DENIED: March 25, 2025

CBCA 8124, 8137

1102 COMPANY,
Appellant,
v.
DEPARTMENT OF HOMELAND SECURITY,
Respondent.
Lewis P. Rhodes of Reston Law Group LLP, Reston, VA, counsel for Appellant.
H. Weston Miller and Denise McLane, Office of the General Counsel, Federal
Protective Service, Department of Homeland Security, Philadelphia, PA, counsel for
Respondent.
VERGILIO, Board Judge.
The 1102 Company (contractor) disputes decisions by a contracting officer for the
Department of Homeland Security (agency) denying contractor claims to receive the full
monthly prices in the contract. As initially signed, and through modifications, the contract
was a firm, fixed-price contract for set monthly dollar amounts for specific numbers of hours
for particular personnel positions the contractor was to provide to the agency. The contract
specified the number of hours required for each position and that the contractor was only to
invoice for actual hours performed. The contractor contends that the contract is a firm, fixedprice, lump sum contract under which it is to receive full payment, without regard to the
hours of service provided. In two appeals, here consolidated, the contractor seeks payments
under its lump sum theory, although it did not fill one position for one month, as detailed in
the first appeal, and another position for three months, as detailed in the second appeal. The
contracting officer denied payment for these positions unfilled for four months.

CBCA 8124, 8137

2

The contract also requires contractor personnel to have security clearances. The
individuals the contractor selected to fill the positions lacked clearances for the months the
positions were unfilled. Separate from its “lump sum” theory, the contractor seeks payment,
however, contending that it had hired the individuals who were ready to perform or
performing various tasks and that the Government delayed the finalization of the clearance
process. The contracting officer found no such delay and denied relief.
The contractor has elected the small claims procedure, such that this decision by one
judge is final, conclusive, and non-precedential and may be set aside only in the event of
fraud. 41 U.S.C. § 7106(b) (2018); Rule 52 (48 CFR 6101.52 (2024)). The fixed-price
contract specifies that the contractor is to invoice only the actual number of hours of
performance. The “fixed” price of the contract relates to the hours required for each position
and the monthly rate. The contractor does not receive the full contract price when it does not
provide the number of personnel for each hour required under the contract. The contractor
also contends that the agency improperly impeded the contractor from filling the two
positions by taking excessive time and making errors during the security clearance process.
This argument fails because the record does not establish agency impropriety. The Board
denies each appeal.
Findings of Fact
The contract
The parties entered into a contract under which the contractor provides personnel,
supervision, and services necessary to perform continuous administrative support services
for a base year (June 1, 2021 through May 31, 2022) with option years. Exhibit 5 at 2.1
Under the firm, fixed-price contract, the contractor is to provide services as full time
equivalents at fixed monthly rates for a stated number of hours for identified positions. The
contract requires full-time equivalent work days of eight hours each work day for each
position. Required positions are described by title, qualifications, duties, other such
information, and the number of hours to be worked. Clearances are required for the
personnel here at issue. Exhibits 5 at 19; 10 at 1, 5-7, 26-28.
In addition to establishing fixed monthly prices for each position, associated with a
number of hours of work, the contract specifies that the contractor “is responsible for
submitting accurate invoices that reflect the actual services provided each month. . . . The
Contractor shall compute the invoice price to reflect the actual amount of hours performed.”
Exhibit 5 at 21.

1

All exhibits are in the appeal file.

