# Petition for Writ of Certiorari — Northside Sanitary Landfill, Inc. v. Reilly

> Briefs, arguments, decisions, and more.

URL: https://www.frixlaw.com/law-library/documents/brief%3Amicro_IA40385002_0626%3A1

## Record

- **Collection:** Supreme Court brief
- **Document type:** Petition for Writ of Certiorari
- **Published:** January 1, 1989
- **Citation:** 489 U.S. 1078

## Text

~

—_—

re eran

, Supreme Court, U.S,
7 FILED

| DEC 71 1988
“JOREPH F. SPANIOL, JR.
‘ CLERK

<8 ao

No.
IN THE

Supreme Court of the United States

October Term, 1988

NoORTHSIDE SANITARY LANDFILL, INC.,
Petitioner,

f

Lee M. THOMAS, AS ADMINISTRATOR OF, AND THE
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY.
Respondents,

PETITION FOR A WRIT OF CERTIORARI TO THE
UNITED STATES COURT OF APPEALS FOR THE
DISTRICT OF COLUMBIA CIRCUIT

Warren D. Krebs
Counsel for

NORTHSIDE SANITARY LANDFILL,
INC.

PARR, RICHEY, OBREMSKEY &
MORTON

121 Monument Circle

Suite 500

Indianapolis, Indiana 46204

(317) 632-3686

QUESTIONS PRESENTED FOR REVIEW

1. Whether the Court of Appeals improperly concluded
that one subject to federal agency action must be cognizant of
“ll decisions directed at it which are both published in the
Federal Register and unpublished; and must detail by the time
for filing for reconsideration all objections later raised upon
judicial review, where the EPA did not serve its response to the
entity's written comments, the EPA’s regulation eliminated the
APA § 552(e) right of reconsideration, the statute does not limit
review to specific objections, and no adjudicatory hearing is
allowed.

2. Whether the Court of Appeals improperly concluded
that a site proposed for the National Priorities List (NPL)
under the National Oil and Hazardous Substances Con-
tingency Plan must raise all of its objections with specificity
prior to judicial review where the statute neither limits review
to objections raised with specificity nor permits an
adjudicatory hearing; where the statute and regulation provide
for only “informal comments”; and where the EPA provided no
reconsideration process under a statute requiring judicial
review within ninety days of the final rule.

3. Whether the EPA’s Final Rule promulgating its Update
to the NPL and the Court of Appeals’ prior decision upholding
EPA’s Hazard Ranking System preclude listing a site which
consists of regulated units of an unabandoned facility having
interim status under the Resource Conservation and Recovery
Act (RCRA).

4. Whether the Court of Appeals failed to apply the proper
standard of judicial review by concluding that it would have
denied Northside’s appeal on the merits where the EPA
obviously failed to comply with several requirements of its
Hazard Ranking System and where all scientific evidence con-
tradicts EPA’s crucial determinations regarding the number
and discontinuity of groundwater aquifers.

TABLE OF CONTENTS

Page
Ouinione TOGO 6. kc cna cas cacseenncea ce bene ewes l
Jutathetional Gusts i. a0 65 «Ae eee eee 2
Statutory And Regulatory Provisions Involved ........ 3
Statement OF The Gaee ioc nhl dee eee 7
Reasons For Allowing The Writ ..................05. 11

1. Congress Has Not Imposed Upon Those Selec-
tively Chosen For Agency Action The Duty To Read
Daily Notices Of Proposed Rulemaking Published
In The Federal Register, And Certainly Has Not
Imposed The Duty To Become Aware Of Agency
Responses Never Transmitted Nor Even Published
By The Agency ....«isccnanavus eee eee 13

2. Judicial Review Is Not Precluded As To Issues Not
Raised As Specific Arguments Or Summarized To
The Agency Unless The Statute Contains Such A
Preclusion Or Unless The Process Entails An
Adjudicatery Heart 6.62 gees waesaceeee ees 18
3. A Court Must Reverse An Administrative Decision

Where The Agency Has Failed To Comply With Its

Own Published Policy And Interpretation Of Con-

gressional Intent To Exclude A Particular Type Of

Facility From The National Priorities List ...... 21
4. The Circuit Court’s Opinion Constitutes The Grant-

ing Of A Degree Of Judicial Deference To An

Agency Action Equaling A Rubber Stamp Of A

Decision Which Is Contrary To The Regulatory

Requirements Of The Hazard Ranking System And

To The Record Eviddenee «6.50.5 s00-enesceaness 24

Cometusion .....acvsasskbsse tee 28

il

NS ee le wes vas eo te A-1
a ERPS ea a A-12
gat iG Cds vdeo sire wcke oercvk A-14
EE re eee A-15
a dois ad owe oso qc h inky, A-16
ens igs son ck nha bo A-17
OEE SER EE See ee ee ae a A-19
I eee eA a Oe | A-47
rh ct ST OE ge A-61
ee ge do cra bin ala bo akc A-62
ea a ae A a a A-63
EE TS ES ee A-65
ES SEES Rg A-73

iil

TABLE OF AUTHORITIES

Cases Page(s)

American Maritime Association v. United States, 766
ob PS Flas 2 | ere ree 17, 19

City of Seabrook, Texas v. U.S. EPA, 659 F.2d 1349
ee OS cca ak keen se chueanwe 12, 13, 14, 18, 19

Consolidated Freightways v. NLRB, 669 F.2d 790

Cea Oe SED la Ke ecs cewuadpuatepeseseasnwes 17
Dobbs v. Costle, 559 F.2d 946 (5th Cir. 1977) .......... 14
Dobbs v. Train, 409 F.Supp. 432 (N.D. Ga. 1975) ...... 14
Eagle-Picher Industries, Inc. v. U.S. EPA, 759 F.2d 905

ie pe | re ree re 8, 138, 19, 22, 24, 25
Eagle-Picher Industries, Inc. v. U.S. EPA, 822 F.2d 132

AG A ED hivn bat bee dene Kenan aensceeaeeanss 8, 19
Ethyl Corporation v. U.S. EPA, 541 F.2d 1 (D.C. Cir.),

cert. denied,426 U.S. 941 (1976) ................ 19, 24
Gage v. AEC, 479 F.2d 1214 (D.C. Cir. 1973) .......... 18
Home Bow Office, Inc. v. FCC, 567 F.2d 9 (D.C. Cir.), cert.

dented, 434 U.S. S20 (IST?) . 0.2.2 seesaw cnscnes 12, 16
Maryland People’s Council v. FERC, 761 F.2d 780 (D. C.

+ | ee pre rrr rer rrr rare 19, 24
Northside Sanitary Landfill, Inc. v. Ruckelshaus and

U.S. EPA, Cause No. 83-2258, U.S. Court of

Appeals for the District of Columbia Circuit ...... 2
Northside Sanitary Landfill, Inc. v. Thomas and U.S.

EPA, 849 F.2d 1516 (D.C. Cir. 1988) ........ 1, 11, 12, 24
Northside Sanitary Landfill, Inc. v. Thomas and U.S.

EPA, 804 F.2d 371 (7th Cir. 1986) ............. 1, 10, 23

Portland Cement Ass’n. v. Ruckelshaus, 486 F.2d 375

GPa Oe SUR acne tian euseusiicue eee 12, 18
Salt River Project v. United States, 762 F.2d 1053 (D.C.

See SU ceded nue sl ienceie eee 24
United States v. Northside Sanitary Landfill, Inc., Cause

No. IP88-172C (S.D. Ind. 1988) (App. H)...... 1,22
United States Satellite Broadcasting Company, Inc. v.

FCC, 740 F.2d 1177 (D.C. Cir. 1984) ............. 16

Vermont Yankee Nuclear Power Corp. v. Natural
Resources Defense Council, Inc., 435 U.S. 519

So Pee eer Pain es Munaicen 12, 13, 18, 19, 27
Washington Association for Television And Children v.
FCC, 712 F.2d 677 (D.C. Cir. 1983) .............. 20
Wisconsin Electric Power Co. v. Costle, 715 F.2d 323 (7th
Ce SE sh cde'cccvusnesy cchloct eee 15
Statutes
Administrative Procedure Act, 5 U.S.C. § 553
SUB: STII icosdsicivitatkesee eee
5 U.S.C. § 553(e) STILETTO
O0.S.C. SGRNOD. .o occ cccsscccevds i, 3, 14, 15, 16, 17, 20
PUA, Hea cide edes sa eesasee ee 3
DUM Ba is cdbiicerinecesvenncseee 3
Oe AL Go tks cds vended bee 2
Resource Conservation and Recovery Act of 1980,
42 U.B.C. §GOOLGBOA ooo ee cco co ccccccee. 8
eR RNR les= + | 22
Oe UE, PG ose ks od ekusuesdee ks Lee 10
SE US. SOD io isan oe snccckcueshe oe 23

Clean Air Act
42 U.S.C. $ TGOT(AMTMB) .. 0. ccc cc ccc cece ec cccens 14

Comprehensive Environmental Response, Compensation and
Liability Act,

42 U.S.C. $ 9601-9657 . 0... ccc cece ccc reece cece 2
42 U.S.C. $ GGOBMa) . 0. ccc cc ccc care ccecccccccccess 3
AZ U.S.C. $ SGC) 2... cece ccc ccc ccc cece ce ceceees 4
42 U.S.C. $ GGIBla). 0. oc cece rece cc ces esceneess 8, 11,17
EPA Regulations

AO CPR Prawt BBB. ooo occ cccesedieieivssonsnsssanas 5
40 CFR Part 260. .... 2. ccccncccccccccccccseccsccs 5
40 CFR, Part 264. .......ccccc cece cc cc cc ecccecess D
40 CFR Part 265... 2.2... ccc cece cece cece ees 5
40 CFR Part 300, Appendix A, Section 2.0........-. 6
40 CFR Part 300, Appendix A, Section 3.5........-- 6
40 CFR § 124.19... 0... ccc cece cee eee cee ee eeee 9, 10
48 Fed. Reg. 40658 (September 8, 1983) .......-----9% 23
48 Fed. Reg. 40674-40682 . 2... 6.6 ee cee eee eee eee i |
49 Fed. Reg. 37070-37090, 40 CFR Part 300 (September

Bi. BDBA). wc ccc cccccccncsecccsnwsevacteseseses 2,7
49 Fed. Reg. 37074... 0.6... cee eee eee eens 5
49 Fed. Reg. 37080-37081 ..........0. eee eee eens 4

vi

No.

In THE

Supreme Court of the United States

October Term, 1988

NorRTHSIDE SANITARY LANDFILL, INC.,
Petitioner,
V.
Ler M. THomas, AS ADMINISTRATOR OF, AND THE

UNITED StaTES ENVIRONMENTAL PROTECTION AGENCY,
Respondents,

PETITION FOR A WRIT OF CERTIORARI TO THE
UNITED STATES COURT OF APPEALS FOR THE
DISTRICT OF COLUMBiA CIRCUIT

Northside Sanitary Landfill, Inc.,! by counsel, hereby peti-
tions for a writ of certiorari to review the judgment of the
United States Court of Appeals for the District of Columbia
Circuit in Northside Sanitary Landfill v. Thomas and EPA.

OPINIONS BELOW

The opinion of the Court of Appeals for the District of Colum-
bia in Northside Sanitary Landfill v. Thomas and EPA (Slip
Opinion .:t App. A., infra, A-1 through A-11 is reported at 849
F.2d 1516 (1988).

The related opinion of the Court of Appeals for the Seventh
Circuit in Northside Sanitary Landfill v. Thomas regarding

'NSL, Ine. is not a subsidiary of any other corporation, is an Indiana
corporation and has its business located five miles from Zionsviile, Indiana.

]

2

the applicability of the Resource Conservation and Recovery
Act to Northside is reported at 804 F.2d 371 (1986). (App. G,
infra, A-19 through A-46 is the Slip Opinion.)

The related Entry and Memorandum opinion issued on April
12, 1988, by the U.S. District Court for the Southern District of
Indiana in United States v. Northside Sanitary Landfill in
Cause No. IP 88-172C, (App. H, infra, A-47 through A-60)
establishes the unabandoned status of the Northside facility.

The determination finally placing Northside on the National
Priorities List is an amendment by the Environmental Protec-
tion Agency to the National Oil and Hazardous Substance
Contingency Plan (App. I, infra A-61), and it and the relevant
EPA Preamble provisions (App. L, infra, A-65 through A-72)
were originally reported at 49 Fed. Reg. 37070 through 37090

‘ Qo 2 ap QR
on September 21, 1984. oe

The related Order of the Court of Appeaté-for- the Disti ict of
Columbia in Northside Sanitary Landfill v. Rueckelsaus, -
Cause No. 83-2258, dismissed without prejudice Northside'’s
initial appeal from the EPA's proposed rule to list NSL which
was published on September 8, 1983, at 48 Fed. Reg.
40674-40682.(App. F, infra A-17)

JURISDICTIONAL SUMMARY

This Petition for Writ of Certiorari filed pursuant to jurisdic-
tion granted by 28 U.S.C. § 1254 is an appeal from a Judgment
entered on March 25, 1988, by the Circuit Court of Appeals for
the District of Columbia (App. B, infra) which dismissed an
appeal from a rulemaking decision by the Administrator of the
United States Environmental Protection Agency (“EPA”)
placing Northside Sanitary Landfill, Inc. (“NSL”) on the
National Priorities List (“NPL”) under the Comprehensive
Environmental Response, Compensation and Liability Act of
1980 (“CERCLA”), 42 U.S.C. §§ 9601-9657. The Admin-
istrator’s Final Rule was promulgated on September 21, 1984,
as 40 CFR Part 300 which amended Appendix B and the
National Oil and Hazardous Substances Contingency Plan

3

under Section 105 of CERCLA. (App. D,infra) It was pub-
lished at 49 Fed. Reg. 37070 et seg. NSL filed an Appeal and
Petition for:Review with the Circuit Court of Appeals for the
District of Columbia on November 30, 1984, pursuant to
exclusive jurisdiction granted by 42 U.S.C. § 9613(a). Having
granted NSL until forty-five days from issuance of its opinion
to file its petition for rehearing, the Circuit Court entered
Orders on August 31, 1988, denying Appellant’s Petition for
Rehearing and Suggestion for Rehearing En Banc. (App. G
and H, infra)

STATUTORY AND REGULATORY PROVISIONS
INVOLVED

Sections 553(b), (c) and (e) of the Administrative Procedure
Act, 5 U.S.C. § 553, regarding notice-and-comment rulemak-
ing provide:

(b) General notice of proposed rule making shall be pub-
lished in the Federal Register, unless persons subject
thereto are named and either personally served or otherwise
have actual notice thereof in accordance with law. . .

