April 10, 2024

CBCA 7990-FEMA

In the Matter of ST. MARK’S EPISCOPAL CHURCH

Stewart L. Robinson, Project Manager of St. Mark’s Episcopal Church, Palatka, FL,
appearing for Applicant.
Stephanie Stachowicz (Twomey), General Counsel, and Dezirée T. Elliott, Senior
Attorney, Florida Division of Emergency Management, Tallahassee, FL, counsel for Grantee;
and Melissa Shirah, Recovery Bureau Chief, Florida Division of Emergency Management,
Tallahassee, FL, appearing for Grantee.
Shahnam Thompson, Office of Chief Counsel, Federal Emergency Management
Agency, Department of Homeland Security, Washington, DC, counsel for Federal
Emergency Management Agency.
Before the Arbitration Panel consisting of Board Judges SHERIDAN, ZISCHKAU, and
O’ROURKE.
SHERIDAN, Board Judge, writing for the Panel.
Pursuant to the arbitration provisions of the Robert T. Stafford Disaster Relief and
Emergency Assistance Act (Stafford Act), 42 U.S.C. §§ 5121–5207 (2018), St. Mark’s
Episcopal Church (St. Mark’s or applicant) seeks $133,881.48 in public assistance (PA)
funding from the Federal Emergency Management Agency (FEMA) for costs associated with
exterior and interior damage caused by Hurricane Irma. For the reasons stated below, we
grant the applicant’s request in part.

CBCA 7990-FEMA

2
Background

In September 2017, Hurricane Irma, a category four hurricane, struck the southern
United States and caused widespread destruction throughout Florida’s peninsula. On
September 10, 2017, the President declared the event a major disaster, FEMA-4337-DR-FL,
entitling eligible entities to apply for public assistance under section 501(b) of the Stafford
Act. The incident period for Hurricane Irma’s disaster declaration was September 4 through
October 18, 2017.
St. Mark’s is in Palatka, Florida, a small town of fewer than 75,000 residents located
in central Florida. St. Mark’s property consists of five buildings, four of which were
damaged in Hurricane Irma: (1) the main Church Building (P1); (2) Parish Hall (P2);1 (3) the
Old Rectory, which is used as a “maintenance workshop” that stored tools and materials
(P3); and (4) James House, another storage facility (P5).2 Applicant’s Reply at 2. P3 was
not being used by St. Mark’s at the time of the disaster. St. Mark’s claims that during
Hurricane Irma all four of these buildings sustained exterior roof damage, causing leakage.
Additionally, the applicant states that due to a combination of roof leakage and a power
outage, the interior walls and ceilings of P1 developed condensation that led to mold
forming. However, the applicant has admitted that its pre-disaster HVAC unit was oversized
for the dimensions of P1. Request for Arbitration (RFA) at 4.
Shortly after the hurricane, on October 3, 2017, the applicant’s insurance adjuster
arrived at the church’s property to inspect the damage caused by the storm. The initial report
consisted of photographs of the property damage. FEMA’s Exhibit 3. For P1, the images
showed that all of the leaks occurred near flashing on the roof3 and confirmed the
condensation accumulation in the interior of the facility. Id. at 6-12. The photos taken of P2,
P3, and P5 revealed wind damage to the roof’s shingles. Id. at 40-43, 89-90, 114-19. This
report was revised in 2018 and 2020 to include estimated repair costs that were omitted from
1

St. Mark’s does not provide details in its briefs about the function of Parish
Hall. However, St. Mark’s website indicates that Parish Hall is used to host receptions and
other social gatherings.
St. Mark’s Episcopal Church, Fellowship,
https://stmarkspalatka.org/fellowship/ (last visited Apr. 9, 2024).
2

There is no mention of the building that would be known as “P4” in the parties’
briefs, but the insurance adjuster’s report shows that P4 is the church’s office building.
FEMA’s Exhibit 3 at 108. This claim does not address any damage to P4.
3

Roof flashing is used to direct water away from critical areas of the roof,
wherever the roof plane meets a vertical surface like a wall or dormer. Flashing is typically
made from a thin layer of galvanized steel to prevent water from finding its way inside.

