle that a contractor
cannot recover for alleged extra work absent compliance with
the School Code and contractual requirements.

The School District in Derry awarded a contract to defen-
dant to replace the roof on the School District's high school. The
contract required the contractor to replace concrete planks on a
unit price basis. The School District's inspector was to make the
determination as to which planks had to be replaced. Initially,
the School District's inspector determined that approximately
400 planks needed to be replaced and the contractor ordered
sufficient replacement planks. However, a new school district
inspector subsequently determined that a number of the planks
did not have to be replaced thereby leaving the contractor with
an excess supply of custom-made planks which were useful only
to the School District on its high school. The contractor sought
to recover against the School District for its out-of-pocket costs
for the unused planks.

The Commonwealth Court in Derry re-affirmed that the
Pennsylvania Supreme Court's decision in Nether Providence
prohibited a contractor from recovering compensation for extra
work performed under a change order which was never ap-
proved by the School Board in accordance with contract require-
ments. The court in Derry, however, noted that the builder was
not seeking to recover for the increased costs of extra work due
to a school district's oral changes to the contract. Rather, the
court emphasized that the builder was claiming compensation
for its reasonable costs “incurred in reliance upon the District's
interpretation of the Contractor's performance under the terms

R.A.16

of the contract, which interpretation thé District later altered to
the Contractor's detriment.” 517 A.2d at 229.

The Derry decision has no application to the facts in this
case. Acmat was required under each of its contracts with the
School District to remove asbestos from three Philadelphia
public schools. Like the plaintiff in Nether Providence, Acmat
now seeks to recover for extra work for which it never obtained
board approval. This is not a case where the School District
initially interpreted the contracts one way and later another and
where Acmat had to “special order” materials which would be
useless to Acmat if the School District later determined that less
work and materials would be involved. Nether Providence
remains the law in Pennsylvania and Acmat’s claims are, there-
fore, barred due to its failure to obtain proper board approval for
work it now claims is extra to its contracts.

E. Acmat Cannot Recover on a Fraud Theory Against the
School District.

Acmat purports to state a fraud claim against the School
District in Count VIII of the Amended Complaint. Acmat
alleges, inter alia, (1) that the School District asked Acmat to
perform various modifications and work not called for in its
original contracts (Amended Complaint at $43), (2) that the
School District represented to Acmat that it would be paid for
this alleged extra work (Id. at 951), (3) that the School District
made these representations notwithstanding its belief that it was
not required to compensate Acmat for this work absent express
approval from the School Board (Id. at $44), (4) that the School
District, therefore, never had any intention to pay Acmat for this
alleged extra work (Id. at 945), and (5) that Acmat justifiably
relied upon these alleged misrepresentations to its detriment.
(Id. at 953.)

There are at least two major deficiencies in Acmat's fraud
claim, each of which requires its dismissal as a matter of law.
First and foremost, Acmat’s fraud count is nothing more than a
thinly veiled attempt to recast contract claims as an action for

fraud. A similar attempt to superimpose a tort theory of recovery

R.A.17

on what is essentially a contractual claim was rejected in the case
of Iron Mountain Security Storage Corp. v. American Specially
Foods, Inc., 457 F. Supp. 1158 (E.D.Pa. 1978).

The Court in Iron Mountain stated the distinction between
tort and contract as follows:

Tort actions lie for breaches of duties imposed by law
as a matter of social policy while contract actions lie for only
breaches of duties imposed by mutual consentual agree-
ments between particular individuals. in tort actions, dam-
ages are awarded to compensate the plaintiff for all loss
suffered by breach of the duty, whereas in contract actions,
damages are limited by the scope of the agreement it must
be forseeable at the time the agreement is made. If a
tort-feasor breaches a duty imposed by society, a monetary
levy beyond that which is compensatory may be imposed
against him to punish the wrongdoing and serve as a
deterrent. Such punitive damages are not assessed for
breach of mere contractual duties, however.

Id. at 1165.

The Pennsylvania Supreme Court has also stated that to
permit tort claims for garden variety breaches of contract actions
“would erode the usual rules of contractual recovery and inject
confusion into our well-settled forms of actions. Most courts
have been cautious about permitting tort recovery for contrac-
tual breaches and we are in full accord with its policy.” Glazer v.
Chandler, 414 Pa. 304, 308-09 (1964).

This principle was also recognized in the case of Argo
Welded Products, Inc. v. J.T. Reyerson Steel & Sons, Inc., 528
F. Supp. 583 (E.D.Pa. 1981). The plaintiff in Argo brought suit
against the defendants for providing steel which failed to meet
specifications set forth in plaintiffs purchase order. The plaintiff
pleaded separate counts under tort and contractual theories.
The court concluded that, under Pennsylvania law, the plaintiff s
tort count was insufficient. The court reasoned that any duties
which may have been breached as to the plaintiff were purely
contractual in nature. Tort recovery is permissible, however,
solely as recompense for breaches of social obligations. Since any

R.A.18

duty which may have breached extended only to the plaintiff,
the court held that the plaintiff could not recover for negligence.

Similarly, in this case, if there has been any breach of
obligation, it would be an obligation solely to Acmat and such a
breach would be purely contractual in nature. Any duties which
allegedly have been breached in this case were imposed solely
by a mutual agreement between the School District and Acmat.
Plaintiffs claim is contractual in nature and does not involve the
breach of duty imposed as a matter of social policy for which an
action in tort would lie. The genesis of this matter is the
underlying contracts and Acmat is not permitted to inject fraud
claims into a purely contractual dispute.

Furthermore, it is readily apparent as a matter of law that
Acmat cannot satisfy the necessary elements to support a fraud
claim. In order to recover on a fraud claim against the School
eee te eee
misrepresentation to Acmat; (2) that the
false; €¥) tisk Gas meiebepccsclionban coke oc coated Get: 10 that
the School District intended that Acmat rely on the misrepre-
sentation; (5) that Acmat justifiably relied on the misrepresen-
wt

Supp. 884, 894 (E.D.Pa. 1981), aff'd., 688 F.2d 820 (3rd Cir.
1982).

Acmat contends that it justifiably relied upon alleged
representations by School District representatives that it would
be paid for alleged extra work. If Acmat ever relied upon these
alleged misrepresentations, however, such reliance was wholly
at odds with the provisions in Acmat’s contract which carefully
set forth the procedures for the approval of extra work on the
projects.

