DENIED: August 7, 2009

CBCA 946

AFR & ASSOCIATES, INC.,
Appellant,
v.
DEPARTMENT OF HOUSING AND URBAN DEVELOPMENT,
Respondent.
Richard L. Moorhouse, Emily C. Parker, and Andrew J. Belofsky of Greenberg
Traurig, LLP, Washington, DC, counsel for Appellant.

Benjamin K. Gibbs, Office of General Counsel, Department of Housing and Urban
Development, Atlanta, GA, counsel for Respondent.
Before Board Judges DANIELS (Chairman), HYATT, and POLLACK.
DANIELS, Board Judge.
The Department of Housing and Urban Development (HUD) declined to exercise its
option to extend for an additional year a contract with AFR & Associates, Inc. (AFR). AFR
submitted a claim in the amount of $3,384,716.92, contending that it is owed this sum
because HUD’s failure to exercise the option was arbitrary and capricious and the product
of bad faith.
The parties have filed cross-motions for summary relief. We conclude, on the basis
of uncontested facts and taking all reasonable inferences in favor of AFR, that HUD’s
determination not to exercise the option had a rational basis and was not tainted by bad faith.

CBCA 946

2

Consequently, we grant the agency’s motion, deny the contractor’s motion, and deny the
appeal.
Background
The Federal Housing Administration (FHA), a bureau of the Department of Housing
and Urban Development (HUD), operates a mortgage insurance program which insures
approved lenders against loss on loans financed for the purchase of single-family residences.
Respondent’s Statement of Uncontested Facts (RSUF) ¶ 1. When these loans go into default,
requiring foreclosure, an FHA-approved lender, to avoid the loss, may submit a benefit claim
to HUD for a portion of its loss and convey the property to HUD. Id. ¶ 2. The properties
conveyed are commonly known as “HUD Homes.” Id. ¶ 3.
After HUD takes possession of each of these houses, it must evaluate the condition
of the house, make any necessary repairs to market it to potential buyers, market it, and sell
it. RSUF ¶ 4. The proceeds from the sale are transferred to the FHA insurance fund, a
largely self-sustaining fund that provides for claims filed by FHA-insured lenders. Id. ¶ 5.
In 1999, HUD decided to have the management and marketing (M&M) functions for
HUD Homes performed by contractors. RSUF ¶ 9. On June 25, 2004, the agency awarded
a contract to AFR to perform these services in the State of Georgia. Id. ¶ 14. The contract
was for a base period running from the effective date of the contract through July 31, 2005.
Appellant’s Statement of Uncontested Facts (ASUF) ¶ 1; Appeal File, Exhibit 1 at 96.
The contract contains Federal Acquisition Regulation clause 52.217-9, “Option to
Extend the Term of the Contract (Mar 2000).” This clause reads:
(a)

The Government may extend the term of this contract by written notice
to the Contractor within 30 days of contract expiration; provided that
the Government gives the Contractor a preliminary written notice of its
intent to extend at least 60 days before the contract expires. The
preliminary notice does not commit the Government to an extension.

(b)

If the Government exercises this option, the extended contract shall be
considered to include this option clause.

(c)

The total duration of this contract, including the exercise of any options
under this clause, shall not exceed 5 years.

Appeal File, Exhibit 1 at 117.

CBCA 946

3

The contract provided for four one-year option periods. ASUF ¶ 1. If the
Government exercised the first option, option year 1 was to run from August 1, 2005,
through July 31, 2006. Each successive option year, if the option was exercised, was to run
from August 1 through July 31 of the following calendar year. Appeal File, Exhibit 1 at 96.
According to the contract, AFR was “to provide Management and Marketing services
to successfully monitor mortgagee compliance, market and manage single family properties
owned by, or in the custody of [HUD], and oversee the sales closing activity, including
proper accounting for HUD’s sales proceeds.” RSUF ¶ 26 (quoting Appeal File, Exhibit 1
at 2). This was AFR’s first M&M service contract. Id. ¶ 17.
M&M contractors were selected and supervised by HUD regional Homeownership
Centers (HOCs). RSUF ¶ 18. Charles Gardner, the head of HUD’s Atlanta HOC, was the
chair of the technical evaluation panel that selected AFR. Id. Within the HOCs were Real
Estate Owned (REO) divisions, which were responsible for the day-to-day management of
single-family programs, including oversight of M&M contractors. Id. ¶ 23. The head of the
Atlanta HOC’s REO division was Janice Cooper. Id. ¶ 24. The government technical
representative (GTR) for AFR’s contract was a branch chief within this division, Debbie
Bonelli-McMahan. Id. ¶ 25. As GTR, Ms. Bonelli-McMahan was responsible for giving
AFR technical advice and guidance related to the work required by the contract. She also
acted as the principal judge of AFR’s performance and as the contracting officer’s
representative in all matters concerning the technical aspects of the contract. Id.
AFR’s proposal included as the major subcontractor National Home Management
Solutions (NHMS). RSUF ¶ 29; Appellant’s Statement of Genuine Issues (ASGI) ¶ 29;
ASUF ¶ 4. NHMS was a new company owned in part by Michael Hardiman. RSUF ¶ 30;
ASUF ¶ 5. AFR selected NHMS as a significant subcontractor because of its extensive
experience, and Mr. Hardiman as project director because of his own extensive experience
in supporting HUD’s M&M requirements. RSUF ¶ 31.
During the start-up phase of the contract, AFR had a number of disputes with
subcontractors, including NHMS. RSUF ¶¶ 32-33. NHMS made demands regarding the
subcontracting arrangement which AFR found unacceptable. Id. ¶ 34; ASGI ¶ 34; ASUF ¶ 7.
HUD also found the demands unacceptable. ASUF ¶ 9. The contract required that AFR
contact HUD prior to changing or substituting a replacement major subcontractor for NHMS.
RSUF ¶ 35. When it became apparent that NHMS would not serve under this contract, HUD
required AFR to obtain a replacement subcontractor for NHMS. Id. ¶ 36; ASUF ¶ 10. The
contracting officer recommended several companies -- among them, First Preston
Management, Inc. (First Preston) -- to replace NHMS. ASUF ¶ 11. AFR selected First
Preston, HUD approved the change, and First Preston served as AFR’s major subcontractor

