THIS OPINION WAS INITIALLY ISSUED UNDER PROTECTIVE ORDER AND
IS BEING PUBLICLY RELEASED IN ITS ENTIRETY ON SEPTEMBER 22, 2025

DISMISSED FOR FAILURE TO STATE A CLAIM: September 4, 2025

CBCA 8151, 8162, 8163

GDM A-E, INC.,
Appellant,
v.
DEPARTMENT OF VETERANS AFFAIRS,
Respondent.
Italia A. Carson, Polaris Law Group, P.C., North Pole, AK, counsel for Appellant.
Neil S. Deol, Office of General Counsel, Department of Veterans Affairs, Decatur,
GA; and Kathleen Ramos, Office of General Counsel, Department of Veterans Affairs,
Arlington, TX, counsel for Respondent.
Before Judges GOODMAN, KULLBERG, and KANG.
GOODMAN, Board Judge.
GDM A-E, Inc. (GDM or appellant) filed three appeals from the Department of
Veterans Affairs (VA or respondent) contracting officer’s (CO) final decisions (COFDs)
denying GDM’s certified claims concerning three contracts.1 These appeals were docketed

1

Appellant designated its notices of appeal, which were not paginated, as
complaints in the three appeals. References to page numbers in the complaints are to the

CBCA 8151, 8162, 8163

2

as CBCA 8151, CBCA 8162, and CBCA 8163. Respondent filed a motion to dismiss in each
of these appeals for failure to state a claim upon which relief may be granted, presenting
substantially similar legal issues across the motions.2 The Board consolidated the appeals
on August 27, 2025, pursuant to Board Rule 2(f) (48 CFR 6101.2(f) (2024)) and resolves the
three motions to dismiss in this decision.3 We grant respondent’s motions and dismiss these
consolidated appeals for failure to state a claim.
Background
The Solicitations and Contracts
The VA issued Requests for A/E [Architect-Engineer] Fee Proposals (solicitations)
pursuant to Federal Acquisition Regulation (FAR), part 36, Construction and ArchitectEngineering Contracts. The solicitations sought proposals to award contracts to A/E
contractors who would, in turn, design construction projects to attain goals associated with
Electronic Health Record Modernization (EHRM) projects. Respondent’s Motions to
Dismiss at 1.
For each solicitation, the VA prepared an independent government cost estimate
(IGCE), which was used to determine the VA’s estimated construction contract price (ECC
price) for the project that would be designed by the A/E contractor. Id.

PDF document filed, beginning with the transmittal cover. References to exhibits are to
appeal file exhibits.
2

The motions are substantially identical. References to page numbers in the
motions are to all three motions without identification of docket number, unless otherwise
indicated.
3

Appellant retained counsel after appellant’s chief executive officer filed the
notices of appeal and oppositions to respondent’s motions. “We construe a pro se litigant’s
pleadings liberally,” but such lenience does not affect “a pro se litigant’s burden of proof or
our [assessment] of the factual record.” House of Joy Transitional Programs v. Social
Security Administration, CBCA 2535, 12-1 BCA ¶ 34,991, at 171,975 (citing Haines v.
Kerner, 404 U.S. 519, 520 (1972); Greenlee Construction, Inc. v. General Services
Administration, CBCA 416, 07-1 BCA ¶ 33,514, at 166,062).

CBCA 8151, 8162, 8163

3

Each solicitation and awarded contract contained the Design Within Funding
Limitations clause (APR 1984), FAR 48 CFR 52.236-22 (2021) (FAR 52.236-22), which
included the ECC price for the project to be designed and reads as follows:
(a)

The Contractor shall accomplish the design services required under this
contract so as to permit the award of a contract, using standard Federal
Acquisition Regulation procedures for the construction of the facilities
designed at a price that does not exceed the estimated construction
contract price as set forth in paragraph (c) of this clause. When bids or
proposals for the construction contract are received that exceed the
estimated price, the contractor shall perform such redesign and other
services as are necessary to permit contract award within the funding
limitation. These additional services shall be performed at no increase
in the price of this contract. However, the Contractor shall not be
required to perform such additional services at no cost to the
Government if the unfavorable bids or proposals are the result of
conditions beyond its reasonable control.