As the School District has already pointed out, Acmat
expressly agreed in each of its contracts with the School District
that any changes to the contracts by the School District would be
subject to approval by the School Board. The contracts further
provide that verbal instructions given by any of the officers,
agents or employees of the Board which depart from the contract

R.A.19

documents, shall not be binding upon the Board. Finally, each
of Acmat’s contracts with the School District provide that the
contracts are entered into subject to the provisions of the Public
School Code of 1949 which provides that a School District may
not be held liable for a contractual obligation unless the plaintiff
can show that the contract was approved by formal resolution of
a majority School Board members.

Given these provisions and the requirements of the Public
School Code of which Acmat had actual or constructive know!-
edge, Acmat can hardly argue that it justifiably relied upon any
alleged oral or written representation by representatives of the
School District as to whether or not it would be paid for alleged
extra work. Acmat was well aware and expressly agreed that any
such representations by School District employees or represen-
tatives would not be binding upon the Board. The School
District, therefore, is entitled to the entry of judgment on its
behalf an Count VIII of the Amended Complaint as a matter of
law and in accordance with the provisions of its contracts with

F. Acmat May Not Recover Delay Damages Under its Con-
tracts with the School District.

Acmat agreed in each of its contracts with the School
District that it would not seek to recover damages from the
School District if it was delayed for any number of reasons in
completing its work under the thee asbestos removal contracts.
Each of Acmat’s agreements with the School District contains

the following delay damages provision:

If any contractor shall be delayed in the completion of
his work by reason of unforseeable causes beyond his
control and without his fault or negligence, including but
not restricted to, acts of Ged, acts or neglect of the School
District, acts or neglect of any other contractor, fires,
floods, epidemics, quarantine, restrictions, strikes, or
freight embargoes, the period hereinabove specified for
completion of his work may be extended by such time as
shall be fixed by the School District, but the contractor shall

R.A.20

not be entitled to any damages or compensation from the
School District on account of any delay or delays resulting

from any of the aforesaid causes.

(Fairhill Contract at 417(c); Lincoln Contract at 915(c); Rush
Contract at §15(c)). This clause prohibits Acmat from seeking
damages from the School District even if it is delayed by acts of
the employees or agents of the School District.

These contractual provisions notwithstanding, Acmat has
asserted multiple claims against the School District in which it
now seeks to recover damages for alleged delays it attributes to
the School District. These claims which are set forth in Acmat’s
Statement of Claim which has previously been submitted to the
Court, can be summarized as follows:

FAIRHILL SCHOOL

Item 6 — Acmat seeks in excess of $200,000 for alleged
delays due to late test reports, disruptions and acceleration
in the level of work, failure of the School District’s inspec-
tors to timely inspect additional cleaning and recleaning,
etc.

Item 7 — Acmat alleges it was delayed in completing its
work at the Fairhill School due to a lack of elevator service.

Item 11 — Acmat contends its productivity was reduced
and that its work on the Fairhill School was delayed by a
requirement of the School District that its employees wear
fullface respirators instead of half-face masks.

Item 12 — Acmat seeks to recover the costs it contends it
had to pay to its independent air monitoring contractor for
being at the Fairhill School longer than Acmat originally
scheduled.

Item 13 — Acmat seeks payment for what it characterizes as
extended home office overhead and the value of field
equipment for a period of two months.

R.A.21

LINCOLN HIGH SCHOOL

Item 4 — Acmat contends it lost productivity because of the
alleged failure by the School District’s air quality inspectors
to conduct inspections on a timely basis.

Item 5 — Acmat claims its work was disrupted by a work
stoppage order on or about October 20, 1984.

Item 6 — Once again, Acmat contends its productivity was
lowered by a requirement of the School District that its
employees wear full-face respirators instead of half-face
masks.

Item 8 — Acmat seeks to recover for delays due to alleged
delayed test results, disruptions and acceleration in the
level work, failure of the School District’s inspectors to
timely inspect the additional cleaning and recleaning, etc.

Item 11 — Once again, Acmat seeks payment for what it
characterizes as extended home office overhead and the
value of field equipment for a period of two months.

RUSH SCHOOL

Item 18— Acmat seeks to recover monetary damages for
alleged lost productivity and inefficient labor which it
claims resulted from lack of heat in the building. Acmat
contends loss of heat was caused by the School District's
failure to provide heat during the winter months.

Item 32 — Acmat seeks payment for what it characterizes as
extended home office overhead and the value of field
equipment for a period of ten months.

Each of the foregoing claims represents an effort by Acmat to
recover for delays it experienced in completing the three
asbestos removal contracts with the School District. The fact
that Acmat attributes some of these delays to the School District
is of no consequence. Acmat’s contracts expressly provide that
delay damages shall not be recoverable even in those instances
where delays are attributable to the acts or neglect of the School
District. The delay damages provisions could not be clearer and

R.A.22

Acmat must be precluded from now seeking to recover damages

it freely and unequivocally agreed to forego in its contracts with
the School District.

G. The School District is Entitled to Make the Final Determi-
nation as to Net Costs of Labor and Materials Under its
Contracts with Acmat.

The three asbestos removal contracts between Acmat and
the School District each provide that the School District may,
subject to approval by the School Board, make changes in the
asbestos removal contracts. The agreements further provide that
the contractor may, in certain limited circumstances, be com-
pensated on a labor and materials basis in connection with any
additional work performed under the contracts. However, in
each instance where the contractor performs work on a labor and
materials basis, the contracts provide that the School District
“will make the final determination as to net costs of labor and
materials.” (Fairhill Contract at $16(b); Lincoln Contract at
{14(b); Rush Contract at 414(b)).

