# Petition — Pennsylvania Department of Transportation v. United States

> Briefs, arguments, decisions, and more.

URL: https://www.frixlaw.com/law-library/documents/brief%3Amicro_IA40385007_2158%3A1

## Record

- **Collection:** Supreme Court brief
- **Document type:** Petition
- **Published:** January 1, 1981
- **Citation:** 454 U.S. 826

## Text

MAY 2 3 1981
80-1978
No. ALEAA: Sn |

in the Supreme Court of the
Unjted States

October Term, 1980

COMMONWEALTH OF PENNSYLVANIA,
DEPARTMENT OF TRANSPORTATION,
Petitioner
¥.

THE UNITED STATES,
Respondent

PETITION FOR WRIT OF CERTIORARI TO
THE UNITED STATES COURT OF CLAIMS

ROBERT H. RAYMOND, JR.
Assistant Chief Counsel
ROBERT W. CUNLIFFE
Deputy to the Chief Counsel
WARD T. WILLIAMS
Chief Counsel
JAY C. WALDMAN
General Counsel
Attorneys for Petitioner
Office of Chief Counsel
Department of Transportation
Commonwealth of Pennsylvania
Harrisburg, Pennsylvania 17120
(717) 787-2111

Murrelle Printing Co., Box 100, Sayre, Pa. 18840—(717) &88-2244

Question Presented for Review

QUESTION PRESENTED FOR REVIEW

Whether the Court erred by ignoring Court of Claims
Rule 147 (b) when it substituted its findings for the Trial
Judge’s findings on the reasonableness of the State’s settle-
ments of certain claims arising out of a Federal Highway
Administration sponsored highway construction project
when the evidence in the record did not rebut the normal
presumption of correctness of the Trial Judge’s findings?

TABLE OF CONTENTS

PETITION: res
Question Presented for Review .........scsscssseeseseeeees i
pe RRA OL LOCAL an wo ii
TCE AAI OG | scccsceseceesesviepcsntecnsineemmnnstpsrseneens iii
Cpbebons Da «sisi sicecessessssosssevnseciisvetoototosessdassinsses 1
Statement Of Jurisdiction .ccccccsscrvessecscsocesisvsvesesooesosss 1
Statutes and Rules Involved ...........cssssssssssrsesssseeees 2
Doabonnnit OF Tae CW coseicccvcsatvissseccecsnisninbesavennassasete 4
ALBUMEN ...ccccccccsrcccoscssscscscecsnccscescoseccscosessoccssssovecsees 8
ORORIIIR © ccnescensoseesesscsceonnnsesszesnnnsbouunibennetinonninvecnestes 13
APPENDIX A:
Opinion of The United States Court of Claims of
February 25, 1961 cccsoccrcscsscscosscveccccssvsseecccesccszee la
judgment of the United States Court of Claims of
February 25, 1961 ccscsccsssscrscesscsscccsssseecssccsnsssoese 24a

APPENDIX B:

Opinion of Trial Judge Fletcher of September 27,
SUPT ccsssnsnsconscscegusistenvssepzaiiseteiocnitiisiecteanbemensisens 25a

ii

TABLE OF AUTHORITIES

CASES: roan
Davis v. United States, 164 Ct. Cl. 612 (1964) ...... 12
H. & H. Manufacturing Co., Inc. v. United States,

BGS C2. C5. S75. CEG. . ccthesepepeceseeineneneroenne Noone

Hebah v. United States, 456 F.2d 696, 197 Ct. Cl.
729 (1972), cert. denied 409 U.S. 870 (1973) 9

J. D. Hedin Construction Co., Inc. v. United States,

347 F.2d 235, 171 Ct. Cl. 70 (1965) ..........0000 9
Louisiana Department of Highways v. United States,

604 F.2d 1339, 221 Ct. Cl. —— (1979) ......... 9,10
STATUTE:

Federal-Aid Road Act of 1916, Ch. 241, 39 Stat.
355 as amended (23 U.S.C. §§101 et seq.
(| RRR ETERS IESE RIC GAR Cea Sie A ogieie Deans 2,3,4

RULES OF COURT:

United States Court of Claims Rule 147
LUPE ‘< ccscusinencahantndpenptensensonsudaigebediniodinegs 3,6,8,12

Opinions Below and Statement of Jurisdiction 1

OPINIONS BELOW

The opinion of the U. S. Court of Claims has not yet
been reported, and a copy thereof is attached hereto as
Appendix A. The judgment of the U. S. Court of Claims
of February 25, 1981, is also attached hereto as Appendix
A. The prior opinion of Trial Judge Fletcher, filed Sep-
tember 27, 1979, is attached hereto as Appendix B.

STATEMENT OF JURISDICTION

The U. S. Court of Claims filed its opinion and judg-
ment on February 25, 1981. The basis for jurisdiction
of this Court is found in 28 U.S.C. Section 1255(1).

2 Statutes and Rules Involved

STATUTES AND RULES INVOLVED

United States Statutes:
23 U.S.C. §106 (a) :

(a) Except as provided in section 117 of this
title, the State highway department shall submit to
the Secretary for his approval, as soon as practicable
after program approval, such surveys, plans, speci-
fications, and estimates for each proposed project
included in an approved program as the Secretary
may require. The Secretary shall act upon such sur-
veys, plans, specifications, and estimates as soon as
practicable after the same have been submitted, and
his approval of any such project shall be deemed a
contractual obligation of the Federal Government for
the payment of its proportional contribution thereto.
In taking such action, the Secretary shall be guided
by the provisions of section 109 of this title.

23 U.S.C. §120(c):

(c) Subject to the provisions of subsection (d)
of this section, the Federal share payable on account
of any project on the Interstate System provided for
by funds made available under the provisions of sec-
tion 108 (b) of the Federal-Aid Highway Act of 1956
shall be increased to 90 per centum of the total cost
thereof, plus a percentage of the remaining 10 per
centum of such cost in any State containing unap-
propriated and unreserved public lands and nontax-
able Indian lands, individual and tribal, exceeding
5 per centum of the total area of all lands therein,

Statutes and Rules Involved 3

equal to the percentage that the area of such lands
in such State is of its total area, except that such
Federal share payable on any project in any State
shall not exceed 95 per centum of the total cost of
such project.

Rule of the U. S. Court of Claims:
Rule 147 (b)

(b) Trial judge’s report. The court may adopt
the trial judge’s report, including conclusions of fact
and law, or may modify it, or reject it in whole or
in part, or direct the trial judge to receive further
evidence, or refer the case back to him with instruc-
tions. Due regard shall be given to the circumstance
that the trial judge had the opportunity to evaluate
the credibility of the witnesses; and the findings of
fact made by the trial judge shall be presumed to be
correct.

4 Statement of the Case

STATEMENT OF THE CASE

This action, brought by the Commonwealth of Penn-
sylvania, Department of Transportation (State) against
the United States, prayed that the United States, through
its agent the Federal Highway Administration (FHWA),
contribute 90 percent of the cost of certain expenditures
made by the State in 1970. These expenditures were
for settlements of claims brought by a local governmental
authority, the Milford Water Authority (Milford), and
the contractor, the Gasparini Excavating Co. (Gasparini) ,
which claims arose out of the construction of Interstate
Highway 84 (I-84) in northeastern Pennsylvania. The
settlements were in the amounts of $275,000.00 and
$835,000.00, respectively. Trial Judge Fletcher, in an
opinion dated September 27, 1979 awarded $999,551.20
to the State. This case came before the U. S. Court of
Claims on the FHWA’s exceptions to this judgment.

Pursuant to the Federal-Aid Highway Act, 23 U.S.C.
Section 106, the State and the FHWA entered into project
agreements for the construction of 1-84 effective July 5,
1966 and January 23, 1967. Actual construction began
in April, 1967.

In August, 1967, Milford contacted the State, com-
plaining that the highway construction was contaminating
its water supply. Subsequent studies revealed that the
highway construction was indeed the source of Milford’s
water supply contamination, and on December 27, 1967,
Milford filed a complaint in equity in state court asking
for the construction of a filtration system, the revision of

Statement of the Case 5

drainage, damages and “such other and further relief as
may be deemed just and proper.”

Negotiations began in earnest with Milford to fore-
stall the issuance of an injunction and a project shutdown.
The State agreed to restrict Gasparini’s use of “borrow”
excavation sites which might affect the water supply, and
notified Gasparini of this restriction on December 22,
1967.

In May, 1968 the Department ordered Gasparini to
stop work while the Department considered major grading
and drainage revisions to alleviate the conditions causing
contamination of the Milford water supply.

Negotiations proceeded with Gasparini and Milford
to resolve the State’s liability with regard to the impeding
of Gasparini’s operation and the pollution of Milford’s
water supply. Representatives of FHWA were present at
these negotiations but offered no constructive comments.

In August, 1970 the State reached a settlement with
Milford, eliminating the threat of an injunction. And,
the Trial Judge, in his evaluation of this settlement, held,
that the FHWA was obligated to reimburse the State for
90 percent of the $275,000.00.

Similarly, in May, 1970, the State reached a final
settlement with Gasparini, eliminating the threat of litiga-
tion for damages. And, the Trial Judge in his evaluation
of this settlement, held that the FHWA was obligated to
reimburse the State 90 percent of the $835,000.00.

In regard to the Milford settlement, the facts show
that the settlement of $275,000.00 was reasonable and
necessary under the circumstances then existent. Although
a consultant’s report concluded that alternative solutions

6 Statement of the Case

existed (i.e., the construction of a full scale water treat-
ment plant at an estimated cost of $560,000.00, or a re-
design of the drainage system at an estimated cost of
$58,000.00) , these alternatives were either. too costly or
possibly insufficient to effect the desired results. As the
Trial Judge reasoned, the “plaintiff (State) acted reason-
ably in concluding that construction of the holding reser-
voir would be the most reliable cure for the turbidity
problem.” Trial Judge’s opinion at 22, 23 (Appendix,
p. 46a.)

The Trial Judge’s findings are uncontroverted that
the Milford settlement was made for the benefit of the
highway construction project in order to avoid a shut-
down or a major design change in the project. The Trial
Judge found that the turbidity problem was attributable
to the highway construction and the method of resolution
contained in the settlement was reasonable.

The Trial Judge also concluded that the settlement
with Gasparini was a reasonable part of the construction
cost of the highway. Gasparini could have sued the State
for damages in excess of $2,300,000.00. The State’s legal
officials, including the Attorney General, were of the opin-
ion that this claim would be upheld in litigation, litigation
which in its nature would have been exorbitantly ex-
pensive. Instead, as the Trial Judge reasoned, the State
acted in good faith in settling this claim and the settle-
ment was reasonable under the circumstances presented.

The Court of Claims ignored these findings by the
Trial Judge and substituted its own findings, despite the
absence of any reason to rebut the presumptive correctness
of the Trial Judge’s finding as espoused by Rule 147 (b).
Instead, the Court found that the implementation of the

Statement of the Case 7

drainage revision and an earlier order to Gasparini to start
borrow operations in the spring of 1968, would have lim-
ited expenditures to $58,000.00 and $90,000.00, respec-
tively, which in light of FHWA’s 90 percent participation,
would have resulted in federal expenditures of $52,200.00
and $81,000.00. The Court of Claims thus reduced the
judgment of the Trial Judge to $153,200.00.

8 Argument

ARGUMENT

The State submits that the Court of Claims has erred
in ignoring Rule 147(b) of the Court of Claims Rules,
and has thereby so far departed from the accepted course
of judicial proceedings as to call for an exercise of this
Court’s power of certiorari. The Court of Claims’ unwar-
ranted substitution of its findings for those of the Trial
Judge has resulted not only in loss to the State of $866,-
350.00 in Federal-Aid Highways Act funds, but also raises
important questions for all states concerning the circum-
stances under which the FHWA may refuse to reimburse
states for costs incurred in settlement of third-party claims
arising during the course of highway construction.

Rule 147 provides in part:

“(b) Trial judge’s report. The court may
adopt the trial judge’s report, including conclusions
of fact and law, or may modify it, or reject it in
whole or in part, or direct the trial judge to receive
further evidence, or refer the case back to him with
instructions. Due regard shall be given to the circum-
stance that the trial judge had the opportunity to
evaluate the credibility of the witnesses; and the
findings of fact made by the trial judge shall be pre-
sumed to be correct.”

Pursuant to this rule, a Trial Judge’s findings of fact
are presumed to be correct. Although the presumption
does not extend to conclusions of law, it does encompass
findings because of the Trial Judge’s opportunity to hear
the witnesses, to determine the weight to be accorded to

Argument 9

their testimony, and to evaluate both oral and documen-
tary evidence in light of the circumstances presented.
Hebah v. United States, 456 F.2d 696, 197 Ct. Cl. 729
(1972) , cert. denied 409 U.S. 870 (1973).