CBCA 7990-FEMA

3

the initial report. FEMA’s Exhibit 1 at 3. The damages were also documented in a
“Damage, Descriptions, and Dimensions” (DDD) report prepared by FEMA. FEMA’s
Exhibit 10.
Subsequently, St. Mark’s requested price proposals from contractors to determine
what the cost would be to replace each building’s asphalt shingle roof with a metal roof and
to install a moisture reduction system in P1 that includes an underfloor spray-foam barrier,
ductwork, and a modification to the HVAC control system. During the pre-installation
inspection by the applicant’s contractor, the contractor noted signs of “age” showing on P1’s
roof. RFA at 41.
In early 2020, St. Mark’s began the process of submitting a Hazard Mitigation
Proposal (HMP) to FEMA. RFA at 12. On June 25, 2020, the Florida Division of
Emergency Management (FDEM or recipient), on behalf of St. Mark’s, sent FEMA an
amended HMP that requested $126,035.84 in mitigation funding—$11,624 for a moisture
reduction system in P1 and $110,911.84 for full roof replacements for P1, P2, and P3.4 Id.
at 13; FEMA Exhibit 4 at 3. FEMA denied $118,749 of the requested amount in a
determination memorandum (DM), concluding that only $7785.86 of the costs were eligible
for reimbursement. FEMA’s Exhibit 4 at 3. In doing so, FEMA concluded that a majority
of the damage to the buildings resulted from deferred maintenance rather than Hurricane
Irma. Id. at 9. St. Mark’s appealed this determination by letter on October 1, 2020,
requesting $112,945.5 Exhibit 9 at 10-20. FEMA issued a first appeal decision on
September 9, 2021, partially granting the appeal but returning the case to the FEMA Region
IV Public Assistance Branch to recalculate the eligible mitigation costs. FEMA’s Exhibit 1
at 7.
FEMA issued a second DM on August 4, 2022, that, among other things, determined
that P3 did not qualify as an eligible facility and analyzed whether each building’s roof
replacement was cost-effective. FEMA’s Exhibit 12. Again, FEMA denied a majority of
the requested costs, and St. Mark’s appealed. In response to the second appeal by the
applicant, FEMA issued a request for information (RFI) to St. Mark’s seeking documentation
that would support the eligibility of P3, information that would establish eligibility for the
metal roof replacements, and clarification on the amount in dispute. FEMA’s Exhibit 6 at
1-3. Instead of responding to FEMA’s RFI, St. Mark’s withdrew its appeal on January 18,
2024, and filed a request for arbitration (RFA) at the Board seeking $133,881.48 in
4

Neither the applicant nor FEMA addresses why P5 was not included in the

HMP.
5

It is not clear from the record why St. Mark’s only appealed $112,945.15,
$5804.83 less than the amount FEMA denied in its initial DM.

CBCA 7990-FEMA

4

reimbursement costs for two mitigation measures: (1) installation of a moisture reduction
system in P1, and (2) full metal roof replacements for P1, P2, P3, and P5. The RFA
described the costs as:
1.

P1 Roof Replacement: Roof Contract Amount ($87,387) - Cost to
Repair In-Kind ($10,272.89) = $77,114.11.

2.

P2 Roof Replacement: Roof Contract Amount ($61,600) - Cost to
Repair In-Kind ($42,341.27) = $18,658.73.

3.

P3 Roof Replacement: Roof Contract Amount ($27,600) - Cost to
Repair In-Kind ($14,265.83) = $13,334.17.

4.

P5 Roof Replacement: Roof Contract Amount ($20,750) - Cost to
Repair In-Kind ($7,599.53) = $13,150.47.

5.

P1 Moisture Reduction System: Underfloor Spray-Foam Barrier
($2,924) + Duct Work ($3,500) + Modification of HVAC Controls
System ($5,200) = $11,624.