CBCA 946

4

and serviced the marketing portion of the contract for the duration of the contract. RSUF
¶¶ 38-39; ASUF ¶ 12. The four subcontractors other than NHMS which were named in
AFR’s proposal also fell through, and none of them was actually used during the contract.
RSUF ¶ 40; ASUF ¶ 14.
HUD evaluated AFR’s work monthly. The evaluations were based wholly (according
to HUD) or in part (according to AFR) on the work required by the contract’s lengthy
performance work statement (PWS). RSUF ¶ 44; ASGI ¶ 44. The evaluations included
statistical analyses of fifteen PWS requirements. RSUF ¶ 45. HUD government technical
managers (GTMs) calculated a percentage of successful performance based on a sample size
of property records, compared that percentage to HUD’s “minimum satisfactory rating,” and
produced a “relative score.” For example, if AFR received an 80% acceptable rating on the
sample of customer service calls reviewed for the month, and the minimum satisfactory
rating was 90% under the contract, AFR would receive a relative score of 89 (80/90 = 88.889
or 89). Id. ¶ 47. All fifteen relative scores under the performance metrics were then totaled,
with slightly more weight given to four of the scores because of their significance to HUD.
The overall scores represented performance quality as follows:
Excellent
Good
Fully successful
Needs improvement
Unacceptable

111 or above
101 to 110
100
90 to 99
89 or below

Id. ¶ 48.
HUD also evaluated the work of M&M contractors, including AFR, through random
on-site inspections or on-line reviews of property condition reports. RSUF ¶ 50. The
agency’s evaluations -- both performance metrics and narrative evaluations -- were delivered
to M&M contractors in monthly report cards beginning in March 2005. Id. ¶ 52. Thus, AFR
(and other M&M contractors) received report cards beginning seven months after contract
performance began -- a total of five report cards during the base year of the contract. Id.
¶¶ 53-54. During this year, AFR, in all five report cards, received evaluations of
unacceptable -- the lowest possible score. Id. ¶ 55. AFR was also criticized in the narrative
portion of the report cards for failure to meet the aspects of the PWS that were not scored
numerically. Id. ¶ 56.
Nevertheless, with the expectation that AFR would improve its performance, HUD
on June 30, 2005, exercised the option to extend the contract from August 1, 2005, through
July 31, 2006. RSUF ¶ 58; ASUF ¶ 16. HUD also gave AFR an incentive payment for the

CBCA 946

5

first year’s performance. ASUF ¶ 16. The agency says it gave all M&M contractors
nationwide an incentive payment, “due to an overly generous and erroneous formula.”
Respondent’s Statement of Genuine Issues (RSGI) ¶ 16.
On August 29, 2005, Hurricane Katrina struck the Gulf Coast. In response, HUD
unilaterally modified M&M contracts in the Southeast, including AFR’s contract, to require
contractors to remove certain properties in inventory from the market for evaluation of the
availability of those properties for Katrina evacuees. RSUF ¶ 62; ASUF ¶ 18. HUD
permitted AFR to submit a request for an equitable adjustment to compensate AFR for the
increased work that resulted from this modification. RSUF ¶ 63. AFR did not object to the
modification. Id. ¶ 64. The performance metrics were not to consider the properties that
were removed from the market pursuant to the modification. Id.1 In October 2005,
properties that could not be made habitable for the allowable cost were permitted to be
returned to the market, and in April 2006, all properties not yet rented to evacuees were
permitted to be returned to the market. Id. ¶ 65.
On September 16, 2005 -- shortly after the modification resulting from Katrina -­
HUD sent to AFR a “letter of concern” which articulated the agency’s concerns with ten
areas in which AFR was not improving. RSUF ¶ 59. The letter told AFR that “[t]he serious
nature of these issues requires immediate attention and correction” and requested a response
within ten days. Id. ¶ 60. The letter did not reflect any impact of the Katrina-inspired
modification. Id. ¶ 66.
AFR responded to the letter of concern four weeks after receiving it. RSUF ¶ 67.
AFR’s response purported to challenge HUD’s findings but provided few if any details as
to how the contractor would address the deficiencies noted. Id. ¶ 68. HUD replied on
December 20, 2005, asserting that AFR’s rebuttals were mostly inaccurate and reflected a
lack of understanding of contractual requirements. Id. ¶¶ 69-70; see also ASGI ¶ 69. AFR
did not respond to this letter. RSUF ¶ 71.
On January 13, 2006, the contracting officer personally delivered to AFR’s president
a letter which requested that AFR “re-examine the actions [AFR] has taken in response to
the concerns raised in our previous letters, and take further action as needed to address these

