# MOTION FOR SUMMARY RELIEF DENIED: September 28, 2012

> Briefs, arguments, decisions, and more.

URL: https://www.frixlaw.com/law-library/documents/agency%3Acbca%3Aa78658e70558c84d

## Record

- **Collection:** Agency decision
- **Document type:** Agency decision

## Text

MOTION FOR SUMMARY RELIEF DENIED: September 28, 2012

CBCA 2407

SHAW AREVA MOX SERVICES, LLC,
Appellant,
v.
DEPARTMENT OF ENERGY,
Respondent.
Mark J. Meagher and Joseph G. Martinez of McKenna Long & Aldridge, LLP,
Denver, CO, counsel for Appellant.
Timothy P. Fischer, Savannah River Site Office, National Nuclear Security
Administration, Department of Energy, Aiken, SC; and Keith R. Landolt, Office of the
General Counsel, National Nuclear Security Administration, Department of Energy,
Washington, DC, counsel for Respondent.
Before Board Judges DANIELS (Chairman), POLLACK, and McCANN.
DANIELS, Board Judge.
The Department of Energy (DOE), respondent, moves for summary relief in a case
regarding the reasonableness of costs which Shaw AREVA MOX Services, LLC (MOX
Services), appellant, incurred, and for which it was reimbursed by the agency, under a costtype contract. We deny the motion, for it is premised on an incorrect legal standard and
material facts are in dispute.

CBCA 2407

2
Background

The contract underlying this dispute is for the design, construction, and operation of
the Mixed Oxide Fuel Fabrication Facility, a nuclear processing facility that will take
plutonium which is surplus to the United States’ national security needs and blend it with
depleted uranium to make fuel to be irradiated in commercial power reactors. The facility
is being built at DOE’s Savannah River Site (SRS) near Aiken, South Carolina. The parties
characterize this contract as a cost reimbursement or cost-plus-fixed-fee contract.
The contract was awarded to Duke, COGEMA, Stone & Webster, LLC in March
1999. After a series of mergers and acquisitions, MOX Services assumed the contract in
mid-2006. MOX Services is owned by Shaw Environmental and Infrastructure, LLC and
AREVA NC.
Between 1999 and 2006, much of the design work under the contract was performed
at Charlotte, North Carolina, and other locations. Toward the end of 2006, as the project
neared the start of construction, MOX Services began to relocate operations to Aiken. At
this time, however, uncertainty existed as to when construction would actually begin.
According to MOX Services, the company encountered a number of difficulties in recruiting
and retaining qualified personnel1 to work at the SRS. These difficulties included hesitancy
by some personnel to permanently relocate to the Aiken area, a housing market in which
prices were declining, increased competition for personnel in the nuclear power industry,
uncertainty regarding funding for the contract, and the limited duration of performance by
certain trades or individuals with certain professional expertise.
To address these concerns, MOX Services says that its senior management considered
several alternatives, including increasing base compensation for personnel who would
relocate to Aiken, tasking personnel from other sites to the SRS on business travel, and
developing a policy to address the circumstances. The company ultimately determined that
the last option was preferable. It established a Long Term Temporary Assignment (LTTA)
policy in February 2007. Under this policy, personnel who maintained a permanent residence
more than fifty miles from Aiken and were deemed by company management to fill a critical
role would be reimbursed for a portion of the expenses they incurred for maintaining a
second residence in the Aiken area. Individuals receiving LTTA payments would receive

1

MOX Services says that it “is an unpopulated limited liability company” and
that any references to “personnel” or “employees” are to “personnel employed by either of
MOX Services’ members and assigned to work on the Contract.”