“A party who undertakes to overcome this presump-
tion must make a strong affirmative showing to the con-
trary.” 456 F.2d at 698. When a case comes to the
Court of Claims, the

{D]efendant [FHWA] has the burden of show-
ing that the Commissioner [i.e., Trial Judge] was
wrong in his factual conclusions. Such a task is far
from slight since we start with the double directive
that due regard must be given to the Commissioner’s
opportunity to judge the credibility of the witnesses
and that his factual findings will be presumed to be

correct. That presumption is dissipated only by a

strong affirmative showing. J. D. Hedin Construc-

tion Co., Inc. v. United States, 347 F.2d 235, 240,

171 Ct. Cl. 70 (1965).

The Court of Claims erred both by ignoring the presump-
tion that the Trial Judge’s findings were correct, and by
disregarding the FHWA’s failure to shoulder its burden
of affirmatively showing that the Trial Judge’s findings
were wrong.

The Trial Judge’s findings recite in detail the circum-
stances surrounding the Milford and Gasparini settlements.
In spite of the FHWA’s allegations of negligence, the Trial
Judge found that the State had not acted negligently but
had responded in a reasonable fashion in settling with
these third parties. In contradistinction to the situation
presented in Louisiana Department of Highways v. United
States, 604 F.2d 1339, 221 Ct. Cl. (1979), where
the state’s counsel admitted that a third-party contractor’s

10 Argument

claim was entirely without merit and that a settlement was
unreasonable, the Trial Judge concluded that there existed
reasonable grounds for belief that the State would have
been liable on the Milford and Gasparini claims.

“Finally, further consideration should be given
to this court’s recent decision in Louisiana Depart-
ment of Highways v. United States, Ct. Cl. No. 129-
76, dated July 18, 1979, 604 F.2d 1339, in which it
is held that in a claim for reimbursement under the
Federal-Aid Highways Act, where the claim is for
costs incurred in settlement of third-party claims
against the state, there must be reasonable grounds
for belief that the state would have been liable on
the third party claims. In the Louisiana case, it was
the opinion of the State’s counsel, concurred in by
the court, that the contractor’s claim was entirely
without merit. The present case differs in that cru-
cial respect. Here, there is ample evidence that, in
the opinion of Pennsylvania’s responsible legal of-
ficials, the Commonwealth of Pennsylvania might
well have been found liable to the third party claim-
ants on the basis of any of several possible legal
grounds had the claims finally gone to litigation.
They determined in good faith that the claims should
be settled, not merely to avoid expensive and trouble-
some litigation, but to avoid the possibility of sub-
stantially greater liability while, as stated above, the
court should be reticent to look behind the assess-
ments of Pennsylvania’s legal c.!icials as to the State’s
liability under Pennsylvania law, I nevertheless con-
clude that their conclusion to settle the claims was
reasonably justified under the unexpected complexi-
ties that had gradually developed.

Argument 11

“While I conclude it was not unreasonable for
Penn DOT to believe that it faced a real danger of
being held liable to the third party claimants, that
potential liability was not grounded on negligence
or unnecessary actions which would excuse the de-
fendant’s contractual obligation to reimburse plain-
tiff for its share of the costs necessary to avoid the
threatened litigation. Given the Act’s presumption
in favor of reimbursement, there must be more than
has been shown here to excuse that obligation. The
Commonwealth of Pennsylvania should have judg-
ment rendered in its favor in the sum of $999,551.-
20, and defendant’s counterclaim for interest should
be dismissed.” (Emphasis added.) (Trial Judge’s
Opinion at 25-26.) (Appendix, pp. 48a-49a.)

The Court itself partly acknowledged these findings,
stating that “the Trial Judge below found, and we con-
cur, that these facts are insufficient to establish design
negligence by the State.”” (Court’s Opinion, at 9.) (Ap-
pendix, p. 13a.) As regards the Gasparini claim, the
Court specifically held that it possessed ‘“‘at least some
merit”. (Jd. at13.) (Appendix, p. 19a.)

It is at this juncture, absent clearly erroneous findings
by the Trial Judge or an affirmative showing of error by
the FHWA, that the Court’s inquiry should have ended.
The Court determined, however, that the Milford and Gas-
parini settlements were unreasonable. As regards the
Milford settlement, the Court submitted that the settlement
was unreasonable because the State failed to act as a
“prudent businessman placed in a similar position”. (Id.
at 12.) (Appendix, p. 16a.) And with the Gasparini
settlement, the Court suggested that the State had acted
unreasonably by not authorizing an alternate borrow site
until August, 1968. (Jd. at 15.) (Appendix, p. 21a.)

12 Argument

These conclusions, however, were founded upon the
Court’s own findings of what a prudent man would have
done under the circumstances, “typically and traditionally
a question of fact.” H. & H. Manufacturing Co., Inc. v.
United States, 168 Ct. Cl. 873, 885 (1965). Thus, the
Court committed error by ignoring Rule 147(b)’s pre-
sumption for the correctness of the Trial Judge’s findings,
and substituted findings unwarranted from the record.

There is also no evidence that the Court’s conclusions
are warranted by any strong affirmative showing from the
FHWA to dissipate the rule’s presumption. Allegations and
innuendo alone are insufficient to abrogate the rule’s scope.
And, “where, as often happens, what appears to be a
sound objection to a finding is answered by an equally
sound explanation in support of it, the presumption will
carry the day.” Davis v. United States, 164 Ct. Cl. 612,
616-617 (1964). Clearly, the Court of Claims had no
justification to substitute its findings for that of the Trial
Judge in this case, and by so doing, it ignored both Rule
147 (b)’s mandate and drastically departed from the ac-
cepted course of judicial proceedings.

Argument 13
CONCLUSION

For the foregoing reasons, Petitioner respectfully
requests that a Writ of Certiorari issue to review the judg-
ment and opinion of the United States Court of Claims
entered in these proceedings on February 25, 1981.

ROBERT H. RAYMOND, JR.
Assistant Chief Counsel
Office of Chief Counsel
Department of Transportation
Commonwealth of Pennsylvania
Harrisburg, Pennsylvania 17120
(717) 787-2111

ROBERT W. CUNLIFFE
Deputy to the Chief Counsel

WARD T. WILLIAMS
Chief Counsel

Jay C. WALDMAN
General Counsel
Attorneys for Petitioner

Opinion, Court of Claims la

APPENDIX A

IN THE UNITED STATES COURT OF CLAIMS
No. 429-75
(Decided February 25, 1981)

COMMONWEALTH OF PENNSYLVANIA,
DEPARTMENT OF TRANSPORTATION
v. THE UNITED STATES

Robert H. Raymond, Jr., attorney of record, for plain-
tiff. Robert W. Cunliffe and Edward G. Biester, Jr., of

counsel.

David M. Cohen, with whom was Assistant Attorney
General Alice Daniel, for defendant. Richard ]. Webber
and Francis ]. Locke, of counsel.

Before NICHOLS, KASHIWA and SMITH, Judges.

OPINION

KASHIWA, Judge, delivered the opinion of the
court:
This case comes before the court on defendant’s ex-

ceptions to the recommended decision of Trial Judge
Fletcher, filed September 27, 1979, pursuant to Rule

2a Opinion, Court of Claims

134(h). We must decide whether the trial judge was
correct in concluding the federal government must con-
tribute 90 percent of the actual settlement costs of two
lawsuits arising from highway construction. After con-
sidering the written submissions of the parties and their
oral presentations, we reject the trial judge’s report and
require 90 percent federal participation only to the extent
expressed in this opinion.

Plaintiff Pennsylvania Department of Transportation
(hereafter the State) has brought this suit alleging a
breach by the United States (hereafter defendant) of an
agreement requiring the United States to reimburse the
State for 90 percent of the necessary costs of construction
of Interstate Highway 84 in northeastern Pennsylvania.
Neither party disputes that if reimbursement is owed,
such reimbursement must, under the -“deral-Aid High-
ways Act,’ be at 90 percent of the allowable costs. The
“costs” for which plaintiff seeks 90 percent reimburse-
ment are unbudgeted amounts paid by the State to a util-
ity (Milford Water Authority) and to the road construc-
tion contractor (Gasparini Excavating Company) in settle-
ment of claims by those parties against the State.

In August 1967, several months after the excavation
of the highway began, the utility complained to the Penn-
sylvania Department of Transportation that occasionally

1The statutory framework, now codified at 28 U.S.C. §§101
et seq. (1976), was first enacted in 1916 as the Federal-Aid Road
Act of 1916, ch. 241, 39 Stat. 355. Although numerous successive
road acts have altered minor details of the scheme, the 1916 frame-
work of state expenditure with federal reimbursement has re-
mained intact. For simplicity’s sake, we refer hereafter to the
statutory framework as if it were contained in a single act of

Congress.

Opinion, Court of Claims 3a

excessive amounts of particulate matter had begun to ap-
pear in its reservoirs, clouding the water. This clouded,
or turbid, water was aesthetically displeasing and had an
unpleasant taste. As some of the watersheds which fed
the Milford reservoirs were located within the construc-
tion area, Milford felt the turbidity problem was caused
by the exposure of bare slopes during highway construc-
tion.

The Department of Transportation engaged an en-
gincering firm, Michael Baker, Jr. Inc., to study the rela-
tionship between the turbidity and highway construction.
If the engineers found the turbidity and construction re-
lated, they were to propose solutions to the problem. The
Baker engineering firm subcontracted the consulting re-
port, so the actual engineering study was done by Gannett,
Fleming, Corddry and Carpenter, Inc. (hereafter Gan-
nett). Gannett monitored the turbidity from March 1967
through September 1968. Neither party disputes Gan-
nett’s expertise as engineers, nor the manner in which the
study was conducted.

While Gannett was conducting the study, Milford
filed a lawsuit on December 27, 1967, in a Pennsylvania
state court seeking drainage revisions, monetary damages,
construction of a filtration system, and other relief as the
court should deem appropriate. Resolution of this lawsuit
was apparently stayed while the Gannett study was being
completed.

The Gannett study was issued on October 31, 1968.
The Abstract of the Report adequately summarizes the
conclusions and recommendations of the consulting engi-

neers:
* * * * * *

4a

Opinion, Court of Claims

The source of the turbidity is the excavation for
Interstate Route 84, L.R. 1049, which is being con-
structed approximately one-half mile north of the Mil-
ford water supply reservoirs. The primary source is
the cut slopes of the highway excavation between
Vantine Brook and Vandermark Creek. After heavy
rains, turbid runoff water from this area enters Van-
tine Brook and then infiltrates to the ground water
body which feeds the Milford water supply reser-
voirs. * * *

The turbidity problem can be significantly re-
duced by transporting all drainage from the highway
slopes east of Vantine Brook to Vandermark Greek,
by stabilizing these same highway slopes with seed
and mulch or other means, and by reducing the ve-
locity and thereby the erosion tendency of water dis-
charged to Vantine Brook. The combined use of
these measures would effect a significant reduction
in the turbidity within two years. After this initial
reduction it is expected that operating procedures at
the Milford water supply can provide water of ac-
ceptable quality. [Emphasis supplied. ]

Should the measures described above prove to
be insufficient the paving of infiltration zones along
Vantine Brook or the construction of a clear water
holding reservoir are feasible alternative solutions.
The project costs for a one million gallon steel hold-
ing reservoir would be about $100,000; the total
cost for channel lining cannot be determined without
additional knowledge of the extent of the zones of
infiltration along Vantine Brook. The construction
of a holding reservoir would represent a permanent

Opinion, Court of Claims 5a

improvement to the Milford supply. [Emphasis sup-
plied. ]

Thus, the primary recommendation of the Report was
to redesign the area’s drainage system and to rapidly re-
plant the exposed slopes. This solution was the least ex-
pensive, with an estimated cost of $58,000, and was likely
to provide an acceptable cure to the problem. More ex-
pensive measures, such as a one million gallon holding
reservoir, costing $100,000, or a complete water treat-
ment facility, costing $750,000, would not be necessary
unless the drainage revisions and the replantings did not
cure the problem. The record indicates the State did
design a revised drainage system costing $58,000, but the
revisions were never made.

Copies of the Report were given to Federal Highway
Administration (FHWA) officials on November 6, 1978.
Thereafter, State officials met with counsel for Milford
in an effort to end the lawsuit. Staff members of the
FHWA attended some of the meetings as observers but
did not participate. The State agreed to finance the con-
structions of a 1.5 million gallon steel reservoir and to
provide a five-year water-quality surveillance program.’
The reservoir was not built Instead, by supplemental
agreement, the State agreed to pay Milford $275,000 to
release all claims against the State.

2The 1.5 million gallon reservior was 500,000 gallons in ex-
cess of that which the consulting engineers recommended as an
alternative if the drainage revisions and replantings proved unsuc-
cessful. The record offers no explanation why the State agreed
to construct a reservior 50 percent greater than that thought neces-
sary by the consultants it hired.

3 The turbidity problem cured itself. The water today is of
acceptable quality.

6a Opinion, Court of Claims

The State paid the money to Milford and submitted
a formal request to the FHWA for reimbursement of the
settlement cost as a construction expense under Project
I-84-1(19)46. The FHWA denied federal participation
on August 7, 1970. Thereafter, the State resubmitted the
denied settlement costs as a right-of-way expense under
Project I-84-1(12)46. Apparently not realizing the costs
were being dealt with as construction expenses and had
already been denied, the right-of-way personnel allowed
the settlement costs under the right-of-way project. When
the mistake was discovered, the FHWA recovered the
$275,000 by means of a setoff against moneys owed Penn-
sylvania under other projects. Eventually, this suit fol-
lowed.

