# In the Matter of HOUSING AUTHORITY OF THE CITY OF LUMBERTON,

> Briefs, arguments, decisions, and more.

URL: https://www.frixlaw.com/law-library/documents/agency%3Acbca%3Aaba1835a6998424e

## Record

- **Collection:** Agency decision
- **Document type:** Agency decision

## Text

February 20, 2024

CBCA 7904-FEMA

In the Matter of HOUSING AUTHORITY OF THE CITY OF LUMBERTON,
NORTH CAROLINA

Danielle M. Aymond of Baker, Donelson, Bearman, Caldwell & Berkowitz, PC,
Baton Rouge, LA, counsel for Applicant.
Will Polk and Pamela M. Thombs, Office of the General Counsel, North Carolina
Department of Public Safety, Raleigh, NC, counsel for Grantee.
Shahnam Thompson and Rebecca J. Otey, Office of Chief Counsel, Federal
Emergency Management Agency, Department of Homeland Security, Washington, DC,
counsel for Federal Emergency Management Agency.
Before the Arbitration Panel consisting of Board Judges BEARDSLEY (Chair),
SULLIVAN, and KANG.
KANG, Board Judge, writing for the Panel.
Applicant, the Housing Authority of the City of Lumberton, North Carolina (HACL),
sought arbitration under 42 U.S.C. § 5189a(d) (2018) of a dispute with the Federal
Emergency Management Agency (FEMA) as to eligibility for public assistance (PA) funding
in connection with Hurricane Matthew. FEMA previously granted part of HACL’s request
for PA funding to repair thirty-three buildings, comprising sixty-eight housing units, but
denied applicant’s request to fully replace them. We find the buildings are not eligible for
replacement.

CBCA 7904-FEMA

2
Background

HACL owns and operates the Lumbee Homes Public Housing Community (Lumbee
Homes) in Robeson County, North Carolina. The buildings at issue here include standalone
and duplex one-, two-, three-, and four-bedroom units. In October 2016, Hurricane Matthew
struck the eastern coast of the United States, including Robeson County. The Lumbee
Homes buildings experienced flooding from the storm’s rainwater, followed by additional
flooding from a levee failure. On October 10, 2016, the President issued a major disaster
declaration (FEMA-4285-DR-NC) for Hurricane Matthew.
In December 2016, FEMA approved emergency work for repairs to certain Lumbee
Homes buildings, including asbestos testing and remediation, which was conducted from
February through August 2017. In July 2017, FEMA prepared permanent work project
worksheets (PWs) for repairs at Lumbee homes: PW 1368, which had an initial project cost
of $524,743, and PW 1370, which had an initial project cost of $515,242.
In June 2019, Anderson Consulting, a consultant retained by HACL, prepared an
estimate of repair and replacement costs.1 Based on this estimate, applicant requested that
FEMA add repair costs to PWs 1368 and 1370 and find the buildings eligible for replacement
because the added costs increased the overall value of the repairs to more than fifty percent
of the estimated costs of replacement. In July and August 2020, Anderson Consulting
provided FEMA itemized estimates for the repair of the buildings. In late August 2020,
FEMA issued amendments to PWs 1368 and 1370 based on the Anderson Consulting
estimates. These PW amendments found that the eligible repair costs were more than fifty
percent of the estimated costs of replacement.
In February 2022, FEMA issued determination memorandums (DMs) for PWs 1368
and 1370 that denied the majority of the repair costs requested by applicant. The DMs found
that some of the costs in the Anderson Consulting estimates were duplicative of costs
approved for the emergency work and that other costs were either not eligible or
unsupported. Based on FEMA’s revised costs in the DMs, FEMA found that the eligible
repair costs were less than fifty percent of applicant’s estimated costs of replacement and
were therefore not eligible for replacement.
Applicant filed first-level appeals of the DMs in April 2022 and June 2022, seeking
increased repair costs that HACL contended justified full replacement of the buildings.
FEMA’s August 2023 decision on the first-level appeals adjusted certain of applicant’s

1

Applicant does not state when Anderson Consulting inspected the Lumbee
Homes buildings for this report, but FEMA states that this occurred in June 2019.