Two requests by Acmat for additional compensation were
submitted to the School Board: the first request involved the
decontamination of school books, supplies and other materials at
the Rush School; the second related to the Work Practices
Supplement at the Fairhill School. The School Board considered
each of these requests and issued resolutions approving payment
of additional compensation to Acmat. Acmat now seeks money
damages for these items in an amount which exceeds the amount
expressly approved by the School Board. At the Rush School, for
example, the Board issued a change order in the amount of
$63,282.89 for the decontamination work performed by Acmat.
The Board determined this was the reasonable value of the work
performed by Acmat after spending in excess of three weeks
reviewing Acmat’s change order requests. Acmat, however,
disagrees with this determination and seeks an additional
$85,115.33 payment on this item. (Acmat Statement of Claim,
Rush School, Item 1).5 This portion of Acmat’s claim, however,

5. Acmat also seeks additional compensation in connection with the
$18,000 change order it agreed to in connection with the Work Practices

H. Acmat is Responsible for the Costs of Removing Asbestos
Overspray at the Rush School.

Acmat seeks in excess of $400,000 from the School District
because it contends it encountered more asbestos overspray at
the Rush School than it originally anticipated when it submitted
its bid to the School District. Acmat describes this work as
follows in its Statement of Claim:

ic nye pr oan goed ar ges shag amoaghe

ered extra because this area should not have had any
fireproofing whatsoever.

(Statement of Claim at p. 39). Eugene Lord, who served as
Acmat’s superintendent at the Rush School, has testified that
asbestos overspray typically extends from between twelve to
eighteen inches on either side of the structural steel beam.
(Lord Dep. at pp. 231-32).° Acmat does not contend that it is
entitled for reimbursement for the removal of all overspray;

Supplement at the Fairhill School. Acmat, for example, seeks $185,000 for
removing carpeting and scraping of carpet glue even though it had agreed in
writing this work was included in the $18,000 Work Practices Supplement.
Similarly, Acmat seeks to recover because of alleged defective testing proce-
dures although it had expressly agreed to these procedures in the Work
Practices Supplement.

6. Relevant portions of Mr. Lord’s deposition testimony are attached
hereto as Exhibit “A”.

R.A.24

rather, it complains that it is entitled to additional compensation
because the overspray at the Rush School was even more
extensive than originally con

Although Acmat wishes to impose the cost of removing the
overspray on the School District, a close examination of the
contract documents reveals that Acmat is solely responsible for
this work. Acmat’s asbestos removal contract for the Rush School
expressly requires the removal of “. . . all asbestos containing
spray-on fireproofing materials.” (Specifications, Section 2080
{7101C, 3.04B). The contract does not distinguish between

asbestos fireproofing sprayed on steel beams and any overspray
surrounding those beams. Acmat now complains that at least a

portion of the overspray was not shown on drawings provided by
the School District. Acmat, however, expressly agreed in its
contract with the School District that anything mentioned in
either of the drawings or the specifications “. . . shall be of like
effect as if shown or mentioned in both. In case of differences
between drawings and specifications, the specifications shall
govern.” (Rush School Specifications at 913(a)).

Furthermore, Acmat’s contract with the School District
expressly required Acmat to conduct an inspection of the
building site prior to submitting its bid to determine the full
scope of its work at the project. The contract expressly provides:

EXAMINATION OF THE SITE

The Contractor bidding on this work must inspect the
sites before submitting the proposal and will be responsible
for informing himself fully on all determinable, existing
conditions and limitations of the sites and will assume
responsibility for all charges and costs resulting from his
failure to verify same.

(Rush Contract, Special Conditions, SC-07). Acmat also agreed
to the following clause in its contract:
CONDITIONS AFFECTING THE WORK

The Contractor shall be responsible for ascertaining
the nature and location of the work and the general and

R.A.25
local conditions which can affect the work or the costs

229-30). Lord further testified that Acmat typeally performs «
thorough inspection before submitting its bids

HE i He
ie oa tig
i fi th! na fi
bee Hi iil 8
i ils He
sitter

R.A.27

IN THE UNITED STATES DISTRICT COURT
FOR THE EASTERN DISTRICT OF PENNSYLVANIA

ACMAT GonPomatiON ==-—=—s:_—« CIVIL ACTION
Plaintiff :

v.

THE SCHOOL DisTRICT OF
PHILADELPHIA :
Defendant : NO. 85-7067
AFFIDAVIT
COMMONWEALTH OF PENNSYLVANIA:
: 88
COUNTY OF PHILADELPHIA

1. 1 was appointed to the Board of Education of the
Schoo: District of Philadelphia in 1981 and have served as

R.A.28

1984 to a price change on the Fairhill Contract in the
amount of $18,000 and a change in specifications known as
the “Work Practice Supplement.” Under date of October
30, 1984, the School District, with School Board Approval,
and Acmat entered into a Supplemental Agreement to the
Rush Contract. This agreement added the first floor of the
Rush School to Acmat'’s contract for an additional $656,000.
In addition, the School District, with School Board ap-
proval, and Acmat agreed to Change Order No. 1 in the
amount of $63,282.89 for extra labor, material and equip-
ment necessary to wet wipe items in closets and cabinets at
the Rush School.

4. Other than the amendment to the Rush Contract
and the two change orders I have just reviewed, no other
change orders or requests for additional compensation were
ever approved by the Board of Education or issued by the
School District in connection with the Rush, Lincoln or
Fairhill contracts.

5. At no time did the Board of Education, by formal
resolution or otherwise, ever waive compliance with the
provisions of the Pennsylvania Public School Code or the
provisions in Acmat Corporation's contracts with the School
District which required formal approval of any modifica-
tions to Acmat Corporation’s contracts by the Board of
Education.

6. At no time, furthermore, did the Board of Education
ever authorize any employee, agent or representative of the
School District of Philadelphia to issue change orders or to
otherwise enter into agreements for the payment of addi-
tional compensation to Acmat Corporation without the
approval of the Board of Education.

ee a

Sworn to and Subscribed
Before me this 15th day
of August, 1988.

R.A.29

NOTARY PUBLIC
FRANCES FIORELLA
Notary Public, Phila., Phila. Co.
My Commission Expires Aug. 29,
1988

R.A.30

ANSWER OF ACMAT CORPORATION TO MOTION FOR
SUMMARY JUDGMENT OF THE SCHOOL DISTRICT OF
; PHILADELPHIA
IN THE UNITED STATES DISTRICT COURT
FOR THE EASTERN DISTRICT OF PENNSYLVANIA

ACMAT CORPORATION
Plaintiff : CIVIL ACTION

oD.