1

AFR asserts that “HUD’s monthly report cards did in fact criticize AFR
regarding . . . properties [that were taken off the market as a result of the modification].”
ASUF ¶ 21. As HUD notes, however, AFR cites only one instance in support of this
assertion, and even there, the criticism was as to the contractor’s record keeping, a basic
contractual requirement, not as to actions regarding the properties themselves. RSGI ¶ 21.

CBCA 946

6

concerns satisfactorily.” RSUF ¶ 72 (quoting Appeal File, Exhibit 43). This letter stated that
the GTR’s assessment of AFR’s performance had worsened since the earlier letters and that
“if HUD’s monitoring of your firm’s performance continues to reflect that AFR’s
performance is not improving, HUD will have to evaluate its options.” Id. ¶ 74 (quoting
Appeal File, Exhibit 43). HUD’s deputy chief procurement officer discussed the situation
with AFR’s president, telling him that HUD would not hesitate to take action if AFR did not
improve its performance. Id. ¶ 75.
AFR presented HUD with a performance improvement plan (PIP) on February 2,
2006. RSUF ¶ 78. HUD had criticized AFR for, among other things, failing to perform
timely initial inspections of properties, failing to perform routine inspections, deviating from
appraiser recommendations without GTR approval, failing to pay taxes and homeowner
association dues timely, not conducting adequate quality control, and not ensuring that
electronic data was comprehensive. The PIP pledged to resolve seventeen issues within
certain time frames. Id. ¶ 79. The contracting officer gave AFR ninety days to demonstrate
performance improvement. Id. ¶ 80. HUD also suggested bi-weekly meetings with AFR to
discuss performance problems. Id. ¶ 81.
Beginning in February 2006, the contracting officer and HOC officials met with AFR
officials frequently -- both formally and informally -- to discuss AFR’s performance
problems and how to resolve them. RSUF ¶ 82. AFR’s performance became better; in each
month from February to June 2006, the contractor achieved a rating of “needs improvement.”
Id. ¶ 84. In March, HUD’s deputy chief procurement officer even commented that AFR was
making good progress. ASGI ¶ 84. AFR never achieved a “fully successful” rating,
however. RSUF ¶ 84.
AFR did not meet all of the representations it made in its PIP. For example, it
acknowledged that it did not perform one hundred percent of initial inspections within
twenty-four hours from its acquisition of properties, as required by the contract; it said that
its average time was twice as long as required. RSUF ¶¶ 85-90. HUD inspections showed,
and AFR acknowledged, that the contractor was not fully complying with the contract’s
health and safety requirements. Id. ¶¶ 91-96. HOC officials felt that although AFR showed
some improvement in its performance, that improvement was not sufficient to warrant
renewal of the contract. Id. ¶ 97. AFR believes that the improvement was sufficient to
warrant renewal. ASGI ¶ 97.
HUD says that:
[t]he PIP period and the frequent contact between the parties resulted in a
heightened realization, in the Atlanta HOC’s collective view, that AFR did not

