MOTION TO DISMISS FOR LACK OF JURISDICTION DENIED: June 23, 2010

CBCA 1884, 1901, 1902, 1903, 1904, 1905, 1906, 1907, 1908,
1909, 1910, 1911, 1912, 1913, 1914, 1915, 1916, 1917

RON ANDERSON CONSTRUCTION, INC.,
Appellant,
v.
DEPARTMENT OF VETERANS AFFAIRS,
Respondent.
William G. Beck and Michele A. Munson of Woods, Fuller, Shultz & Smith P.C.,
Sioux Falls, SD, counsel for Appellant.

Lindsay C. Roop, Office of Regional Counsel, Department of Veterans Affairs,
Minneapolis, MN, counsel for Respondent.
Before Board Judges SOMERS, BORWICK, and SHERIDAN.

SOMERS, Board Judge.
The Department of Veterans Affairs (VA or the Government) entered into a contract
with Ron Anderson Construction, Inc. (contractor or appellant) to remodel a wing at the VA
Black Hills Health Care System in Hot Springs, South Dakota. During the course of
contract performance, the contracting officer made changes to the contract, or the appellant
determined that constructive changes had occurred. The parties would discuss these
changes, and the contractor would proceed after receiving verbal approval from the
contracting officer. After completing the work, the appellant would submit a change order
indicating the additional charges for the changes. The VA would either pay the entire
amount, dispute portions of the charges, or deny payment entirely.
The contract included the following VA Supplemental Changes clause:

CBCA 1884, 1901, 1902, 1903, 1904, 1905, 1906, 1907, 1908, 1909,
1910, 1911, 1912, 1913, 1914, 1915, 1916, 1917

2

VAAR 852.236-88 Contract Changes - Supplement (JUL
2002)
(b)
Paragraphs (b)(1) through (b)(11) apply to proposed
contract changes costing $500,000 or less:[1]
(1)
When requested by the contracting officer, the contractor
shall submit proposals for changes in work to the resident
engineer. Proposals, to be submitted as expeditiously as
possible but within 30 calendar days after receipt of the request,
shall be in legible form, original and two copies, with an
itemized breakdown that will include materials, quantities, unit
prices, labor costs (separated into trades), construction
equipment, etc. (Labor costs are to be identified with specific
material placed or operation performed.) The contractor must
obtain and furnish with a proposal an itemized breakdown as
described above, signed by each subcontractor participating in
the change regardless of tier. When certified cost or pricing
data or information other than cost or pricing data are required
under FAR [Federal Acquisition Regulation] 15.403, the data
shall be submitted in accordance with FAR 15.403-5. No
itemized breakdown will be required for proposals amounting
to less than $1,000.
(2)
When the necessity to proceed with a change does not
allow sufficient time to negotiate a modification or because of
failure to reach an agreement, the contracting officer may issue
a change order instructing the contractor to proceed on the basis
of a tentative price based on the best estimate available at the
time, with the firm price to be determined later. Furthermore,
when the change order is issued, the contractor shall submit
within 30 calendar days, a proposal that includes the
information required by paragraph (b)(1) for the cost of the
changes of work.

1

None of these appeals involve proposed contract changes involving costs
exceeding $500,000.

CBCA 1884, 1901, 1902, 1903, 1904, 1905, 1906, 1907, 1908, 1909,
1910, 1911, 1912, 1913, 1914, 1915, 1916, 1917

3

(3)
The contracting officer will consider issuing a settlement
by determination to the contract if the contractor’s proposal
required by paragraphs (b)(1) or (b)(2) of this clause is not
received within 30 calendar days, or if agreement has not been
reached.
Respondent’s Motion to Dismiss, Attachment 2.2
Thus, as noted by the VA, many of the appeals involve what are called “settlements
by determination,” which are contemplated by the above-cited clause. When the parties
could not agree on the amount that the Government should pay for the proposed change
within a reasonable period of time, the contracting officer would unilaterally change the
contract through a contract modification. Most of the contract modifications included the
following language:
This is the final decision of the Contracting Officer. You may
appeal this decision to the agency board of contract appeals and
provide a copy to the Contracting Officer from whose decision
this appeal is taken. The notice shall indicate that an appeal is
intended, reference this decision, and identify the contract by
number.
See Attachments to the Notices of Appeal for CBCA 1884, 1901, 1902, 1903, 1904, 1905,
1907, 1908, 1911, 1912, 1913, 1914, 1915, 1916, and 1917. In some of the settlements by
determination, the VA provided that the Government would take no further action regarding
the contractor’s change orders.
The remaining three appeals, CBCA 1906, 1909, and 1910, all involve circumstances
in which the contractor submitted a cost proposal for changed work, the VA did not pay for
the alleged changes, and the contracting officer did not issue a final decision. In these cases,
the contractor demanded payment for the alleged changes. If the contracting officer did not
pay upon request, the contractor submitted additional information and continued to demand
payment. After months had passed without payment, the contractor requested final
decisions. When the contracting officer failed to act, the appellant appealed the contracting
officer’s failure to act as a deemed denial of its claim.