SCHOOL DISTRICT OF PHILADELPHIA :
Defendant

and :
HUGHES URETHANE CONSTRUCTION, :
INC. :
Third Party Defendant : NO. 85-7067

ANSWER OF ACMAT CORPORATION
TO MOTION FOR SUMMARY JUDGMENT

OF THE SCHOOL DISTRICT OF PHILADELPHIA

The School District of Philadelphia is not entitled to the
entry of judgment on its behalf, because there exist genuine
issues of material fact and because the School District is not
entitled to judgment as a matter of law. In opposing the Motion
for Summary Judgment, ACMAT relies upon its accompanying
memorandum of Law, the exhibits thereto, and ACMAT's
Memorandum of Law on Disputed or Unusual Legal Issues
previously filed with its Pretrial Memorandum, a copy of which

is attached hereto. KORN, KLINE & KUTNER
Bie y wad AT

ae A. Korn, gm

1845 Walnut Street

21st Floor

Philadelphia, PA 19103

(215) 751-0500
Attorney for Plaintiff

ACMAT Corporation

R.A.31

IN THE UNITED STATES DISTRICT COURT
FOR THE EASTERN DISTRICT OF PENNSYLVANIA

ACMAT CORPORATION CIVIL ACTION

HUGHES URETHANE
CONSTRUCTION, INC.

Third Party Defendant : NO. 85-7067

MEMORANDUM OF LAW OF ACMAT CORPORATION
IN OPPOSITION TO MOTION FOR SUMMARY
JUDGMENT OF THE SCHOOL DISTRICT OF PHILA-
DELPHIA

I. INTRODUCTION

ACMAT Corporation (“ACMAT’) entered into three sepa-
rate contracts with the Schoo! District of Philadelphia (“School
District”) for asbestos abatement at Fairhill Elementary School,
Lincoln Senior High School and Rush Middle School. ACMAT,
having completed its work at the three schools, now seeks to
recover damages in the amount of $4,389,268.00, allocated as

follows:
Rush _ $2,436,556.00
Fairhill _ $1,134,021.00
Lincoln _ $ 818,691.00

The original contracts, before extras and modifications,
totaled $2,001,283.00. Owing to defects in the contract docu-
ments as bid, the School District’s requiring of extra work
outside the scope of the contract, incorrect and inconsistent

R.A.32

interpretation and administration of the work practices under
each contract, unreasonable requests by the School District
personnel or its agents, and other improper acts of the School
District, ACMAT’s project costs rapidly escalated. The School
District failed to pay amounts due ACMAT, and ACMAT now
has claimed balances due under the base contract, balances due
for authorized and recognized extra work, balances due for work
performed beyond the scope of the original contract document,
and other damages particularized in the claim submitted by
ACMAT.

The School District has filed a Motion for Summary Judg-
ment. That Motion should not be granted because there exist
genuine issues of material fact, and the School District is not
entitled judgment as a matter of law. The moving party has the
burden of establishing the non-existence of genuine issues of
material fact. Adickes v. S. H. Kress & Co., 398 U.S. 144,
159-60, 90 S.Ct. 1598, 1609-10, 26 L.Ed.2d 142 (1970). The
School District has failed to meet this burden. Summary judg-
ment is not appropriate if there is the “slightest doubt,”
concerning the existence of material facts. Tomalewski v. State
Farm Life Insurance Co., 494 F.2d 882, 884 (3d Cil,. 1974).

The pertinent facts, conveniently overlooked by the School
District, were that School District employees and agents or-
dered ACMAT, verbally and in writing, to perform extra work.
ACMAT was threatened with termination and liquidated dam-
ages if it refused to comply with those mandates.

ACMAT submitted timely clairns for additional compensa-
tion. When payment was not forthcoming, ACMAT was prom-
ised that if it continued to perform, its claims would be equitably
adjusted. The School District never advised ACMAT that its
claims would not be submitted to the Board of Education or that
the School District never intended to pay ACMAT for millions of
dollars of extra work, of which they had knowledge. How
convenient to now argue that ACMAT's claim cannot be be-
tween $5-6 million, when the base contracts total $2.001,283.00.
The explanation is simple —the School District’s employment of

R.A.33

people untrained and incompetent in asbestos abatement, cou-
pled with the ordering of extra work, resulted in significant cost
overruns.

The facts, and the law applied to the facts, require a denial
of this Motion. The balance of this Memorandum of Law will
amplify upon this introductory statement and will address the
relevant factual and legal issues which require denial of tile
School District’s motion.

Il. ARGUMENT

A. As A Matter Of Law, ACMAT Is Entitled To Assert A
Claim For Additional Compensation From The School
District Under Both The Pennsylvania Public School
Code And The Contract Between ACMAT And The
School District é

Under the provisions of both the Pennsylvania Public
School Code and the contracts for asbestos removal entered into
by ACMAT and the School District, ACMAT is entitled to assert
claims for additional compensation for work it performed on the
three school projects. The foregoing is true even though AC-
MAT did receive formal approval from the School Board for the
majority of the items of additional work for which it now seeks
additional compensation. Under the facts of this case, the
non-receipt of School Board approval does not preclude recov-
ery of additional compensation.

1. Public School Code Requirement

Under the statutory law of the Commonwealth of Pennsyl-
vania, a Public School Board must formally approve all contacts
for work which has a value greater than One Hundred Dollars
($100.00). 24 Pa. C.S.A. §5-508 (Supp. 1987). Such a provision
includes all modifications to a contract which had been entered
into by the School District. Matevish v. Ramey Borough School
District, 167 Pa. Super. 313, 74 A.2d 797 (1950).

Absent specific statutory approval, contracts with school
districts generally are not enforceable unless formally approved
by the appropriate School Board. School District of Philadelphia

R.A.34

v. Framlau Corp., 15 Pa. Comm. 621, 328 A.2d 866 (1974).
There are, however, exceptions to this general rule. Primarily,
these exceptions include instances dealing with situations where
time is of the essence and the delay in waiting for School Board
approval would be detrimental to the citizens of the Common-
wealth. See In re: Chester School District's Audit, 301 Pa. 203,
219, 151 A. 81 (1930). If an emergency or other circumstance
exists which limits the time available for Board approval, a
School District or Board is justified in not meeting the require-
ments of the statute. Id.

