# In the Matter of HOUSING AUTHORITY OF THE CITY OF

> Briefs, arguments, decisions, and more.

URL: https://www.frixlaw.com/law-library/documents/agency%3Acbca%3A287b0c73476306b2

## Record

- **Collection:** Agency decision
- **Document type:** Agency decision

## Text

August 16, 2023

CBCA 7717-FEMA

In the Matter of HOUSING AUTHORITY OF THE CITY OF
LUMBERTON, NORTH CAROLINA

Antonio R. Pavía-Vidal of Baker, Donelson, Bearman, Caldwell & Berkowitz, PC,
Washington, DC; and Danielle M. Aymond of Baker, Donelson, Bearman, Caldwell &
Berkowitz, PC, Baton Rouge, LA, counsel for Applicant.
Jonathan Ekblad and Will Polk, Office of the General Counsel, North Carolina
Department of Public Safety, Raleigh, NC, counsel for Grantee.
Charles Schexnaildre, Office of Chief Counsel, Federal Emergency Management
Agency, Department of Homeland Security, Baton Rouge, LA; and Anthony Homer, Office
of Chief Counsel, Federal Emergency Management Agency, Department of Homeland
Security, Washington, DC, counsel for Federal Emergency Management Agency.
Before the Arbitration Panel consisting of Board Judges BEARDSLEY (Chair),
GOODMAN, and ZISCHKAU.
GOODMAN, Board Judge, writing for the panel.
The applicant, the Housing Authority of the City of Lumberton, North Carolina,
sought arbitration of a dispute with the Federal Emergency Management Agency (FEMA)
in accordance with section 423 of the Robert T. Stafford Disaster Relief and Emergency
Assistance Act, as amended, 42 U.S.C. § 5189a (2018). The issue before us is whether the
applicant is entitled to the costs of replacing, rather than repairing, public housing units in
accordance with FEMA’s “fifty-percent rule.” We find that the applicant is only eligible for
the costs of repairing the housing units, not the costs for replacement.

CBCA 7717-FEMA

2
Background

The applicant seeks public assistance (PA) funding for thirty units in its Turner
Terrace housing facility, which is a public low-income housing facility located in Robeson
County, North Carolina. The panel conducted a hearing on June 14, 2023.
From October 4 to 24, 2016, Hurricane Matthew caused storms and flooding in
Robeson County and other parts of North Carolina. The units in Turner Terrace were
flooded as a result of the storm. On October 17, 2016, the applicant contracted with ServPro
and K&S Builders for cleanup and remediation of the units.1 ServPro completed its work on
November 18, 2016. K&S Builders completed its work on August 17, 2017. The costs for
cleanup and remediation were included in FEMA project worksheet (PW) 20 for ServPro and
PW 315 for K&S Builders. The scope of work in PW 20 was to restore the condition of the
Turner Terrace housing facility, which included general construction, demolition, water
extraction, and remediation of mold. Exhibit 21 at 9–10. The scope of PW 315 was cleanup
and remediation—to “remove contamination . . . to eliminate or reduce the immediate threat
of significant damage”—which was accomplished by removal of debris. Exhibit 22 at 8.
Neither PW 20 nor PW 315 included costs for asbestos removal. Ultimately, the costs for
PW 20 and PW 315 were paid as emergency work projects under category B funding to
eliminate or lessen threats to lives, public health, or safety, or threats of damage to public or
private property in a cost effective manner. Public Assistance Program and Policy Guide
(PAPPG) (Jan. 2016) at 57.
In February 2017, the applicant hired Matrix Health and Safety Consultants, L.L.C.
(Matrix) to inspect the units for asbestos and lead. Exhibits 15, 16. Matrix found asbestos
in both the ceiling texture and the tan floor tile and mastic. Exhibit 15 at 5. The applicant
also supplied an inspection report, seemingly completed during 2021,2 which found asbestos
to be “oozing” through the tile floor and recommended removal. In 2017, the applicant
claims it obtained a quote to remediate the asbestos present in the units at issue and at other
nearby housing units not the subject of this dispute. The applicant asserts that it divided that
quote by the total number of units, which resulted in an average cost of $22,751.76 per unit.
Applicant’s Reply at 21-22. The applicant then adjusted the unit cost for inflation, to
$23,234.88. See Exhibit 19 at 3, line 33.

1

ServPro was used for insured units while K&S Builders was used for uninsured

units.
2

The report is undated. FEMA notes that “metadata suggests the report was
completed sometime in 2021.” FEMA’s Sur-Reply at 5 n.4.

