# YRT Services Corp. v. United States

> United States Court of Federal Claims · May 6, 1993 · 38 Cont. Cas. Fed. 76,512

URL: https://www.frixlaw.com/law-library/cases/6643696

## Case

- **Full name:** YRT SERVICES CORPORATION v. United States
- **Court:** United States Court of Federal Claims
- **Decided:** May 6, 1993
- **Citations:** 38 Cont. Cas. Fed. 76,512; 28 Fed. Cl. 366; 1993 U.S. Claims LEXIS 44; 1993 WL 155625
- **Precedential status:** Published
- **Opinion:** Opinion of the court by Horn
- **Judges:** Horn
- **Cited by:** 19 later opinions in the Frix Law Library

## Citator (automated)

- No negative treatment found by the automated citator. That is not the same as a confirmation that the case is good law; read the citing cases.
- Full citator and citing cases: https://www.frixlaw.com/law-library/cases/6643696

## How later opinions describe it (automated extraction)

- concluding that an NPS concession contract for the provision of “lodging, food and gift services” in Yosemite National Park “does not constitute a procurement, but is a grant of a permit to operate a business and the government is not committing to pay out government funds or …
- finding the agency’s actions reasonable and that the agency did not merge two distinct evaluation phases when it used “largely the same individuals” from the first phase of evaluations to conduct the second phase of evaluations

## Opinion text

OPINION 1
HORN, Judge.
BACKGROUND
The plaintiff, YRT Services Corporation (YRTSC), is a disappointed applicant seek *370 ing to enjoin the United States National Park Service (Park Service or NPS), from awarding a concession contract to Delaware North Companies, Ine. (Delaware North). 2 Plaintiff claims that its offer to provide concession services at Yosemite National Park was not considered fairly and fully; that the National Park Service failed to employ the evaluation criteria stated in the Statement of Requirements (SOR); and that plaintiffs offer was the best overall offer, for which plaintiff should have been awarded the contract. In plaintiff’s second amended complaint, now before this court, the plaintiff requests a permanent injunction and a declaratory judgment barring the defendant from awarding the contract to any person other than the plaintiff, as well as bid preparation costs and attorneys’ fees. In the complaint, as originally filed, the plaintiff requested a preliminary injunction, a permanent injunction and a declaratory judgment barring award of the contract to Delaware North.
In view of plaintiff’s request for injunc-tive relief, this litigation has progressed on an accelerated schedule, made possible, in no small part, by the professional demean- or and competence of the attorneys for both parties. Plaintiff’s original complaint was filed on January 11, 1993, and amended twice as new facts arose during the course of discovery. Originally, the plaintiff sought a preliminary injunction, but when, at a status conference, the defendant agreed not to award the concession contract without first notifying the court, plaintiff amended its complaint to request a permanent injunction. 3 At the time the lawsuit was filed, the government had not yet complied with the congressional notification requirement mandated by 36 C.F.R. § 51.4 (a) (1992), which provides that after negotiation of a concession contract, for a term of five years or more, or with anticipated revenues in excess of $100,000, the Park Service must forward the proposed contract to the Senate Committee on Energy and Natural Resources and the House Committee on Interior and Insular Affairs for a sixty-day waiting period prior to award. 36 C.F.R. § 51.4 (d) (1992).
Discovery was completed in less than six weeks. Voluminous, separate, records were filed by both plaintiff and defendant. Cross-motions for summary judgment were simultaneously filed on February 25, 1993. Reply briefs were simultaneously filed on March 3, 1993. Amicus curiae briefs were submitted by counsel representing Delaware North Companies, Inc., the selectee on the contract, on February 25, 1993, and by counsel representing Yosemite Park Services, L.P., another disappointed applicant, on March 3, 1993. A number of sta *371 tus conferences, scheduled by the court, were attended by both parties and either one or both of the amicus participants. 4 Extensive oral argument on the cross-motions for summary judgment was held on March 5, 1993.
FACTS
YRT Services Corporation, a new company established by the Yosemite Restoration Trust for the purpose of providing concession services in Yosemite National Park, brought this suit to enjoin NPS from awarding a concession services contract to anyone other than the plaintiff.
The Park Service enters into contracts for concession and related services (concession contracts) in national parks such as Yosemite Park which is located in California. Concession contracts are unusual in several respects. Unlike traditional government contracts, the government does not make payments to the contractor. Instead, contractors, known as concessioners, charge for services provided to the public, and, in turn, pay NPS a fee for the right to operate a concession business. 5 Conces-sioners also provide services to the Park Service. The concession contract proposed in the instant case includes a broad range of services, including lodging, food and gift services. Concessions Policy Act of 1965 (CPA), 16 U.S.C. § 20d (1988). Furthermore, the concession contract is for a fifteen-year term, and, pursuant to the Concessions Policy Act of 1965, 16 U.S.C. § 20d; 36 C.F.R. § 51.3 (b) (1992), the con-cessioner is entitled to a statutory preference for follow-on contracts.
Concessioner fees to be paid to the Park Service under the instant contract include: a franchise fee (currently set at 0%); a rental fee for hotel and other facilities which goes into a Government Improvement Account (GIA); and a Capital Improvement Fund (CIF) fee, which enables the concessioner to undertake projects to improve facilities supporting the concession services. CIF improvement projects are selected by the Superintendent of Yosemite National Park, and must have the written approval of the Director of the Park Service’s Western Region. The Franchise Fee, CIF contributions and GIA amounts are reconsidered every four years.
The CPA provides that the Secretary of Interior, consistent with his statutory mission, “to administer national park system areas in accordance with the fundamental purpose of conserving their scenery, wildlife, national and historic objects and providing for their enjoyment in a manner that will leave them unimpaired for the enjoyment of future generations____” shall take actions “to provide and operate facilities and services which he deems desirable for the accommodation of visitors in areas administered by the National Park Service.” 16 U.S.C. § 20 (1988). Terms and conditions specified in the statute are intended to promote these goals. Regulations implementing the Concessions Policy Act promote the same goals, and also set standards for selection of concession contractors. 36 C.F.R. § 51 (1992). In pertinent part, the applicable federal regulations provide that:
the principal factors to be considered in selection of the best proposal shall be (1) the experience and related background of offerors, (2) the offeror’s financial capability, and (3) conformance to the terms and conditions of the prospectus in relation to quality of service to the visitor. Secondary factors shall include franchise *372 fee offered and other factors as may be specified.
36 C.F.R. § 51.4 (b) (1992).
NPS-48, an internal National Park Service handbook, outlines the comparative and individual evaluation methods for concession contracts. In the instant case, it appears that the method employed was that of individual analysis, detailed in NPS-48.
Individual Analysis
This approach calls for an analysis of each individual proposal including an evaluation of how each element of the proposal fits and balances with each of the other pieces. This approach can be used effectively in situations where there are very few responses. The final selection is based on the total analysis and judgment of the benefits to the public and impact on the park.
In both instances, a written evaluation report from the panel or evaluator to the executing official should be prepared which summarizes the selection process and provides the medium for the official recommendations. The strengths and weaknesses of each offeror should be summarized and the qualified offers identified along with the recommended offer. The narrative should contain the support for these decisions and the criteria used by the panel. Any qualifications or conditions placed on the recommendations should be clearly discussed so as to properly inform the selecting official.
National Park Service, CONCESSIONS GUIDELINE, NPS-48, Chapter 8, Page 4.
For selection of the Yosemite concession contractor, the Park Service used a two-phase solicitation process. In Phase I, NPS issued a Statement of Requirements (SOR), also called a prospectus, to prequalify offerors, and asked applicants to demonstrate the following:
CRITERION 1. THE APPLICANT DEMONSTRATES SUBSTANTIAL COMPETENCE TO MANAGE A COMPLEX SERVICE-ORIENTED BUSINESS ACTIVITY EFFECTIVELY. CRITERION 2. THE APPLICANT DEMONSTRATES WITH REASONABLE ASSURANCE THE ABILITY TO PROVIDE NOT LESS THAN $12 MILLION OF INITIAL EQUITY CAPITAL TO UNDERTAKE THE CONCESSION OPERATION.
Only applicants found qualified in Phase I were eligible to compete in the Phase II SOR, which was issued on July 15, 1992, and closed on November 16, 1992. The best proposal was described as the one most likely to achieve the National Park Service objectives set forth in the Statement of Requirements.
Secondary factors listed in the Phase II SOR included the offeror’s proposed Capital Improvement Fund (CIF) contribution, equal opportunity program, and its understanding and commitment to the preservation of the resources of Yosemite National Park. In the Phase II SOR, the primary and secondary factors were divided into sixteen evaluation criteria.
Successful Phase I applicants were told explicitly in the Phase II Statement of Requirements:
Documents submitted under the Phase I process should be regarded as being for that purpose only. They will not be used by the Service in evaluating offers under Phase II. Except for the purpose of addressing the specific criteria of Phase I, the Service neither accepts or rejects any of the proposals or ideas included in submittals under Phase I.
The Park Service indicated in the Phase II SOR that “[t]he offer which NPS determines best meets the overall objectives of the National Park Service will be selected.” The Phase II SOR contained the following instructions regarding evaluation of proposals:
To establish the best proposal, the National Park Service, in narrative form through panel review, will evaluate each proposal against the Evaluation Criteria. The Service will select as the best proposal that proposal which it considers is most likely to effectively achieve the objectives of the Service for concession services and facilities in Yosemite National *373 Park as reflected in the Statement of Requirements and related documents.
In this regard:
1. The services requested, generally as described herein, will be sufficient for the park’s needs. Proposals of expansion, deletions, or other similar suggestions not in accordance with Service planning documents or of facilities of a type not requested will not be considered better proposals. Similarly, elements of proposals which offer to provide direct or indirect monetary or other benefits to the Park or government outside of the scope and requirements of the CONTRACT will not be considered as elements of a better proposal.
2. Proposals for financial commitments will be closely reviewed against Balance Sheet and Income Statement projections and the Service’s knowledge of the operating costs of this business. Predictable, stable, and well-run businesses consistently providing maximum service to the public in operations and facilities that are the best of their type are most consistent with the National Park Service’s objectives of public service. Financial commitments which appear inconsistent with these objectives and/or which do not appear to allow the concessioner a reasonable opportunity for a profit from the operations authorized hereunder based on the capital invested are not acceptable. However, not-for-profit or nonprofit proposals will be evaluated as such.
3. The APPLICATION and related materials should reflect the entire proposal being made. The Service may verify information and clarify points as it feels necessary. If supplemental material is desired, the NPS will offer that opportunity to all APPLICANTS.
5. It is the intention of the National Park Service to select a concessioner from the proposals made without further submittals or presentations. However, the National Park Service reserves the right to request additional information and oral presentations from all APPLICANTS or from the most highly successful APPLICANTS if a ‘best proposal’ can not be selected from the initial submit-tals.
The Phase II SOR also included other pertinent, important conditions, including:
First, as a condition of the award of the contract, the selected applicant had to agree to accept the assignment, without exceptions, of the Agreement and Plan of Merger (merger agreement) between the National Park Foundation (NPF) and the current concessioner, Yosemite Park and Curry Company (YP & CC), as signed on September 20, 1991. The merger agreement was negotiated by the NPF, a nonprofit, non-governmental entity, with the current concessioner, YP & CC. The Phase II Statement of Requirements (SOR) for the new concession contract further required that the new concessioner accept an assignment of YP & CC’s assets and liabilities from the NPF, which was to act as a facilitator of the transfer. The price and terms of the merger agreement were defined as non-negotiable. Second, offerors were required to submit proposals with the understanding that NPS could not assure that any particular government planning decisions for utilization of Yosemite National Park would be made, could not assure when more decisions would be made, and could not guarantee that plans would not be altered, once made, given the statutory requirement that the park be managed to preserve and protect resources and the responsibility of NPS to continue a process of study with respect to the park activities in general, and the concession facilities in particular. Third, applicants were discouraged from proposing modifications to the contract. Proposals could not be conditioned on the Park Service’s acceptance of substantive modifications to the contract.
The Phase II SOR listed sixteen criteria, grouped in five (5) parts, to which offerors *374 were to respond, and by which the proposals were to be judged. Applicants were instructed to be sure that they addressed each of the criteria provided, and that failure to address any part of the application might cause the proposal to be considered as non-responsive. The Phase II criteria identified were as follows:
Part I
Identifying Information
CRITERION 1. THE APPLICANT HAS CLEARLY IDENTIFIED THE ENTITY^) MAKING THIS PROPOSAL, THE ENTITY(S) THAT CONTROL THE APPLICANT, AND THE ENTITY(S) TO BE INVOLVED IN OPERATING THE BUSINESS AND HAS PROVIDED THE SUPPORTING MATERIALS CALLED FOR.