In the case of Smith Laboratories v. Chester School Dis-
trict, 33 Del. Co. 97 (1946), the Court was faced with a situation
where time was of the essence and School Board approval could
not be obtained in adequate time. In Smith Laboratories, the
pupils and teachers at a certain school were being made ill as a
result of unknown causes and conditions at the school. The
School District, through duly authorized officers, hired an
investigator to determine the cause of the illnesses. The School
District, however, had taken no formal action to have the hiring
of the investigator approved by the School Board. Once the
investigator discovered the cause of the illness, the School
District refused to accept responsibility for his bill. Id. at 98.

The Court held that:

In view of the emergency existing and the lack of know!l-
edge as to what cost might be incurred, the defendant
directors were fully justified in contracting for the services
by their proper officers without waiting for a formal meeting
in order to record the minutes of such action. Neither the
time nor the conditions permitted any delay or discussion
.... The safety of the school child is at all times the
primary factor, and if necessary all requirements should be
passed over in order to protect them.

Id. at 99-100.

The circumstances involved here are similar. ACMAT was
involved in the removal and abatement of asbestos from three
public schools during the summer break at all three schools. Its
contracts provided that time was of the essence, and the hazard

R.A.35

imposed by the asbestos clearly jeopardized the health and
welfare of the students and teachers. Faced with a constant

demand for extra work from the School District, ACMAT could
simply not wait for the formal approval of the Board. To do so
would have created additional costs and expenses because
ACMAT would have been required to stop what it was doing,
clean up that area as best as possible, and begin anew in another
part of the school, causing large scale inefficiences. Once formal
approval was given, ACMAT would have had to restart in each
room where it was forced to stop. The asbestos removal process,
which required that an isolated area be totally cleaned and kept
from further contamination thereafter simply did not lend itself
to a piecemeal removal process. The extra cost would have been
astronomical, and re-contamination of areas would have been
likely.

Furthermore, the additional costs arising from the exist-
ence of asbestos overspray in the schools and other extra work
was unknown during the course of its work. From its vantage
point, ACMAT could not discern a reasonable cost for the extra
work and, therefore, was compelled to perform on a time and
material basis. Consequently, the School District could not
submit a known price to the School Board until after ACMAT
was done with the extra work. The work ACMAT encountered
was out of the ordinary and a price could not have reasonably
been set beforehand as would have been the usual case. Thus, as
in Smith Laboratories, unknown cost, health and safety require-
ments, and time requirements justified performance of extra
work without Board approval.

Because time was of the essence, the health and welfare of
the citizens of the Commonwealth were involved, and the value
of the work to be performed was unknown, the statutory
provision requiring formal approval by the School Board could
not have possibly been met at the time the work was to be done.
This does not mean, however, that the statute should be

. On the contrary, once the work had been com-
pleted for each change order, the School District, as required by
the contract, should have made an equitable adjustment to the
Contract amount. See, e.g., Fairhill contract §16, quoted infra

R.A.36

in Section IIB. When such an adjustment was made, the School
Board would make the final approval of the adjustment and
enter its approval into the School Board minutes as required by
the statute. As with any act of government, a reasonableness
standard would be applied to School Board approval at that
time. It was inequitable and unconscionable for the School
Board to use the statute at that time to withhold payment from
ACMAT.

The cases.cited by the School District in its Memorandum
of Law in Support of its Motion for Summary Judgment do not
involve the conditions present here. The Framlau case, supra,
involves a situation in which a plaintiff entered into a settlement
agreement with the School District which was approved by the
counsel for the School Board and the School Board president.
Framlau, supra, 328 A.2d at 868. The Board, however, later
rescinded the settlement agreement, saying that it was never
formally approved by the Board as required by the statute. Id.
at 869. The Court held for the School Board and ruled that the
settlement agreement was unenforceable. That case does not
involve a “time of the essence” problem, a health and welfare
question, or a situation where the costs of the changes in the
contract were unknown. Furthermore, the contract in Framlau,
unlike those here, was expressly conditioned on subsequent
approval by the Board, and did not affirmatively provide for an
equitable adjustment. Id. at 870. Consequently, Framlau is
clearly distinguishable from this case.

The Matevish opinion, supra, is distinguishable on the
same grounds. There, a conflict arose when a plaintiff furnished
a six year old bus rather than a new one as required under the
transportation contract entered into with the School District.
The use of the old bus was agreed to orally but was never
formally approved by the School Board. Matevish, 167 Pa.
Super. at 315-16. The Court ruled that the modification of the
contract had to be approved by the School Board and, therefore,
the contract was unenforceable. Id, at 317. Matevish does not
involve questions of time, health, welfare, or uncertain costs.
Nor did the contract involved require an equitable adjustment.
The case deals with a bus, not the removal of asbestos which had

R.A.37

to be done in a limited amount of time and with the safety of the
public in mind. It is therefore inapposite.

2. Contract Requirements

The requirement for approval by the School Board outlined
in 24 Pa. C.S.A. §5-508 is supplemented by a provision in the
contract between the School District and ACMAT which sub-
jects adjustments to the contract or contract price to School
Board approval. The clause states, “If such changes cause an
increase or decrease in the contractor's costs of, or time required
for, performance of the contract, an equitable adjustment shall
be made and the contractor notified in writing accordingly, any
such change in the contract price being subject to the approval
of the Board.” Fairhill contract, General Conditions, §16(a)
(emphasis added).

Under such a provision. ACMAT is entitled to an equitable
adjustment to the contract for any changes in the drawings or
specifications of the contract. If such a change is made, the new
contract price is subject to the approval of the School Board.
Such clauses have been the subject of numerous legal actions in
Pennsylvania, as well as other jurisdictions.