(b)

The Contractor will promptly advise the Contracting Officer if it finds
that the project being designed will exceed or is likely to exceed the
funding limitations and it is unable to design a usable facility within
these limitations. Upon receipt of such information, the Contracting
Officer will review the Contractor’s revised estimate of construction
cost. The Government may, if it determines that the estimated
construction contract price set forth in this contract is so low that award
of a construction contract not in excess of such estimate is improbable,
authorize a change in scope or materials as required to reduce the
estimated construction cost to an amount within the estimated
construction contract price set forth in paragraph (c) below, or the
Government may adjust such estimated construction contract price.
When bids or proposals are not solicited or are unreasonably delayed,
the Government shall prepare an estimate of constructing the design
submitted and such estimate shall be used in lieu of bids or proposals
to determine compliance with the funding limitation.

(c)

The estimated construction contract price for the project described in
this contract is $ [amount of the contract].

CBCA 8151, 8162, 8163

4

CBCA 8151, Exhibit 15 at 15-16; CBCA 8162, Exhibit 9 at 13; CBCA 8163, Exhibit 20
at 18.
Veterans Affairs Acquisition Regulation (VAAR) 836.606-71, 48 CFR 836.606-71,
limited the A/E contractor’s fee to six percent of the ECC price specified in the contract. If
the Government changed the scope of work of the project to be designed by the A/E
contractor, the A/E contractor could request an equitable adjustment in its fee pursuant to the
Changes clause, FAR 52.243-1. CBCA 8151, Exhibit 15 at 18; CBCA 8162, Exhibit 9 at 15;
CBCA 8163, Exhibit 20 at 30.
The solicitation for the contract for the Togus, Maine, EHRM Infrastructure Upgrades
was issued on May 6, 2022. CBCA 8151. Appellant submitted a fee proposal, CBCA 8151,
Exhibit 14, and was awarded a firm-fixed price (FFP) A/E design services contract on
December 1, 2022, in the amount of $3,836,578.86 if all options were exercised (Togus
contract). CBCA 8151, Exhibit 15 at 7; Exhibit 7; Exhibit 30 at 1 (COFD). The contract
established an ECC price of $29,984,000. Id. at 16.
The solicitation for the contract for the Birmingham, Alabama, EHRM Infrastructure
Upgrades was issued on August 19, 2021. CBCA 8162, Exhibit 5. Appellant submitted a
fee proposal, CBCA 8162, Exhibit 7, and was awarded a FFP A/E design services contract
on September 27, 2021, in the amount of $1,350,185 (Birmingham contract), with an ECC
price of $16,503,365. CBCA 8162, Exhibit 9 at 5, 13. The total estimated award if all
options were exercised was $1,889,773. Id. at 5. Five modifications were issued, increasing
the contract price to $2,524,569.36. CBCA 8162, Exhibit 62 at 2 (COFD).
The solicitation for the contract for the Murfreesboro, Tennessee, EHRM
Infrastructure Upgrades was issued on August 30, 2022. CBCA 8163, Exhibit 14. Appellant
submitted a fee proposal, CBCA 8163, Exhibits 16, 19, and was awarded a FFP A/E design
services contract on January 31, 2023, in the amount of $2,858,918 (Murfreesboro contract).
CBCA 8163, Exhibit 20 at 7. The contract established an ECC price of $30,945,000. Id.
at 18.
Each solicitation and contract contained a list of attachments and/or attachments
comprised of several hundred pages, which included the statements of work, specifications,
site maps, and other contract requirements. Solicitation (CBCA 8151), Exhibit 7 (sixty-eight
pages with attachments listed but not included); Contract (CBCA 8151), Exhibit 15 (556
pages including attachments); Solicitation (CBCA 8162), Exhibit 5 (362 pages including
attachments); Contract (CBCA 8162), Exhibit 9 (344 pages including attachments);