The types of information required to be submitted under this criterion included names of owners, corporate officers, and members of the Board of Directors, the Articles of Incorporation and By-Laws, and financial statements for the proposer and parent company.
Part II
Experienced Related Background
CRITERION 2. THE COMPETENCE OF THE ENTITY, AS REFLECTED IN THE APPLICATION, TO MANAGE THIS BUSINESS ACTIVITY EFFECTIVELY.
and
CRITERION 3. THE COMPETENCE OF THE PRINCIPAL AND OTHER STAFF, AS REFLECTED IN THE APPLICATION, TO OPERATE HOTEL, MOTEL, CABIN, RESTAURANT, CAFETERIA, TOUR and INTERPRETATION, FAST FOOD, SNACK BAR, MERCHANDISE, GROCERY MARKET, GIFT SHOP, SERVICE STATION, TRANSPORTATION, SKIING, PUBLIC SHOWERS, LAUNDRY and RELATED FACILITIES and SERVICES.
Information requested under Criteria two and three included detailed resumes for all partners, sole proprietors and key employees, including on-site managers, the education and special skills, special training and licenses of each, as well as, the specific role of each such individual manager. The SOR requested specific information on the size of operation, dates, areas of operation, specific duties, number of people supervised, hours worked per week, and other factors that would be helpful to reviewers in establishing a clear understanding. Applicants were instructed not to omit training, education or special qualifications, ratings, or licenses, needed in some special occupations.
Part III
Plans for Operation (which encompassed criteria four through eleven)
CRITERION 4. THE EXTENT TO WHICH THE BUSINESS STRUCTURE PROPOSED IS SUFFICIENTLY STAFFED AND IS APPROPRIATELY STRUCTURED TO DELIVER THE SERVICES REQUIRED IN A QUALITY MANNER.
Requested information included an organizational chart showing principal lines of authority, the number of employees in each department, together with their projected functions, and identification of management decision-makers and key employees. Proposed wage levels, estimated hours per work for positions and the proposer’s plan for transition from the former contractor were also to be provided.
CRITERION 5. THE EXTENT TO WHICH EMPLOYEE POLICIES ARE WELL-PLANNED AND WILL PROVIDE QUALITY EMPLOYEES.
The SOR requested details regarding policies for hiring, including the offeror’s plan for conducting background reviews of job applicants, as well as specifics about policies for training, recreation, housing, and termination. Also, the applicant was required to outline its proposed program(s) to ensure that employees would be hospitable and would exercise courtesy to the public.
CRITERION 6. THE EXTENT TO WHICH THE MAINTENANCE ACTIVITIES PROPOSED ARE SYSTEMATIC AND REFLECT A GOAL OF SUS *375 TAINED HIGH QUALITY FACILITIES. THE APPLICANT ACCEPTS THE PROPOSED MAINTENANCE PLAN [furnished by NPS]. AN ELEMENT OF A BETTER OFFER WILL REDUCE NPS RESPONSIBILITY OR COSTS UNDER THE PROPOSED PLAN.
Criterion six asked the applicant to describe its plans to provide proper maintenance of all equipment, rental equipment, furnishings, fixtures, buildings, and grounds. Also, the applicant was asked to describe its approach towards the care of what the government determined to be “reserved property” in the contract, to indicate whether the offeror would accept the proposed maintenance plan, and if the applicant could make changes to the plan, to suggest the changes which would be proposed.
CRITERION 7. THE EXTENT TO WHICH THE OPERATIONS PROPOSED MEET THE SERVICES OBJECTIVES AND REFLECT A GOAL OF SUSTAINED HIGH QUALITY FACILITIES AND SERVICES THAT ARE THE BEST OF THEIR TYPE. THE APPLICANT ACCEPTS THE PROPOSED OPERATING PLAN.
Under this criterion, the applicant was asked to express its concerns or reservations with the terms and conditions of the NPS plans included in the proposed contract (which was provided to applicants and covered the Concession Services Plan and the Housing Plan). Also, the applicant was asked to express any reservations with the operating plan. However, applicants were reminded that proposals of expansion or deletion, not in accordance with NPS planning documents, would not be considered better proposals. Additionally, applicants were asked to provide details on brand names, logos, pricing, internal quality control procedures and any design and construction necessitated under the contract, as well as quality control procedures and employee incentive programs.
CRITERION 8. THE EXTENT TO WHICH SAFETY, SECURITY AND SANITATION ISSUES ARE IDENTIFIED AND SOLUTIONS PLANNED.
This criterion required the applicant to specify its existing Loss Control Plan, if any, and to describe its plan for managing safety, security, and sanitation.
CRITERION 9. THE QUALITY OF THE APPLICANT’S PROPOSED EQUAL OPPORTUNITY PROGRAM.
The applicant was asked in criterion nine to provide details of its minority participation plan to advance equal opportunity goals and to indicate whether it had previously “participated in a previous permit, contract, or sub-contract subject to the Equal Opportunity Clause contained in Executive Order No. 11246.”
CRITERION 10. LIABILITY AND PROPERTY INSURANCE MEETS OR EXCEEDS THE REQUIREMENTS OF THE NATIONAL PARK SERVICE INSURANCE PROGRAM.
Regarding insurance, the SOR asked of-ferors to describe in detail the property coverage, liability coverage and any other coverage the offeror proposed to carry. The SOR required the winning concession-er to insure the buildings, structures, equipment, furnishings and betterments and merchandise used in the operation. Full replacement value coverage was stated as the preferred insurance approach.
CRITERION 11. IF THE MCA 6 FINANCING IS ACCEPTED BY THE APPLICANT, THE PROPERTY AND LIABILITY INSURANCE MEETS OR EXCEEDS THE REQUIREMENTS OF THE MERGER AGREEMENT.
The Statement of Requirements asked of-ferors to describe in detail the property insurance coverage, the liability coverage and any other insurance which the applicant intended to carry if selected.
Part IV
Joining the National Park Service Mission
CRITERION 12. THE EXTENT TO WHICH THE ENTITY WILL, *376 THROUGH ASPECTS OF IT’S [sic] OPERATION DESCRIBED BELOW, DIRECTLY CARRY OUT PROGRAMS WHICH PRESERVE, PROTECT AND INTERPRET THE RESOURCES OF YOSEMITE NATIONAL PARK. CRITERION 13. THE EXTENT TO WHICH THE ENTITY REFLECTS AN UNDERSTANDING OF THE NATIONAL PARK SERVICE MISSION AND A CONCESSIONER’S ROLE IN CARRYING OUT THAT MISSION.
Applicants were cautioned in regard to criteria twelve and thirteen: “proposals that offer to provide benefits to the park or government that are outside the terms of the CONTRACT will not be considered a better offer.” Applicants were asked to give specifics regarding: the contemplated redirection of the gift and souvenir program; plans for setting standards and training to achieve a consistent level of knowledge and friendly attitudes among all staff about the park; and, the applicant’s resource protection program. Moreover, applicants were expected to address the following resource protection issues: solid waste disposal, water and energy conservation, pest management, EPA requirements for underground tanks, air quality, mitigation of human-wildlife interactions, and, the harmonious construction of facilities. The overall goal was to minimize negative impacts on the environment. Offerors were requested to provide their “philosophy on operating within a National Park Service area.”
Part V
Financial Operations and Financing
CRITERION 14. THE EXTENT TO WHICH THE APPLICANT HAS A WELL-FOUNDED ESTIMATION OF THE LEVEL OF SALES AND EXPENSES THE BUSINESS WILL GENERATE, AND HAS MADE SOUNDLY BASED ESTIMATES SHOWING CASH FLOW AND RETURNS ON THE CAPITAL INVESTED.
CRITERION 15. THE EXTENT TO WHICH THE APPLICANT DEMONSTRATES ADVANTAGEOUS TERMS FOR FINANCING.
CRITERION 16. THE PROPOSAL MAKES THE COMMITMENT TO THE CAPITAL IMPROVEMENT FUND THAT THE NPS CONSIDERS WILL ADVANCE THE IMPLEMENTATION OF THE GOALS OF THE CONCESSION SERVICES PLAN AND THE HOUSING PLAN TO THE GREATEST EXTENT POSSIBLE WHILE BEING CONSISTENT, IN NPS JUDGEMENT, WITH A REASONABLE OPPORTUNITY FOR A PROFIT ON THE CAPITAL INVESTED AND FULFILLMENT OF OTHER OBLIGATIONS OF THE CON-CESSIONER.
Applicants were expected to provide detailed estimates of projected revenues and expenses, in formats provided by NPS, for the fifteen (15) years of the contract period, and to show estimated, annual cash flow, utilizing a 4% inflation rate. Additionally, applicants were expected to propose a Capital Improvement Fund (CIF) contribution, expressed as a percentage of gross receipts. For this criterion, the Park Service suggested that less than a 5% CIF proposal would likely be considered insufficient, but that applicants were free to make whatever proposal they felt appropriate.
Regarding initial equity for working capital, the Phase II Statement of Requirements stated:
The APPLICANT will provide a minimum of $12 million as initial equity for working capital. That amount is intended to include the amount reimbursable to NPF [National Park Foundation] as described at page 9 of BUSINESS OPPORTUNITY, Purchase of Existing Assets and Business. This must appear on the books of the New Concessioner as equity, not debt. Make sure that these commitments are reflected in the financial information provided. Describe the source of and terms for these funds.
Regarding the source of financing, the Phase II SOR abandoned the “reasonable assurance” standard utilized in Phase I, 7 *377 and adopted a higher, “compelling evidence” standard:
Identify the source of any financing needed. Document the availability of financing with financial statements, financing agreements and letters of intent from lenders. Present compelling evidence of proposers ability to obtain the necessary financing. Be specific. Identify all sources. [Emphasis added.]
In addition, applicants were directed to describe the financial terms of each proposed financing source; to submit sufficient documentation to demonstrate, in a compelling way, the availability and commitment of funds raised from individuals; and to include details of funds raised from other sources. The SOR directed applicants to “[p]rovide also a departmental pro forma for fifteen years in the format provided. The assumptions on which the projections are based must be explained to a degree sufficient for reviewers to judge the validity of the estimates.” The SOR also stated that if funds were to be raised from individuals, the applicant was instructed to submit sufficient documentation with its application to demonstrate, in a compelling way, the availability and commitment of such funds.
Applicants were also instructed to describe how the offeror’s financing arrangements, taken as a whole, were advantageous to the government:
Describe how your financing arrangements taken as a whole, are advantageous terms for financing that balance the financial interests of the Service in this CONTRACT, the need for a soundly financed company with the least number of financing issues to be negotiated in the future. Paying MCA cash at the closing, financing the purchase price through equity contributions and/or alternative financing arrangements, or an equity investment in excess of the $12 million minimum requirement, could all be aspects of a better offer depending on their overall effect of the park’s future.
APPLICANTS should note that, ideally, NPS would prefer to award the CONTRACT to an APPLICANT that does not choose to utilize the MCA financing arrangements due to the complex nature of the security agreement involved. Alternative financing arrangements will be considered as an element of a better offer in circumstances where the overall financing aspects of the proposal are viewed as advantageous to NPS taking into account the terms of the MCA financing package.
The APPLICANT selected by NPS to be awarded the CONTRACT may, subsequently, propose for NPS consideration modifications to its financing arrangements if they are at least as favorable to NPS as those presented in the offer. NPS, however, is not obligated to accept such modifications. Modifications in financial terms approved by NPS, including but not limited to modifications to the MCA financing arrangement, if applicable, will not be considered a material amendment to the terms and conditions of this SOR or the CONTRACT.
Please provide any additional information as to how you would meet the objectives of the above criteria.
The NPS evaluation panel met in San Francisco on December 1-9, 1992. Two weeks were set aside to conduct a detailed evaluation of the proposals and report to the selection panel. The selection panel met in San Francisco on December 10, 1992, and spent one-half day with the evaluation panel and one-half day on internal deliberations. The selection panel met again in Washington, D.C. on December 16, 1992 to present its recommendation to the Deputy Director of NPS.
*378 Instructions were given to the six evaluation panel members by Stephen G. Crab-tree, chairman of the evaluation panel, in a memorandum dated November 13, 1992. 8 The memo stated:
Our schedule is proposed as follows:
1. Read all offers and discuss the evaluation methodology.
2. Discuss offers looking for obvious unsuccessfuls and document that.
3. Divide into subject teams. Each team to review and rank offers for a few Criteria. Document pluses and minuses of each response on each criterion.
4. Assemble the prioritizations with team presentations. Discuss pluses and minuses. As we go along, make a matrix of the results — each offer against all criterion.
