# Brief for the Respondent in Opposition — Ranieri v. United States

> Briefs, arguments, decisions, and more.

URL: https://www.frixlaw.com/law-library/documents/brief%3Amicro_IA34086415_1331%3A2

## Record

- **Collection:** Supreme Court brief
- **Document type:** Brief for the Respondent in Opposition
- **Published:** January 1, 1942
- **Citation:** 317 U.S. 690

## Text

4
y + y I
INDEX H
Serene {
Page
Opinion below ’ : 1
Jurisdiction ]
Questions presented 2
Statement of facts 9 4
Argument 7
Conclusion 31 é
CITATIONS }
Cases:
Hollerbach v. United States, 233 U.S. 165 13 i
United States y. Atlantic Dredging Co., 253 U.S. 1 ; 13 ’
United States v. Rice and Burton, No. 31, decided Nov. 9, 1942. 13 i
(1) it
iH
ri
i
i}
i

[AIT AIR AOS AEA DI! TAT TREE NANT LI

Inthe Supreme Court of the United States

OcrospeR TeRM, 1942

No. 463

ALEX RANIERI, PETITIONER
Vv.

THe Unirep Srates

ON PETITION FOR WRIT OF CERTIORARI TO THE COURT
OF CLAIMS

BRIEF FOR THE UNITED STATES IN OPPOSITION

OPINION BELOW
The opinion of the Court of Claims (R. 38-42)
is not yet officially reported.
JURISDICTION
The judgment of the Court of Claims was en-
tered February 2, 1942 (R. 42). A motion for
anew trial was overruled June 1, 1942 (R. 43).
On June 29, 1942, the time within which to file
the petition for writ of certiorari was extended
by order of the Chief Justice to October 29, 1942
(R. 57). The petition for writ of certiorari was
filed October 17, 1942 (R. 58). The jurisdiction
of this Court was invoked under Section 3(b) of
(1)

2

the Act of February 13, 1925, as amended by the
Act of May 22, 1939.

QUESTIONS PRESENTED

1. Whether there is lack of substantial evidence
to sustain certain findings of fact made by the
Court of Claims; whether ultimate findings of
fact of the court are inconsistent with the evi-
dentiary or primary findings; and whether the
court failed to make findings of fact on the mate-
rial issues.

2. Whether, under a contract calling for the
construction of a levee by petitioner, the United
States undertook to furnish petitioner clean earth,
free from all foreign matter which would not
slough or show a tendency to do so and be of the
best grade, or whether it merely agreed to make
earth available out of which petitioner was re-
quired to select the proper type for the construc-
tion of the levee.

3. Whether the United States made any mate-
rial misrepresentation as to the character of earth
available or as to the subsoil conditions which
existed in the borrow pits from which petitioner
was required to take the soil with which to con-
struct the levee.

STATEMENT OF FACTS

This case involves a suit by petitioner against
the United States for the recovery of $258,880.49
claimed to be due on account of construction work

-

3

(R. 1-8). The United States filed a special an-
swer denying the sum was due (R. 8-12) and a
counterclaim for $37,653.20 (R. 12-15).

The facts as found by the Court of Claims (R.
30-38) and as shown by the evidence may be sum-
marized as follows:

Petitioner and the United States entered into
a contract dated October 12, 1931, whereby for a
consideration of 12.4 cents per cubie yard peti-
tioner agreed to “furnish all labor and materials,
and perform all work required for the construc-
tion of Item R 831, Chamberlain-Lobdell Levee,
Lots A, B, C, and D, containing approximately
two million nine hundred and fifty thousand
(2,950,000) yards, situated in the Atchafalaya
Front Levee District,’’ in accordance with speci-
fications, schedules, and drawings, all made part
of the contract (R. 30-31). The levee to be eon-
structed extended for a distance of about 22,000
feet (R. 31). The contract provided that work
was to be commenced on each of the four lots
within twenty calendar days after the date of re-
ceipt of notice to proceed and was to be completed
within 450 calendar days from the date of receipt
of such notice (R. 31). On October 30, 1931, peti-
tioner received notice to proceed, thereby fixing
the completion date as January 22, 1933 (R. 32).
Within the contract time petitioner comm.>nced
the preliminary work of clearing, grubbing, and
plowing. which required about one week’s time

Re ies,
Sa on
mieten

—

+

(R. 32). He commenced the placing of material
in the levee on lots A, B, C, and D, 103, 228, 298,
366 days, respectively, after the receipt of notice
to proceed (R. 32).

