# Petition for Writ of Certiorari — Lawrence Coal Co. v. Pennsylvania Department of Environmental Resources

> Briefs, arguments, decisions, and more.

URL: https://www.frixlaw.com/law-library/documents/brief%3Amicro_IA40385020_1257%3A1

## Record

- **Collection:** Supreme Court brief
- **Document type:** Petition for Writ of Certiorari
- **Published:** January 1, 1990
- **Citation:** 495 U.S. 931

## Text

go-14a820) | Prers|

MAR 19 1999
BQSEPH F.
No. L CRN Re
IN THE

Supreme Court of the United States

October Term, 1989

LAWRENCE COAL COMPANY,
Petitioner.

vs.

COMMONWEALTH OF PENNSYLVANIA,
DEPARTMENT OF ENVIRONMENTAL RESOURCES,

Respondent.

PETITION FOR WRIT OF CERTIORARI
TO THE PENNSYLVANIA SUPREME COURT

WILLIAM M. RADCLIFFE, ESQ.
Counsel of Record
LOUISE D. MONAGHAN, ESQ.
COLDREN, ADAMS, DEHAAS

& RADCLIFFE
700 Gallatin Bank Building
Post Office Box 1327
Uniontown, Pennsylvania 15401
(412) 437-2711

Attorneys for Petitioner

Batavia Times Publishing Co.
Harold L. Berkoben
Pitteburgh. Pa. (412) 881-7463

Question Presented For Review

I. Is it a violation of Due Process to permit a single
member of an Administrative Tribunal to determine a
case when the remaining other two members have
already been recused due to the appearance of
impropriety?

Statement of Interested Parties

All interested parties are listed in the caption of this
case.

iii.
TABLE OF CONTENTS.

QUESTION PRESENTED FOR REVIEW........ sa!
STATEMENT OF INTERESTED PARTIES ...... ii
pe iii
See Oe MUEMPOMITIES .................... Vv
NN oo coco occ ccccccewcccce 2
eee ci ce cece cece ccecccee 3
STATEMENT OF THE CASE .................. 4
REASONS FOR GRANTING THE WRIT........ 7

DUE PROCESS IS NOT COMPLIED WITH
NOR IS THE APPEARANCE OF BIAS
EXPUNGED BY PERMITTING ONE
MEMBER OF A THREE MEMBER
ADMINISTRATIVE AGENCY TO MAKE A
DETERMINATION WHEN THE OTHER
TWO MEMBERS HAVE BEEN JUDICIALLY
se os i bs cescccccveccle 7

eas eave es cencpeccvecec. 10

iv.

Page

Appendix:
Appendix ‘“‘A”—Petition for Allowance of Appeal
Dated December 19, 1989. ......------++eeeees
Appendix “‘B’’—Memorandum Opinion and Order
of the Commonwealth Court of Pennsylvania
Dated July 12, 1989 .........- eee eee eee:
Appendix ‘“‘C’’—Adjudication of the
Environmental Hearing Board by Robert D.
Myers, Dated July 5, 1988.......---+-+++++5:
Appendix ‘‘D’—Opinion and Order of the
Commonwealth Court of Pennsylvania
(unreported) Dated January 25, 1988........--.
Appendix ‘““E’’—Adjudication of the
Environmental Hearing Board by Maxine
Woelfling, Dated May 27, 1986........-------

la

2a

9a

54a

Page
TABLE OF AUTHORITIES.

(-—

Cases:
FTC v. Flotili Products, Inc., 389 U.S. 179 (1967)... y
Gardner v. Repasky, 434 Pa. 126, 252 A.2d 704

MG) eae ee ee 9
Gibson v. Berryhill, 411 U.S. 564 (1973)........... 8
In Re Murchison, 349 U.S. 133 (1955)............. 8
R. R. Yardmasters of America v. Harris, 721 F.2d

a RASS Mpeg elie esae og iii 9

Withrow v. Larkin, 421 U.S. 35 (1975) ............ 8
Statutes:
MIE os oe ccc wcccccccccccececces 4
Be I 6 55 55 < o's wee duce Vibwn eeleaceecs 9
ori 6 Ss ink eb 0S bw kbc dee as 4
i es 3
Regulation:

Pe IN 6 kb 6 dbo W sowie ccc cbaxedecec dl, 7

IN THE

Supreme Court of the United States

October Term. 1989

No.

LAWRENCE COAL COMPANY,
Petitioner,
vs.
COMMONWEALTH OF PENNSYLVANIA,

DEPARTMENT OF ENVIRONMENTAL RESOURCES,
Respondei t.

PETITION FOR WRIT OF CERTIORARI
TO THE PENNSYLVANIA SUPREME COURT

Lawrence Coal Company, petitioner in the action
below, respectfully prays that a writ of certiorari issue to
review the denial of allowance of appeal by the
Pennsylvania Supreme Court filed on the 18th day of
December, 1989.

2

Opinions Below

The order of the Pennsylvania Supreme Court denying
the petitioner's petition for allowance of appeal is
reproduced in Appendix “A”. The memorandum opinion
and order of the Commonwealth Court of Pennsylvania
dated July 12, 1989 is reproduced in Appendix “B’’. The
adjudication of the Environmental Hearing Board by
Robert D. Myers, Member, dated July 5, 1988 is
reproduced in Appendix ‘‘C’’. The opinion and order of
the Commonwealth Court of Pennsylvania (unreported)
dated January 25, 1988, is reproduced as Appendix ‘‘D”.
The adjudication of Environmental Hearing Board by
Maxine Woelfling dated May 27, 1986, is reproduced as
Appendix ‘‘E”’.

3
Jurisdiction
The denial of the petitioner's petition for allowance of
appeal to the Pennsylvania Supreme Court was filed on
December 18, 1989. This petition was filed within 90

days. The jurisdiction of this Court is founded upon 28
U.S.C. §1257(a) (1989).

4

Statement of the Case

Respondent, Commonwealth of Pennsylvania,
Department of Environmental Resources (hereinafter
‘“DER’’), seeks civil penalties pursuant to Section 605 of
the Clean Streams Law against surface coal operator
Lawrence Coal Company (hereinafter ‘‘Lawrence’’). 35
Pa. Cons. Stat. Ann. §691.5 (Purdon 1977 and Supp.
1989).

The events which are pertinent are as follows:

The Chairman of the Environmental Hearing
Board (hereinafter ‘“‘Board’’), Dennis J. Harnish,
presided over 11 days of hearings which concluded
on November 23, 1982.'

The bulk of the testimony centered around
Lawrence’s_ responsibility for several off-site
discharges along a township road adjacent to the
mining site.

Harnish resigned from the Board in May of 1983
without having prepared an adjudication. (Appendix
“E”’ at p. 63a).

The case was later assigned by the Board to
Hearing Examiner Edward Casey for preparation of
a proposed adjudication. After review of the case,
Casey wrote a letter to both counsel indicating that
he made certain findings and recommended
settlement of the case for the sum of $1,000.
(Appendix “‘C’’ at p. 11a).

The DER then petitioned to remove Casey based
upon ex parte unverified communications between
the DER and former Chairman Dennis Hauish.
(Appendix ‘‘E’’ at p. 63a). The Board granted the
DER’s petition for recusal.

‘The Board, an administrative tribunal consisting of five members,
has inter alia jurisdiction to determine civil penalties in surface mine
operations. 35 P.S. §7513(b) (Purdon 1977 and Supp. 1989).

5

After the Board granted the DER'’s petition for
recusal, Lawrence petitioned for recusal of the Board
because its decision was based upon unverified ex
part conversations between the DER and Harnish.
The Board held that ‘‘an indicia of conflict could be
perceived from the disclosures made by Harnish to
DER counsel, and the Board thought it in the best
interest of all concerned that the members of the
Board not involved in the unfortunate incident
reserve unto themselves the final determination of
the controversy.” (Appendix “‘D”’ at p. 57a).

On May 27, 1986, three and one half years after
the testimony had concluded, an adjudication was
handed down by the remaining two members of the
Board, Chairman Maxine Woelfling and Edward
Gerjuoy. The adjudication found against Lawrence
on all major points and assessed $150,700 in
penalties. (Appendix “‘F”’ at p. 64a).

Lawrence, upon receiving notice that Woelfling
had participated in the determination, filed a
petition for recusal of Woelfling and Gerjuoy.
(Appendix ‘‘C’” at p. 12a). It was determined that
Woelfling had been associated with the subject case
in her position as an attorney for the DER for 11
years. The petition was denied and the adjudication
of May 27, 1986, of the Board was affirmed without
modification. (Appendix “‘C’’ at p. 12a).

In Lawrence’s appeal to the Commonwealth Court,
the Court held the case was ‘‘so tarnished as to
create a clear susceptibility to potential bias against
Lawrence” and that “... the possibility of
unfairness to Lawrence exists and improprieties
might have occurred.’ (Appendix ‘“D’’). The case
was remanded for a new adjudication based upon
the record already established. (Appendix ‘‘D”’).

The only remaining member of the Board, Robert
Myers,? again found in favor of the DER on all
major issues and assessed civil penalties in the
amount of $104,050. (Appendix ‘E’’).

Lawrence’s appeal to the Commonwealth Court
was denied by a three judge panel with one judge
abstaining and the other joining only in the result.
(Appendix ‘‘B”’). Lawrence’s petition for allowance of
appeal was denied before the Supreme Court without
opinion.

?The Commonwealth Court, in its first opinion, held that the two
other members of the Board could not participate in the decision.
Myers made findings of fact and conclusions of law substantially the
same as the Board had in its previous tarnished adjudication, but
reduced the damages by $50,000.

a ee

7

REASONS FOR GRANTING THE WRIT

DUE PROCESS IS NOT COMPLIED WITH NOR IS
THE APPEARANCE OF BIAS EXPUNGED BY
PERMITTING ONE MEMBER OF A _ THREE
MEMBER ADMINISTRATIVE AGENCY TO MAKE
A DETERMINATION WHEN THE OTHER TWO
MEMBERS HAVE BEEN’ JUDICIALLY
DISQUALIFIED.

There can be no question that the proceedings in this
case have created the appearance of impropriety:

The hearing officer originally appointed by the
Board made a recommendation the case be settled
for $1,000.

That hearing officer was recused without a
hearing, pursuant to the DER’s request, on the
basis of an unverified ex parte communication
between the DER and the former Chairman of the
Environmental Hearing Board.

The subsequent adjudication was rendered against
Lawrence in the amount of $150,700 was authored
by the current Chairman of the Environmental
Hearing Board who, at the time the complaint was
initially filed against Lawrence by the DER, had
been an employee of the DER and had reviewed the
matter as part of her position with the DER.

After a determination by the appellate court that
the case was tarnished by the above events, and in
violation of the statute and the Board’s own rules,
one member of the three member Board’, without

* The Board’s own rules provide that determinations are to be made
by a majority of the Board after a hearing. 25 Pa.Code §21.86 (1990).

hearing any testimony, rendered a_ decision
substantially similar to the original tainted
adjudication.‘

It has long been recognized by this Court that ‘‘[a] fair
trial and a fair tribunal is a basic requirement of due
process.” In re Murchison, 349 U.S. 133, 136 (1955). This
requirement applies to administrative agencies as well as
to the courts. Gibson v. Berryhill, 411 U.S. 564, 579
(1973). The courts have recognized not only that a biased
decisionmaker is unconstitutional but also that the
constitution seeks ‘‘. . . to prevent even the probability of
unfairness.”” In re Murchison, 349 U.S. at 136. This
Court has relied upon experience and common sense in
determining when the probability of actual bias on the
part of the decision maker is too severe to be
constitutionally appropriate. Withrow v. Larkin, 421 U.S.
35, 47 (1975).

From a practical standpoint, the dilemma facing Myers
in making his adjudication was obvious. As the newest
Board member, Meyers was asked to decide a case which
three of his predecessors, two of whom were current
Board members, had previously decided against
Lawrence. He was placed in an impossible position. To
decide contrary to the prior decision of his colleagues
would be a _ public betrayal. The appearance of
impropriety is obvious and compelled by logic and
practicality, both of which are standards recognized by
this Court. Withrow v. Larkin, supra at 47.

‘A cursory examination of the adjudication of Myers indicates his
obvious bias. This complicated case, which concerned off-site alleged
acid mine drainage, was based entirely upon circumstantial evidence.
Every crucial point was disputed and although the burden of proof
was on the DER, Myers stated in his adjudication, that it was not
necessary for him to reach sensible conclusions from the DER’s
evidence because Lawrence failed to address several important points
in the case. (Appendix ‘‘C’’ at 4la-42a). This statement is completely

contrary to the rule as to burden of proof recognized by both sides
which placed the burden on the DER.

9

The Environmental Hearing Board is a quasi-judicial
agency. 35 P.S. §$§$7511-7516. This is not a situation
where the statute or the Board's own rules permit the
delegation of determinations to a minority member. E.g.,
R. R. Yardmasters of America v. Harris, 721 F.2d 1332,
1340 (1983). Both the statute and its own rules require
the Board to speak through a majority of its members.
Jd.; 25 Pa.Code §21.86. Even assuming that the Board
followed the common law rule that a quorum of a
majority of a question is required to participate, FTC v.
Flotill Products, Inc., 389 U.S. 179 (1967), neither a
quorum nor a majority of that quorum made the
determination in this matter.

This Court has never determined the issue of whether
disqualification of a majority of the members of a
tribunal due to the appearance of impropriety
constitutionally requires that the remedy be dismissal of
the complaint. However, some courts have previously
dismissed cases where the appearance of impropriety has
risen to a constitutional level due to irreparable prejudice
and long delay. E.g., Gardner v. Repasky, 434 Pa. 126,
130, 252 A.2d 704, 706 (1969).

In view of the standards established by this Court
regarding due process: (1) that a biased decision maker is
unconstitutional; (2) that the constitution has endeavored
to prevent even the probability of unfairness; (3) and
that experience and common sense are to be used in
determining when the offenses rise to the level of
violations of constitutional due process, certiorari should
be granted with regard to this issue of first impression
before the court.

10

Conclusion.

A writ of certiorari should be issued to review the
judgment of the Pennsylvania Supreme Court so as to
determine if due process infraction has been violated
when a minority member of a three member tribunal
renders a determination in violation of both state statute
and administrative rules in a case already tarnished by
the appearance of impropriety.

Respectfully submitted,

WILLIAM M. RADCLIFFE, ESQ.
Counsel of Record
LOUISE D. MONAGHAN, ESQ.
COLDREN, ADAMS, DEHAAS

& RADCLIFFE
700 Gallatin Bank Building
Post Office Box 1327
Uniontown, Pennsylvania 15401
412-437-2711

la

APPENDIX “A”

Petition for Allowance of Appeal
Dated December 19, 1989.