See RFA at 7.
Prior to the arbitration, FEMA submitted a number of documents in support of its
position, including a report titled “Evaluation on Storm Related Damages and Repair
Alternatives” (Consolidated Resource Center (CRC) Report) that was produced by a staff
professional engineer (PE). FEMA’s Exhibit 11. This report was prepared to “review the
claimed damages and cause to each of the claimed facilities” and “to evaluate the technical
feasibility and cost-effectiveness of the proposed mitigation measures per FEMA policy.”
Id. at 2. The CRC Report provided an overview of each claim as well as FEMA’s benefitcost analyses for P1 and P2. St. Mark’s submitted its own benefit-cost analysis in appendix J
of its RFA. RFA at 51. FEMA also provided its PE’s testimony, which gave insight into the
calculations and conclusions included in the CRC Report.
Discussion
The Board is authorized by the Stafford Act, 42 U.S.C. § 5189(d), to arbitrate actions
between applicants and FEMA. To be eligible for financial assistance, the applicant must
provide documentation to support the four basic components of eligibility: (1) applicant;
(2) facility; (3) work; and (4) cost. FEMA Public Assistance Program and Policy Guide
(PAPPG) (Apr. 2018) at 9. FEMA does not dispute St. Mark’s status as an eligible applicant,
as St. Mark’s is considered a private non-profit (PNP) organization or institution that owns

CBCA 7990-FEMA

5

or operates a PNP facility.6 Id. at 10-11; 44 CFR 206.222(b). Here, FEMA is challenging
the three other components of eligibility, including (1) that two of the buildings in St. Mark’s
request for PA—P3 and P5—are not eligible facilities; (2) that the damage to those buildings
was not caused directly by Hurricane Irma; and (3) that St. Mark’s mitigation-related repairs
were not cost-effective. See PAPPG at 10-11, 13-15, 97-99.
Eligibility of St. Mark’s Facilities
When an applicant operates multiple facilities, each building must be evaluated
independently, even if all are located on the same grounds. PAPPG at 15. An eligible PNP
facility is one that “provides educational, utility, emergency, medical, or custodial care,
including for the aged and disabled, and other essential social-type services to the general
public.” Id.; see also 42 U.S.C. § 5122(11)(a). A PNP facility is considered to provide
services to the general public if: (1) the facility is not limited to a certain number or defined
group of individuals; (2) facility access is not prohibited with gates or other security
measures; and (3) any membership fee is nominal, is not large enough to exclude a
significant portion of the community, and could be waived if an individual can show inability
to pay the fee. PAPPG at 11. However, other than “custodial care facilities and museums,
administrative and support buildings essential to the operation of the PNP’s non-critical
services are not eligible facilities.” Id. at 13.
Here, P1 and P2 are used for the church’s worship services and other social
gatherings. There is no evidence that St. Mark’s excludes any members of the community
from these events. As such, P1 and P2 are facilities that are open to the general public and,
thus, constitute facilities that provide eligible non-critical services. However, FEMA
contends that P3 and P5 are ineligible facilities because they function as administrative and
support buildings. The record shows that the applicant describes P3 and P5 as storage
facilities or buildings used for the support of the PNP. There is no evidence in the record that
these buildings are open to the public. Applying the guidance in the PAPPG to these facts,
P3 and P5 are not eligible facilities.
St. Mark’s asserts that the exception for administrative and support buildings should
not apply because it is only included in the PAPPG and not listed in the Stafford Act, as
amended in 2019. See 42 U.S.C. §§ 5121-5207 (2019). Specifically, St. Mark’s contends
that, because the Stafford Act’s most recent amendments did not include the exception, the
PAPPG now “conflicts” with the Act. This argument has no merit. In determining eligibility
for PA funding, the Board looks to and applies FEMA policies, including the PAPPG. We

6

“Houses of worship” is listed as an eligible type of PNP applicant that provides
non-critical, essential, social-type services. PAPPG at 13.