(c) After notice required by this section, the agency shall
give interested persons an opportunity to participate in the
rule making through submission of written data, views, or
arguments with or without opportunity for oral presenta-
tion. After consideration of the relevant matter presented,
the agency shail incorporate in the rules adopted a concise
general statement of their basis and purpose. When rules
are required by statute to be made on the record after
opportunity for an agency hearing, sections 556 and 557 of
this title [5 USCS 8§ 556 and 597] apply instead of this
subsection.

(e) Each agency shall give an interested person the right to
petition for the issuance, amendment, or repeal of a rule.

(Sept. 6, 1966, P. L. 89-554 § 1, 80 Stat. 3&3.)

Section 105 of CERCLA, 42 U.S.C. § 9605(a), provided in its
relevant part regarding Revisions and Republications:

4

Within one hundred and eighty days after December 11,
1980, the President shall, after notice and opportunity for
public comments, revise and republish the national con-
tingency plan for the removal of oil and hazardous sub-
stances, originally prepared and published pursuant to
section 1321 of Title 33, to reflect and effectuate the respon-
sibilities and powers created by this chapter.

Section 105 of the Comprehensive Environmental Response,
Compensation and Liability Act of 1980 (“CERCLA”), 42
U.S.C. § 9605(¢), provides in its relevant part regarding revi-
sions to the Hazard Ranking System:

(1) REVISION—Not later than 18 months after the enact-
ment of the Superfund Amendments and Reauthorization
Act of 1986 and after publication of notice and opportunity
for submission of comments in accordance with section 553 of
title 5, United States Code, the President shall by rule
promulgate amendments to the hazard ranking system in
effect on September 1, 1984.

EPA’s Preamble to its Final Rule promulgating Update I to
the National Priorities List published at 49 Fed. Reg. 57070, at
37080 and 37081 (1984), provided in its relevant part regarding
EPA’ adopted procedure against administrative reconsidera-
tion:

EPA believes that the current approach of scoring by EPA or

the States, EPA quality assurance review, public comment

on the scoring, and EPA review of the comments provides
adequate safeguards against incorrect site scores.(App.

L,infra, A-71)

In addition to the foregoing reasons, other considerations
justify the current position not to rescore sites after final
listing. These considerations apply not only to cleanup situa-
tions but also to situations where a score might be affected
by new information about a site or by detection of an error in
the original calculations. The process established by EPA for
developing the NPL is comprehensive, involving initial scor-
ing, public proposal, consideration of public comment, re-

5

examination of data and scores, final score calculation, and
inclusion on the final NPL. Given this level of scrutiny, and
the time and expense involved in scoring sites, EPA finds it
necessary to rely upon the interested public to identify
factors pertinent to HRS score in a timely manner. EPA
believes that it is appropriate to consider inclusion of a site on
the final NPL to end the scoring process. (App. L, infra,
A-72)

The EPA Preamble to the Update I amending 40 CFR Part
300, Appendix B (Hazardous Priorities List) to include NSL
contains the following agency interpretation precluding the
listing of RCRA Sites, at 49 Fed. Reg. 37074 (September 21,
1984):

As stated in EPA’ previous NPL rulemaking (48 FR 40658,
September 8, 1983), both CERCLA and the Resource Con-
servation and Recovery Act (RCRA) contain authorities
applicable to hazardous waste facilities. These authorities
overlap for certain sites. Accordingly, where a site consists
only of regulated units of a RCRA facility operating pur-
suant to a permit or interim status, it will not be included on
the NPL but will instead be addressed under the authorities
of RCRA except as provided in the paragraph that follows.
The Land Disposal Regulations under RCRA (40 CFR Parts
122, 260, 264, and 265) gives EPA and the States authority to
control active sites through a broad program which includes
monitoring, compliance inspections, penalties for violations,
and requirements for postclosure plans and financial respon-
sibility. RCRA regulations require a contingency plan for
each facility. The regulations also contain ground water pro-
tection standards.

Given this alternative authority to ensure cleanup, regulated
units of RCRA facilities generally are not included on the
NPL. If the facility is abandoned or lacks sufficient
resources and the RCRA corrective action requirements
cannot be enforced, EPA will consider listing the site on the
NPL for possible response under CERCLA. This policy is
applicable not only to sites subject to EPA-administered
hazardous waste programs but also to sites in States that
administer programs approved by EPA.

6

Section 2.0 to Appendix A to 40 CFR Part 300 entitled
“Uncontrolled Hazardeus Waste Site Ranking System: A
User's Manual” provides in its relevant part regarding man-
datory data:

Use of the HRS requires considerable information about the
facility, its surroundings, the hazardous substances present,
and the geological character of the area down to the aquifers
that may be at risk... .

Where there are no data for a factor, it should be assigned a
value of zero... .

Using the guidance provided, attempt to assign a score for
each of the three possible migration routes. Bear in mind
that if data are missing for more than one factor in connec-
tion with the evaluation of a route, then you must set that
route score at 0 (.e., there is no need to assign scores to
factors in a route that will be set at 0).

Section 3.5 of Appendix A to 40 CFR Part 300 of the Uncon-
trolled Hazardous Waste Site Ranking System provides in its
relevant part regarding assigning ground water values for
“Distance to Nearest Well/Population Served”:

Distance to nearest well is measured from the hazardous
substance (not the facility boundary) to the nearest well that

draws water from the aquifer of concern. If the actual dis-

tance to the nearest well is unknown, use the distance ies
between the hazardous substance and the nearest occupied
building not served by a public water supply (e.g., a farm-
house). If a discontinuity in the aquifer occurs between the
hazardous substance and all wells, give this factor a score of
0, except where it can be shown that the contaminant is
likely to migrate beyond the discontinuity.

Population served by ground water is an indicator of the
population at risk, which includes residents as well as others
who would regularly use the water such as workers in facto-
ries or offices and students. . . The well or wells of concern
must be within three miles of the hazardous substances,
including the area of known aquifer contamination, but the

7

“population served” need not be. Likewise, people within
the three miles who do not use water from the aquifer of
concern are not to be counted.

STATEMENT OF THE CASE

The EPA Administrator initially placed Northside (“NSL”)
upon the proposed Update I to the National Priorities List
(“NPL”) under CERCLA on September 8, 1983. 48 Fed. Reg.
40674. This Federal Register publication did not contain the
EPA’s scoring documents related to Northside. NSL submit-
ted to EPA on January 26, 1984, its 422 pages of Comments
consisting of scientific written data and views opposing its
proposed listing. (J.A. below aty%14) The Administrator on
September 21, 1984, issued by publication as a Final Rule an
Amendment to the National Dil and Hazardous Substances
Contingency Plan, National Priorities List, which finally
placed NSL on-the NPL. 49 Fed. Reg. 37070-37090. (App. I.
infra, A-61) Also during September, 1984, EPA issued without
publication its Support Document wherein it discussed NSL
Comments, but left unchanged the prior score for this facility
under the Hazard Ranking System (“HRS”). (J. A. below at
455) The Final Rule omitted publishing this Support Docu-
ment, and nothing in the administrative record shows it to have
been provided by EPA to Northside. (App. L, infra, A-67)

NSL had originally sought judicial review of the September
8, 1983, proposed rule by filing a petition with the Court of
Appeals on December 7, 1983. This appeal was dismissed by
the Circuit’s Order of March 28, 1984, upon the Joint Motion to
Deconsolidate and to Dismiss. (App. F, infra, A-17) In this
motion the Government agreed that the dismissal “shall be
without prejudice to Northside Sanitary Landfill, Inc. to file a
new petition for review, if and when EPA finally amends the
National Priorities List under Section 105 of [CERCLA] so as
to finally add petitioner's facility to that list.” (Record in No.
83-2247, D.C. Cir.)

On November 30, 1984, NSL did file with the Court of
Appeals a Petition for Review of the September 21, 1984, Final

8

Rule, pursuant to jurisdiction exclusively granted to the Dis-
trict of Columbia Circuit by 42 U.S.C. § 9613(a). Because of the
pendency of the Circuit's first review of EPA’s Hazard Ranking
System in Eagle-Picher Industries, Inc. v. EPA, 159 F.2d 905
(D.C. Cir. 1985) and 822 F.2d 132 (D.C. Cir. 1987), the Circuit
Court deferred briefing and consideration of the NSL Petition
for Review.

Northside Sanitary Landfill, Inc. (“Northside” or “NSL")
presently operates a landfill near Zionsville, Indiana, and had
provided sanitary and hazardous waste disposal services for
Indianapolis and Boone County, Indiana. It presently con-
tinues to provide sanitary disposal for nonhazardous refuse.
(App. H, ‘fra, A-48) Northside was in existence for many
vears prior to the passage of the Resource Conservation &
Recovery Act (RCRA), 42 U.S.C. 8§ 6901-6991. On November
1X, 1980, Northside submitted a Part A application to EPA fora
hazardous waste treatment and disposal permit. As part of its
application materials, Northside included a hand-drawn scale
map of its facility. This map delineated five areas within North-
side’s property boundary comprising approximately 134 acres.

On June 9. 1982. the EPA Region V Administrator at Chi-
cago acknowledged that Northside’s application qualified it for
RCRA interim status. On January 26, 1983, the Region V
Administrator requested that Northside submit a Part B
application by July 29, 1983. NSL filed a Part B application, but
on April 30, 1984, NSL informed Region V that it was “offi-
cial{ly|” withdrawing its Part B application. Nevertheless, on
July 25, 1984, the Region V Administrator issued a notice of his
tentative decision to deny Northside’s permit application on
the grounds that the application was deficient, did not ade-
quately provide for the protection of groundwater, and that
other “continuing environmental violations” had occurred.

At the subsequent informal public hearing, EPA stated that
Northside’s Part B application did not include closure informa-
tion regarding the areas of its facility for which interim status
had been granted. In response, Northside stated that the

9

Region V Administrator had incorrectly considered its Old
Farm Area (forty acres) as part of Northside’s permit applica-
tion. Northside maintained that it had sought a permit for a 303
acre-feet disposal capacity, that this was to be located only in
the East Farm Area (thirty acres), and that only twelve acres
had actually been used for the treatment and disposal of haz-
ardous wastes.

On October 12, 1984, the Regien V Administrator denied
Northside’s Part B application and terminated its interim sta-
tus on the ground that a final administrative disposition had
been made of Northside’s permit application. The Region V
Administrator stated that hazardous waste had been disposed
of after November 19, 1980, in the Old Farm Area as well as the
East Farm, and thus concluded that “{t|he entire hazardous
waste landfill area outlined in the November 18, 1980, Part A
application must be closed. This includes the ‘Old Farm Area.”
The order required Northside to commence immediate closure
proceedings under the applicable Indiana regulations.

On November &, 1984, pursuant to 40 CFR 124.19, Northside
petitioned the Administrator for review of the Region V order.
Northside claimed both before the Administrator and before
the Seventh Circuit that on January 4, 1985, the Region V
Administrator submitted drawings to the EPA Administrator
which inaccurately depicted the areas that Northside had
requested EPA consider for a hazardous waste management
permit.

On April 5, 1985, the Administrator issued an order denying
Northside’s petition for review of the Region V Administrator's
denial of Northside’s hazardous waste application. The Admin-
istrator did, however, state that the questions Northside raised
regarding the areas within the (1) facility that were encom-
passed by its Part A and Part B permit applications and (2) that
could properly be closed, addressed two of:

the most rudimentary pieces of information that go into a

proper permit decision. If the permit decision does not iden-

tify where the facility is located, or how big it is, the permit

10

decision cannot be implemented successfully regardless of
the outcome of the decision. This is particularly apparent in
the present case, for either including or excluding the Old
Farm Area will significantly alter the area of Petitioner's
landfill that is subject to the closure and postclosure require-
ments of the regulations.

The Administrator concluded that although the sort of issue
Northside raised was within the ambit of 40 CFR § 124.19,
Northside “has not sustained its burden of showing that the
permit determination is either clearly erroneous or involves an
exercise of discretion or policy which warrants (liscretionary
review.”

On April 19, 1985, Northside filed a Motion to Reconsider
with the Administrator, arguing that the issue as to whether
the Old Farm Area is a part of the Part A interim site and
subject to RCRA closure was presently being litigated before
the Indiana Environmental Management Board. On July 2,
1985 (within the ninety day review period from the Order of
April 2, 1985) Northside filed a petition for review with the
Seventh Circuit. On November 27, 1985, a few days before
EPA’s brief was to be filed with the Seventh Circuit, the
Administrator denied Northside’s motion for reconsideration.
However, the Seventh Circuit found that the “Administrator
adopted a completely different rationale ‘by holding that’ Indi-
ana had been granted authority pursuant to 42 U.S.C. § 6926 to
conduct closure proceedings for interim status permits.”
Northside Sanitary Landfill, Inc. v. Thomas, 804 F.2d 37],
375-377 (7th Cir. 1986). (App. G, infra, A-29)

The Seventh Circuit found “it is clear that the parties were
not given a full and fair opportunity to litigate the issue,”
noting EPA “allotted only five minutes to comment.” (App. G,
infra, A-38) However, the Circuit held that it was withholding
judgment on this issue raised in NSL's appeal because it
appeared that the state procedure would provide NSL the due
process hearing which EPA had denied it on issues of RCRA
closure. (App. G, infra, A-45) The Seventh Circuit also held
that Final EPA action on NSL’s RCRA application did not
occur until the issuance of the Administrator's Order on Recon-

ll

sideration. (App. G, infra, A-30) Thus, NSL held interim sta-
tus until November 27, 1985.