SEAL

THE SUPREME COURT OF PENNSYLVANIA
WESTERN DISTRICT

PROTHONOTARY 801 City-County Building
IRMA T. GARDNER Pittsburgh, Pa.
DEPUTY PROTHONOTARY 15219

(412) 565-2816
December 19, 1989

Ira B. Coldren, Jr., Esquire

Louis D. Monaghan, Esquire
Coldren, Adams, DeHaas & Radcliffe
700 Gallatin Bank Building

P. O. Box 1327

Uniontown, Pa. 15401

In Re: Lawrence Coal Co. v. Dept. of Environmental
Resources No. 457 W. D. Allocatur Docket 1989

Gentlemen:

The Court has entered the following Order on your
Petition for Allowance of Appeal in the above matter:

“December 18, 1989

Petition Denied

Per Curiam”’
Very truly yours,
IRMA T. GARDNER
DEPUTY PROTHONOTARY

ITG:cho
cc: Diana J. Stares, Esq.
Hon. Jacob Kalish

2a

APPENDIX “‘B”

Memorandum Opinion and Order of the Commonwealth
Court of Pennsylvania Dated July 12, 1989.

IN THE COMMONWEALTH COURT
OF PENNSYLVANIA

No. 1891 C.D. 1988

LAWRENCE COAL COMPANY,
Petitioner,

Vv.

COMMONWEALTH OF PENNSYLVANIA,
DEPARTMENT OF ENVIRONMENTAL
RESOURCES,
Respondent.

BEFORE: HONORABLE DAVID W. CRAIG, Judge
HONORABLE JOSEPH T. DOYLE, Judge
HONORABLE JACOB KALISH, Senior
Judge

ARGUED: May 4, 1988
OPINION NOT REPORTED

MEMORANDUM OPINION
BY SENIOR JUDGE KALISH FILED: July 12, 1989

Lawrence Coal Company (Lawrence) petitions for
review of a decision of the Environmental Hearing Board
(Board), which assessed civil penalties against Lawrence
for certain violations.

3a

On November 20, 1987, this court remanded this
matter to the Board for a new hearing and a new
decision on the basis of a 1982 record and any associated
briefs and papers filed by the parties.

The basis for this remand was that upon consideration
of the proceedings, the matter was so tarnished as to
create a clear susceptibility to potential bias against
Lawrence. Additionally, the possibility of unfairness to
Lawrence existed and improprieties may have occurred.

At the remand hearing, Robert Myers, recently
appointed as a Board member, heard the matter. and
assessed civil penalties of $104,500 against Lawrence,
which now petitions this court for review. We Affirm.

Lawrence contends that the proceedings were so
irreparably tainted that a remand based on the
previously-made record was not curable. It is further
contended by Lawrence that the Board’s findings are not
based on substantial evidence. In the previous appeal,
this court did consider the question of taint, and while
recognizing that the proceedings at least had the
appearance of impropriety, nevertheless did not find that
the evidence itself was tainted. Therefore, the matter was
remanded for an administrative hearing based on the
record previously made. Because the parties have
previously litigated the issue of taint before this court, it
is now res judicata, since parties are the same and the
same issue is involved. They are barred from relitigating
the issue.

Lawrence now contends that Myers was not a Board
member at the time of the original hearings, the
procedure for the conduct of hearings before the Board
was not followed, and that in any event, the findings are
not based on substantial evidence.

4a

Our scope of review is limited to determining whether
the Board committed constitutional violations, errors of
law, or whether any necessary fingings are unsupported
by substantial evidence. Pennsylvania Game Commission
v. Department of Environmental Resources, 97 Pa.
Commonwealth Ct. 78, 509 A.2d 877 (1986), aff'd
Pa. , 555 A.2d 812 (1989).

Our legislature vested in the Department of
Environmental Resources (DER) the implementation of
the policy of our state, namely, ‘(T]he people have a
right to clean air, pure water, and to the preservation of
the natural, scenic, historic and esthetic values of the
environment.’ Pa. Const. art. I, §27. An administrative
agency has wide discretion in performing its
administrative duties, including promulgating rules,
regulations, and standards, and the Commonwealth
Court will not interfere with the exercise of such
discretion, absent proof of fraud, bad faith or blatant
abuse of discretion.. Haycock Township v. Department of
Environmental Resources, 108 Pa. Commonwealth Ct.
466, 530 A.2d 514 (1987), petition for allowance of appeal
denied, 518 Pa. 656, 544 A.2d 1343 (1988).

Section 21.86 of DER regulations, 25 Pa.Code §21.86,
reads in pertinent part as follows:

(a) Hearings may be held at the discretion of the
Board, before the Board as a whole, by individual
Board members sitting as hearing examiners or by
hearing examiners who are not members of the
Board. Hearings held by hearing examiners not
members of the Board will be decided by the Board
upon its review of the record and the examiner's
proposed adjudication.

In McIntire Co. v. Department of Environmental
Resources, 108 Pa. Commonwealth Ct. 443, 530 A.2d 140
(1987), petition for allowance of appeal denied, 518 Pa.

5a

614, 540 A.2d 536 (1988), the hearing examiner was not a
member of the Board at the time the adjudication was
rendered. In that case we held:

[W]e refuse to read into the regulation a requirement
that a Board member sitting as a hearing examiner
must be a current member at the time of
adjudication. .. . [Djue process does not require that
administrative adjudicators be present at a hearing
but only that they review the record in preparing
their decisions.
Id. at 453, 530 A.2d at 145; Caldwell v. Clearfield County
Children and Youth Services, 83 Pa. Commonwealth Ct.
49, 476 A.2d 996 (1984). Furthermore, administrative
adjudicators are not precluded from determining
credibility of witnesses from the reading of a transcript.
Caldwell.

There is a _ prima-facie presumption that the
adjudicator read the record and there is nothing in the
record to overcome this regularity of his acts. See
Mignatti Construction Co. v. Environmental Hearing
Board, 49 Pa. Commonwealth Ct. 497, 411 A.2d 860
(1980).

Lawrence had a strip-mining permit for its operation,
the Rogers Mill Strip. Located uphill from the Rogers
Mill Strip is a strip known as the Chanin Strip operated
by the Marsolino Coal and Coke Mining Company,
fronting along Pirl Spring Road. Pirl Spring Road
contains culverts which carry water under the road
toward the Buck Run Tributary and Buck Run.

The Board found that at several of the culverts the
discharge was acid mine drainage. The Board found that
stream degradation is solely attributable to the mining
activities of Lawrence and Marsolino and held Lawrence
responsible for the drainage discharge into the
Commonwealth waters.

6a

Lawrence contends that this finding is not based on
substantial evidence. Lawrence asserts that the drainage
did not come solely from its mining operations, and that
therefore the causal relationship of the drainage from
Lawrence was not proven. Furthermore, it is asserted
that Marsolino was responsible for the acid drainage, and
that Lawrence was responsible for only a few isolated
instances.

In Commonwealth v. Harmar Coal Co., 452 Pa. 77, 306
A.2d 308 (1973), appeal dismissed, 415 U.S. 903 (1974),
our Supreme Court reviewed the legislative history of
The Clean Streams Law (Law), Act of June 22, 1937,
P.L. 1987, as amended, 35 P.S. §$§691.1-691.702, and
the applicable court decisions. The critical and principal
conduct prohibited by the Law is water pollution. It was
concluded that in view of the Law's objective not only to
prevent further pollution of the waters of the
Commonwealth, but also to eliminate existing water
pollution, it is the fact of mine drainage discharge into
the surface waters which is critical, rather than
identification of the original source of the polluted
waters. Discharge must be authorized by the Board's
rules and ‘regulations. ‘‘Mine drainage’ consists of
waters which have been polluted by operation of a mine,
and includes ‘‘fugitive mine water,” that is, water which
enters a particular mine by gravity or pressure.

Also, section 315 of the Law, 35 P.S. §315, provides
that no person shall operate a mine or allow a discharge
from a mine. Thus, while Lawrence may not be
responsible for actually causing the pollution, it certainly
harms the Commonwealth by discharging the polluted
water into the surface waters. There is nothing in the
record to indicate that Lawrence has the right to
discharge acid mine drainage into the waters of the

ne ETO

2, ee

7a

Commonwealth. The Clean Streams Law applies to ail
discharges of mine drainage. Harmar. The fact that the
condition arises from the activities of another mine does
not affect the appropriateness of invoking the police
power to dispel the immediate dangerous condition.
Commonwealth v. Barnes and Tucker Co., 472 Pa. 115,
371 A.2d 461 (1977).

Substantial evidence, albeit circumstantial, establishes
clearly and logically a link between the discharge from
the other mines and the acid mine drainage from
Lawrence.

There was evidence of the tracing of the flow of the
drainage from the Rogers Mill Strip. There was evidence
of the groundwater flow pattern at the mine in
topographical and structural designs and controls. The
mine forms a hillside and the groundwater penetrating
the mine at the higher level would tend to flow downhill,
discharging at the lower level in the vicinity of Pirl
Spring Road. The structural controls would direct the
drainage toward the culverts, and a portion of the acid
mine drainage from the Rogers Mill Strip traveled along
the pavement of the mined coal seam.

The record shows that the discharges of acid drainage,
rather that an isolated instance, occurred on eleven
separate days within a ten-month period. It was
deliberate and willful on the part of Lawrence not to
treat the drainage system after having been directed to
comply for a period of two and a half years.

Thus, the penalty imposed was proper, and we affirm.

JACOB KALISH
Jacob Kalish, Senior Judge

Judge Doyle concurs in the result only.

8a

IN THE COMMONWEALTH COURT
OF PENNSYLVANIA

No. 1891 C.D. 1988

LAWRENCE COAL COMPANY,
Petitioner,

Vv.

COMMONWEALTH OF PENNSYLVANIA,
DEPARTMENT OF ENVIRONMENTAL
RESOURCES,
Respondent.

ORDER

NOW, July 12, 1989, the decision of the
Environmental Hearing Board, No. 81-021-CP-M, is
affirmed.

JACOB KALISH
Jacob Kalish, Senior Judge

CERTIFIED FROM THE RECORD
AND ORDER EXIT

Jul 12, 1989

C.R. HOSTUTLER
Deputy Prothonotary—Chief Clerk

9a

APPENDIX ‘“‘C’’

Adjudication of the Environmental Hearing Board
by Robert D. Myers, Dated July 5, 1988.

SEAL

COMMONWEALTH OF PENNSYLVANIA
ENVIRONMENTAL HEARING BOARD
101 South Second Street
Suites Three—Five
Harrisburg, PA. 17101

(717) 787-3483
M. DIANE SMITH
SECRETARY TO THE BOARD

EHB Docket No. 81-021-CP-M
Issued: July 5, 1988

COMMONWEALTH OF PENNSYLVANIA,
DEPARTMENT OF ENVIRONMENTAL
RESOURCES

Vv.

LAWRENCE COAL COMPANY

ADJUDICATION
By the Board
Synopsis

This proceeding involves a Complaint for Civil
Penalties filed by the Department of Environmental
Resources (DER) against Lawrence Coal Company

10a

(Lawrence) under Section 605 of the Clean Streams Law
(CSL), Act of June 22, 1937, P.L. 1987, as amended, 35
P.S. §691.605. DER sustained its burden of proving by a
preponderance of the evidence that Lawrence had
violated provisions of the CSL, provisions of DER’s
regulations, and provisions of its mine drainage permits
by discharges of acid mine drainage (AMD) and sediment
at two surface mining sites in Fayette County, and by
the improper handling of reject material at one of the
sites. The unlawful discharges were shown to have
degraded Buck Run (a high quality cold water fishery)
and to have interfered with its use as a fishing stream.

In determining the amount of a civil penalty, the
Board considered wilfullness and the damage to Buck
Run. It did not consider the cost of restoration or
employ a deterrence factor because of insufficient
evidence.

PROCEDURAL HISTORY

On February 25, 1981, DER filed a Complaint for Civil
Penalties against Lawrence, alleging (1) the discharge of
acid mine drainage, (2) the failure to implement and
maintain effective erosion and sedimentation controls, (3)
the failure to properly dispose of toxic waste, and (4) the
disturbing of land designated as a barrier. The
allegations pertained to Lawrence's surface mining
operations under Mining Permit No. 1063-5 in
Springfield Township, Fayette County, and under Mining
Permits Nos. 1063-7 and 1063-8 in Dunbar Township,
Fayette County, during 1980 and the early months of
1981.

On March 16, 1981, Lawrence filed an Answer denying
the allegations of the Complaint, alleging in New Matter
that it had attempted in good faith to cooperate with
DER in determining the cause of the alleged pollution of

lla

the waters of the Commonwealth. DER filed a Reply to
this New Matter on April 1, 1981, denying the
allegations.

Hearings began before Board Chairman Dennis J.
Harnish in Pittsburgh on June 2, 1981. At that time it
was stipulated that the Complaint did not include any
alleged violations with respect to Mining Permit No.
1063-5A. DER filed on July 6, 1981, an Application for
Leave to Amend Complaint to include Mining Permit No.
1063-5A, to which Lawrence objected in an Answer filed
on July 19, 1981. Chairman Harnish denied DER’s
Application at the outset of the hearing on July 26,
1981.

A total of eleven days of hearings were held before
they concluded on November 23, 1982. By agreement of
counsel, the deposition of Donald L. Streib, dated
January 21, 1983, together with exhibits, was filed as
part of the record on January 31, 1983. Post-hearing
briefs were filed by both parties during March 1983. On
March 28, 1983, DER filed a Motion to Amend
Complaint to Conform to Proof. Lawrence filed an
Answer to the Motion on April 7, 1983.

Chairman Harnish resigned from the Board on May 16,
1983, without having prepared an Adjudication. The case
was assigned to Edward R. Casey, a Board-appointed
Hearing Examiner, who began reviewing the record on
September 15, 1983. On October 20, 1983, Mr. Casey
wrote a letter to legal counsel for both parties, setting
forth his candid overview of the case and suggesting a
settlement that would involve the assessment of civil
penalties in the maximum amount of $1,000.

On November 7, 1983, DER filed a Petition for Recusal
of Mr. Casey and a Motion for Reassignment, alleging,
inter alia, that Mr. Casey had ignored a recommendation

12a

of former Board Chairman Harnish to find in favor of
DER. On November 22, 1983, the Board entered an
Order recusing Mr. Casey and reassigning the case to
Board Member Anthony J. Mazullo, Jr. for the purpose
of preparing an Adjudication.

On November 30, 1983, Lawrence filed a Petition,
requesting either a dismissal of the case because of
alleged improper communications between former Board
Chairman Harnish and legal counsel for DER or, in the
alternative, a reassignment of the case to a neutral
hearing examiner who was not involved with the Board
during Harnish’s tenure. The Petition was denied in an
Opinion and Order issued by the Board (Members Mazullo
and Edward Gerjuoy) on December 12, 1983.