CBCA 8151, 8162, 8163

5

Solicitation (CBCA 8163), Exhibit 14 (644 pages including attachments); Contract (CBCA
8163), Exhibit 20 (627 pages including attachments).
Claims and Appeals
For each of the three contracts, appellant submitted a certified claim pursuant to the
Contract Disputes Act (CDA), 41 U.S.C. §§ 7101–7109 (2018). On February 5, 2024,
appellant submitted a certified claim with regard to the Togus contract in the amount of
$2,513,128.14. On May 28, 2024, the CO issued a COFD denying the claim. On July 18,
2024, appellant filed a notice of appeal, docketed as CBCA 8151.
On January 22, 2024, appellant submitted a certified claim with regard to the
Birmingham contract in the amount of $456,455.58. On May 21, 2024, the CO issued a
COFD denying the claim. On July 29, 2024, appellant filed a notice of appeal, docketed as
CBCA 8162.
On June 24, 2024, appellant submitted a certified claim with regard to the
Murfreesboro contract in the amount of $1,052,936. On July 9, 2024, the CO issued a COFD
denying the claim. On July 29, 2024, appellant filed a notice of appeal, docketed as CBCA
8163.
Appellant attached to its notices of appeal its certified claims and requests for
equitable adjustments previously submitted to the COs.4 After appellant designated its
notices of appeal as complaints in the three appeals, respondent designated the COFD in
CBCA 8151 as its answer and, thereafter, filed a motion to dismiss the appeal. In
CBCA 8162 and CBCA 8163, respondent filed motions to dismiss in lieu of responsive
pleadings.
The complaints are substantially similar, including identical introductions:
The following documented cardinal change required GDM to perform duties
above and beyond those required by the solicitation and awarded contract for
which GDM is seeking—and rightfully owed—equitable compensation.

4

The same CO administered the Togus and Birmingham contracts, and a second
CO administered the Murfreesboro contract.

CBCA 8151, 8162, 8163

6

Complaint (CBCA 8151) at 3; Complaint (CBCA 8162) at 3; Complaint (CBCA 8163) at 3.
Appellant’s factual allegations and legal arguments in the complaints are included as
they relate to the issues in the discussion below.
Discussion
Appellant, an A/E contractor, after reviewing solicitations and submitting proposals,
was awarded three FFP contracts to design VA projects based upon the scope of work,
specifications, and the ECC prices in the contracts. The Design Within Funding Limitations
clause of the contracts required appellant to design the projects pursuant to the statements of
work, specifications, and other requirements that would then allow the VA to award
construction contracts that did not exceed the ECC prices. The ECC prices in the contracts
were the VA’s estimates of the prices for the construction contracts that would be eventually
awarded based on appellant’s designs. Appellant’s fee, under these FFP contracts, was
limited to six percent of the ECC price specified in the contract. The fee could be increased
if the scope of work of the project appellant designed was increased under circumstances
described in the Design Within Funding Limitations clause.
Appellant submitted certified claims for the contracts, alleging that the IGCEs upon
which the ECC prices were based were defective and did not reflect the complexities of the
projects to be designed. During performance of the contracts, appellant’s ECC prices for the
projects it designed exceeded the ECC prices specified in the contracts. Appellant advised
the COs as to the increase in the ECC prices and also that, as a result of its design efforts, the
number of design drawings it produced exceeded the number estimated in its proposals.
However, the COs did not revise the scopes of work of the projects being designed by
appellant or increase the contract ECC prices but directed appellant to continue to design the
projects within the scopes of work of its contracts. Appellant, therefore, asserts that the
continued directions to design under these circumstances were cardinal and constructive
changes, entitling it to compensation for the increased costs that it incurred in excess of the
FFPs for its contracts.
Standard of Review
Respondent has moved to dismiss the appeals for failure to state a claim upon which
relief may be granted, pursuant to Rule 8(e). The standard to resolve a motion to dismiss for
failure to state a claim is well established. The contractor must point to factual allegations
that, if true, would state a claim for relief that is plausible on its face when the Board draws

