sroberts on PROD1PC70 with NOTICES

Federal Register / Vol. 71, No. 151 / Monday, August 7, 2006 / Notices
public.referenceroom@ferc.gov. The
draft EIS also may be viewed on the
Commission’s Web site at http://
www.ferc.gov under the eLibrary link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC Online
Support at
FERCOnlineSupport@ferc.gov or tollfree at 1–866–208–3676, or for TTY,
(202) 502–8659.
CD versions of the draft EIS have been
mailed to everone on the mailing list for
the project. Copies of the CD, as well as
a limited number of paper copies, are
available from the Public Reference
Room identified above.
You may also register online at
http://www.ferc.gov/docs-filing/
esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
Comments should be filed with
Magalie R. Salas, Secretary, Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426.
All comments must be filed by October
3, 2006, and should reference Project
No. 1971–079. Comments may be filed
electronically via the Internet in lieu of
paper. The Commission strongly
encourages electronic filings. See 18
CFR 385.2001(a)(1)(iii) and instructions
on the Commission’s Web site at
http://www.ferc.gov under the eLibrary
link.
Anyone may intervene in this
proceeding based on this draft EIS (18
CFR 380.10). You must file your request
to intervene as specified above.1 You do
not need intervenor status to have your
comments considered.
In addition to or in lieu of sending
written comments, you are invited to
attend public meetings that will be held
to receive comments on the draft EIS.
Two meetings have been scheduled for
Thursday night, September 7, and
Friday morning, September 8, 2006, in
Boise, Idaho. Details of these public
meetings, and other meetings yet to be
scheduled, will be included in a
separate notice, as well as posted on the
Commission’s Web site (www.ferc.gov).
For further information, contact Alan
Mitchnick at (202) 502–6074,
alan.mitchnick @ferc.gov; or Emily
1 Interventions may also be filed electronically via
the Internet in lieu of paper. See the previous
discussion on filing comments electronically.

VerDate Aug<31>2005

17:19 Aug 04, 2006

Jkt 208001

Carter at (202) 502–6512,
emily.carter@ferc.gov.
Magalie R. Salas,
Secretary.
[FR Doc. E6–12717 Filed 8–4–06; 8:45 am]
BILLING CODE 6450–01–P

DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP06–412–000]

Puget Sound Energy, Inc., Notice of
Intent To Prepare an Environmental
Assessment for the Proposed Jackson
Prairie Storage Deliverability
Expansion Project, Request for
Comments on Environmental Issues
July 28, 2006.

The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Jackson Prairie (JP) Storage
Deliverability Expansion Project
involving abandonment, construction,
and operation of facilities by Puget
Sound Energy, Inc. (Puget) in Lewis
County, Washington.1 The Commission
will use the EA in its decision-making
process to determine whether or not to
authorize the project. This notice
announces the opening of the scoping
period that will be used to gather
environmental input from the public
and interested agencies on the project.
Your input will help us determine the
issues that need to be evaluated in the
EA. Please note that the scoping period
will close on August 28, 2006.
This notice is being sent to potentially
affected landowners; Federal, State, and
local government agencies; elected
officials; environmental and public
interest groups; Native American Tribes,
other interested parties; local libraries
and newspapers. State and local
government representatives are asked to
notify their constituents of this planned
project and encourage them to comment
on their areas of concern.
A fact sheet prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility on My Land? What Do I Need
To Know?’’ is available for viewing on
the FERC Web site (www.ferc.gov). This
fact sheet addresses a number of
typically asked questions, including the
use of eminent domain and how to
participate in the Commission’s
proceedings.
1 Puget’s application was filed with the
Commission under section 7 of the Natural Gas Act
and part 157 of the Commmission’s regulations.