Board Member Mazullo prepared a draft Adjudication
which had not been adopted by the Board at the time of
his resignation on January 31, 1986. On May 27, 1986,
the Board (acting through its remaining incumbents,
Chairman Maxine Woelfling and Member Gerjuoy)
issued an Adjudication, which adopted Mazullo’s draft
Adjudication with certain modifications and which
assessed civil penalties in the amount of $150,700.

On June 6, 1986, Lawrence filed a Petition for
Reconsideration. As supplemented on June 24, 1986, the
Petition requested that the Adjudication of May 27,
1986, be vacated and that Chairman Woelfling and
Member Gerjuoy be recused from any further
participation in the case. William A. Roth became a
Member of the Board on June 24, 1986. On August 7,
1986, the Board informed the parties that Members
Gerjuoy and Roth would decide whether Chairman
Woelfling should be recused.

-

13a

On September 12, 1986, the Board (Members Gerjuoy
and Roth) issued an Opinion and Order deferring a
decision on the recusal of Chairman Woelfling until
Gerjuoy and Roth acted on Lawrence’s Petition for
Reconsideration. On September 19, 1986, the Board
(Members Gerjuoy and Roth) issued on Opinion and
Order denying the Petition for Reconsideration and
dismissing as moot the request for the recusal of
Chairman Woelfling.

Lawrence filed with Commonwealth Court (No. 3062
C.D. 1986) on October 16, 1986, a Petition for Review of
the Board’s Orders of September 19, 1986, and May 27,
1986. Commonwealth Court handed down a
Memorandum Opinion and Order on January 25, 1988,
vacating the Board’s Orders and remanding the case for
new hearings. On April 8, 1988, the Order was amended
to provide for a new Adjudication, to be issued within 90
days, on the basis of the 1982 record and associated
briefs and papers, and without the participation of
Chairman Woelfling and Member Roth. (Board Member
Gerjuoy had left the Board in 1987 and had been
succeeded by Robert D. Myers.)

The record consists of the pleadings, a transcript of
1914 pages, a deposition of 54 pages and 118 exhibits.

FINDINGS OF FACT

1. DER is an administrative department of the
Commonwealth of Pennsylvania, and is responsible for
administering the provisions of the CSL and the rules
and regulations adopted pursuant thereto. (Complaint,
Para.1; 71 P.S. §61)

2. Lawrence is a company engaged in the surface
mining of coal at sites in Springfield and Dunbar
Townships, Fayette County. (Complaint Para. 2 and 3)

14a

3. Lawrence's surface mining operation in Springfield
Township is the Rogers Mill Strip. (N.T. 10)

4. Mine Drainage Permit No. 3376SM15 (MDP), which
pertains to the Rogers Mill Strip, was issued by DER to
William K. Tedesco on November 10, 1976, and was
transferred to Lawrence on July 19, 1977. (N.T. 11)

5. Mining Permit No. 1063-5 (MP5), covering 63 acres
of the Rogers Mill Strip, was issued by DER to
Lawrence on July 1, 1977. (N.T. 11-12)

6. Mining Permit No. 1063-5A (MP5A), covering an
additional 20.4 acres of the Rogers Mill Strip, was issued
by DER to Lawrence on July 29, 1977. (N.T. 11-12)

7. Mining Permit No. 1063-7 (MP7) and Mine Drainage
Permit No. 3374SM31T both pertain to a surface mining
operation conducted by Lawrence at the Kennedy Strip
in Dunbar Township. (Complaint Para. 4; N.T. 275)

8. Mining Permit No. 1063-8 (MP8) and Mine Drainage
Permit No. 3378BC10 both pertain to a surface mining
operation conducted by Lawrence on the Spruell Strip in
Dunbar Township. (Complaint Para. 4; N.T. 264)

9. The Rogers Mill Strip lies east of the junction of T-
683 (Pirl Spring Road) with T-687 (Fish Hatchery Road).
Fish Hatchery Road runs in a_ northeasterly-
southwesterly direction and forms the western boundary
of MP5A. Pirl Spring Road runs in a northwesterly-
southeasterly direction and forms the southwestern
boundary of MP5. T-685 (Haul Road) runs in a general
easterly direction from Pirl Spring Road (about 250 feet
away from the junction with the Fish Hatchery Road),
crosses the Rogers Mill Strip and forms the dividing line
between MP5 and MPSA. (N.T. 21-24; Commonwealth
Exhibit (CX) 1)

15a

10. Topographically, the Rogers Mill Strip descends
about 500 feet from the southeast to the northwest with
a slight ridge or “tongue’’ extending through the center.
Drainage from the Strip flows southwest toward Buck
Run and northeast toward Middle Fork. (N.T. 13, 720-
721; CX 1)

11. Also located in the Buck Run watershed is a
surface mining operation, conducted by Marsalino Coal &
Coke, Inc. (Marsalino) pursuant to Mining Permit No. 71-
27 on the Chanin Strip, upgradient from and immediately
to the south of, the Rogers Mill Strip. (N.T. 17-18; CX 1)

12. The Rogers Mill Strip and the Chanin Strip are
the only current mining operations in the Buck Run
watershed. (N.T. 18)

13. In prior years, deep mining had been conducted
beneath both the Rogers Mill Strip and the Chanin Strip,
and surface mining had been conducted on the Rogers
Mill Strip by William K. Tedesco, Lawrence's
predecessor. (N.T. 606-610, 750-757, 918, 1377-1378,
1392-1393)

14. Buck Run flows in a northerly direction west of the
Pirl Spring Road, but veers toward the west near the
junction of the Pirl Spring Road with the Fish Hatchery
Road, running beneath the latter at the Rogers Mill
Bridge. About 700 feet upstream from this bridge, Buck
Run divides into two branches which rejoin after a
distance of about 500 feet. An unnamed tributary flows
west of Pirl Spring Road and empties into the easterly
branch of Buck Run about 150 feet upstream from its
junction with the westerly branch. (N.T. 13, 86, 104-107; CX
1)

16a

15. Buck Run has been classified as a cold water
fishery and was stocked with trout by the Pennsylvania
Fish Commission from 1976 through 1978. (N.T. 14,
1837, 1853)

16. The Rogers Mill Strip and the Chanin Strip are
situated on the northwestern flank of the Laurel Ridge
anticline. Both Strips are geologically similar,
characterized by moderately steeply dipping sedimentary
rock. The main coal seam (the seam mined by both
Marsalino and Lawrence) strikes North 30° East and
dips to the northwest. It is overlain with 50 to 60 feet of
sandstone. A rider seam lies below the main seam,
separated from it by 40 to 60 feet of sandstone and
shale. (N.T. 712-713, 731-735, 790-791, 1326-1327)

17. In the vicinity of the Haul Road, a roll occurs in
the main seam, causing it to flatten considerably while
still dipping to the northwest. (N.T. 735)

18. The main seam outcrops on the southwestern
portions of the Rogers Mill Strip and the Chanin Strip
along a line that runs roughly parallel to, and about 400
feet away from, Pirl Spring Road. The outcrop line then
swings toward the north on the Rogers Mill Strip and
runs parallel to, and about 150 feet away from, Fish
Hatchery Road. (CX 1; Defendant’s Exhibit (DX) 4)

19. The rider seam outcrops at Pirl Spring Road. (DX
4)

20. Groundwater penetrating the surface at the higher
elevations would tend to flow in a _ northwesterly
direction, discharging at the lower elevation in the
vicinity of Pirl Spring Road and Fish Hatchery Road.
(N.T. 736-737)

17a

21. Lawrence’s MP5 pit was 1,000 feet to 1,200 feet
long. The highwall was about 60 feet high and oriented
in a general north-south direction. It was composed of
highly fractured sandstone. The northern endwall was
adjacent to the Haul Road and the southern endwall was
next to the boundary line between the Rogers Mill Strip
and the Chanin Strip. (N.T. 716-717, 720; CX1; CX 36;
DX 4)

22. A series of ten culverts carry water under Pirl
Spring Road to Buck Run and the unnamed tributary.
The first five of these are adjacent to the MP5 portion of
the Rogers Mill Strip and the remaining five are
adjacent to the Chanin Strip. Culvert 1 (the farthest
toward the northwest) and culvert 2 flow directly toward
Buck Run. The others all flow toward the unnamed
tributary. (N.T. 20, 39; CX 1)

23. On January 23, 1980, Mark Frederick, a Surface
Mining Conservation Inspector for DER, observed
discharges of water from culverts 1 through 5 and
obtained samples for analysis. (N.T. 19-20)

24. Mr. Frederick determined the following sources for
the flows at culverts 1 through 5:

culvert 1—sediment pond on MP5A (not reievant to
this proceeding) _

culvert 2—swampy area at toe of spoil on MP5

culvert 3—swampy area at toe of spoil on MP5

culvert 4—toe of spoil near dead tree on MP5

culvert 5—embarkment above ditch along Pirl Spring
Road near boundary between Rogers Mill Strip and
Chanin Strip. Since the precise source of the discharge
could not be determined, Mr. Frederick was unable to
decide whether Lawrence or Marsalino was responsible
for it. (N.T. 24-25, 51-54, 64-66)

18a

25. Marsalino had been cited by DER on July 31, 1979,
for discharging AMD into Buck Run and its tributaries.
Marsalino’s discharges continued into 1980. (N.T. 317-
325; DX 1)

26. The analysis of water samples obtained by Mr.
Frederick on January 23, 1980, revealed that the
discharges at culverts 2 through 5 exceeded the effluent
limitations imposed by Lawrence’s MDP and by DER's
regulations, and constituted AMD. (N.T. 40-48)

27. Mr. Frederick recommended that Lawrence develop
and implement a plan to collect and treat any
substandard water leaving the Rogers Mill Strip and
flowing toward Buck Run or the unnamed tributary.
(N.T. 25)

28. Mr. Frederick inspected the Rogers Mill Strip on
January 28, 1980, in the company of Archie Johnson,
Lawrence’s foreman. Mr. Frederick observed discharges
of water from culverts 2 through 5 but did not obtain
any samples. There was no treatment of the discharges
but Mr. Johnson agreed to look into the feasibility of
constructing a ditch to collect and divert water to a
treatment basin. (N.T. 70-72)

29. Mr. Frederick inspected the Rogers Mill Strip on
February 28, 1980, accompanied by James V. Filiaggi,
Lawrence’s Supervisor, Mr. Johnson, Mr.
Frederick’s immediate superior and another DER mine
inspector. Mr. Frederick directed Lawrence to install the
siltation (toe of spoil) ditch required by the MDP by
March 30, 1980, and to construct it at a grade and depth
adequate to collect both surface runoff and discharges of
AMD. (N.T. 73-74)

19a

30. The toe of spoil ditch was dug between May 27,
1980, and June 10, 1980, but was not deep encugh or
long enough to intercept all the water discharging at the
culverts. Lawrence extended the ditch as far as the
dividing line between the Rogers Mill Strip and the
Chanin Strip by July 1, 1980. The ditch was dug in
rubbly material and was not impermeable. (N.T. 170-171,
182,194, 851)

31. Water in the toe of spoil ditch was diverted to a
sedimentation pond constructed by Lawrence between
May 13, 1980, and June 12, 1980. A_ second
sedimentation pond was in place by July 1, 1980.
Lischarges from the ponds flowed to culvert 2. (N.T. 132,
134, 182, 194, 1516)

32. After the toe of spoil ditch and the two
sedimentation ponds had been constructed, the amount
of water discharged at culverts 2, 3, and 4 decreased
significantly. (N.T. 225, 238-239,489)

33. On October 10, 1980, Mr. Frederick suggested that
Lawrence deepen the original section of the toe of spoil
ditch in an effort to intercept seepage still reporting to
culverts 3 and 4. (N.T. 252-254)

34. DER did not hold Lawrence responsible for
treating the discharge at culvert 5 from January 23,
1980 to June 10, -1980, did hold Lawrence responsible
from June 10, 1980, to July 1, 1980, did not hold
Lawrence responsible from July 1, 1980 to September 10,
1980, and held Lawrence jointly responsible with
Marsalino after September 10, 1980. (N.T. 168, 201-202,
249, 299-300)

35. Mr. Frederick also sampled the discharges at the
Rogers Mill Strip on February 28, 1980, March 12, 1980,
March 20-21, 1980, May 13, 1980, May 21, 1980, June

20a

10, 1980, July 7, 1980, July 22-23, 1980, August 14,
1980, and October 3, 1980. (N.T. 74-79, 80, 82, 84, 90,
123, 131, 139, 147, 168169, 171-172, 223-224, 226-227,
237-238, 245, 249)

36. Discharges at culvert 2:

(a) exceeded effluent limitations and constituted
AMD on February 28, 1980, March 12, 1980, March
20-21, 1980, May 21, 1980, July 7, 1980, August 14,
1980, and October 3, 1980; (N.T. 74-79, 8f, 82, 90,
148, 225, 239, 250; CX 33A)

(b) were being treated on May 13, 1980, June 10,
1980, July 1-2, 1980, and July 22-23, 1980. Ps and
acidity levels may have been within effluent
limitations on these dates, but metal concentrations
exceeded effluent limitations. (N.T. 133, 173, 201,
227, 237; CX 33A)

37. Discharges at culvert 3:

(a) exceeded effluent limitations and constituted
AMD on February 28, 1980, March 12, 1980, March
20-21, 1980, May 21, 1980, August 14, 1980, and
October 3, 1980; (N.T. 74-79, 80, 82, 90, 148, 238,
250; CX 33A)

' (b) were being treated on May 13, 1980, June 10,
1980, July 1-2, 1980, and July 22-23, 1980. Pn and
acidity levels may have been within effluent
limitations on these dates, but metal concentrations
exceeded effluent limitations; (N.T. 133, 172, 201,
227, 234; CX 33A)

(c) were not sufficient to take laboratory samples
on July 7, 1980, and August 14, 1980; (N.T. 224,
238)

38. Discharges at culvert 4:

(a) exceeded effluent limitations and constituted
AMD on February 28, 1980, March 12, 1980, March
20-21, 1980, May 21, 1980, June 10, 1980, July 7,
1980, August 14, 1980, and October 3, 1980; (N.T.
74-79, 80, 82, 90, 148, 172, 225, 238, 250; CX 33A)

2la

(b) were being treated on May 13, 1980, July 1-2,
1980, and July 22-23, 1980. Ph and acidity levels
may have been within effluent limitations on these
dates, but metal concentrations exceeded effluent
limitations; (N.T. 132, 201, 227; CX 33A)

(c) were not sufficient to take a laboratory sample
on July 7, 1980. (N.T. 224)
39. During the periods when DER considered Lawrence
wholly or partly responsible for the discharges at culvert
5, such discharges:

(a) were not being treated on June 12, 1980; (N.T.
182)

(b) were being treated on July 1, 1980, but not for
the removal of metals; (N.T. 198)

(c) exceeded effluent limitations and constituted
AMD on October 3, 1980. (N.T. 250)

40. The only method employed by Lawrence to
neutralize the discharges involved the placement in the
culverts of burlap bags filled with sodium carbonate
briquettes. This treatment did not remove metals or
solids. (N.T. 116-117, 134, 224, 602)

41. The toe of spoil ditch and the sedimentation ponds
constructed by Lawrence on MP5 provided a facility for
the removal of metals and solids from water intercepted
by the ditch; but no similar treatment was administered
to the water that continued to discharge at culverts 2
through 5. (N.T. 171, 181, 222-223, 227, 256)

42. Karl K. Shaeffer, a Water Pollution Biologist for
DER, performed a macro invertebrate study of Buck
Run adjacent to the Rogers Mill Strip and Chanin Strip
on March 20, 1980. This type of study attempts to
measure the quality of a stream as a fishery by
observing the insects resident in the stream. (N.T. 85-89,
388, 392) The March 20, 1980, study disclosed:

22a

(a) that Buck Run met the requirements for a high
quality cold water fishery upstream from a haul
road built by Marsalino in conjunction with the
Chanin Strip operation; (N.T. 402, 406-407)

(b) that Buck Run was somewhat degraded below
Marsalino’s haul road to the point where the
unnamed tributary enters the stream, but still met
the requirements for a high quality cold water
fishery; (N.T. 402, 407, 409)

(c) that Buck Run below the point where the
unnamed tributary enters the stream was degraded
to the extent that the macro invertibrate community
was nonexistent. Siltation and metal deposition on
the substrate were readily observable; (N.T. 402,
407)

(d) that the metal deposition observable in Buck
Run is typical of what occurs when AMD enters a
stream and undergoes a certain amount of
neutralization. (N.T. 408)

43. Karl K. Shaeffer conducted an electrofishing
survey of Buck Run adjacent to the Rogers Mill Strip
and Chanin Strip on October 3, 1980. This type of study
attempts to measure the quality of a stream as a fishery
by stunning the fish, counting them, and identifying
them by species and size. (N.T. 411-414) The October 3,
1980, survey disclosed:

(a) that 75 brook trout of varying sizes, as well as
some other associated cold water species, were found
in that part of Buck Run immediately above the
Marsalino haul road; (N.T. 417)

(b) that 3 brook trout were found in that part of
Buck Run immediately above the Rogers Mill
Bridge; (N.T. 416)

(c) that the fish community in Buck Run below the
confluence with the unnamed tributary had been
almost completely devastated; (N.T. 419)

23a

(d) that Buck Run below the confluence with the
unnamed tributary was affected by AMD, siltation
and metal deposition, all of which is harmful to fish
life; (N.T. 430-432, 436-438)

(e) that surface mining operations were the cause
of the conditions in Buck Run below the confluence
with the unnamed tributary. (N.T. 438-439)

44. The water in the Pirl Spring and the water
discharging at culverts 7, 8, 9 and 10 are unaffected by
surface mining on the Rogers Mill Strip and Chanin
Strip, and represent background water quality for Buck
Run. This water had a P: between 5 and 6; alkalinites
are usually between 10 and 20 parts per million (ppm);
acidities are usually less than 10 ppm; iron, maganese,
and aluminum are ali under 1 pmm. It does not
constitute AMD. (N.T. 497-500, 759-761, 1612)

45. The background water quality of Buck Run is such
that the stream has little or no capacity to handle AMD.
(N.T. 499, 761)

46. Observations and water samplings of Buck Run
and the unnamed tributary on May 12, 1980, established:

(a) that Buck Run was slightly turbid, somewhat
more alkaline and contained a higher concentration
of iron below the confluence with the unnamed
tributary; (N.T. 118-119; CX 33A)

(b) that Buck Run below the confluence with the
unnamed tributary became highly polluted with silt
and iron after a heavy rain shower; (N.T. 120-121;
CX 33A)

(c) that the urnamed tributary reflected increases
in alkalinity and iron as it flowed past the Rogers
Mill Strip and Chanin Strip toward Buck Run; (N.T.
110-115; CX 33A)

(d) that the unnamed tributary near its confluence
with Buck Run was discolored and reflected metal
deposition; (N.T. 115)

24a

(e) that both Marsalino and Lawrence were
treating discharges with sodium carbonate
briquettes on that day, accounting for the increases
in alkalinity in the unnamed tributary and Buck
Kiun; (N.T. 115-116)

(f) that neither Marsalino nor Lawrence was
using any facilities for the removal of solids on that
day, accounting for the increases in iron and
turbidity in the unnamed tributary and Buck Run.
(N.T. 116)

47. Observations and water samplings of Buck Run
and the unnamed tributary on May 13, 1980, established:

(a) that both Marsalino and Lawrence were
treating discharges with sodium carbonate
briquettes on that day; (N.T. 130, 132; CX 33A)

(b) that neither Marsalino nor Lawrence was using
any facilities for the removal of solids on that day;
(N.T. 130, 132; CX 33A)

(c) that the eastern branch of Buck Run below the
confluence with the unnamed tributary had a
yellowish appearance and metal deposition, but the
western branch was very clear; (N.T. 135; CX 33A)

(d) that the condition of the eastern branch of
Buck Run was caused by the inadequate treatment
of the discharges from the Rogers Mill Strip and the
Chanin Strip. (N.T. 135; CX 33A)

48. Observations and water samplings of Buck Run
and the unnamed tributary on May 21, 1980, established:

(a) that both branches of Buck Run above the
confluence with the unnamed tributary were clear
and had no signs of metal deposition; (N.T. 160; CX
33A)

(b) that the eastern branch of Buck Run below the
confluence with the unnamed tributary was slightly
turbid and had metal deposition; (N.T. 160; CX 33A)

(c) that Buck Run below the joinder of the two
branches was slightly cloudy and had metal
deposition. (N.T. 161; CX 33A)

25a

49. Observations and stream samplings of Buck Run
and the unnamed tributary on June 10, 1980,
established:

(a) that both branches of Buck Run above the
confluence with the unnamed tributary were very
clear; (N.T. 175; CX 33A)

(b) that the eastern branch of Buck Run below the
confluence with the unnamed tributary was slightly
turbid; (N.T. 175; CX 33A)

(c) that the unnamed tributary at its mouth was
turbid and alkaline. (N.T. 175, CX 33A)

50. On July 1-2, 1980, the eastern branch of Buck
Run was clear above the confluence with the unnamed
tributary and turbid below it. (N.T. 200, 209-213, CX
14C-CX 14H)

51. On July 22-23, 1980, silt deposits were in the
unnamed tributary and in Buck Run below the
confluence with the unnamed tributary. (N.T. 233)

52. Observations and water samplings established
that Lawrence's discharges into Buck Run and the
unnamed tributary exceeded effluent limitations for the
total suspended solids on March 20, 1980, May 12-13,
1980, May 21, 1980, June 10, 1980, July 1-2, 1980, and
July 22-23, 1980. (N.T. 90, 96-123, 125-135, 151-161, 172-
179, 198-199, 209-223, 233-237; CX 8; CX 9; CX 10; CX
14C; CX 14D; CX 14E; CX 33A)

53. Buck Run (for a couple of miles below the
unnamed tributary) and the unnamed tributary itself
were degraded by the surface mining operations of both
Lawrence and Marsalino. (N.T. 438-439, 461)

54. Lawrence's discharges, taken alone, or
Marsalino’s discharges, taken alone, were sufficient to
degrade these waterways. Taken together, they had a
cumulative effect. (N.T. 473-474)

26a

55. The surface mining operations of Lawrence and
Marsalino are the only apparent sources of AMD flowing
into culverts 2 through 5. (N.T. 870-871)

56. The Pennsylvania Fish Commission ceased
stocking Buck Run after the 1978 fishing season,
primarily because of the AMD caused by Marsalino’s
operation on the Chanin Strip. At that time, there were
no discerible discharges from the Rogers Mill Strip. (N.T.
555-557, 559-564, 1853)

57. From 1978 through 1981 there was little fishing
done on Buck Run below the confluence with the
unnamed tributary. (N.T. 1846-1848)

58. Samples of water in the toe of spoil ditch, taken
on July 1-2, 1980, and July 22, 1980, had the
characteristics of AMD and were similar in chemical
composition to the water discharging at the culverts,
with the exception of iron. Iron concentrations were
higher in the ditch water than in the culvert water. (N.T.
241-245, 865-866, 1070-1072; CX 17A; CX 33A)

59. Lawrence’s pit floor dipped, in part, toward
Pirl Spring Road and, in part, toward Fish
Hatchery Road. Initially, water flowed across
the pit floor at a 45 degree angle away from the
highwall and toward Pirl Spring Road. Later, it tended
to flow toward the highwall and into the corner formed
by the highwall and the northern endwall. (N.T. 260-263,
717)

60. Lawrence’s pit floor water was analyzed in 1977,
1980, 1981 and 1982 and determined to be AMD. (N.T.
150, 1069; CX 18)

61. On May 13, 1980, Mr. Frederick informed
Lawrence personnel that reject material was to be buried
above the level of the pit floor to reduce the possibility
of contaminating pit floor water. (N.T. 124-125, 375-380)

27a

62. Lawrence continued to pile reject material on the
pit floor on June 10, 1980, and on July 1-2; 1980. (N.T.
171, 219-220; CX 14P)

63. The surface mining of coal disturbs the normal
flow of groundwater in the overburden. During and after
the removal of coal, groundwater tends to penetrate to
the pavement below the point where the coal seam was
located and to discharge at the crop line. (N.T. 769-770)

64. Groundwater also may penetrate into the rock
strata lying below the point where the coal seam was
located. (N.T. 777)

65. Water flowing into the toe of spoil ditch and into
culverts 2 through 5 represents both crop line discharges
and discharges from below the crop line. (N.T. 782)

66. The roll in the main seam in the vicinity of the
Haul Road diverts groundwater toward culvert 4 (at a
point below the crop line of the main coal seam where a
dead tree is the predominant landscape feature). This
groundwater was intercepted by the toe of spoil ditch
after it was constructed. (N.T. 798-799, 884-885)

67. Water that discharges into the toe of spoil ditch
previously flowed off the Rogers Mill Strip and was
affected by Lawrence’s surface mining operations. (N.T.
801, 1029)

68. Water that continued to discharge into culverts 2,
3, 4, and 5 after construction of the toe of spoil ditch
flowed off the Rogers Mill Strip, but may have had its
source, in part, on the Chanin Strip. The water was
affected both by Lawrence’s and by Marsalino’s surface
mining operations. (N.T. 808-812, 1031-1036)

28a

69. There is a hydrologic connection between water
disturbed by Lawrence’s surface mining operation on the
Rogers Mill Strip and water discharged at culverts 2
through 5. (N.T. 487-494, 579-580, 782, 808-812, 838-844,
884-885, 1029-1036, 1633; CX 28)

70. Lawrence has acknowledged that some of the
water that previously flowed to culvert 4 before
construction of the toe of spoil ditch originated on the
Rogers Mill Strip. (N.T. 487-488, 1162-1163, 1283, 1632-
1633)

71. Lawrence has acknowledged that it never
performed any analysis of the water discharging at
culverts 2 through 5. (N.T. 1512-1513)

72. A study of Buck Run in 1981 and 1982
established:

(a) that fish and macro invertebrates were
reestablished in that part of Buck Run below the
confluence with the unnamed tributary; (N.T. 451-
457, 1674-1676)

(b) that metal deposition still existed in that part
of Buck Run below the confluence with the unnamed
tributary, but that recovery was taking place; (N.T.
455)

(c) that the recovery of Buck Run was attributable
directly to the reduction or elimination of discharges
of AMD, silt and metals from the Rogers Mill Strip
and the Chanin Strip; (N.T. 457)

(d) that, given the status quo, Buck Run will be
rr id restored in three to five years. (N.T. 460-

461
73. On September 4, 1980, Lawrence did not have a
toe of spoil ditch on the Spruell Strip, had not
constructed sedimentation ponds in accordance with
plans approved by DER and was not providing separate

29a

treatment in the sedimentation ponds. There was
evidence of sediment runoff from the site into a tributary
of Morgan Run. (N.T. 269-270, 274)

74. On September 4, 1980, Lawrence allowed a
discharge of AMD to flow from the Spruell Strip into a
tributary of Morgan Run. (N.T. 270, 274)

75. On September 15, 1980, Lawrence had spoils piled
on the Kennedy Strip within several feet of Dickerson
Run. (N.T. 275-276)

DISCUSSION
DER had brought this action under Section 605 of the
CSL, 35 P.S. §691.605. During the time period covered
by the alleged violations, Section 605 read, in pertinent
part, as follows:

“In addition to proceeding under any other
remedy available at law or in equity for a violation
of a provision of this act, rule, regulation, order of
the department, or a condition of any permit issued
pursuant to this act, the department, after hearing,
may assess a civil penalty upon a person or
municipality for such violation. Such a penalty may
be assessed whether or not the violation was wilful.
The civil penalty so assessed shall not exceed ten
thousand dollars ($10,000) per day for each violation.
In determining the amount of the civil penalty the
department shall consider the wilfullness of the
violation, damage or injury to the waters of the
Commonwealth or their uses, cost of restoration,
and other relevant factors... .”’

DER has the burden of proving by a preponderance of
the evidence that Lawrence committed violations of the
CSL and that civil penalties should be assessed: 25 Pa.
Code §21.101(b)(1).

30a

Count I—-AMD

In Count I of its Complaint, DER alleged that
Lawrence discharged AMD from the MP5 portion of the
Rogers Mill Strip into Buck Run and its tributaries. The
discharges were alleged to have been continuous,
specifically including the following dates: January 23,
February 28, May 13, May 21, May 27, June 2, June 10,
July 1, July 2, July 7, July 22, July 23, August 14,
October 10, October 23, November 17, all in 1980, and
January 7, and January 28 in 1981. In its post-hearing
brief, DER abandoned entirely the period following
October 10, 1980, and eliminated the claim of continuous
discharges for the period subsequent to May 27, 1980.

There is no dispute about the fact that discharges at
culverts 2 through 5 constituted AMD. There is serious
dispute, however, about the source of those discharges.

DER points, inter alia, to the following evidence
linking those discharges to Lawrence’s surface mining
operation on the MP5 area of the Rogers Mill Strip:

1. the discharges emanated from MP5;

2. the discharges at culverts 2, 3, and 4 were
traced to the toe of spoil on MP5;

3. construction of the toe of spoil ditch on MP5
reduced the flows at culverts 2, 3 and 4;

4. Lawrence mined MP5 above culverts 2
through 5;

5. the discharges at culverts 7 through 10 are not
AMD;

6. the water discharged at culverts 2 through 5
is chemically similar to the water on MP5;

7. there is no other logical source of AMD than
the surface mining operations of Lawrence on MP5
and Marsalino on the Chanin Strip.