5. [Five appears to have been accidently omitted. The original skips from 4 to 6.]
6. Discuss each company on an overall basis and document pluses and minuses.
7. Prioritize the companies and document why.
8. Review the full analysis on Thursday, December 10, 1992, with the Management Team of Stan, Mike, Jack, and Lee. [United States Department of the Interior employees, but the team also included Mr. Calvin Cooper, Acting Assistant Director, Denver Service Center.] We will discuss our prioritized offers in order. This session will be to explain and inform. It is a way of both briefing management and looking for loose ends.
9. Ask the management [selection] team to pick.
10. Finish up any documentation needs. We want to be finished completely by the [sic] December 11, 1992.
Crabtree indicated that the evaluation process could be altered depending on the nature of the offers received. Crabtree also indicated that he would have blank evaluation sheets available for each panel member and that when the evaluation was complete, the panel would produce one summary sheet for each offer reflecting the comments. At the end of the process, Crabtree indicated that a matrix would be produced by the evaluation panel, comparing all offers, as well as a memo to management describing how and why the applications were ranked.
The evaluation panel rated each of the six (6) applicants individually on each of the sixteen criteria detailed in the SOR, and produced a matrix, titled “Yosemite Concession Offer of Summary Ratings,” comparing the offers received on all the criteria. Plaintiff YRTSC’s proposal was rated successful on all but criteria fifteen and sixteen, on which plaintiff YRTSC’s proposal was rated “unsuccessful.” 9 For the Phase II SOR Criterion 15, the Park Service required the -applicants to provide a minimum of $12 million as initial equity for working capital and to describe the source and terms for these funds. The applicant was directed to present “compelling evidence” of the ability to obtain the necessary financing, utilizing documents such as financial statements, financial agreements and letters of intent from lenders. As indicated, the SOR also specified that the applicant must “[d]eseribe how your financing arrangements taken as a whole, are advantageous terms for financing that balance the financial interests of the Service [NPS] in this CONTRACT, the need for a soundly financed company with the least number of financing issues to be negotiated in the future.” The evaluation panel gave plaintiff YRTSC an “unsuccessful” rating,, based on its failure to present “compelling evidence” of meeting Criterion 15. In its report, the evaluation panel stated:
*379 This proposer states that they raised $7 million of the required $12 million equity contribution as of the submission of the proposal. 10 There is no compelling evidence that the balance is available. 11
YRTSC álso proposed to use the MCA note, to finance $61,575,000, but indicated that if it was awarded the contract, YRTSC could anticipate entering into immediate negotiations with MCA to revise the repayment schedule and to negotiate a discount from the face value in return for payment of the note. 12 In an apparent equivocation regarding whether or not YRTSC possessed the necessary $12 million financing on hand, the applicant stated that “[w]ith this agreement in hand, we are confident that the required funding will be secured.” [Emphasis added.]
The evaluation panel also rated YRTSC “unsuccessful” on Criterion 16 because YRTSC had conditioned its proposal by stating that any change in operations by NPS introduced by implementing actions under the CSP or Housing Plan will be subject to negotiation. Additionally, the level of contribution to the CIF would also be subject to negotiation. The evaluation panel wrote:
YRT’s ‘assumption’ that plan implementations and contributions be renegotiated for any change in operations occasioned by implementation of each component of the Concession Services Plan or the Housing Plan is not an acceptable condition. 13
We conclude that the present value of the proposer’s contribution to the CIF would be approximately $65.7 million over the life of the contract. This translates to an average percentage of 6.1% of the present value of gross receipts. 14 Considering only the first four years of the contract (recognizing that NPS will renegotiate the CIF percentage), the proposer’s offer was $7.0 million. This *380 translates to an average percentage of 2.0% of the present value of gross receipts. 15
According to the proposer’s figures, it will obtain a 14% before tax return on investment.
We feel that the proposer’s estimate of general and administrative expenses begin somewhat higher and ended somewhat lower than might reasonably be expected. Adjusting those expenses accordingly would yield the proposer a before tax return on investment of approximately 14%, a reasonable return.
We noted, however, that this proposer limited its environmental remediation liability to $12.3 million. Any cost above this amount would, therefore, presumably be absorbed by the government.
Regarding liability for environmental remediation, the evaluation panel noted that YRTSC proposed to limit its liability to $12.3 million. 16 Presumably, under plaintiff’s proposal, any cost above that amount was to be absorbed by the government.
Specifically, the plaintiff proposed: YRTSC has forecast costs for such a program at $5 million over the first four years of the contract as shown in the financial projections. Beyond year four, an additional $7 million has been included in the forecasts for continued underground tank and other environmental cleanup costs.
At the end of year four, YRTSC will review the results of continuing monitoring and clean-up and reassess the estimated costs of clean-up. To the extent that in any year the amount spent in environmental clean-up is less than 75% of the YRTSC forecast amount, the difference will be held in a segregated sinking fund account. The Park Service may direct YRTSC to contribute funds from this sinking fund to the CIF. The government or MCA will indemnify YRTSC against environmental expenditures in any year for which such expenses exceed the YRTSC forecast amount, plus the amount accumulated in the sinking fund.
The selection panel found this limitation to be unacceptable, and wrote:
The offer also proposes to limit YRTSC’s environmental mitigation liability to $12.3 million requiring indemnification from the government or MCA in this regard____ In any event, such ... limitation of liability could not be accepted, even if otherwise lawful and in the best interests of the government, without re-solicitation of the concession opportunity because they constitute material changes to the terms of the solicitation for the benefit of the offeror.
Based on the documents and evaluation reports in the record, the Park Service used the same process to evaluate all the offers, including that of the plaintiff, YRTSC, and that of the applicant ultimately selected, Delaware North. Delaware North’s proposal was found “successful” with regard to each criterion. In fact, it was the only application which achieved the “successful” rating in every category. For Criterion 15, the Park Service found Delaware North’s offer “satisfactory” and concluded:
As evidenced by its balance sheet, this entity has the financial strength necessary to contribute $12 million towards equity.
No alternative financing to the MCA note has been proposed.
*381 The panel also found Delaware North’s proposal to be “satisfactory” on Criterion 16 and observed:
We conclude that the present value of the proposer’s contribution to the CIF would be approximately $56.5 million over the life of the contract. 17 This translates to an average percentage of 5.2% of the present value of gross receipts.
Considering only the first four years of the contract (recognizing that NPS will renegotiate the CIF percentage) the proposer’s offer was $18 million. This translates to an average percentage of 5.2% of the present value of gross receipts.
According to the proposer’s figures it will obtain a 19% before tax return on investment. 18
We feel that the proposer’s estimate of general and administrative expenses were higher than might reasonably be expected. Adjusting those expenses downward would yield the proposer a before tax return on investment of approximately 52%.
This proposer indicated a willingness to assume whatever costs were necessary for environmental remediation, and estimated the costs to total $16.9 million. 19
Therefore, to compare this proposal on an equal footing with the other proposals, recognizing that the environmental remediation costs are not known, we applied a similar expenditure ($12.5 million) and expenditure pattern as for the other evaluations. In doing so, we determined that the resulting return on investment would be 53%, only slightly higher than without the adjustment, mainly because most of the expenditure reduction occurs in the last years of projected occurrence. It is also noted that the CIF contribution under this proposal will drop to 4.7% in the event that if, upon closing, the net current liabilities of YPCC are not equal to net current assets. If this should occur, a 4.7% contribution only reduces the net present value of the proposed 5.2% contribution by $5,425,000 ($56,538,-000 reduced to $51,113,000) over a fifteen year period. This difference would not cause us to evaluate the proposal as marginal or unsatisfactory with respect to Criterion 16.
By contrast to YRTSC, Delaware North did not impose any limitations on environmental liability, and stated:
e. Environmental/remediation Pursuant to the SOR, the Company will have responsibility for certain environ *382 mental preservation and remediation activities. The projected expense related to such responsibilities is based upon a survey conducted by the Company’s environmental consultants, ERM-West, Inc., adjusted for inflation. Management anticipates that all known potential environmental pollution exposures will be resolved by 2003.
Accordingly, both the evaluation panel and selection panel rated Delaware North “successful” on the environmental liability issue.
In response to Criterion 16, Delaware North expressed concern about possible changes in the scope of concession operations. Delaware North’s proposal stated:
The SOR provides that the implementation of the revised General Management Plan, Housing Plan, or Concession Services Plan in the future may affect the operations of the concessioner during the term of the Concession Contract. The scope and financial impact of such changes are not yet known and the NPS has directed in the SOR that applicants not take any such potential changes into account.
Accordingly, DNC [Delaware North] management has assumed, for purposes of these projected financial statements, that no such changes will occur during the term of the Concession Contract and that should they occur, appropriate adjustments will be made to allow the Company to attain a reasonable return on its investment.
Apparently, on about December 8, 1992, Stephen Crabtree, chairman of the evaluation panel, phoned Dennis Szefel, of Delaware North to ask a question about the meaning of Delaware North’s proposed CIF contribution should current liabilities of YP & CC exceed current assets at the time of the merger. The relevant section in Delaware North’s proposal about which Crabtree inquired reads as follows:
The Company has projected contributions to a Capital Improvement Fund in the amount of 5% of gross receipts ... ... DNC has assumed in the accompanying projections that the assets of YP & CC at the Merger Date will include a sufficient amount of cash to equate current assets to current liabilities. In the event that such cash is not available, the Company’s contribution to the Capital Improvement Fund would be reduced to 4V2% of annual gross receipts and the projected financial statements would be revised accordingly.
According to Stephen Crabtree, after reviewing Delaware North’s proposal, the evaluation panel was uncertain as to whether or not Delaware North intended to offer a CIF contribution of 5% or 4V2%, so he asked: “Which is it?” According to Mr. Crabtree, Delaware North replied: "... it means just exactly what it says. If its current assets are less than current liabilities, we are for 4.5. If current assets are greater or equal to, we offer 5.” Crabtree then conveyed that information to the evaluation panel. According to Crabtree, the phone conversation lasted less than a minute. There is no evidence in the record that any of the other offerors were contacted, nor is there any allegation or evidence that any offeror, including Delaware North, was permitted to change or supplement its proposal.
On December 10, 1992, the selection panel was briefed by the evaluation panel for a half day and then the selection panel deliberated separately. Only Delaware North received a “satisfactory” rating on each of the criteria in the Phase II SOR from the evaluation panel. The next week, the selection panel met in Washington, D.C. to present its recommendations to Herbert S. Cables, Jr., Deputy Director of the National Park Service, who endorsed the memo prepared by the selection panel. On December 17, 1992, the Park Service announced its selection of Delaware North Companies, Inc. as its next concessioner.
DISCUSSION
Request for Summary Judgment
Summary judgment in this court is properly granted only when there is no genuine issue as to any material fact and the moving party is entitled to judgment as *383 a matter of law. Rule 56 of this court is patterned on Rule 56 of the Federal Rules of Civil Procedure (Fed.R.Civ.P.) and is similar in language and effect. 20 Both Rules provide that summary judgment “shall be rendered forthwith if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” Rule 56(c) of the Rules of this court provides that in order for a motion for summary judgment to be granted, the moving party bears the burden of showing that there is no genuine issue of material fact and is entitled to judgment as a matter of law. Adickes v. S.H. Kress & Co., 398 U.S. 144, 157 , 90 S.Ct. 1598, 1608 , 26 L.Ed.2d 142 (1970); Rust Communications Group, Inc. v. United States, 20 Cl.Ct. 392, 394 (1990); Lima Surgical Ass’n, Inc. Voluntary Employees’ Beneficiary Ass’n Plan Trust v. United States, 20 Cl.Ct. 674, 679 (1990), aff'd, 944 F.2d 885 (Fed.Cir.1991).
Disputes over facts which are not outcome determinative under the governing law will not preclude the entry of summary judgment. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 , 106 S.Ct. 2505, 2510 , 91 L.Ed.2d 202 (1986). Summary judgment will not be granted if “the dispute about a material fact is ‘genuine,’ that is, if the evidence is such that a reasonable jury [judge] could return a verdict for the non moving party.” Id.; see also Uniq Computer Corp. v. United States, 20 Cl. Ct. 222, 228-29 (1990).