Under Section 13 of the specifications the Gov-
ernment agreed to furnish the right-of-way and
earth for the construction of the levee without
eost to the contractor (R. 16-17) and under Article
39 of the specifications the material for the work
was to be obtained from riverside borrow pits
and from the existing levee to the extent indicated
in the drawings which the court below found to
be 2,000 linear feet (R. 31). Paragraph 19 of
the specifications (R. 17) stated that the soil con-
ditions indieated that a B section was required
throughout.’ There was sufficient satisfactory ma-
terial in the borrow pits and in the available see-
tions of the old levee from which to construct a
B section (R. 50, 51, 52, 55), and the new levee
was eventually successfully constructed from these
sources (R. 31-32; 52).

Borings had been taken over the site of the pro-
posed levee at intervals of 1,000 feet each to a
depth of about 25 feet and a chart of these borings
appeared on the contract map (R. 31). The chart
classified the earth disclosed by the borings as
sandy loam, sandy clay, sand and loam, clay, loam,

1 A B section was described as having “a crown of 10 feet,
a riverside slope of 1 on 314, the landside slope as contain-

ing a seepage line of 1 on 614, and the governing material
as loam” (R. 31).

eo

5

sand and silt, clay and silt, brown clay, soft brown
clay and sand, soft blue clay, hard blue clay, and
soft brown clay (R. 31; 55). There was no evi-
dence to show that the borings were inaccurately
charted (R. 32).2. Prior to the submission of peti-
tioner’s bid he had been furnished the contract
map and specifications and his representatives
visited and inspected the site of the proposed
levee (R. 31; 46, 48).

The petitioner had no experience in building
levees (R. 31). In the course of the work, Gov-
ernment inspectors served 231 notices upon peti-
tioner of his departures from contract require-
ments, including the overdigging of borrow pits,
impounding water between partial fills, placing
wet materials and materials showing a tendency
to slough on the embankment, improper prepara-
tion of foundations, leaving the foundation base
wet, and digging inspection ditches to excess
of width and depths (R. 32; 52). The contracting
officer on numerous occasions called petitioner’s
attention to the harmful practices of like character
in which he was engaging (R. 33-34), directed
him to correct these practices, and advised him
that he would be held responsible for resulting
damage to the levee (R. 34-36).

On September 15, 1932, the contracting officer
notified petitioner in writing that the progress of

? The evidence conclusively established that the material

actually encountered corresponded closely to that disclosed
by the bori: gs (R. 55).

—_——a LIBRO LONE IM LOLS LAT TS

6

the work was unsatisfactory and demanded the
use of additional equipment. On October 14,
1932, he repeated these demands, pointing out the
harmful practices in which petitioner was en-
gaged, and advising petitioner the embankment
already installed was not considered entirely sat-
isfactory for completion and that no further
partial payments would be made for incomplete
embankments on Lots A and B (R. 34-35). At no
time did petitioner appeal from the decision of
the contracting officer to the Secretary of War (R.
36). On December 12, 1932, petitioner ceased
work on the project and by letter advised the con-
tracting officer that it elected to rescind the con-
tract, contending that subsurface or latent condi-
tions at the site differed materially from those
represented in the plans and specifications (R. 36),
On that date petitioner had completed about 45
percent of the required work and had exhausted
about 91 percent of the contract time (R. 37).
The contracting officer replied on December 14,
1932, denying the right of petitioner to rescind
the contract and demanding resumption of opera-
tions (R. 36). Operations were not resumed and
the contracting officer, on January 3, 1933, termi-
nated the petitioner’s right to proceed under
Article 9 of the contract (R. 36-37). The work
remaining to be done was relet by advertisement
to other contractors who successfully completed
the work at an excess cost to the government of

‘ii
2 na

Z ies eo

7

$108,995.71 (R. 37-38). At the time petitioner
abandoned work there was retained the sum of
$71,342.51 making the net excess cost to the
United States of completing the levee $37,653.20
(R. 38).