PO 00000

Frm 00079

Fmt 4703

Sfmt 4703

44683

If you are a landowner receiving this
notice, you may be contacted by a Puget
representative about the acquisition of
an easement to construct, operate, and
maintain the proposed facilities. The
pipeline company would seek to
negotiate a mutually acceptable
agreement. However, if the project is
approved by the Commission, that
approval conveys with it the right of
eminent domain. Therefore, if easement
negotiations fail to produce an
agreement, the pipeline company could
initiate condemnation proceedings in
accordance with state law.
Summary of the Proposed Project
Puget is seeking authorization to
design, construct, operate, and maintain
the following new facilities at the
existing JP Storage Field in Lewis
County, Washington:
• Up to ten new withdrawal/injection
wells with associated well connect
pipeline;
• About 0.8 mile of new 24-inchdiameter pipeline to loop a portion of
the existing gathering system;
• One new 10,480-horsepower (hp)
compressor unit at the existing JP
Compressor Station; and
• Upgrades and auxiliary facility
additions at both the JP Compressor
Station (total 1,551 hp increase) and JP
Meter Station.
Puget also requests to abandon
various facilities that would be replaced
by the proposed upgraded facilities.
The existing JP Storage Field
interconnects with Northwest Pipeline
Corporation’s transmission system
which provides natural gas supplies to
markets in the Pacific Northwest.
Puget’s proposed new and upgraded
facilities would allow it to increase
maximum firm withdrawal
deliverability of the JP Storage Field
from 850 million cubic feet per day
(MMcfd) to 1,150 MMcfd. Puget is
expected to commence construction for
the drilling of up to five of the new
wells and installation of associated well
connect lines in the spring of 2007.
Production rate tests on the initial wells
would be conducted to help determine
the minimum number of wells required
to achieve the desired 300 MMcfd. The
remaining facilities are anticipated to be
constructed in 2008.
The general location of Puget’s
proposed facilities is shown on the map
attached as Appendix 1.2
2 The appendices referenced in this notice are not
being printed in the Federal Register. Copies of this
notice, other than appendix 1 (maps), are available
on the Commission’s Web site at the ‘‘eLibrary’’ link
or from the Commission’s Public Reference Room,
888 First Street, NE., Washington, DC 20426, or call

E:\FR\FM\07AUN1.SGM

Continued

07AUN1

44684

Federal Register / Vol. 71, No. 151 / Monday, August 7, 2006 / Notices

Land Requirements for Construction
Puget states that all of the proposed
activities associated with this project
would occur on private lands owned or
leased by the JP Storage Field. About
29.66 acres of land would be affected
during construction and about 22.23
acres would be permanently maintained
for operation of the proposed facilities.
Six of the new withdrawal well sites
would be located on new graveled well
pads covering an area of 150 feet by 250
feet for drilling operations; the
remaining four well sites would be colocated on two new graveled well pads
which would require an area of 150 feet
by 300 feet.
The new 24-inch loop gathering line
would be constructed within a 90-footwide right-of-way (ROW); and Puget is
proposing to maintain a 75-foot-wide
permanent ROW along the pipeline
route. The total surface disturbance for
the well connect lines and well pads
would require about 12.22 acres. These
new well connect lines would range
from 6- to 10-inch-diameter pipeline
and would tie-in to the JP gathering line.
Puget would generally use established
access roads; however, one new access
road would need to be constructed and
improvements on an existing two-track
road would be necessary. Most
modifications to the JP Compressor
Station would occur within the station
boundaries; however, the station would
need to be expanded 0.51 acre to
accommodate the new gas coolers. All
of the modifications to the JP Meter
Station would occur within the existing
footprint. The existing Chehalis
Compressor Station, which is about 2
miles southwest of the JP Storage Field,
would be used as a pipe storage yard for
the project.

sroberts on PROD1PC70 with NOTICES

The EA Process
We 3 are preparing the EA to comply
with the National Environmental Policy
Act (NEPA) which requires the
Commission to take into account the
environmental impacts that could result
from an action whenever it considers
the issuance of a Certificate of Public
Convenience and Necessity. NEPA also
requires us to discover and address
concerns the public may have about
proposals. This process is referred to as
‘‘scoping’’. The main goal of the scoping
process is to focus the analysis in the
EA on the important environmental
issues. By this Notice of Intent, the
(202) 502–8371. For instructions on connecting to
eLibrary refer to the last page of this notice. Copies
of the appendices were sent to all those receiving
this notice in the mail.
3 ‘‘We’’, ‘‘us’’, and ‘‘our’’, refer to the
environmental staff of the Office of Energy Projects
(OEP).