CBCA 7990-FEMA

6

are tasked “to determine whether FEMA has properly applied its policies in the factual
circumstances presented to us.” New York Society for the Relief & the Ruptured & Crippled
Maintaining the Hospital for Special Surgery, CBCA 7543-FEMA, 23-1 BCA ¶ 38,268, at
185,810. Thus, we consider the PAPPG in determining eligibility for PA funding.
Accordingly, we deny PA funding for costs associated with P3 and P5 because they
are ineligible PNP facilities. The following sections address only P1 and P2 since they are
the only two facilities eligible for hazard mitigation.
St. Mark’s Hazard Mitigation Efforts
The Stafford Act provides for hazard mitigation funding in two provisions. Section
404 (42 U.S.C. § 5170(c)) is intended to protect facilities that are subject to recurring
weather-related damages without reference to a specific disaster. Non-Flood Protection
Asset Management Authority, CBCA 4980-FEMA, 18-1 BCA ¶ 37,078, at 180,485. Section
406 (42 U.S.C. § 5170(e)(1)(A)(ii)) covers hazard mitigation funding for facilities that were
damaged by the disaster to protect them in future events. Non-Flood Protection Asset
Management Authority, 18-1 BCA at 180,485. The key difference in these sections is that
section 406 is a PA program, while section 404 is a Hazard Mitigation Assistance (HMA)
program.
Because we are determining whether St. Mark’s is eligible for PA funding, the
mitigation measures must satisfy the requirements listed in section 406. Here, St. Mark’s is
requesting funding for two mitigation measures: (1) a moisture reduction system for P1,
including a new underfloor spray-foam barrier, new ductwork, and a modification of HVAC
controls, and (2) a full roof replacement for P1, P2, P3, and P5. As stated above, P3 and P5
are not eligible facilities and will not be considered in this section.
1.

Moisture Reduction System

First, FEMA argues that the installation of a new moisture reduction system in P1 is
not an eligible mitigation measure under section 406 because “the underfloor area,
[ductwork], and HVAC controls” were not damaged by Hurricane Irma. FEMA’s Response
at 18. The applicant argues, conversely, that “all installed moisture control measures are
additive and designed to prevent loss of the building . . . due to moisture . . . [that was caused
by] the loss of offsite power.” Applicant’s Reply at 13-14. Generally, to be eligible for PA
funding, the applicant must prove that costs are directly tied to the performance of eligible
work by showing that the damage was a direct result of the declared incident. PAPPG at 19,
21-23. This is also true for hazard mitigation measures. “FEMA has the authority to provide
PA funding for . . . hazard mitigation measures for facilities damaged by the incident.” Id.
at 97 (emphasis added). However, PA funding is not available for costs associated with

CBCA 7990-FEMA

7

pre-existing damage, deterioration, deferred maintenance, or the applicant’s negligence. Id.
at 19-20. Hence, St. Mark’s has the burden to prove that the damage caused by the interior
moisture accumulation in P1 was caused directly by Hurricane Irma and not by issues already
present in the building.
The DDD prepared by FEMA states that the damage to P1’s interior was caused by
“condensation from rain leaking in from [the] roof.” FEMA’s Exhibit 10 at 1-2.
Nevertheless, multiple pieces of evidence show that the roof had pre-existing damage.
Notably, the photos taken by the insurance adjuster immediately following the hurricane
show that the leaks happened near the flashing areas of P1’s roof. FEMA’s Exhibit 3 at 9-11.
The insurance adjuster did not find damage at any other portions of the roof, which indicates
pre-existing damage or deterioration to the flashing. See id. at 6-12. The applicant’s
contractor also noted signs of “age” during its inspection of the roof. RFA at 41.
Furthermore, the applicant admits that its pre-disaster HVAC unit was oversized for the
dimensions of the facility and that, as a result, parts of the building did not receive proper air
circulation. RFA at 4. FEMA’s PE agreed, stating that when an HVAC unit is oversized,
it does not cool the space gradually, “which can be detrimental to the HVAC components.”
FEMA’s Exhibit 11 at 7. St. Mark’s has not provided maintenance reports or other evidence
to refute FEMA’s position that the aforementioned issues contributed to the leakage or
abundance of condensation that accumulated in the building post-hurricane. While it is true
that Hurricane Irma caused some leakage and a power outage, we find that St. Mark’s has
not satisfied its burden of proof in showing that an ineffective HVAC unit, pre-existing
damage, deterioration, or deferred maintenance did not contribute to the damage of P1.
Therefore, the installation of a new moisture reduction system in P1 does not qualify as a
hazard mitigation measure that is eligible for PA funding.
2.

Roof Replacements

FEMA also contends that a full roof replacement for P1 is not considered costeffective. For a mitigation measure to be eligible for PA funding under section 406, the
measure must be considered cost-effective. PAPPG at 98. Mitigation measures will be
considered cost-effective if any of the following are met: (1) the cost for the mitigation
measure does not exceed fifteen percent of the total eligible repair cost (prior to any
insurance reductions) of the facility (fifteen-percent rule); (2) the mitigation measure is listed
in Appendix J of the PAPPG, titled “Cost-Effective Hazard Mitigation Measures,” and the
cost does not exceed 100% of the eligible repair cost (prior to any insurance reductions)
(Appendix J rule); or (3) the applicant can demonstrate through an acceptable benefit-cost
analysis that the measure is cost-effective. Id. A benefit-cost analysis is accomplished by
comparing the total eligible cost of the mitigation measure to the total value of expected
benefits. Id.