Although the State of Indiana was proceeding with RCRA
enforcement, EPA continued with its activities under
CERCLA and issued a Record Of Decision in September, 1987.
This “ROD” included the future covering of the entire NSL
facility with a multilayer cap described by EPA as a “RCRA
Cap.” United States v. Northside Sanitary Landfill, Inc.,
Cause No. IP88-172C (S.D. Ind. 1988). (App. H, infra, A-48) In
March 1988, the United States obtained an immediate evidenti-
ary hearing on its motion to enjoin Northside from conducting
any further landfilling operations on its property. The U.S.
District Court in its Memorandum Opinion held that “while the
danger posed by the possible release of CERCLA substances
from Northside may be minimal, the EPA has shown that
there is a reasonable basis to believe there may be a release of
such substances from the site at some future date.” ( App. H,
infra, A-54) The District Court denied the Government's
motion and summarized that “nothing in the record illustrates
that the EPA’s current pian for closure will be delayed in any
way by defendants continued operation of a sanitary landfill.”
United States v. Northside, (S.D. Ind. 1988) (App. H, infra,
A-59)

REASONS FOR ALLOWING THE WRIT

Congress by legislating the Comprehensive Environmental
Response, Compensation and Liability Act of 1980
(“CERCLA”) mandated EPA to revise the National Con-
tingency Plan (“NCP”) to include a system to prioritize
releases or threatened releases nationally for remedial action
and to list the priority sites and update the list annually.
Congress granted the Circuit Court of Appeals for the District
of Columbia exclusive jurisdiction nationwide to review any
regulation promulgated for those purposes. 42 U.S.C. 9613(a).
Northside Sanitary Landfill v. Thomas (App. A, infra, A-1
through A-11) is one of a handful of opinions rendered by the
Court of Appeals since 1985 which involves the listing of a
facility on the National Priorities List (“NPL”) pursuant to
EPA's Hazard Ranking System (“HRS”), (App. M, iuvfra, A-73
through A-79) Because of the large number of waste disposal

12

sites which were and are being rated under the HRS for possi-
ble future inclusion on the NPL, the present case is extremely
important and has ramifications affecting many other potential
NPL sites.

The D. C. Cireuit’s Northside Opinion written by U.S. Dis-
trict Court Judge Kaufman (who was sitting by designation)
should be reviewed because it is directly contrary to the pre-
viously leading opinion in City of Seabrook, Texas v. U.S. EPA,
659 F.2d 1349 (1981). Therein the Fifth Circuit (1) refused to
“accept the EPA's argument that Petitioners should be barred
from raising any objection not raised during the ‘notice and
comment period,’ ” and (2) refused to accept the “rule urged by
EPA [which] would require everyone who wishes to protect
himself from arbitrary agency action not only to become a
faithful reader of the notices of proposed rulemaking published
each day in the Federal Register, but a psychic able to predict
the possible changes that could be made in the proposal when
the rule is finally promulgated.”

Secondly, the District of Columbia Circuit's opinion has
decided an important question of federal law misapplying this
Court’s decision in Vermont Yankee Nuclear Power Corp. ¢.
Natural Resources Defense Council, Ine., 435 U.S. 519 (1978),
as well as the Circuit’s own decisions in Portland Cement Ass'n
v. Ruckelshaus, 486 F.2d 375, 394 (1973) and Home Bow Office,
Inc. v. FCC, 567 F.2d 9, 35 (1977), cert. denied, 334 U.S. 829
(1977). These decisions only require detailed objections to
agency rulemaking decisions during the administrative pro-
cess where either the statutes precluded judicial review of
objections not specified or allowed an adjudicatory hearing, not
where the statute, as here, provided for only informal notice
and comment rulemaking.

Thirdly, the Circuit Court by its dismissal has in effect
decided incorrectly an important question of federal law as the
Circuit with exclusive federal jurisdiction, which question has
not been, but should be, settled by this Court. The Circuit's
dismissal has allowed EPA to place upon the National Pri-
orities List under CERCLA a “RCRA-Related Site” which is

15

not abandoned and which held RCRA interim status when
EPA issued the final rule for its listing. This action is contrary
to EPA’s own interpretation of the relationship between the
CERCLA and RCRA statutes as set forth in the Preamble to
the Final Rule listing Northside, and is contrary to the D.C.
Circuit’s original opinion that the NPL is for “inactive haz-
ardous waste sites.” Eagle-Picher v. EPA, 759 F.2d at 905, 922
(1985).

Fourthly, the Circuit Court by denying the appeal without
consideration on the merits has refused to require EPA to
follow its own HRS which this Circuit upheld in 1985 in Eagle-
Picher Industries v. EPA, 759 F.2d 905 at 919-922. The Circuit
has allowed the EPA to ignore its regulation requiring the
assigning of a scoring value of 0 where support data is lacking
and not documented, its regulation requiring a score of 0 where
a discontinuity in the aquifer occurs between the hazardous
substance and all wells, and its regulation precluding from
consideration people within three miles of the aquifer who do
not use water from the aquifer of concern. Because all of the
evidence in the administrative record, including EPA's ground-
water study, revealed the aquifer discontinuity, the Circuit
Court's opinion has incorrectly determined an important ques-
tion of federal law as the Circuit of exclusive national jurisdic-
tion, which has not been, but should be settled by this Court. It
has also failed to correctly apply the leading decision of this
Court in Vermont Yankee Nuclear Power Corp. v. National
Resources Defense Council, 435 U.S. 519 at 549 ( 1978), requir-
ing that a finding not sustainable on the administrative record
must be vacated and remanded.

1. Congress Has Not Imposed Upon Those Selectively
Chosen For Agency Action The Duty To Read Daily
Notices Of Proposed Rulemaking Published In The
Federal Register, And Certainly Has Not Imposed The
Duty To Become Aware Of Agency Responses Never
Transmitted Nor Even Published By The Agency.

In the leading case City of Seabrook, Texas, supra, at 1360,
the Fifth Circuit addressed the precise issue determined by
the D.C. Circuit panel, but instead concluded:

14

[Wle cannot accept the EPA's argument that petitioners
should be barred from raising any objection not raised dur-
ing the “notice and comment” period. The EPA made the
same argument in a case it has failed to cite to us, and the
argument was rejected by Judge Hill, then a district judge.
Dobbs v. Train, 409 F.Supp. 432, 434-35 (N.D. GA 1975), aff'd
sub nom. Dobbs v. Costle, 559 F.2d 946 (5th Cir. 1977). While
Dobbs was an action to review an agency denial of benefits
pursuant to the challenged rule, and this action is one for
direct review, we agree with Judge Hill that the courts
should not generally hold a petitioner estopped from object-
ing to an agency rule because his specific objection was not
made during the “notice and comment” period.' The rule
urged by EPA would require everyone who wishes to protect
himself from arbitrary agency action not only to become a
faithful reader of the notices of proposed rulemaking pub-
lished each day in the Federal Register, but a psychic able to
predict the possible changes that could be made in the pro-
posal when the rule is finally promulgated. This is a fate this
court will impose on no one.

In its supporting footnote 19, the Fifth Circuit concluded:

We note that Congress has attempted to impose such a fate,
albeit with some escape clauses, in § 307(d)(7)(B) of the
Clean Air Act, 42 U.S.C. § 7607(d)(7)(B). The EPA con-
cedes, however, that § 307(d) does not apply to the approval
or disapproval of implementation plans.

Completely contrary to this decision in City of Seabrook,
Texas, the D.C. Cireuit concluded that NSL had been given
sufficient notice because its name and the date upon which the
comment period closed were published in the Federal Register.
(App. A, infra, A-5) The D.C. Circuit went even further by
concluding NSL had failed to exercise its statutory right under
5 U.S.C. § 553(e) to request EPA to reconsider and amend its
final rule after NSL received EPA’s response to NSL's Com-
ments, but had instead incorrectly instituted judicial review to
attack its inclusion on the NPL. (App. A, infra, A-6) The
importance of this second conclusion is set forth at page 10 of
the Circuit's Slip Opinion where it found that NSL should have

Fos ge peor cern TR

15

been more specific as to why and how it thought its 422 page
submittal of “written data” and scientific “views” were relevant
to the scoring, stating (App. A, infra, A-10):

We are not suggesting that Northside should have com-
mented in great detail on every study, but we de conclude
that Northside could and should have done far more than it
did do to alert the EPA to its positions, which would have
then required and allowed the EPA fully to consider North-
side's version of the facts, and to act upon them appropri-
ately.'!\(emphasis added)

In its supporting footnote 11, the Circuit elaborated as follows:

'! At the very least, Northside itself could have pointed out
those facts which it believed that the EPA had overlooked in
the EPA’s response to Northside’s comments. Specifically,
when Northside received the EPA's response to its com-
ments, it was on notice that the EPA had not interpreted
those comments as Northside evidently expected the agency
would. At that point, pursuant to 5 U.S.C. 553(e), see note &,
supra, Northside was free to petition the EPA to reconsider
its position concerning those comments in the light of the
specific objections which Northside now raises before this
court. See Wisconsin Electric, 715 F.2d at 327-28. However,
Northside did not take advantage of that opportunity.
(emphasis added)

Firstly, the applicable APA § 553(e) requires the commentor
to submit only “written data, views, or arguments,” and not to
submit specific positions.

Secondly, EPA never provided NSL with its response to
NSL'’s Comments, and it never even notified NSL that it had
developed such a response which it designated as the Support
Document for the Final Revised NPL.

Thirdly, EPA made it impossible for NSL to exercise its
right to reconsideration under § 553(e) by not providing for any
reconsideration procedure in its Final Rule and by stating such
a petition would be an effort in futility, even though this section
of the APA statute provided:

16

Each agency shall give an interested person the right to
petition for the issuance, amendment, or repeal of a rule.
(emphasis added)

Although the Circuit Court also concluded that “{i]t is cer-
tainly incumbent upon the EPA under 5 U.S.C. § 553(¢) to
‘respond in a reasoned manner to significant comments
received,” citing United States Satellite Broadcasting Com-
pany, Inc. v. FCC, 740 F.2d 1177, 1188 (D.C. Cir. 1984); it went
on to say that “the ‘dialogue’ between administrative agencies
and the public ‘is a two-way street,” citing Home Bow Office,
567 F.2d at 35 (D.C. Cir.), cert. denied, 434 U.S. &29 (1977).
Dialogue cannot be a two-way street (1) where EPA merely
publishes in the Federal Register a proposed rule naming NSL
on the NPL and requiring comments within 60 days; (2) where
NSL submits its comments consisting of both scientific written
data and views allowing the EPA eight months to review and
respond; but (3) where EPA fails to transmit to NSL or even to
publish its written response, which was not issued until it
promulgated its final NPL Update rule. EPA instead chose to
publish only five lines of reference to this mandatory Support
Document which it buried in its thirteen pages of Preamble to
the Final Rule of eight pages which it merely published in the
massive Federal Register. The Circuit concluded NSL broke
down the two-way street dialogue by not asking for recon-
sideration from a response never received and by not pointing
out to EPA that it had misinterpreted NSL’s Comments, when
in fact EPA never provided NSL with its response even after
issuing its Final Rule.

EPA’s actions from the beginning both eliminated the two-
way dialogue contemplated by the rulemaking process of
§ 553(b) and (c) of the APA, and eliminated NSL's right under
§ 553(e) to petition for reconsideration of the Final Rule. EPA
established a procedure where comments from an affected
party are required to be filed with EPA, but no EPA response
to those comments are returned to the affected party and
where no reconsideration will be considered. EPA’s Preamble
to this Final Rule provided:

17

The process established by EPA for developing the NPL is
comprehensive, involving initial scoring, public proposal,
consideration of public comment, reexamination of data and
scores, final score calculation, and inclusion on the final
NPL. Given this level of scrutiny, and the time and expense
involved in scoring sites, the EPA finds it necessary to rely
upon the interested public to identify factors pertinent to
HRS score in a timely manner. EPA believes that it is
appropriate to consider inclusion of a site on the final NPL to
end the scoring process. (App. L, infra, A-72)

The Circuit's opinion places an impossible burden upon a party
not only affected by, but individually named in an agency
decision. It fails to recognize that EPA would not change its
Final Rule once published. This Final Rule reflects that EPA
had established no process for reconsideration.

Thus, EPA’s Final Rule specifically omitted the right to
reconsideration mandated by § 553(e) of the APA. At this point
NSL‘ only remedy was to raise its objections to the D.C.
Circuit Court in a petition for review which 42 U.S.C. § 9613(a)
required to be filed within 90 days of the issuance of the Final
Rule.

Even where a statute requires the filing of objections and
precludes issues not so specifically raised with the agency,
which is not the procedure established under CERCLA and
the NCP, the D.C. Circuit itself previously has concluded: “The
critical inquiry is whether the objections made before the
Board were adequate to put the Board on notice that the issue
might be pursued on appeal,” and that “the standard requires a
close factual inquiry.” Consolidated Freightways v. NLRB, 669
F.2d 790, 794 (D.C. Cir. 1981). More recently, Judge Wald
writing for the D.C. Circuit in American Maritime Associa-
tion v. United States, 766 F.2d 545, 566, n.30 (D.C. Cir, 1985)
stated:

At least in the absence of an explicit statutory directive, the

general rule is ultimately a matter of judicial discretion and

will not be applied to perpetuate unfairness to the parties.

Under these facts, it was not only unfair, but also inconsistent
with § 553(¢) and (e) for the Court of Appeals to deny NSL's

18

appeal on the basis that NSL should have more specifically
pointed out and argued its objections and positions to EPA
upon the non-receipt of EPA’s response to NSL's Comments
which contained both scientific “written data” and “views”
thereon. The CERCLA statute did not specifically require the
exclusion of objections not detailed and summarized for EPA as
did the Clean Air Act, and EPA never bothered to transmit its
“dialogue” response to NSL.

2. Judicial Review Is Not Precluded As To Issues Not
Raised As Specific Arguments Or Summarized To The
Agency Unless The Statute Contains Such A Preclu-
sion Or Unless The Process Entails An Adjudicatory
Hearing.