CBCA 946

7

have the organizational and management capacity to perform under the
Contract. In short, the failures of AFR to adequately improve during this
period of intensive assistance from HUD convinced the HOC and [the
contracting officer] that AFR would not be able to ever adequately perform.
RSUF ¶ 98. AFR contends to the contrary that “HUD’s non-renewal decision was the
culmination of acts taken in . . . bad faith and resulting from an abuse of discretion, not a
realization that . . . AFR was unable to perform the contract.” ASGI ¶ 98.
On April 10, 2006, HUD officials in Atlanta and Washington, D.C., held a conference
call in which they decided to recommend to the contracting officer that she not exercise the
option to extend AFR’s contract for another year. RSUF ¶ 99; ASGI ¶ 99; see also ASUF
¶ 40, RSGI ¶ 40 (questioning whether the decision was actually that the option not be
exercised, rather than to recommend that the contracting officer not exercise the option).
Lengthy discussions continued within the agency after that date, as to how to proceed with
regard to the contract. RSUF ¶ 100.
HUD considered various alternatives. One was to extend the contract for several
months to provide more time in which to evaluate AFR’s performance. RSUF ¶ 103. Others
were to terminate the contract for default or to terminate it for the convenience of the
Government. Id. ¶ 104. A representative of the Small Business Administration with whom
the contracting officer consulted urged that the default termination alternative not be pursued.
Id.
At a meeting held on April 24, 2006, Mr. Gardner, the director of the Atlanta HOC,
told AFR’s president, “I’ve one run [sic] M&M contractor out of town and I have no problem
running AFR [out of town].” ASUF ¶ 44; RSGI ¶ 44; Appellant’s Response to RSGI ¶ 44.
On May 31, 2006, HUD sent to AFR a “preliminary notice that HUD may exercise
option year two on [your] contract.” The notice cautioned, “This notice does not commit
HUD to the extension. If the option is exercised, a modification to your contract . . . will be
issued.” Appeal File, Exhibit 66.
HUD did not send a cure notice to AFR. It believed that because it had pointed out
its concerns to the contractor in many letters and orally, and AFR had not met its own
representations in the PIP, a cure notice was necessary only as a preliminary step to a
termination for default. RSUF ¶ 101.
In its proposed Statement of Uncontested Facts, AFR asserts that HUD made several
errors in its evaluation of the contractor’s performance. ASUF ¶¶ 21-39. In response, HUD

CBCA 946

8

maintains that the criticisms are invalid, and that even if they were correct, the allegations
are immaterial because AFR’s performance was deficient in many areas not mentioned in the
Statement. RSGI ¶¶ 21-39. In this regard, we note the following: Prior to the end of July
2006, HUD made numerical evaluations of AFR’s performance for each month from March
2005 to June 2006, and also for the fourth quarter of federal fiscal year 2005 and the each of
the first three quarters of federal fiscal year 2006. Each of these evaluations resulted in a
score of either “unacceptable” or “needs improvement.” Appeal File, Exhibits 5, 8, 11, 17,
19, 30, 34, 36, 38, 40, 42, 45, 52, 53, 55, 61, 63, 64, 69, 73. AFR contested the scores for
only the first four of these months. In contesting the scores, AFR maintained that its score
should be higher than the one assigned, but should still rank in the “unacceptable” range. Id.,
Exhibits 7, 9, 15, 18. In responding specifically to other evaluation scores, AFR accepted
HUD’s number and promised to strive to reach a “fully successful” score in the future. Id.,
Exhibits 27, 37, 44, 73.
Because HUD’s internal deliberation process involved lengthy debate, discussion, and
documentation, the final acceptance by the Deputy Federal Housing Commissioner of the
decision not to exercise the option did not occur until July 28, 2006, three days before the
then-existing option year was to end. RSUF ¶ 107.
HUD informed AFR by telephone on July 28, 2006 -- one business day before the
expiration of the first option year under the contract -- that it would not exercise the option
for an additional year of performance under the contract. ASUF ¶ 46. The contracting
officer modified the contract on July 31 to implement the plan for transition to a new
contractor. Id. The contracting officer was asked in her deposition, “Who made the decision
not to renew AFR’s contract?” She responded, “[I]t was my decision based on all the input
I was getting from my customer.” She acknowledged that during the long internal discussion
as to how to proceed, she had at one point suggested extending the contract for a short period
of time to give AFR further opportunity to improve its performance. Ultimately, however,
“my technical experts [naming HOC officials Gardner, Cooper, and Bonelli-McMahan]
convinced me that wasn’t possible.” “My customer[s] who were technical experts were of
the . . . adamant and reasoned and documented opinion that AFR was not doing this
particular function satisfactorily.” RSUF, Exhibit 13 at 80-81, 121; see also ASUF ¶¶ 42-43
(contracting officer relied on advice from HOC staff and others in authority in determining
not to exercise the option).
In lieu of extending AFR’s contract, HUD identified three potential replacement
M&M contractors who could handle the work in Georgia. RSUF ¶ 108. One of the agency’s
criteria for selecting the three contractors was that the contractor was “performing
consistently at a satisfactory level or better.” ASUF ¶ 48. HUD selected PEMCO, Ltd. from
among these contractors to perform the work. Id. ¶ 109; ASGI ¶ 109; Appeal File, Exhibit