Simultaneous with the events involving the Milford
Water Authority, a related dispute arose between the Penn-
sylvania Department of Highways and its construction
contractor, Gasparini. By letter of December 20, 1967,
Gasparini requested the State’s approval of a borrow site*
known as the Olmstead site, beginning in spring 1968.°
This was Gasparini’s first formal request to use this par-
ticular site, although apparently other grading and bor-
row operations had occurred in 1967. The contract spe-
cifications required the State to approve any borrow site
adjacent to the highway or likely to cause pollution of
waterways. The Olmstead site was adjacent both to the
highway and, unfortunately, to Vantine Brook, a feeder
stream into the utility’s reservoirs. Fearful that borrow

4A borrow site is where fill material for grading operations
is excavated.

5 Borrow and fill operations generally cannot be conducted
during winter months in northern climates, as the frozen ma-

terials will not pack properly.

Opinion, Court of Claims 7a

operations at the site would exacerbate the turbidity prob:
lem, the State indicated it would approve the site only
if Milford also agreed to the borrow site. Gasparini
sought, but did not receive, Milford approval. Neverthe-
less, throughout early 1968 the State encouraged Gasparini
to continue to try to gain Milford approval of the Olm-
stead site rather than to direct the contractor to obtain
fill elsewhere. The State finally formally directed Gas-
parini to use alternate borrow sites on August 12, 1968.
Had the State directed the use of alternate borrow sites
by April 1, 1968, additional costs of approximately $90,-
000 above the contract price for borrow would have been
incurred,

By letter of August 20, 1968, Gasparini gave written
notice of its intention to assert a claim for delay based on
the borrow dispute. On February 20, 1970, Gasparini
submitted a delay (and related expenses) claim of $2.3
million. The $2.3 million claim represented the contrac-
tor’s total cost for the entire grading and borrow portions
of the project, net of payments previously received, plus
a $225,000 profit. The contractor computed his costs
not on actual expenditures but, instead, by using artificial
hourly rental (“force account”) rates. By use of the force
account rates, Gasparini’s equipment charges were 300
percent of actual equipment costs.

State highway officials met with Gasparini to resolve
the claim in March and April 1970. As with the Mil-
ford negotiations, FHWA staff members attended the
meetings as observers but did not participate, At the April
meeting, Gasparini offered to withdraw its $2.3 million
claim if the State would pay $846,778, which Gasparini
alleged represented its actual costs for the entire grading

8a Opinion, Court of Claims

and borrow portions of the project, plus a profit of $144,-
000. This proposal did not use the force account rates
to compute equipment costs. The State tentatively ac-
cepted the settlement at the meeting and finalized the set-
tlement by letter later that month. Gasparini was sub-
sequently paid $835,612, of which 90 percent reimburse-
ment is demanded from the United States.

We begin by observing that these settlement costs
exceed the original Project Agreement cost limitations.
Although neither party has cited authority which requires
reimbursement of these unforeseen costs, the defendant
concedes it has a policy of reimbursing unbudgeted settle-
ment costs." On brief, no doubt based on this policy, the
defendant assumes that reimbursement of reasonable settle-
ment costs is required (presumably under the original
Project Agreement) and, instead, addresses itself to the
question of to what extent these settlements were reason-
able. There is nothing in this record which causes us to
reject defendant’s understanding of its obligations. The
majority therefore cannot agree with the suggestion in

“The court’s own research discloses that the FHWA had is-
sued at least one formulation of this policy prior to the date of
this Project Agreement, Paragraph 19 of Policy and Procedure
Manual 21-6.3 (now 23 C.F.R, §635,.120 (1980)). That paragraph
seemingly became a part of this Agreement under a clause incor-
porating ‘‘regulations[,] * * * policies and procedures * * *’’ of
the FHWA even though the paragraph was not then formally a
regulation, See People of the State of California v, United States,
213 Ct. Cl, 329, 338, 551 F.2d 843, 848, cert, denied, 434 U.S, 857
(1977) ; People of the State of California v, United States, 547 F.
2d 1388, 1390 (9th Cir.), cert. denied, 484 U.S, 824 (1977),
Neither party, however, has argued that Paragraph 19 applies to
these settlements. Accordingly, we rest our decision on other

grounds,

Opinion, Court of Claims 9a

the concurring and dissenting opinion that reimbursement
can only be required where a separate formal request has
been made prior to settlement. On these facts, the de-
fendant’s view that it is required to reimburse reasonable
settlement costs under the Project Agreement is sufficient.

Defendant’s decision to limit its reimbursement ob-
ligation to only reasonable settlement costs, we think,
necessarily follows from the statutory scheme (and its
legislative history) establishing the federal highway aid
program. From that scheme,

* * * it is clear that Congress did contemplate
that the Secretary exercise administrative expertise
to see that apportioned funds are not expended on
projects which fail to meet reasonable standards of

cost.
* * * " * *

The Congressional intent is that the Secretary
may exercise his discretion to insure that the roads
are well constructed and safely built at the lowest
possible cost, all in furtherance of the Act * * *,

State Highway Commission of Missouri v. Volpe, 479 F.
2d 1009, 1113-1114 (8th Cir. 1973); see Mahler v. United
States, 306 F.2d 713, 718-719 (3d Cir.) , cert. denied, 371
U.S. 923 (1962). See also Citizens Organized to Defend
Environment, Inc. v. Volpe, 353 F. Supp. 520, 531 (S.D.
Ohio 1972).

A rule requiring federal participation regardless of
reasonableness might well be imprudent where the state
disbursing the moneys bears only a small fraction of the
true costs. Applying a rule of reasonableness to unfore-
seen costs in cases under the Act is consistent with the

10a Opinion, Court of Claims

more general rule requiring that a government contractor
must proceed reasonably in order to recover expenses be-
yond the limitations contained in a cost-reimbursement
contract. E.g., Singer-General Precision, Inc. v. United
States, 192 Ct. Cl. 435, 427 F.2d 1187, 1192 (1970).
We find the defendant’s requirement, that unbudgeted
settlement costs are reimbursable only if reasonable, to
be proper. Indeed the State does not seriously dispute
that only reasonable settlement costs are eligible for fed-
eral participation.

Nor does the State dispute the well-established rule
in this court that a ‘government contractor bears the
‘burden of establishing the fundamental facts of liability,
causation and resultant injury.’” Electronic and Missile
Facilities, Inc. v. United States, 189 Ct. Cl, 237, 253, 416
F.2d 1345, 1355 (1969), citing Wunderlich Contracting
Co. v. United States, 173 Ct. Cl. 180, 199, 351 F.2d 956,
968 (1965); Roberts v. United States, 174 Ct. Cl. 940,
956, 357 F.2d 938, 949 (1966). See also Huerta v.
United States, 212 Ct. Cl. 473, 548 F.2d 343 (1977).

Instead, the State argues as an initial matter that un-
der the Federal-Aid Highways Act actual, or historic, costs
are presumed to be reasonable, This alleged presumption,
the State continues, shifts the ultimate burden of proof
from it as a contractor, see Electronic and Missile Facili-
ties, supra, to the defendant. Thus, once actual costs are
shown in a suit under the Act, the State concludes, reim-
bursement must be made unless the defendant proves the
actual costs are umieasonable, Following this reasoning,
the trial judge below concluded that the defendant failed
in its burden and that reimbursement was appropriate in
the full amount sought by plaintiff.

Opinion, Court of Claims lla

We assume, arguendo, that a presumption for reim-
bursement does arise under the Federal-Aid Highways Act
once actual payment by a state is shown. Cf. Bruce Con-
struction Corp. v. United States, 163 Ct. Cl. 97, 102, 324
F.2d 516, 519 (1963) (in general equitable adjustment
actions, “historical’’ costs are presumed reasonable). In
modern federal civil practice, Federal Rule of Evidence
301 controls the effect of presumptions. It provides:

Rule 301.

PRESUMPTIONS IN GENERAL IN CIVIL ACTIONS
AND PROCEEDINGS

In all civil actions and proceedings not other-
wise provided for by Act of Congress or by these
rules, a presumption imposes on the party against
whom it is directed the burden of going forward with
evidence to rebut or meet the presumption, does not
shift to such party the burden of proof in the sense
of the risk of nonpersuasion, which remains through-
out the trial upon the party on whom it was originally
cast. [Emphasis supplied. ]

Thus, unless Congress has otherwise required the ultimate
burden of proof in cases under the Act to shift to the
Government, F.R.E. 301 requires the ultimate burden to
remain with the State here, the presumption notwithstand-
ing.

Nowhere in the Federal-Aid Highways Act is there
an express requirement that the ultimate burden must shift
once actual costs are shown. Moreover, although the lan-
guage of a statute might implicitly require such a result,
cf., e.g., Griggs v. Duke Power Co., 401 U.S. 424, 432
(1971) (intent of Title VII is to shift burden to employer

12a Opinion, Court of Claims

to disprove discrimination); Albemarle Paper Co. v.
Moody, 422 U.S. 405, 425 (1975) (same), our review
of the relevant legislative history surrounding the initial
passage of the Act in 1916 convinces us that Congress
was concerned that imprudent state action might drain
the federal treasury. E.g., H. Rep. No. 26, 64th Cong.,
Ist Sess. 4-5 (1916); S. Rep. No. 250, 64th Cong., Ist
Sess. 15-6 (1916). See generally Mahler v. United States,
306 F.2d at 719-722. That concern seems inconsistent
with a conclusion that Congress intended the FHWA to
affirmatively disprove the reasonableness of state dis-
bursals exceeding project spending limitations. Also, we
are not unmindful that under the legislative scheme, the
various states actually disburse the money and then seek
reimbursement from the FHWA. Thus, a state seems
far better able to prove the reasonableness of an ex-
penditure than is the FHWA to disprove the reasonable-
ness of the expenditure. For these and other reasons, no
previous federal appellate decision has shifted the ultimate
burden in an FHWA case to the Government. See, e.g.,
People of the State of California v. United States, 213 Ct.
Cl. 329, 551 F.2d 843; Louisiana Department of High-
ways v. United States, 221 Ct. Cl. ——, 604 F.2d 1339
(1979); Mahler v. United States, supra; State Highway
Commission of Missouri v. Volpe, supra; People of the
State of Calfiornia v. United States, 547 F.2d 1388. See
also Massachusetts v. Connor, 248 F. Supp. 656 (D. Mass.
1966). We see no reason to reach a different result to-
day merely because the State wishes it so.

Therefore, since Congress has not otherwise provided,
F.R.E. 301 precludes the shifting of the ultimate burden
from the State of Pennsylvania to the defendant. Since
the defendant met the presumption by offering evidence

Opinion, Court of Claims 13a

that the settlement costs were unreasonable, we now turn
to each settlement to determine its reasonableness.

We begin by rejecting the defendant’s argument that
neither the Milford nor the Gasparini settlements could
be reasonable because both disputes stemmed from the
State’s negligence in design of the highway. We are hesi-
tant to adopt such a broad rule, especially where the
FHWA must itself approve highway design prior to any
construction. On these facts, however, we need not reach
the absolute rule for which the defendant contends. The
trial judge below found, and we concur, that these facts
are insufficient to establish design negligence by the State.
Similarly, we reject the State’s initial argument that estop-
pel lies against the defendant to deny either claim. Noth-
ing in this record convinces us the Government misled the
State. Moreover, the thrust of the State’s argument, that
Arizona Highway Department v. United States, 204 Ct.
Cl. 171, 494 F.2d 1285 (1974), somehow limits the
Government’s right to recover the erroneous payments of
the Milford claim, is incorrect as a matter of law. The
United States has inherent authority to recover sums er-
roneously paid, and it cannot be estopped from doing so
by the mistakes of its officers or agents. Aetna Casualty
& Surety Co. v. United States, 208 Ct. Cl. 515, 520, 526
F.2d 1127, 1130 (1976), and citations contained therein.

With these initial comments, we turn to the central
matter, whether these settlement payments were reason-

able.
Milford Settlement

In arguing that its settlement for $275,000 with the
water utility was reasonable, the State stresses both that
the Milford lawsuit posed an enormous potential liability

14a Opinion, Court of Claims

and that the drainage revisions its own consultants recom-
mended were not guaranteed to solve the turbidity prob-
lem. Since the settlement ended all potential exposure,
the State concludes, the settlement was a fortiori reason-
able. For its part, the defendant asserts that the drainage
revisions and replantings recommended by Gannett if im-
plemented would have controlled the turbidity at a much
lower cost. Thus, the defendant says, any settlement cost
in excess of $58,000, the amount the State concedes the
revisions and replantings would have cost, was unneces-
sary and hence unreasonable."

The true liability that a lawsuit poses is rarely sus-
ceptible of precise quantification prior to final judgment.
Both parties in litigation may encounter unforeseen dif-
ficulties of proof. The skill of opposing counsel and the
resources each side can devote to the conflict may be addi-
tional unknowns. Moreover, no party can be precisely
certain of the interpretation the trier of fact will give to
either the facts or the law. All of these factors are dif-
ficult to quantify and even though free to recognize
frivolous claims, we have been reluctant to second-guess
the decisions of litigating parties and their counsel with
respect to settlements involving claims of at least some
merit. Louisiana Department of Highways, 221 Ct. Cl.
at ——, 604 F.2d at 1347-1348. Our reluctance to sit

7™The Government also argues that under Policy and Proce-
dure Memorandum 30-4, which is applicable to this project, any
settlement costs which exceed the cost of the drainage revisions
and replantings constitute a betterment to the utility and are in-
eligible for federal participation. Under our holding, we need
not reach this contention regarding Policy and Procedure Mem-
orandum 30-4. Moreover, we note the argument also turns on a
determination of whether the revisions and replantings were the
reasonable solution to the turbidity problem.