2

The VA has provided limited excerpts of the contract in this case. No appeal
files have yet been submitted.

CBCA 1884, 1901, 1902, 1903, 1904, 1905, 1906, 1907, 1908, 1909,
1910, 1911, 1912, 1913, 1914, 1915, 1916, 1917

4

The VA has moved to dismiss the appeals for lack of jurisdiction, alleging that the
appellant never submitted a claim in any of the appeals. See Respondent’s Motion to
Dismiss at 2 (citing 48 CFR 2.101). The Government asserts that the cost proposals
submitted by the contractor do not constitute claims sufficient to meet the requirements of
the Contract Disputes Act of 1978 (CDA), 41 U.S.C. § 605(a) (2006), because they are
submitted pursuant to a provision in the contract which calls for the proposals to be resolved
by “settlements by determination.”
The appellant disagrees, and states in an affidavit that it submitted cost proposals
demanding payment for unforeseen or unintended changes, in addition to being in response
to change orders issued by the contracting officer. After submitting these cost proposals,
the appellant provided additional information at the VA’s request, while continuing to
demand payment. Appellant’s Brief in Response and Opposition to Respondent’s Motion
to Dismiss, Exhibit 1. The appellant contends that the fact that many of the unilateral
contract modifications provided contract appeal rights served as a further indication that the
Government considered the proposals to be claims and the unilateral modifications to be
final decisions.
Discussion
Under the CDA, “all claims by a contractor against the Government relating to a
contract shall be in writing and shall be submitted to the contracting officer for a decision.”
41 U.S.C. § 605(a). The CDA does not define a claim. The Federal Acquisition Regulation,
however, defines a claim as “a written demand or written assertion by one of the contracting
parties seeking, as a matter of right, the payment of a sum certain, the adjustment or
interpretation of contract terms, or other relief arising or relating to the contract.” 48 CFR
2.101 (2009). The Court of Appeals for the Federal Circuit uses this definition in
determining whether a communication is a claim. M. Maropakis Carpentry, Inc. v.
United States, No. 2009-5024, 2010 WL 2403337, at *3 (Fed. Cir. June 17, 2010) (citing
Reflectone, Inc. v. Dalton, 60 F.3d 1572 (Fed. Cir. 1995) (en banc)).
Whether a communication is deemed a claim sufficient to invoke the Board’s
jurisdiction depends on an evaluation of the relevant contract language, the facts of the case,
and the regulations implementing the CDA. See Reflectone; EBS/PPG Contracting v.
Department of Justice, CBCA 1295, 09-2 BCA ¶ 34,208; Guardian Environmental Services,
Inc. v. Environmental Protection Agency, CBCA 994, 08-2 BCA ¶ 33,938. The intent of the
communication governs, and we must use a common sense analysis to determine whether the
contractor communicated its desire for a contracting officer’s decision. Id. There is no
requirement that a dispute exists at the time of submission of a non-routine request for it to