When reaching a summary judgment determination, the judge’s function is not to weigh the evidence, but to determine whether there is a genuine issue for trial. Anderson v. Liberty Lobby, Inc., 477 U.S. at 249 , 106 S.Ct. at 2510 ; see, e.g., Cloutier v. United States, 19 Cl.Ct. 326, 328 (1990), aff'd, 937 F.2d 622 (Fed.Cir.1991). The judge must determine whether the evidence presents a disagreement sufficient to require submission to fact finding, and then may also determine that the issues presented are so one-sided that one party must prevail as a matter of law. Anderson v. Liberty Lobby, Inc., 477 U.S. at 250-52 , 106 S.Ct. at 2511-12 . When the record could not lead a rational trier of fact to find for the nonmoving party, there is no genuine issue for trial, and the motion must be granted. Matsushita Elec. Industrial Co. v. Zenith Radio Corp., 475 U.S. 574, 587 , 106 S.Ct. 1348, 1356 , 89 L.Ed.2d 538 (1986). If, however, the nonmoving party produces sufficient evidence to raise a question as to the outcome of the case, then the motion for summary judgment should be denied. As indicated above, any doubt over factual issues must be resolved in favor of the party opposing summary judgment, to whom the benefit of all presumptions and inferences runs. Id.; see also Litton Industrial Products, Inc. v. Solid State Systems Corp., 755 F.2d 158, 163 (Fed.Cir. 1985); H.F. Allen Orchards v. United States, 749 F.2d 1571, 1574 (Fed.Cir.1984), cert. denied, 474 U.S. 818 , 106 S.Ct. 64 , 88 L.Ed.2d 52 (1985).
The initial burden on the party moving for summary judgment to produce evidence showing the absence of a genuine issue of material fact may be discharged if *384 the moving party can show, alternatively, that there is an absence of evidence to support the nonmoving party’s case. Celo-tex Corp. v. Catrett, 477 U.S. 317, 325 , 106 S.Ct. 2548, 2553-54 , 91 L.Ed.2d 265 (1986); see also Lima Surgical Assoc., 20 Cl.Ct. at 679 . If the moving party makes either showing, the burden is placed on the non-moving party to show that a genuine factual dispute exists by presenting evidence establishing the existence of an element of its case upon which it bears the burden of proof. Celotex Corp. v. Catrett, 477 U.S. at 322, 106 S.Ct. at 2552 ; Lima Surgical Assoc. Ass’n, 20 Cl.Ct. at 679. If, under no scenario, can the nonmoving party present the evidence to support its case, then there should be no genuine need for the parties to undertake the time and expense of a trial, and the moving party should prevail without further proceedings. Under Rule 56, the motion for summary judgment may succeed, whether or not accompanied by affidavits and/or other documentary evidence in addition to the pleadings already on file. Celotex Corp. v. Catrett, 477 U.S. at 324, 106 S.Ct. at 2553 . Generally, however, in order to prevail, the nonmoving party will need to go beyond the pleadings, by use of evidence such as affidavits, depositions, answers to interrogatories and admissions, in order to show that a genuine issue for trial exists. Celotex Corp. v. Catrett, 477 U.S. at 324, 106 S.Ct. at 2553 .
Both parties have filed motions for summary judgment and stated that there are no genuine issues of material fact in dispute to preclude summary judgment. With respect to the question of whether or not there are genuine issues of material fact in dispute, however, plaintiff has not always been consistent. Although defendant has consistently maintained that there are no material issues of fact in dispute, plaintiff has taken a more complex position. Plaintiff has filed its own cross-motion for summary judgment, asserting that the record before the court is essentially fully developed, but, at the same time, arguing that there are material facts in dispute regarding the issues raised in defendant’s motion for summary judgment.
Both defendant’s and plaintiff’s counsel have opined that little would be gained by going to trial. Despite the request by plaintiff’s counsel that defendant’s motion for summary judgment be denied, plaintiff’s counsel stated that the record would not be improved by hearing live testimony, or hardly expanded, if summary judgment were to be denied by the court. In fact, both parties seem to agree that between the two Appendices submitted, one by plaintiff and one by defendant, which total approximately 1900 pages, that the parties have offered a complete record to which very little could be added:
MR. VICTORINO: ... with respect to the need of a trial, we understand, and we will clarify here today, that there very well may be some issues of fact that are not stipulated or are in dispute.
However, I think we are both in agreement that I don’t think the record will be improved by having live testimony. We think the record is probably going to be about as good as it is.
Later, plaintiff reemphasized this point:
MR. VICTORINO: ... My feeling was that while there are issues that are in contention, that we cannot agree on, I don’t think there is anything that we can add that wasn’t covered in deposition. Or Your Honor may have to take a deposition statement of one person and compare it to another, and maybe some documents, and decide what the truth is.
... my view is I don’t think the record would be improved, certainly not substantially, by having live testimony.
Indirectly, defendant’s counsel also indicated that the record was complete. “... the briefing has been extensive, notwithstanding the time crunch. I get the feeling the case has been briefpd to within an inch of its life as well as ^íaybe having been ap-pendixed to within an inch of its life as well.”
Because of the inconsistencies regarding the need to develop additional evidence at a trial, during the oral argument on the cross-motions for summary judgment, the court asked plaintiff to clarify its position regarding whether material issues of fact *385 in dispute were present in the case, and, if so, to specifically identify any such disputed facts. There occurred three separate discussions between the court and plaintiff’s counsel regarding which material facts were claimed to be in dispute by plaintiff. The first colloquy was somewhat difficult for the court to follow. Therefore, the court repeated its question to plaintiff’s counsel:
THE COURT: I’m asking you again, because I still don’t know the answer. Are there or are there not material issues in dispute? You give me these double barreled answers that say on one scenario there are not, on another scenario there are.
MR. VICTORINO: There are clearly issues of fact in this case.
THE COURT: Are they material?
MR. VICTORINO: Yes.
THE COURT: What are they? Give me a list.
MR. VICTORINO: Those are the ones that we just mentioned.
THE COURT: Okay. All of those are material issues in dispute—
MR. VICTORINO: Yes.
THE COURT: Then how could you have cross moved for summary judgment?
MR. VICTORINO: Because those issues aren’t at issue on the areas that we raised on motion for summary judgment. Those are issues raised by Defendant’s case and Defendant’s motion for summary judgment.
Later, during the oral argument, and at the court’s urging, plaintiff recapitulated its list of those proposed findings of uncon-troverted fact, offered by the plaintiff or the defendant, which plaintiff maintains are material facts in dispute, and which, according to plaintiff, should preclude summary judgment for the defendant:
THE COURT: ... so let me review this list with you once again, because this is going to become critical.
Plaintiff’s Uncontroverted Facts 82, 83, 84, 86, 87, 97, 105, 114, 118, 125, 130, 131, 132,133 and 135, is that correct, Mr. Victorino? Those are items that you believe, as I understand it, correct me if I’m wrong, that you believe are material facts in dispute based on the record that’s before the Court.
MR. VICTORINO: Yes. And I emphasize material.
THE COURT: Material. Absolutely. They have to be material to get us past summary judgment, ...
As to material facts in dispute with regard to the Defendant’s Proposed Findings of Uncontroverted Fact, the same statement that these are material facts in dispute that would, in the opinion, of the Plaintiff, defeat summary judgment, numbers 18, 29, 34, 37. Is that correct, Mr. Victorino.
MR. VICTORINO: Yes.
THE COURT: All right.
I propose to take you at your word, Mr. Victorino, and take those numbers as the facts on which the Court needs to rule as to whether there are material facts in dispute, and use that as the basis for deciding whether or not summary judgment is appropriate here. 21
The fact that both parties have moved for partial or full summary judgment, based on the alleged absence of genuine issues of material fact, does not relieve the court of its responsibility to determine the appropriateness of summary disposition in the particular case. Prineville Sawmill Co. v. United States, 859 F.2d 905, 911 (Fed.Cir.1988) (citing Mingus Constructors, Inc. v. United States, 812 F.2d 1387, 1391 (Fed.Cir.1987)). “Simply because both parties moved for summary *386 judgment, it does not follow that summary judgment should be granted one or the other.” LewRon Television, Inc. v. D.H. Overmyer Leasing Co., 401 F.2d 689, 692-93 (4th Cir.1968), cert. denied, 393 U.S. 1083 , 89 S.Ct. 866 , 21 L.Ed.2d 776 (1969). See also Levine v. Fairleigh Dickinson Univ., 646 F.2d 825 , 833 (3d Cir.1981); Home Ins. Co. v. Aetna Cas. & Sur. Co., 528 F.2d 1388, 1390 (2d Cir.1976). Cross-motions are no more than a claim by each party that it alone is entitled to summary judgment, and the making of such inherently contradictory claims does not establish that if one is rejected the other is necessarily justified. Rains v. Cascade Indus., Inc., 402 F.2d 241, 245 (3d Cir.1968). The court must evaluate each party’s motion on its own merits, taking care to draw all reasonable inferences against the party whose motion is under consideration. Mingus Constructors, Inc. v. United States, 812 F.2d at 1391 .
After a careful review of the record filed in the instant case and the proposed findings of uncontroverted fact which plaintiff has listed as precluding summary disposition of this case, the court can find no reason why summary judgment should not be granted. The “facts” identified by the plaintiff as material facts in dispute do not entitle plaintiff to summary judgment because they are questions of law and not issues of fact, they are facts in dispute which do not affect the ultimate outcome of the instant litigation, and are, thus, not material, there is an absence in the record (which the plaintiff has conceded is probably nearly as complete as it could be) of evidence to support the plaintiff’s case, or, plaintiff has failed to establish the existence of an element of its case upon which plaintiff bears the burden of proof. Celo-tex Corp. v. Catrett, 477 U.S. 317, 325 , 106 S.Ct. 2548, 2553-54 , 91 L.Ed.2d 265 (1986). Moreover, as will be discussed below, plaintiff has failed to show that the government acted in an arbitrary and capricious manner, thus breaching its duty to fairly and honestly consider plaintiff’s proposal. The court, therefore, GRANTS defendant’s motion for summary judgment. Plaintiff’s cross-motion for summary judgment is, hereby, DENIED.
Plaintiffs Request for a Permanent Injunction to Enjoin the Selection of Delaware North
Plaintiff initially requested a temporary restraining order and preliminary injunction to prevent the defendant from awarding a contract until such time as this litigation could be resolved. However, because defendant voluntarily agreed to withhold any award pending notification of the court, the case was converted to one for a permanent injunction and the cross-motions for summary judgment currently before the court were filed.
Injunctive relief is considered a drastic measure, and when such relief is requested, the court should exercise caution. N.V. Philips Gloeilampenfabrieken v. United States, 1 Cl.Ct. 783, 784 (1983). Moreover, judicial review of an agency’s preaward procurement decision is limited in scope. Magnavox Elec. Sys. Co. v. United States, 26 Cl.Ct. 1373, 1380 (1992); RADVA Corp. v. United States, 17 Cl.Ct. 812, 818 (1989), aff'd, 914 F.2d 271 (Fed.Cir. 1990); Drexel Heritage Furnishings, Inc. v. United States, 3 Cl.Ct. 718, 721 (1983); Baird Corp. v. United States, 1 Cl.Ct. 662, 664 (1983). Frustrated bidders, however, have a right to seek redress in the federal courts for alleged arbitrary or capricious actions on the part of contracting officers. Scanwell Labs., Inc. v. Shaffer, 424 F.2d 859 (D.C.Cir.1970). Elaborating on Scanwell, in M. Steinthal & Co. v. Seamans, 455 F.2d 1289 (D.C.Cir.1971), the court addressed the deference federal courts should give to agency decision making in contract matters, and articulated the test for review of a contracting officer’s decision. In order to succeed in a request for injunctive relief, a plaintiff must meet the heavy burden of showing that there was no rational basis for the agency’s decision. Steinthal, 455 F.2d at 1301, 1306 ; Southwest Marine, Inc. v. United States, 3 Cl.Ct. 611, 613 (1983); AABCO, Inc. v. United States, 3 Cl.Ct. 109, 113 (1983); Baird Corp. v. United States, 1 Cl.Ct. 662, 664 (1983). More *387 over, great deference is accorded to preaward agency procurement decisions. RADVA Corp. v. United States, 17 Cl.Ct. at 818 . It is through a narrow lens, therefore, that this court is charged with determining whether the government has satisfied the implied contractual condition that each bid, received by the government in response to a request for proposals, will be fairly and honestly evaluated. National Forge Co. v. United States, 779 F.2d 665, 667 (Fed.Cir.1985); CACI, Inc. v. United States, 719 F.2d 1567, 1573 (Fed.Cir.1983); Prineville Sawmill Co. v. United States, 859 F.2d 905, 909 (Fed.Cir.1988); Coastal Corp. v. United States, 713 F.2d 728, 730 (Fed.Cir.1983); Skytech Aero, Inc. v. United States, 26 Cl.Ct. 251, 253-54 (1992); Celtech, Inc.-Federal v. United States, 24 Cl. Ct. 269 , 273 n. 1 (1991); Data Transformation Corp. v. United States, 13 Cl.Ct. 165, 171 (1987); Dynalectron Corp. v. United States, 4 Cl.Ct. 424, 428 , aff'd, 758 F.2d 665 (Fed.Cir.1984); Space Age Eng’g, Inc. v. United States, 4 Cl.Ct. 739, 741 (1984).