CBCA 8151, 8162, 8163

7

all reasonable inferences in favor of the contractor. B.L. Harbert International, LLC v.
General Services Administration, CBCA 6300, et al., 19-1 BCA ¶ 37,335, at 181,569. In
resolving respondent’s motions to dismiss, “[t]he Board decides legal issues, and may treat
any document that is incorporated in or attached to the complaint as part of the pleadings.”
Id. (citing Amec Foster Wheeler Environment & Infrastructure, Inc. v. Department of the
Interior, CBCA 5168, et al., 19-1 BCA ¶ 37,272, aff’d mem., 835 F. App’x 603 (Fed. Cir.
2021)).
Appellant’s Complaints
Respondent states that, “[i]n this matter, Appellant’s Complaint references the
Solicitation as well as the certified claim, which claim references the awarded Contract. As
such, both the Solicitation and Contract are appropriate to review in the context of a Motion
to Dismiss.” Motion to Dismiss (CBCA 8151) at 4; Motion to Dismiss (CBCA 8162) at 3-4;
Motion to Dismiss (CBCA 8163) at 4. We consider appellant’s notices of appeal designated
as complaints and all attachments to determine whether the complaint can survive the motion
to dismiss for failure to state a claim. Strawberry Hill, LLC v. General Services
Administration, CBCA 5149, 16-1 BCA ¶ 36,561, at 178,063-64 (citing Systems
Management & Research Technologies Corp. v. Department of Energy, CBCA 4068, 15-1
BCA ¶ 35,976, at 175,789).
Failure to State a Claim
Despite the allegations in the claims and complaints, appellant has not asserted factual
allegations that, if true, would state a claim for relief. Even when the Board draws all
reasonable inferences in favor of the contractor, appellant has failed to state a claim in the
three, now consolidated, appeals, as described herein.
Allegations of Defective IGCEs and Contract ECC Prices
Appellant alleges that the VA utilized inappropriate parametric estimating, rather than
typical standards of preliminary cost estimating, to calculate the IGCEs that were used as the
basis for the ECC prices included in the solicitations and contracts upon which, in turn, its
FFP fees were based. Appellant asserts that the resulting ECC prices violated an implied
warranty of the Government to supply accurate information, with appellant emphasizing that
“A/E firms rightfully assume that the VA has reviewed and understand[s] the complexities
of the scope of work, schedule, and site-specific features and has provided a reasonably

CBCA 8151, 8162, 8163

8

accurate estimated construction contract price and design funding limitation.” Complaint
(CBCA 8153) at 4; Complaint (CBCA 8162) at 4; Complaint (CBCA 8163) at 5.
Appellant also alleges:
The design limitation provides the A/E with an understanding of how the VA
has interpreted the risks, magnitude, and complexities of the design along with
underlying assurances that the VA has accurately reflected the costs of the
future construction project.
....
The accepted Fee Proposal was based on a defective estimate in the form of
the stated design limit, and the VA benefitted from all the additional design
work.
Complaint (CBCA 8153) at 8; Complaint (CBCA 8162) at 7; Complaint (CBCA 8163) at 6-7
(with editorial variations).
Case law does not support appellant’s assertions that an ECC price in a solicitation
or contract is a warranty of accurate information such that it represents the VA’s
determination of the ECC price of the project that will be designed by the A/E contractor.
In Acres American, Inc., ASBCA 27743, 85-1 BCA ¶ 17,865, an A/E contractor under a
similar contract, which also contained the Design Within Funding Limitations clause, alleged
that the ECC price had been negligently prepared and sought an increase in the contract price
for designing a project in excess of the ECC price. In that case, the Armed Services Board
of Contract Appeals (ASBCA) acknowledged that, in some circumstances, government
estimates have been held to have been negligently prepared when the Government’s
estimator fails to consider reasonably available information. Id. at 89,437. However, in the
case of an ECC price in an A/E contract, the ASBCA concluded that:
[T]he Government construction limitation [ECC price] is not a normal
construction estimate because it depends on the design to be developed by the
[A/E firm] under the contract for which the fee negotiations were being
conducted.
....

CBCA 8151, 8162, 8163

9

We need not decide whether the Government’s construction limitation was
negligently prepared because we find that it is not the type of estimate or
opinion upon which a contractor could reasonably rely. Statements of opinion
are those where different points of view are to be expected. Restatement of
Contracts, Second, § 168, comment a. at 456. Predictions of the cost to
construct a project not yet designed clearly fit this definition.
Id. at 89,437 (emphasis added).
In the Acres American decision, the ASBCA explained that when a contract’s ECC
price reflects a design that is to be developed by the A/E firm, “the subject matter of the
transaction is one on which the two parties have roughly equal skill and judgment, each must
generally form his own opinions and neither is justified in relying on the other’s.” Acres
American, 85-1 BCA at 89,437-38 (quoting Restatement (Second) of Contracts § 169 cmt.
b (1981)). The exceptions to this general rule are: (1) the Government has superior
knowledge of facts not reasonably available to the recipient; (2) the Government is especially
skilled compared to contractor; and (3) the contractor does not know the underlying facts on
which the ECC is based and reasonably infers that the Government’s opinion is based on
sufficient facts to form such an opinion. Id.; see also O’Neal Engineering, Inc.,
ASBCA 32013, 86-3 BCA ¶ 19,114, at 96,619 (denying, based on Acres American, A/E
contractor’s increased design costs claim that alleged reliance on Government’s “inaccurate”
construction estimates).
The exceptions to the general rule that a statement of opinion may not be relied upon
are not applicable here. Appellant challenges the VA’s method for computing the IGCEs
upon which the contract ECC prices were based, not whether the VA had superior knowledge
of the project requirements. The projects’ requirements upon which appellant based its
proposals were set forth in the solicitations and the awarded contracts, as the Government
was seeking an A/E contractor to evaluate the requirements and create designs to construct
the projects within the contract ECC prices.
There is no evidence that the government personnel who compiled the solicitations
and contracts were more skilled than the bidding A/E contractors, as the Government’s effort
was to set forth the parameters of the project that would be designed by the awardees of the
contracts. The attachments to the solicitations contained the projects’ scopes of work,
specifications, and other requirements for potential A/E contractor bidders to review when
deciding whether to submit a proposal seeking a design contract award. If the contractor,
after reviewing the solicitation and scope of work and specifications (amounting to several