CBCA 2407

3

a monthly lump-sum payment equal to seventy percent of the per diem allowance established
by the General Services Administration for government employees traveling to Aiken.
MOX Services kept the DOE contracting officer informed about its development of
the LTTA program. The company and the contracting officer engaged in many discussions
about the program and its application. The contracting officer expressed concerns that the
information the company provided was not adequate to support the costs claimed. By letter
dated March 7, 2008, the contracting officer proposed that $1,483,023.23 would be
disallowed unless documentation was presented to support these costs.
In August 2008, the contracting officer approved MOX Services’ fourth iteration of
LTTA (now called Jobsite Living Allowance (JLE).) This iteration included at least two
revisions which had been made at the contracting officer’s request. The company capped
reimbursements to an employee at the amount equal to the cost of relocating that employee
to Aiken, but excluding the costs of later relocating him following completion of his work
on the contract. The company also limited the duration of LTTA/JLE benefits to twenty-four
months.
DOE continued to review LTTA/JLE costs. In October 2010, the contracting officer
sent to the company a second notice of intent to disallow costs, identifying $2,172,670 as
unallowable. After discussions with the company, the contracting officer reduced this
amount to $2,097,993.15. The company continued to maintain that these costs are allowable.
On February 1, 2011, the contracting officer sent to MOX Services a decision which held that
the company must make payment to DOE in the amount of $2,097,993.15 “for the . . .
personnel who received inappropriate monetary benefits which were previously invoiced and
paid by the Government.” MOX Services has appealed this decision.
The amount at issue involves payments to approximately half of the sixty-eight
(according to the contracting officer) or sixty-nine (according to MOX Services) personnel
who received LTTA/JLE benefits.
The contracting officer says that some of the employees had agreed to accept
permanent positions in Aiken with lump-sum relocation benefits, and that the LTTA/JLE
payments granted to those individuals were considerably more than the lump-sum benefits
would have been. She also maintains that the company’s documentation shows that some
employees received LTTA/JLE benefits for periods of time which were not temporary –
some lasting as long as five years – in violation of program requirements. She explained,
“The jobs were not temporary in nature. MOX Services took no steps to find replacements
for the individuals filling the positions temporarily, and many of the employees stated that
they intended to stay on the project long term.” Thus, the contracting officer concluded that

CBCA 2407

4

the costs at issue were not reasonable, as that term is understood in Federal Acquisition
Regulation 31.201-3.
MOX Services, on the other hand, says that it “made a determination that payment of
LTTA was appropriate to address: (1) individuals who intended to relocate to Aiken, South
Carolina, but were unable to do so as anticipated because of the housing downturn in 2007
and 2008; and (2) individuals who were offered relocation, but nevertheless indicated they
were not willing to relocate to Aiken.” The company also states that it encouraged personnel
to relocate permanently to Aiken and worked to recruit personnel who were willing to
relocate permanently. MOX Services also notes that the contracting officer did not cite any
justification other than lack of reasonableness for demanding repayment of the funds at issue.
Discussion
Resolving a dispute on a motion for summary relief is appropriate when the moving
party is entitled to judgment as a matter of law, based on undisputed material facts. The
moving party bears the burden of demonstrating the absence of genuine issues of material
fact. All justifiable inferences must be drawn in favor of the nonmovant. Celotex Corp. v.
Catrett, 477 U.S. 317 (1986); Anderson v. Liberty Lobby, Inc., 477 U.S. 242 (1986).
The parties agree that whether the costs in question are reasonable is to be determined
by application of Federal Acquisition Regulation 31.201-3, “Determining reasonableness.”
This provision states:
(a)
A cost is reasonable if, in its nature and amount, it does not
exceed that which would be incurred by a prudent person in the conduct of
competitive business. Reasonableness of specific costs must be examined with
particular care in connection with firms or their separate divisions that may not
be subject to effective competitive restraints.
No presumption of
reasonableness shall be attached to the incurrence of costs by a contractor. If
an initial review of the facts results in a challenge of a specific cost by the
contracting officer or the contracting officer’s representative, the burden of
proof shall be upon the contractor to establish that such cost is reasonable.
(b)
What is reasonable depends upon a variety of considerations and
circumstances, including –
(1)
Whether it is the type of cost generally recognized as
ordinary and necessary for the conduct of the contractor’s business or
the contract performance;

CBCA 2407

5
(2)
Generally accepted sound business practices, arm’s length
bargaining, and Federal and State laws and regulations;
(3)
The contractor’s responsibilities to the Government, other
customers, the owners of the business, employees, and the public at
large; and
(4)
Any significant deviations from the contractor’s
established practices.