3la

Lawrence disputed much of this evidence. Its
witnesses maintained that the discharges could not have
been traced to the toe of spoil on MP5; that the water
discharged at the culverts is chemically different in
certain respects from the water on MP5; that there is no
geologic mechanism on MP5 that would enable water to
penetrate below the crop line of the main seam; and that
the water discharged from MP5 constituted AMD before
any surface mining had been done.

Much time could be devoted to weighing the evidence
on each of these disputed points, resolving the many
conflicts and attempting to reach sensible conclusions.
That is unnecessary, in my judgment, because
Lawrence’s evidence failed to address several decisive
points in DER’s case.

The first of these pertains to the flow of water at
culverts 2, 3 and 4. DER’s undisputed evidence is that
such flows diminished substantially but not completely
after the toe of spoil ditch was constructed. This fact is
strong evidence that some hydrologic connection existed
between the MP5 area and culverts 2, 3, and 4. While
Lawrence’s experts went to great lengths to disprove
any connection, they offered no explanation at all for the
reduction in flows.

Lawrence’s experts also were hardpressed to explain
why discharges at culverts 2, 3, 4 and 5 constituted
AMD while discharges at culverts 7, 8, 9, and 10 did not.
The latter culverts all were along and down gradient
from Marsalino’s Chanin Strip; and yet the discharges
showed no evidence of AMD. Beginning with culvert 5,
however (just 300 feet or so away), and continuing
downgrade to culvert 2, the discharges are AMD. This
evidence clearly points primarily to Lawrence, and not to
Marsalino, as the generator of the condition.

32a

Lawrence's witnesses attempted to establish that the
discharges at culverts 2 through 5 cannot originate on
MP5 because they emanate from below the crop line of
the main seam which Lawrence mined. The pavement
below the main seam, these witnesses contend, is
impermeable, preventing any vertical percolation of
AMD from Lawrence’s operation. The only other
currently possible source of these discharges would be
Marsalino; but that operator mined the same coal seam
as Lawrence and as close as one hundred feet upgrade
from Lawrence’s south endwall. If AMD could not
percolate below that coal seam on Lawrence’s site, it is
unlikely that it could have done so on Marsalino’s.
Lawrence’s final rationale maintains that discharges
from MP5 were AMD prior to any mining activity at all.
Aside from the fact that this is possible, the only
evidence to support the argument is a comment
supposedly made by a former DER inspector in 1975 and
overheard by the man who now is Lawrence's foreman.
After securing a sample of water from the ditch along
Pirl Spring Road, the inspector reportedly said that he
had not found any good water in the vicinity.

At best, this evidence provides feeble support for
Lawrence’s position. It loses even this significance when
measured against other evidence. It is undisputed that
Buck Run was classified as a high quality cold water
fishery and was stocked with trout by the Pennsylvania
Fish Commission before any surface mining began on
nearby land. After the 1978 season, Buck Run was taken
off the stocking list because the portion of it below the
confluence with the unnamed tributary had degraded to
the point where macro invertebrates were completely
absent. While this action was taken as a result of
Marsalino’s operation on the Chanin Strip (which was
cited for AMD discharges in 1979), the evidence

33a

substantiates the fact that Buck Run was not degraded
prior to 1979. This means that there could not have been
any appreciable volume of AMD entering the stream
from the Rogers Mill Strip, the Chanin Strip or any other
source.

If the water in the ditch along the Pirl Spring Road
had any negative characteristics when tested by the
DER inspector in 1975, the nature of the contaminant
and the volume of the discharge obviously were not
enough to impact Buck Run. This fact is reinforced by
the testimony of Terry Confer, a DER inspector, who
walked the Pirl Spring Road with Lawrence’s foreman on
July 24, 1979, and could find no discharges at all from
the Rogers Mill Strip. Six months later, when the flows
at culverts 2 through 5 amounted to thousands of
gallons per day, the impact of Buck Run was
devastating. Clearly, these discharges were caused by
Lawrence’s surface mining operation and exceeded in
volume and, perhaps, in potency any AMD that
previously might have originated from the Rogers Mill
Strip.

DER had not shown the precise mechanism by which
AMD migrated below the crop line of the main seam on
the Rogers Mill Strip, has not explained the disparity in
iron concentrations revealed by the water samples, and
has not shown a precise breakdown of the volumes of
AMD contributed by Lawrence’s operation and by
Marsalino’s operation.’ Nonetheless, the evidence
connecting Lawrence’s operation to the discharges of
AMD at culverts 2 through 5 is overwhelming.
Lawrence, in fact, has admitted to part of it.

' DER’s pollution loading calculation, which attempts to estimate the
pounds per day of pollutants discharging at the culverts along Pirl
Spring Road, assigns about 50% of the total pollutior load to
Lawrence. See CX 29, CX 30 and CX 31.

34a

The burden of proof in a case like this does not require
that every stone be turned, that every detail be
completely explained. Evidence can be compelling and
overpowering even though it is circumstantial. Dillsburg
Septic Service v. DER, 1976 EHB 184; DER v. Bucks
County Water and Sewer Authority and The Korman
Corp., 1975 EHB 414. The circumstantial evidence of a
hydrologic connection in this case, unlike that in
Hepburnia Coal Company v. DER, 1986 EHB 563, rises
to that level and implicates Lawrence. The fact that
Marsalino also may be at fault does not exonerate
Lawrence. Lawrence is responsible for all discharges
caused by its surface mining operation, even though
some of the AMD may originate off the Rogers Mill
Strip. Commonwealth v. Barnes & Tucker Company, 472
Pa. 115, 371 A.2d 461 (1977); Commonwealth v. Harmar
Coal Company, 452 Pa. 77, 306 A.2d 308 (1973).

DER has carried its burden of proving that the
discharges from culverts 2, 3, and 4 violated the effluent
limitations contained in DER’s regulations and in
Lawrence’s MDP on a number of dates in 1980. DER
maintains that the discharges were continuous from
January 23, 1980, to May 27, 1980. The evidence shows
that during this period, laboratory samples and/or field
P, tests were run on each of these culverts on January
23, 1980, February 28, 1980, March 12, 1980, March 20-
21, 1980, May 13, 1980, and May 21, 1980. In every
instance, the discharges violated the effluent limitations
in one or more respects. Treatment was being provided
by Lawrence only on one of those dates, May 13, but the
metals were not being affected.

? The evidence could support a conclusion that the discharges were
continuous to a date beyond May 27, 1980; but, since DER has not
made such a claim, the Board will not impose it.

35a

The flows at culverts 2, 3, and 4 did not diminish
significantly until construction of the toe of spoil ditch
began on May 27, 1980. It is reasonable to conclude that,
up to that point, the discharges were flowing
continuously into the culverts. It is also reasonable to
conclude that, since this water was not diverted to
sedimentation ponds until after May 27, 1980, the metals
were never treated in any manner prior to that time.
Since the concentrations of metals consistently exceeded
effluent limitations when they were measured prior to
May 27, it is reasonable to conclude that they did so on
every day.

DER claims that, for the period following May 27,
1980, the discharges at culverts 2, 3 and 4 exceeded
effluent limitations only on the actual dates when DER
inspected the Rogers Mill Strip. However, there were
some inspections when no laboratory or field tests were
done. When these are excluded, the pertinent dates for
culverts 2 and 4 are the following dates in 1980: June 10,
July 1-2, July 7, July 22-23, August 14 and October 3.
For culvert 3 they are June 10, July 1-2, July 22-
23, August 14 and October 3. The evidence establishes
that, on these dates, the discharges violated the effluent
limitations in one or more respects.

In summation, Lawrence’s discharges from the Rogers
Mill Strip into Buck Run or the unnamed tributary
violated effluent limitations for 125 days between
January 23, 1980, and May 27, 1980, and for a maximum
of 6 days between May 28, 1980, and October 10, 1980.

DER acknowledges that it vacillated on culvert 5,
charging Lawrence with the duty to treat that discharge
only for a period June 11, 1980, to June 30, 1980, and for
a period September 10, 1980 to October 10, 1980. While

36a

DER claims that the discharges were continuous during
these two periods, aggregating 52 days, water samples
were taken only on October 3, 1980. There is no question
that the discharge on that date exceeded effluent
limitations, but to extrapolate that one instance into 52
days would be highly inappropriate. Moreover, Lawrence
already has been charged with unlawful discharges on
October 3, 1980, at culverts 2, 3 and 4. The fact that the
culvert 5 discharge also was unlawful! on that date does
not add another day to the total.

In its Complaint, DER charged Lawrence with
discharging AMD into the waters of the Commonwealth
from the Spruell Strip ‘at all times material to the
Complaint, including September 4, 1980....”° In its
Motion to Amend Complaint to Conform to Proof, DER
requests that the allegation with respect to AMD at the
Spruell Strip be limited to September 4, 1980. Since the
evidence in the record concerns only that one date,
DER’s Motion is granted.

DER’s evidence firmly establishes the fact that
Lawrence allowed AMD to discharge from the Spruell
Strip on September 4, 1980. Lawrence presented no
evidence to the contrary. Accordingly, I conclude that
Lawrence violated its effluent limitations on discharges
from the Spruell Strip on one day.

In its Complaint, DER alleges that tne discharges of
AMD constitute violations of Sections 3, 301, 307, 315
and 401 of the CSL, Sections 77.92(c), 99.33a), (b) and (c)
of DER’s regulations in 25 Pa. Code, and Standard
Conditions 10, 11 and 12 of Lawrence’s mine drainage
permits. All statutory and regulatory citations, of course,
relate to those in effect during the period January 23,
1980, to October 10, 1980.

37a

Section 3 of the CSL, 35 P.S. §691.3, declares the
discharge of industrial waste into the waters of the
Commonwealth, causing or threatening pollution, to be a
public nuisance. Mine drainage is specifically included in
the definition of ‘industrial waste’ in Section 1 of the
CSL, 35 P.S. §691.1. Section 301, 35 P.S. §691.301,
prohibits the discharge of industrial waste, except as
provided later in the statute. Section 307, 35 PS.
§691.307, prohibits the discharge of industrial waste
unless it is pursuant to a permit from DER or in
accordance with DER regulations. Section 315, 35 P.S.
$691.315, prohibits any discharge from a mine unless it
is pursuant to a permit from DER and in accordance
with DER regulations. Section 401, 35 P.S. §691.401,
declares it to be unlawful to pollute the waters of the
Commonwealth by the discharge of any substance of any
kind.

25 Pa. Code $77.92(c) sets forth water quality criteria
for permittees under the CSL. Petinent to this
discussion are requirements that discharges of mine
drainage have a P., between 6 and 9 and no
concentrations of iron exeeding 7 milligrams per liter. 25
Pa. Code $99.33(a), (b) and (c), which also relate to mine
drainage, impose the additional requirement that the
discharge not be acid. These same effluent limitations are
incorporated into Lawrence's mine drainage permits as
Standard Conditions 10, 11 and 12.

Certainly Lawrence's discharges violated all of these
provisions.

Count II]—Erosion and Sedimentation Controls

In Count II of the Complaint, DER alleged that
Lawrence failed to implement and maintain effective
erosion and sedimentation (E&S) control measures on the

38a

MP5 portion of the Rogers Mill Strip, resulting in the
conveyance of sediment into Buck Run and its
tributaries. The discharges were alleged to have been
continuous, specifically including the following dates:
February 28, May 13, May 21, May 27, June 2, June 10,
July 1, July 2, July 7, July 22, July 23, August 14,
October 3, all in 1980, and January 26, 1981.

In the Application for leave to Amend Complaint filed
by DER on July 6, 1982, DER sought to revise the
allegations in Count II to include discharges emanating
from MP5A. The Application was denied by former
Board Chairman Harnish, as stated in the procedural
history portion of this Adjudication, but testimony
relating to the inadequacy of E&S controls on MP5A
was admitted into the record. DER again sought to
include the MP5A violations in the Complaint in its
Motion to Amend Complaint to Conform to Proof filed
after the hearings were concluded.

The precise scope of Harnish’s ruling is not clear, from
the record. Nonetheless, the ruling denied DER’s
Application to Amend and, on its face, appeared to
exclude E&S violations on MP5A from the case. Even
though some testimony on these violations was
introduced and even though Lawrence has made no claim
of being prejudiced by DER’s post-hearing Motion to
include them, I am not convinced that the subject was
fully litigated. Accordingly, I deny DER’s Motion to
Amend with respect to alleged E&S violations on MP5A
and refuse to consider them in assessing civil penalties
against Lawrence.

The evidence discloses that Lawrence’s MDP required
the construction of a toe of spoil ditch prior to
commencement of any mining operations. The primary
purpose of this ditch was E&S control. Lawrence

39a

commenced mining without having constructed the
ditch, relying instead on the grading of roads to keep
surface runoff on the site. No DER inspector had
complained about the absence of the toe of spoil ditch
until February 28, 1980, when Mark Frederick ordered
that it be dug. It is clear that Mr. Frederick's chief
concern at that time was not E&S but AMD. He directed
that the ditch be dug long enough and deep enough to
intercept the discharges flowing to culverts 2, 3 and 4.

E&S problems on MP5 became a concern on March 20,
1980, when a heavy discharge of muddy water was
observed flowing from the Haul Road into Buck Run.
Subsequently, on May 12-13, May 21, June 10, July 1-2
and July 22-23, in 1980, observations and water
samplings revealed that discharges from MP5 into Buck
Run and the unnamed tributary exceeded the effluent
limitation for total suspended solids.

Lawrence began constructing the toe of spoil ditch on
May 27, 1980. By July 1, 1980, the ditch and the two
sedimentation ponds to which it connected were
completely installed. These facilities provided effective
E&S controls for much of the discharge emanating from
culverts 2, 3 and 4. In addition, since the flows at those
culverts significantly lessened after the ditch was dug
and deepened, the amount of silt washing off the site
was also reduced. In fact, on July 7, 1980, the flows at
culverts 3 and 4 were so low that laboratory samples
were not taken; and the total suspended solids measured
at the culvert 2 discharge were within effluent
limitations.

The failure to have effective E&S controls on MP5 was
continuous from March 30, 1980, when the toe of spoil
ditch was supposed to have been in place
pursuant to Mr. Frederick’s order, to July 1,
1980, when the E&S facilities were completely
installed. March 20, 1980, must be considered

40a

an isolated violation since it occurred prior to the
compliance date mandated by Frederick. Likewise, July
22-23, 1980, must be treated apart from the continuous
violations, since there was a period earlier in July when
E&S controls were working effectively. The violations
cover a total of 95 days.