Opinion, Court of Claims 15a

as a local court on the merits of the Milford claim, how-
ever, does not insulate the eventual settlement from all
scrutiny to determine reasonableness when federal par-
ticipation is sought. Thus, the fact that these sums were
expended to settle litigation is to be considered, but in
no sense is decisive on the issue of their reasonableness.

In Louisiana Department of Highways, supra, the
State of Louisiana had settled a claim with little, if any,
merit. Under Paragraph 19 of Policy and Procedure
manual 21-6.3, which had been incorporated into Lou-
isiana’s Project Agreement, reimbursement would only be
made of settlement costs which were “grounded in con-
tract provisions and specifications and actual costs in-
curred.” In construing this language, we wrote:

* * * the language particularly pertinent to this
case is: ‘the extent to which such settlements are
grounded in contract provisions and specifications
and actual costs incurred.’ Though the wording is
far from clear (and could and should be clarified)
we understand this provision to mean that the Fed-
eral Highway Administration will refuse to partici-
pate if the contractor’s claim is not reasonably,
arguably, or colorably founded in some part of the
contract or the specifications, fairly construed. Con-
versely, the regulation seems to mean that the Fed-
eral Government will not participate in a settlement
of a contractor’s claim which is wholly unmeritorious,
insubstantial or frivolous. We take it to be the de-
liberate policy of the Highway Administration to
discourage the making and settlement of such worth-
less claims by letting it be known in advance that it
will not participate in a settlement—even though the
Federal Government will be liable to share the costs

16a Opinion, Court of Claims

of the litigation if the matter does go to trial. That
policy choice is, of course, one for the Highway Ad-
ministration to make. [221 Ct. Cl. at ——, 604 F.
2d at 1340.]

With that as a predicate, we concluded that, even if Lou-
isiana’s settlement with the contractor was assumed to be
reasonable in a general sense when considering a policy
favoring settlement of litigation, the standard expressed
in Policy and Procedure Manual 21-6.3 demanded that
“Ca] contractor’s claims have more substantiality and
potential merit than the claim involved [there].” Jd.
We think similar considerations are applicable here. At
a minimum, a claim against a state must have some basic
merit to be considered for reimbursement as “reasonable.”
But the mere fact that a claim against a state may have
some legal merit does not mean any possible settlement
of the claim is reasonable. We must also look to wheth-
er the settlement, as made, appears to be reasonable on
all of the facts available to a state at the time of settle-
ment. We have, in other circumstances, characterized
the duty of reasonableness in several ways, but the essence
of the term is that a party must proceed prudently, wisely,
and efficiently. See H & H Manufacturing Co. v. United
States, 168 Ct. Cl. 873, 884-885 (1964); Bruce Construc-
tion Corp. v. United States, 163 Ct. Cl. at 100-101, 324
F.2d at 518-519; Nager Electric Co. v. Uni.cd States, 194
Ct. Cl. 835, 852-853, 442 F.2d 936, 945-946 (1971).
The settlement is reasonable only to the extent it would
have been made “by a prudent businessman placed in a
similar” position. Nager Electric Co., 194 Ct. Cl. at 852,
442 F.2d at 945. See Bruce Construction Corp., 163 Ct.
Cl. at 100-101, 324 F.2d at 518-519.

Opinion, Court of Claims 17a

Here, the Milford settlement for $275,000 was unrea-
sonable in light of the alternative action the State might
have taken to end its potential liability. As its own con-
sultants’ Report demonstrated, the Milford turbidity prob-
lem was likely to have been cured had the State im-
plemented the drainage revisions and replantings costing
$58,000 that it designed following the Report. While
the State is correct that the engineers did not guarantee
this solution, we think the State requires too much.

It is clear from the Report that the engineers con-
cluded the drainage revisions and replantings would pro-
vide an acceptable and workable solution to the turbidity
problem:

XII CONCLUSIONS

* * * * * *

(11) The careful construction [of the drainage
modifications] * * * should result in the gradual
reduction of the turbidity problem at the Milford
reservoirs. They represent the fastest and most
practical solution. It is expected that by following
* * * [this recommendation] the problem can be
reduced sufficiently in about two years to the point
where operating procedures at the reservoirs can
adequately handle the problem. As the slopes of the
highway stabilize, the turbidity problem should
gradually reduce and, after five years, be minimal.
[Emphasis supplied. ]

Further, it is clear that Gannett recommended the drain-
age revisions and replantings as the most reasonable and
economic solution to the problem. In the Report, Gan-
nett exhaustively analyzed the sources of the problem,
proposed solutions and evaluated the effectiveness of each

18a Opinion, Court of Claims

solution, and then compared the various alternatives on a
cost-effective basis. Gannett’s recommendation, based
upon the 18-month study, was that the drainage revisions
and replantings should be implemented and only if the
replantings and revisions failed to control the problem
would it be necessary to explore other more costly alter-
natives. After reviewing this record, we conclude im-
plementation of the drainage revisions and replantings af-
forded the State an opportunity to resolve the Milford
litigation at a far lower cost than the eventual cash set-
tlement the State chose. We find a private businessman
in such a position would have chosen to implement the
drainage revisions and replantings to end the litigation.
We require no less prudence from the State as a public
businessman.

Therefore, we conclude that implementation of the
drainage revisions and replantings at a cost of $58,000
provided the reasonable solution to the Milford litigation.
We hold that defendant must participate only to the ex-
tent of 90 percent of $58,000, or $52,200, in the Milford
settlement.

Gasparini Claim

To justify its Gasparini settlement, the State argues
that it faced a potential liability of $2.3 million for Gas-
parini’s excess borrow costs when the State formally re-
quired the use of an alternate borrow site on August 12,
1968. The defendant counters by asserting either that the
State had an unqualified contract right to reject the Olm-
stead site without liability for excess costs or, alternatively,
if liability existed, that the State unreasonably fail-d to
mitigate the excess costs when it delayed until August 12,
1968, in requiring an alternate site.

Opinion, Court of Claims 19a

Both parties have pled and argued Pennsylvania law
in support of their respective positions on whether the
State would have been found liable had Gasparini pros-
ecuted its claim. After considering the arguments of each,
we conclude the State has met the threshold test we have
established for settlement costs to be reasonable, i.e., there
was at least some merit to the Gasparini claim. See Com-
monwealth, G.S.A. v. Loffredo, 16 Pa. Commonwealth
Ct. 237, 328 A.2d 886 (1974). See also Carbon Con-
struction Co. v. Commonwealth, Department of Trans-
portation, Bd. of Arbitration No. 476 (decision of Sep-
tember 30, 1976). But see Central Penn Industries, Inc.
v. Commonwealth of Pennsylvania, Department of Trans-
portation, 25 Pa. Commonwealth Ct. 25, 358 A.2d 442
(1976). We have considerable doubt, however, that
Gasparini’s settlement proposals accurately reflected the
excess costs incurred solely because of the alternate site
requirement. We leave to another day whether erroneous
assumptions concerning the true date of breach, the proper
allocation of costs to the post breach period, and the prof-
itability of the contractor may themselves render a settle-
ment unreasonable. See, e.g., Boyajian v. United States,
191 Ct. Cl. 233, 239-240, 245-254, 423 F.2d 1231, 1235,
1238-1244 (1970) , and cases cited therein.

As we have already discussed with regard to the Mil-
ford settlement, the State must demonstrate that it pro-
ceeded reasonably in settling the Gasparini litigation.
Reasonableness requires, we think, not only that the State
explore and adopt less expensive alternative means of
terminating the lawsuit other than by outright cash settle-
ment but, also, that the State proceed in a manner so that
its potential liability on claims is kept to a minimum.

20a Opinion, Court of Claims

This record indicates that the State did not formally
request Gasparini to use an alternate site until August
12, 1968, and in fact encouraged Gasparini throughout
early 1968 to continue to seek approval (however un-
likely) of the Olmstead site from Milford. This Gas-
parini did from December 1967 through August 1968.
Milford, during this time, had already sued the State over
the turbidity. The State’s hope that Milford might gratui-
tously approve the Olmstead site and its potential for in-
creased turbidity seems unfounded in light of Milford’s
observable willingness to protect its water supply. More
prudently, the State at some point prior to the scheduled
start of spring 1968 borrow operations should have con-
cluded that no such approval would be forthcoming from
Milford and that another borrow site would have to be
used. Had the State acted, it could have avoided delay.
The State was well aware that any delay in the start of
the spring 1968 borrow operations would greatly increase
the excess costs associated with an alternate site. Pru-
dence dictated that the State make a timely decision so
that delay could be avoided and any excess costs kept to
a minimum. This the State failed to do. Had the State
acted in a timely manner, the record is clear that Gas-
parini’s excess borrow costs would have been significantly
lower than the $846,000 the contractor claimed as a re-
sult of delay until August. The trial judge found, and
we concur, that had the State required an alternate bor-
row site on April 1, 1968, Gasparini would have incurred
additional costs approximately $90,000. The failure of
the State to give such timely direction was unreasonable.
Cf. Astro-Space Laboratories, Inc. v. United States, 200
Ct. Cl. 282, 308-309, 470 F.2d 1003, 1018 (1972) (re-
procurement must occur in a timely manner after default
and mitigation of damages to be reasonable) .

Opinion, Court of Claims 21a
Concurring and Dissenting Opinion

Therefore, we conclude that the reasonable solution
to the borrow site controversy was for the State to direct
the contractor by the start of spring 1968 borrow opera-
tions to obtain borrow elsewhere. Had the State done
this, the contractor’s excess borrow costs would have been
limited to $90,000. We hold that defendant must par-
ticipate only to the extent of 90 percent of $90,000, or
$81,000, in the Gasparini settlement.

Based on the foregoing, we conclude federal par-
ticipation in these settlements is required to the extent
of $52,200 plus $81,000, or $133,200. Judgment of
$133,200 is entered for plaintiff.

NICHOLS, Judge, concurring and dissenting:

I agree with the holding of the panel insofar as it
reduces the award from $999,551.20 to $133,200, but,
respectfully, | would go further and dismiss the petition.

The FHWA contract with the State specified an
amount and stated as follows: ‘“[fJederal funds are ob-
ligated for the project not to exceed the amount shown
herein.” The contract and relevant regulation on the
pertinent date are silent as to what happens in case of
unbudgeted claims, breaking the ceiling if allowed. I
think, in such circumstances, certain requirements are
implied, or are to be met by reformation to effect the real
agreement of the parties. They are, if the State wishes
to pay the claims and be reimbursed, it should obtain
FHWA approval in advance. It is not sufficient to inform
the FHWA officials to attend the settlement negotiations
as observers. The State should have insisted on prompt

22a Opinion, Court of Claims
Concurring and Dissenting Opinion

decisions. In argument before us, State counsel said they
were fearful of an injunction suit (in the case of the Mil-
ford claim) and were aware by past experience how dila-
tory the FHWA would probably be in passing on requests
for unbudgeted funds. I do not consider this excuse ad-
equate. If defendant had failed to rule promptly on ex-
plicit reimbursement requests, thereby delaying the project
and increasing the cost, it would have been liable in breach
damages for failing in its “implied duty of cooperation
and noninterference which is inherent in any contract.”
S. A. Healy Co. v. United States, 216 Ct. Cl. 172, 188,
576 F.2d 299, 306 (1978), and cases cited. But an im-
plied burden on defendant to make a ruling promptly does
not arise until it has a request for one before it.

I do not read Louisiana Department of Highways v.
United States, 221 Ct. Cl. ——, 604 F.2d 1339 (1979)
as the panel does. The opinion of Senior Trial Judge
White, which the court adopts as its own, seems to me to
hold in the concluding portion that the settlement there
involved was “reasonable and in the public interest” but
reimbursement was not allowable because not given ap-
proval by defendant before being paid. The court in its
preliminary per curiam remarks construes the White opin-
ion to view the settlement as prudent to make but not
reimbursable because not ‘“‘grounded in contract provisions
and specifications and actual costs incurred,” a standard
stated in a regulation not argued to be applicable here.
Apparently the regulation was meant to require disallow-
ance of claim settlements even if prudent and reasonable,
if the claim does not meet some objective criteria. But
the court did not disavow the alternative ground stated
in the White opinion and I think it is correct. Defend-

24a Judgment

UNITED STATES COURT OF CLAIMS

No. 429-75

COMMONWEALTH OF PENNSYLVANIA,
DEPARTMENT OF TRANSPORTATION

vs.

THE UNITED STATES

At a Court of Claims held in the City of Washington,
on the 25th day of February, A.D. 1981, judgment was
ordered to be entered as follows:

IT IS ADJUDGED AND ORDERED that plaintiff
recover of and from the United States pursuant to the
court’s opinion entered this date the sum of one hundred
thirty three thousand two hundred dollars ($133,200.00) .

A true copy of record.