48 CFR 31.201-3 (2011).2
According to DOE, because the contracting officer made a thoughtful determination
that the costs in question are not allowable, the Board must deny MOX Services’ appeal of
what the agency characterizes as a discretionary act. In support of this position, DOE cites
the following paragraph from Planning Research Corp. Systems Service Co., NASA BCA
680-11, 81-2 BCA ¶ 15,179, at 75,121-22:
In the absence of an express contract provision or established practice between
the parties controlling the allocability of the costs in question, this Board will
not substitute its judgment for that of the Contracting Officer in the reasonable
exercise of his discretionary authority. Appellant assumed the risk and
responsibility of being wrong when it substituted its judgment for the
Contracting Officer’s.
As MOX Services points out, if this formulation of the law was ever correct, it has not
been so since enactment of the Contract Disputes Act in 1978. This Act states that if a
contracting officer makes specific findings in his decision, they “are not binding in any
subsequent proceeding.” 41 U.S.C. § 7103(e) (Supp. IV 2011) (restating language previously
found at 41 U.S.C. § 605(a)). The Court of Appeals for the Federal Circuit has held, “[T]he
Disputes Act itself suggests that, where an appeal is taken to a board [of contract appeals]
or court, the contracting officer’s award is not to be treated as if it were the unappealed
determination of a lower tribunal which is owed special deference or acceptance on appeal.”
Wilner v. United States, 24 F.3d 1397, 1401 (Fed. Cir. 1994) (en banc) (quoting Assurance
Co. v. United States, 813 F.2d 1202, 1206 (Fed. Cir. 1987)). Further, as explained by the
Court, “[D]e novo review precludes reliance upon the presumed correctness of the decision.

2

This provision has been in effect since May 1987, and thus, throughout the life
of the contract in question.

CBCA 2407

6

. . . [O]nce an action is brought following a contracting officer’s decision, the parties start
in court or before the board with a clean slate.” Id. at 1401-02; see also Bay Shipbuilding
Co. v. Department of Homeland Security, CBCA 54, et al., 07-2 BCA ¶ 33,678, at 166,743.
Thus, now that the contracting officer’s decision has been appealed, it is the
prerogative of the Board, writing on a clean slate, to determine whether the costs which DOE
reimbursed and now believes were not allowable, are allowable or not. DOE acknowledges
that “there could be differing opinions on the reasonableness of the disallowed costs.” This
concession, which we find corroborated by conflicting conclusions of the contracting
officer’s decision and a Shaw Environmental and Infrastructure vice president’s affidavit,
demonstrates that material facts are in dispute and therefore precludes summary relief. The
appeal file submitted by DOE contains documentary evidence which may bear on this issue,
as to each of the employees to whom payment of LTTA/JLE benefits is considered
unreasonable by DOE and reasonable by MOX Services. We have scheduled a hearing at
which we will receive testimony which may elucidate the documentary evidence and the
justification for the conclusions reached by the parties. We will then decide, based on a
preponderance of the evidence, how much of the costs, if any, were reasonably incurred by
the company. See Commercial Contractors, Inc. v. United States, 154 F.3d 1357, 1362 (Fed.
Cir. 1998); Kelly Martinez, IBCA 3140, et al., 97-2 BCA ¶ 29,243, at 145,458; Conner
Brothers Construction Co., VABCA 2519, et al., 95-1 BCA ¶ 27,409, at 136,643 (1994);
Griffin Services, Inc., GSBCA 11171, 92-1 BCA ¶ 24,556, at 122,534.
Decision
DOE’s motion for summary relief is DENIED.

_________________________
STEPHEN M. DANIELS
Board Judge
We concur:

_________________________
HOWARD A. POLLACK
Board Judge

_________________________
R. ANTHONY McCANN
Board Judge

---

Source: Frix Law Library, https://www.frixlaw.com/law-library/documents/agency%3Acbca%3Aa78658e70558c84d. Public record. Not legal advice.