The plaintiff YRTSC bears the burden of showing by a preponderance of the evidence that the selection was irrational or involved a violation of applicable statutes or regulations, Quality Transport Services, Inc. v. United States, 12 Cl.Ct. 276, 281 (1987), and, therefore, that the government has breached its duty to fairly and honestly consider its proposal. Harris Data Communications, Inc. v. United States, 2 Cl.Ct. 229, 237, aff'd mem., 723 F.2d 69 (Fed.Cir.1983). The disappointed bidder must show that the government acted in an arbitrary and capricious manner in its selection. Tidewater Management Servs., Inc. v. United States, 216 Ct.Cl. 69, 72 , 573 F.2d 65, 67 (1978); Keco Industries, Inc. v. United States (I), 192 Ct.Cl. 773, 782 , 428 F.2d 1233, 1238 (1970); Keco Industries, Inc. v. United States (II), 203 Ct.Cl. 566, 574 , 492 F.2d 1200, 1203-04 (1974). As stated by the United States Court of Appeals for the Federal Circuit, a court will not find a breach by the government official and intervene unless it has been clearly determined that the agency in reaching its determination acted in an arbitrary and capricious manner when it rejected plaintiff’s bid. CACI, Inc-Federal v. United States, 719 F.2d 1567, 1573 (Fed.Cir.1983); Magnavox Elec. Sys. Co. v. United States, 26 Cl.Ct. 1373, 1380 (1992); Skytech Aero, Inc. v. United States, 26 Cl.Ct. 251, 254 (1992); Excavation Constr. Inc. v. United States, 204 Ct.Cl. 299, 302 , 494 F.2d 1289, 1290 (1974).
In Keco Industries, Inc. v. United States, 203 Ct.Cl. 566, 574 , 492 F.2d 1200, 1203-04 (1974) (Keco II), the Court of Claims set forth four factors to be considered when determining whether the government acted arbitrarily or capriciously towards a bidder-claimant: 1) whether the government procuring officials acted in bad faith, thus depriving the bidder of fair and honest consideration of its proposal; 2) whether there was a reasonable basis for the government’s decision; 3) the degree of discretion given to the procurement officials by applicable statutes and regulations; and, 4) whether government officials violated pertinent statutes or regulations, which, if violated, may form the basis for recovery, but which need not automatically constitute grounds for recovery. Keco II, 203 Ct.Cl. at 574 , 492 F.2d at 1203-04 .
In Tidewater Management Services, Inc., the United States Court of Claims amplified on the analytical framework established in Keco II, by which plaintiff must prove that the government’s action was arbitrary and capricious in order to recover. The Court stated:
Arbitrary and capricious action on the part of the Government may be shown by proof that there existed no reasonable basis for the award of the contract to another. Continental Business Enterprises, Inc. v. United States, supra, 196 Ct.Cl. at 637-38, 452 F.2d at 1021; Keco Industries (II) v. United States, 203 Ct.Cl. 566, 574 , 492 F.2d 1200, 1203-04 (1974). Subjective bad faith on the part of the procuring officials is such proof. Heyer Products Co. v. United States [ 135 Ct.Cl. 63 , 140 F.Supp. 409 (1956)], supra; Keco Industries (II) v. United States, supra. Proof that the procuring officials violated ‘pertinent statutes or *388 regulations can, but need not necessarily, be a ground for recovery.’ Keco Industries (II) v. United States, supra, 203 Ct.Cl. at 574 , 492 F.2d at 1204 .
Tidewater Management Services, Inc., 216 Ct.Cl. at 73 , 573 F.2d at 67 .
A situation similar to the facts presented by the instant case was faced by the court in Quality Transport Services, Inc. v. United States, which articulated an applicable standard of review:
Having moved for summary judgment, defendant now contends that plaintiff must show a strong likelihood of success by clear and convincing evidence. Defendant agreed to withhold award of the subject contract until April 30, 1987, so that plaintiff’s challenge could be adjudicated. By doing so, defendant obviated the need to rule on the application for a temporary restraining order and motion for preliminary injunction. At issue is whether plaintiff is entitled to an injunction prohibiting the award of the subject contract to anyone other than plaintiff, not whether plaintiff qualifies for an interim injunction. In short, the question is not whether plaintiff can show a strong likelihood of success, but whether plaintiff succeeds in showing by a preponderance of evidence either that the contracting officer’s decision was irrational or involved a violation of statutes or regulations. See Harris Data Communications, Inc. v. United States, 2 Cl.Ct. 229, 237 , aff'd mem., 723 F.2d 69 (Fed.Cir.1983).
Quality Transp. Services, Inc. v. United States, 12 Cl.Ct. 276, 281 (1987). Unlike the requirements for issuance of a preliminary injunction, to succeed on a request for a permanent injunction, plaintiff must meet its burden of proof and actually succeed on the merits. Howell Const. Inc. v. United States, 12 Cl.Ct. 450, 453 (1987); Drexel Heritage Furnishings v. United States, 7 Cl.Ct. 134, 143 (1984).
By reviewing the list of facts allegedly in dispute according to the plaintiff, the court feels it has also covered the issues pertinent to deciding the merits of the case raised by the plaintiff regarding the NPS solicitation for concession services in Yosemite Park. In an effort to simplify the ensuing discussion, and to avoid repetitive discussions, the court has chosen to address the proposed findings of fact, alleged by plaintiff to be in dispute, by grouping them in subject matter categories. Although some repetition is necessary, where possible, the court has also attempted to refer the reader back to earlier discussions regarding recurring points.
Plaintiffs Proposed Findings of Uncon-troverted Fact 82, 84, 97 and 105
Plaintiffs 82 — In evaluating the YRTSC offer, NPS required ‘compelling evidence’ that YRTSC had $12 million in equity for working capital.
Plaintiffs 84 — NPS determined that YRTSC did not present compelling evidence that YRTSC had $12 million at the time of the offer and for that reason rated YRTSC unsuccessful on Criterion 15.
Plaintiffs 97 — NPS has determined that YRTSC met this [that YRTSC demonstrate the Phase I requirement with reasonable assurances that it had the ability to provide not less than $12 million of initial equity capital to undertake the concession operation] requirement.
Plaintiffs 105 — YRTSC believed that lack of binding commitments would not preclude YRTSC from consideration and, as stated in the proposal and the accompanying proposal letter, believed that more time would be allowed to submit information.
Compelling Evidence of Plaintiffs Ability to Obtain a Minimum of $12 million in Equity For Working Capital
As described above, plaintiff’s counsel identified plaintiff’s proposed findings of uncontroverted fact 82, 83, 84, 86, 87, 97 and 105 as material issues of fact in dispute. These items all relate to the issues raised in counts I, II and IX of plaintiff’s complaint and relate to plaintiff’s allegation that YRTSC should not have been found “unsuccessful” on Criteria 15 and 16 of the Phase II SOR. Plaintiff alleges that during the evaluation, the NPS incorrectly interpreted the Phase II SOR provision, *389 that an offeror provide a minimum of $12 million as initial equity for working capital, to require applicants to document the availability of those commitments at the time of the application. Plaintiff maintains that NPS improperly treated this issue as one of responsiveness, and rated YRTSC “unsuccessful” on criterion 15. Therefore, according to YRTSC, its offer was improperly eliminated without comparison to the other offers. Plaintiff, moreover, maintains that YRTSC had adequately demonstrated the ability to provide $12 million in equity capital under the Phase I standard of “reasonable assurances.”
The applicable SOR provisions regarding the proposer’s ability to obtain the necessary financing are found in the application section of the Phase II SOR. In pertinent part, they state:
5. The applicant will provide a minimum of $12 million as initial equity for working capital. That amount is intended to include the amount reimbursable to NPF [the National Park Foundation] as described at page 9 of BUSINESS OPPORTUNITY, Purchase of Existing Assets and Business. This must appear on the books of the New Concessioner as equity, not debt. Make sure that these commitments are reflected in the financial information provided. Describe the source of and terms for these funds. [Emphasis added.]
6. Identify the source of any financing needed. Document the availability of financing with financial statements, financing agreements and letters of intent from lenders. Present compelling evidence of proposers ability to obtain the necessary financing. Be specific. Identify all sources.
Describe the financial terms of each proposed financing source. Explain the financial arrangements you propose to use to finance any acquisition debt and to provide working capital.
If funds are to be raised from individuals, the APPLICANT must submit sufficient documentation to demonstrate, in a compelling way, the availability and commitment of such funds. [Emphasis added.]
Initially, the court notes that the interpretation of the terms of a government contract is a matter of law. Fortec Constructors v. United States, 760 F.2d 1288, 1291 (Fed.Cir.1985); Hol-Gar Mfg. Corp. v. United States, 169 Ct.Cl. 384, 386 , 351 F.2d 972, 973 (1965). The language of a contract must be given the meaning that would be derived from the contract by a “reasonably intelligent person acquainted with the contemporaneous circumstances.” Id., 169 Ct.Cl. at 388 , 351 F.2d at 975 . Only when the language of a contract is ambiguous will factors outside of the contract terms be taken into account. See Sylvania Elec. Prods., Inc. v. United States, 198 Ct.Cl. 106, 126 , 458 F.2d 994, 1005 (1972). When interpreting the language of a contract, a court must give reasonable meaning to all parts of the contract and not render portions of the contract meaningless. Fortec Constructors, 760 F.2d at 1292 ; United States v. Johnson Controls, Inc., 713 F.2d 1541, 1555 (Fed.Cir.1983). By analogy, the terms of a SOR, which is part of the government contracting process, should be interpreted in the same way. If the words of the SOR are clear, it is not the role of the court to second guess the plain meaning of those words by reaching beyond them for an interpretation.
The words of the Part V Financial Operations & Financing, Phase II SOR, when read as a whole, make it perfectly clear that NPS intended that the evaluators use the “compelling evidence” standard to review the Phase II applicants’ description of funds raised, to meet the minimum $12 million equity position requirement. Part V reads: “If funds are to be raised from individuals, the APPLICANT must submit sufficient documentation to demonstrate, in a compelling way, the availability and commitment of such funds.” (Emphasis added.) Nevertheless, plaintiff argues that pursuant to the terms of the Phase II SOR:
Financing as is used in this paragraph, includes loans. Loans, however, are specifically excluded from the definition of equity for working capital by paragraph 5 [of the Phase II SOR]. The compelling *390 evidence requirement of paragraph 6, therefore, cannot apply to the $12 million in equity for working capital. Paragraph 6, then, applies to loans that an offeror plans to use in connection with its proposal.
To determine which standard the evaluation team should use to evaluate an applicant’s response to the equity capital requirement, plaintiff, therefore, asks the court to go outside the Phase II document, back to the Phase I SOR, and adopt the Phase I standard of “reasonable assurance” with respect to an applicant’s proof of $12 million equity for working capital. If the Park Service was concerned about contracting with a financially viable organization, which it clearly was, why would NPS ask for “compelling evidence” only of loans, as plaintiff contends, but not ask for “compelling evidence” of the other sources of money to demonstrate the equity position of applicants?
Although plaintiff urges that the court reach back to the Phase I SOR to adopt a “reasonable assurance” standard for the equity capital requirement, this court will not do so. The language of the Phase II SOR is not ambiguous. The Park Service acted reasonably when it refused to take into account factors outside of Phase II SOR document and applied the “compelling evidence” test.
Plaintiff also contends that during the Phase I SOR evaluation the Park Service had already determined that YRTSC met the equity capital requirement. However, it appears to the court that because the purposes of the Phase I SOR and the Phase II SOR were different, a changed standard on evidence is not unreasonable. The Phase I objective was to screen applicants to establish a pool of eligible applicants, but not to make a final selection of a concessioner. As stated in an unsigned cover memorandum, dated April 4, 1992, sent to prospective applicants along with the Phase I SOR: “We hope, from Phase I, to have a list of those who would like to take a detailed look at our proposition and who are financially and managerially likely to be able to be competitive.” By contrast, the Phase II SOR was designed to effect the final selection of a concessioner, by which a close relationship, to last at least 15 years would commence. It is, therefore, reasonable that the NPS would insert a more stringent standard for final selection in Phase II of the SOR than in Phase I.
Moreover, the Phase II SOR, by its terms, explicitly distinguishes between Phases I and II of the SOR, to the point that documents considered under one phase of the SOR are not to be used in the other. The Phase II SOR states:
Documents submitted under the Phase I process should be regarded as being for that purpose only. They will not be used by the Service in evaluating offers under Phase II. Except for the purpose of addressing the specific criteria of Phase I, the Service neither accepts or rejects any of the proposals or ideas included in submittals under Phase I.