In testimony whereof I have hereundo set my hand
and affixed the seal of said Court at Washington, this 25th
day of February, A.D. 1981.

Frank T. Peartree
Clerk, Court of Claims.

Attest: Daniel M. Friedman
Chief Judge.

Opinion, Court of Claims 23a
Concurring and Dissenting Opinion

ant did acknowledge that the FHWA has consistently
contributed to additional (unbudgeted) costs (it deemed)
reasonably incurred. That it has commendably waived
the contract cost ceiling when persuaded the claim was
reasonable, does not mean it waives it when not so per-
suaded. Nor do I think it can be estopped into a waiver
by inaction (laches) of its representatives. Costello v.
United States, 365 U.S. 265, 281 (1961).

It appears to me plaintiff is seeking equitable relief,
whether we deem it reformation of the basic contract or
enforcement of clauses added to it by implication. Where
any obligation it incurs is supposedly to be reimbursed
by the United States up to as much as 90 percent, it owes
the United States a strong obligation in equity, first, to
protect the interests of the United States, and second, to
give it every opportunity to protect its own interests. It
did not do the first, as we find, in the portions of the
opinion I join in, that the settlements were grossly ex-
cessive. It did not do the second: instead of miscon-
struing the silence and nonfeasance of dilatory FHWA
representatives, it should have demanded a decision in a
manner to reach the attention of FHWA highest levels.
He who seeks equity must do equity. Viewing the claim
as equitable, as I do, I do not deem a claimant that had
conducted itself as inequitably as Pennsylvania has here,
can require us still to reconstruct the agreement of the
parties to allow Pennsylvania the small amounts the ma-
jority consider properly allowable. I would let all the
loss lie where it has fallen.

24a Judgment

UNITED STATES COURT OF CLAIMS

No. 429-75

COMMONWEALTH OF PENNSYLVANIA,
DEPARTMENT OF TRANSPORTATION

vs.

THE UNITED STATES

At a Court of Claims held in the City of Washington,
on the 25th day of February, A.D. 1981, judgment was
ordered to be entered as follows:

IT IS ADJUDGED AND ORDERED that plaintiff
recover of and from the United States pursuant to the
court’s opinion entered this date the sum of one hundred
thirty three thousand two hundred dollars ($133,200.00) .

A true copy of record.

In testimony whereof I have hereundo set my hand
and affixed the seal of said Court at Washington, this 25th
day of February, A.D. 1981.

Frank T. Peartree
Clerk, Court of Claims.

Attest: Daniel M. Friedman
Chief Judge.

Opinion, Trial Judge 25a

APPENDIX B

IN THE UNITED STATES COURT OF CLAIMS
TRIAL DIVISION

No. 429-75
(Filed: September 27, 1979)

COMMONWEALTH OF PENNSYLVANIA,
DEPARTMENT OF TRANSPORTATION

v.
THE UNITED STATES

Contracts; Federal-Aid Highways Act; reimbursement of
State; litigation between highway contractor, affected
utility, and State; settlement; Federal participation.

Stuart ]. Moskovitz, Assistant Attorney General, at-
torney of record for plaintiff. Robert W. Cunliffe, Deputy
Attorney General and Gerald Gornish, Acting Attorney
General, of counsel.

Richard ]. Webber, with whom was Assistant At-
torney General Barbara Allen Babcock, for defendant.

26a Opinion, Trial Judge
OPINION*

FLETCHER, Trial Judge: This case presents a
claim by the Commonwealth of Pennsylvania Department
of Highways, (hereinafter ‘Penn DOT”), under the Fed-
eral-Aid Highways Act, 23 U.S.C. §§101 et seg. (1970).
Penn DOT insists that it is entitled to reimbursement for
90 percent of certain costs incurred by it in the settlement
of claims by third parties arising out of interstate highway
construction in Pennsylvania.

Under the Federal-Aid Highways Act funds are ap-
propriated and allocated among the states for the purpose
of providing Federal participation in the construction costs
of the interstate highway system. The degree of Federal
participation is determined under a complex statutory
formula which in this case yields a 90 percent Federal
contribution.

Penn DOT had obtained Federal approval evidenced
by Letters of Authorization for the proposed construction
of a portion of Interstate Highway 84 in Northeastern
Pennsylvania under the designation Project No. 1-84-1
(19)46. After Federal approval of the project’s detailed
plans, specifications, and estimates, Penn DOT entered
into project agreements with the Federal Government
under which defendant was obligated to pay 90 percent
of the estimated total cost of the construction and inci-
dental utility and right-of-way expenses. Meanwhile,
Penn DOT had contracted with the Gasparini Excavating
Company (hereinafter “Gasparini” or “contractor”) for
clearing, grubbing, grading, drainage, and structures on

*The trial judge’s recommended decision and conclusion of
law are submitted in accordance with Rule 134 (h).

Opinion, Trial Judge 27a

the project, and Gasparini commenced work on April 25,
1967.

On or about August 8, 1967, the Municipal Water
Authority of the Borough of Milford (hereinafter “Au-
thority” or “MWA”’) contacted Penn DOT complaining
of excessive turbidity in the Authority’s water supply
which was located in reservoirs about one mile from the
highway construction. The Authority expressed the view
that the turbidity problem was the direct result of the
highway construction operations being conducted in the
neighborhood of its reservoirs.

Penn DOT engaged the firm of Gannett, Fleming,
Corddry & Carpenter, Inc. to perform a study and prepare
a report regarding the cause and cure of the above-de-
scribed problem. The study was completed and an En-
gineering or Consultant’s Report thereon was printed and
issued under date of October 31, 1968.

The report concluded that the excavation for Inter-
state 84 was, in fact, the cause of the turbidity in the Au-
thority’s reservoirs. In addition, the report recommended
alternative actions to cure the problem. The report stated
that the surest way to eliminate the contamination of the
water supply would be through the construction of a water
treatment facility at an estimated cost of $560,000. Such
a solution would take several years to complete and would
represent a betterment to the Authority’s facilities. The
second most certain remedy would be the construction of
a one million gallon steel holding reservoir at a probable
cost of $100,000. Such a reservoir would be filled with
water during periods of lesser turbidity and that water
could be used in place of the water from the open reser-
voirs during periods of turbidity. Finally, the least ex-

28a Opinion, Trial Judge

pensive approach to the problem would call for the re-
design of the drainage system coupled with rapid refolia-
tion of the excavations and periodic monitoring of the
water quality in the reservoirs. The cost of such drain-
age revision was estimaied to be $58,000, and the report
stated that the third approach would reduce the turbidity
to a level where “it is expected that operating procedures
at the Milford water supply can provide water of an ac-
ceptable quality.” Both plaintiff and defendant rely on
this Engineering Report and neither has questioned its
accuracy.

Following conferences and an exchange of letters, on
December 21, 1967, the Authority filed a Complaint in
equity in the Commonwealth Court of Pennsylvania
against the Pennsylvania Secretary of Highways, ihe Gas-
parini Excavating Company, and the consulting engineer.
That suit demanded construction of a filtration system,
redesign and revision of drainage, money damages, and
“such other and further relief as may be deemed just and
proper.”

Conferences and negotiations between representatives
of MWA and Penn DOT followed the filing of the Com-
plaint. Also, it appears clear that representatives of the
Federal Highway Administration (FHWA) were aware
of these negotiations and even attended some of the con-
ferences.

Following a meeting on November 27, 1968, a
“Memorandum of Understanding” was prepared and
signed by counsel for both Penn DOT and MWA. The
Memorandum resulted in an agreement dated January 23,
1969 whereby plaintiff agreed to build a 1.5 million gallon
reservoir and to provide a five-year water quality mon-
itoring, or surveillance, program.

Opinion, Trial Judge 29a

The January 23 agreement, however, was suspended
by a later agreement dated August 3, 1970, whereby Penn
DOT agreed to pay MWA $275,000 in return for MWA’s
release of Penn DOT from all claims and a voluntary dis-
missal of its pending court Complaint. At all times,
cognizant representatives of FHWA were aware of the
aforesaid negotiations and agreements between Penn DOT
and MWA, but at no time did they either approve or dis-
approve them.

The Authority has never constructed a holding reser-
voir which might be deemed a permanent improvement to
MWA facilities. In fact, by August 3, 1971, the level
of turbidity had lessened to levels well within the require-
ments of the U.S. Public Health Service with no appre-
ciable difference between the quality of the water up-
stream from the construction and that downstream from
the construction. According to the testimony of a Penn
DOT engineer, this would indicate that the I-84 construc-
tion presently does not contribute any significant turbidity
to the Milford water supply. Of course, it was unknown
at the time of the settlement between the Authority and
Penn DOT that the contemplated corrective measures
would not in fact be needed. Indeed, the experts had
consistently taken a cautious approach. For example,
after outlining a redesign of drainage facilities and a two-
year surveillance program, the Engineering Report, supra,
had this to say:

B. If the program outlined under A above
does not prove effective, it is recommended that a
more elaborate program be undertaken. Specifically,
it would be recommended that if all infiltration
zones cannot be isolated and if the turbidity problem
must be solved at the Milford reservoirs, the Penn-

30a

Opinion, Trial Judge

sylvania Department of Highways should consider
participating with the Municipal Authority of the
Borough of Milford in the construction of a holding
reservoir which would be filled with water during
times when there is no turbidity and which would
supply water to the system when both the present
reservoirs are turbid.

The cost of such a holding reservoir was estimated

to be about $100,000, plus the continuing costs of under-
taking the recommended surveillance program. Mean-
while, as a consequence of the pollution of the Authority’s
water supply, Penn DOT had become concerned about the
contractor’s previous choice of a site for obtaining bor-
row’ for highway grading. The contractor’s choice had

1 Pertinent contract provisions relating to borrow operations

are as follows:

(a) Specifications, Section 3.5.3

The obtaining of borrow pits shall be the contractor’s
responsibility.
“eee
Where the contractor desires to obtain borrow adjacent
to the highway, written approval of the engineer shall be
secured, * * *
ene

(ce) Specifications, Section 1.7.13

** * The contractor shall take all necessary precautions
to prevent damage to all overhead and underground struc-
tures, and to protect and preserve property within and ad-
jacent to the project and shall be responsible for damage
thereto. Special care shall be exercised by the contractor in
the prosecution of the work in order to avoid interference
or damage to any operating utilities or plants; however,
where there is any possibility of interference or damage, the
contractor shall make satisfactory arrangements with the

Opinion, Trial Judge 3la

been a property near the highway known as the Olmstead
site which was adjacent to Vantine Brook, a feeder stream
for the Authority’s reservoirs. In order to avoid the pos-
sibility of further contamination of the Authority’s water
supply, Penn DOT directed that Gasparini could use the
Olmstead site only if approved in advance by MWA.
Gasparini was never able to obtain such approval from
the Authority. After some delay, Gasparini was able to
find another borrow site at a more distant location. This
change resulted in increased hauling costs, and caused
further construction delay. When that site was exhausted,
additional borrow was still needed. In addition, the bor-
row at this alternative site was of lesser quality than that
at the Olmstead site so that it became necessary to man-
ually remove stones from the material, an unanticipated

responsible officers or with the owners of the utilities or
plants; covering the necessary precautions to be used as
safeguards during the performance of the work by the con-
tractor. These arrangements shall be made before said work
is started and shall be subject to the approval of the engineer,
which approval shall not be considered as releasing the con-
tractor from any responsibility for the acts of himself or his
employees or representatives.
eee

(d) Specifications, Section 1.7.19

The contractor shall take sufficient precautions to pre-
vent pollution of streams, lakes, and reservoirs with fuels,
oils, bitumens, calcium chloride or other harmful materials.
He shall schedule and conduct construction operations to
prevent when necessary, and otherwise minimize, pollution
of streams, etc., with sediment or other harmful materials.

The areas of erosive land exposed by construction opera-
tions at any one time which may cause subsequent water
pollution, are subject to the approval of the Engineer.

32a Opinion, Trial Judge

operation, again causing delay and increased cost. These
cumulative delays resulted in shifting the construction
schedule into the winter months during which little ac-
tivity was possible, thus causing further delay and ex-

pense.

On February 4, 1970, Gasparini presented a claim
for additional costs predicated on the aforesaid delays and
increased borrow costs. Two alternative claims were pre-
sented. One was for $2,300,000 which was the amount
to be sought if litigation ultimately became necessary.
The other, for a lesser amount, represented the figure
for which Gasparini would be willing to settle. The dif-
ference in amounts was based primarily on a difference
in accounting method. The higher amount based claims
for equipment cost on accepted book rates for rental. The
lesser amount represented actual costs which were docu-
mented by the contractor and which, pursuant to an audit
by Penn DOT, were found to aggregate over $835,000.

As indicated previously, throughout the negotiations
with the Authority and Gasparini, the FHWA representa-
tives were kept fully informed at all levels. They were
invited to and attended meetings where the claims of the
Authority and the contractor were discussed. Yet, at
none of these meetings did the FHWA representatives
express an opinion for or against the potential settlements,
and this refusal to offer guidance or any adverse comments
caused the Department to conclude that FHWA had no
objection to the settlements either with MWA or Gas-
parini.

