# Town of Mount Vernon v. James Landherr

> Supreme Judicial Court of Maine · July 24, 2018 · 2018 ME 105

URL: https://www.frixlaw.com/law-library/cases/4296983

## Case

- **Court:** Supreme Judicial Court of Maine
- **Decided:** July 24, 2018
- **Citations:** 2018 ME 105
- **Precedential status:** Published
- **Opinion:** Opinion
- **Cited by:** 9 later opinions in the Frix Law Library

## Citator (automated)

- No negative treatment found by the automated citator. That is not the same as a confirmation that the case is good law; read the citing cases.
- Full citator and citing cases: https://www.frixlaw.com/law-library/cases/4296983

## Opinion text

MAINE	SUPREME	JUDICIAL	COURT Reporter	of	Decisions
Decision: 2018	ME	105
Docket: Ken-17-478
Argued: June	14,	2018
Decided: July	24,	2018

Panel: SAUFLEY,	C.J.,	and	ALEXANDER,	MEAD,	GORMAN,	JABAR,	HJELM,	and	HUMPHREY,	JJ.

TOWN	OF	MOUNT	VERNON

v.

JAMES	LANDHERR	et	al.

SAUFLEY,	C.J.

[¶1] James Landherr and Valerie Center, whom we refer to as the

landowners,	appeal	from	a	judgment	entered	by	the	District	Court	(Waterville,

Stokes, J.) in favor of the Town of Mount Vernon on its land use violation

complaint	filed	pursuant	to	30-A	M.R.S.	§	4452	(2017)	and	M.R.	Civ.	P.	80K. The

dispute between the landowners and the Town centers on a relatively large

generator	that	the	landowners	had	installed	on	their	small	lot	on	Minnehonk

Lake	before	seeking	a	permit	or	a	variance.

[¶2] Prior	to	the	proceedings	before	us,	on	appeal	from	a	decision	of	the

Town’s code enforcement officer, the Mount Vernon Board of Appeals

determined	that	the	landowners’	generator	was	a	“structure”	pursuant	to	the

Town’s	Land	Use	Ordinance. When	the	landowners	did	not	appeal	that	decision
2

and yet failed to comply with the Town’s request for the removal of the

generator because that structure was placed on the lot in violation of the

Ordinance,	the	Town	filed	a	land	use	violation	complaint. The	court	determined

that the previous decision of the Board of Appeals was res judicata as to

whether	the	generator	met	the	definition	of	“structure”	in	the	Town’s	Land	Use

Ordinance	and	found	the	landowners	in	violation	of	the	Ordinance,	assessing	a

penalty	and	attorney	fees. We	affirm	the	judgment	of	the	court.

I. BACKGROUND

[¶3] In	early	2015,	after	experiencing	a	number	of	power	outages,	the

landowners	installed	a	generator	on	their	lakefront	property. The	generator

was set on a concrete pad and was connected to the house by underground

electric	and	gas	lines. The	landowners	did	not	consult	with	the	Town	or	apply

for	a	permit	before	installing	the	generator.

[¶4] The	Town’s	Land	Use	Ordinance	requires	that	all	new	and	accessory

“structures”	be	set	back	at	least	100	feet	from	the	normal	high-water	line	of	any

great	pond	within	the	shoreland	zone. Mount	Vernon,	Me.,	Land	Use	Ordinance

§	5(C)(2)(a)	(June	13,	2015).1 The	Ordinance	further	provides	that	“[n]o	person

1 The Ordinance defines “structure” as “[a]nything temporarily or permanently located, built,

constructed	or	erected	for	the	support,	shelter	or	enclosure	of	persons,	animals,	goods	or	property
of	any	kind,	together	with	anything	constructed	or	erected	on	or	in	the	ground.” Mount	Vernon,	Me.,
3

shall	engage	in	any	activity,	land	use,	or	placement	of	a	structure	.	.	.	requiring	a

permit	in	the	district	in	which	such	activity	or	use	would	occur	.	.	.	without	first

obtaining a permit.” Id. § 11(B). There is no dispute that the landowners’

generator	was	placed	less	than	100	feet	from	the	lake.