CBCA 7904-FEMA

3

requested repair costs, concluding that some had been improperly excluded or found not
eligible, while others had been improperly found eligible. Relevant here, the costs that
FEMA found eligible included replacement of heating, ventilation, and air conditioning
(HVAC) systems, replacement of exterior wall insulation, and replacement and repair of
parts of the flooring.
Overall, FEMA found applicant eligible for $1,726,309 in repair costs under PW 1368
and $850,843 in repair costs under PW 1370. Because the eligible repair costs were less than
fifty percent of applicant’s estimated replacement values of the buildings ($8,591,270 for PW
1368 and $9,813,993 for PW 1370), FEMA found that the buildings were still not eligible
for replacement.
Applicant requested arbitration on October 2, 2023. The parties elected to conduct
the arbitration on the basis of the record submitted to the panel.
Discussion
The Robert T. Stafford Disaster Relief and Emergency Assistance Act (Stafford Act),
42 U.S.C. §§ 5121-5207 (2018), provides the statutory authority for FEMA’s federal disaster
response activities. Congress enacted the Stafford Act to provide “assistance by the Federal
Government to State and local governments in carrying out their responsibilities to alleviate
the suffering and damage which result from [major] disasters.” 42 U.S.C. § 5121(b). The
Stafford Act is “designed to assist the efforts of [states affected by major disasters] in
expediting the rendering of aid, assistance, and emergency services, and the reconstruction
and rehabilitation of devastated areas.” Id. § 5121(a).
An applicant has the burden to demonstrate that damage was directly caused by a
declared disaster. FEMA’s Public Assistance Program and Policy Guide (PAPPG)
(Jan. 2016) at 9, 19.2 To be eligible, costs must be directly tied to the performance of eligible
work and adequately documented. Id. at 21. Moreover, PA funding is intended to restore
damaged facilities to their prior function in accordance with applicable codes and standards,
and an applicant must demonstrate that the repair costs are for damage directly caused by the
disaster rather than by pre-existing damage or by a failure to reasonably mitigate damages.
Id. at 19, 81-82.
When evaluating whether a damaged facility is eligible for replacement, rather than
repair, “FEMA compares the repair cost with the replacement cost and evaluates the

2

The January 2016 PAPPG applies to declared disasters from January 1, 2016,
through March 31, 2017.

CBCA 7904-FEMA

4

feasibility of repairing the facility.” PAPPG at 96. “A facility is considered repairable when
disaster damages do not exceed 50 percent of the cost of replacing a facility to its predisaster
condition, and it is feasible to repair the facility so that it can perform the function for which
it was being used as well as it did immediately prior to the disaster.” 44 CFR 206.226(f)(1)
(2016).
Applicant seeks replacement of thirty-three buildings, comprising sixty-eight housing
units, at Lumbee Homes. HACL’s request for arbitration (RFA) initially asked “only [that]
the Panel determine whether or not the units are eligible for replacement.” RFA at 2.
Applicant raises two primary arguments in support of its position that the costs to repair the
buildings exceed fifty percent of the costs of replacing them. First, applicant contends that
the panel should accept the estimates prepared by HACL’s consultant that were presented
in the first appeal and that the estimates reflect repair costs in excess of fifty percent of the
costs of replacement.3 Second, in the event the panel does not accept the consultant’s
original estimates, applicant submits new estimates that identify three additional categories
of costs that were not raised in connection with the first appeal and that increase the repair
costs for the buildings above the fifty-percent threshold.
Notwithstanding the limited scope of the request set forth in the RFA, applicant’s
reply to FEMA’s response added new alternative requests in the event the panel does not find
the buildings eligible for replacement. These alternative requests ask that we either direct
FEMA to work with applicant to conduct a more detailed inspection of the buildings and
develop mutually-agreeable repair costs or remand the matter of repair costs for
reconsideration by FEMA. We therefore address applicant’s primary arguments in support
of its position that the costs to repair the buildings exceed fifty percent of the costs of
replacing them as well as applicant’s new alternative requests.
I.

Estimates from Applicant’s Consultant

Applicant argues that FEMA is obligated under its policies to accept as dispositive the
cost estimates prepared by HACL’s consultant, Anderson Consulting. Applicant contends

3

Applicant also contends that FEMA improperly reversed the findings in its
August 2020 amendments to PW 1368 and 1370, which found eligibility for repair costs in
excess of fifty percent of the estimated replacement costs. FEMA is not prohibited from
reconsidering or changing an initial determination, and an applicant cannot demonstrate
eligibility for PA funding based solely on the fact that FEMA had initially made a more
favorable finding. See Montgomery County Secondary Roads, CBCA 7480-FEMA, 22-1
BCA ¶ 38,230, at 185,659-60.