CBCA 946

9

86. AFR asserts that PEMCO’s overall score for the entire period of its then-current M&M
contract fell in the “needs improvement” range. ASUF ¶ 49. While this is true, it is also true,
as HUD points out, that PEMCO’s score had been improving over time and had been in the
“good” range during the most recent rating quarter. HUD believed that the earlier, lower
ratings may have been attributable to errors in its sampling methodology regarding this
contractor’s inventory of properties. RSGI ¶ 49 (referencing ASUF, Exhibit 34 at 2).
In January 2007, Ms. Cooper, who had been the head of the Atlanta HOC’s REO
division, retired from government service and launched a consulting firm. Her clients consist
almost entirely of entities that hold contracts with HUD; among them are PEMCO and
NHMS. Ms. Cooper’s work for PEMCO involves that firm’s M&M work in Georgia. ASUF
¶ 53.
On March 22, 2007, AFR sent to the contracting officer a “claim for breach of
contract damages for failure to exercise second option year.” The claim, which was certified,
was in the amount of $3,384,716.92. Appeal File, Exhibit 99. The contracting officer denied
the claim on August 1, 2007, asserting, “HUD’s actions in the non-exercise of the option
were consistent with the law and, accordingly, AFR does not have a basis for a claim in this
matter.” Id., Exhibit 100 at 1. AFR appealed her decision on October 26, 2007.
Discussion
Each party has asked the Board to resolve this appeal by granting its own motion for
summary relief and denying the opposing party’s motion. Resolving a dispute on a motion
for summary relief is appropriate when the moving party is entitled to judgment as a matter
of law, based on undisputed material facts. The moving party bears the burden of
demonstrating the absence of genuine issues of material fact. All justifiable inferences must
be drawn in favor of the nonmovant. Celotex Corp. v. Catrett, 477 U.S. 317 (1986);
Anderson v. Liberty Lobby, Inc., 477 U.S. 242 (1986). Nevertheless, to defeat a motion for

summary relief, the nonmoving party must come forward with specific facts showing the
existence of a genuine issue for trial. “Where the record taken as a whole could not lead a
rational trier of fact to find for the non-moving party, there is no ‘genuine issue for trial.’”
Matsushita Electric Industrial Co. v. Zenith Radio Corp., 475 U.S. 574, 587 (1986).
When both parties move for summary relief, each party’s motion must be evaluated
on its own merits and all reasonable inferences must be resolved against the party whose
motion is under consideration. First Commerce Corp. v. United States, 335 F.3d 1373, 1379
(Fed. Cir. 2003); DeMarini Sports, Inc. v. Worth, Inc., 239 F.3d 1314, 1322 (Fed. Cir.
2001). The mere fact that the parties have cross-moved for summary relief does not impel

CBCA 946

10

a grant of one of the motions; each motion must be independently assessed on its own merit.
California v. United States, 271 F.3d 1377, 1380 (Fed. Cir. 2001).
The Board has previously explained the law governing the merits of this case:
Because an option clause does not obligate the Government to exercise an
option, but rather gives the Government the discretion to decide whether to
engage in such exercise, unless the contract says otherwise, the Government’s
discretion as to the exercise of an option is nearly complete. Integral Systems,
Inc. v. Department of Commerce, GSBCA 16321-COM, 05-2 BCA ¶ 32,984,
at 163,472. Case law establishes that the Government’s decision not to
exercise an option can provide a vehicle for relief only if the contractor proves
that the decision was made in bad faith or was so arbitrary or capricious as to
constitute an abuse of discretion. Aspen Helicopters, Inc. v. Department of
Commerce, GSBCA 13258-COM, 99-2 BCA ¶ 30,581, at 151,024; IMS
Engineers-Architects, P.C., ASBCA 53471, 06-1 BCA ¶ 33,231, at 164,674
[aff’d sub nom. IMS Engineers-Architects, P.C. v. Geren, 274 F. App’x 898
(Fed. Cir. 2008)]; James Hovanec, PSBCA 4767, 04-2 BCA ¶ 32,805, at
162,262.
Greenlee Construction, Inc. v. General Services Administration, CBCA 416, 07-1 BCA
¶ 33,514, at 166,062; see also Blackstone Consulting, Inc. v. General Services
Administration, CBCA 718, 09-1 BCA ¶ 34,103, at 168,636; Innovative (PBX) Telephone
Services, Inc. v. Department of Veterans Affairs, CBCA 44, et al., 08-1 BCA ¶ 33,854, at
167,584.
A contractor who asserts that a government official was motivated by bad faith
in the conduct of his duties bears the burden of proving its assertion by clear
and convincing evidence -- “evidence which produces in the mind of the trier
of fact an abiding conviction that the truth of a factual contention is highly
probable.”
Greenlee Construction, 07-1 BCA at 166,062. In setting forth this standard, the Board relied
on the decision of the Court of Appeals for the Federal Circuit in Am-Pro Protective Agency,
Inc. v. United States, 281 F.3d 1234, 1239-40 (Fed. Cir. 2002). In so doing, we expressly
declined to adopt a lesser standard advocated by the Court of Federal Claims in Tecom, Inc.
v. United States, 66 Fed. Cl. 736, 757-72 (2005). In following Am-Pro rather than Tecom,
we explained that the Court of Appeals for the Federal Circuit is our appellate authority and
its decisions are binding on us, whereas the Court of Federal Claims merely has coordinate