The School District seeks to bar ACMAT’s claim for addi-
tional compensation for extra work by relying extensively on the
case of Nether Providence Township School Authority v.
Thomas M. Durkin & Sons, Inc.. 505 Pa. 42, 476 A.2d 904
(1984). In Durkin, the contractor entered into a contract for the
construction of a new high school. Soon after the construction
began, the contractor noticed discrepancies between the site
plan provided by the School District under a separate contract
with an engineering firm and the actual site conditions. The
resolution of these discrepancies required additional work. The
Authority's president sent a letter to the contractor recommend-
ing that the contractor continue working on the project and that
the problem would be resolved at a later date. Relying on the
president's representation, the contractor completed the work
despite a contract provision requiring all change orders for extra
work to first be approved by the School Board.

|
|
;

mine the amount of “cut and fill” needed to

jl
E
|
Es
i
Lise

¥
:
fe

2A
ite
nt
an
Hi
Hie
SLE

i z
He
(HI
ih
i
ails

to make his own estimate of the necessary excavation and submit
a bid including the additional excavation costs. Thus, Durkin
stands for the proposition that a contractor is required to follow

asus agg ALN
ba Tee Eee fi
ai ete Ap
: PBR (yieeitae 1 ti
+ i eet Le bet
IRL ERE RUT
HHA ai Hadad Hl is

R.A.40

HEH TH ee rH {iil 4 i
Beare
at stl Tea Ht
eee HE vii ul
eal anutilieian
Hoan porta Hae
SUH HH TRL ATH

aa Ht Hi SHH
HAE a ILE H ath TE in
ea it TATE ‘

He

13842) F ay iy iis
HEP null ine ht Ant HIE

a TT Te

R.A.41

R.A.42

were sent authorizing the extra work. Consequently, the Board
would be unjustly enriched if it could reap the benefits of
ACMAT's performance without fully compensating the contrac-
tor. See also Lindbrook Construction v. Mukilteo School District
No. 6, 458 P.2d 1 (Wash. 1969) (holding that a School District
was estopped from denying its obligation to pay when its
representative directed work to proceed without a written
order, even though one was required by the contract) and
C. Norman Peterson v. Container Corp., 218 Cal. Rpter. 592,
172 Cal. App. 3d 55 (1985)(holding that clauses requiring change
orders to be approved in writing can be waived by an extremely
tight time schedule as well as cardinal changes to the scope of
the contract).

The case law upon which the School District relies is clearly
distinguishable. None of those cases contain clauses providing
for an equitable adjustment of the contract; none of them involve
a situation in which time is of the essence; none of them involve
circumstances which would not permit a contractor to simply
stop its work and wait for the approval of the School Board; and
none of them involve a continual pattern of threats of termina-
tion and liquidated damages which force the contractor to
continue. To allow a School District to take advantage of a
contractor because of such conditions would work an immense
injustice. In such a situation, the oral or written directives of the
School District representatives must be held to be the equiva-
lent of School Board approval. If they do not rise to that level,
the directives must be found to have given ACMAT the right to
an equitable adjustment which would be subject to the reason-
able approval of the School Board at a later time.

ACMAT is not attempting to circumvent either the statute
or the contractual requirement of School Board approval.
Rather, it is attempting to abide by these provisions as best it
can under the circumstances involved. Given the conditions
under which ACMAT was performing its contractual duties, it
would have been unreasonable for ACMAT to await School
Board approval. Furthermore, to allow the School District to
take advantage of ACMAT's position with the School District's
endless threats of termination and liquidated damages and for

R.A.43

the School District to later argue that ACMAT is not entitied to
further compensation because of the statute or contractual
provisions would create a grave inequity. While the purpose of
these provisions is to protect the public from fraud and a
plundering of its treasury, they should not be used to allow the
School District to plunder its contractors.

B. As A Matter Of Law, ACMAT Is Entitled To Assert A
Claim For The Reasonable Cost Of Work Performed
Beyond The Scope Of Its Written Contracts, Under

Theories Of Equitable Estoppel And Quasi-Contract

Even if the Court were to conclude that ACMAT is not
entitled to compensation for extra work performed because such
work was not formally approved by the School Board in writing,
ACMAT is nonetheless entitied to reasonable compensation
under quasi-contract and estoppel theories. ACMAT’s claims
under these theories are supportable based on the terms of the
School District's contracts, and as a matter of law.

The School District's arguments against quasi-contract and
estoppel recovery are simply regurgitations of its argument that
the School Code and written contract provisions required School
Board approval for work beyond the scope of the contracts. The
School District argues that if a party does not expressly comply
with a contractual provision requiring written approval of a
public Board or authority, recovery under an estoppel or
quasi-contract theory may never be had, no matter what the
facts or circumstances. This is allegedly so because, otherwise,
the sanctity of the formal approval process would be violated.
School District Memorandum of Law, pp. 17-19.

The School District’s argument that ACMAT is entitled
only to compensation for School Board approved changes in the
contracts ignores the terms of the contracts which expressly, and
affirmatively provide for an “equitable adjustment” to compen-
sate ACMAT for work beyond the scope of the contract. Each
contract’s General Conditions provides, as in Section 16 of the
Fairhill contract:

R.A.44

(a) The School District may, at any time, subject to
approval of the Board and without notice to the sureties,
make changes in the drawings and/or specifications of this
contract if within its general scope, such changes to be
made in writing. If such changes cause an increase or
decrease in the contractor’s cost of, or time required for,
performance of the contract, an equitable adjustment shall
be made and the contractor notified in writing accordingly,
any such change in contract price being subject to the
approval of the Board.

(b) The determination of the increase or decrease in
compensation to be paid to the contractor for additions to or
reductions in the work, respectively, shall be determined
by application of unit prices when such are set forth in the
Special Conditions of the contract, or in those cases where
unit prices are not applicable, by a lump sum mutually
agreed upon by the Board and the contractor. If however,
unit prices are not applicable and if the parties cannot agree
upon a lump sum, then additional compensation to be paid
the contractor shall be determined by the actual cost in
labor and materials, plus fifteen percent (15%) for profit and
overhead. Reductions in the contract price in the form or
credits shall be determined by the actual net cost in labor
and materials if the aforementioned lump sum cannot be
agreed upon. The fifteen percent (15%) for profit and
overhead will be retained by the contractor. The School
District will make the final determination as to net cost of
labor and materials.

(c) Should the contractor encounter subsurface and/or
other conditions at the site materially differing from those
shown on the drawings or indicated in the specifications, he
shall immediately give notice to the School District of such
conditions, before they are disturbed. The School District
will investigate the conditions and if it finds that they
materially differ from those shown on the drawings or
indicated in the specifications, it shall make such changes in
the drawings and/or specifications as it may find necessary.

R.A.45

Any increase or decrease of cost resulting from such
changes shall be adjusted in the manner provided herein for
adjustment as to changes.

(d) Verbal instruction given by way of the officers,
agents, or employees of the Board which depart from the
contract documents shall not be binding upon the Board.