CBCA 8151, 8162, 8163

10

hundred pages), did not believe it could accomplish the design, it could decide not to submit
a proposal.
There was no assurance, or warranty, as suggested by appellant, that the ECC prices
accurately reflected the costs of the future construction contracts. While appellant contends
that its proposals relied upon the ECC prices, it also acknowledges that its decision to submit
proposals was also based on its review of each contract’s requirements as stated in the
solicitation. In fact, appellant alleges:
There are three essential pieces of information in a solicitation that are relied
on to formulate the A/E fee proposal—the scope of work, the as-built drawings
and other attached pertinent materials, and the stated Design Limitation [ECC
price]; it is imperative that these pieces of information are complete and
accurate when formulating the fee proposal. The design limitation provides
the A/E with an understanding of how the VA has interpreted the risks,
magnitude, and complexities of the design along with underlying assurances
that the VA has accurately reflected the costs of the future construction
project. With those essential pieces of information, the A/E formulates their
fee proposal along with providing the VA with the number of contract
drawings needed to complete the design deliverable.5 The design deliverable
includes not only the contract drawings and details, but the calculations and a
design narrative write-up that support the basis of design.
Complaint (CBCA 8153) at 8 (emphasis added); Complaint (CBCA 8162) at 7 (emphasis
added); Complaint (CBCA 8163) at 6 (emphasis added) (with editorial variations).
In O’Neal Engineering, the ASBCA held that an ECC price was not to be relied upon
under circumstances similar to those in this appeal. While the A/E contractor in O’Neal
Engineering alleged a “grossly inaccurate” ECC price in the solicitation and contract, the
ASBCA noted that the contractor had an opportunity to study the Government’s detailed
statement of work and to visit the construction site. 86-3 BCA at 96,619. The O’Neal
Engineering decision summarizes the appellant’s responsibilities here:

5

As noted elsewhere in this decision, the number of contract drawings in the
proposals were estimates.

CBCA 8151, 8162, 8163

11

It was [A/E firm’s] job, not the Government’s, to provide the direct design
services based upon the contractually defined work scope. [The A/E firm’s]
efforts, in this regard, were expected to lead to the more detailed plans, and
the more precise construction cost estimate. These were [the A/E firm’s]
contractual obligations. Moreover, [the A/E firm was well aware [this was the
case] when it was asked to submit a detailed fee proposal based on its
anticipated design effort. . . . It was during this period that [the A/E firm] had
the opportunity to more precisely define its direct design costs.
....
[The A/E firm] was awarded this contract based upon its architectural ability
in designing electrical and mechanical projects. The Government was not the
expert. It was [the A/E firm] upon whom the Government relied and to whom
it gave the basic information to submit a proposal to design [the project].
Id. (emphasis added).
Here, it is clear that the VA was relying upon the expertise of the A/E contractors to
evaluate the information in the solicitation, and not to simply rely upon the ECC price, when
submitting their proposals.
Allegations of Increased ECC Prices
Respondent does not dispute that the ECC prices of the designed projects increased
as appellant performed its contracts. An increase in the ECC price of the project as designed
does not entitle an A/E contractor to additional compensation. Schoenfeld Associates, Inc.,
VABCA 2104, et al., 87-1 BCA ¶ 19,648, at 99,478. As explained in Schoenfeld Associates,
The mere fact that [the A/E firm] had provided the VA with a project with a
higher budget than that anticipated does not establish a right to compensation.
The [A/E firm] came in with a contract price. The VA evidently did not
require the [A/E firm] to redesign back to the original price. Thus, there was
no extra work directed by the VA from that done under the original contract.
The [A/E firm] has presented absolutely no evidence that the scope of the
work, which it designed for, was any different when it bid, then when it
completed its design. Only the price for construction was higher than either