[¶5] On	July	15,	2015,	the	Town’s	CEO sent	a	letter	to	the	landowners

advising them that “[a]ll structures located in a shoreland district require a

permit” and stating that a generator on their property appeared to be in

violation	of	the	Ordinance’s	setback	requirements. The	letter	ordered	them	to

either	remove	the	generator	or	apply	for	a	permit	on	or	before	August	10,	2015.

[¶6] The	landowners	filed	an	application	for	an	after-the-fact	permit	to

maintain	the	generator	in	its	location. By	letter	dated	August	12,	2015,	the	CEO

denied	the	permit,	stating	that	“the	structure	is	nonconforming	from	side,	front

and rear setbacks on the lot.” The CEO provided the landowners with

instructions for appealing his decision and applications for hardship and

administrative	variances. They	timely	appealed	the	CEO’s	denial	of	their	permit

to	the	Mount	Vernon	Board	of	Appeals,	arguing	that	their	generator	was	not	a

“structure”	as	defined	by	the	Town’s	Land	Use	Ordinance.

Land	Use	Ordinance	§	3	(June	13,	2015). “Accessory	structure”	is	defined	as	a	“structure	100	square
feet	or	greater,	except	in	the	shoreland	zone,	where	there	is	no	minimum	size.” Id.
4

[¶7] In	September	2015,	the	Board	of	Appeals	held	a	public	hearing	on

the	appeal. The	landowners	attended	the	hearing,	where	they	were	provided

an opportunity to argue their position. At the conclusion of the hearing, the

Board	of	Appeals	unanimously	voted	to	uphold	the	CEO’s	decision	and	issued	a

written	decision	concluding	that	the	generator	was	a	“structure”	after	finding

that	“the	generator	sits	on	a	pad,	has	underground	propane	pipes	and	[a]	power

line,	and	was	intended	to	remain	in	place.” The	landowners	did	not	appeal	the

decision of the Board of Appeals to the Superior Court.2 See 30-A M.R.S.

§	2691(3)(G)	(2017);	M.R.	Civ.	P.	80B.

[¶8] Approximately one month later, the CEO sent a letter requesting

that the landowners agree in writing to either remove the generator by

November	30,	2015,	or	incur	a	penalty	for	every	day	after	November	30	that

the	generator	remained	in	violation	of	the	Ordinance. On	November	11,	2015,

after	the	landowners	failed	to	respond	to	his	letter	and	the	time	for	filing an

appeal had expired, the CEO sent them a notice of violation pursuant to

30-A	M.R.S. § 4452, requiring the landowners to sign and return a consent

agreement,	which would	require	that	they pay	a $1,000	fine and	remove	the

2 The	landowners	also	applied	for	a	variance,	which	the	Board	of	Appeals	denied	after	a	public

hearing. They	do	not	appeal	from	that	decision.
5

generator	by	November	30. The	notice	stated	that	they	“must	notify	the	Code

Enforcement	Officer	when	corrective	action	is	taken	so	that	a	compliance	check

may be made” and warned that a failure to comply would “result in court

action.” (Emphasis	in	original.) The	landowners	responded	with	an	email	to

the	CEO,	acknowledging	the	notice	of	violation	and	stating	that	they	planned	to

make the generator mobile, but that it was unlikely that the work would be

completed by November 30, and that they would update the CEO when the

expected date of completion became known. They did not have any further

communication	with	the	CEO.

[¶9] On February 3, 2016, the Town filed a land use citation and

complaint in the District Court pursuant to 30-A M.R.S. § 4452 and M.R.

Civ.	P.	80K,	alleging	that	the	generator	had	not	been	removed	as	required	by	the

notice	of	violation	and	order	for	corrective	action	dated	November	11,	2015.

The Town sought a permanent injunction and order for the removal of the

generator	as	well	as	attorney	fees	and	civil	penalties. The	landowners	denied

the	allegations	and	the	matter	was	set	for	trial.

[¶10] Prior	to	trial,	the	Town	moved	for	summary	judgment	on	the	issue

of	whether	the	generator	was	a	“structure”	as	defined	by	the	Town’s	Land	Use

Ordinance,	see	M.R.	Civ.	P.	56,	asserting	that	the	decision	of	the	Board	of	Appeals
6

was a valid, final judgment and that relitigating the matter was barred by

principles of res judicata, see 30-A M.R.S. § 2691(4) (2017). Landherr and

Center	objected.