The Supreme Court does not preclude judicial review of
issues not raised as specific objections or as detailed arguments
during an administrative rulemaking process which allows only
comments from interested parties, unless the statute requires
the exclusion of such issues or provides the party with an
adjudicatory hearing process. Portland Cement Ass'n, supra
(1973), relied upon by the Circuit Court, involved the Clean Air
Act which precluded the raising of issues not specifically raised
as objections to the EPA. The Fifth Circuit in City of Seabrook,
Tewas, supra at 1360, n.17 and 19, found in 1981 that “the EPA
has cited no authority for the proposition that an argument not
raised during the comment period may not be raised on
review,” because Seabrook did not involve the Clean Air Act as
did Portland Cement.

The Fifth Circuit found in 1981 that its own research had
uncovered only one case “lending some support to the proposi-
tion that a party may be estopped from raising an argument on
direct review if he failed to raise it during the rulemaking
proceeding.” But it noted that Gage v. AEC, 479 F.2d 1214,
1217-19 (D.C. Cir. 1973) “involved a statute which entitled inter-
ested persons to become ‘parties’ and get a ‘hearing’ on their
objections, and which granted the right of direct review only to
such ‘parties.’

The D.C. Circuit relied upon, but misapplied, this Court's
1978 decision in Vermont Yankee, supra. The Supreme Court in

19

Vermont Yankee precluded the raising of an alternative to
nuclear power plant fuel disposal where the intervenor had
failed to submit either specific contentions or evidence to evalu-
ate the alternative. To the contrary, NSL submitted 422 pages
of scientific “written data and views” on groundwater aquifers
and quality. In Vermont Yankee, supra, at 554, this Court
noted that the NRC “continually invited further clarification of
Saginaw’s contentions,” and “even without such clarification it
indicated a willingness to receive evidence on the matters.” To
the contrary, during the eight months between the filing of
NSL'‘ 422 pages of scientific data and views and the issuing of
EPA's Final Rule, EPA requested nothing.

Most importantly, Vermont Yankee, supra, at 526-527,
involved a licensing process where parties could raise conten-
tions during adjudicatory hearings under the Atomic Energy
Act. Northside could only participate in the EPA described
“informal notice and public-comment rulemaking” procedures.
(EPA Brief below, D.C. Circuit at p. 14) The CERCLA and
NCP sections dealing with NPL listings do not allow
adjudicatory hearings, nor do they require the exclusion of
objections and arguments not raised with specificity during the
agency comment period. Thus, the Circuit Court panel should
have adopted the Fifth Circuit’s opinion in City of Seabrook,
Tevas, supra, and the similar review standard established by
the D.C. Cireuit en banc in Ethyl Corporation v. U.S. EPA,
541 F.2d 1, 34, cert. denied, 426 U.S. 941 (1976); in Maryland
People’s Council v. FERC, 761 F.2d 780, 785 (1985); in Ameri-
can Maritime Association v. United States, 766 F.2d 545, 566
(1985) and in Eagle-Picher Industries, Inc. v. EPA, 759 F.2d
905, 921 (1985). This Circuit held en banc in Ethyl Corporation,
supra, at 34:

This is not to say, however, that we must rubber-stamp the

agency decision as correct. To do so would render the appel-

late process a superfluous (although time consuming) ritual.

In its third opinion issued in Eagle-Picher Industries v.
EPA, 822 F.2d 132 (1987), the Circuit denied review regarding
the “population using an aquifer” on the basis that the respon-

20

dent had never identified to EPA the data relied upon and
because the record supported EPA’s finding. To the contrary
NSL submitted 422 pages of written data and views, including
the EPA sponsored 1983 Hydrogeological Study Report.

Also, in Washington Association For Television and Chil-
dren v. FCC, 712 F.2d 677 (1983), the D.C. Circuit Court held:
“Moreover, it is not always necessary for a party to raise an
issue, so long as the Commission, in fact considered the issues.”
Although the D.C. Circuit strongly criticized Northside for not
filing its Comments with the EPA until January 31, 1984,
“despite the November 7, i983 deadline,” (App. A, infra, A-5)
EPA’s Preamble to this Final Rule states that “EPA considered
all comments received by March 30, 1984.” (App. L, infra,
A-66) Where EPA admits it considered the written comments
filed by a party and where the statute neither requires specific
objections nor allows an adjudicatory hearing, the Circuit
Court cannot dismiss an appeal which is required by statute to
be filed within ninety days of the issuance of the final rule, on
the basis that the agency was not fully apprised of the specific
issues being controverted and the arguments by the comment-
ing party.

EPA’s Final Rule of September 21, 1984, did not even include
an effective date, but stated it would publish a Federal Register
notice at the end of a congressional review period and announce
the effective date for this NPL Update. No such subsequently
published effective date has been discovered, and EPA Head-
quarters is unable to determine this date. Therefore, the D.C.
Cireuit Court of Appeals should have at least granted the
review, reversed the placement of NSL on an NPL Update
having no effective date, and remanded this matter to the EPA,
including the requiring of a process where an affected and
named party can petition for reconsideration under § 553(e) of
the APA.

Indeed, the Circuit’s previous Order preserved NSL’s right
to judicial review of its Final Rule listing. NSL originally
appealed its proposed listing upon the NPL on December 7,
1983. The D.C. Circuit dismissed that appeal by Order issued

21

March 28, 1984, upon the Joint Motion to Deconsolidate and to
Dismiss. (App. F, infra A-17) The Justice Department and
EPA agreed that:

The dismissal of the petition for review at No. 83-2258 shall
be without prejudice to Northside Sanitary Landfill, Inc. to
file a new petition for review, if and when EPA finally
amends the National Priorities List under §105 of
[CERCLA] so as to finally add petitioner's facility to that
List.

Nevertheless, EPA subsequently argued successfully to the
Court of Appeals panel that NSL is barred from raising any
issues whatsoever in its second petition for review timely filed
within 90 days after EPA finally added NSL to the NPL.

In summary, it would have been impossible for NSL to have
pointed out in a petition for reconsideration to EPA that it had
misinterpreted NSL’s written comments where EPA’s
response to those comments was not developed as a Support
Document for the Revised NPL until the final rule was promul-
gated. (J.A. below at 455 and 988 and Certified Index to the
Record, p. 37) If EPA did not comprehend how the scientific
written data and views submitted by NSL affected the scoring,
it should have so advised NSL during the eight months
between the filing of these comments and the promulgation of
the Final Rule, as did the Atomic Safety Board in Vermont
Yankee, supra, at 554. Instead EPA agreed to a dismissal of the
original Petition for Review and to the filing of a second petition
two months after NSL filed its data and views.

3. A Court Must Reverse An Administrative Decision
Where The Agency Has Failed To Comply With Its Own
Published Policy And Interpretation Of Congressional
Intent To Exclude A Particular Type Of Facility From
The National Priorities List.

D.. ing 1986 EPA argued to the Seventh Circuit Court of
Appeals that NSL was a RCRA-related site and should be
required to proceed through RCRA closure of its entire 134-
acre facility, but with the state of Indiana making the final

rey

determinations because of recent delegation of EPA’s author-
ity. (App. G, infra A-37; and EPA’s Brief to the Seventh Cir-
cuit, p. 64, n. 34) Nevertheless, EPA has proceeded much
farther than simply listing Northside on the NPL. In Sep-
tember 1987 it issued a Record of Decision (“ROD”) under
CERCLA which included requiring the construction of a multi-
layer cap to cover Northside and which EPA denominated as a
“RCRA cap.” United States v. Northside Sanitary Landfill,
Inc. (App. H, infra, A-48)

After the adoption of the EPA regulation on Land Disposal
Corrective Actions on July 26, 1982, and even after January 26,
1983, which EPA has argued as their effective date,” EPA
headquarters advised U.S. Senator Quayle that “active dis-
posal sites such as Northside Landfill are regulated through
RCRA” with enforcement by Indiana. (J.A. below at 345) Ina
contemporaneous letter to U.S. Senator Lugar, EPA’s Admin-
istrator stated: “It is EPA policy to use our compliance
authorities under RCRA to address such sites and conserve
superfund resources for those inactive and abandoned facilities
where no other resources can be brought to bear.”

This EPA advocated policy was evidently adopted by the
D.C. Circuit in its first opinion wherein it reviewed the Hazard
Ranking System. In Eagle-Picher v. EPA, 759 F.2d at 922, the
Court held: “CERCLA was designed to address the growing
problem of inactive hazardous waste sites throughout the
United States.” Indeed, even both the proposed rule and the
Final Rule to Update I to the NPL recognized that it was an
improper construction of the CERCLA and RCRA statutes to
place a RCRA-related facility on the NPL. (App. K, infra,
A-63 through A-64; and App. L, infra, A-69 through A-70)

2 Apparently for the purpose of making these RCRA requirements enforcea-
ble against hazardous waste facilities which had opted out of accepting
RCRA waste by January 26, 1983, as had Northside, Congress subsequently
made the Land Disposal Corrective Actions retroactive to a RCRA interim
status facility which “receives hazardous waste after July 26, 1982." 42
U.S.C. § 6925(i) as amended by the Hazardous and Solid Waste Amendments
of 1984 (Pub. L. 98-616, Nov. &, 1984).

23

EPA's Preamble to the Final Rule as set forth more completely
in the Statutory section and App. L, infra, provides in part:

As stated in EPA’s previous NPL rulemaking (48 FR 40658,
September 8, 1983), both CERCLA and the Resource Con-
servation and Recovery Act (RCRA) contain authorities
applicable to hazardous waste facilities. These authorities
overlap for certain sites. Accordingly, where a site consists
only of regulated units of a RCRA facility operating pur-
suant to a permit or interim status, it will not be included on
the NPL but will instead be addressed under the authorities
of RCRA except as provided in the paragraph that follows.

=? &

Given this alternative authority to ensure cleanup, regulated
units of RCRA facilities generally are not included on the
NPL. If the facility is abandoned or lacks sufficient
resources and the RCRA corrective action requirements
cannot be enforced, EPA will consider listing the site on the
NPL for possible response under CERCLA. This policy is
applicable not only to sites subject to EPA-administered
hazardous waste programs but also to sites in States that
administer programs approved by EPA. (emphasis added)

Quite simply, NSL held interim status until November 27,
1985, and RCRA Section 3008(h) provided for “interim status
corrective action orders.” 42 U.S.C. 6928 (h). The Seventh Cir-
cuit in Northside v. Thomas, 804 F.2d 371 at 378 (1986) (App. G,
infra, A-30) determined that NSL’s RCRA status was not
finally determined until November 27, 1985. Nowhere was
Northside classified as a “non-regulated unit” not subject to
such corrective actions when the NPL Update was finalized on
September 21, 1984. Indeed, in its Brief to the Seventh Circuit
in Northside v. Thomas, supra, EPA stated on January 27, 1986
that: “Since it is conceded that hazardous waste was disposed of
somewhere on the facility after November 19, 1980, as a legal
matter the entire facility became subject to RCRA coverage.”
(EPA’s Brief, Cause No. 85-2119, 7th Circuit, p. 64)

Thus, as a matter of Circuit law and of EPA policy interpret-
ing Congressional intent, the D.C. Circuit was required to

24

reverse the Administrator’s placement of Northside on the
NPL Update of September 21, 1984. Not only was NSL then
operating and holding RCRA interim status, but even as late as
April 12, 1988 the U.S. District Court for the Southern District
of Indiana denied the Government's attempt to create an aban-
doned facility by permanently enjoining all landfilling opera-
tions at Northside. (App. H, infra, A-59)

4. The Circuit Court’s Opinion Constitutes The
Granting Of A Degree Of Judicial Deference To An
Agency Equaling A Rubber-Stamp Of A Decision
Which Is Contrary To The Regulatory Requirements
Of The Hazard Ranking System And To The Record
Evidence.

In Ethyl Corporation v. U.S. EPA, supra, at 34, the D.C.
Circuit held en bance:

This is not to say, however, that we must rubber-stamp the
agency decision as correct. To do so would render the appel-
late process a superfluous (although time-consuming) ritual.

The Circuit's Opinion in Northside is contrary to its Ethyl
Corporation decision as well as its more recent decision in
Maryland People’s Council v. FERC, supra, at 785, wherein it
held that it should inspect the record to determine whether an
agency decision was based upon consideration of the relevant
factors and whether there has been a clear error of judgment.
In one of the few other cases interpreting the Hazard Ranking
System (“HRS”), the D.C. Circuit held that under the arbi-
trary and capricious standard it should “look to see if the
agency has examined relevant data and has articulated a
rational explanation of its action.” See Eagle-Picher Indus-
tries, Inc. v. EPA, 759 F.2d at 921. There must be a “rational
connection between the facts found and the choice made.” See
Salt River Project v. United States, 762 F.2d 1053, 1058 (D.C.
Cir. 1985). Nevertheless, the Circuit panel in Northside con-
cluded that if it had addressed the merits, there would exist
ample support in the record for this NPL listing. (App. A,
infra, A-11) It disregarded the obvious agency deficiencies.

25

Section 2.0 of the HRS requires for its application:

Use of the HRS requires considerable information about the
facility, its surroundings, the hazardous substances present,
and the geological character of the area down to the aquifers
that may be at risk... .

Where there are no data for a factor, it should be assigned a
value of zero. (App. M, infra A-76)

Discussing the importance of documented data to support val-
ues assigned during the HRS scoring, EPA’s Director of Emer-
gency and Remedial Response stated in his May 12, 1983
“Guidance for Update in the National Priorities List” that:

It is essential that the documentation records contain a clear
explanation of the sources of information. Please ensure that
each information item is supported by a document or other
identified source according to a specific title, date, person, or
event as appropriate. (See J.A. below at 360)

Because no data was cited in the Documentation Record for the
subfactor of Groundwater Use which was assigned the max-
imum value, the scoring for NSL violated this HRS require-
ment as approved by the D.C. Circuit in Eagle-Picher I, supra.
Secondly, due to the lack of this mandatory documentation, it
was also improper to assign the maximum score for “Distance
to Nearest Well” and a high score for “Population Served” by
groundwater wells within a 3-mile radius. The combination of
these two values alone resulted in 30 of the 39 points assigned
to NSL for Groundwater Targets.