The Court of Claims made an ultimate finding
that plaintiff could have satisfactorily completed
the work in the agreed time with the material
available and that his failure to do so was
due to his own fault and negligence, to delay on
his part in getting started in the actual handling
of levee material, to his violation of the terms of
the contract, and to unsound practices in the
handling of material (R. 37).

After making the foregoing findings of fact the
court directed that the petition be dismissed and
entered judgment for the United States on its
counterclaim in the sum of $37,653.20 (R. 42).
Petitioner’s motion for a new trial was overruled
(R. 43).

ARGUMENT

Petitioner contends that the court below made
findings of fact which were not supported by evi-
dence, that evidentiary findings of fact are in-
consistent with its ultimate findings of fact, and
that it failed to make findings of fact in respect
of material issues. Petitioner also contends that
under the terms of the contract and specifications
the United States undertook to furnish him clean
earth, free of all foreign matters, which would not

8

slough or show a tendency to slough and would be
of the best grade. Finally, he contends that the
Government misrepresented the working condi-
tions which would be encountered at the site of
the construction of the levee. We submit that
these contentions raise no substantial issue and
are without merit.

1. The finding that sufficient satisfactory soil
was available for the construction of the levee was
correct. The evidence disclosed that there was
suitable material with which to construct a B see-
tion levee of which the governing material is loam
(R. 55). The uncontradicted testimony of the
government expert discloses that loam is a mix-
ture of earth containing less than 30 percent of
clay particles and less than 80 percent of sand
particles (R. 55). Clearly there was enough clay
and sand available to furnish suitable material
for this type of construction * (R. 55). Moreover
a subsequent contractor was able to complete the
building of the levee (R. 51) ; the levees adjoining
at both ends the one here in controversy were
completed within the contract time and without
difficulty (R. 52); and witnesses testified that the
work could have been performed within contract
time (R. 50, 52).

’ The presence of a large amount of clay (buckshot) would
permit the construction of a B section since buckshot is suit-
able even for the construction of an A section, the sidewalls

of which have a sharper angle than a B section (Specifica-
tion 19, R. 17; 50).

9

Petitioner also contends that it was entitled to
a finding that all the material supplied was wet and
showed a tendency to slough. The record, however,
discloses that this condition of the material was
brought about by the faulty methods of construe-
tion employed by petitioner (R. 34-35, 53). Any
type of soil if allowed to become sufficiently im-
pregnated with water will become wet and if im-
properly handled it will show a tendency to slough
(R. 52-53). Rains and seepage were common oc-
eurrences in the part of the country where pe-
titioner undertook to construct the levee. It was
his duty to provide adequate drainage to minimize
the water content and to handle his material in
such a manner as to reduce the possibility of
sloughing to a minimum (R. 34-35, 52-53). This
he did not do. The fact that other contractors
completed their work out of the material at hand
(R. 51, 52) and that the expert witnesses testified
that the work could be completed with the material
available (R. 50, 52) warranted the court below
in refusing to make the finding to which petitioner
claims he is entitled.

The evidentiary facts found by the court below
are not inconsistent with its ultimate findings in
respect of the character of the earth. The evi-
dentiary findings were to the effect that the pe-
titioner unnecessarily permitted material to become
wet and placed wet soil and soil which had a tend-
ency to slough in the levee (R. 32-35). Such find-

inns

RUROINI CAT Odi

10

ings, however, relate to the manner in which pe-
titioner performed his work. They plainly are not
inconsistent with the ultimate findings that there
was material which was satisfactory (R. 37).

Petitioner was not therefore entitled to his re-
quested findings,‘ and the findings of the court
below to which he excepts are all supported by
adequate evidence.’