Subsection (a) specifically requires “equitable adjustments” in
the contract price. Use of the word “shall” mandates an equita-
ble adjustment where contract changes cause an increase in the
contractors cost of or time for performance. Although Subsection
(a) states that any increased cost of performance is “subject to
approval of the board”, mandatory language of the contracts
relating to equitable adjustments in the contract price created an
affirmative obligation of the School District to present all such
requests for equitable adjustments to the School Board, and
required the School Board to exercise reasonableness in evalu-
ating requests for equitable adjustments. The contract's lan-
guage mandating an “equitable adjustment”, “subject to” School
Board approval does not make Board approval a condition
precedent to recovery. At best, it creates an ambiguity in the
contract with respect to whether and when Board approval was
required, which, since it was drafted by the School District,
must be resolved against it by implying a requirement that the
School Board employ a “reasonableness” standard in its review
of any requests for equitable adjustment. See Restatement
(Second) of Contracts, §205.1

None of the cases cited by the School District in opposition
to recovery in quasi-contract or estoppel involve contracts, like
those here, with affirmative language mandating equitable
adjustments. That the contracts make the equitable adjustments
“subject to School Board approval” does not require that such
adjustments be rejected. To the contrary, the contract language

1. That the contracts contemplate reasonableness in determining the
amount of an equitable adjustment is bolstered by Subsection (b) which sets
forth a formula for compensation in the absence of an agreement between the
School District and a contractor.

R.A.46

imposes a good faith obligation on the School District to present
all claims to the School Board, and on the School Board to fairly
and reasonably evaluate them. See Tamaqua Borough v. Rush
Township Sewer Authority, 85 Pa. Comm. 421, 482 A.2d 1167,
1173 (law implies agreement to perform things according to
reason and justice that party should perform in order to carry out
purpose for which contract was made and to refrain from doing
anything that would destroy other party's right to receive fruits
of contract). Absent application of this standard, it cannot be said
that the adjustment process imposed by the contracts was in any
sense “equitable” ,? as required by the contracts.

The record before this Court reflects 2 consistent pattern of
oral and written School District approvals to ACMAT to perform
work beyond the scope of its written contracts. See Exhibits
1-35. In reliance on these explicit instructions, ACMAT per-
formed hundreds of thousands of dollars of extra work. Yet, it is
uncontroverted that most of ACMAT’s requests for extra work
were never even placed before the School Board for review, let
alone fairly considered by the School Board for equitable
adjustment. See Exhibits 42-44. The School District’s contracts
state that an equitable adjustment shall be made for extra work.
Thus, the School District’s argument, reduced to essentials,
becomes a tautology: ACMAT cannot be accorded equitable
relief because the School Board (although permitted to approve
equitable relief) was not given the opportunity to approve
payment for alleged extra work performed by ACMAT.* Buried
within the rationale of this argument lies this flawed premise:
the School Board is the sole and exclusive arbiter of ACMAT's

2. “Equitable” means “Just; conformable to the principles of justice and
right . . . just, fair, and right, in consideration of the facts and circumstances
of the individual case.” Black’s Law Dictionary, Revised 4th Ed.

3. The discovery record establishes that many of ACMAT’s requests for
compensation for extra work were considered and rejected by lower level
School District officials, without further review by the School Board. (Exhibits
42-43). In so doing, the School District officials clearly acted as agents for the
School Board. If agents in rejecting ACMAT's claims, these School District
officials must also be agents, binding the School Board, for all extra work
approved by them and on which ACMAT was instructed to proceed.

R.A.47

entitlement to equitable compensation. The contracts do not so
provide, as they mandate equitable adjustment for extra work
performed.

In none of the cases cited by the School District did the
contracts involve certain clauses, like those in this case, affirma-
tively mandating an equitable adjustment for extra work. In
Commonwealth v. Seagrams Distillers Corporation, 379 Pa. 411
(1954), an oral contract for the transportation and delivery of
liquor was construed. Quasi-contract recovery was denied,
therefore, in the absence of an affirmative contract provision, as
here, mandating an equitable adjustment. Once the School
District chose to provide for an equitable adjustment in AC-
MAT’s contract price, it exposed itself to quasi-contractual relief
based on principles of estoppel. Montgomery v. Philadelphia,
391 Pa. 591 (1958) is not to the contrary. In that case, the
contract provided that no claim for extra work would be allowed
unless “ordered in writing by the engineer and approved by the
recreation commissioner”, a condition precedent to recovery.
Here, the contract creates a right to an equitable adjustment,
subject to subsequent School Board approval. This right to an
equitable adjustment cannot be unreasonably witheld, given the
contract language. See Teodori v. Penn Hills School District
Authority, 413 Pa 127, 196 A.2d 306 (1964).

The School District also argues that ACMAT is not entitled
to quantum meruit recovery because “ACMAT failed to proceed
in accordance with the requirements of the School Code” to
obtain School Board approval. However, the question of
whether School Board approval was improperly witheld by the
School District is a question of fact which can be resolved only
upon determination of whether the work performed by ACMAT
was in fact an extra to the contract. ACMAT has alleged: that
certain work which the School District required was a “cardinal
change” to the contract which fundamentally altered the con-
tractual undertaking; that unforeseen and unforseeable condi-

tions existed which created “differing site conditions” creating a

right to additional compensation: and that the School District
actively interfered with its work, thereby creating additional
costs. Equitable adjustment for the claimed extra work is

R.A.48

contemplated by the contacts, subject to reasonable and fair
approval and evaluation by the School Board. Because the
question of whether the School Board actually, or should have,
reviewed ACMAT’s requests for extra compensation in a rea-
sonable and fair way is one of fact, summary judgment should
not be granted.

The disputed facts giving rise to ACMAT's claim have been
fully developed in discovery. ACMAT can prove that it received
written directives from high level and project level School
District employees to perform thousands of dollars of extra

- work. The School District had an affirmative duty, based on the

contracts, to submit ACMAT’s requests for additional compen-
sation to the School Board, and the School Board was required
to promptly, fairly, and reasonably review those requests. As
developed in discovery, neither the School Board nor the School

It is overwhelmingly clear that ACMAT relied on instruc-
tions from School District employees in performing large
amounts of extra work. To prohibit recovery as a matter of law
would be to permit the School Board to use its potentially bad
faith refusal to evaluate ACMAT's claims as a sword to preclude
ACMAT from proving its entitlement to compensation. The law
does not and should not sanction this harsh result.