CBCA 8151, 8162, 8163

12

party anticipated. That alone is not grounds for an increase in design fee. The
[A/E firm] has failed to meet its burden of proof on this issue.
Id.; see also R.M Otto Co. & Associates, VABCA 1526, 82-2 BCA ¶ 15,889, at 78,795 (“An
increase in the cost of construction does not, standing alone, entitle the A/E to additional
compensation.”); Shaw Metz & Associates, VACAB 774, 71-1 BCA ¶ 8679, at 40,310;
Praeger-Kavanagh-Waterbury, DOT CAB 67-13, 69-1 BCA ¶ 7482, at 34,716.
Even if, as appellant has alleged, the ECC prices of the contracts did not reflect the
complexities of the projects to be designed, as discussed previously, appellant was required
to design the projects based upon all the information in the contracts, within the scopes of
the work upon which it based its proposals. It was foreseeable that appellant would conclude
during contract performance that the designs would be more complex than it anticipated
when it prepared its proposals and therefore result in increased ECC prices for the designed
projects. The Design Within Funding Limitations clause alerts those submitting proposals
of this possibility, and the Government was not obligated to change the scope of the project
the awarded A/E contractor was designing. As stated previously, GDM’s efforts, as the A/E
contractor, were expected to lead to more detailed plans and more precise construction cost
estimates, which could exceed the ECC prices in the contracts. See, e.g., O’Neal
Engineering, 86-3 BCA at 96,619.
Pursuant to the Design Within Funding Limitations clause, the A/E contractor is only
entitled to increased compensation if the Government increases the scope of the project to
be designed. As noted by appellant in its complaints, the VA did not increase the scopes of
work but directed appellant to design within the scopes upon which appellant based its
proposals:
For nearly a year, the VA was told over and over again that the project scope
of work was exceeding the design funding limitation. The project scope of
work was not revised in any way to stay within the design funding limitation
at any of the four design submittal stages (35%, 65%, 95%, and 100%) that
took place over the year[-]long design process. The Contracting Officer did
not provide any direction on the matter whatsoever. No request to redesign.
No revised scope of work. No changed specifications. No other direction that
might have lowered the estimated cost of construction was ever received.
Complaint (CBCA 8153) at 6 (emphasis added); Complaint (CBCA 8162) at 6 (emphasis
added). In its CBCA 8163 complaint, appellant similarly acknowledges that:

CBCA 8151, 8162, 8163

13

In accordance with FAR 52.236-22 Design Within Funding Limitations, GDM
alerted the VA with each design submittal (35%, 65%, 95%, and 100%) that
the design limitation was being exceeded. At no time did the VA authorize a
change in scope or materials as required to reduce the estimated construction
cost (ECC) to an amount within the funding limitation.
Complaint (8163) at 5 (emphasis added).
Allegations of Cardinal and Constructive Change
Under a FFP contract, a contractor can demonstrate entitlement to additional
compensation pursuant to the Changes clause, FAR 52.243-1, if the Government changes the
scope of work. See Hengel Associates, P.C., VABCA 3921, 94-3 BCA ¶ 27,080, at 134,965
(explaining that, absent evidence that a design firm “performed any [d]esign work in addition
to that for which it originally contracted” an increased construction budget, alone, does not
establish a right to compensation); Schoenfeld Associates, 87-1 BCA at 99,478. Since the
appellant admits that the Government did not explicitly order a change, appellant would need
to prove constructive change. Nova Group/Tutor-Saliba v. United States, 159 Fed. Cl. 1, 49
(2022), aff’d, 87 F.4th 1375 (Fed. Cir. 2023). Prevailing on a constructive change claim
requires allegations of fact showing: “(1) that appellant performed work beyond the contract
requirements, and (2) that the additional work was ordered, expressly or impliedly, by the
government.” Id. (quoting Bell/Heery v. United States, 739 F.3d 1324, 1335 (Fed. Cir.
2014)); see also Praeger-Kavanagh-Waterbury, 69-1 BCA at 34,717 (holding that additional
compensation is warranted when the Government “alters the basic project requirements so
as to importantly affect the prior design work, thus imposing a significant additional
workload on the architect.”).
In its complaints, appellant alleges that, as it performed the design contracts, the total
numbers of design drawings appellant produced exceeded the estimated number included in
appellant’s proposals.6 For the Togus contract, the number of drawings increased from an
estimated 305 to 573. Complaint (CBCA 8151) at 8. For the Birmingham contract, the
number increased from an estimated 305 to 467. Complaint (CBCA 8162) at 7. And, for the
Murfreesboro contract, the number increased from an estimated 295 to 477. Complaint
(CBCA 8163) at 7.