Plaintiff also maintains that the evaluation process was flawed because the individuals conducting the Phase I evaluation were largely the same individuals who served on the Phase II Evaluation Panel, and that the panel members, therefore, had seen the financial materials submitted during Phase I. Plaintiff reasons, therefore, that because the Phase I financial materials had been reviewed and discussed by some of the evaluators during the Phase I evaluation, those materials should be considered part of the relevant record for the Phase II selection process, and not excluded from Phase II consideration on the requirement for $12 million in equity for working capital.
This court, however, finds that the overlap of personnel on the evaluation and selection panel does not automatically result in a merger of the Phase I and Phase II evaluation processes. Plaintiff has failed to document that during the Phase II evaluation, the panel actually utilized or relied on any of the materials submitted during Phase I. Even if some of the individuals conducting the Phase I evaluation were on the Phase II evaluation panel, it is not clear that documents submitted during Phase I should have been considered in evaluating *391 offers under Phase II, or, in fact, were referred to during the Phase II evaluation. The selections from the depositions of Maurice Robinson and David Dornbusch provided to the court by the parties, and cited to by plaintiff, are not helpful to plaintiffs point that the Phase I materials should be used in the Phase II evaluation. In fact, a close reading of the Dornbusch deposition makes it clear that he understood he was not to rely on information which had been submitted in response to the Phase I SOR during the Phase II evaluation. Accordingly, the court finds that the plain meaning of the words of the Phase II SOR is that NPS clearly announced to all applicants, including YRTSC, that it intended to use the “compelling evidence” standard to evaluate financial operations and commitments, including the requirement for a minimum of $12 million in equity capital under the Phase II SOR. This court finds the actions of the NPS reasonable.
Plaintiffs Proposed Findings of Uncon-troverted Fact 83, 86 and 87
Plaintiffs 83 — Under the NPS interpretation, YRTSC had to have binding commitments for the $12 million at the time of the offer; YRTSC had to show that it had the money available at the time of the offer. [Emphasis in original.]
Plaintiffs 86 — NPS treated this requirement for evidence of working capital at the time of the offer as a responsiveness issue. Because, in the view of NPS, YRTSC did not meet the standard the SOR required, YRTSC was not considered further and precluded from selection as the new concessioner.
Plaintiffs 87 — Because YRTSC received unsuccessful ratings on Criteria 15 and 16, neither the Evaluation Panel nor the Selection Panel took YRTSC’s offer to the next stage for evaluation of the offer as a whole against the other offers.
Plaintiff next alleges that the Park Service improperly required YRTSC to have binding commitments for equity capital at the time the application was submitted, instead of at the time the contract was awarded. Plaintiff characterizes the Park Service’s evaluation of the equity capital requirement as tantamount to a responsibility determination, and argues that by finding YRTSC “unsuccessful” on the financing issue, NPS also found plaintiff’s application non-responsive. Therefore, plaintiff maintains that NPS breached its duty to consider YRTSC’s offer fully and fairly by eliminating plaintiff from consideration. Plaintiff stated:
NPS improperly based its negative responsibility determination solely on the materials in the Phase II offer. Instead of inquiring about YRTSC’s working capital, NPS rejected its proposal as non-responsive and gave it no further consideration.
Plaintiff alleges that YRTSC should have been allowed to present evidence regarding responsibility anytime before award. 48 C.F.R. § 9.105 -l(b) (1991). 22 At oral argument, plaintiff’s counsel also argued that, notwithstanding any authority the NPS might have under the CPA, the concepts of responsiveness and responsibility have been long established, that they predate the Competition in Contracting Act (CICA), and that they are “fundamental principles” of federal procurement. In response, defendant contends that CICA is not applicable to concession contracts awarded by the National Park Service because CICA, although generally applicable to procurement activities, contains an express exclusion for “procurement procedures otherwise expressly authorized by statute.” 41 U.S.C. § 253 (a)(1) (1988). Defendant also reasons that if CICA is not applicable to concessions contracts, then the “federal norm” relied on by plaintiff regarding the concepts of responsibility and responsiveness also has no applicability to the instant case. Defendant further argues that the Secretary of the Interior is expressly, and separately authorized, in the Concessions Policy Act (CPA) to contract for concessions in *392 national parks. Sections 2 and 3 of the CPA, 16 U.S.C. §§ 20a & 20b (1988), give the Secretary broad discretion to include in the final contract terms and conditions appropriate to carry out his mission under the Act. More important, however, as pointed out by defendant, NPS has promulgated its own regulations to give effect to the CPA. 36 C.F.R. §§ 51.1-51.7 (1992).
The question of whether or not concession contracts awarded pursuant to the CPA should be subject to Federal Acquisition Regulations (FAR) has been a matter of some debate. The Comptroller General has held that when the Department of the Interior issued a permit in exchange for a franchise fee, as authorized by the concessions statute, such was not a procurement of property or services within the meaning of the Competition in Contracting Act, and, therefore, the FAR was not applicable. Crystal Cruises, Inc., Comp.Gen.Dec. B-238347.2 (June 14, 1990), 90-1 C.P.D. ¶ 560, pp. 2-3. In Crystal Cruises, the Comptroller General states: “We found that' the issuance of a permit for a franchise fee granting a right of access to government land and property under the authority of 16 U.S.C. § 3 , which provides for the granting of such concessions by the Secretary of the Interior, is not a procurement of property or services within the meaning of CICA.” Likewise, the Comptroller General earlier had noted that procurements conducted under the authority of the Public Concessions Act (Concessions Policy Act) were not subject to the Competition in Contracting Act, and that the FAR did not apply. Stephen Sloan Marine Corp., Comp.Gen.Dec. B-234219 (May 9, 1989), 89-1 C.P.D. ¶ 435, p. 4. 23
In order to finally resolve whether a concession contract should conform to standard procurement rules, the Department of the Interior published a final rule in the Federal Register on September 3, 1992, to clarify that Federal Acquisition Regulations do not apply to such concession contracts. The regulation, however, was published after the Phase I and Phase II SORs in the instant case were issued, on April 1, 1992 and July 15, 1992, respectively, but before the applications were due for submission to NPS on November 16, 1992, and before the selection was made on December 17, 1992. The new regulation clearly states:
All concession contracts and permits are subject to the requirements of this part 51. They are not federal procurement contracts or permits within the meaning of statutory or regulatory requirements applicable to federal procurement actions.
57 Fed.Reg. 40,496 (1992) (to be codified at 36 C.F.R. § 51 ). The plaintiff questions the legality of this action, maintaining that the Park Service cannot, by regulation, exempt itself from the Competition in Contracting Act. Because of the date of the issuance of the new regulation, however, the court has not relied on it in this decision.
By its own terms, CICA does not encompass procurement procedures which are *393 otherwise expressly authorized by other statutes. 41 U.S.C. § 253 (a)(1) (1988). Moreover, it is clear that the CPA intended to authorize the Secretary of the Interior to award concessions contracts, and for the Secretary to exercise a great deal of discretion in choosing the means to do so, even if those actions are not in compliance with the FAR. The Concessions Policy Act is codified at 16 U.S.C. § 20a (1988), and reads in pertinent part:
[t]he Secretary of the Interior shall take such action as may be appropriate to encourage and enable private persons and corporations (hereinafter referred to as “concessioners”) to provide and operate facilities and services which he deems desirable for the accommodation of visitors in areas administered by the National Park Service. (Emphasis added).
Significantly, in both the Phase I and Phase II solicitation packages, distributed to all applicants, the applicants were alerted to the difference between the concession contract application process and traditional government contracting. In the Phase I SOR, the following words appear: “This Phase I-SOR is issued under rules and Federal Regulations unique to the NPS Concession Management Program.” Likewise, in the Phase II SOR, the NPS wrote:
This SOR is issued under rules unique to the National Park Service Concession Management Program. The Concession [sic] Policy Act (PL 89-249) is included with this document. Regulations are at 36 C.F.R. 51 and are under revision. Not all terms of the CONTRACT are discussed here. Applicants should carefully review all provisions of the draft CONTRACT.
This court, therefore, recognizes that the concession contract disputed in the instant case was issued pursuant to the CPA and is unique from a standard government contract. Accordingly, for all the reasons discussed above, this court will treat the con-cessioner selection process in this case as not subject to the FAR.
However, for argument’s sake, even applying the standards of the Federal Acquisition Regulations (FAR), it is clear that during the SOR evaluations at issue, the Park Service did not make a negative responsibility determination of YRTSC’s proposal, nor was YRTSC’s proposal arbitrarily or capriciously eliminated from further consideration. 24 Moreover, before making a non-responsibility determination under the FAR, the responsible government official must fulfill certain procedural and documentation requirements, in part because the effect of a non-responsibility determination is to preclude further consideration for an award, and because no standard contract award may be made unless the prospective contractor is affirmatively determined by the contracting officer to be responsible. See 48 C.F.R. §§ 9.101-9.105 -2 (1991). In making a responsibility determination, a contracting officer must consider, among other factors: financial resources; ability to comply with the proposed performance schedule; past performance record; past record of integrity; existence of the necessary organization, experience, operational controls, technical skills and quality assurance measures; whether the offeror has a satisfactory record of integrity and business ethics, and whether the offeror possesses the necessary facilities or has the ability to obtain them. 48 C.F.R. § 9.104-1 (1991).
If a non-responsibility determination is made, it must be documented. The FAR requires that:
Determinations____ When an offer on which an award would otherwise be *394 made is rejected because the prospective contractor is found to be nonresponsible, the contracting officer shall make, sign, and place in the contract file a determination of nonresponsibility, which shall state the basis for the determination.
Support documentation. Documents and reports supporting a determination of responsibility or nonresponsibility, including any preaward survey reports and any applicable Certificate of Competency, must be included in the file.
48 C.F.R. §§ 9.105-2 (a) & 9.105-2(b) (1991).
In the instant case, plaintiff has offered no evidence of documents or reports in the record to support that a final determination of non-responsibility by a selection official was made. Rather, as is more fully discussed below, the record demonstrates that plaintiffs application was evaluated and considered by the evaluation panel, the selection panel and then the selection official. It was not rejected until the selection official made his decision. In fact, the memorandum from the chairman of the selection panel to the selection official summarizes the results of the review of all the Phase II proposals and specifically states that only one offeror, California National Resource Management, Inc., not YRTSC, was considered “non-responsive.”
Moreover, even if plaintiff could point to documentation showing that a non-responsibility determination had been made, or if the plaintiff could show that it had not received the selection because of a finding of non-responsibility, the government is entitled to some deference in its decision making. The standard of review regarding the actions of a government official who has made a responsibility determination under the FAR is a difficult one for a plaintiff to meet. The court in Hayes Intern. Corp. offered a helpful summation of the standard:
It is well-established that the contracting official has a considerable degree of discretion in arriving at a responsibility determination. See Keco, 203 Ct.Cl. at 576 , 492 F.2d 1200 ; Trilon Educational Corp. v. United States, 217 Ct.Cl. 266 , 578 F.2d 1356 (1978). Because the criteria for determining bidder responsibility are not readily susceptible to reasoned judicial review and essentially involve a matter of business judgment, see Trilon, 217 Ct.Cl. at 270-271 , 578 F.2d 1356 , affirmative determinations of responsibility generally will not be overturned absent allegations of fraud or bad faith. Id.; accord Keco, 203 Ct.Cl. at 576 , 492 F.2d 1200 .
Hayes International Corp. v. United States, 7 Cl.Ct. 681, 685 (1985). Financial capability is but one of a number of factors to be considered when making a responsibility determination under the FAR and a firm with adequate financial resources may be found non-responsible if it does not meet the other criteria. Adequate financial capability, in and of itself, does not equate to meeting the responsibility requirements. 48 C.F.R. § 9.104-1 (1991).
Under the solicitation at issue in this case, even if an applicant, such as YRTSC, passes the test of responsibility under Phase I of the solicitation, as far as Phase II of the solicitation is concerned, the National Park Service can point to independent regulatory authority for its decision to consider financial capability as part of the Phase II proposal evaluation process. This authority is codified at 36 CFR § 51.4 (b) (1992), which implements the CPA and reads:
The principal factors to be considered in selection of the best proposal shall be (1) the experience and related background of offerors, (2) the offeror’s financial capability, and (3) conformance to the terms and conditions of the prospectus in relation to quality of service to the visitor. Secondary factors shall included franchise fee offered and other factors as may be specified.