VerDate Aug<31>2005

17:19 Aug 04, 2006

Jkt 208001

Commission staff requests public
comments on the scope of the issues to
address in the EA. All comments
received are considered during the
preparation of the EA.
By this notice, we are also asking
Federal, State, and local agencies with
jurisdiction and/or special expertise
with respect to environmental issues to
formally cooperate with us in the
preparation of the EA. Agencies that
would like to request cooperating status
should follow the instructions for filing
comments below (see Public
Participation).
Our independent analysis of the
issues will be in the EA. Depending on
the comments received during the
scoping process, the EA may be
published and mailed to Federal, State,
and local agencies, public interest
groups, interested individuals, affected
landowners, newspapers, libraries, and
the Commission’s official service list for
this proceeding. A comment period will
be allotted for review if the EA is
published. We will consider all
comments on the EA before we make
our recommendations to the
Commission.
Currently Identified Environmental
Issues
In the EA, we will discuss impacts
that could occur as a result of the
construction and operation of the
project. We will also evaluate possible
alternatives to the proposed project or
portions of the project.
We have already identified some
issues that we think deserve attention
based on a preliminary review of the
proposed facilities and the
environmental information provided by
Puget. This preliminary list of issues
may be changed based on your
comments and our analysis.
• Potential impacts on local Noise
Quality associated with construction
and operation.
• Potential impacts on Water Use and
Quality.
• Potential impacts on Land Use from
a 75-foot-wide permanent ROW.
Public Participation
You can make a difference by
providing us with your specific
comments or concerns about the project.
By becoming a commentor, your
concerns will be addressed in the EA
and considered by the Commission. You
should focus on the potential
environmental effects of the proposal,
alternatives to the proposal (including
alternative locations and routes), and
measures to avoid or lessen
environmental impact. The more
specific your comments, the more useful

PO 00000

Frm 00080

Fmt 4703

Sfmt 4703

they will be. Please carefully follow
these instructions to ensure that your
comments are received in time and
properly recorded:
• Send an original and two copies of
your letter to: Magalie R. Salas,
Secretary, Federal Energy Regulatory
Commission, 888 First St., NE., Room
1A, Washington, DC 20426.
• Label one copy of the comments for
the attention of Gas Branch 1.
• Reference Docket No. CP06–412–
000.
• Mail your comments so that they
will be received in Washington, DC on
or before August 28, 2006.
Please note that the Commission
strongly encourages electronic filing of
any comments or interventions or
protests to this proceeding. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site at
http://www.ferc.gov under the ‘‘eFiling’’ link and the link to the User’s
Guide. Before you can file comments
you will need to create an account
which can be created on-line.
Becoming an Intervenor
In addition to involvement in the EA
scoping process, you may want to
become an official party to the
proceeding known as an ‘‘intervenor’’.
Intervenors play a more formal role in
the process. Among other things,
intervenors have the right to receive
copies of case-related Commission
documents and filings by other
intervenors. Likewise, each intervenor
must send one electronic copy (using
the Commission’s e-Filing system) or 14
paper copies of its filings to the
Secretary of the Commission and must
send a copy of its filings to all other
parties on the Commission’s service list
for this proceeding. If you want to
become an intervenor you must file a
motion to intervene according to Rule
214 of the Commission’s Rules of
Practice and Procedure (18 CFR
385.214).4 Only intervenors have the
right to seek rehearing of the
Commission’s decision.
Affected landowners and parties with
environmental concerns may be granted
intervenor status upon showing good
cause by stating that they have a clear
and direct interest in this proceeding
which would not be adequately
represented by any other parties. You do
not need intervenor status to have your
environmental comments considered.
Additional Information
Additional information about the
project is available from the
4 Interventions may also be filed electronically via
the Internet in lieu of paper. See the previous
discussion on filing comments electronically.

E:\FR\FM\07AUN1.SGM

07AUN1

Federal Register / Vol. 71, No. 151 / Monday, August 7, 2006 / Notices
Commission’s Office of External Affairs,
at 1–866–208–FERC or on the FERC
Internet Web site (www.ferc.gov) using
the eLibrary link. Click on the eLibrary
link, click on ‘‘General Search’’ and
enter the docket number excluding the
last three digits in the Docket Number
field. Be sure you have selected an
appropriate date range. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll
free at 1–866–208–3676, or for TTY,
contact (202) 502–8659. The eLibrary
link also provides access to the texts of
formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission now
offers a free service called eSubscription
which allows you to keep track of all
formal issuances and submittals in
specific dockets. This can reduce the
amount of time you spend researching
proceedings by automatically providing
you with notification of these filings,
document summaries and direct links to

the documents. Go to www.ferc.gov/
esubscribenow.htm.
Magalie R. Salas,
Secretary.
[FR Doc. E6–12722 Filed 8–4–06; 8:45 am]
BILLING CODE 6450–01–P

DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Docket No. PF06–28–000

Southeast Supply Header, LLC; Notice
of Intent To Prepare an Environmental
Impact Statement for the Proposed
Southeast Supply Header Project,
Request for Comments on
Environmental Issues, and Notice of
Public Scoping Meetings
July 28, 2006.