CBCA 8124, 8137

3

The contract identifies security clearance requirements. Contractor personnel must
complete background investigations and obtain a favorable decision permitting entry on duty
prior to commencing work. Exhibits 5 at 71-73; 10 at 26-28. The agency recognizes that it
responded to a question presented prior to the submission of the proposals when it specified
that the length of time to obtain a favorable entry on duty decision after the submission of
completed security forms is approximately thirty days, with the caveat that the timeline could
vary, depending upon the background check for the individual. Exhibit 26 at 1-2.
Clearances
The contractor provided security information for one individual on July 28, 2023, and
obtained a clearance and approval for entry on duty on August 23, 2023. That individual did
not perform services under the contract prior to early September 2023. Exhibit 11 at 1, 4.
The contractor provided security information for another individual on December 13,
2023. On December 27, 2023, the agency sent an email seeking information for its
background investigation. The email was incorrectly addressed. On January 3, 2024, the
agency sent the email to the correct address. The employee submitted a package for final
adjudication on January 23, 2024. Exhibit 17 at 3-4, 6-7. On January 25 and 26, and
thereafter, the agency reached out to the individual to obtain additional information, because
the security review entailed inquiries and analysis, beyond the initial submission. The
preliminary adjudication was approved on March 1, 2024, which allowed entry on duty. Id.
at 12, 14-15.
The record does not indicate that the second individual would have responded any
earlier than occurred had the email initially been sent to the correct address. The record is
silent on the individual’s availability to respond between December 27 and January 3. The
record further does not support a conclusion that the agency acted improperly in reviewing
the application and ultimately approving the individual’s security clearance. The situation
is consistent with the agency’s pre-proposal comment that some background checks may
require more than thirty days to obtain clearance and approval to work under the contract.
Invoices
The contractor invoiced the agency seeking payment for August 2023. Included in
the amount sought was $10,094 for the “first” individual who had not received a clearance
to enter on duty during the month. The agency did not pay that portion of the invoice.
Exhibit 13.
The contractor invoiced the agency seeking payment for December 2023 and January
2024, reflecting charges for the position which it had not filled. The contractor noted in its

CBCA 8124, 8137

4

invoice for February 2024 that it would be seeking payment for the position which it had not
filled. At issue is the “second” individual who had not yet received the necessary clearance
to begin work under the contract. The contractor sought in a claim, and here seeks, a total
of $16,076.58 relating to the individual who had not received a clearance to enter on duty
during those months. The agency did not pay the portion of the invoices relating to the
individual who lacked clearance and denied the claim for the amount. Exhibits 19, 21, 23.
Discussion
The contractor seeks payment of $10,094 and $16,076.58 under the plain language
of the firm, fixed-price contract. As separate bases for relief, it contends that the agency
acted improperly in using excessive time to grant each clearance.
Firm, fixed-price contract
In asserting that it is entitled to a fixed amount each month, with the amount not tied
to the number or hours worked by personnel, the contractor misconstrues the contract. The
firm, fixed-price aspect refers to the rates for the positions. The contract does not obligate
the agency to pay the contractor a lump sum per month without regard to the hours worked
by each individual for each position. The contract is clear. The contract requires full time
equivalent work days of eight hours each work day for each position. The contractor is to
invoice only for hours worked: “The Contractor is responsible for submitting accurate
invoices that reflect the actual services provided each month. . . . The Contractor shall
compute the invoice price to reflect the actual amount of hours performed.” Exhibit 5 at 20.
The agency has paid the contractor for the actual number of hours of work performed; the
two individuals, for whom the contractor seeks payment, did not “work” under the contract
during the months in question. The contractor has not established a basis for relief under this
theory. There is no agency breach in paying the contractor pursuant to the terms of the
contract.
Obtaining required clearances
The contractor asserts that the agency inhibited its ability to readily staff positions,
given the time the agency expended in granting clearances, including the agency’s use of an
incorrect email address. The contractor has not established agency liability. The contract
requires that individuals possess clearances. It takes time to obtain a clearance. For the
“first” individual, from application submission to approval, the period was less than thirty
days. For the “second” individual, the time from submittal to approval and clearance was
two and one-half months. Given the need for further information to complete the clearance
review, the record does not demonstrate that the time from submission to approval was
excessive. Regarding the initial use of the incorrect email address, the record does not

CBCA 8124, 8137

5

demonstrate that the individual could or would have responded any sooner had the initial
email been properly addressed or that the time for approval would have been shortened. For
both individuals, the record fails to support the theory of an agency breach of duty with
respect to the clearance processing times.
Decision
The Board DENIES the appeals.

Joseph A. Vergilio
JOSEPH A. VERGILIO
Board Judge

---