Plaintiff, nonetheless, continues to assert that the issue of performance capability, which it maintains can include inquiries into financial resources, experience, past performance, place of performance and integrity, are issues of contractor responsibility and should not be used as an evaluation factor. Although there has *395 been some debate regarding whether or not financial capability is appropriate for use as an evaluation factor, in Delta Data Systems Corp. v. Webster, 744 F.2d 197 (D.C.Cir.1984), now Justice Scalia wrote:
As we have noted, however, GAO decisions support the proposition that responsibility factors may be considered in the course of proposal evaluation____ We agree with that assessment, and find no basis for excluding from its generality financial factors where they are reasonably relevant to the proposal in hand.
Id., 744 F.2d at 203 . Likewise, Professors Nash and Cibinic similarly indicate that responsibility related factors also can be used in the evaluation process:
Agencies commonly use responsibility related factors in the evaluation process, notwithstanding the fact that a responsibility determination must ultimately be made____ This process does not constitute a responsibility determination, ...
John Cibinic, Jr. and Ralph C. Nash, Jr., Formation of Government Contracts 547 (1986).
The Phase II SOR, therefore, permissibly stated:
Proposals for financial commitments will be closely reviewed against Balance Sheet and Income Statement projections and the Service’s knowledge of the operating costs of this business. Predictable, stable, and well-run businesses consistently providing maximum service to the public in operations and facilities that are the best of their type are most consistent with the National Park Service’s objectives of public service. Financial commitments which appear inconsistent with these objectives and/or which do not appear to allow the concessioner a reasonable opportunity for a profit from the operations authorized hereunder based on the capital invested are not acceptable. However, not-for-profit or nonprofit proposals will be evaluated as such.
Having passed the threshold review in Phase I of the SOR, the proposal submitted by YRTSC was in fact reviewed in Phase II by the evaluation panel, the selection panel and the selection official, and was not, as plaintiff would have us believe, eliminated following an alleged finding of non-responsibility. A December 17, 1992 memorandum from Mr. John H. Davis, chairman of the selection panel asking for the concurrence of Mr. Herbert S. Cables, Jr., Deputy Director of the National Park Service, who was the individual designated to make the selection, tells the story. According to the memorandum:
The Yosemite Concession Selection Panel was established to review these offers and select the best overall proposal received for award of the contract. The ‘best proposal’ is described in the prospectus as that offer which is considered most likely to effectively achieve the objectives of the National Park Service for concession services and facilities in Yosemite National Park as stated in the prospectus and related documents. In addition to conformance to the terms and conditions of the prospectus, the principal factors to be considered in the selection of the best proposal are the experience, related background and financial capability of the offeror. These principal factors are set forth in the Phase I prospectus Selection Criteria. Particularly, Phase I applicants had to demonstrate substantial competence to operate a complex, service-oriented business and demonstrate with reasonable assurance the ability to provide not less than $12 million initial equity capital. The five Parts of the additional Selection Criteria contained in the Phase II prospectus contain more specific criteria related to these principal factors (Part II and Part V Selection Criteria) and a variety of secondary criteria, including the level of the offeror’s concession facility financial commitments (Selection Criterion 16), Equal Opportunity programs (Selection Criterion 9), and the offeror’s understanding and commitment to the preservation and interpretation of the resources of Yosemite National Park (Part IV Selection Criteria or ‘resource preservation criteria’).
Following the review and evaluation of Phase II proposals, Mr. Davis recounted *396 how the selection panel reached its decision:
All the offers, except one considered as non-responsive, [California National Resource Management, Inc.] were determined satisfactory in regard to the principal factor of experience and related background. The results of the evaluation of financial ability and conformance to the terms and conditions of the prospectus were more varied. Several of the offers did not contain the required “compelling evidence” of the ability to provide $12 million of initial equity capital and several were conditioned on substantive changes to the proposed concession contract for the benefit of the offer- or, including shifting of environmental liabilities, contrary to the terms of the prospectus. Only one offer was determined to meet all the principal selection factors. This offer is clearly the best overall offer in the opinion of the Selection Panel for the reasons discussed below.
Further, Davis added:
YRTC is a newly formed company with an experienced board of directors and management team but is not an ongoing concern. The Selection Panel considers that the offer demonstrates satisfactory experience and related background. The Selection Panel also considers that YRTC[’s] offer is satisfactory with respect to Equal Opportunity and resource preservation factors. However, YRTC did not present required evidence of an ability to fulfill the stated financial requirements. The offer states that YRTC has raised only $7 million of the $12 million minimum requirement for equity capital but intends to raise the balance by award of the contract. The $7 million the offer states has been raised was accomplished by a private stock placement. The offer did not contain copies of purchase pledges for the $7 million nor does it present any evidence to the effect that it has the ability to raise the balance of the $12 million. The prospectus, in this regard requires offerors to submit specific “compelling evidence” of an ability to obtain the necessary financing. The Selection Panel considers that YRTC does not meet the principal factor of financial capability.
YRTC proposes a CIF contribution of 2% for the first four years of the contract and 6.1% for the balance ($65.7 million total present value). However, a substantial portion of this contribution is conditioned on a sharing of profits in later years of the contract, an eventuality which is not assured.
The offer also proposes to limit YRTC’s environmental mitigation liability to $12.3 million requiring indemnification from the government or MCA in this regard. The offer further assumes that implementation actions under the Concessions Services Plan or Housing Plan will be subject to negotiation with NPS, including the level of contribution to the CIF. This assumption is contrary to the terms of the prospectus and contract. Acceptance of this assumption by NPS would impact the ability of NPS to implement these plans as needed and could prove detrimental to visitor service as the effect could be to reduce contributions to the CIF and/or impede implementation of concession improvements. In any event, such assumption and limitation of liability could not be accepted, even if otherwise lawful and in the best interests of the government, without re-solicitation of the concession opportunity because they constitute material changes to the terms of the solicitation for the benefit of the offeror.
YRTC is specifically rated unsatisfactory with respect to Criteria 15 and 16 as discussed further in the attached evaluation.
John Davis went on to state that the selection panel considered that, “the offer of Delaware North Companies, Inc. is the best overall offer as it is the most likely to achieve the objectives of the National Park Service for concession services and facilities in Yosemite National Park.” The evaluation panel performed its assignments. It reviewed and analyzed each proposal and then compared the proposals. A comparative matrix was prepared. The statement *397 by Stephen Crabtree at his deposition that the evaluation panel did not have to compare the applications point by point because they had only one offer which was found “satisfactory” on all criteria does not mean that offers found “unsatisfactory” on one or more criteria were eliminated from further consideration by the evaluation panel. The following colloquy at Stephen Crab-tree’s deposition is instructive:
Q. [counsel for plaintiff] What is the significance of having only one that meets all the criteria?
A. Well, one that meets all the criteria is presumably better than any who don’t meet some of the criteria.
Q. Okay. Did you meet any criteria, other than 15 or 16, in which Delaware North’s proposal was considered better that the proposal of YRTSC?
A. That evaluation phase was never done. You wouldn’t get to that phase. You would not spend the time to evaluate the specific quality of each until you reached satisfactory. Then you would evaluate all of the offers that were satisfactory against each other.
Because the evaluation panel found only one offer to be successful on all criteria, the evaluation panel felt that it could shortcut its work and reach an earlier recommendation, which could then be reviewed by the selection panel, and, then, by the NPS selection official. YRTSC was treated in exactly the same manner as all the other offerors who had submitted applications pursuant to the Phase II SOR.
The reasons why an applicant, such as YRTSC, was found “unsatisfactory” on Criteria 15 and 16 were included in the evaluation report, which discussed each of the proposals received in depth. The evaluation report was then made available to the selection panel for their review. The selection panel prepared its own report and presented it to Herbert Cables, the selection official. The selection panel “strongly” recommended that Delaware North be selected for award of the final contract. Herbert Cables, as the individual designated to make the selection, endorsed the selection panel’s memo, resulting in the announcement that Delaware North had been selected. The National Park Service’s evaluation of all the proposals received, including YRTSC’s proposal, was carefully arrived at and documented with an evaluation memorandum of over twenty-five pages of supporting rationale on just YRTSC, as well as a twenty-three page memorandum evaluating Delaware North. Similar detailed evaluations appear to have been prepared on each of the other applications. Additionally, the selection panel’s memorandum was another eight pages. The language of the evaluation memorandum is clear that the evaluation panel did not make the final decision regarding the winning contractor, but presented options to a selection panel. The selection panel did not make the final decision either, but made a recommendation to Mr. Cables, the NPS Deputy Director, who made the final decision, which was announced on December 17, 1992. Accordingly, plaintiff's claim that it was precluded from further consideration after receiving an “unsuccessful” rating from the evaluation panel on Criteria 15 and 16 is without merit. Plaintiff was considered at each stage of the review, but Delaware North was found to have submitted the “best overall offer.”
Part of plaintiff’s confusion as to the evaluation procedure, including plaintiff’s versions of the concepts of responsibility and responsiveness, may arise, in part, from the fact that in plaintiff’s briefing material submitted to this court, plaintiff appears to have used the terms “bid” and “offer” interchangeably, and apparently has ignored the distinctions between sealed bidding and negotiation. “Sealed bidding is a method of contracting which employs competitive bids, public opening of bids, and awards.” 48 C.F.R. § 14.101 (1991). Professors Cibinic and Nash explain some of the distinctions between negotiation and sealed bidding as follows:
Negotiation differs significantly from sealed bidding. First, proposals are not available for public inspection prior to award. In contrast, under sealed bidding public opening of bids is a major part of the process and bids may be examined by any person at that time. Second, the *398 contracting officer is not required to reject proposals which vary from the RFP requirements but may consider such proposals. Thus, negotiation does not involve the concept of responsiveness developed in sealed bidding even though the term is sometimes used in negotiations, Pacificon Productions, Inc., Comp. Gen.Dec. B-196371, 80-2 CPD II58 (1980). The concept of responsiveness was developed in sealed bidding where a contracting officer is prohibited from considering a bid which deviates from the IFB. This prohibition is not applicable to negotiation where the contracting officer is permitted and encouraged to conduct oral or written discussions with offerors whose proposals vary from the RFP. Third, the negotiation process permits discussion between the parties and modifications of proposals by offerors while sealed bidding does not. Finally, under negotiation the Government’s source selection officials have much greater discretion in selecting the successful offeror for award. They may “trade off” cost to the Government against other subjective factors such as technical performance or management capability in arriving at the source selection decision____
John Cibinic, Jr. and Ralph C. Nash, Jr., Formation of Government Contracts 523-24 (1986). Had the instant selection process been conducted as a sealed bid, which it was not, failure to comply in all material respects with the invitation for bids would have been fatal to the bidder’s chances for award. 48 C.F.R. § 14.301 (1991). Therefore, if the Park Service’s Phase II SOR had been a sealed bid procurement, then YRTSC’s failure to be responsive to Criteria 15 or 16 would have precluded further consideration of YRTSC’s proposal. In the case at bar, however, the Park Service requested proposals pursuant to rules for negotiations, not sealed bidding. Contrary to what would have happened in a sealed bid situation, plaintiff was not precluded from further consideration after the evaluation panel found YRTSC’s proposal “unsuccessful” for Criteria 15 and 16.
Plaintiffs Proposed Findings of TJncon-troverted Fact 105
Plaintiffs 105 — YRTSC believed that lack of binding commitments would not preclude YRTSC from consideration and, as stated in the proposal and the accompanying proposal letter, believed that more time would be allowed to submit information.
Plaintiff contends that YRTSC believed that the lack of binding commitments on the date the offer was submitted should not have precluded plaintiff from consideration and selection, and that more time should have been allowed to plaintiff to submit information confirming those commitments, up to the time a contract was signed; this, plaintiff contends, represents a material fact in dispute which should preclude summary judgment.
Plaintiff argues that:
NPS’s requirement of binding commitments of $12 million in equity for working capital at the time offers were submitted also conflicts with the terms of the SOR itself. The SOR contains a document drafted by NPS entitled: “Format for Applicant’s Proposal Letter” that of-ferors were required to include with their offers. That document states:
We also agree to provide the National Park Service within thirty days of the presentation of the final Concession Contract binding commitments for the financing proposed by our offer and agree to make the required $12 million initial capital investment in the NEW CONCESSIONER as of its formation. [Emphasis in original.]
Defendant, however, contends that plaintiff’s showing of financial capability for a minimum of $12 million in equity for working capital was to be included in the proposal on the date the application was submitted, so that the offer could be evaluated individually and collectively. According to the defendant, the SOR clearly stated that NPS intended to select the concessioner without further submittals, and that NPS, therefore, was under no duty to seek additional information.