The ultimate question now before the court would
seem to be this: Under what circumstances, if any, may
the FHWA refuse its agreed participation in costs which

Opinion, Trial Judge 33a

were unanticipated at the time of the contract between the
Federal and State Governments but which nonetheless
were incurred by the State in connection with a Federal-
Aid Highway project?

Considering the complexity and unpredictability of
iiighway construction projects, and in the light of the con-
flicts inherent in an arrangement wherein one party (the
state) manages the construction project while another
party (the Federal Government) pays the bulk of the
cost, one would have expected that in the fifty-odd years
of Federal-Aid roadway projects this issue would have
been confronted and fully resolved. So far as I can deter-
mine, however, it has not been so resolved, at least in the
context of this case.

An answer to the question requires, initially, a brief
review of the workings of Federal-Aid Highway projects.
Under the Federal-Aid Highways Act, supra, after Con-
gressional appropriation of highway funds, those funds
are apportioned among the states. States then generate
highway proposals which are submitted to the Secretary
of Transportation for approval. The Secretary is then
required to review the proposal applying criteria estab-
lished by Section 109 of the Act. If the project is ap-
proved, the state then develops and submits detailed
“plans, specifications, and estimates” for final approval
by the Secretary. The Act specifies that approval of those
detailed plans shall create “a contractual obligation of the
Federal Government for the payment of its proportional
contribution thereto.” (Sec. 106(a)). Thereafter, the
State and Federal Governments execute formal Project
Agreements. In the present case, there was one agreement
covering the acquisition of rights-of-way and another
covering the actual highway construction. Those Project
Agreements state, in pertinent part:

34a Opinion, Trial Judge

The State, through its Highway department, -
having complied, or hereby agreeing to comply, with
the terms-and conditions set forth in (1) Title 23,
U.S. Code, Highways, (2) the Regulations issued
pursuant thereto by the Secretary of Commerce and,
(3) the policies and procedures promulgated by the
Federal Highway Administrator relative to the above
designated project, and the Bureau of Public Roads
[now the Federal Highways Administration] having
authorized certain work to proceed as evidenced by
the date entered opposite the specific item of work,
Federal funds are obligated for the project not to
exceed the amount shown herein, the balance of the
total cost being an obligation of the State. Such
obligation of Federal funds extends only to project
costs incurred by the State after the Bureau of Public
Roads authorization to proceed with the project in-
volving such costs. | z

Although the percentage of Federal participation may
vary as between projects, in the instant case, the Federal
reimbursement share is established by Sec. 120 of the Act
to be “90 per centum of the total cost thereof.”

Federal participation in a project after the signing
of the Project Agreements typically seems to be quite lim-
ited. It is the state which purchases required right-of-
way, arranges utility adjustments, enters into contracts
with the companies that will perform the construction,
and which generally oversees all aspects of construction,
independently making all necessary decisions, routine and
otherwise. There may be occasional Federal site inispec-
tions and Federal reviews and approvals of vouchers for
costs incurred by the state. Where, as in the present case,
unanticipated problems arise, officials of the FHWA may

Opinion, Trial Judge 35a

be drawn more closely into the decision-making process.
However, as shown by the facts here, their role can some-
times be merely one of passive observation.

At the finish of construction, the Act calls for Fed-
eral inspection of the finished project followed by final
payment of the Federal share of the balance of cost upon
approval by the Secretary.

The plaintiff contends essentially that where the
claimed costs have arisen in connection with a Federal-
Aid Highway Project and have been actually incurred by
the State, the inquiry is at an end, and the FHWA must
contribute its proportionate share of such costs. While
there is considerable merit to this contention,’ on balance
it appears overly simplistic.

2 As previously stated, the Act deems approval of the ‘‘ plans,
specifications, and estimates’’ to create a ‘‘contractual obligation
of the Federal Government for the payment of its proportional
contribution thereto.’’ (Sec. 106 (a)). The degree of Federal
participation is established by Sec. 120 of the Act which in this
case sets the Federal participation at ‘‘90 per centum of the
total cost thereof.’’

In addition to this statutory language, the legislative history
of the Act lends some support to the plaintiff’s position. The
debates during the initial passage of the Act in 1916 reflect a
concern with striking a balance between the protection of state
independence in roadway construction and protection of the Fed-
eral Treasury against wasteful state spending. Those debates
suggest that the Federal purse was thought to be adequately
protected by the Act’s provisions granting the Secretary of Ag-
riculture (then administering the Act) the authority to review
plans and refuse approval of those projects not meeting Federally
established standards. In addition, the final inspection provision
allowed the Secretary to witkaold approval of future projects in
states which failed to meet those standards in the execution of

36a Opinion, Trial Judge

The first weakness in plaintiff’s preliminary conten-
tion is that it appears to ignore the well-settled rule
that the FINWA may limit its participation in costs in-
curred by way of Policy and Procedure Memoranda
(PPM) which are incorporated by reference into the
Project Agreements. People of the State of California v.
United States, 213 Ct. Cl. 329, 551 F.2d 843 (1977)
(PPM limiting Federal participation in right-of-way ac-
quisitions to fair market value rather than cost-of-replace-
ment held binding on State); People of the State of Cali-
fornia v. United States, 547 F.2d 1388 (9th Cir. 1977)
(PPM limiting Federal participation in interest payments
on condemnation awards to that amount accrued during
the first 30 days from deposit in court held binding on

-

State.) oe, “engages

While the Ninth Circuit decision directly addressed
only the question of whether the PPM was enforceable
by the FHWA, in reaching that conclusion, the court dis-
cussed the broader issue stating:

The interpretation sought by the State would
prevent the Secretary . . . from making any evalua-
tion as to the reasonableness of the costs of construc-
tion or from promulgating regulations reasonably
designed to limit such costs. Certainly, Congress
must have intended that the statutory obligation to
pay 90 percent of the total cost must include some
corresponding right to impose reasonable limitations
upon such costs, rather than leave the Federal Trea-

projects. Further protections of the Federal purse were apparent-
ly not then considered to be necessary or even desirable. S. Rep.
No. 250, 64th Cong., 1st Sess. See generally, Mahler v. United
States, 306 F.2d 713 (3d Cir. 1962).

Opinion, Trial Judge 37a

sury at the mercy of unfettered discretion by the
State as to what expenditures may be made and
charged accordingly. 547 F.2d at 1390.

Similar reasoning was applied in Commonwealth of
Massachusetts v. Connor, 248 F. Supp. 656 (D. Mass.
1966) where Massachusetts sought by way of mandamus
to force approval by the Secretary of a reimbursement
voucher. The voucher represented the cost of a Federal-
Aid Highway right-of-way as determined by a condemna-
tion proceeding jury verdict. In refusing to grant man-
damus relief, the court stated:

Certainly the duty, if any, of the Secretary to
approve the state’s voucher in the present case is not
a ministerial one. The Secretary must make a de-
cision as to whether the claim presented is a proper
one. Certainly it cannot be contended that he is
bound to accept without question any claim in what-
ever amount Massachusetts wishes to make. 248 F.
Supp. at 659.

The above cases are well-grounded in common sense.
Absent some clear statutory or contractual statement to
the contrary, it must be assumed that the intent of Con-
gress and of the contracting parties was that the FHWA
should, and does, retain some discretion to refuse par-
ticipation in unreasonable costs incurred by the state.’

Another possible interpretation of the agreement be-
tween Penn DOT and the FHWA arises from certain lan-

3 Indeed, even Pennsylvania seems to recognize this when, in
its reply brief it fails to reassert the argument that the FHWA
lacks such discretion, and seems to argue only that the FHWA
must participate in ‘‘reasonable’’ costs.

38a Opinion, Trial Judge

guage of the Project Agreements. That language, stating
that ‘Federal funds are obligated for the project not to
exceed the amount shown herein,” would appear at first
blush to establish a cost reimbursement ceiling. From
that language it could be argued that, absent prior con-
tractual approval of a specific cost, the FHWA is under
no obligation to reimburse the state for that cost.‘ In the
present case, the settlements were neither included within
the initiai project agreements, nor were they approved as
subsequent projec: modifications.

There are, however, problems with that interpreta-
tion. The language of the Project Agreements does not
so clearly establish a maximum reimbursement amount
that it cannot be interpreted in the light of contrary evi-
dence. See Scherr & McDermott, Inc. v. United States,
175 Ct. Cl. 440, 360 F.2d 966 (1966). Also, such an
interpretation would seem in conflict with the language
of the Federal-Aid Highways Act discussed above and
would depart from the administrative practice of FHWA
which does not require prior approval of costs, but rather
allows an evaluation of the cost after it has been incurred.’

*See for example, the recent decision in Louisiana Depart-
ment of Highways v. United States, Ct. Cl. No. 129-76, —— F.
2d ——, decided July 18, 1979, which may well reflect this view
by indicating that, because certain unanticipated costs were not
contractually approved by the FHWA, the FHWA was not liable
for participation despite a finding that the state had acted rea-
sonably and in the public interest by incurring the costs in ques-
tion.

5 Closely related to the issue here is the question of the weight,
if any, to be accorded the final decision of the FHWA denying
reimbursement. It could possibly have been argued (but was not)
that the function of this court under the cireumstances here pres-
ent is limited to a review of the FHWA’s determination only

Opinion, Trial Judge 39a

Here, Penn DOT orally sought advance FHWA ap-
proval of the settlements and urged quick action to avoid
possible rejection by the third parties. In addition FHWA
representatives were kept fully informed. They were in-
vited to and attended most, if not all, of the meetings
where the third parties’ claims were discussed. They
offered no guidance one way or the other, but voiced no
objections, causing Penn DOT representatives reasonably
to conclude that FHWA in fact had no objections. None-
theless, several years later FHWA issued its decision deny-
ing the requested participation.

While neither of the parties has attempted to char-
acterize the agreement herein, it seems to me, reading the
statute and the project agreements together, that it can
best be described as a specialized type of percentage-of-
cost contract. Consequently, the rules generally applicable
to cost reimbursement type contracts would seem ap-
plicable here.

As a general matter, the costs to be reimbursed under
a cost-type contract are actual costs, not reasonable costs.
Charles A. Burton, Inc. v. Durkee, 162 Ohio 433, 123

for possible arbitrary or capricious action. Such an argument,
however, could be disposed of quickly. The decision of the FHWA
is nothing more than a statement of position by one of the con-
tracting parties. In the absence of some statutory or contractual
provision for dispute resolution elsewhere, authority is vested in
this court by the Tucker Act, 28 U.S.C. Sec. 1491, to render its
decision de novo. Under these circumstances, it is clear that the
decision of one of the contracting parties (the FHWA) carries
no special weight in this court’s disposition of the case. See,
Southwest Welding and Mfg. Co. v. United States, 188 Ct. Cl.
925, 413 F.2d 1167 (1969). In fact, the court’s task is to deter-
mine whether the FHWA’s refusal to participate in the settle-
ments was itself a breach of the contract.

40a Opinion, Trial Judge

N.E. 2d 432 (1954), 17 Am. Jur. 2d, Contracts Sec. 349.
This court has held that actual or historical costs are pre-
sumed reasonable. Nager Electric Co. v. United States,
194 Ct. Cl. 835, 442 F.2d 936 (1971), Bruce Construc-
tion Co. v. United States, 163 Ct. Cl. 97, 324 F.2d 516
(1963).

In this case, there is no question but that the claimed
costs of settlement were actually incurred. Since those
costs are presumed reasonable, the burden rests with the
defendant to justify its non-participation through persua-
sive evidence of fraud, misrepresentation, negligence, or
some other affirmative proof of unreasonable behavior
on the part of the plaintiff. See, James, Burdens of Proof,
47 Va. L. Rev. 51 (1961). To hold otherwise would
encourage the Federal Government to sit idly by, as it
did here, secure in the knowledge that the State must af-
firmatively justify the incurring of any unanticipated costs.
This burden rests upon the defendant despite the presence
in the Project Agreements of a clause purporting to estab-
lish a cost ceiling because “[t]he general rule with respect
to a [cost reimbursement] contract, unless it is clearly
negatived, is that the Government assumes the risk of ex-
penses beyond the estimated price which are not due to
unreasonable conduct by the contractor.” Singer-General
Precision v. United States, 192 Ct. Cl. 435, 446, 427 F.
2d 1187 (1970), citing Wyman-Gordon Co., 59-2 BCA
para. 2344 ASBCA No. 5100. See also Lykes Bros. SS
Co. v. United States, 198 Ct. Cl. 312, 459 F.2d 1393
(1972) holding that the burden of proof does not neces-
sarily follow the burden of pleading. In my opinion,
defendant has not succeeded in discharging its burden
of proving negligent conduct or other unreasonable be-
havior on the part of Penn DOT.