2. Petitioner erroneously contends that the
United States agreed to furnish him with earth
for the construction of the levee which should be
‘clean earth, free from all foreign matter, which
would not slough or show a tendency to do so and
be of the best grade.’’ The United States under-
took, by Paragraph 13 of the specifications, only
to furnish without cost to the contractor the right-
of-way and earth for constructing the leevee (R.
16-17). Article 7 of the contract provides that
all workmanship, equipment, materials, and ar-

‘If it were material petitioner might have been entitled to
a finding that he encountered cypress stumps in the borrow
pits. Such a finding, however, would necessarily have to be
coupled with a further finding that the presence of cypress
stumps in borrow pits was common occurrence (R. 50, 53)
which should have been expected and that their presence was
not such as to interfere with the successful conclusion of the
work (R. 53). Accordingly, the failure of the court to make
a finding in this respect is immaterial since the conclusion
cannot be affected by it.

‘In the statement of facts, supra, record references to the
evidence which supports the findings of the court below are

given in addition to the record references of the findings
themselves.

11

ticles incorporated in the work covered by the
contract are to be of the best grade of their
respective kinds for the purpose (R. 24). Clearly
this was an obligation placed upon the contractor
and not one assumed by the United States. See-
tion 22a of the specifications which set forth the
manner in which the contractor should construct
the embankment provided that the contractor
should use clean earth free from all foreign mat-
ter in constructing the levee and that no earth
which sloughs or shows a tendency to slough shall
be placed in the embankment (R. 17-18). These
also clearly are obligations which were placed
upon the contractor whose duty it was to select
from the material at hand, which the United
States undertook to furnish, suitable material. As
the court below found (R. 37), there was suitable
material available for the construction of the
levee, and the failure of the petitioner to select
that material, not the failure of the United States
to provide such material, caused petitioner’s
losses.

3. Petitioner’s contention that the United
States misrepresented the character of the soil to
be encountered and the working conditions is with-
out merit. At intervals of 1,000 feet along the
base of the levee borings were taken to disclose
the character of the material present (R. DD).
As the court below found (R. 32) these borings
were accurately charted and properly reflected
the condition of the soil to be encountered. There

SR Ren NO RE My oe IN a

12

was no obligation on the part of the United States
to take any borings at all, and having taken the
borings its sole duty, which it fulfilled (R. 31), was
to make available to the contractor the informa-
tion which it had obtained. Moreover, there was
no misrepresentation of any material facts by any
failure of the Government to disclose facts of
which it had notice. Whether cypress stumps
would be encountered was a matter which the
contractor was as capable of anticipating as the
Government officials. Although there is testimony
to indicate that the character of the vegetation
erowing on the borrow pits was sufficient to warn
of the fact that there may have been an under-
lying eypress swamp (R. 50), other evidence
would support a finding that no one could know
if cypress stumps were present (R. 51). In
either aspect, however, petitioner was placed upon
the same notice as were the officers of the United
States. The prevalence of rainfall and the fact
that drainage might have to be maintained were
a notorious fact which was open for all to see. It
was a condition reasonably to be expected and
po duty existed on the part of the government
io call it to the bidder’s attention, Nor was
there a warranty by the United States of the
working conditions which would be encountered.
Only where the United States either represents
itself as having knowledge which it does not
possess or fails to convey information as to hidden
conditions which it does possess is it held to war-

13

rant subsoil conditions. Jollerbach v. United
States, 233 U. 8. 165, 172; United States v. At-
lantic Dredging Co., 253 U.S. 1, 10-11.

Even assuming that subsoil or latent conditions
existed which neither party to the contract had
in contemplation, it was the duty of the contractor
under Article IV of the contract (R. 23-24) to
proceed with the work and seek an equitable ad-
justment under Article IIT (R. 23) for the in-
creased costs of the work. But petitioner did not
seek his remedy by the procedure thus prescribed
but imstead sought to rescind the contract when
he became dissatisfied with working conditions
(R. 36). He is not now entitled to the benefits
of clauses in the contract with which he failed
tocomply. See United States v. Rice and Burton,
No. 31, decided November 9, 1942.

CONCLUSION

The decision below is correct. We respectfully
submit therefore that the petition for a writ of
certiorari should be denied.

CHARLES Fauy,
Solicitor General.
Francis M. Sura,
Assistant Attorney General.
D. L. Krercer,
Pau A. SWEENEY,

Attorneys.
DECEMBER 1942.