Thirdly, the Target score was contrary to both the HRS rule
and the record data. HRS Section 3.5 provides that:

If a discontinuity in the aquifer occurs between the haz-
ardous substance and all wells, give this factor a score of 0.
except where it can be shown that the contaminant is likely
to migrate beyond the discontinuity.

ee & &

Likewise, people within three miles who do not use water
from the aquifer of concern are not to be counted. (App. M,
infra A-79)

26

The HRS requires a minimum score of 28.5 points to list a
site. The State scored NSL at 46 points, but this required a
mismatch of aquifers contrary to the HRS rules aiid to all
evidence. Without such a mismatch, the Targets factor would
have reduced the total Groundwater Route score to 6.12 and the
HRS site score to no more than 3.98. This mismatch involved
the “aquifer of concern” which EPA determined was located
between the depth of 40 feet and 200 feet below the surface
(J.A. below at 110) and a surficial water table aquifer which
EPA's own experts concluded was between only a depth of 5 to
15 feet below the ground surface. (J.A. below at 529) Although
the State EPA scored groundwater for an “observed release,”
the only documentary support for such a release was water
analyzed from a monitoring well within the shallow surficial
water table aquifer. (J.A. below at 394 and 151-202)

To support this inaccurate score and the aquifer mismatch,
EPA argued to the Circuit that only two aquifers exist at the
NSL site, with the first being from the ground surface to
approximately 40 feet, and the second being at a depth of 40
feet and below. Nothing in the record supports such a scientific
theory. EPA argued to the Circuit panel in its Brief below at pp.
46 and 48.

However, short of conducting a full hydrogeologic investiga-
tion — something never contemplated for the PA/SI stage of
the CERCLA review and cleanup process — it is impossible
to have 100 percent certainty as to the exact geologic condi-
tions beneath the Northside site.

3y contrast, there was no accepted assumption about a
second confining layer, and there was sufficient evidence in
the record to provide a reasonable basis for a judgment that
there was not a second confining layer between the surface
and 40 feet.

The Government did represent to the Circuit Court that “[i|fit
had been EPA’s judgment that a second confining layer did in
fact exist within the shallow aquifer zone, EPA would have

27

discounted wells beneath it for the purpose of population
counts.” (EPA’s Brief below at p. 48)

The record contains a site hydrogeological study by a Purdue
University geosciences engineer, a study by the State environ-
mental agency's Chief of Geology/Chemistry, a geological/
groundwater evaluation by a national environmental engineer-
ing firm, and even a Hydrogeological Study Report dated
August 22, 1983, and prepared by EPA’s own consultants. All
four study reports conclude that three rather than two aquifers
exist and that a confining layer exists between the surficial
water table aquifer and the two deeper ones. EPA’s consultants
concluded:

Three aquifers occur at different elevations and appear to be
fairly continuous under the site. These are:

(1) A Water Table Aquifer, approximately 5 to 15’ below
ground surface.

(2) A Shallow Confined Aquifer, approximately 20 to 30’
below ground surface.

(3) A Deep Confined Aquifer, approximately 150 to 165’
below ground surface. (J.A. below at 529, emphasis
added)

Thus, EPA's (1) conclusion that a release observed in the shal-
low water table aquifer can be matched to the groundwater
Target of the “aquifer of concern” below a 40-foot depth, (2)
conclusion that no confining layer exists between them, and (3)
conclusion that only two rather than three aquifers exist: are
each contrary to all the record evidence. “If the finding is not
sustainable on the administrative record made, then the Comp-
troller’s decision must be vacated and the matter remanded to
him for further consideration.” Vermont Yankee, 519 U.S. at
949 (1978). The HRS scoring of the NSL site was done on May
23, 1985, but the EPA Hydrogeologic Study was issued three
months later. NSL provided EPA with a copy of its report eight
months prior to the promulgation of the Final Rule on Sep-
tember 21, 1984.

28

Although the Circuit panel held that NSL in its comments to
EPA did not clearly point out its positions and arguments
against EPA's scoring, NSL identified EPA’s Hydrogeologic
Study Report in its transmittal letter. G.A. below at 575)
Although this EPA Report consisted of 138 pages, including the
boring data and attachments, its text was only seven pages and
even stated under its “CONCLUSIONS?” section:

Two confined aquifers were identified in sand and gravel

zones beneath the ECC site. The deep aquifer occurs at a

depth of about 155 to 165 feet below ground surface and just

above the top of rock surface. A shallow aquifer occurs at
about 20 to 30 feet below ground surface. A thick glacial till
sequence of hard silty clay and clayey silt separates the two.

The upper aquifer appears to be confined by a silty clay layer.

(J.A. below at 534; emphasis added)

EPA scored this factor at 30 which gave NSL three-fourths of
its score for Groundwater Targets, even though the HRS
required that “if a discontinuity in the aquifer occurs between
the hazardous substance and all wells, give this factor a score of
().” This was contrary to the record evidence and to the require-
ments of EPA’s HRS. At the time the Final Rule was issued,
four separate hydrogeologic study reports submitted by NSL
in its Comments concluded that three aquifers existed and that
the deeper two were confined and discontinuous from the shal-
low water table aquifer having an onsite observed release. This
included an EPA study prepared three months after the State's
site scoring in May, 1983.

Thus, EPA obviously issued a decision contrary to its own
HRS requirements and to all scientific evidence.

CONCLUSION
The Petition for a Writ of Certiorari should be granted.
Respectfully submitted,
Warren D. Krebs

Counsel for
Northside Sanitary Landfill, Inc.

121 Monument Circle, Suite 500
Indianapolis, Indiana 46204

A-1

APPENDIX A

Notice: This opinion is subject to formal revision before publication
in the Federal Reporter or U.S.App.D.C. Reports. Users are requested
to notify the Clerk of any formal errors in order that corrections may be
made before the bound volumes go w press.

Yuited States Court of Appeals

FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued March 14, 1988 Decided June 28, 1988

No. 84-1586

NORTHSIDE SANITARY LANDFILL, INC.
Vv.

LEE M. THOMAS, ADMINISTRATOR

U.S. ENVIRONMENTAL PROTECTION AGENCY, and
U.S. ENVIRONMENTAL PROTECTION AGENCY

Petition for Review of an Order of the
Environmental Protection Agency

Warren D. Krebs for petitioner.

Lawrence E. Blatnik, Attorney, Department of Justice,
with whom Roger J. Marzulla, Acting Assistant Attorney
General, and Francis S. Blake, General Counsel, Mark
Greenwood, Assistant General Counsel, and Lawrence E.
Starfied, Attorney, Environmental Protection Agency,
were on the brief, for respondents.

Before: ROBINSON and SENTELLE, Circuit Judges and
KAUFMAN,” Senior District Judge.

Bills of costs must be filed within 14 days after entry of judgment. The
court looks with disfavor upon motions to file bills of costs out of time.

A-2

Opinion for the Court filed by Senior District Judge
KAUFMAN.

KAUFMAN, Senior District Judge: Petitioner, North-
side Sanitary Landfill, Inc. (Northside), seeks review of
an order of the Environmental Protection Agency (the
EPA or agency) which placed a hazardous waste site
owned by Northside on the National Priorities List
(NPL), and thereby made the site eligible for Super-
fund-financed remedial action pursuant to the Compre-
hensive Environmental Response, Compensation and Lia-
bility Act of 1980 (CERCLA), 42 U.S.C. 8§ 9601-57
(1982 & Supp. III 1985).' We have jurisdiction to re-

* Of the United States District Court for the District of
Maryland, sitting by designation pursuant to 28 U.S.C
§ 294(d).

1The description of CERCLA set forth in this opinion
contains those principles essential to an understanding of
this case. We have already commented extensively with re-
gard to what Judge Starr has aptly termed the “complex web
of ‘Superfund’ legislation.” Eagle-Picher Industries, Inc. v.
EPA, 759 F.2d 922, 925 (D.C. Cir. 1985) (Eagle-Picher II).
The three Eagle-Picher decisions of this court provide a use-
ful introduction to the background, interpretation, and appli-
cation of the Superfund legislation. See Eagle-Picher Indus-
tries, Inc. v. EPA, 759 F.2d 905 (D.C. Cir. 1985) (Eagle-
Picher 1); Eagle-Picher II, supra; Eagle-Picher Industries,
Inc. v. EPA, 822 F.2d 132 (D.C. Cir. 1987) (Eagle-Picher III).

After the events which are the subject of this petition
occurred, Congress amended CERCLA, enacting the Super-
fund Amendments and Reauthorization Act of 1986 (SARA),
Pub. L. No. 99-499, 100 Stat. 1613. Those amendments were
intended to “revitalize the Superfund program.” H.R. Rep.
No. 253(1), 99th Cong., 2d Sess. 54, reprinted in 1986 U.S.
CopE Conc. & ADMIN. NEWS 2835, 2836. Most of SARA went
into effect on October 17, 1986; however, some of SARA’s
provisions did not become effective until] January 1, 1987.
See 42 U.S.C. § 9601 note. As part of SARA, Congress re-
designated the “Hazardous Substance Response Trust Fund”

3
g
*

A-3

view that EPA order, id. § 9613(a), and, for the reasons
stated below, deny Northside’s petition for review.?

I. BACKGROUND

This case arises out of the EPA’s continuing attempts
to comply with the requirements of CERCLA, legislation
“designed [by Congress] to address the growing problem
of inactive hazardous waste sites throughout the United
States.” Eagle-Picher Industries, Inc. v. EPA, 759 F.2d
922, 925 (D.C. Cir. 1985) (Eagle-Picher II). “To enable
EPA to respond to those sites most urgently in need of
cleanup, EPA is required under . . . [CERCLA], 42
U.S.C. § 9605(8) (B), to compile the National Priorities
List (“NPL”) of releases or threatened releases” of haz-
ardous substances across the country. Id. at 926. In
order to pay for the cleanup of the sites, Congress created
a fund known as the “Hazardous Substance Response
Trust Fund,” or, as it is commonly called, the “Super-
fund.” 42 U.S.C. § 9631; Eagle-Picher II, 759 F.2d at
926 n.1.

In deciding whether a given site belongs on the NPL,
the EPA employs the “Hazardous Ranking System”
(HRS), a scientific model designed to determine the rela-
tive hazard which that site presents. The EPA “applies
the HRS to data from an observed or potential release
fof hazardous waste] to obtain a ‘score’ or estimate of
the risk from the release. The EPA then relies on HRS

as the “Hazardous Substance Superfund,” repealed 42 U.S.C.
§ 9631, and relocated the substance of that provision in the
Internal Revenue Code, 26 U.S.C. § 9507.

SARA does not affect the listing status of the hazardous
waste site owned by Northside. Except as otherwise indicated
in this opinion, we refer to the provisions of CERCLA which
were in effect at the time the Northside site was iisted on
the NPL.

2? We entered an Order granting judgment for the EPA on
March 25, 1988, and noted in that Order that this opinion
would follow.

A-4

scores to determine which [sites] should be listed on the
NPL.” Eagle-Picher I, 759 F.2d at 910 (footnote
omitted). A score of 28.5 or more leads to the inclusion
of the site on the NPL. 7d. at 910 n.17.

When the EPA orders a site to be placed on the NPL,
that site becomes eligible for remedial action financed
by the Superfund, although the mere listing of the site
on the NPL does not mean that the EPA will take such
remedial action. See 40 C.F.R. §300.68(a) (1987);
Eagle-Picher I, 759 F.2d at 911 & n.26. However, should
the EPA take remedial action against a site listed on the
NPL, past and present owners of the site become liable
for the cost of the cleanup. 42 U.S.C. § 9607(a) ; Eagle-
Picher II, 759 F.2d at 926 n.1. The initial version of the
NPL was promulgated as a final rule of the EPA on
September 8, 1983. The list, as required by Congress,
is revised to include new sites “no less often than an-
nually.” 42 U.S.C. § 9605(8) (B).

II. Facts

Northside owns and operates a 131-acre hazardous
waste site near Zionsville, Indiana (the Northside site).
The Northside site was included as part of the EPA’s
first annual revision to the NPL, which was published in
the form of a proposed rule on September 8, 1983. See
48 Fed. Reg. 40,674-82 (1983). Pursuant to 5 U.S.C.
§ 553(c),* the EPA allowed interested parties, including

348 Fed. Reg. 40,658 (1983). The NPL, including subse-
quent revisions, is codified at 40 C.F.R. Part 300, App. B
(1987). The NPL is promulgated in the form of a final rule
under informal notice-and-comment rulemaking procedures.
See 42 U.S.C. § 9605; 5 U.S.C. § 553(c).

4Section 553(c) of the Administrative Procedure Act

(APA), 5 U.S.C. §§ 551-59, 701-06 (1982 & Supp. III 1985),
provides in relevant part:

After notice required by this section, the agency shall

give interested persons an opportunity to participate in

PBA yee

A-5

Northside, to comment upon the proposed revision, and
gave them until November 7, 1983 to do so. 48 Fed. Reg.
40,674 (1983).

Despite the November 7, 1983 deadline, Northside did
not comment upon its site’s inclusion in the NPL revision
until more than two and one-half months after the com-
ment period had officially closed. On January 31, 1984,
the EPA received from Northside 420 pages of documents
consisting of various geological studies, water quality
evaluations, and correspondence pertaining to the North-
side site. The documents were accompanied by a letter
dated January 26, 1984 from Jonathan W. Bankert,
president of Northside, asking that “the Agency review
these documents even though not summited [sic] by No-
vember 7, 1983 since we were not advised of that date.”
J.A. 516.5 Although Bankert’s letter briefly described each
of the eleven separate documents Northside was submit-
ting, the letter did not in any way comment concerning the
specific relationship between any of the documents and
Northside’s objections to the way in which the EPA had
applied the HRS when scoring the Northside site. Nor
were specific statements about the relationship between
the documents and the HRS contained in the documents
submitted to the EPA along with Bankert’s letter.

Even though Northside’s comments were untimely filed,
the EPA did review those comments and prepared a four-
teen and one-half page response to them. See J.A. 469-

the rule making through submission of written data,
views, or arguments with or without opportunity for oral
presentation. After consideration of the relevant matter
presented, the agency shall incorporate in the rules
adopted a concise general statement of their basis and
purpose. . .