CBCA 7904-FEMA

5

that these estimates demonstrate that the costs of repairing the buildings exceed fifty percent
of the costs of replacement. We find no merit to these arguments.
The PAPPG states that FEMA will use an applicant’s cost estimate to determine PA
eligibility where it:
•

Is prepared by a licensed Professional Engineer or other estimating
professional, such as a licensed architect or certified professional cost
estimator who certifies that the estimate was prepared in accordance
with industry standards;

•

Includes certification that the estimated cost directly corresponds to the
repair of the agreed upon damage;

•

Is based on unit costs for each component of the SOW and not a lump
sum amount;

•

Contains a level of detail sufficient for FEMA to validate that all
components correspond with the agreed-upon SOW; and

•

Is reasonable.

PAPPG at 132.
To the extent applicant contends that the mere submission of certified estimates by
a licensed professional establishes cost eligibility, we disagree, as the adequacy of an
estimate’s details and its overall reasonableness must be considered.
FEMA does not dispute that the Anderson Consulting estimates were prepared by a
licensed professional engineer. FEMA argues, however, that the estimates do not contain
adequate detail, are not reasonable, and do not establish eligibility of repair costs that exceed
the fifty-percent threshold. FEMA notes that the estimates were based on inspections that
took place more than three years after Hurricane Matthew. Based on the passage of time,
FEMA contends that applicant cannot demonstrate that Hurricane Matthew was the direct
cause of the damage to the buildings, as opposed to delays in remediating the damage from
that storm or intervening events such as the flooding experienced in the buildings caused by
Hurricane Florence in September 2018.4

4

We do not agree with FEMA’s assertion that an assessment conducted three
years after a disaster is “blanketly unreliable.” FEMA Response at 13. However, we agree

CBCA 7904-FEMA

6

The 2019 and 2020 Anderson Consulting estimates consist solely of costs and do not
directly address why the claimed damages were eligible for reimbursement. Applicant
submitted an affidavit from Larry Anderson, president of Anderson Consulting, to support
the estimates, but the assertions therein do not adequately explain why inspections three
years later are reliable.5 In light of the passage of time and lack of adequate explanations,
the estimates do not contain details sufficient to validate that all of the repair costs are within
the scope of work or are otherwise reasonable. In sum, applicant does not establish that
FEMA policy requires deference to the estimates prepared by applicant’s consultant.
II.

Additional Repair Costs

We next address three categories of costs that applicant contends should be added to
the FEMA-approved repair costs: HVAC replacement, wall insulation replacement, and
flooring repair and replacement. Applicant contends that the addition of these costs increases
the repair costs above the fifty-percent threshold, thereby qualifying the buildings for
replacement. We find no merit to these arguments.
A.

HVAC Replacement Costs

FEMA granted $4554.54 to replace the HVAC systems at each of the thirty-three
affected buildings. FEMA’s Exhibit 26, Declaration of Jack Marlowe (Nov. 16, 2023) ¶ 18;
Applicant’s Exhibit 1, First Appeal Decision Analysis at 15; Cost Estimating Formula Sheets
(CEFs) at 1-78. This amount consists of $2777.16 for a condenser, evaporator, air handler,
and ductwork, plus $1777.38 for soft costs. Id. Applicant contends, based on the opinion
of Anderson Consulting and cost survey data, that the costs of replacing the HVAC systems
that the passage of time generally increases the burden on an applicant to demonstrate that
the claimed damage was directly caused by the disaster and not by alternative causes. See
City of Hattiesburg, Mississippi, CBCA 7228-FEMA, 22-1 BCA ¶ 38,029, at 184,684.
5

Applicant also argues that failure to promptly assess damage is due to FEMA’s
failure to conduct inspections of the buildings, as contemplated by the PAPPG. The PAPPG
provides that, during project formulation, “FEMA and the Recipient conduct site inspections
with the Applicant to validate, quantify, and document the cause, location, and details of the
reported damage and debris impacts and identify [environmental and historic preservation
(EHP)] issues and hazard mitigation opportunities . . . .” PAPPG at 128. In June 2017,
FEMA inspected two of applicant’s buildings for damage to assess EHP issues. Even if the
inspections were not the joint inspections anticipated by the PAPPG (a matter we need not
resolve), applicant does not establish that a failure to conduct inspections requires FEMA to
accept applicant’s estimates or otherwise excuses applicant from the requirement to establish
its entitlement to PA funding.