Where a contractor relies to his detriment on representa-
tions of a public authority, Pennsylvania law provides a quasi-
contractual remedy based on estoppel. in Derry Township
School District v. Suburban Roofing, 102 Pa. Comm. 54, 517
A.2d 225 (1986), the court held that theories of equitable
promissory estoppel are applicable to public contracts
governmental agencies, and expressly rejected a School Dis-

applicable to public contracts. 517 A.2d at 228-229.

In Derry, a School District official modified the amount of
material which it had previously orally ordered a contractor to
procure pursuant to a contract for replacing a roof. Because the

R.A.49

contractor had relied on an earlier representation, it had or-
dered material some of which was useless as a result of the
changes. The change had not been approved in writing as
required by the contract. The court held that because the School
District had induced the contractor to purchase supplies which
thereafter could not be used, promissory or equitable estoppel
prevented it from denying liability. Id at 229.

The School District attempts to distinguish Derry from this
case because, supposedly, “this is not a case where the School
District initially interpreted the contracts one way and later
another in which ACMAT had to ‘special order’ materials which
would be useless to ACMAT if the School District later deter-
mined that less work and materials would be involved”. School
District Memorandum of Law, p.22. To the contrary, this is a
case where differences in contract interpretation by the School
District resulted in the expenditure of huge amounts of addi-
tional labor and material. The proper scope of ACMAT’s work
under the contracts forms the primary basis for much of its
claim. During its performance, ACMAT and the School District
were continually at odds over what was expected of ACMAT
under the contract; this case is almost exclusively about differ-
ences in contact interpretation. Because the essence of the
dispute between ACMAT and the School District is one of
contract interpretation, and the proper scope of work as defined
in the contracts, equitable and promissory estoppel theories,
pursuant to Derry, are cognizable against the School District.

Moreover, the contracts in this case affirmatively require an
equitable adjustment for work performed which is outside the
scope of the contracts. To argue that the mandate of Derry does
not apply here merely because “special order” materials are not
involved is to unfairly and disingenuously limit its holding, and
would produce the absurd result of permitting estoppel claims
against public authorities only where its promises resulted in
“useless” materials being ordered. Derry’s holding is not so
limited; it permits recovery against a public agency based on

R.A.50

estoppel principles where, as a result of contract interpretation,
work outside the scope of a contact is performed.

In deciding the issue of ACMAT’s entitlement to recover
based on equitable and promissory estoppel principles, the
Court should be mindful that the doctrine of equitable estoppel
is one of fundamental fairness. Brog Pharmacy ov. Department of
Public Welfare, 87 Pa. Comm. 181, 687 A.2d 49 (1985). Penn-
sylvania law emphatically authorizes recovery against public
agencies based on estoppel principles. Plymouth Twp. Council
v. Montgomery Co., 531 A.2d 1158, 1162 (Pa. Comm. 1987);
Commonwealth o. Dixon Contracting Company, 80 Pa. Comm.
438, 471 A.2d, 934 (1984); Frank v. County of Greany, 50 Pa.
Comm. 30, 412 A.2d 663 (1980).

Here, the facts as developed in discovery reflect that the
School District repeatedly ordered ACMAT to perform work,
much of which ACMAT believed to be outside the scope of its
contracts. See Exhibits 1-37. In so doing, the School Board
reeatedly represented in writing to ACMAT that it would be
compensated for extra work. Yet, the facts reflect that the School
District presented only two change order requests to the School
Board, leaving the lion’s share of ACMAT s claims for extra work
compensation, totalling hundreds of thousands of dollars, unre-
viewed by the very Board whose review is required by the
contracts! ACMAT had no control over the School Board review
process. Therefore, the School District had an affirmative
obligation to submit all of ACMAT’s claims to the School Board;

it clearly did not do so. To grant summary ‘udgment to the
School District based on lack of School Board approval would be

4. The Derry decision distinguishes Nether Providence Twp. School
Authority 0. Durkin & Sons, Inc., 505 Pa. 42, 476 A.2d 904 (1984) because
Derry involved “contract interpretation” and Durkin involved the enforceabil-
ity of an oral change order. The Durkin decision did not bar estoppel claims
against public authorities; it held simply that based on the facts of that case an
oral change order was not enforceable. Where, as here. the primary issue is
one of contract interpretation, Derry is clearly incompatible with Durkin and
permits recovery, based on estoppel theory, for claims based on oral and
written representations of School District officials, whether or not formally
approved by the School Board.

eit numa

R.A.51

to condone a system in which authorized representatives of a
School District can: 1) repeatedly instruct a contractor, orally
and in writing, to perform work which the contractor believes to
be beyond the scope of a contract; 2) promise orally and in
writing that the contractor will be paid for this work: 3) threaten
the contractor with termination of its contract and liquidated
damages if the extra work is not performed; 4) fail to submit the
contractor's requests to the School Board for approval; and 5)

cess would give a license to public school districts to use lack of
School Board approval as a sword to defeat contractors, legiti-
mate claims for work performed based on express instructions
from School Discrict officials. This would surely be the moral
equivalent of acquitting a child for the murder of his parents
because he was an orphan! Not having followed its own contract,
the School District cannot use that contract's processes to defeat
ACMAT's claim. _

Equity will not allow a School District to act as both judge
and jury with respect to « contractor's claim. Given that
ACMAT's contracts affirmatively require an equitable adjust-
ment, that the facts reflect that the School Board was given the
opportunity to review or approve ACMAT's extra work claim,
and that ACMAT performed work based on written and oral
promises of compensation from School District officials, AC-
MAT's claims based on equitable and promissory estoppel are
cognizable as a matter of law.

Lastly, a substantial portion of ACMAT's claim for equitable
adjustment arises from unforeseen conditions which required an
inordinate amount of work not anticipated by ACMAT. For
instance, ACMAT claims that asbestos overspray on large por-
tions of concealed portions of the Rush School was unforeseeable
and resulted in a significant amount of additional work.

Subsection (c) (e.g. section 16(c) of

[Text truncated at 120,000 characters. The full text is on the page linked above.]

---