5 Despite this statement in Bankert’s letter, Northside had
been given notice concerning the date upon which the comment
period closed because, as is indicated in the text of this opinion,
that date was published in the Federal Register.

aaa aai aia aeielen b

A-6

83. Because Northside had not made any specific state-
ments about the purpose of its comments in Bankert’s
letter or elsewhere, the EPA was forced to make certain
assumptions about the documents which Northside had
submitted :

These documents include results of geologic sur-
veys and water quality evaluations pertaining to
ground and surface water in the area around the
[Northside] site. Northside made no further specific
comments, based on the documentation, regarding the
scoring factors on which the HRS score for this site
was based. For this reason, EPA’s response ad-
dresses only major findings or conclusions presented
in the documents which relate to the HRS score and
subsequent listing of the site on the NPL....

In general, all of the documentation which was
submitted appeared related to the linking of the con-
taminants found in samples of surface water and in
on-site wells to the landfill and to indicate contami-
nation is more likely migrating from the Envirochem
site located to the north of Northside landfill.

J.A. 470 (emphasis added).

After reviewing Northside’s comments, the EPA con-
firmed its previous conclusion that “the site has been
properly scored as proposed and is eligible for listing on
the NPL.” J.A. 483.° Accordingly, the Northside site
was included in the first annual revision of the NPL
when the latter was promulgated as a final rule on
September 21, 1984. 49 Fed. Reg. 37,070-90 (1984) .’
Northside did not request the EPA to reconsider its

6 The Northside site received a score of 46.04, J.A. 483,
well above the score of 28.5 required for inclusion on the
NPL. The Northside site is ranked 237th out of the 703
sites listed on the current version of the NPL. 40 C.F.R.
Part 300, App. B (1987).

™The Northside site is specifically listed at 49 Fed. Reg.
37,084 (1984).

A-7

ruling, although it had the right to do so. See 5 U.S.C.
§ 553(e).* Instead, Northside instituted this suit in this
court to attack its inclusion on the NPL.

III. Discussion

Northside challenges the EPA’s order on a variety of
substantive and procedural grounds. Essentially, North-
side contends that (1) the Northside site cannot be listed
on the NPL because portions of that site had already
been granted interim status under the Resource Conser-
vation and Recovery Act of 1976, 42 U.S.C. §§ 6901-911
(1982 & Supp. III 1985); (2) the documentation in the
record does not support the score which the Northside
site received under the HRS; and (3) in scoring the
Northside site, the EPA deviated from certain internal
quality control procedures. The EPA disagrees on the
merits with all of Northside’s claims. Furthermore, the
EPA contends that this court should refuse to consider
Northside’s objections because Northside failed properly
to raise them during the rulemaking proceeding. We
agree with the EPA that, by neglecting timely to put the
EPA on proper notice of its objections, Northside has
forfeited its right to have this court examine those ob-
jections on the merits.

While Northside did submit 420 pages of documents
to the EPA, it made no attempt to specify why it con-
sidered those documents or anything in them relevant
to the rulemaking procedure. Northside contends that
the notice-and-comment rulemaking provisions of 5
U.S.C. § 553(¢) do not require such specificity. North-
side apparently believes that the mere submission of
voluminous documentation to the EPA is enough to put

8 Each agency shall give an interested person the right
to petition for the issuance, amendment, or repeal of a
rule.

5 U.S.C. §553(e). For further discussion, see infra note 11.

A-8

the EPA on notice of all possible reasons why a site
should not have been included on the NPL. But common
sense and case law dictate that Northside should have
assumed at least a modicum of responsibility for flagging
the relevant issues which its documentary submissions
presented. As Judge Leventhal has noted:

(C]omments must be significant enough to step over
a threshold requirement of materiality before any
lack of agency response or consideration becomes of
concern. The comment cannot merely state that a
particular mistake was made .. .; it must show why
the mistake was of possible significance in the results
[the agency reaches}.

Portland Cement Ass’n v. Ruckelshaus, 486 F.2d 375,
394 (D.C. Cir. 1973), cert. denied sub nom. Portland
Cement Ass’n v. Administrator, EPA, 417 U.S. 921
(1974) (emphasis added).

In Vermont Yankee Nuclear Power Corp. v. Natural
Resources Defense Council, Inc., 435 U.S. 519 (1978),
then-Justice Rehnquist expressed the unanimous opinion
of seven members of the Supreme Court® that a party
such as Northside has the burden of clarifying its posi-
tion for the EPA.*° Even though the EPA has the stat-

® Neither Justice Powell nor Justice Blackmun took part
in the decision of Vermont Yankee.

10 Portland Cement and Vermont Yankee arose in somewhat
different contexts. Portland Cement involved the propriety
of proposed EPA regulations under the Clean Air Act, 42
U.S.C. §§ 7401-7642 (1982 & Supp. III 1985), regarding the
standards of performance for portland cement plants. At
issue in that case was an interested party’s right to comment
under 5 U.S.C. §553(c) concerning the methodology which
the EPA had used in establishing those standards. Justice
Rehnquist’s comments in Vermont Yankee are addressed to
the application of the National Environmental Policy Act, 42
U.S.C. §§ 4321-70a (1982 & Supp. III 1985) in a licensing
context and indicate the thoroughness with which the EPA
must consider the environmental impact of a proposed action

A-9

utory obligation to consider fully significant comments,
“it is still incumbent upon intervenors who wish to par-
ticipate [in a licensing proceeding] to structure their par-
ticipation so that it is meaningful, so that it alerts the
agency to the intervenors’ position and contentions.”
435 U.S. at 553. Justice Rehnquist then quoted with ap-
proval Judge Leventhal’s remarks in Portland Cement,
id., and concluded that

administrative proceedings should not be a game or
a forum to engage in unjustified obstructionism by
making cryptic and obscure references to matters
that “ought to be” considered and then, after failing
to do more to bring the matter to the agency’s
attention, seeking to have that agency determination
vacated on the ground that the agency failed to con-
sider matters “forcefully presented.”

Td. at 553-54.

Applying those principles to Northside’s petition for
review, it is quite clear that Northside’s comments did
not alert the EPA to any of the contentions which
Northside presses before us. President Bankert’s trans-
mittal letter did nothing more than list the titles of the
documents enclosed with it. Neither Bankert’s letter nor
any of the documents submitted with it made clear the
objections which Northside now contends that it was
making. Indeed, as the EPA’s response to Northside’s
comments reveals, Northside’s documents lend themselves
to an interpretation of Northside’s objections which, al-
though not what Northside intended, is still entirely con-
sistent with the types of objections which a party might
make when a hazardous waste site which it owns is
listed on the NPL.

It is certainly incumbent upon the EPA under 5
U.S.C. § 553(c) to “respond[] in a reasoned manner to

in the light of the comments which interested parties make
about that action.

A-10

significant comments received.” United States Satellite
Broadcasting Co., Inc. v. FCC, 740 F.2d 1177, 1188
(D.C. Cir. 1984) ; see also, e.g., Home Box Office, Inc. v.
FCC, 567 F.2d 9, 35-386 & n.58 (D.C. Cir.), cert. denied,
434 U.S. 829 (1977). But the “dialogue” between ad-
ministrative agencies and the public “is a two-way
street.” Home Box Office, 567 F.2d at 35. Just as “the
opportunity to comment is meaningless unless the agency
responds to significant points raised by the public,” id.
at 35-36 (footnote omitted), so too is the agency’s oppor-
tunity to respond to those comments meaningless unless
the interested party clearly states its position. See Wis-
consin Electric Power Co. v. Costle, 715 F.2d 323, 326
(7th Cir. 1983) (“the rules of administrative law apply
across the board, to agencies and interested parties
alike’).

We hold that when Northside submitted its comments
to the EPA, Northside should have been specific as to
why and how it thought the 420 pages of documents
were relevant to the scoring of the Northside site. We
are not suggesting that Northside should have com-
mented in great detail on every study, but we do con-
clude that Northside could and should have done far
more than it did do to alert the EPA to its positions,
which would have then required and allowed the EPA
fully to consider Northside’s version of the facts, and to -
act upon them appropriately." We therefore conclude

11 At the very least, Northside itself could have pointed
out those facts which it believed that the EPA had overlooked
in the EPA’s response to Northside’s comments. Specifically,
when Northside received the EPA’s response to its comments,
it was on notice that the EPA had not interpreted those
comments as Northside evidently expected the agency would.
At that point, pursuant to 5 U.S.C. §553(e), see note 8,
supra, Northside was free to petition the EPA to reconsider
its position concerning those comments in the light of the
specific objections which Northside now raises before this
court. See Wisconsin Electric, 715 F.2d at 327-28. However,
Northside did not take advantage of that opportunity.

A-1l

that the EPA’s failure to respond to the specific issues
which Northside asserts were presented by its comments
was neither arbitrary nor capricious. See Home Box
Office, 567 F.2d at 35-36 n.58. We agree with the EPA
that Northside never presented its objections to the
agency in a way which could reasonably have permitted
the agency to examine those contentions.

Because Northside did not properly present its ob-
jections to the EPA during the rulemaking process, we
will not address the merits of those objections. Eagle-
Picher III, 822 F.2d at 146; see also, €.g., Natural Re-
sources Defense Council, Inc. v. Thomas, 805 F.2d 410,
427-28 (D.C. Cir. 1986); Washington Ass’n for Televi-
ston and Children v. FCC, 712 F.2d 677, 680-82 (D.C.
Cir. 1983). However, we note that were we to reach
those merits, we would still deny Northside’s petition
for review because the EPA’s decision to place the
Northside site on the NPL finds ample support in the
record before us. Thus, in our view, the EPA’s decision
was in no way arbitrary or capricious. See Eagle-Picher
I, 759 F.2d at 921 (setting forth the standard of review
for decisions concerning NPL). Accordingly, we hereby
confirm our Order of March 25, 1988 affirming the
EPA’s placement of the Northside site on the NPL, and
denying Northside’s petition for review thereof. The pe-
tition is

Denied.

A-12

Received March 30, 1988 W.D.K.
United States Court of Appeals For the District of Columbia
Circuit. Filed March 25, 1988. Constance L. Dupre’, Clerk.
APPENDIX B
United States Court of Appeals
FOR THE DISTRICT OF COLUMBIA CIRCUIT

No. 34-1586 September Term, 1987
NorTHSIDE SANITARY LANDFILL, INC.
Petitioner
V.
Lert M. THOMAS, ADMINISTRATOR,
UNirep STATES ENVIRONMENTAL PROTECTION AGENCY,
ET. AL.
Respondents

ON PETITION FOR REVIEW OF AN ORDER OF THE
ENVIRONMENTAL PROTECTION AGENCY

Before ROBINSON, AND SENTELLE, Circuit Judges, and
KAUFMAN, Senior District Judge*.

JUDGMENT

This cause came on for consideration on a petition for review
of an order of the Environmental Protection Agency, and was
briefed and argued by counsel.

Upon consideration thereof, it is

ORDERED AND ADJUDGED by the Court that the peti-
tion for review herein be and hereby is denied. The opinion of
the Court will follow. It is

A-13

FURTHER ORDERED, by the Court, swa sponte, that
Clerk withhold issuance of the mandate herein until seven days
after disposition of any timely petition for rehearing. See D.C.
Cir. Rule 15.

Per Curiam
For the Court
/s/ Catherine L. Bateman

Constance L. Dupre
Clerk
Of the United States District Court for the District of Maryland, sitting by
designation pursuant to 28 U.S.C. § 294(d).

A-14

Received May 11, 1988 W.D.K.
United States Court of Appeals For the District of Columbia
Circuit. Filed May 9, 1988. Constance L. Dupre , Clerk.

APPENDIX C
United States Court of Appeals
FOR THE DISTRICT OF COLUMBIA CIRCUIT

No. 84-1586 September Term, 1987

NorrHsiDE SANITARY LANDFILL, INC.
Petitioner
V.
Let M. THOMAS AS ADMINISTRATOR OF THE
U.S. ENVIRONMENTAL ProrecTion AGENCY, AND
U.S. ENVIRONMENTAL ProrecTrion AGENCY
Re sponde nts

ORDER

Upon consideration of the Motion of Petitioners for E:xten-
sion of Time, it is

ORDERED that the motion is granted and the time within
which to file a petition for rehearing and/or suggestion for
rehearing en bane is extended for a period of 45 days from the
date of issuance of the opinion of the court.

FOR THE COURT:

CONSTANCE L. DUPRE, CLERK

BY: /s/ Robert A. Bonner
Robert A. Bonner
Deputy Clerk

A-15

Received September 2, 1988
United States Court of Appeals For the District of Columbia
Circuit. Filed August 31, 1988. Constance L. Dupre’, Clerk.
APPENDIX D
United States Court of Appeals
FOR THE DISTRICT OF COLUMBIA CIRCUIT

No. 84-1586 September Term, 1987

NoORTHSIDE SANITARY LANDFILL, INC.
Petitioner

V.
LEE M. THOMAS, ADMINISTRATOR,
U.S. ENVIRONMENTAL ProrecTiION AGENCY

Respondent

BEFORE: Robinson and Sentelle, Circuit Judges, and
Kaufman *, Senior District Judge

ORDER

Upon consideration of Appellant's Petition for Rehearing it is
ORDERED, by the court, that the Petition is denied.

FOR THE COURT:
CONSTANCE L. DUPRE, CLERK
BY: /s/ R. A. Bonner

Robert A. Bonner
Deputy Clerk

“of the United States District Court For The District of Maryland, sitting by
designation pursuant to 28 U.S.C. 294(d).

ec Aa sms

A-16

Received September 2, 1988.
United States Court of Appeals For the District of Columbia
Circuit. Filed August 31, 1988. Constance L. Dupre’, Clerk.