Opinion, Trial Judge 4la

In this connection it is important to bear in mind
that all of the unanticipated costs here claimed were
expended by plaintiff in the settlement of actual and
potential legal actions. Of course, it cannot be the task
of this court here to decide the probable outcome of some
hypothetical litigation in the Pennsylvania courts between
Penn DOT and MWA or Gasparini. Had those disputes
gone to trial in Pennsylvania, Penn DOT would have
been found to be either liable or not liable for specific
reasons. There would be no gray area. Those disputes,
however, did not go to trial in Pennsylvania, and MWA
and Gasparini were neither present nor represented at
the trial of the present case. Since the disputes were set-
tled without trial, this court surely cannot be called upon
to determine the probable outcome of any hypothetical
local litigation. Instead, one should test the reasonable-
ness of the settlements, by making a determination which
must take into account factors more than the relative
merits of the disputants’ legal positions. One factor to
be considered is the public policy which favors settlement
of legal disputes thereby decreasing the burden on limited
judicial resources. From the perspective of the parties,
settlements will preserve their personal and financial re-
sources, reduce acrimony, and improve the prospects for
satisfactory future relationships between the parties.
Finally, of course, settlements eliminate the uncertainties
always attendant upon any trial. All of these considera-
tions are difficult to quantify, and even though free to
recognize frivolous claims, courts should be reticent to
“second-guess” the decisions of litigating parties and their
counsel with respect to matters which involve claims
having potential merit. See Louisiana Department of
Highways v. United States, supra. Despite the criticisms

42a Opinion, Trial Judge

expressed by the Auditor General of Pennsylvania in his
letter of July 20, 1970, to the Secretary of Transporta-
tion,’ (finding 40) I am persuaded by the record in this
case that Penn DOT’s actions in this regard were not negli-
gent in the legal sense and that the firm belief of the At-
torney General (finding 38) that the claims had merit was
correct.

In sum, where unanticipated costs arise in connection
with an approved Federal-Aid Highway project and the
Federal Government refuses to participate in those costs,
the state must prove that such costs were actually incurred
and that they arose out of a federally approved project.
Such evidence establishes a prima facie case for reim-
bursement. Since under those cimcumstances the statute
creates a presumption in favor of payment, the burden
then must fall upon the Federal Government to justify
non-payment through proving a breach by the plaintiff.
If there are no contract provisions, PPMs for example,
limiting the Federal obligation, then the Government must
affirmatively prove that the state expenditure was unrea-
sonable.

The defendant’s first affirmative defense to payment
of its proportionate share of the unanticipated costs is that
all of the additional costs were incurred as a result of
the damage to the Milford Water Authority and that such
damage was a result of negligence on the part of the plain-
tiff’s employees. In support of this contention, defend-
ant introduced documentary evidence suggesting that cer-
tain Pennsylvania officials were of the opinion that Penn

®It should be noted that during his testimony at the trial
of this case, Mr. Casey appeared to retract, or at least consider-
ably soften, his earlier criticisms of Penn DOT’s actions.

Opinion, Trial Judge 43a

DOT acted negligently in the design and construction of
the highway because the State had received notice of the
- possibility of harm to the Authority’s reservoirs. See
findings 37-40. However, the only direct evidence of no-
tice to Penn DOT, is contained in a letter from the Au-
thority to Penn DOT dated December 27, 1965. That
letter stated:

We have been advised by our engineer, that he
does not believe that the construction of this highway
will affect our springs or the probable locations of
the veins of water leading to the springs.

However, there is always a possibility that if
there were deep cutting or blasting done in the event
[sic] of these veins, the supply of water to these
springs could be disrupted.

Negligence, of course, will not be presumed, and in
my view it has not been established by the evidence in
this case. Aside from some opinions of Pennsylvania
officials rendered several years after the effect of the con-
struction on the reservoirs became known, there remains
only the letter quoted above which in a rather awkward
way appears to conclude that damage to the reservoirs or
water supply was not likely.

It should also be noted that the location and design
of the highway had been previously approved by the de-
fendant itself which apparently did not recognize the pos-
sibility of contamination of the Authority’s reservoirs lo-
cated less than a mile from the construction.

Finally, the defendant suggests nothing that could and
should have been done differently. It seems clear that,
in order to avoid participation in unanticipated costs in-
curred in connection with highway construction, the de-

44a Opinion, Trial Judge

fendant must show that the cost to it would have been
less had the acts complained of not taken place. Here
there is no evidence showing that the highway could
have been built without incurring the cost of eliminating
the contribution of the highway’s construction to unac-
ceptable turbidity in the Authority’s reservoirs.

The defendant makes the alternative argument that,
even if the Federal Government 1s obligated to contribute
to the cost of the settlement between the Commonwealth
of Pennsyivania and the Milford Water Authority, that
obligation is limited to the cost of a drainage revision, a
substantially lesser cost than the actual settlement amount.

In support of this argument, defendant first relies on
its Policy and Procedure Memorandum (“PPM’’) 30-4
as limiting its participation to that portion of the MWA
settlement which does not represent a “betterment” to the
Authority’s preexisting facilities.

There remains no doubt that the Federal Govern-
ment’s reimbursement obligation may be limited by its
Policy and Procedure Memoranda which are incorporated
by reference into the terms of the Project Agreements be-
tween the State and Federal Governments.’ People of the

7 Of course, only those regulations which are in effect at the
time of the making of the contract can be incorporated by refer-
ence. Sundstrand Turbo v. The United States, 182 Ct. Cl. 31,
389 F.2d 406 (1968). The PPM at issue here was issued on Oc-
tober 15, 1966, after the date of the Secretary’s approval of the
‘‘plans, specifications, and estimates’’ and after the effective date
of the Project Agreement covering construction, The plaintiff
addresses this issue only by once characterizing this PPM as
‘*after-the-fact,’’ without explanation. For the purposes of this
decision, it is not necessary to decide whether this PPM was, in
fact, incorporated into the contract. It will be assumed arguendo
that it was.

Opinion, Trial Judge 45a

State of California v. United States, 213 Ct. Cl. 329, 551
F.2d 843 (1977). PPM 30-4 states that the Federal reim-
bursement share for utiity adjustments shall be limited to
the total cost incurred less any portion which represents
a “betterment” to the utility. Defendant contends that
plaintiff, if entitled to some compensation is entitled to
only the cost incurred in the settlement less the difference
between the cost of a drainage revision and the cost of
the holding reservoir because in the Government’s view
the surplus over the drainage revision cost represented a
betterment and was so described by the consultants in
their Report.

“Betterment” is defined by PPM 30-4 to mean “any
upgrading made solely for the benefit of and at the elec-
tion of the utility, not attributable to the highway con-
struction.” In the context of this case, however, plain-
tiff is entitled to full reimbursement if the holding reser-
voir reasonably appeared to be the minimum necessary
cure for the damage caused by the highway construction.*

Defendant points to opinions contained in the con-
sultants’ Report to the effect that a drainage revision could
be effectuated quickly and would significantly reduce the
turbidity problem. The consultants, however, specifically
advised that such measures might not prove to be suf-
ficient, and if insufficient, other more costly cures would

8 The defendant repeatedly and correctly points out that the
holding reservoir was never actually constructed by the Milford
Water Authority. This fact, however, should be of no comfort
to defendant. All that is necessary is that the plaintiff reason-
ably believed the holding reservoir to be necessary at the time
the decision to settle was made, Sundstrand Turbo v. United
States, supra. All are blessed with 20-20 vision hindsight but
few can claim the same of their foresight.

46a Opinion, Trial Judge

have to be effectuated. The Report found that construc-
tion of a water treatment facility might become necessary.
The alternative of the holding reservoir “would cost less
than half as much as the treatment plant and could repre-
sent a nearly 100 percent effective solution to the tur-
bidity problem.” Consultants’ Report p. 61. In addition,
the consulting engineers never attempted to design a drain-
age revision. That task fell to Mr. Finn, Pennsylvania’s
Construction Engineer for the project, and his group of
engineers. His uncontroverted testimony was that they
were unable to design a practical drainage revision.

Under all of these circumstances, it is my opinion
that the plaintiff acted reasonably in concluding that con-
struction of the holding reservoir would be the most re-
liable cure for the turbidity problem and since that prob-
lem was entirely attributable to the highway construction,
it would not represent a betterment to the Authority’s
existing facilities.”

Defendant then proceeds to argue that the FHWA
is not obligated to participate in the cost of the settlement
with the Gasparini Construction Company. In support
of this contention, defendant says that no claim by Gas-
parini would have arisen but for the plaintiff’s negligence
in causing the turbidity problem. Having previously
concluded that the turbidity problem was not negligently
caused, an argument based upon the contrary conclusion
clearly cannot be accepted. In addition, however, there

® As an alternative argument for limiting Federal reimburse-
ment to the cost of a drainage revision, the defendant contends
that, quite apart from the PPM limitation, it was unreasonable
for the plaintiff to agree to build a holding reservoir. This con-
tention is essentially the same as that raised by the principal argu-
ment and is necessarily resolved the same way.

Opinion, Trial Judge 47a

is an element not present in the Milford Water Authority
settlement claim but present in the Gasparini claim. It
raises a subsidiary issue of whether the defendant’s par-
ticipation is foreclosed by Penn DOT’s alleged fraud or
misrepresentation. The defendant points to letter opin-
ions by the Attorney General of Pennsylvania and his
deputy stating their belief that the State would be liable
to Gasparini because the State’s failure to inform the con-
tractor of the possibility that the construction might cause
contamination to the water supply of MWA amounted to
fraud or misrepresentation.

This contention must fail in the light of the limited
evidence of prior knowledge of such possible contamina-
tion on the part of Penn DOT. As previously stated, the
defendant presented only a letter from the Authority to
Penn DOT and that letter concluded in effect that the
highway construction was unlikely to contaminate the Au-
thority’s water supplies. Such knowledge would hardly
require Penn DOT to inform the contractor of the pos-
sibility of contamination.

The defendant also claims that it is not liable for its
share of the cost of the Gasparini settlement because un-
der the terms of the contract between Pennsylvania and
Gasparini, Pennsylvania had the right to refuse approval
of borrow sites. Hence, defendant says since Pennsyl-
vania by refusing to approve the Olmstead site was merely
exercising a contractual right, it was not liable to Gas-
parini for the resulting delay. Thus, in defendant’s view,
the settlement payment was gratuitous and the Federal
Government need not participate in gratuitous payments.
The plaintiff, of course, interprets the applicable specifica-
tion differently because it believes that the right to reject
a borrow site under section 1.7.19 dealt only with con-

48a Opinion, Trial Judge

siderations of possible erosion after completion of the
work and not with the effect of the borrow operation dur-
ing the construction period.

Here again, the resolution of this issue is not for this
court’s determination of whether Penn DOT had a con-
tractual right under Pennsylvania law to refuse approval
of the Olmstead borrow site. To repeat, the basic task
for this court is to determine whether the Federal Gov-
ernment has shown that it was unreasonable, in light of
the complexities involved, for Penn DOT to enter into
the settlement with Gasparini. In my opinion, defendant
has failed to carry that burden.

Finally, further consideration should be given to this
court’s recent decision in Louisiana Department of High-
ways v. United States, Ct. Cl. No. 129-76, dated July 18,
1979, F.2d , in which it is held that in a claim
for reimbursement under the Federal-Aid Highways Act,
where the claim is for costs incurred in settlement of third-
party claims against the state, there must be reasonable
grounds for belief that the state would have been liable
on the third party claims. In the Louisiana case, it was
the opinion of the State’s counsel, concurred in by the
court, that the contractor’s claim was entirely without
merit. The present case differs in that crucial respect.
Here, there is ample evidence that, in the opinion of Penn-
sylvania’s responsible legal officials, the Commonwealth
of Pennsylvania might well have been found liable to the
third party claimants on the basis of any of several pos-
sible legal grounds had the claims finally gone to litiga-
tion. They determined in good faith that the claims should,
be settled, not merely to avoid expensive and troublesome
litigation, but to avoid the possibility of substantially
greater liability. While, as stated above, the court should

Opinion, Trial Judge 49a

be reticent to look behind the assessments of Pennsyl-
vania’s legal officials as to the State’s liability under
Pennsylvania law, I nevertheless conclude that their con-
clusion to settle the claims was reasonably justified un-
der the unexpected complexities that had gradually de-
veloped.

While I conclude it was not unreasonable for Penn
DOT to believe that it faced a real danger of being held
liable to the third party claimants, that potential liability
was not grounded on negligence or unnecessary actions
which would excuse the defendant’s contractual obligation
to reimburse plaintiff for its share of the costs necessary
to avoid the threatened litigation. Given the Act’s pre-
sumption in favor of reimbursement, there must be more
than has been shown here to excuse that obligation. The
Commonwealth of Pennsylvania should have judgment
rendered in its favor in the sum of $999,551.20, and de-
fendant’s counterclaim for interest should be dismissed.

FINDINGS OF FACT

1. This action arises out of the Federal-Aid High-
way Act, 23 U.S.C. Secs. 101 et. seg. (1970). Under
that Act, the Federal Government assumes a proportion-
ate share of the costs incurred by the several states in the
construction of Interstate Highway projects. In this case,
the applicable Federal participation, as determined under
§120(c) of the Act, was “90 per centum of the total cost
thereof.”