In its Complaint, DER also charged Lawrence with
E&S violations at the Spruell Strip ‘“‘on dates including
but not limited to September 4, 1980.’’ In its Motion to
Amend Complaint to Conform to Proof, DER seeks to
revise its allegation with respect to the Spruell Strip so
as to limit it to September 4, 1980. Since the only
evidence presented concerned this date alone, the
amendment will be allowed.

DER proved that on September 4, 1980, Lawrence had
not constructed a toe of spoil ditch on the Spruell Strip,
as required by its mine drainage permit, and there was
evidence of sediment runoff into a tributary of Morgan
Run. Lawrence made no attempt to dispute these facts.
Accordingly, I conclude that Lawrence violated the E&S
requirements of its permit pertaining to the Spruell Strip
on one day.

DER’s Complaint alleges that Lawrence's failure to
implement and maintain effective E&S controls resulted
in the conveyance of sediment into the waters of the
Commonwealth, including Buck Run, which
contamination has destroyed Buck Run’s capacity to
support benthic macro invertebrate and other aquatic
communities. In its Motion to Amend Complaint to,
Conform to Proof, DER proposes to revise this
allegation so as to limit it to the MP5 and MP5A
portions of the Rogers Mill Strip.

4la

As already noted, the inclusion of MP5A at this late
point in the proceedings is not appropriate. However, the
only evidence of stream pollution presented by DER
relates to Buck Run and the unnamed tributary. No
evidence concerning the tributary to Morgan Run
appears in the record. Consequently, DER’s Motion to
Amend will be granted to the extent that it limits the
allegation of stream pollution to E&S violations on MP5.

These violations, according to the Complaint, are
contrary to the provisions of Sections 3, 301, 307, 315
and 401 of the CSL, the provisions of 25 Pa. Code
§102.4(a) and Standard Condition No. 3 of Lawrence's
mine drainage permits. It should be noted, at this point,
that ‘industrial waste’ as defined in Section 1 of the
CSL, 35 P.S. §691.1, includes ‘‘silt, coal mine solids, rock,
debris, dirt and clay from coal mines...."
Thus, the provisions of Sections 3, 301 and 307 of the
CSL, as applied previously with respect to AMD, is
equally applicable to the discharges caused by the E&S
violations.

Section 315 of the CSL, 35 P.S. §691.315, which
prohibits mining operations or discharges except in
accordance with a permit and DER regulations, also
applies. 25 Pa. Code §102.4(a) requires the
implementation of E&S controls to minimize accelerated
erosion and sedimentation. Standard Condition No. 3 of
Lawrence’s mine drainage permits mandates that no silt,
coal mine solids, rock, debris, dirt and clay be washed,
conveyed or otherwise deposited into the waters of the
Commonwealth. Lawrence clearly has violated these
provisions.

Section 401 of the CSW, 35 P.S. §691.401, the ‘‘catch-
all” provision that prohibits pollution by any substance
of any kind, also has been violated by Lawrence's failure
to provide effective E&S controls.

42a

Count III—Improper Disposal of Toxic Material

In Count III of the Complaint, DER alleges that
Lawrence failed to properly dispose of acid-bearing
material ‘‘at the site covered by Mining Permit No. 1063-
5 and amendments on dates including but not limited to
May 12, 1980; and has caused degradation of the
waters of the Commonwealth.

DER’s_ evidence involved only M25; so it is
unnecessary to discuss any allegations concerning
MP5A. The evidence presented shows that Mark
Frederick observed on May 13, 1980, that Lawrence was
disposing of acid and toxic bearing materials on the floor
of the pit against the spoils. Lawrence’s foreman told
him that the previous DER inspector had approved that
method of handling reject material. Mr. Frederick
examined Lawrence’s MDP and _ concluded that
Lawrence's method violated Standard Condition No. 29.
He ordered Lawrence to change its method of handling
this type of material. Mr. Frederick observed that
Lawrence had not changed its handling method on June
10, 1980, or on July 1-2, 1980.

As noted above, DER charged in the Complaint that
these alleged violations occurred on dates including but
not limited to May 12, 1980, but no evidence was
presented concerning that date. In its post-hearing brief,
DER states that the alleged violations occurred on May
13, June 6, June 16, and July 1, all in 1980, and were not
continuous. But there is no testimony whatever
concerning June 6 and June 16. The only dates for which
there is any testimony on this subject are May 12, June
10 and July 1-2.

DER claims that Lawrence’s handling method violated
Standard Condition No. 29 of the MDP. However, the
precise language of this Standard Condition is not part

43a

of the record. Mr. Frederick testified that Lawrence’s
handling method ‘was indeed contrary to the permit”
(N.T. 125), and Lawrence made no attempt to show that
it was not. Consequently, I conclude that Standard
Condition No. 29 of the MDP was violated by
Lawrence’s method of handling reject material.

DER concedes that these violations did not directly
cause any injury to waters of the Commonwealth, but
argues that they may have contributed to the AMD
discharges from MP5. In the Complaint, DER alleged
violations of Sections 315 and 402 of the CSL, in addition
to Standard Condition No. 29 of the MDP. Section 315,
35 P.S. §691.315 prohibits the operation of a mine except
in accordance with a DER permit and DER regulations.
Section 402, 35 P.S. §691.402, provides for regulatory
control over activities creating a danger of water
pollution. Since DER has not cited any regulation
governing the handling of reject materials in a mining
operation, Section 402 is not in issue.

The record does establish, however, that Lawrence
violated the MDP and Section 315 of the CSL on a total
of three days.

Count I1V—Disturbing Land Designated as a Barrier

In this Count, DER alleged that on September 5, 1980,
Lawrence disturbed land within 75 feet of a stream on
the Kennedy Strip by pushing spoils and rock onto the
area. This is alleged to be a violation of Standard
Condition No. 35 of Lawrence’s Mine drainage permit
and of Section 315 of the CSL, 35 P.S. §691.315.

The only evidence presented by DER on this subject
involved September 15 and not September 5, as alleged
in the Complaint. DER made no request to amend this
Count in its Post-hearing Motion to Amend Complaint to

44a

Conform to Proof. As a result, the allegations of the
Complaint remain in effect and have not been proved.
This Count, accordingly, will be disregarded.

Assessment of Civil Penalty

Section 605 of the CSL, 35 P.S. §691.605 (quoted at
the outset of this Discussion), requires the Board to
consider the following factors in determining the amount
of a civil penalty:

i. wilfullness of the violation;

2. damage or injury to the waters of the
Commonwealth or their uses;

3. cost of restoration; and
4. other relevant factors.

The Board has interpreted the last factor to include
deterrence. DER v. Jefferson Township, 1978 EHB 134.
No evidence has been presented on the cost of restoration;
so that factor will be excluded.

The Board has discussed wilfullness in a number of
prior opinions, especially in DER v. Rushton Mining Co.,
1976 EHB 117. In that case the Board observed that
there is a degree of wilfullness evident from the
knowledge that certain consequences are likely to result
from a particular action or failure to act. Lawrence's
AMD discharges from MP5 certainly involved this level
of wilfullness from January 23, 1980, when first informed
of them, until July 1, 1980, when the toe of spoil ditch
had been dug deep enough and long enough to intercept
most of the flow going to culverts 2, 3 and 4. Only four
instances of unlawful discharges occurred subsequent to
July 1, 1980. These involved flows that continued to
emanate from MP5 despite the efforts previously
devoted to intercepting them. While Lawrence's

45a

responsibility was no different with respect to these
flows than it was with respect to those previously
discharged, the wilfullness does not seem to rise to the
same level.

The circumstances surrounding the AMD discharge at
the Spruell Strip were not developed on the record to any
great extent. Therefore, it is not possible to assign a
level of wilfullness to this discharge.

Lawrence’s failure to construct the toe of spoil ditch to
provide E&S controls on MP5, which was required by its
permit, until months after being ordered to do so by
DER rises to a high level of wilfullness and constitutes
nearly intentional conduct. Lawrence's failure is more
egregious with respect to E&S violations than with
respect to AMD violations because the primary purpose
of the ditch was E&S control. While Lawrence's
resistance to digging the ditch deep enough and long
enough to intercept groundwater flowing to the culverts
is perhaps understandable (but not excusable), there is
absolutely no reason why it did not immediately
construct the ditch in order to stop surface runoff. This
wilfullness on Lawrence’s part must be deemed to have
affected all of the E&S violations on MP5 except for the
one on March 20, 1980, before the ditch was required to
be installed, and the one on July 22-23, after the toe of
spoil ditch and sedimentation ponds had been completely
installed.

As with the AMD discharge, the circumstances
surrounding the E&S violation at the Spruell Strip are
not sufficiently developed in the record to enable a
determination to be made as to whether it was wilfull.

Lawrence is charged with improperly handling reject
materials on three days. Apparently, Lawrence was not
aware that its method was improper until the violation

iid

46a

was observed on the first day. That violation cannot be
viewed as wilfull; but the other two subsequent
violations are inexcusable.

DER presented an overwhelming array of evidence to
show the injury done to Buck Run and the unnamed
tributary by Lawrence’s discharges of AMD, metals and
suspended solids. While Lawrence’s witnesses attempted
to soften the force of this evidence, it remained basically
untouched. The combined effects of AMD, metals and
suspended solids rendered Buck Run unsuitable as a
fishery. It is true that Marsalino’s discharges had
created the first significant impact on Buck Run and had
prompted the Pennsylvania Fish Commission to remove
it from the stocking list. Nonetheless, Lawrence's
discharges added to the problem and, most assuredly,
prolonged the recovery period for the stream. DER’s
witness estimated in 1982, two years after the date when
Lawrence finally began to take some steps to control the
discharges, that it would take another three to five years
for Buck Run to recover to its pre-mining condition. On
the other hand, Lawrence’s witness maintained that
neither Buck Run nor the unnamed tributary showed any
signs of degradation in 1982. This opinion is of
questionable value since this witness did not believe that
the two streams had ever been seriously degraded in the
first place.

The preponderance of the evidence clearly proves that
Buck Run and the unnamed tributary were seriously and
adversely affected by Lawrence’s discharges and that the
use of Buck Run as a fishery was interrupted for a
period of years.

In its post-hearing brief, DER submits. that
Lawrence’s degrading of Buck Run and the unnamed
tributary is a violation of Section 401 of the CSL, 35 P.S.

Pita aetna ania

47a

§691.401, separate and distinct from the violations of
other sections of the CSL and DER’s regulations.
Lawrence argues that the violations merge. DER’s
position is legally correct, although its impact on the
final outcome of this case is not significant. Violations of
regulations and permit conditions can occur even if they
do not result in the degradation of waters of the
Commonwealth. Section 401 of the CSL, already referred
to in this Adjudication as a ‘‘catch-all’’ provision, was
intended to prohibit water pollution by whatever means,
whether the activity is lawful or not. Accordingly, there
can be a viclation of Section 401 even if no other sections
of the CSL are involved.

DER presented no evidence to show what, if any,
impact the discharges of AMD and suspended solids
from the Spruell Strip had on the waters of the
Commonwealth. Likewise, it presented no evidence to
establish that the improper handling of reject materials
on MP5 polluted the waters of the Commonwealth.
Accordingly, that factor will not be considered in
determining civil penalties for these violations.

Fashioning a civil penalty containing an element of
deterrence is appropriate in this case because of the
dramatic effect discharges of AMD, metals and
suspended solids have on streams like Buck Run that are
uniquely suited for the propagation of native brook trout
and the accommodation of introduced species. The
delicate ecosystem of such streams is easily devastated;
and restored, if at all, only by the slow, painstaking work
of Mother Nature.

The problem posed by the present case is the total
absence of evidence on which to base a meaningful
decision that will serve as a deterrent to Lawrence and
to others. There is no evidence of Lawrence’s net worth;

48a f

no evidence of the amount of money Lawrence saved by
not implementing control measures earlier than it did; no
evidence of the cost of injury to Buck Run or the cost of
restoring it; no evidence of any kind to suggest an
amount of civil penalty that would deter Lawrence from
similar actions in the future. Absent such evidence, we
are left only with a very generalized approach to
deterrence whereby something more than a “nominal’’
amount is assessed. Since the nature and extent of
Lawrence's violations already demand something more
than a nominal penalty, deterrence cannot be much of a
factor in determining the final amount.

The discharges of AMD from the Rogers Mill Strip
warrant a civil penalty of $500 for each of the days of
continuous violations from January 23, 1980, to May 27,
1980, and for June 10, 1980, and July 1-2, 1980, when
the toe of spoil ditch was completed. The discharges of
AMD subsequent to that date, not rising to the same
level of wilfullness, warrant a civil penalty of $450 each.
Since the record is not as complete with respect to the
discharge of AMD at the Spruell Strip, a civil penalty of
$350 will be assessed for that one day’s violation.

The violations of E&S controls at the Rogers Mill Strip
were not as serious in nature as the discharges of AMD.
However, the wilfullness of the continuing violations
from March 30, 1980, to July 1, 1980, rises to a higher
level than that for AMD. Accordingly, 4 civil penalty of
$400 is appropriate for those 93 days while a civil
penalty of $250 is appropriate for the two remaining
days. Circumstances surrounding the E&S violation at
the Spruell Strip, being equally as uncertain as the AMD
discharges at that Strip, a civil penalty of $200 is all
that seems appropriate.

49a

Lawrence’s improper handling of toxic material cannot
be considered serious violations since DER did not show
any impact on waters of the Commonwealth.
Accordingly, a civil penalty of $100 is all that should
properly be imposed for the first day’s violation. Since
the other two days involve a higher element of
wilfullness, however, a civil penalty of $200 will be
imposed for each of those days.

CONCLUSIONS OF LAW

1. The Board has jurisdiction over the parties and the
subject matter of this appeal.

2. DER has the burden of proving by a
preponderance of the evidence that Lawrence violated
the CSL and that civil penalties should be assessed.

3. The AMD discharges at culverts 2, 3 and 4
emanated from Lawrence’s MP5 area, were affected by
Lawrence’s surface mining operations on the MP5 area,
and constituted violations of Sections 3, 301, 307, 315
and 401 of the CSL, 35 P.S. §§691.1 et seq., Sections
77.92(c), 99.33(a), (b) and (c) of DER’s regulations in 25
Pa. Code, and Standard Conditions 10, 11 and 12 of
Lawrence’s MDP.

4. The unlawful discharges of AMD at culverts 2, 3
and 4 were continuous for 125 days from January 23,
1980, to May 27, 1980, and intermittent on six days
between May 28, 1980, and October 10, 1980.