CBCA 7904-FEMA

7

should be higher, ranging from $11,432.82 for one-bedroom duplex units to $21,137.03 for
four-bedroom duplex units.
FEMA’s first appeal decision approved full replacement of HVAC systems for the
buildings, including replacement of existing 2.5-ton capacity units.6 Applicant’s consultant
states that the approved costs are inadequate, in part, because they do not include costs for
the larger three- to four-ton units. Applicant’s Exhibit 17, Affidavit of Larry W. Anderson
(Dec. 5, 2023) ¶ 11. The PWs for the buildings all provide for 2.5-ton capacity replacement
units, stating that they are “equivalent in size” to the existing units. Applicant’s Exhibit 6
at 7. While applicant appears to argue that the buildings require units larger than 2.5 tons,
applicant does not demonstrate that the existing units had this capacity. Thus, even if
upgrades to larger units were appropriate in light of previously undersized units at Lumbee
Homes, applicant is eligible only for restoration to the prior function of the units and not for
improvements or upgrades.7 On this record, applicant does not demonstrate that it is eligible
for replacement of the larger units.8
In addition, applicant’s RFA included a chart titled “NEW HVAC SYSTEM COST,”
citing cost survey data from the Homeguide.com website.9 Applicant contends that this data
shows significantly higher costs for HVAC replacements. The data, however, does not
address the size of the HVAC systems replaced or the locality of the work. Thus, nothing

6

Confusingly, FEMA’s response to the RFA stated that only the outdoor parts
of the HVAC systems were eligible for replacement, as there was no evidence of damage to
the interior parts of the system. The same response, however, stated that the outdoor
condenser, indoor component costs were eligible as well. Moreover, the first appeal decision
stated that the buildings were eligible for HVAC replacement, and the CEFs identified costs
for both the indoor and outdoor components. Applicant’s Exhibit 1, First Appeal Decision
Analysis at 15, 23-129 CEFs at 1-78. Thus, despite applicant’s contention that FEMA only
granted costs for the interior parts of the HVAC systems, the record shows that FEMA
granted costs for the indoor and outdoor components.
7

A building is eligible for upgrades required by applicable codes and standards.
PAPPG at 81-82; City of Hattiesburg, Mississippi, CBCA 7017-FEMA, 22-1 BCA ¶ 37,986,
at 184,457-58 (2021). Applicant, however, does not contend that upgrades to the size of the
HVAC units are required based on codes or standards.
8

Applicant does not explain whether its request for larger units applies to some
or all of the buildings, leaving the panel unable to assess the reasonableness of the costs.
9

Homeguide.com describes itself as a website that provides information services
homeowners and contractors. See https://homeguide.com/about (last visited Feb. 16, 2024).

CBCA 7904-FEMA

8

about this information establishes applicant’s costs as reasonable. On this record, applicant
is not eligible for costs for HVAC replacement in excess of that granted by FEMA.
B.

Exterior Walls Insulation Replacement

FEMA approved replacement of exterior wall insulation. Applicant contends that
additional repair costs are required for the related work of removing an exterior brick wrap
to access the insulation. Applicant also contends that fiberboard sheathing between the
exterior wall and the brick wrap must be sanitized and that this sheathing can only be
accessed by removing the brick wrap.
FEMA states that the exterior wall insulation may be accessed without removal of the
exterior brick wrap, making those costs not eligible for reimbursement. FEMA’s response
included photos and detailed rebuttals of applicant’s arguments regarding the design of the
buildings and the accessibility of the insulation from the interior of the building. FEMA also
states that photos of the units show plywood sheathing that does not require sanitizing, rather
than fiberboard sheathing, as claimed by applicant.
Applicant does not meaningfully explain why the insulation is inaccessible and
requires removal of the brick sheathing. Photos provided by applicant, which are cited by
both parties, appear to show that the insulation is accessible from the inside of the building
units. Further, while applicant represents that buildings of the type at Lumbee Homes
“typically” have fiberboard sheathing that requires replacement after flooding, applicant does
not directly address FEMA’s finding that the buildings do not have damaged fiberboard
sheathing. On this record, applicant is not eligible for costs for exterior wall insulation in
excess of that granted by FEMA.
C.