CBCA 7717-FEMA

3

FEMA denied the asbestos abatement costs, finding the work not eligible. FEMA
determined that asbestos abatement was not needed to repair the flooring because “the floor
tile in the housing units was covered with a second layer of vinyl tile to encapsulate
asbestos,” which FEMA found was a common method of asbestos protection. Exhibit 3 at 6
& n.14. The applicant’s director of operations of public housing at the time of Hurricane
Matthew testified during the arbitration hearing that moisture present in the units due to the
flooding caused the second layer of vinyl tile to start popping up and that, as a result, the tile
and black mastic were cracked, exposing the asbestos material.
In April 2017, the applicant provided a sworn statement as to proof of loss for the
thirteen insured units. Exhibit 20. FEMA’s initial PW 1385 was submitted on May 13,
2017, and mistakenly only captured the damage to the nine housing units that were
uninsured. This PW reported flooding from six to twenty-four inches, which caused mold
damage. It also stated that the kitchen countertops and cabinets, electrical receptacles, and
interior doors and hardware needed to be replaced, the walls needed to be remediated, and
the vinyl and ceramic tile flooring needed to be patched and repaired. The PW stated further
that there would be an attempt to salvage the heating, ventilation and air conditioning
(HVAC) system, hot water heaters, cast iron tubs, sinks, and toilets. Exhibit 7.
In September 2018, Hurricane Florence flooded the facility in Turner Terrace again.
In June and October 2019, over two years after Hurricane Matthew, the applicant hired the
Wooten Company to provide an estimate on the cost to repair thirty-two units3 due to the
damage from Hurricane Matthew. The repair cost was greater than fifty percent of the
replacement costs for each of the thirty units. Based on the Wooten Company’s estimates,
the applicant submitted a request to change the scope of work to include: increasing the
damaged facilities captured from nine to all thirty-two units; asbestos abatement for vinyl
floor tiles; replacing undamaged cast iron bathtubs; upgrading the electrical wire runs and
receptacles; interior wall trim and painting; exterior wall insulation replacement; and HVAC.
Exhibit 13. PW 1385 was updated with new cost estimates. Exhibits 2, 13. The work
included installing new doors, walls, kitchen cabinets and sinks, and vinyl floor tiling and
a new water heater. Thus, the applicant requested that the units be deemed eligible for
replacement rather than repair. See Exhibit 13.

3

The applicant appealed the fifty-percent calculation on thirty-two units, but
before the Board, the applicant amended its position and no longer requested the replacement
costs of two of the thirty-two units.

CBCA 7717-FEMA

4
Discussion

The applicant argues that FEMA’s fifty-percent calculation, which concluded that
each of the thirty units was only eligible for repair costs, did not include all eligible costs.
We review the fifty-percent rule de novo and are not bound by FEMA’s prior determinations.
City of Hattiesburg, Mississippi, CBCA 7017-FEMA, 22-1 BCA ¶ 37,986, at 184,457
(2021).
Pursuant to the PAPPG at 96, the fifty-percent rule is “[t]he comparison of the repair
cost to the replacement costs . . . with the repair cost as the numerator and the replacement
costs as the denominator.” Not included in the repair cost are upgrades of non-damaged
elements even if required by standards, demolition beyond that which is essential to repair
the damaged elements, site work, soft costs, contents, hazard mitigation measures, and
emergency work. PAPPG at 96–97. Not included in the replacement cost is demolition, site
work, soft costs, contents, hazard mitigation measures, and emergency work. Id. at 97.
The applicant does not accept FEMA’s determination that the repair cost does not
exceed fifty percent of the replacement costs. First, the applicant argues that FEMA should
have used the actual quantities in the insurance proof of loss statement rather than the
quantities FEMA used. Second, the applicant believes that FEMA should approve costs for
asbestos remediation and that those costs should be included in FEMA’s fifty-percent-rule
calculation. Third, FEMA’s fifty-percent-rule calculation did not include the costs for water
and mold remediation.
The applicant also argues that regardless of the fifty-percent-rule calculation, repair
is not feasible, and, therefore, the project should be deemed eligible for replacement.
Actual Proof of Loss
Costs are only eligible if, among other things, the costs are “[d]irectly tied to the
performance of eligible work” and “[a]dequately documented.” PAPPG at 21. For work to
be eligible, it must (1) be required as a result of the disaster; (2) be located within the disaster
area, with the exception of sheltering and evacuation activities; and (3) be the legal
responsibility of an eligible applicant. PAPPG at 19. “The [a]pplicant is responsible for
providing documentation to demonstrate its claimed costs are reasonable.” Id. at 22.
According to the applicant, FEMA’s estimated costs contain inaccurate quantities for
several damaged elements which decreased the repair value, as FEMA used quantities which
were inconsistent with the quantities listed in the proof of loss. For example, in the unit at
309 Myrtle Court, the proof of loss listed 692.5 square feet of insulation compared to the 484
square feet listed in FEMA’s cost estimate. Compare Exhibit 20 at 125 (proof of loss) with