CBCA 946

11

jurisdiction to our own. Greenlee Construction, 07-1 BCA at 166,064 n.7.2 The Federal
Circuit has amplified its Am-Pro holding in Galen Medical Associates, Inc. v. United States,
369 F.3d 1324, 1330 (Fed. Cir. 2004) (quotations and citations omitted):
[W]hen a bidder alleges bad faith, in order to overcome the presumption of
good faith on behalf of the government, the proof must be almost irrefragable.
“Almost irrefragable proof” amounts to clear and convincing evidence. In the
cases where the court has considered allegations of bad faith, the necessary
“irrefragable proof” has been equated with evidence of some specific intent to
injure the plaintiff.
In determining whether the decision not to exercise the option was so arbitrary or
capricious as to constitute an abuse of discretion, we consider -­
(1) evidence of subjective bad faith on the part of the government official, (2)
whether there is a reasonable, contract-related basis for the official’s decision,
(3) the amount of discretion given to the official, and (4) whether the official
violated an applicable statute or regulation.
McDonnell Douglas Corp. v. United States, 182 F.3d 1319, 1326 (Fed. Cir. 1999) (citing
United States Fidelity & Guaranty Co. v. United States, 676 F.2d 622, 630 (Ct. Cl. 1982)).
Whether HUD acted in bad faith will be considered under the standards described above.
AFR does not contend that HUD violated a statute or regulation in not exercising the option.
Thus, our inquiry into whether the agency’s decision was arbitrary or capricious will focus
on factors (2) and (3).

2

AFR, which reiterates the arguments for a Tecom standard made unsuccessfully
by the appellant in Greenlee, also contends that Federal Circuit decisions demonstrate that
the Board is bound by decisions of the Court of Federal Claims. AFR cites for this
proposition several decisions which were issued by the United States Court of Claims.
Appellant’s Memorandum in Response to HUD’s Opposition to AFR’s Cross-Motion for
Summary Relief and HUD’s Reply Brief in Support of HUD’s Motion for Summary Relief
at 4. The Court of Claims is a different court from the Court of Federal Claims. The Court
of Claims was a predecessor court to the Federal Circuit, which accepts its decisions as
binding precedent. South Corp. v. United States, 690 F.2d 1368, 1369 (Fed. Cir. 1982) (en
banc). The Federal Courts Improvement Act of 1982, Pub. L. No. 97-164, which created the
Federal Circuit, also established the Court of Federal Claims (then called the United States
Claims Court) as a distinct, trial-level entity.

CBCA 946

12

As to factor (3), the Court of Appeals has explained, “Where the Government is
entitled to exercise its discretion, the ‘plaintiff has an unusually heavy burden of proof in
showing that the determination made . . . was arbitrary and capricious.’” Balboa Insurance
Co. v. United States, 775 F.2d 1158, 1164 (Fed. Cir. 1985) (quoting Royal Indemnity Co. v.
United States, 529 F.2d 1312, 1320 (Ct. Cl. 1976)). “[T]he greater the discretion granted to
a contracting officer, the more difficult it will be to prove the decision was arbitrary and
capricious.” Galen, 369 F.3d at 1330 (quoting Burroughs Corp. v. United States, 617 F.2d
590, 597 (Ct. Cl. 1980)). The Government has the right under a standard option clause such
as the one in this contract to exercise, or not to exercise, the option; the Government is not
under an obligation to exercise it. Continental Collection & Disposal, Inc. v. United States,
29 Fed. Cl. 644, 650 (1993). The discretion to exercise a contract option or not has therefore
been characterized as “broad.” IMS Engineers-Architects, 06-1 BCA at 164,672;
Kirk/Marsland Advertising, Inc., ASBCA 51075, 99-2 BCA ¶ 30,439, at 150,408; Plum Run,
Inc., ASBCA 46091, et al., 97-2 BCA ¶ 29,193, at 145,230. Consequently, proving that the
decision not to exercise the option was arbitrary or capricious will be difficult. We will
examine factor (2), whether there was a reasonable, contract-related basis for the decision,
in that light.
From the uncontested facts in this case, the picture that appears is essentially the one
painted by the agency: HUD evaluated AFR’s work on a regular, comprehensive basis and
consistently determined that the work was unacceptable or needed improvement. The agency
noted its concerns in a series of letters and met with the contractor frequently, during the first
half of 2006, in an effort to prompt better performance. AFR’s performance did improve,
but it never reached the fully successful level, and it did not meet the goals the contractor set
in a performance improvement plan it devised itself. HUD gave extensive consideration as
to how to proceed with this contract. It reviewed several alternatives as a part of this process,
which involved officials in both Atlanta and Washington. The contracting officer was not
the sole participant in this review, but she was an active participant. She listened to the
advice given by program officials and ultimately trusted their judgment that exercising the
option to continue the contract for another year would not be in the agency’s best interest.
These uncontested facts do not reveal any bad faith on the part of the agency, or any abuse
of discretion, in the determination not to exercise the option. See Optimal Data Corp.,
NASA BCA 381-2, 85-1 BCA ¶ 17,760, at 88,719 (1984), reconsideration denied, 85-2 BCA
¶ 18,165 (contractor’s unsatisfactory performance good cause for not exercising option).
AFR takes issue with this view, but in so doing, it merely nibbles around the edges
of the picture described in the previous paragraph. AFR “conducted exhaustive discovery,
including ten depositions of high-ranking HUD officials, and [received from HUD the
production of] hundreds of confidential documents.” Respondent’s Memorandum in Support
of Its Motion for Summary Relief at 2 (uncontested). Even with all this information at its