6

Appellant’s proposals contained estimated numbers of contract drawings.
CBCA 8151, Exhibit 14 at 9; CBCA 8162, Exhibit 7 at 14; CBCA 8163, Exhibit 19 at 17.

CBCA 8151, 8162, 8163

14

While appellant emphasizes that it produced more drawings than specified in its
accepted fee proposals, the number of drawings appellant specified in its proposals were
clearly designated as estimates. An increase in the actual number of drawings from an
estimated number does not prove a change in scope, entitle a contractor to additional
compensation, or lead to the conclusion that a change in the scope of work has been
authorized. See Elcon Associates, ASBCA 44189, 95-2 BCA ¶ 27,859, at 138,915 (requiring
an A/E firm to allege more than just that it produced more drawings than anticipated).
Appellant acknowledges that the Government did not increase the scopes of the work.
Accordingly, there was no change, actual, constructive, or cardinal.
Again, appellant’s primary basis for relief is the less tangible assertion that the
projects’ designs became more complicated than anticipated. A more complicated design is
not, in and of itself, the basis for a compensable change. Schoenfeld Associates, Inc., 87-1
BCA at 99,478. “It [is] the [A/E firm’s] expertise that the Government [seeks and] . . . the
A/E’s job to flesh out and focus the design so that an end product [can] be constructed.” Id.
As stated previously, appellant had the opportunity to review the detailed requirements in the
solicitations before submitting its proposals. If an A/E firm views an estimate as woefully
inadequate, it should not bid or accept the contract. Id; see also Hengel Associates, P.C.,
94-3 BCA at 13,965 (“If [the A/E firm] felt that the Government’s estimate was unrealistic
and thus if it could not do the design for the price offered, it should not have put in a final
offer.”).
Respondent’s Direction Pursuant to the Design Within Funding Limitations Clause
Appellant advised the COs that the ECC price of the projects that were being designed
to meet the contracts’ requirements continued to increase and exceeded the ECC prices in
paragraph c of the Design Within Funding Limitations clauses in the contracts. While the
COs did not increase the scopes of work of the contracts or of the projects to be designed,
appellant asserts that it is entitled to an increase in its design fees for the quantum of the
certified claims. Complaint (CBCA 8153) at 3; Complaint (CBCA 8162) at 3; Complaint
(CBCA 8163) at 3.
As noted previously, appellant states that the COs did not revise the scopes of the
projects when appellant advised that the construction projects could not be designed within
the stated funding limitations of the contracts (i.e., the ECC prices in the contracts).
Appellant asserts that this lack of revision of the scopes of the projects denied appellant an
increase in its fee:

CBCA 8151, 8162, 8163

15

GDM used the [Design Within Funding Limitations clause] . . . and the other
solicitation documents to develop a proposal for a project of the magnitude and
with the complexities presented. In accordance [with the Design Within
Funding Limitations clause,] GDM advised the Contracting Officer that the
design limitation was being exceeded. At no time did the Contracting Officer
revise the scope or required materials nor did the Government revise the [ECC
price] published in paragraph (c) of the clause. Rather, the Contracting
Officer[s] took no action other than to advise GDM to continue with the
design. By advising GDM to continue with the design without any revision to
the scope of work, materials, or the design limitation implies acceptance of
GDM’s 100% construction documents and estimated construction cost,
constituting a cardinal change to the contract.
Complaint (CBCA 8153) at 6 (emphasis added) ; Compliant (CBCA) 8162 at 6 (emphasis
added); Complaint (CBCA 8163 at 5) (emphasis added).
As mentioned previously, appellant alleges:
For nearly a year, the VA was told over and over again that the project scope
of work was exceeding the design funding limitation. The project scope of
work was not revised in any way to stay within the design funding limitation
at any of the four design submittal stages (35%, 65%, 95%, and 100%) that
took place over the year long design process. The Contracting Officer did not
provide any direction on the matter whatsoever. No request to redesign. No
revised scope of work. No changed specifications. No other direction that
might have lowered the estimated cost of construction was ever received.
The problem with this assertion is that the VA could write in any unreasonable
“low-ball” estimated construction contract price knowing that an A/E firm is
restricted by the Brooks Act to 6% of construction for design and construction
documents, abusing the right to direct additional design effort without
consequence.[7]