Floor Repair and Replacement

The floors at the Lumbee Homes buildings consist of two layers of vinyl floor
composite (VTC) tile and mastic adhesive paste over concrete floors. The parties agree that
the lower layer of VTC tiles and mastic contains asbestos. The parties also agree that the
upper layer of VTC tiles and mastic does not contain asbestos and was installed to
encapsulate the asbestos-containing lower layer, thereby preventing the release of asbestos
fibers.
FEMA’s first appeal decision found evidence of damage to some areas of the flooring,
including places that required removal and replacement of the upper layer of VTC and places
that required removal and replacement of both layers. FEMA noted, however, that applicant
did not provide specific dimensions or quantities for damaged tiles. FEMA therefore granted
costs to replace up to twenty-five percent of the lower layer of VTC tiles and mastic,

CBCA 7904-FEMA

9

including removal and disposal of materials containing asbestos, as well as up to 100% of
the upper layer of VTC tiles.
Applicant does not specifically dispute that the asbestos in the lower layer of VTC
tiles and mastic are encapsulated by the upper layer. Applicant also does not specifically
dispute that the upper layer of VTC tiles can be replaced without disturbing the asbestos in
the lower layer of VTC tiles and mastic. Instead, applicant’s consultant states that the flood
water that entered the buildings was “black water,” or “Category 3 water,” which the
consultant characterizes as “toxic.” Anderson Affidavit ¶ 7. Based on the assumption that
the water was toxic, applicant contends that both layers of the flooring require replacement,
as well as additional remediation and monitoring to address asbestos, and that the concrete
subfloor requires decontamination.
As FEMA notes, category 3 water is “grossly contaminated” and includes “water
originating from seawater, ground water, surface water, rising rivers and streams, and winddriven rain from hurricanes and tropical storms.” FEMA’s Exhibit 30 at 9.10 Such water is
not necessarily toxic but is rather “heavily contaminated and can contain pathogens or
toxins.” Id. at 19 (emphasis added). Additionally, guidance cited by applicant, issued by
FEMA in connection with Hurricane Katrina, states that, while vinyl tiles placed over wood
floors should be removed following flooding, vinyl tiles placed over concrete floors should
be removed if damaged, i.e., curled. See FEMA’s Exhibits 31 at 2, 32 (pt. 5) at 8-18.
Applicant assumes, but does not demonstrate, that toxins requiring decontamination
are present in the flooring. Apart from its argument that toxins require replacement of both
layers of all flooring, applicant does not demonstrate that FEMA’s estimate that twenty-five
percent of the lower layer of flooring is damaged and requires replacement is incorrect. On
this record, applicant is not eligible for costs for floor replacement in excess of that granted
by FEMA.

10

FEMA’s Exhibit 30 is a document titled “Report to [the Environmental
Protection Agency (EPA)] on Guidance Documents to Safely Clean, Decontaminate, and
Reoccupy Flood-Damaged Houses,” which appears to be a report provided by consultants
to the EPA. This document cites the S500 Standard and Reference Guide for Professional
Water Damage Restoration, published by the Institute of Inspection, Cleaning, and
Restoration Certification, which categorizes water by level of contamination in categories
1 through 3.

CBCA 7904-FEMA
III.

10

Alternative Requests

As alternatives to finding that the Lumbee Homes buildings are eligible for
replacement, applicant makes two additional requests. First, applicant requests that we direct
HACL and FEMA to “work together (to include a building-by-building joint site inspection,
if necessary) to submit to the Panel a mutually agreeable final repair CEF for each of the four
representative unit types in accordance with FEMA Policy.” Applicant’s Reply to FEMA
Response at 5. As a second alternative, applicant requests that “the Panel order FEMA to
remand this matter for genuine reconsideration of the repair values.” Id. at 17. We find no
basis to grant either of these alternative requests.
The applicable regulation states that “[a]n eligible applicant may request arbitration
to dispute the eligibility for assistance or repayment of assistance.” 44 CFR 206.206(b)
(2022). The regulation does not anticipate that the panel will direct FEMA to assist an
applicant with identifying information to support its application nor does the regulation
anticipate that the panel will order FEMA to conduct a general reconsideration of an
application, absent any specific errors. For these reasons, we deny applicant’s alternative
requests for relief.
Decision
The buildings at issue are not eligible for replacement costs, as the costs for repairs
do not exceed fifty percent of the costs to replace the units. No other relief is granted.

Jonathan L. Kang
JONATHAN L. KANG
Board Judge

Erica S. Beardsley
ERICA S. BEARDSLEY
Board Judge

Marian E. Sullivan
MARIAN E. SULLIVAN
Board Judge

---

Source: Frix Law Library, https://www.frixlaw.com/law-library/documents/agency%3Acbca%3Aaba1835a6998424e. Public record. Not legal advice.