5. The AMD discharges at culvert 5 emanated from
Lawrence’s MP5 area, were affected by Lawrence's
surface mining operations on MP5, and constituted
violations of Sections 3, 301, 307, 315 and 401 of the
CSL, 35 P.S. §§691.1 et seq., Sections 77.92(c), 99.33(a),
(b) and (c) of DER’s regulations in 25 Pa. Code, and
Standard Conditions 10, 11 and 12 of Lawrence’s MDP.

50a

6. The unlawful discharges of AMD at culvert 5,
during the periods when DER held Lawrence solely or
jointly responsible for them, occurred only on one date
and that date coincided with unlawful discharges of
AMD at one or more of the other culverts.

7. On September 4, 1980, a discharge of AMD
emanated from Lawrence’s Spruell Strip, was affected by
Lawrence's surface mining operations on the Spruell
Strip, and constituted violations of Sections 3, 301, 307,
315 and 401 of the CSL, 35 P.S. §§691.1 et seq., Section
77.92(c), 99.33(a), (b) and (c) of DER’s regulations in 25
Pa. Code, and Standard Conditions 10, 11 and 12 of the
mine drainage permit for the Spruell Strip.

8. Lawrence’s failure to implement and maintain
adequate E&S controls on the MP5 area resulted in
discharges of sediment from the MP5 area that violated
Sections 3, 301, 307, 315 and 401 of the CSL, 35 P.S.
§$691.1 et seq., Section 102.4(a) of DER’s regulations at
25 Pa. Code, and Standard Condition No. 3 of
Lawrence's MDP.

9. The unlawful discharges of sediment from MP5
were continuous for 33 days from March 30, 1980, to
July 1, 1980, and intermittent on March 20, 1980, and
July 22-23, 1980.

10. On September 4, 1980, as a result of Lawrence’s
failure to implement and maintain adequate E&S
controls on the Spruell Strip, sediment was discharged
from the Spruell Strip in violation of Sections 3, 301,
307, 315 and 401 of the CSL, 25 P.S. §§691.1 et seq.,
Section 102.4(a) of DER’s regulations at 25 Pa. Code,
and Standard Condition No. 3 of the mine drainage
permit for the Sprueil Strip.

5la

11. On 3 separate dates, Lawrence improperly
handled reject material on the pit floor of the MP5 area
in violation of Section 315 of the CSL, 35 P.S. §691.315,
and Standard Condition No. 29 of Lawrence's MDP.

12. Lawrence’s unlawful discharges of AMD and
sediment from the MP5 area degraded Buck Run and the
unnamed tributary and adversely affected the use of
Buck Run as a cold water high quality fishery.

13. Lawrence’s unlawful discharges of AMD from the
MP5 area were wilfull from January 23, 1980, until July
1, 1980, but were less wilfull after that date.

14. Lawrence's unlawful discharges of sediment from
the MP5 area were wilfull nearly to the point of being
intentional on all relevant dates except March 20, 1980,
and July 22-23, 1980.

15. Lawrence’s unlawful handling of reject material
on the pit floor of the MP5 area was wilfull on the last
two of the three dates involved.

16. DER did not present sufficient evidence to show
any degree of wilfullness connected with Lawrence's
unlawful discharges of AMD and sediment from the
Spruell Strip.

17. DER did not present sufficient evidence to enable

the Board to consider deterrence and the cost of
restoration in setting a civil penalty.

18. DER did not present evidence to sustain the
allegations in the Complaint relating to the Kennedy
Strip.

52a

19. The assessment of civil penalties is appropriate in
this case in the following amounts:

Rogers Mill Strip

AMD 127 x $500 =$ 63,500
4 x $450 = 1,800
$ 65,300
E&S 93 x $400 =$ 37,200
2x$250 = 500
37,700
Rejects 1 x $100 = $ 100
2 x $200 = 400
500
Total $ 103,500
Spruell Strip
AMD 1 x $350 = $ 350
E&S 1 x $200 - 200:
Total 550

GRAND TOTAL $ 104,050

53a

ORDER

AND NOW, this 5th day of July, 1988, civil penalties
are assessed against Lawrence Coal Company in the
aggregate amount of $104,050 for violations of the CSL,
the regulations of DER, and the provisions of its mine
drainage permits.

The entire civil penalty is due and payable immediately
into the Clean Water Fund. The Prothonotary of Fayette
County is ordered to enter the full amount of the civil
penalty as a lien against any property of Lawrence Coal
Company, together with interest at the rate of 6% per
annum from the date hereof. No costs may be assessed
upon the Commonwealth for entry of the lien on the
docket.

ENVIRONMENTAL HEARING
BOARD

ROBERT D. MYERS
Robert D. Myers, MEMBER

DATED: July 5, 1988

cc: Bureau of Litigation

Harrisburg, PA

For the Commonwealth, DER:
Diana J. Stares, Esq.
Western Region

For Appellant:
William M. Radcliffe, Esq.
Uniontown, PA

In accordance with the order of Commonwealth Court,
neither Chairman Maxine Woelfling nor Member William
A. Roth participated in the decision of this case.

She

APPENDIX “D”

Opinion and Order of the Commonwealth Court
of Pennsylvania (unreported) Dated
January 25, 1988.

IN THE COMMONWEALTH COURT
OF PENNSYLVANIA

No. 3062 C.D. 1986

LAWRENCE COAL COMPANY,
Petitioner,

Vv.

COMMONWEALTH OF PENNSYLVANIA,
DEPARTMENT OF ENVIRONMENTAL

RESOURCES,
Respondent.

BEFORE: HONORABLE JOHN A. MacPHAIL,

Judge
HONORABLE MADALINE PALLADINO,

Judge
HONORABLE JACOB KALISH,
Senior Judge

ARGUED: November 20, 1987
OPINION NOT REPORTED

MEMORANDUM OPINION
BY JUDGE PALLADINO FILED: January 25, 1988

| elidel

55a

Lawrence Coal Company (Lawrence) appeals from an
order of the Environmental Hearing Board (Board)
which, after reconsideration, affirmed its prior
adjudication assessing $150,700 in civil penalties against
Lawrence for violations of the Clean Streams Law (Law).'
For the reasons set forth below, we vacate and remand.

On February 25, 1981, the Department of
Environmental Resources (DER) filed a complaint
against Lawrence for civil penalties pursuant to Section
605 of the Law for violations alleged to have occurred in
1980. The Board, with Chairman Dennis J. Harnish
presiding, held eleven days of evidentiary hearings
between June 2, 1982 and November 23, 1982. In May of
1983, before the Board had rendered an adjudication on
the matter, Chairman Harnish resigned.

The matter was assigned to the two remaining Board
members, Anthony Mazullo and Edward Gerjuoy.
However, because both Mazullo and Gerjuoy were unable
to attend to the matter because of substantial caseloads
of their own, the case was reassigned to newly appointed
Hearing Examiner Edward R. Casey.

On October 20, 1983, Casey, without consulting either
of the other Board members, wrote a letter to counsel for
both the DER and Lawrence explaining his view of the
matter based upon his reading of the record. After
recounting portions of the testimony of expert witnesses
for both Lawrence and the DER, Casey concluded that

“[t]his is simply not the kind of case where a
regulatory agency should seek continuing civil
penalties against a defendant; because... the
testimony of DER witnesses on the issue of

' Act of June 22, 1937, P. L. 1987, as amended, 35 P.S. $§691.1-
691.1001.

56a

Lawrence’s direct responsibility for acid mine
drainage... was equivocal at best and it just does
not satisfy DER’s burden of proof to establish this
pivotal fact by a fair preponderance of the
evidence.”

Casey recommended that the two parties reach settlement
on the matter and suggested that a ‘‘nominal’’ fine of
$100 per month up to $1000 total might be appropriate.

Thereafter, according to sworr affidavit of counsel for
DER, the following occurred:

On October 24, 1985, Mr. Harnish, who was no
longer employed by the Board, was in the offices of
the Western Region Bureau of Litigation for the
purpose of meeting with another attorney on a
personal matter, and [counsel for DER] showed Mr.
Harnish the letter written by Mr. Casey. ... After
reviewing the letter, Mr. Harnish informed [DER
counselj that, prior to resigning from the Board, Mr.
Harnish had discussed this case with Mr. Casey and
had advised him that after hearing the evidence
presented by both parties he had initially concluded
that the Department had met its burden of
establishing that Lawrence was responsible for the
unauthorized discharges of mine drainage.

After hearing Harnish’s comments on the Casey letter,
counsel for DER wrote a letter to Casey alleging bias
against DER and filed a petition with the Board for
Casey’s recusal.

On November 22, 1983, in response to DER’s petition,
the remaining members of the Board (Mazullo and
Gerjuoy) granted DER’s motion for recusal and
reassigned the matter to Mazullo for purposes of
drafting a proposed adjudication on the merits of the
contest. Lawrence, who had opposed the DER’s petition
for recusal, thereafter filed a petition requesting the
Board either to dismiss the complaint against Lawrence,

57a

or in the alternative, to recuse Mazullo, since he was a
member of the original Board on which Harnish had sat,
and reassign the matter to a neutral hearing examiner.
The Board denied this petition in an order and opinion
dated December 14, 1983. By way of explanation for the
recusal of Casey and reassignment to Mazullo, the Board
stated that ‘‘an indicia of conflict could be perceived
from the disclosures made by Harnish to DER counsel,
and the Board thought it in the best interest of all
concerned that the members of the Board not involved in
the unfortunate incident reserve unto themsleves the
final determination of the controversy.’’ The case was
scheduled for proposed adjudication by Mazullo.

Mazullo subsequently prepared a propose adjudication
on the merits of the controversy. During this time,
Maxine Woefling was appointed to the chair of the
Board. Before her appointment, Woefling was Chief
Regulatory Counsel for the DER and had also been an
attorney with DER during pendency of the hearings
conducted in 1982.

On January 31, 1986, before the Board had taken any
action on the proposed adjudication, Mazullo resigned
his position. Four months later, on May 27, 1986, the
' Board issued an adjudication signed by Woefling and
) Gerjuoy which purported to adopt, with modifications,
the draft of Mazullo. The order assessed $150,700 in civil
penalties for multiple violations of the Clean Streams
Law and the regulations adopted pursuant thereto.

Lawrence subsequently filed two petitions for
reconsideration requesting (1) the recusal of Woefling; (2)
the recusal of Gerjuoy; or, in the alternative, (3)
dismissal of the complaint against Lawrence. On
September 12, 1986, the Board, consisting of Gerjuoy
and William A. Roth, a newly appointed Board member,

a

586

issued an order denying Lawrence's motion for recusal of
Gerjuoy. On September 19, 1986, the Board, still
composed of Gerjuoy and Roth, dismissed Lawrence’s
petition for reconsideration and affirmed its prior May
27, 1986 adjudication assessing $150,700 in civil
penalties against Lawrence. The Board concluded that
since Woefling had in no way participated in the Board’s
reconsideration and affirmance of its May 27, 1986
adjudication, the issue of her participation in the matter
was moot. Following this final order, Lawrence appealed
to this court.

Lawrence contends that it was denied its due process
right. to a fair and impartial adjudication on the subject
matter of the dispute because improprieties occurred.
Lawrence also challenges the legality of the Board’s
assessment of $150,700 in civil penalties.

It is fundamental that the resolution of any
controversy be rendered in an impartial manner by
irreproachably impartial officials. To this end, ‘any
tribunal permitted by law to try cases and controversies
must not only be unbiased but must avoid even the
appearance of bias.’’ Horn v. Township of Hilltown, 461
Pa. 745, 337 A.2d 858, 859-60 (1975) (quoting Gardner v.
Repasky, 434 Pa. 126, 129, 252 A.2d 704, 706 (1969)).
This foundational maximum applies equally in the
context of administrative tribunals as it does in courts of
law. As President Judge Crumlish, speaking for this
court, has stated:

The crucial function in the prosecution and
adjudication of administrative proceedings is in the
resolution ot disputed facts because the findings of
fact emanating from administrative proceedings are
subject only to limited appellate review. Therefore,
we must afford this process the broadest of
constitutional protection and prevent even the
possibility of unfairness.

DIE ci RNP en SEC SC EC

59a

Goldberg v. Commonwealth of Pennsylvania, State Board
of Pharmacy, 49 Pa. Commonwealth Ct. 123, 129-30, 410
A.2d 413, 417 (1980).

Upon review, this court concludes that the proceedings
in this matter taken as a whole are so tarnished as to
create a clear susceptibility to potential bias against
Lawrence. This court concludes that the possibility of
unfairness to Lawrence exists and that improprieties
might have occurred. Accordingly, we remand this case
to the Board for new hearings on the matter. Case
remanded for proceedings consistent with this opinion.

MADALINE PALLADINO
Madaline Palladino, Judge

60a

IN THE COMMONWEALTH COURT
OF PENNSYLVANIA

No. 3062 C.D. 1986

LAWRENCE COAL COMPANY,
Petitioner,

Vv.

COMMONWEALTH OF PENNSYLVANIA,
DEPARTMENT OF ENVIRONMENTAL
RESOURCES,
Respondent.

ORDER

AND NOW, January 25, 1988, the order of the
Environmental Hearing Board dated September 19, 1986
in the above-captioned matter affirming the Board’s
prior May 27, 1986 adjudication is vacated. The case is
remanded for further proceedings consistent with this
opinion.

Jurisdiction relinquished.

MADALINE PALLADINO
Madaline Palladino, Judge

CERTIFIED FROM THE RECORD
AND ORDER EXIT

JAN 25, 1988

C.R. HOSTUTLER
Deputy Prothonotary—Chief Clerk

6la

APPENDIX “E”

Adjudication of the Environmental Hearing Board
by Maxine Woelfling, Dated May 27, 1986.

SEAL

COMMONWEALTH OF PENNSYLVANIA
ENVIRONMENTAL HEARING BOARD
221 North Second Street
Third Floor
Harrisburg, Pennsylvania, 17101
(717) 787-3483

MAXINE WOELFLING, CHAIRMAN M. DIANE SMITH
EDWARD GERJUOY, MEMBER SECRETARY TO THE BOARD

Docket No. 81-021-CP-M
Issued: May 27, 1986

COMMONWEALTH OF PENNSYLVANIA,
DEPARTMENT OF ENVIRONMENTAL
RESOURCES

Vv.

LAWRENCE COAL COMPANY

ADJUDICATION
By the Board
Synopsis

This matter involves a complaint by the Department of
Environmental Resources (DER) against Lawrence Coal
Company (Lawrence) for the assessment of civil penalties

62a

pursuant to §605 of the Clean Streams Law, the Act of
June 22, 1937, P.L. 1987, as amended, 35 P.S. §691.605
(CSL). It was proven by DER by a preponderance of the
evidence that acid mine drainage (AMD) emanated from
Lawrence’s permit area and that discharges of AMD
were caused or affected by Lawrence’s mining operations
in violation of §§3, 301, 307, 315, and 401 of the CSL and
the rules and regulations adopted thereunder at 25 Pa.
Code §§77.92, 95.1 and 99.33. It was further proven by a
preponderance of the evidence that Lawrence failed to
install and maintain adequate erosion and sediment
controls in violation of §402 of the CSL and 25 Pa. Code
$102.4.