CBCA 7990-FEMA

8

As previously mentioned, FEMA submitted a CRC Report that reviewed each of St.
Mark’s claims. FEMA’s Exhibit 11. The amounts utilized in the CRC Report for the
calculations are the same as the applicant uses in its RFA. First, for the fifteen-percent rule,
the parties stipulate that the cost to repair P1’s asphalt shingles without a full roof
replacement would have been $10,272.89, and the contracted cost for the metal roof
replacement is $87,387. See id. at 10-11; see also RFA at 7 & Exhibit J. Hence, the cost for
the mitigation measure equals $77,114.11 ($87,387-$10,272.89), and the total eligible repair
cost is $10,272.89. To drive home this point, we note that $77,114.11 is 750.65% of
$10,272.89 and, thus, is not considered cost-effective under the fifteen-percent rule. Second,
while Appendix J of the PAPPG includes pre-approved mitigation measures for roofs, St.
Mark’s proposed measure of a metal roof replacement is not listed. PAPPG at 193.
Both parties have submitted separate benefit-cost analyses. FEMA’s Exhibit 11 at 12;
RFA at 51-52. For a measure to be considered cost-effective in a benefit-cost analysis, the
benefit-cost ratio must be greater than 1.0. St. Mark’s asserts that the replacement of P1’s
roof has a benefit-cost ratio greater than one.7 Applicant’s RFA shows that it produced this
number using calculations made without using an outside tool. RFA at 51-52. FEMA,
conversely, used its publicly available benefit-cost analysis online calculator. The use of this
tool resulted in a benefit-cost ratio of 0.50. Exhibit 11 at 6, 9. Additionally, the testimony
of FEMA’s PE asserted that the applicant’s calculations were skewed based on several
incorrect assumptions, such as that “incident-related damages result in an entire roof
replacement” and that a “comparison to the life cycle of each type of roof” (metal or asphalt
shingle) was proper. FEMA’s Written Testimony at 4-5. St. Mark’s did not successfully
rebut this assertion during the live arbitration nor has it shown how its benefit-cost analysis
calculations are more accurate than FEMA’s online benefit-cost analysis calculator. It is for
these reasons that we will use FEMA’s benefit-cost analysis calculations in determining the
benefit-cost ratio for P1. Because 0.50 is less than one, the full roof replacement of P1 is not
considered cost-effective. Hence, the metal roof replacement of P1 is not a cost-effective
mitigation measure and, thus, is not eligible for PA funding under section 406 of the Stafford
Act.
Finally, FEMA concedes that a full roof replacement of P2 is eligible for
reimbursement under the PAPPG because the damage was caused directly by Hurricane Irma
and the replacement is considered cost-effective. We agree. Similar to P1, the roof
replacement of P2 is not considered cost-effective when using the fifteen-percent rule or the
Appendix J rule. However, FEMA’s online benefit-cost analysis tool resulted in a benefitcost ratio of 2.96, which is greater than the required 1.0. FEMA’s Exhibit 11 at 6, 12.

7

The applicant does not provide an exact number for this calculation, only the
following equation: ($46,582 x 4 / $87,387). RFA at 51.

CBCA 7990-FEMA

9

Additionally, the photos taken by the insurance adjuster show considerable wind damage to
the roof’s shingles. FEMA’s Exhibit 3 at 40-43. Thus, the damage to P2’s roof was directly
caused by the hurricane, and the metal roof replacement is a cost-effective mitigation
measure under section 406. Accordingly, St. Mark’s is entitled to reimbursement of
$18,865.73 in PA funding.
Decision
We grant the application in part. FEMA shall pay St. Mark’s $18,865.73.

Patricia J. Sheridan
PATRICIA J. SHERIDAN
Board Judge

Jonathan D. Zischkau
JONATHAN D. ZISCHKAU
Board Judge