2. Section 106 of the Federal-Aid Highway Act
provides in part:

>

50a Opinion, Trial Judge

Section 106. Plans, specifications, and estimates

(a) Except as provided in section 117 of this
title the State highway department shall submit to the
Secretary for his approval, as soon as practicable
after program approval, such surveys, plans, speci-
fications, and estimates for each proposed project
included in an approved program as the Secretary
may require. The Secretary shall act upon such sur-
veys, plans, specifications, and estimates as soon as
practicable after the same have been submitted, and
his approval of any such project shall be deemed a
contractual obligation of the Federal Government for
the payment of its proportional contribution thereto.
In taking such action, the Secretary shall be guided
by the provisions of section 109 of this title. [Em-
phasis supplied. ]

1

3. Effective January 23, 1967, defendant, acting
through the Bureau of Public Roads (now the Federal
Highway Administration) , (hereinafter “FHWA ) issued
a Letter of Authorization for construction of Federal Aid
Project No. I-84-1 (19) 46, a segment of Interstate High-
way 84 in Northeastern Pennsylvania. A similar Letter
of Authorization had previously been issued for acquisi-
tion of rights-of-way and for utility readjustment expenses
incident to the construction.

4. Plaintiff, Pennsylvania Department of Trans-
portation (hereinafter “plaintiff” or “Penn DOT”) con-
tracted on April 18, 1967, with Gasparini Excavating
Company (hereinafter “Gasparini” or “the contractor’)
for the grading and drainage of the aforesaid portion of
I-84. The contract period was 275 working days and the
estimated price was $3,047 ,572.94.

Opinion, Trial Judge 5la

5. Thereafter, plaintiff and defendant entered into
two Federal-Aid Project Agreements, each of which pro-
vided, in part:

The State, through its Highway Department,
having complied, or hereby agreeing to comply, with
the terms and conditions set forth in (1) Title 23,
U.S. Code, Highways, (2) the Regulations issued
pursuant thereto by the Secretary of Commerce and,
(3) the policies and procedures promulgated by the
Federal Highway Administrator relative to the above
designated project, and the Bureau of Public Roads
having authorized certain work to proceed as evi-
denced by the date entered opposite the specific item
of work, Federal funds are obligated for the project
not to exceed the amount shown herein, the balance
of the estimated total cost being an obligation of the
State. Such obligation of Federal funds extends only
to project costs incurred by the State after the Bureau
of Public Roads authorization to proceed with the
project involving such costs.

6. Gasparini commenced the physical construction
of the project on April 25, 1967.

Claim of Milford Water Authority

7. In early August 1967, the Milford Water Au-
thority (hereinafter the “Authority” or “MWA”) con-
tacted plaintiff, indicating MWA’s belief that the excava-
tion and grading operations taking place on the project
were adversely affecting the Authority’s water reservoirs,
especially after periods of heavy rain. The problems being
encountered included discoloration of the water, turbidity,
deterioration in the potability of the water (citing one
occasion when a sample from the East Reservoir did not

52a Opinion, Trial Judge

meet the recommended limits of the Pennsylvania Depart-
ment of Health with respect to color, turbidity, and iron
content), possible effects on clothing, and problems with
contamination of distribution mechanisms.

8. Penn DOT engaged the firm of Gannet, Fleming,
Corddry & Carpenter, Inc. to perform a study and prepare
a report regarding the cause and cure of the above-de-
scribed problem. The study was completed and an en-
gineering or consultant’s report thereon was printed and
issued under date of October 31, 1968.

9. The report concluded that the excavation for
Interstate 84 was, in fact, the cause of the turbidity in the
Authority’s reservoirs. In addition, the report recom-
mended alternative actions to cure the problem. The re-
port stated that the surest way to eliminate the contamina-
tion of the water supply would be through the construc-
tion of a water treatment facility at an estimated cost of
$560,000. Such a solution would take several years to
complete and would represent a betterment to the Author-
ity’s facilities. The second most certain remedy would be
the construction of a one-million gallon steel holding re-
servoir at a probable cost of $100,000. Such a reservoir
would be filled with water during periods of lesser tur-
bidity and that water could be used in place of the water
from the open reservoirs during periods of turbidity.
Finally, the least expensive approach to the problem
would call for the redesign of the drainage system coupled
with rapid refoliation of the excavations and periodic
monitoring of the water quality in the reservoirs. The
cost of such drainage revision was estimated to be $58,-
000, and the report stated that the third approach would
reduce the turbidity to a level where “it is expected that

Opinion, Trial Judge 53a

operating procedures at the Milford water supply can pro-
vide water of an acceptable quality.” Both plaintiff and
defendant rely on this Engineering Report and neither has
questioned its accuracy.

10. Prior to the issuance of the above-described
report, meetings had been arranged between MWA and
Penn DOT officials. A memorandum of October 6, 1967
to Mr. H. Poulson, Deputy Chief Engineer, from A. V.
Cesare, Civil Engineer, describes a meeting of October 5,
1967, attended by Pennsylvania Deputy Attorney Generals
John Rezzolla and Robert Cunliffe, as follows:

As you requested, I attended a meeting on Thurs-
day, October 5, 1967 in John Rezzolla’s office to
discuss the complaint concerning the possible con-
tamination of the Milford Reservoirs by our High-
way Construction on L. R. 1012-14.

Unfortunately, the complainants did not appear
and Rezzolla called the meeting off. We did, how-
ever, discuss the problem at length with John Rez-
zolla, Robert Cunliffe, and Joseph Jendrejewski from
District 4-0.

Some of the pertinent results of this discussion
were:

1. The rough grading is completed and the fine
grading and seeding will be completed within a week
or ©9 within the controversial area. Since this is only
a grading project and the paving contract will not be
let for several years, an injunction would have no
serious effect on the immediate progress of the work.

2. Apparently the complainants had a study
made by a geologist from Pennsylvania State Univer-
sity which indicates that our project may be con-
taminating this reservoir.

54a Opinion, Trial Judge

3. Our own soils people feel that we could
possibly be contaminating the reservoir.

4. John Rezzolla feels that we should have a
complete study made by a competent hydraulic en-
gineer to support our position either way. We agree
with this necessity. The District will explore this
further and be in contact with our office.

11. Thereafter, in a letter of October 17, 1967,
Robert G. Bartlett, plaintiff's Secretary of Highways,
wrote the following to the MWA:

This will acknowledge receipt of your letter of
October 11, 1967, advising me that the Board of
Directors of the Municipal Authority of the Borough
of Milford have directed their Solicitor to institute
injunction proceedings against the Department of
Highways and its contractor in order to protect its
water supply.

Please be advised that representatives of our
District Engineer’s Office in Dunmore, our Chief
Engineer’s Office and our Chief Counsel were to
meet with your Solicitor on October 5, 1967, at the
Chief Counsel’s Office.

If the Solicitor would have attended this meet-
ing, he would have learned that the contractor had
ceased excavating and grading operations in this area
because he is now at grade. The only operations
now being carried on are those which will be of bene-
fit to the Authority if the cause of the turbidity is
the highway cut, namely, seeding and mulching and
drains. Paving is not to take place until 1969, The
Solicitor would also have learned that this Depart-
ment has ordered a study by Hydraulic Engineers

Opinion, Trial Judge 55a

to determine if the turbidity is being caused by the
Highway cut and if so, what corrective steps can be
taken to insure that the Authority receives the same
quality of water it had in the past.

When this study has been completed, we will be
in touch with the Authority to advise them of the
findings. In view of the aforementioned facts, we
do not believe that the Authority should seek a rem-
edy in equity at this time.

Thank you for your best wishes for my tenure
in office, and I assure you that the Authority will
receive the cooperation of the Department of High-
ways if it is established that we are causing the al-
leged damage.

12. On December 27, 1967, the Authority filed in
the Commonwealth Court of Pennsylvania a Complaint
in Equity demanding construction of a filtration system,
redesign and revision of drainage, money damages and
“for such other and further relief as may be deemed just
and proper.” At the time the complaint was filed, ex-
cavation and grading in the pollution-causing area had
ceased and the road was up to grade. The remaining
work was of a type which actually would reduce but not
cure the pollution problem.

13. A summary of the conclusions of the consulting
engineers appears at the beginning of the Engineering Re-

port as follows:
ABSTRACT

Turbidity in the water supply reservoirs of the
Municipal Authority of the Borough of Milford could
result in the supplying of water to customers with a
quality less than that recommended by the Pennsyl-

56a

Opinion, Trial Judge

vania Department of Health. The turbidity, which
occurs after periods of heavy precipitation, is a sus-
pension of very fine material. The East Reservoir
is affected by turbidity more often and for longer
periods of time than the West Reservoir.

The source of the turbidity is the excavation for
Interstate Route 84, L. R. 1049, which is being con-
structed approximately one-half mile north of the Mil-
ford water supply reservoirs. The primary source is
the cut slopes of the highway excavation between
Vantine Brook and Vandermark Creek. After heavy
rains, turbid runoff water from this area enters Van-
tine Brook and then infiltrates to the ground water
body which feeds the Milford water supply reser-
voirs.

The construction drawings for Interstate Route
184 in the Vantine Brook and Sawkill Creek water-
sheds indicate that the highway design meets recog-
nized standards and practices.

The turbidity problem can be significantly re-
duced by transporting all drainage from the highway
slopes east of Vantine Brook to Vandermark Creek,
by stabilizing these same highway slopes with seed
and mulch or other means, and by reducing the velo-
city and thereby the erosion tendency of water dis-
charged to Vantine Brook. The combined use of
these measures would effect a significant reduction in
the turbidity within two years. After this initial
reduction it is expected that operating procedures at
the Milford water supply can provide water of ac-
ceptable quality.

Should the measures described above prove to be
insufficient, the paving of infiltration zones along

Opinion, Trial Judge 57a

Vantine Brook or the construction of a clear water
holding reservoir are feasible alternative solutions.
The project costs for a one million gallon steel hold-
ing reservoir would be about $100,000; the total
cost for channel lining cannot be determined without
additional knowledge of the extent of the zones of
infiltration along Vantine Brook. The construction
of a holding reservoir would represent a permanent
improvement to the Milford supply.

The construction of Interstate Route 84 will not
cause a significant change in the yield of the Milford
water supply and has not significantly affected the
storage capacity of the contributing ground water
aquifer.

Future roadway salting for Interstate Route 84
may cause a slight increase in the chloride content of
the Milford water supply, but is not expected to cause
the chloride content to approach or exceed the maxi-
mum concentration recommended by the Pennsylva-
nia Department of Health.

14.. The report describes MWA’s physical plant as
consisting of two reservoirs, designated West and East,
each of which is fed primarily by an enclosed spring. The
average daily demand on the water supply system is 200,-
000 gpd (gallons per day), and peak demand is estimated
at 500,000 gpd. The combined storage capacity of the
two reservoirs is 550,000 gallons. Total yield from the
springs which feed the reservoirs is estimated as 1,750,-
000 gpd.

15. Occurrences of turbidity in each of the reser-
voirs were monitored from May 1967 to September 1968.
The turbidity appeared within eight hours after a heavy

58a Opinion, Trial Judge

rain, primarily in the East Reservoir, although the West
Reservoir had traces of turbidity on occasion. The tur-
bidity lasted from one to several days after a rainfall.
Only one water sample, taken on August 25, 1967, showed
a quality which did not meet the recommended limits of
the Pennsylvania Department of Health, and that condi-
tion occurred in the East Reservoir only.

The Report discusses alternative solutions to the tur-
bidity problem and, with respect to highway drainage,
stated in part:

(1) Highway drainage. Changing the drain-
age pattern at the highway will have the greatest
effect on reducing that turbidity which has been fol-
lowing natural drainage paths and then infiltrating
through the stream bottom or banks. It will have
limited value in reducing that turbidity which may
be traveling entirely along an underground route.
The contribution of the latter type of turbidity move-
ment is considered to be minor, however. Changing
the drainage pattern of the runoff from the highway
areas would be the most effective way to prevent tur-
bid water from flowing over previous drainage chan-
nels and moving toward the Authority’s reservoirs.
It is not considered practical, however, to take all
of the drainage which is now designed to be dis-
charged to Sawkill Creek and Vantine Brook and
convey it to another stream. The areas adjacent to
Sawkill Creek and to the west of Vantine Brook have
small percentages of silt and clay particles and, based
on filed observations, the contribution of turbidity
from these areas probably is small. It is felt, there-
fore, that these areas could be drained as presently
designed. Care should be taken at the discharge

Opinion, Trial Judge 59a

points of the drains to reduce scouring by protection
at the ends of culverts and by allowing the runoff
water to flow over a few hundred feet of forest-
covered land before it enters the water courses. In
no case should high velocity water be discharged
directly into the streams or directly onto bare soil.

% * * * * * *

The initiation of the drainage change described
above, as soon as possible, should result in a sig-
nificant improvement in the turbidity problem. At-
tention should be paid to all details to insure that
all areas in the section are drained away from Van-
tine Brook. This work should result in an improve-
ment both during the construction period and during
the period while the highway slopes are stabilizing.

* * * * * * *

The redesign and construction of highway drain-
age to carry runoff water from the area east of Van-
tine Brook to Vandermark Creek is a potential solu-
tion which could be carried out immediately. This
measure would have relatively few uncertainties, few
operation 2° d maintenance problems, and could sub-
stantially reduce the turbidity problem at the Milford
supply.

* * * * * * *

Since quick results and economy are important
considerations in the solution of the turbidity prob-
lem, revisions to the highway drainage and imme-
diate work toward the stabilization of the highway
slopes have advantages over the other methods pro-
posed, even though there is some uncertainty that a
complete solution to the turbidity problem will be

60a Opinion, Trial Judge

obtained. Observation of the

[Text truncated at 120,000 characters. The full text is on the page linked above.]

---