7

Appellant’s speculation that the VA might intentionally have included
unreasonable ECC prices to reduce the A/E’s fee is not supported by appellant’s complaints,
which challenge the VA’s methodology of calculating the IGCEs but do not allege any
intention to include reduced ECC prices to disadvantage those who submit proposals.

CBCA 8151, 8162, 8163

16

Complaint (CBCA 8153) at 6 (emphasis added); Complaint (CBCA 8162) at 6 (emphasis
added).
The Government’s actions described by appellant above do not entitle appellant to
additional compensation. As explained in Michael Roth & Associates, Architects & Planners
Inc., 133 Fed. Cl. 279 (2017), which is factually similar to the case here, “[t]he design within
funding limitations clause imposes only one duty on the VA.” Id. at 290. That duty is to
review the contractor’s revised ECC after the contractor informs the Government that the
project, as designed, is likely to exceed the initial ECC. Id. And, then after review, the
Government “may . . . authorize a change in scope or materials as required to reduce the
estimated construction cost to an amount within the estimated construction contract price . . .
or the Government may adjust such estimated construction contract price.” Id. (quoting FAR
52.236-22) (emphasis added). The use of “may” is permissive, and the Government here was
not obligated to change appellant’s scope when appellant informed it of the increased ECC.
See id. (stating that “the VA was not obligated to choose one of the options set forth in the
[funding limitations] clause; the options were discretionary.”). Here, the Government did not
authorize a change in scope or an increase in the contract ECC price. Appellant
acknowledges this discretion when it alleges:
GDM understands that had the Contracting Officer issued direction to revise
the scope of work, services necessary for the redesign would have been at
GDM’s expense (FAR 52.236-22); however, that is not what took place.
Rather, the VA remained silent and maintains that “the decision to increase the
ECC . . . was at the discretion of VA.”
Complaint (CBCA 8153) at 6 (emphasis added); Complaint (CBCA 8162) at 6 (emphasis
added) (editorial variations).
Thus, appellant acknowledges that even if the CO had increased the scopes of the
contracts by directing redesign to comport with increased ECC prices, there would be no
entitlement to additional compensation.
Conclusion
Appellant concludes:
On numerous occasions through the year-long design process, GDM fulfilled
its responsibility to inform the VA that the estimated cost of construction was
exceeding the design limitation. By advising GDM to continue designing the

CBCA 8151, 8162, 8163

17

awarded scope of work, the VA approved a change to the estimated cost of
construction contract. As this is a material matter to the solicitation and award,
it is GDM’s position that this is a cardinal change to the contract for which
GDM is owed equitable compensation.
Complaint (CBCA 8153) at 8-9; Complaint (CBCA 8162) at 8; Complaint (CBCA 8163)
at 7.
Appellant agreed to perform each contract for a firm, fixed price. The fact that
appellant realized during performance of the design contracts that the contract requirements
were more complex than it had anticipated when preparing its proposals—requiring more
design effort than appellant estimated, resulting in increased ECC prices for the projects
designed—did not change the scopes of the projects being designed or require the
Government to increase the scopes or require redesign of the projects. There were no
changes to the design contracts—actual, constructive, or cardinal, as alleged by
appellant—for which appellant is owed additional compensation. In these appeals, appellant
has failed to state claims upon which relief can be granted.
Decision
Respondent’s motions to dismiss for failure to state a claim, filed in CBCA 8151,
CBCA 8162, and CBCA 8163, are granted, and these consolidated appeals are DISMISSED.

Allan H. Goodman
ALLAN H. GOODMAN
Board Judge
We concur:

H. Chuck Kullberg
H. CHUCK KULLBERG
Board Judge