CBCA 1884, 1901, 1902, 1903, 1904, 1905, 1906, 1907, 1908, 1909,
1910, 1911, 1912, 1913, 1914, 1915, 1916, 1917

5

be considered a claim. Reflectone, 60 F.3d at 1576-78. Nor is there any “requirement in the
Disputes Act that a ‘claim’ must be submitted in any particular form or use any particular
wording.” Contract Cleaning Maintenance, Inc. v. United States, 811 F.2d 586, 592
(Fed. Cir. 1987).
Appellant bears the burden of establishing subject matter jurisdiction by a
preponderance of the evidence. McNutt v. General Motors Acceptance Corp., 298 U.S. 178,
189 (1936); Reynolds v. Army and Air Force Exchange Service, 846 F.2d 746, 748
(Fed. Cir. 1988); 801 Market Street Holdings, L.P. v. General Services Administration,
CBCA 425, 08-1 BCA ¶ 33,853. In assessing whether the Board has subject matter
jurisdiction, the allegations of the complaint should be construed favorably to the pleader.
Scheuer v. Rhodes, 416 U.S. 232, 236 (1974); United Pacific Insurance Co. v. United States,
464 F.3d 1325, 1327-28 (Fed. Cir. 2006); accord Hamlet v. United States, 873 F.2d 1414,
1416 (Fed. Cir. 1989); CACI, INC.-FEDERAL v. General Services Administration,
GSBCA 15588, 02-1 BCA ¶ 31,712, at 156,635 (2001). When a motion to dismiss for lack
of subject matter jurisdiction challenges the truth of alleged jurisdictional facts, the Board
may consider relevant evidence beyond the pleadings to resolve disputed facts. Cedars-Sinai
Medical Center v. Watkins, 11 F.3d 1573, 1583-84 (Fed. Cir. 1993); B&M Cillessen
Construction Co. v. Department of Health and Human Services, CBCA 931, 08-1 BCA
¶ 33,753 (2007); Innovative (PBX) Telephone Services, Inc. v. Department of Veterans
Affairs, CBCA 12, et al., 07-2 BCA ¶ 33,685
The VA asserts that it has not received a specific demand seeking payment as a matter
of right. It argues that the submission of proposals required under the contract cannot
constitute claims as “[i]t is well settled that price proposals submitted by either party in the
ordinary course of contract administration are not CDA claims,” citing Interstate
Contractors, Inc., VABCA 3404, 92-1 BCA ¶ 24,480 (1991). Pointing to the change orders,
the appellant notes that the proposals contain the statement “[w]e hereby propose to furnish
the materials and perform the labor necessary for the completion of . . . .” Respondent’s
Motion to Dismiss at 3 (referencing change order 14 of CBCA 1906). The respondent
contends that the appellant did not assert payment as a matter of right or demand a
contracting officer’s decision in any of the proposals. As to the unilateral change orders in
the form of settlements by determinations, the fact that the contracting officer included final
appeal language did not create a final decision.
Contrary to the Government’s assessment, the request for a final decision need not be
affirmative, but can be implied by the text of the submission. See, e.g., EBS/PPG
Contracting, 09-2 BCA at 169,111. “As long as the basic requirements of the CDA are met,
and the contracting officer knows the bases for the claims and the final amounts sought, the

CBCA 1884, 1901, 1902, 1903, 1904, 1905, 1906, 1907, 1908, 1909,
1910, 1911, 1912, 1913, 1914, 1915, 1916, 1917

6

‘request’ for a final decision may be inferred from the circumstances of the case.” Id.
(quoting Mega Construction Co. v. United States, 29 Fed. Cl. 396, 443 (1993)).
Based on a review of the limited record before us, we note that language expressly
requesting a contracting officer’s final decision does not appear in any of the cost proposals
or correspondence between the parties relating to the change orders and cost proposals.
However, the Board also looks to whether the appellant’s submissions and the circumstances
surrounding them imply a desire for a contracting officer’s final decision.3 EBS/PPG
Contracting, 09-2 BCA at 169,111; Guardian Environmental Services, Inc., 08-2 BCA at
167,946. Here, looking at the actions of the parties and the totality of the circumstances
before us, we find that in each appeal, the contractor submitted a cost proposal which
contained “a written demand, seeking, as a matter of right, the payment of money in a sum
certain,” to the contracting officer, thus fulfilling the requirements for the submission of a
claim. See Reflectone, 60 F.3d at 1575. The circumstances and correspondence surrounding
the submission of each cost proposal support this conclusion.
Decision
VA’s motion to dismiss these appeals for lack of jurisdiction is DENIED. The
presiding judge will convene a telephonic conference with counsel to discuss further
proceedings in these cases.

___________________________
JERI KAYLENE SOMERS
Board Judge

3

The VA cites Interstate Contractors, Inc. and Winding Specialists Co.,
ASBCA 37765, 89-2 BCA ¶ 21,737, in support of its contention that the cost proposals
cannot be considered claims because they do not expressly seek a final decision or assert a
payment as a matter of right. These cases, however, predate the guidance set forth in
Reflectone. While it is true that the issuance of a “settlement by determination” does not
serve to convey jurisdiction upon the Board in the absence of a valid claim or dispute, under
Reflectone, the facts surrounding the issuance of a “settlement by determination” may give
rise to a CDA claim, entitling the claimant to appeal rights.

CBCA 1884, 1901, 1902, 1903, 1904, 1905, 1906, 1907, 1908, 1909,
1910, 1911, 1912, 1913, 1914, 1915, 1916, 1917
We concur:

__________________________
ANTHONY S. BORWICK
Board Judge

___________________________
PATRICIA J. SHERIDAN
Board Judge