CBCA 7717-FEMA

5

Exhibit 10 at 27–28 (FEMA cost estimate). These differences appear throughout the two
documents. FEMA provides no reason why the quantities differ and even indicates in its
reply that FEMA’s cost estimators will review the differences and make changes, if
warranted. FEMA’s Sur-Reply at 2 n.1. We find that the applicant has adequately
documented the costs in the proof of loss statement. However, in order to prevail and
achieve replacement status for any of the units, the applicant must prove additional eligible
repair costs to achieve the required values under the fifty-percent rule. See Applicant’s 50
Percent Rule Demonstrative; Exhibit 26.
Asbestos Abatement
The applicant asserts FEMA should have approved the costs for asbestos abatement
and included them in the fifty-percent calculation, while FEMA maintains that costs for
asbestos abatement are not eligible work. According to FEMA, asbestos abatement was not
required as a result of the disaster because photographs of the units’ floors and the insurance
proof of loss do not indicate damage to the underlying asbestos. In addition, vinyl tiling
containing the asbestos was encapsulated under a second layer of vinyl tiling.
We find the applicant has shown the need for asbestos abatement as a result of the
disaster. If the inspection report recommending the asbestos abatement, which was
conducted after another hurricane and subsequent flooding, was the only evidence before us,
we would not find the applicant had shown the asbestos abatement was eligible work.
However, the inspection report is supported by the 2017 asbestos and lead test which
discovered asbestos in the floor tile and mastic and the statements of a witness who told the
panel that immediately following the storm she found asbestos material to be “oozing” out
of the tile and mastic.
Even though we find the need for asbestos abatement was the result of the disaster,
FEMA is correct that asbestos abatement is not an eligible cost because the applicant has not
adequately documented or supported the costs. The applicant’s claimed asbestos abatement
costs are based on a 2017 quote adjusted for inflation4 that includes costs for remediation of
asbestos present in the units at issue and in other units. The applicant, however, failed to
provide the quote or any other documentation to support the costs claimed but, instead, only
mentioned the cost in two lines in its adjusted cost estimating formula, comments in its reply
brief, and at the hearing. See Applicant’s Reply Brief at 21–22; see also Exhibit 19 at 3,
lines 33–34. There is no information provided on the quantities, hours, or materials that
support the costs. See id. There is also no evidence in the record as to whether the per-unit

4

The applicant has not sufficiently explained why the 2017 quote should be
adjusted for inflation instead of obtaining a more recent quote.

CBCA 7717-FEMA

6

cost is a reasonable reflection of the asbestos abatement costs for the units in Turner Terrace.
Because the applicant has failed to adequately document its costs, we find the costs for
asbestos abatement are ineligible costs.
Water and Mold Remediation
The applicant asserts that remediation for water and mold was improperly excluded
from both the numerator and the denominator in the fifty-percent calculation. FEMA
excluded the water and mold remediation because FEMA classified it as emergency work,
which is not included in the fifty-percent calculation. While not clear, the applicant’s
argument appears to be that because the flood waters remained standing in the housing units
for over two weeks, instead of immediately receding, the remediation of these units cannot
be classified as emergency work.
Under FEMA regulations, emergency work is defined as “work which must be done
immediately to save lives and to protect improved property and public health and safety, or
to avert or lessen the threat of a major disaster.” 44 CFR 206.201 (2022). Emergency work
is performed to “[e]liminate or lessen an immediate threat of additional damage.” PAPPG
at 42. An “immediate threat” is defined as “the threat of additional damage or destruction
from an event which can reasonably be expected to occur within five years.” 44 CFR
206.221(c). FEMA emergency work is funded through category A (debris removal) or
category B (emergency protective measures) grants. PAPPG at 43, 57. Here, the water and
mold remediation work began about three weeks after the flooding receded. This work was
done to protect the property until additional repairs could be completed. Both the applicant
and FEMA agree the water and mold remediation was funded through PW 20 and PW 315,
which were paid as emergency work projects under category B. This work is clearly within
the definition of emergency work and is therefore excluded from the fifty-percent
calculation.
Feasibility
It must also be feasible to repair the facility. A facility is feasible to repair when “it
can perform the function for which it was being used as well as it did immediately prior to
the disaster.” 44 CFR 206.226(f)(1).5 If a facility is “not repairable . . . approved restorative
work may include replacement of the facility”—even if the repair cost does not get over the
replacement threshold under the fifty-percent rule. 44 CFR 206.226(f)(2).

5

Similarly, a facility is feasible to repair if “it can perform the pre-disaster
function as well as it did prior to the incident.” PAPPG at 96.

CBCA 7717-FEMA

7

The applicant argues that the facility is not repairable because of the high cost of flood
proofing the homes through elevation or another means and that, therefore, it must be
replaced. Little evidence was provided to show either that the homes need to be elevated to
be able to house people again or what the total repair costs would be. As such, we do not
find that the units are infeasible to repair.
Decision
We conclude that the units at issue are ineligible for replacement costs, as the cost to
repair does not exceed fifty percent of the cost to replace the units.

Allan H. Goodman
ALLAN H. GOODMAN
Board Judge

Erica S. Beardsley
ERICA S. BEARDSLEY
Board Judge

Jonathan D. Zischkau
JONATHAN D. ZISCHKAU
Board Judge

---

Source: Frix Law Library, https://www.frixlaw.com/law-library/documents/agency%3Acbca%3A287b0c73476306b2. Public record. Not legal advice.