APPENDIX E
United States Court of Appeals
FOR THE DISTRICT OF COLUMBIA CIRCUIT

No. 84-1586 September Term, 1987

NorTHSIDE SANITARY LANDFILL, INC.
Petitioner
v.
Lee M. THOMAS, ADMINISTRATOR
U.S. ENVIRONMENTAL PROTECTION AGENCY
Respondent
BEFORE: Wald, Chief Judge; Robinson, Mikva,
Edwards, Ruth B. Ginsburg, Starr, Silber-
man, Buckley, Williams, D.H. Ginsburg and
Sentelle, Circuit Judges and Kaufman*,
Senior District Judge
ORDER
Appellant’s suggestion for rehearing en banc has been
circulated to the full court. No member of the court
requested the taking of a vote thereon. Upon consideration
of the foregoing it is
ORDERED, by the court en banc, that appellant’s sug-
gestion is denied.
FOR THE COURT:
CONSTANCE L. DUPRE’, CLERK

BY: /s/ R.A. Bonner
Robert A. Bonner
Deputy Clerk

‘of the United States District Court For The District of Maryland, sitting by
designation pursuant to 28 U.S.C. 294(d).

A-17

Received April 2, 1984
United States Court of Appeals For the District of Columbia
Circuit. Filed March 28, 1984. George A. Fisher, Clerk.
APPENDIX F
United States Court of Appeals
FOR THE DISTRICT OF COLUMBIA CIRCUIT

No. 83-2247 September Term, 1983
SCM CorrPoRATION
Petitioner
V.
WILLIAM D. RuCKELSHAUS, ADMINISTRATOR,
U.S. ENVIRONMENTAL PROTECTION AGENCY

Respondent
No. 83-2258
NoORTHSIDE SANITARY LANDFILL, INC.
Petitioner
V.
WILLIAM D. RUCKELSHAUS, ef. al.
Respondent

ORDER

On consideration of the joint motion to deconsolidate and to
dismiss case No. 83-2258 from Nos. 83-2247, et al., it is

ORDERED that the aforesaid motion is granted and docket
No. 83-2258 is hereby terminated.

The foregoing docket termination applies only to No. 83-2258
and the Clerk is directed to transmit forthwith to the respon-

aoe

A-18

dent a certified copy of this order in lieu of formal mandate in
that case.
FOR THE COURT:
GEORGE A. FISHER, CLERK
BY: /s/ Dan M. Cathey
Daniel M. Cathey
First Deputy Clerk

FER eee pare 2

A-19

APPENDIX G

dn the
United States Court of Appeals
Bor the Seventh Cirrntt

No. 85-2119
NORTHSIDE SANITARY LANDFILL, INC.,
Petitioner,
VU.

LEE M. THOMAS, as the Administrator of the United
States Environmental Protection Agency, and the
United States Environmental Protection Agency,

Respondents.

Petition for Review of an Order of the
United States Environmental Protection Agency

ARGUED APRIL 4, 1986—DECIDED OCTOBER 23, 1986

Before Woop, CoFFEY, Circuit Judges, and ESCHBACH,
Senior Circuit Judge.

ESCHBACH, Senior Circuit Judge. The primary ques-
tion that we will consider in addressing this petition for
review of an order of the Administrator of the Environ-
mental Protection Agency (‘‘Administrator’’) denying the
petitioner’s hazardous waste management permit applica-
tion, is whether the petitioner has standing to challenge
remarks concerning the scope of closure of the petitioner’s
facility that were made by the Administrator during the
permit denial proceedings. For the reasons stated below,
we will dismiss the petition for review.

as |

A-20

I
A. Statutory and Regulatory Provisicns

The Resource Conservation and Recovery Act of 1976
(“‘Act’’), codified as amended at 42 U.S.C. §§ 6901-6991,
governs the disposal of solid waste in the United States.
In particular, §§ 3001 through 3013 of the Act, codified
as amended at 42 U.S.C. 8§ 6921-6934, regulate hazardous
waste management and disposal. Section 3005(a) of the
Act, codified as amended at 42 U.S.C. § 6925(a), provides
that “the Administrator shall promulgate regulations re-
quiring each person owning or operating an existing [haz-
ardous waste disposal] facility . . . to have a permit issued
pursuant to this section.” Section 3004 of the Act, codified
as amended at 42 U.S.C. § 6924(a), requires that the Ad-
ministrator “promulgate regulations establishing such per-
formance standards, applicable to owners and operators
of facilities for the treatment, storage, or disposal of hazar-
dous wastes .. ., as may be necessary to protect human
health and the environment.”

Recognizing that the Environmental Protection Agen-
cy (“EPA”) could not issue permits to all hazardous waste
applicants before the effective date of the Act, Congress
provided that, under § 3005(e) of the Act, the Adminis-
trator promulgate regulations that allowed the owner or
operator of a hazardous waste management facility that
was in existence on November 19, 1980, to file a ‘Part
A application,” and to continue hazardous waste disposal
pending the final administrative action on the facility’s ap-
plication. The Part A application calls for minimal infor-
mation concerning the nature of the applicant’s business,
a description of the hazardous waste management proc-
esses it employs, a specification of the types of hazardous
wastes processed, stored, or disposed of at the facility,
as well as maps, drawings and photographs of the facili-
ty’s past, present, and future waste processing areas. Id.
§ 270.13. If the Administrator finds no reason to believe
that the Part A application does not meet the disclosure
requirements of id. § 270.18, once it has filed a Part A

A-21

application and given proper notice of hazardous waste -
activities, an existing facility “shall have interim status
and shall be treated as having been issued a permit.” 42
U.S.C. § 6925(e); 40 C.F.R. § 270.70. The operation of
a facility that has been granted interim status is limited
to the types of wastes, as well as the processing, storage,
and disposal procedures specified in the Part A applica-
tion. Under 40 C.F.R. § 270.71, the facility must comply
with the operating standards set forth at 40 C.F.R. Part
265. A facility’s interim status terminates either upon final
administrative disposition of a permit application, 40 C.F.R.
§ 270.73(a), or upon failure of the operator to furnish the
full information required by the Part B application, as
described below.!

Following the approval of a facility’s Part A applica-
tion and the grant of interim status, the facility must file
a “Part B application” with the EPA. The Part B appli-
cation calls for detailed information, including chemical and
physical analyses of the hazardous waste treated at the
facility, a description of procedures for preventing con-
tamination of water supplies, a determination of the ap-
plicable seismic standard for the facility, a determination
whether the facility is located within a flood plain, and
data relating to groundwater monitoring. Jd. § 270.14. The
applicant must also furnish information concerning its use
of hazardous waste containers, storage or disposal tanks,
surface impoundments, waste piles, incinerators, land
treatment facilities, and landfills. Jd. §§ 270.15-270.21.
Upon successful completion of both the Part A and Part

1 Under the 1984 amendments t.» the Act, a facility that had been
granted interim status before November 8, 1984, shall have that
status terminated on November 9, 1985, should the facility fail to
apply for a final determination regarding the issuance of a permit
pursuant to 42 U.S.C. § 6925(c) (Part B application) before
November 9, 1985, and to certify that it is in compliance with all
applicable groundwater monitoring and financial responsibility re-
quirements. 42 U.S.C. § 6925(eX2) (as amended by P. L. No. 98-616,
98 Stat. 3221).

A-22

B application, an operator is issued a hazardous waste per-
mit, and is required to comply with the standards set
forth in id. §§ 264.1-264.351 (“Part 264”’).

A facility that has been approved for interim status
operation must prepare a written closure plan, a copy of
which must be kept at the facility. Jd. § 265.112. The pur-
pose of the closure plan is to “protect human health and
the environment, [to prevent] post-closure escape of hazar-
dous waste, hazardous waste constituents, leachate, con-
taminated rainfall, to [protect against the escape] of waste
decomposition products to the ground or surface waters
or to the atmosphere.” Jd. § 265.111(b). Once closure has
been ordered, the owner or operator of the facility must
terminate operations in a manner that minimizes the need
for further maintenance of the facility. Jd. § 265.111(a).

A closure plan must “identify the steps necessary to
completely or partially close the facility at any point dur-
ing its intended operating life and to completely close the
facility at the end of its intended operating life.” Jd.
§ 265.112(a). In addition, the closure plan must provide
for post-closure care for a period of thirty years after the
facility is closed. Jd. § 265.117(a). Post-closure measures
include ground-water monitoring, muintenance of other
monitoring and waste containment systems, and periodic
reporting. Jd. § 265.117. The plan may be amended as
changes in the operation of the facility so dictate. Jd.
§ 112(4Xb).

The owner or operator of a hazardous waste manage-
ment facility must submit a closure plan to the appro-
priate EPA regional administrator at least 180 days be-
fore the date the facility is expected to begin closure. Jd.
§ 112(4Xc). However, if the EPA has terminated the facili-
ty’s interim status and has not issued a hazardous waste
permit for the facility, the closure plan must be submitted
to the EPA no later than fifteen days after interim status
is terminated. Jd. § 112(4XcX1). The public is provided an
opportunity to comment on the submitted plan. Jd. § 112
(4Xd). The regional administrator must approve, modify,

A-23

or disapprove the closure plan within ninety days of its
receipt. The owner or operator of the facility is given six-
ty additional days to modify or prepare a new plan should
the Regional Administrator have modified or rejected the
original plan. Jd. Whatever modification or revision the
Regional Administrator then makes of the operator’s re-
vised plan shall become the approved closure plan. /d.

Section 3005(c) of the Act, codified as amended at 42
U.S.C. § 6925(c), provides that a state environmental
agency, as authorized by the Administrator pursuant to
42 U.S.C. § 6947(a), is responsible for the issuance of
hazardous waste management permits. Section 3006 of the
Act, codified as amended at 42 U.S.C. § 6926, provides
that a state may apply to the Administrator for authority
to develop and enforce a hazardous waste program ‘‘in
lieu of’ a federal program and federal enforcement. 40
C.F.R. §§ 271.1-271.137 (“Part 271’’) sets forth the re-
quirements for authorizing state programs. Under these
regulations, a state may obtain “interim authorization”
in two “phases.” Phase I tracks the regulations of 40
C.F.R. §§ 265.1-265.430 (“Part 265’’), and authorizes the
state agency to, among other things, conduct closure pro-
ceedings for interim status facilities. See id. § 271.28. Once
a state obtains Phase I authorization, its regulations and
procedures displace the federal interim status regulations.
Phase II authorization allows the state to issue permits
under standards corresponding to those found in Part 270,
and to enforce standards corresponding to those found at
Part 264.

Section 7006(b) of the Act, codified as amended at 42
U.S.C. § 6976(b), provides that “{rleview of the Adminis-
trator’s action . . . in issuing, denying, modifying, or
revoking any permit ... may be had by any interested
person in the Circuit Court of Appeals of the United
States for the Federal judicial district in which such per-
son resides or transacts such business upon application
by such person. . . . Such review shall be in accordance
with sections 701 through 706 of Title 5.” If a party has
been aggrieved by the action of an authorized state agen-

A-24

cy, review of the agency’s decision shall be had in ac-
cordance with the applicable state regulations.

B. Facts

The petitioner, Northside Sanitary Landfill, Inc., (“North-
side’’), operates a landfill near Zionsville, Indiana, and pro-
vides sanitary and hazardous waste disposal services for
Indianapolis and Boone County, Indiana. Northside was
in existence for many years prior to the passage of the
Act. On November 18, 1980, Northside submitted a Part
A application to the Administrator for a hazardous waste
treatment and disposal permit. As part of its application
materials, Northside included a hand-drawn scale map of
its facility. The map delineated five areas within North-
side’s property boundary.

The first, the ‘““Old Farm” area (also called the ‘Past
Treatment and Disposal Area’’ or the “West Farm’’), con-
sisted of forty acres. Northside claims that it had not used
the Old Farm for the disposal of hazardous wastes after
the statutory cut-off date of November 19, 1980. The Ad-
ministrator disputes this claim. The second, the “East
Farm Area’’ (also called the ‘“‘Current Treatment and
Disposal Area’’), consisted of approximately thirty acres.
Northside and the Administrator agree that hazardous
wastes were disposed of in the East Farm area after
November 19, 1980. The third area, composed of two
tracts and designated the “‘Proposed Future Treatment
and Disposal Area” (also called the “North Farm Area”),
consisted of sixty-four acres. In its brief before this court,
the Administrator acknowledged that “it appears from the
record that no wastes of any kind have been disposed of
in this area.” The fourth area was labelled the ‘‘Storage
and Treatment Tank Area.” The fifth and final tract (un-
named in the application) had upon it a storage barn, re-
pair shop, and Northside’s office.

In its Part A application, Northside requested approval
of a “303 acre-feet” disposal capacity. Northside maintains
that the disposal capacity proposed was solely for the thir-

=

A+25

ty acre East Farm area. On June 9, 1982, the Region V
Administrator acknowledged that Northside’s application
qualified it for interim status, and noted that a 303 acre-
feet process design capacity has been approved for North-
side’s facility. On January 26, 19838, the Region V Admin-
istrator requested that Northside submit a Part B applica-
tion by July 29, 1983. According to the Administrator, that
application was received on Augusi 5, 1983.

After the submission of Northside’s Part B application,
the Region V Administrator sent Northside three notices
that the information contained in the application was defi-
cient and, hence, the application did not comply with the
applicable regulations. Northside failed by the required
dates to correct the deficiencies. On April 30, 1984, North-
side informed the Region V Administrator by letter that
it was “official[ly]” withdrawing its Part B application.
On July 25, 1984, the Region V Administrator, however,
pursuant to 40 C.F.R. § 124.10, issued a notice of his ten-
tative decision to deny Northside’s permit application on
the grounds that the application was deficient, did not ade-
quately provide for the protection of groundwater, and
that other “continuing environmental violations’ had oc-
curred. In accordance with 42 U.S.C. § 6974(b) and 40
C.F.R. §§ 124.11-124.12, a public hearing was held on
August 28, 1984, at Zionsville, Indiana.

At the public hearing, the EPA stated that Northside’s
Part B application did not include closure information re-
garding the areas of its facility for which interim status
had been granted. In response, Northside stated that the
Region V Administrator had incorrectly considered the
Old Farm Area as part of Northside’s permit application.
Northside maintained that it had sought a permit for a
303 acre-feet disposal capacity, and that this was to be
loeated in the East Farm. Northside added that, of the
thirty acres composing this area, only twelve acres had
actually been used for the treatment and disposal of hazar-
dous wastes. Northside did not, however, contest the
denial of its Part B application.