CBCA 946

13

disposal, the contractor has not presented any evidence which would lead us reasonably to
conclude that HUD acted in bad faith or abused its discretion in not renewing AFR’s
contract.
AFR urges that the problems it sees in the agency’s actions reflect both bad faith and
abuse of discretion, so we will examine the assertions as to both aspects of the appeal. Much
of AFR’s effort addresses imperfections in the scoring system HUD used in the metric part
of its evaluations. Even if all the contractor’s assertions as to the alleged imperfections are
correct, however, AFR has not shown how the scores could be adjusted to a fully successful
level; to the contrary, when the contractor did ask for adjustments, while the contract was in
effect, those changes would merely have increased scores to be higher but still unacceptable.
Similarly, AFR contends that HUD did not consider, in its evaluation of the contractor’s
performance, the number of houses AFR sold or the total revenue it returned to FHA funds
(said to be about $600 million by HUD and about $700 million by AFR; see ASUF ¶ 17;
RSGI ¶ 17). The contractor has failed to explain, however, whether these figures represented
good, bad, or mediocre performance. Thus, the fact that AFR sold many houses does not
show that HUD’s evaluation was made in bad faith or arbitrary or capricious. And the fact
that HUD gave AFR an incentive payment for its first year’s performance does not invalidate
the comprehensive monthly evaluations, given the agency’s explanation that the payment was
based on “an overly generous and erroneous formula.”
AFR also sees HUD’s failure to give the contractor a cure notice to be an indication
of bad faith or arbitrary action. If any statute, regulation, or case law supports the theory that
a cure notice is a necessary prerequisite to a determination not to exercise an option,
however, AFR does not bring it to our attention. HUD did give AFR much notice, over a
number of months, in both letters and meetings, that it was dissatisfied with the contractor’s
performance. Whether the written communications should have been denominated “letters
of concern” (as HUD calls them) or not (as advocated by AFR), the communications clearly
demonstrated concern. AFR recognized the criticisms; it made numerous promises to
improve and even drafted and sent to HUD a performance improvement plan. The contractor
failed to measure up to the standards it set for itself in its own performance plan, however.
AFR also finds perplexing HUD’s decision not to exercise the option, less than two
months after having sent a preliminary notice that it would exercise the option. We find no
legal fault in the agency’s actions. By the terms of a contract clause, HUD could not exercise
the option unless it had sent the preliminary notice -- but sending the notice “[did] not
commit the Government to an extension” of the contract. Continental Collection & Disposal,
29 Fed. Cl. at 650. Similarly, HUD’s determination to renew the contracts of other M&M
contractors who were not performing well, at the same time that it did not renew AFR’s
contract, does not show bad faith or an abuse of discretion. The performance of other

CBCA 946

14

contractors has no bearing on whether AFR reached a level of performance that was
acceptable to HUD. An agency “has the right to insist upon the quality of performance called
for by the contract even though it may have accepted, under previous or future contracts, a
lower level of quality than that to which it was entitled.” All South Properties, Inc.,
HUDBCA 92-G-7604-C12, et al., 97-2 BCA ¶ 29,329, at 145,818; see also Patricia J.
Stevens, PSBCA 3272, 94-1 BCA ¶ 26,419, at 131,430 (1993), reconsideration denied, 94-2
BCA ¶ 26,951. And contrary to AFR’s assertion, there is uncontested evidence that the
contractor selected by HUD to replace AFR in Georgia was higher-rated than AFR.
AFR’s president testified in his deposition that HUD’s contracting officer had “always
been fair with me” and would never intend to injure him or AFR. RSUF, Exhibit 12 at 43­
44. Perhaps because the president had such respect for the contracting officer, the contractor
urges that the contracting officer must have abdicated her responsibility, and improperly
deferred to others in the agency, in deciding not to exercise the option. As the case law
makes clear, however, the requirement for a decision by the contracting officer does not
preclude the obtaining of advice from others within the agency. Pacific Architects &
Engineers Inc. v. United States, 491 F.2d 734, 744 (Ct. Cl. 1974); J. A. Terteling & Sons, Inc.
v. United States, 390 F.2d 926, 927 (Ct. Cl. 1968).
The Congress understood in establishing this requirement that -­
practicability dictates that the extent to which the contracting officer relies on
his own judgment or abides by the advice or determination of others is
dependent on a variety of factors, including the officer’s personal knowledge,
capability, and executive qualities, as well as the nature of the particular
procurement. With so many variables, it is impossible to generalize as to what
the contracting officer’s role should be in all situations. In addition, it is
unrealistic to suggest that the various levels of management responsible for the
projects and programs to which a contract relates and that bear the
responsibility for the propriety and wisdom of the agency’s action should at all
times remain aloof from the manner in which contracts are administered and
contractual actions are taken.
S. Rep. No. 95-1118, at 11 (1978), as reprinted in 1978 U.S.C.C.A.N. 5255.
Applying this reasoning, one of our predecessor boards of contract appeals held,
“While the decision must be that of the [contracting officer], the courts have recognized that
the complexities of Government contracting may require extensive consultation, coordination
and other staff assistance.” Mike Gibson & Mike Bearden, Co-Trustees in Dissolution of
Delta Products Co., AGBCA 88-139-1, 93-2 BCA ¶ 25,615, at 127,508 (1992). As in

