# DISMISSED FOR LACK OF JURISDICTION: February 15, 2013

> Briefs, arguments, decisions, and more.

URL: https://www.frixlaw.com/law-library/documents/agency%3Acbca%3A0ac7d985f8245171

## Record

- **Collection:** Agency decision
- **Document type:** Agency decision

## Text

DISMISSED FOR LACK OF JURISDICTION: February 15, 2013

CBCA 3053

JRS MANAGEMENT,
Appellant,
v.
DEPARTMENT OF JUSTICE,
Respondent.
Jacqueline Sims, Owner of JRS Management, Lawrenceville, GA, appearing for
Appellant.
William D. Robinson and Nihar H. Vora, Office of General Counsel, Federal Bureau
of Prisons, Department of Justice, Washington, DC, counsel for Respondent.
Before Board Judges VERGILIO, GOODMAN, and ZISCHKAU.
GOODMAN, Board Judge.
On October 16, 2012, appellant, JRS Management, filed this appeal pursuant to the
Contract Disputes Act. Appellant alleged that the contracting officer of respondent, the
Federal Bureau of Prisons, had failed to issue a final decision in response to appellant’s claim
submitted on August 15, 2012. Appellant therefore treated its claim as deemed denied by the
contracting officer and appealed. Respondent has filed a motion to dismiss, asserting that
the Board lacks jurisdiction as the appeal is untimely. We find that the appeal was not timely
filed, as appellant did not timely appeal a contracting officer decision on an earlier version
of the claim. We grant respondent’s motion and dismiss the appeal for lack of jurisdiction.

CBCA 3053

2
Background

On July 15, 2009, respondent awarded a parenting instructor services contract (the
contract) to appellant. The contract was for a total amount of $81,432; it did not exceed the
simplified acquisition threshold of $150,000. Respondent prepared contractor performance
evaluations with regard to appellant’s performance during the contract’s base year and one
option year.
On March 27, 2012, appellant submitted a claim (claim 1) to the contracting officer.
The claim stated in relevant part:
[T]he contract did not contain any terms authorizing the preparation and
release of Contractor Performance Reports. Moreover, the reports were flawed
erroneous, and inaccurate.
Claim 1 alleged two counts. The first count was entitled “Unilateral Adjustment of
Contract Terms - Performance Evaluations not Authorized by Contract.” In this count,
appellant maintained that Federal Acquisition Regulation (FAR) 42.1502 only requires
federal agencies to prepare performance evaluations for contracts that exceed the simplified
acquisition threshold of $150,000. Appellant further maintained that, as the contract did not
exceed this threshold, respondent’s preparation of performance evaluations breached the
contract, and respondent’s actions in releasing the performance evaluations to government
officials for source selection purposes, without first obtaining appellant’s permission
pursuant to FAR 52.212-4(c), was arbitrary and capricious.
The second count was entitled “The Performance Evaluation was Flawed/Inaccurate The Contract was Legally Unenforceable.” In this count, appellant maintained that even if
respondent had the right to issue performance evaluations, the performance evaluations were
flawed, erroneous, and inaccurate. Additionally, appellant argued that the contract was
legally unenforceable and was only enforceable to the extent it was performed. Appellant
also argued that respondent breached its “implied contractual duty of good faith and fair
dealing.”
Claim 1 sought an equitable adjustment of $1500 as compensation for the unilateral
modification of contract terms, and a modification of the performance evaluations prepared
by respondent to delete comments that appellant found to be inaccurate.
The contracting officer issued a decision on May 24, 2012, denying claim 1 in its
entirety. The decision stated: “Although per FAR 42.1502(b), Federal agencies are only
required to prepare evaluations of contractor performance for a contract that exceeds the

CBCA 3053

3

simplified acquisition threshold, Contracting Officers are not prohibited from utilizing this
resource for contracts not exceeding the simplified threshold.” The decision included
additional statements by the contracting officer with regard to the legal and factual
allegations raised in claim 1, and stated appeal rights to this Board and the Court of Federal
Claims. Appellant received the decision on May 29, 2012. Appellant did not file a notice
of appeal of this decision within ninety days of receiving the decision, or any time thereafter.
On August 15, 2012, appellant submitted another claim (claim 2) to respondent. Claim
2 alleged three counts. The first count was entitled “Agency Exceeded its Statutory
Authority and Violated Regulations by Preparing a Past Performance Evaluation Report.”
This count made essentially the same assertions as the first count of claim 1, with regard to
the requirements and alleged violations of FAR 42.1502 and 52.212-4(c).
The second and third counts were entitled “Agency Preparation of Past Performance
Evaluation Report Constituted a Constructive, Unilateral Change that Materially Breached
the Terms of the Contract, and Breached the Covenant of Good Faith and Fair Dealing” and
“The Performance Evaluation was Flawed, Inaccurate, Erroneous, Arbitrary, Capricious, and
An Abuse of Discretion.” These counts contain arguments similar to those made in the first
and second counts of claim 1, i.e., breach of FAR 52.212-4 and the covenant of good faith
and fair dealing.
The relief requested in claim 2 was similar to that in claim 1. The first count
requested an interpretation of the contract that performance evaluations were not authorized
and therefore a breach. The second count requested monetary damage allegedly arising from
the breach consisting of actual damages of $1218.21 - the alleged cost of appellant for
reviewing the performance evaluations, researching case law and the FAR, and preparing the
claim; and consequential damages of $4071.60 - calculated as 5% of the contract value as
compensation for “loss of the substantive contractual right to negotiate in advance any
proposed changes”. The third count requested additional interpretations that the contract was
legally unenforceable and that respondent did not have the right to unilaterally change the
contract, and demanded revisions in the performance evaluations.
The contracting officer issued a response to claim 2 by letter dated October 12, 2012.
That letter stated that “the allegations made stem from the same set of operative facts as the
original claim, and are substantially the same as, the original claim.” Additionally, the
contracting officer stated that claim 2 was properly addressed in the decision of May 24,
2012.