A-26

On October 12, 1984, the Region V Administrator denied
Northside’s Part B application on the ground that North-
side had failed to submit the necessary information. Pur-
suant to 40 C.F.R. § 270.73(a), the Region V Administra-
tor also terminated Northside’s interim status on the
ground that a final administrative disposition had been
made of Northside’s permit application. In response to
Northside’s position at the public hearing, the Region V
Administrator stated in his order that hazardous waste
had been disposed of after November 19, 1980, in the Old
Farm Area as well as the East Farm. The administrator
concluded that “(t]he entire hazardous waste landfill area
outlined in the November 18, 1980, Part A application
must be closed. This includes the ‘Old Farm Area.’ ”’ The
Region V Administrator’s order disallowed any further
hazardous waste storage, treatment, or disposal of hazar-
dous waste at the Northside facility. Moreover, the order
required Northside to commence immediate closure pro-
ceedings under the applicable Indiana regulations.

On November 8, 1984, pursuant to 40 C.F.R. § 124.19,
Northside petitioned the Administrator for review of the
Region V order that denied its permit application and or-
dered closure. Attached to Northside’s petition was a copy
of its Part A application with a drawing of the facility
and a copy of an aerial photograph taken of the facility
on September 9, 1980. Northside also included the revised
“General Facility Description” from its Part A applica-
tion, which description indicated that the forty-acre Old
Farm Area had not been used for hazardous waste treat-
ment and disposal since November 1980, and that the
sixty-four acre North Farm Area had never been used
for hazardous waste processing. Northside claimed (both
before the Administrator and before this court) that, on
January 4, 1985, the Region V Administrator submitted
drawings of Northside’s facility to the Administrator that
inaccurately depicted the areas that Northside requested
the EPA consider for a hazardous waste management
permit.

A-27

In its petition for review to the Administrator, Northside
twice reiterated its position that it was not challenging
the denial of its Part B application. It claimed, however,
that the comments made by the Region V Administrator
relating to the scope of closure were based upon inac-
curate information and were, therefore, clearly erroneous.
Although Northside, by implication, maintained that the
disputed comments addressed a matter, viz., closure, not
appropriately a subject for permit denial proceedings, it
argued that, if the Administrator nevertheless considered
the comments appropriate in the context, then Northside
should have an appeal as of right under 40 C.F.R. § 124.19.
Finally, in an effort to challenge the disputed comments,
not to challenge the denial of its Part B application per
se, Northside stated that, “{ilf necessary for administrative
appellate review, the Administrator should consider North-
side’s submittal an appeal from the permit decision.”

On April 3, 1985, the Administrator issued an order de-
nying Northside’s petition for review of the Region V Ad-
ministrator’s denial of Northside’s hazardous waste ap-
plication. The Administrator did, however, state that the
questions Northside raised regarding the areas within the
(1) facility that were encompassed by its Part A and Part
B permit applications and (2) that could properly be closed
addressed two of:

the most rudimentary pieces of information that go
into a proper permit cecision. If the permit decision
does not identify where the facility is located, or how
big it is, the permit decision cannot be implemented
successfully regardless of the outcome of the decision.
This is particularly apparent in the present case, for
either including or excluding the Old Farm Area will
significantly alter the area of Petitioner’s landfill that
is subject to the closure and post-closure requirements
of the regulations.

The Administrator concluded:

Therefore, even though . . . [Northside] has stated that
it does not object to the denial of its permit, I am

A-28

persuaded that the matter... [Northside] is raising
is such an integral part of the permit decision that
it is the kind of matter which can be reviewed under
§ 124.19.

The Administrator also observed that “{t]here is no
review as of right from the Region’s determination.”
Rather, ‘(40 C.F.R. § 124.19] clearly provides that...
permits will not be reviewed unless the Petitioner is able
to show that the permit determination is clearly erroneous
or involves an exercise of discretion or policy which is
important and which should be reviewed as a discretion-
ary matter.’”’ The Administrator then concluded that, al-
though the sort of issue Northside raised was within the
ambit of 40 C.F.R. § 124.19, Northside “has not sustained
its burden of showing that the permit determination is
either clearly erroneous or involves an exercise of discre-
tion or policy which warrants discretionary review.”

On Apri! 19, 1980, Northside filed a motion to recon-
sider with the Administrator, in which it noted that:

[TJhe issue as to whether the Old Farm Area is a part
of the Part A interim site is presently being litigated
before a hearing officer of the Indiana Environmental
Management Board. . . . Therefore, the Region’s deci-
sion, as confirmed by the Administrator’s recent
Order, has ruled upon an issue which the U.S. En-
vironmental Protection Agency has delegated to the
State [Environmental Management Board]. . . . This
results in a denial of both procedural and substantive
due process of law and affords the Petitioner no hear-
ing at any time on the administrative determination
of this issue.

On July 2, 1985, before the Administrator had ruled on
the motion for reconsideration, Northside filed a petition
for review with this court.

On November 27, 1985, approximately two days before
briefs were to be filed with this court in support of North-
side’s petition for review, the Administrator denied North-
side’s motion for reconsideration. Although the effect of

A-29

his order was to affirm his initial order, the Administrator
adopted a completely different rationale on reconsidera-
tion by holding that, because Indiana had been granted
authority pursuant to 42 U.S.C. § 6926 to conduct closure
proceedings for interim status permits, the comments in
the Administrator’s initial order regarding the scope of
closure (and those comments made bv the EPA and the
Regional Administrator in the permit denial proceeding
itself) “are without legal effect.” In addition, the Admin-
istrator also noted that a parcel considered part of the
facility for the purposes of a permit application need not
automatically undergo closure upon a denial of the per-
mit application.

II
A. Timeliness of Petition for Review

Northside’s petition for review raises a number of juris-
dictional issues; some have been considered by the par-
ties, others have not. The first question we must decide
is whether this court has jurisdiction under 42 U.S.C.
§ 6976(b), the judicial review provision for the Solid Waste
Disposal Act, to entertain Northside’s petition. Section
6976(b) provides that a petition for review must be filed
with this court within ninety days from the date of the
Administrator’s action in issuing, denying, modifying, or
revoking a permit. Northside filed the instant petition for
review on July 2, 1985. This was within ninety days of
the Administrator’s order of April 2, 1985 denying North-
side review of Region V’s order, which rejected North-
side’s Part B application. Northside had, however, on
April 19, 1985, filed a motion requesting that the Admin-
istrator reconsider his order of April 2. It was not until
November 27, 1985, some five months later, that the Ad-
ministrator denied the reconsideration motion.? Northside

2 In the interim, both Northside and the Administrator had filed
a number of motions (not concerning the issues of jurisdiction and
standing) in this court in regard to Northside’s petition for review.

A-30

did not, however, amend its original petition to reflect
the Administrator’s denial of its motion for reconsidera-
tion, which became the final administrative order on its
Part B application.

On December 5, 1985, the Administrator filed a motion
with this court requesting to amend the certified list of
documents constituting the administrative record under
review to include the November 27 order. Northside ob-
jected to the motion. On December 12, 1985, we issued
an order stating that the Administrator’s motion would
be considered with the merits of Northside’s petition.
Following our order, Northside again took no action to
amend its petition for review. Oral argument on North-
side’s petition was held on April 4, 1986, well over ninety
days after the November 27, 1985, order denying recon-
sideration.

The limitation period set forth in § 2976(b) is jurisdic-

tional, see Arch Mineral Corp. v. Director, No. 84-2633,

slip op. at 2 (7th Cir. Aug. 11, 1986); Natural Resources
Defense Council v. NRC, 666 F.2d 595, 602 (D.C. Cir.
1981), and hence, we must consider the timeliness and suf-
ficiency of Northside’s petition, whether the parties have
raised the issue or not. See Bender v. Williamsport Area
School District, 106 S. Ct. 1326, 1331 (1986); Christian-
son v. Colt Industries Operating Corp., No. 86-1145, slip
op. at 8-9 (7th Cir. Aug. 19, 1986); Foster v. Center Town-
ship, LaPorte County, No. 85-1560, slip op. at 8 (7th Cir.
Aug. 13, 1986). We shall then determine whether North-
side’s petition for review was premature when filed on
July 2, 1985, and hence, insufficient to invoke our juris-
diction under § 2976(b). By the same token, if we find
that the petition was not premature when filed, we must
decide whether Northside’s failure to amend the petition
to reflect the Administrator’s final order affected our
jurisdiction.

In reviewing a petition challenging an award of benefits
under the Black Lung Benefits Act, codified as amended
at 30 U.S.C. §§ 901-960, we recently held that “a peti-
tion for review ... is timely if filed within sixty days

|

A-31

of the . . . [Benefits Review] Board’s denial of a timely
motion for reconsideration.”’ Arch Mineral, No. 84-2633,
slip op. at 8 (emphasis added). In Arch Mineral, we noted
that “{a] clear majority of the cases involving appellate
review of administrative decisions hold that, where the
applicable statute and administrative regulations are
silent, the filing of a motion for reconsideration suspends
the time for filing a petition for review.” Id., slip op. at 6.

Nevertheless, Arch Mineral involved a statutory scheme
of judicial review quite different than that presented in
the instant case. 42 U.S.C. § 6976(b) provides that judicial
review of the Administrator’s actions “shall be in ac-
cordance with sections 701 through 706 of Title 5,” that
is, the Administrative Procedure Act. Section 704 provides
that “{e]xcept as otherwise expressly required by statute,
agency action otherwise final is final for the purposes of
this section whether or not there has been presented or
determined an application for . . . any form of reconsidera-
tion.” Thus, by its terms, “(t]he Administrative Procedure
Act explicitly permits [a] judicial appeal and [a] request
for agency reconsideration to be pursued simultaneously.”’
American Trucking Associations, Inc. v. ICC, 697 F.2d
1146, 1148 n.* (D.C. Cir. 1983) (Scalia, J.). We hold, there-
fore, that Northside’s petition for review, which was filed
withir: ninety days of the Administrator’s initial order de-
nying review, was timely under § 6976(b) and thus suffi-
cient to invoke our jurisdiction.? See also Selco Supply

3 In Arch Mineral Corp. v. Director, No. 84-2633, slip op. at 7
(7th Cir. Aug. 11, 1986), we noted that ‘“{i}t is obviously wasteful
of the resources of the courts to burden them with objections to
adm.nistrative action which may be obviated by agency:action on
reconsideration.”’ Nevertheless, citing Selco Supply Co. v. EPA,
632 F.2d 863, 865 (10th Cir. 1980), cert. denied, 450 U.S. 1030
(1981), we noted that in the context of environmental legislation,
the need for “prompi decisionmaking procedures that could bet-
ter prevent unnecessary injury” must be taken into account. Arch
Mineral, No. 84-2633, slip op. at 7. We cannot be unmindful at
this juncture that the EPA has expressed concern about the ef-

(Footnote continued on following page)

|

A-32

Co. v. EPA, 632 F.2d 863, 865 (10th Cir. 1980), cert.
devried, 450 U.S. 1030 (1981) (motion to reconsider does
not toll sixty-day limit under 7 U.S.C. § 136n(b), which
governs judicial review of EPA orders under the Federal
Insecticide, Fungicide and Rodenticide Act, codified as
amended at 7 U.S.C. §§ 135-136y).

In addition, we grant the Administrator’s motion to
amend the certified list of documents constituting the
record on the instant petition to include the Administra-
tor’s order on reconsideration. This, however, raises the
question whether Northside should have amended its orig-
inal petition to reflect the Administrator’s order on recon-
sideration. In our opinion, it was unnecessary for North-
side to have done so. As noted above, § 704 permits the
sudicial review and administrative reconsideration of an
agency’s order to occur simultaneously. Once our jurisdic-
tion has been properly invoked by a petition for review,
it makes little sense to require an amendment to the peti-
tion to preserve that jurisdiction only because the agen-
cy has ruled on the motion for reconsideration. In North
American Telecommunications Association v. FCC, 751
F.2d 207, 209 (7th Cir. 1984) (per curiam), we noted “{tJhe
presumption in favor of judicial reviewability of agency
action . . . (on which, see, e.g., Abbott Laboratories v.

3 continued

fects of Northside’s hazardous waste disposal on the water sup-
ply of the City of Indianapolis. Thus, the need for “prompt deci-
sionmaking procedures” is especially strong in the instant case.
In addition, under the statutory provisions relevant here, unlike
those cases cited in Arch Mineral, there is no prescribed period
in which the agency must pass upon a motion for reconsideration.
See, e.g., 49 U.S.C. § 10322(gX2). In theory then, the wait for ad-
ministrative action on a motion for reconsideration could be in-
definite. Nor are we faced with a case in which a motion for recon-
sideration is the only available channel to present matters of
general importance for plenary consideration by, for example, the
entire Interstate Commerce Commission (as opposed to inferior
panels). See B.J. McAdams v. ICC, 551 F.2d 1112, 1114-15 (8th
Cir. 1977).

A-33

Gardner, 387 U.S. 136, 140, (1967)), implies to us that pro-
cedural rules should not lightly be interpreted to prevent
a party from obtaining judicial review.” We noted also
that “the action of this court in accepting the transfer
of the petition from [another federal circuit] may have
lulled NATA [the petitioning party] into thinking that it
had not filed its notice of appeal prematurely.” Jd. Our
action in ordering that the Administrator’s motion seek-
ing to amend the scope of the administrative record be
considered with the merits of Northside’s petition might
have “lulled” Northside into thinking that its petition need
not be amended to reflect that order to sustain our juris-
diction. Insofar, then, the reasoning of Citizens State Bank
is equally applicable here. Cf. Bernstein v. Lind-Waldock
& Co., 738 F.2d 179, 182-83 (7th Cir. 1984); Textor v.
Board of Regents, 711 F.2d 1387, 1390-91 (7th Cir. 1983).

B. Standing and Ripeness

Northside asks this court to “reverse .. . [the Admin-
istrator’s order denying review], . . . the Region’s per-
mit denial, {and the] interim status . . . and closure deter-
mination[s], . . . and [to} order . . . [the Administrator]

to hold a formal evidentiary hearing on said permits and
closure, utilizing t

[Text truncated at 120,000 characters. The full text is on the page linked above.]

---

Source: Frix Law Library, https://www.frixlaw.com/law-library/documents/brief%3Amicro_IA40385002_0626%3A1. Public record. Not legal advice.