The staff of the Federal Energy
Regulatory Commission (FERC or

Commission) will prepare an
environmental impact statement (EIS)
that will identify and address the
environmental impacts that could result
from the construction and operation of
the Southeast Supply Header Project
proposed by Southeast Supply Header,
LLC (SESH) a partnership between Duke
Energy Gas Transmission and
CenterPoint Gas Transmission.
In order to assist staff with the
identification of environmental issues
and to comply with the requirements of
the National Environmental Policy Act
of 1969 (NEPA), a thirty day scoping
period has been opened to receive
comments on the proposed project.
Please note that the scoping period for
this project will close on August 28,
2006.
Additionally, as part of the scoping
process, we will also hold three public
meetings, as described below, to receive
comments on the proposed project.

Date and time

Location

Monday—August 21, 2006, 7 p.m. to 9 p.m. (CST) ..........

Multipurpose Building in Gallman, West Gallman Road, Gallman, Mississippi, Telephone: (601) 953–9007.
Hattiesburg Lake Terrace, Convention Center, One Convention Center Plaza, Hattiesburg, Mississippi 39042, Telephone: (800) 638–6877.
Lucedale Rocky Creek Inn, 120 Woods Ridge Road, Lucedale, Mississippi 39452,
Telephone: (601) 947–6900.

Tuesday—August 22, 2006, 7 p.m. to 9 p.m. (CST) .........
Thursday—August 24, 2006, 7 p.m. to 9 p.m. (CST) .......

sroberts on PROD1PC70 with NOTICES

44685

This notice is being sent to affected
landowners; federal, state, and local
government agencies; elected officials;
environmental and public interest
groups; Native American tribes; other
interested parties; and local libraries
and newspapers; all of which are
encouraged to submit comments on the
proposed project. Details on how to
submit comments are provided in the
Public Participation section of this
notice.
If you are a landowner receiving this
notice, you may be contacted by a SESH
representative about the acquisition of
an easement to construct, operate, and
maintain the proposed project facilities.
The pipeline company would seek to
negotiate a mutually acceptable
agreement. However, if the project is
approved by the FERC, that approval
conveys with it the right of eminent
domain. Therefore, if easement
negotiations fail to produce an
agreement, the pipeline company could
initiate condemnation proceedings in
accordance with state law.
A fact sheet prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility on My Land? What Do I Need
To Know?’’ is available for viewing on
the FERC Internet Web site

VerDate Aug<31>2005

17:19 Aug 04, 2006

Jkt 208001

(www.ferc.gov). This fact sheet
addresses a number of typically asked
questions, including the use of eminent
domain and how to participate in the
FERC’s proceedings.
Summary of the Proposed Project
SESH proposes to construct, own and
operate a new 36-inch-diameter natural
gas pipeline and associated facilities
that would be capable of receiving and
transporting about 1.0 billion cubic feet
of natural gas per day in Richland and
Madison Parishes, Louisiana; Warren,
Claiborne, Hinds, Copiah, Simpson,
Lawrence, Jefferson Davis, Covington,
Jones, Forrest, Perry, Greene, George,
and Jackson Counties, Mississippi; and
Mobile County, Alabama.
The general location of the proposed
pipeline is shown in the figure included
as Appendix 1.1
Specifically, SESH proposes to
construct and operate the following
facilities:
• Approximately 270 miles of 36inch-diameter pipeline beginning in
Richland Parish, Louisiana and ending
in Mobile County, Alabama;
1 The appendices referenced in this notice are not
being printed in the Federal Register.

PO 00000

Frm 00081

Fmt 4703

Sfmt 4703

• Three natural gas compressor
stations: Delhi Compressor Station in
Richland Parish (30,000 hp), Louisiana;
Gwenville Compressor Station in
Jefferson Davis County, Mississippi
(15,000 hp) and the Lucedale
Compressor Station in George County,
Mississippi (15,000 hp);
• Three booster compressor stations
at the Texas Eastern Transmission LP
(TETLP) meter and regulation (M&R)
Station, at the Transcontinental Gas
Pipeline Corporation (Transco) M&R
Station, and at the Tennessee Gas
Pipeline Company (Tennessee Gas)
M&R Station in Copiah, Jefferson Davis
and Forrest Counties, Mississippi;
• Twelve natural gas pipeline
interconnects and M&R Stations; and
• Three pig launching and receiving
facilities and several mainline valves.
SESH proposes to have the project
constructed and operational by June
2008.
Land Requirements for Construction
As proposed, the typical construction
right-of-way for the project pipeline
would be 100 feet wide. Following
construction, SESH has proposed to
retain a 50-foot-wide permanent rightof-way for operation of the project.

E:\FR\FM\07AUN1.SGM

07AUN1

---