CBCA 3053

4

Appellant filed this appeal on October 16, 2012, with regard to claim 2, alleging that
the contracting officer failed to issue a final decision in response to claim 2 as required by
the Contract Disputes Act.
Discussion
Respondent has filed a motion to dismiss, asserting that this Board lacks jurisdiction
to entertain this appeal. Respondent asserts that claim 1 and claim 2 arise from the same
operative facts, the issuance of performance evaluations, and are therefore the same claim.
Since appellant did not timely appeal the decision issued in response to claim 1, that decision
can no longer be appealed to this Board. Therefore, respondent maintains that the appeal of
claim 2 as a deemed denial of that claim is actually an untimely appeal of the decision
denying claim 1. Thus, respondent moves to dismiss the instant appeal as an untimely appeal
of claim 1.
In Battley v. Social Security Administration, CBCA 1063, 08-2 BCA ¶ 33,896, this
Board stated:
The established test for what constitutes a “new” claim is whether “claims are
based on a common or related set of operative facts. If the court will have to
review the same or related evidence to make its decision, then only one claim
exists.” Environmental Safety Consultants, Inc., ASBCA 54995, 06-1 BCA
¶ 33,230, at 164,666 (citing Placeway Construction Corp. v. United States,
920 F.2d 903, 907 (Fed. Cir. 1990)).
08-2 BCA at 167,768.
In Battley, the Board found that the appellant’s two claims arose from the same
operative facts and were the same claim. As the appellant had failed to timely appeal the
decision denying the first claim, the appeal of the alleged deemed denial of the second claim
was dismissed as an untimely appeal of the first claim.
We have the same situation in the instant appeal. Appellant’s two claims arise from
the same operative fact that respondent issued performance evaluations. Both claims allege
that respondent had no basis to issue the performance evaluations and that the performance
evaluations as issued were detrimental to appellant. The claims allege in substance the same
legal theories. The relief sought in claim 2 is substantially the same as that sought in claim
1 with some additional relief sought. Claim 2 is not a new claim.

CBCA 3053

5

In this case, the evidence we would review to reach the merits of the appeal would be
the performance evaluations and the contract. The introduction of additional facts that do
not alter the nature of the original claim, a dollar increase in the amount claimed, or the
assertion of a new legal theory of recovery, when based on the same operative facts as
included in the original claim, do not constitute new claims. Trepte Construction Co.,
ASBCA 38555, 90-1 BCA ¶ 22,595. The fact that appellant asserts differing legal theories
and seeks greater relief does not convert claim 2 into a new claim, as it arose from the same
operative facts as those in claim 1, i.e., the issuance of the performance evaluation.
As appellant failed to timely appeal the decision in response to claim 1, the appeal of
claim 2 as an alleged deemed denial is untimely and must be dismissed. As we stated in
Battley:
The CDA [Contract Disputes Act], which governs the Board’s review of
contracting officer decisions, requires that an appeal of such decision be filed
“[w]ithin ninety days from the date of receipt of [the] decision.” 41 U.S.C.
§ 606 (2000). The plain language of the CDA clearly confers finality and
unreviewability of a contracting officer’s decision that is not properly appealed
within the statutory period provided. That finality is not limited to the
contracting officer’s authority to issue such a decision or the validity of the
contracting officer’s decision. See, e.g., United States v. Kasler Electric Co.,
123 F.3d 341, 346 (6th Cir. 1997). The statute affords the opportunity to
challenge the authority and/or validity of the decision, provided the challenge
is made within the statutory period. If a challenge is not made within the
statutory period, section 605(b) mandates that the contracting officer’s
decision “be final and conclusive and not subject to review.” 41 U.S.C. §
605(b). This deadline for filing has been strictly construed by the Court of
Appeals for the Federal Circuit because the authorization to make the filing is
a waiver of sovereign immunity. A late filing divests the Board of jurisdiction
to consider the case on its merits.
08-2 BCA at 167,768.1

1

The referenced provisions of the Contract Disputes Act have be recodified as
follows: The ninety-day limitation formerly found at § 606 is now in § 7104(a). The
finality of an unappealed contracting officer decision is now stated at § 7103(g), rather
than § 605(b).

CBCA 3053

6
Decision

Respondent’s motion to dismiss is granted. The appeal is untimely and therefore
DISMISSED FOR LACK OF JURISDICTION.

__________________________
ALLAN H. GOODMAN
Board Judge

We concur:

________________________________
JOSEPH A. VERGILIO
Board Judge

___________________________
JONATHAN D. ZISCHKAU
Board Judge

---

Source: Frix Law Library, https://www.frixlaw.com/law-library/documents/agency%3Acbca%3A0ac7d985f8245171. Public record. Not legal advice.