CBCA 946

15

Gibson & Bearden, the contracting officer here “read [the decision] in detail, consulted with
others within the agency, and agreed with the decision before signing it.” Id. at 127,509.
Indeed, the contracting officer here was extensively involved in the long, internal agency
deliberations about the fate of AFR’s contract. She ultimately accepted the judgment of her
“technical experts” -- the agency program personnel who dealt with the contractor on a
regular basis -- that the contract should not be extended because AFR “was not doing this
particular function satisfactorily.” This does not constitute an abdication of responsibility;
rather, it seems to have been a thoughtful response to a difficult situation.
Finally, AFR sees bad faith and an abuse of discretion in the actions of two of the
program personnel on whose advice the contracting officer relied, Mr. Gardner and Ms.
Cooper. Mr. Gardner told AFR’s president, “I’ve one run [sic] M&M contractor out of town
and I have no problem running AFR [out of town].” This comment was intemperate. It was,
however, an isolated statement, unlike the “virtual rancid cornucopia of . . . communications
evidencing a specific intent by key government officials to injure” the contractor that was
present in North Star Alaska Housing Corp. v. United States, 76 Fed. Cl. 158, 190-93 (2007).
It was also out of character for Mr. Gardner, according to the deposition testimony of AFR
representatives -- the company’s president said that he had had “[v]ery good” experience
with Mr. Gardner on prior contracts, and consultant Christopher Lord said that he had known
Gardner for “some time” and had “never had a problem with him” and had never known him
to treat a contractor unfairly. RSUF, Exhibits 12 at 15, 16 at 104-05. In the overall context
of the uncontested facts before us, Mr. Gardner’s comment standing alone does not provide
a sufficient basis for a finding of bad faith on the part of HUD. Furthermore, “even if it were
true that Government officials had animus towards [the contractor], the existence of such
animus can not obviate the clear reasonable basis for permitting the contract to end without
the exercise of options.” Pennyrile Plumbing, Inc., ASBCA 44555, et al., 96-1 BCA
¶ 28,044, at 140,029 (1995).
AFR’s other allegation that Mr. Gardner showed bad faith toward it is even more
attenuated. Mr. Gardner was the chair of the technical evaluation panel that selected AFR
for award. The major subcontractor identified in AFR’s proposal was NHMS. Mr. Gardner
was also involved, prior to the inception of contract performance, in directing AFR to find
a subcontractor to replace NHMS as the major subcontractor under the contract. HUD gave
AFR only a short period of time in which to make this replacement. The predicament in
which both the contractor and the agency found themselves at that time was caused by a
dispute between the contractor and its subcontractor. We do not understand why the agency
should have been responsible for this predicament, why it shows that Mr. Gardner favored
NHMS over AFR, or why it was unreasonable for the agency to insist that AFR begin quickly
the performance it had promised.

CBCA 946

16

The problem asserted with regard to Ms. Cooper is also worthy of only brief mention.
Ms. Cooper retired from government service at the end of 2006, five months after HUD had
decided not to exercise the option to continue AFR’s contract. AFR believes that in doing
consulting work in 2007 for M&M contractors, including AFR’s successor M&M contractor
in Georgia (PEMCO), Ms. Cooper violated ethical guidelines set forth in 18 U.S.C. § 207.
Whether Ms. Cooper violated these guidelines or not has no bearing on whether she showed
bad faith toward AFR in recommending that the option not be exercised. AFR’s president
testified at his deposition that Ms. Cooper was a “taskmaster” -- a “[d]rill sergeant type” -­
but that he found her to be “fair” in her dealings with him and AFR. RSUF, Exhibit 12 at
17. We do not see anything in the record before us on the cross-motions that indicates she
behaved differently as to the option exercise issue.
Decision
HUD’s motion for summary relief is granted. AFR’s cross-motion for summary relief
is denied. The appeal is DENIED.

_________________________
STEPHEN M. DANIELS
Board Judge
We concur:

_________________________
CATHERINE B. HYATT
Board Judge

_________________________
HOWARD A. POLLACK
Board Judge

---