Section 316 of the CSL does not provide a separate
basis of liability in this case because DER has chosen to
seek civil penalties rather than issue an order pursuant
to §316. Violations of §401 of the CSL do not merge into
violations of §§301, 307, and 315 because violating the
terms and conditions of a permit issued pursuant to
these sections of the CSL is distinct from causing
pollution. The discharge violations were continuous
because the sampling was sufficiently close in time to
establish a continuing AMD discharge.

In calculating a civil penalty, the Board did not
consider the cost of restoration of the receiving waters,
since DER presented no evidence as to such costs.
Damage to the stream was held to be moderate, and
certain violations were held to be wilful. Deterrence was
also considered by the Board in assessing the penalty.

ne

Pe eee eo

63a

INTRODUCTION

This action involves a complaint for civil penalties filed
on February 25, 1981, by DER against Lawrence for
alleged violations of the CSL resulting from Lawrence's
strip mining operations in Springfield Township, Fayette
County.

Former Board Chairman Dennis J. Harnish presided
over eleven days of hearings, which concluded on
November 23, 1982. Following Chairman Harnish’'s
resignation from the Board in May, 1983, the case was
assigned to hearing examiner Edward R. Casey.
Subsequently, the Board ordered the recusal of Mr.
Casey for reasons recounted in an earlier Board Opinion
and Order (1983 EHB 608), and assigned the case to
Board Member Anthony J. Mazullo, Jr.

After the filing by both parties of post-hearing briefs,
and the filing by DER of a reply brief, the record was
presented for adjudication. Member Mazullo drafted an
adjudication for the consideration of the Board. He
resigned on January 31, 1986. The Board is adopting his
draft adjudication with modifications.

bbe

FINDINGS OF FACT

1. The plaintiff is DER, the agency entrusted with
the duty to enforce the provisions of the CSL.

2. The defendant is Lawrence, a corporation, which is
the permittee of a surface mining operation in Springfield
Township, Fayette County, which operation is referred to
herein as the Rogers Mill Strip. (T 10).

3. The Rogers Mill Strip is covered by Mine Drainage
Permit 3376SM15, which was issued by the Department
pursuant to Section 315(a) of the CSL. (T 11).

4. Mine Drainage Permit 3376SM15 was originally
issued to William K. Tedesco on November 10, 1976. (T
11).

5. Mine Drainage Permit 3376SM15 was transferred
by DER to Lawrence on July 19, 1977. (T 11).

6. Mining Permit 1063-5 is encompassed within the
area covered by Mine Drainage Permit 3376SM15. (T 11).

7. Lawrence is the permittee on Mining Permit 1063-5
which was issued by DER pursuant to Section 4(a) of the
Surface Mining Conservation and Reclamation Act, the
Act of May 31, 1945, P.L. 1198, as amended, 52 P.S.
§1396.1 et seq.

8. Mining Permit 1063-5 (“MP 5’’) covers an area of
63 acres and was issued to Lawrence on July 1, 1977. (T
12).

9. Drainage from the Rogers Mill Strip flows to Buck
Run and its unnamed tributary. (T 13)

10. Marsolino Coal and Coke, Inc. (‘‘Marsolino’’) has a
mining operation located immediately uphill from the
Rogers Mill Strip. This operation is referred to herein as
the MP 71-27 Strip. (T 17).

a

65a

11. The Rogers Mill Strip and the MP 71-27 Strip are
the only two surface mining operations on the Buck Run
watershed which could have had an impact on the
quality of Buck Run and its unnamed tributary in the
vicinity of the Rogers Mill Strip. (T 18).

12. There are three township roads in the immediate
vicinity of the Rogers Mill Strip. The Rogers Mill Strip
is bounded on the northwest by T-687, a paved road,
which runs to the Angelo Fish Hatchery and beyond
(‘Fish Hatchery Road’’). The site is bounded on the
southeast by T-683, a dirt road, which runs to the
residence and spring of Glen Pirl and beyond (''Pirl
Spring Road’’). The third road is T-685, a dirt road,
which runs through the Rogers Mill Strip (‘‘Haul Road’’).
The Haul Road joins the Pirl Spring Road approximately
150 feet from the intersection of the Pirl Spring Road
and the Fish Hatchery Road. There is a bridge on the
Fish Hatchery Road which crosses Buck Run and is very
near this intersection (‘Buck Run Bridge’). (T 22-24,
DER Exhibit 1).

13. There are a number of culverts along the Pirl
Spring Road which carry water under the road towards
Buck Run and the Buck Run tributary. (DER Exhibit 1).

14. Buck Run is to the southeast of the Rogers Mill
Strip. The Pirl Spring Road is between the Rogers Mill
Strip and Buck Run. Buck Run has a tributary which is
located between the main stream of Buck Run and the
Pirl Spring Road (‘Buck Run tributary’). The Buck Run
tributary confluences with Buck Run upstream from the
Buck Run Bridge between culverts 2 and 3 on Pirl
Spring Road. (DER Exhibit 1).

15. Drainage from culvert 2 flows directly to Buck
Run, while drainage from culverts 3 and 4 flows to the
Buck Run tributary. (T 54-55).

66a

16. Lawrence mined above the discharges at culverts
2 through 4 along the Pirl Spring Road. (T 298).

17. The area of the site is characterized by
moderately steep dipping sedimentary rocks. There is
frequent rolling that is at times sudden and severe. (T
713).

18. The rock formations in this area are the Middle
and Lower Allegheny rock formations, with the coal
seams being the Lower Kittanning through Freeport coal
seams. (T 714).

19. The overburden which was mined on the site and
which is evidenced by the existing highwall was a highly
fractured massive sandstone 50 to 60 feet thick. The
sandstone had many joints and fractures, and there were
smooth faces where the joints had been weathered. This
sandstone has coaly inclusions. The overburden has been
fairly consistent throughout the mining operation. (T
145, 717-718).

20. Topographically, the site resembles a tongue with
valleys on each side. The tongue has significant relief
from the tip of the tongue at the northwest to the top of
the hill in the south. The relief from the Angelo hatchery
to the top of the area mined by Marsolino is about 500
feet. (T 720-721). hice

21. Stratigraphically, the Rogers Mill Strip had one
coal seam which was mined. That coal seam was covered
by a massive sandstone 50 to 60 feet thick. Immediately
under the coal was a layer of shale 2 to 15 feet thick.
Some 40 to 60 feet below the mined coal seam is a thin
coal seam which has been referred to as the rider seam.
A few drill holes indicate that there are both sandstones
and shales between the mined seam and the rider seam.
(T 731, 1167; DER Exhibits 34, 39; Lawrence Exhibits 5,
6, 7, and 8).

sung

sin aAGUALiIe tedden Ske ml

67a

22. Structurally, the mined coal seam was fairly
uniform. (T 732). The mined coal seam dipped to the
northwest and in a northeast to southwest. direction. The
seam, or the underpavement remaining, has a moderate
uniform dip beginning on the Marsolino site (MP—27
Strip) and dipping uniformly until the area of the Haul
Road where there was a roll in the coal. At the roll, the
dip flattens somewhat but still dips to the northwest. (T
734-735).

23. The general recharge area for the Rogers Mill
Strip is the topographic high, which is the whole area of
sandstone uphill from the site to the uphill cropline of
the sandstone. (T 736-739).

24. The general discharge area is the lower end of the
tongues, which is the west and northwest area bounded
by the Pirl Spring Road and the Fish Hatchery Road.
This would cover the area from the north and south
WPA seals at the Angelo Hatchery along the crop line
and below it along the Hatchery Road and along the Pir!
Spring Road up as far as the Marsolino site. (T 737, 745-
746).

25. The primary controls on groundwater flow at the
Rogers Mill Strip are the topography, structure, and
stratigraphy of the site. (T 747-748).

26. On the reclaimed area of the surface mine,
infiltrating water will flow to the pit floor. The flow will
then be controlled primarily by structure, with
groundwater flowing downdip perpendicular to contour
lines until it reaches a crop line where it will discharge.
(T 769-770, 771).

27. The flow of the pit on the Rogers Mill Strip dips
in two directions, towards the Fish Hatchery Road and
towards the Pirl Spring Road. The component of dip

68a

towards the Pirl Spring Road was steeper in the area
closer to the Pirl Spring Road than it was in area of the
pit at the time of the view. In that area the dip towards
the Pirl Spring Road was steeper than the dip towards
theFish Hatchery Road. (T 260-261).

28. Discharges can occur anywhere along the north
and west croplines of the Rogers Mill Strip depending on
local rolls and undulations. (T 776).

29. The floor of the pit on the Rogers Mill Strip was
not perfectly flat. (T 1493).

30. The roll in the pavement of the mined site
channels water towards culvert 4 on the Pirl Spring
Road, and water following this course discharges at the
dead tree above culvert 4, which is below the cropline of
the mined seam. (T 798).

31. The Rogers Mill Strip produces AMD. (T 794,
1024).

32. Lawrence's mining operation is a source of the toe
of spoil discharge at the dead tree above culvert 4. (T
1632-1633).

33. Lawrence’s mining operations at the Rogers Mill
Strip have contributed to the discharge of mine drainage
at the toe of spoil on MP 5 near the dead tree above
culvert 4. (T 1632-1633).

34. There are no logical sources of the AMD at the
culverts along T-683 except the Lawrence and Marsolino
surface mines. (T 871-873).

35. Lawrence and Marsolino both mined the same
coal seam. (T 1326-1327).

36. Outcrop areas, such as the area of the Rogers Mill
Strip along the Pirl Spring Road, are normally fractured.
(T 1614).

ee

Oe th Nate etn

37. It is common for water to pass through coal crop
lines. (T 1617).

.38. Flows of water at culverts 2, 3, and 4 were greatly
reduced after the toe of spoil mine drainage collection
ditch and the two treatment ponds on MP 5 were
constructed. (T 224-226, 495).

39. The quality of the seep of mine drainage into the
toe of spoil collection ditch and the water seeping out of
the road bank between culverts 4 and 5 is similar in most
respects. (DER Exhibit 334A).

40. There is a hydrologic connection between the
Rogers Mill Strip and the acid mine drainage discharges
at culverts 2, 3 and 4. (T 720-721, 731, 734-735, 747-748,
871-873, 1632-1633; DER Exhibits 33, 33A, 33B, 33C).

4i. There are discharges of AMD from the zone
between the mined seam and the rider seam. These
discharges exist or existed in the vicinity of culverts 2, 3,
4, 6, and 7 along the Pirl Spring Road. There are also
discharges from this zone at culverts 8, 9, 10 and the Pirl
Spring, but they are not AMD. (DER Exhibits 33A and
33B).

42. The AMD which flowed to culvert 2 on the Pirl
Spring Road flowed from the culverts directly to Buck
Run, and the AMD which flowed to culverts 3 and 4,
flowed from those culverts to the Buck Run Tributary.
(T 54-55).

43. The observable source of the water that flowed to
culverts 2 and 3 on January 23, 1980 was a swampy area
located below the toe of spoil of the Rogers Mill Strip, in
the area of the present location of the MP 5 treatment
ponds. This swampy area dried up some time after the
treatment ponds were constructed. The volume of these

70a

discharges decreased significantly after the toe of spoil
AMD collection ditch and the treatment ponds were
constructed on MP 5. (T 52, 224-226, 491-492, 495, 501;
DER Exhibit 334A).

44. The observable source of the water that flowed to
culvert 4 on January 23, 1980 was an area at the toe of
spoil of the Rogers Mill Strip in the vicinity of a dead
tree above culvert 4. Water continued to flow above
ground from the toe of spoil area to culvert 4 until a toe
of spoil ditch was constructed by Lawrence. The toe of
spoil ditch was originally constructed some time between
May 27, 1980 and June 10, 1980. After the construction
of the ditch, the flow of water at culverts 3 and 4 greatly
reduced. (T 51-52, 170, 224-226, 491, 495).

45. There is nothing between the sources of the
culvert discharges and the culverts which would alter the
chemical character of the water. (T 887).

46. DER’s file for the Rogers Mill Strip does not
indicate that there were any pre-mining pollutional
discharges below the Rogers Mill Strip along the Pirl
Spring Road. (T 25-28).

47. Lawrence never performed field tests or
laboratory tests of the mine drainage at the culverts
along the Pirl Spring Road prior to the time DER
Inspector Mark Frederick first sampled them. (T 1512-
1513, 1642).

48. The water quality at culverts 8, 9, 10, and the Pirl
Spring represents background or ambient water quality
for the area of the Rogers Mill Strip. (T 499-500).

49. The background water quality concentration for
sodium is less than lppm. (T 594-595).

>. oe aerial,

7la

50. On January 23, 1980, Lawrence was not treating
the AMD that flowed to culverts 2, 3 and 4 along the
Pirl Spring Road. (T 55).

51. On January 23, 1980, parameters sampled in the
mine drainage at culvert 4 had the following
concentrations (values, except for pH, are hereinafter
expressed in milligrams per liter): the pH was 3.2; the
acidity of 618 exceeded the alkalinity of 0; iron was 32.3;
and manganese was 56. (T 40; DER Exhibits 33, 334A).

52. On January 23, 1980, the parameters sampled in
the mine drainage at culvert 3 had the following
concentrations: the pH was 3.7; acidity of 891 exceeded
alkalinity of 0; and manganese was 140. (T 47; DER
Exhibits 33 and 334A).

53. On January 23, 1980, parameters sampled in the
mine drainage at culvert 2 had the following
concentrations: the pH was 4.5; acidity of 150 exceeded
alkalinity of 0; and manganese was 41. (T 48; DER
Exhibit 33A).

54. On January 23, 1980, Lawrence exceeded the
applicable effluent limits for pH, acidity, and manganese
at culverts 2, 3, and 4, and the applicable effluent limit
for iron at culvert 4.

55. On January 28, 1980, DER Inspector Frederick
inspected the Rogers Mill Strip and was accompanied by
Archie Johnson, the foreman at the strip. On that date
the discharges at culverts 2 through 4 were flowing but
were not sampled. Lawrence was not collecting or
treating the discharges on January 28, 1980. (T 71-72).

56. Inspector Frederick inspected the Rogers Mill
Strip on February 28, 1980, and was accompanied by
Archie Johnson and James Filiaggi, the superintendent
of Lawrence’s mining operati

[Text truncated at 120,000 characters. The full text is on the page linked above.]

---

Source: Frix Law Library, https://www.frixlaw.com/law-library/documents/brief%3Amicro_IA40385020_1257%3A1. Public record. Not legal advice.