*399 The court finds, however, that whether , or not YRTSC should have been allowed more time to present its financial information can be resolved by the court by a plain reading of the SOR Phase II language, and is not a question of fact. The relevant paragraphs read:
5. The APPLICANT will provide a minimum of $12 million as initial equity for working capital. That amount is intended to include the amount reimburseable to NPF as described at page 9 of BUSINESS OPPORTUNITY, Purchase of Existing Assets and Business. This must appear on the books of the New Conces-sioner as equity, not debt. Make sure that these commitments are reflected in the financial information provided. Describe the source of and terms for these funds.
6. Identify the source of any financing needed. Document the availability of financing with financial statements, financing agreements and letters of intent from lenders. Present compelling evidence of proposers ability to obtain the necessary financing. Be specific. Identify all sources.
Describe the financial terms of each proposed financing source. Explain the financial arrangements you propose to use to finance any acquisition debt and to provide working capital.
If funds are to be raised from individuals, the APPLICANT must submit sufficient documentation to demonstrate, in a compelling way, the availability and commitment of such funds.
7. The APPLICANT selected by NPS to be awarded the CONTRACT may, subsequently, propose for NPS consideration modifications to its financing arrangements if they are at least as favorable to NPS as those presented in the offer. NPS, however, is not obligated to accept such modifications. Modifications in financial terms approved by NPS, including but not limited to modifications to the MCA financing arrangement, if applicable, will not be considered a material amendment to the terms and conditions of this SOR or the CONTRACT.
(Emphasis added.) The language of these paragraphs of the Phase II SOR clearly requires that an applicant submit its best presentation of the requested information at the time an application was sent to NPS. In fact, paragraph 7 states that a modification to the financial proposal submitted may be proposed for NPS consideration, but that NPS is not obligated to accept such modifications.
The Phase II SOR is clear that all applicants were asked to submit compelling evidence of the source availability of financial commitments along with their proposals for evaluation purposes. As stated in the solicitation “Make sure that these commitments [for the minimum of $12 million] are reflected in the financial information provided.” It would have been impossible for the NPS evaluators to compare the applications received should some applicants have chosen to turn in financial information with their applications and others have chosen not to do so. Surely such cannot have been the intent of the words of the Phase II SOR. The plain instruction of the Phase II SOR was to require submission of evidence of financial information with the application when it was tendered to the NPS. Additionally, 36 C.F.R. § 51.4 (b) (1992), the concession regulations, state that “the principal factors to be considered in selection of the best proposal shall be ... (2) the offer- or’s financial capability.”
Although plaintiff maintains that it could have raised $12 million in equity capital at the time the proposal was submitted, only $7,035,000 were documented in YRTSC’s application. The Phase II proposal submitted by plaintiff states: “YRT Services Corporation will raise $12 million through a private placement of convertible preferred stock. Of this amount, commitments in the amount of $7 million have been received since efforts were initiated, ...” In addition, in the cover letter submitted with plaintiff’s Phase II proposal, and dated November 16, 1992, plaintiff states, “we anticipate receiving additional commitments of $5.0 million before contractor selec-tion____” (Emphasis added.)
*400 Plaintiff also places reliance on the proposed “Format for Applicant’s Proposal Letter,” attached to the Phase II SOR, which states “[w]e also agree to provide the National Park Service within thirty days of the presentation of the final Concession Contract binding commitments for the financing proposed by our offer and agree to make the $12 million initial capital investment in the NEW concessioner as of its formation.” Plaintiff argues that the language of this document allowed applicants thirty days following presentation of the Concession Contract to the winner to provide its binding $12 million commitments to the NPS. There is, however, a difference between the need to provide the actual binding commitment documents for the $12 million to the NPS, together with making the initial $12 million investment in the new concessioner, as compared to the Phase II SOR requirement to present “compelling evidence” of the $12 million as available so that all the applications can be compared to each other. Plaintiff, YRTSC, in fact, only presented “compelling evidence” of just over $7 million of available equity for working capital.
In addition, plaintiff tries to construct an argument based on its subjective belief that it was not required to submit all its financial information prior to award, but that it would have more time to submit financial information up to the time of award. Plaintiff relies on deposition testimony, given after the lawsuit was filed, of Mr. Richard Martyr, a board member of YRTSC. He testified that YRTSC was “not aware of requirements of proof for the $12 million, at least what specific documents the Park Service would require,” that YRTSC “didn’t know if the commitment letters themselves would be sufficient, that the Park Service may need something else” and that YRTSC was “prepared to provide any of that information [financial] should the Park Service require it.” Likewise, Mr. Green, Executive Director of YRTSC, stated following initiation of the lawsuit, that YRTSC did not believe that the lack of binding commitments would preclude YRTSC from consideration and believed that more time would be allowed to submit information. YRTSC’s beliefs, however, are not material and do not rise to the level of a material fact in dispute to preclude defendant’s motion for summary judgment. The language of the Phase II SOR is controlling in this situation. Moreover, plaintiff has pointed to nothing in the record which was written or said by a NPS official to mislead or alter the words of the Phase II SOR.
Plaintiff’s underlying contention that NPS ceased to consider YRTSC’s proposal further, after binding commitments for the $12 million were found to be missing, is also incorrect. As discussed previously, YRTSC was considered for an award up to the point Herbert Cables, the NPS Deputy Director, reviewed the selection panel’s memorandum and concurred in the selection of Delaware North. Despite the evaluation panel’s early recognition that “we had only one company that was satisfactory,” as documented in the deposition of Stephen Crabtree, the evaluation panel chairman, YRTSC was not precluded from further consideration following the panel’s recognition that plaintiff had failed to establish its ability to raise a minimum of $12 million, as required. To the contrary, the selection panel reviewed the work of the evaluation panel, including its analysis of the proposal submitted by YRTSC, and then sent a recommendation to Herbert Cables, the Deputy Director of the Park Service, who as the selection official also reviewed the recommendation and made the selection.
Moreover, there are clear indications in the record that YRTSC management understood it would have to document funding commitments, at a minimum, of $12 million at the time the Phase II proposal was submitted to NPS on November 16, 1992, even though, arguably, the paperwork reflecting the binding commitments had to be presented to the Park Service within thirty days of the presentation of the final concession contract and the $12 million initial capital investment had to be made in the new concessioner as of its formation. A letter from managing director, Bernard L. Butcher, a member of the YRTSC Board of *401 Directors, soliciting funds, included the following revealing language: "... Our bid for the contract must be in by mid-November, accompanied by funding commitments totaling $12 million____ A commitment is needed now but funding would take place only if and when we win the contract which will be well into 1993. In other words ... would only be supporting us if we are able to beat the competition on our own merits and be chosen by the Park Service____” Likewise, in the “YRT Services Corporation’s Private Placement Memorandum,” dated September 24, 1992, sent to prospective potential investors, the following words appear:
VIII. FINANCIAL PLAN
The Park Service has indicated that a prospective bidder for the Contract must demonstrate financial commitments of at least $12 million, and through realistic financial projections show that an appropriate return can be generated on this level of commitment. The $12 million figure is an estimate by the Park Service (concurred in by YRTSC) of the working capital needed to operate this business, with a reasonable margin for safety.
Plaintiffs Proposed Findings of Uncon-troverted Fact 114
Plaintiffs 114 — The commitments for the $12 million in equity for working capital are as follows:
[Investor 1] $4,000,000
[Investor 2] $ 500,000
[Investor 3] $1,500,000
[Investor 4] $1,000,000
[Investor 5] $3,000,000
[Investor 6] $1,000,000
[Investor 7] $1,000,000
Any doubts about availability of working capital could have been resolved through a request for clarification.
Plaintiff contends that any doubts about the availability of its $12 million in working capital could have been resolved through a request by NPS to YRTSC for clarification. Moreover, plaintiff asserts in “Plaintiff’s Motion for Summary Judgment and Memorandum in Support,” that it has obtained commitments for the $12 million since the bid opening.” (Emphasis added.) Allowing itself a little license in language, however, plaintiff, in its proposed findings of uncontroverted fact 114, submitted to the court on February 25, 1993, well after the November 16, 1992 submission application date, states, “the commitments for the $12 million in equity for working capital are as follows: ...” (Emphasis added.) As evidence of these commitments, the plaintiff points to the separate letters from each potential investor. In fact, plaintiff’s commitment letters appear to have been received by YRTSC after the proposal was submitted and, indeed, after the selection by NPS of Delaware North Corporation. Moreover, in the letters cited, several of plaintiff’s investors, even well after the applications had been submitted, indicated that the funds were not “committed” in the amounts claimed by plaintiff, but had been seriously conditioned on future approvals and events. For example, BankAmerica’s letter stated their “commitment to purchase up to $2,500,000 of the Preferred Stock ... we will consider increasing the level of commitment to a total of $3,000,000 if needed ... subject to BankAmerica Capital Investment Incorporated Board of Directors approval.” (Emphasis added.) Likewise, the letter from another investor stated that to increase its commitment from $500,000 to $1,000,000 would require “approval by the committee ... subject to full board approval at its next meeting.” (Emphasis added.)
By contrast, Delaware North, the company selected to receive the award, presented the NPS with a commitment for the $12 million equity contribution for working capital as of the date of the application, as well as assurances for additional financial commitments. The Delaware North proposal in response to the requirement for the $12 million financial commitment reads:
The financial commitment that DNC is prepared to make to the National Parks *402 Service for Yosemite National Park is indeed significant. In addition to the $12 million equity contribution for working capital, DNC has agreed to take on the liability of the National Parks Foundation’s note to MCA. Further, DNC is prepared to commit five percent of gross receipts to the Capital Improvement Fund and to make the required payments to the Government Improvement Account. When combined with the projected environmental remediation costs required during this period, additional services to be performed by the concession-er that were previously performed by the NPS, and capital expenditures not covered under the CIF, DNC’s financial proposal is indeed substantial.
In order to ensure that a prudent and thorough assessment has been made of the financial implications of the Yosemite operation, DNC has engaged the assistance of leading experts in various fields. In addition to its own highly trained in-house financial and auditing groups which have performed the due diligence, DNC has retained its outside auditors, Price-Waterhouse, to review and test its financial assumptions; ERM-West, Inc., to review existing and future environmental liabilities and to establish an ongoing remediation program; Pannell Kerr Forster to review hotel operations; and the Gallup Organization in order to help assess current and future customer wants and needs.
Regardless of the information plaintiff included in its Phase II application submission and the choices plaintiff made when it assembled its application, plaintiff, nonetheless, contends that any question regarding the amount of equity capital available could have been resolved through a clarification. Plaintiff cites to 48 C.F.R. § 15.601 (1991) to help define the concept of clarification as a means of “communication with an offeror for the sole purpose of eliminating minor irregularities, informalities, or apparent clerical mistakes in the proposal.” 25 The regulations applicable to concession contracts state: “The Director may solicit from any applicant additional information or written or verbal clarification of a proposal.” 36 C.F.R. § 51.4 (c) (1992). (Emphasis added.) The court, however, finds that YRTSC’s proposal was not in the least ambiguous, rather, the minimum $12 million dollars in equity capitalization simply was not documented by plaintiff in its submission. Consequently, the NPS could not have resolved anything by asking for a clarification. Plaintiff’s application clearly stated, as shown above, that YRTSC had commitments of just over $7 million, but anticipated raising the additional capital at a later date, subject to conditions by certain of its investors that additional funds still would require approval from their Boards of Directors. Thus, it is clear that YRTSC did not have commitments for the initial $12 million in equity capital, and apparently did not see the absence of the commitments as a problem, despite the clear language of the Phase II SOR to document, by “compelling evidence,” the proposer’s ability to raise a minimum of $12 million. Moreover, in their proposal plaintiff described the timing as follows:
Commitment, contingent on award of contract to YRTSC and successful placement of the Minimum Amount, are due by contract award, expected in January 1993. Funding to occur in August 1993.
In other words, plaintiffs proposal puts the financial cart before the horse. By making commitments for the $12 million contingent on award of the contract, plaintiff admits that it might not even have full funding available before award, or even at the time of award. Indeed, plaintiff even intended that funding would be obtained in August, 1993, seven months after the anticipated award date.
*403 It is highly questionable that plaintiff could have “resolved” a matter such as documenting roughly $5 million in missing financial commitments through a clarification. In order to resolve plaintiffs application defect, NPS would have had to permit YRTSC to change its offer, by removing the language making funding commitments contingent on the award of a contract and would have had to allow YRTSC to solicit changes in the qualified commitments from its financial backers to eliminate the contingent nature of their commitments. The SOR is clear that the proposal submitted should reflect the whole proposal made by an applicant. Moreover, the Park Service emphasized that it anticipated selecting a concessioner from the proposals made “without

[Text truncated at 120,000 characters. The full text is on the page linked above.]

---