[¶11] The court held a one-day trial in April 2017. After hearing

argument, the court granted the Town’s motion for summary judgment.

Because	the	landowners	did	not	dispute	that	the	generator	was	located	within

100	feet	of	a	great	pond	in	violation	of	the	Town’s	Land	Use	Ordinance,	the	trial

proceeded to the dispositional phase during which the landowners asserted

that	the	Town	should	be	equitably	estopped	from	prosecuting	the	violation	and

that the violation was de minimis. On August 21, 2017, the court entered a

judgment	in	favor	of	the	Town. The	court	found	that	the	landowners	failed	to

present	sufficient	evidence	to	prove	their	equitable	defenses,	ordered	them	to

pay	a	minimal	civil	penalty	of	$500,	and	awarded	the	Town	attorney	fees	and

costs	totaling	$2,264.73. The	landowners	timely	filed	a	notice	of	appeal. See

14	M.R.S.	§	1901	(2017);	M.R.	App.	P.	2A,	2B.

II. DISCUSSION

[¶12] The	landowners	contend	that	the	court	erred	by	concluding	that

the	decision	of	the	Board	of	Appeals	precluded	them	from	relitigating	the	issue

of	whether	their	generator	was	a	“structure”	as	defined	by	the	Town’s	Land	Use
7

Ordinance,	arguing	that	summary	judgment	was	inappropriate	in a	Rule	80K

proceeding	and	that	they	were	entitled	to	a	de	novo	hearing	on	the	merits. They

urge	us	to	determine	that,	as	a	matter	of	judicial	policy,	it	would	be	better	for

the	public	to	be	able	to	litigate	issues	anew	in	any	land	use	violation	litigation.

[¶13] The	effect	of	a	prior	judgment	on	a	present	action	is	a	question	of

law	that	we	review	de	novo. State	v.	Thompson,	2008	ME	166,	¶	8,	958	A.2d	887.

Preliminarily,	we	reject	the	landowners’	contention	that	Rule	80K	prohibits	the

use of summary judgment in land use violation proceedings. See M.R.

Civ.	P.	80K(a) (stating that “[e]xcept as otherwise provided in this rule, [the

Rules of Civil Procedure] shall apply to proceedings in the District Court

involving	alleged	violations	of	land	use	laws	and	ordinances”).

[¶14] We	note,	however,	that	the	Town	was	not	required	to	file	a	motion

for summary judgment in order to have the court apply the decision of the

Board of Appeals. The issue could have been addressed in a more

straightforward	manner	by	a	request	from	the	Town	that	the	court	take	judicial

notice	of	that	decision. See	M.R.	Evid.	201;	see	also	Manguriu	v.	Lynch,	794	F.3d

119,	121	(1st	Cir.	2015)	(noting	that	courts	may	take	judicial	notice	of	agency

determinations); Furnari v. Warden, Allenwood Fed. Corr. Inst., 218 F.3d 250,

255-56	(3d	Cir.	2000)	(same);	Opoka	v.	INS,	94	F.3d	392,	394-95	(7th	Cir.	1996)
8

(citing cases from several federal circuit courts of appeals supporting the

“well-settled	principle	that	the	decision	of	another	court	or	agency,	including

the decision of an administrative law judge, is a proper subject of judicial

notice”); cf. United States v. Jones, 29 F.3d 1549, 1553 (11th Cir. 1994) (“[A]

court	may	take	judicial	notice	of	a	document	filed	in	another	court	not	for	the

truth	of	the	matters	asserted	in	the	other	litigation,	but	rather	to	establish	the

fact	of	such	litigation	and	related	filings.”	(quoting	Liberty	Mut.	Ins.	Co.	v.	Rotches

Pork	Packers,	Inc.,	969	F.2d	1384,	1388	(2d	Cir.	1992))).

[¶15] Ultimately, regardless of the vehicle by which the issue was

brought to the court, the court correctly determined that the decision of the

Board of Appeals was binding on the landowners. An issue of law or fact

litigated and decided in a valid, final judgment is conclusive in a subsequent

legal	proceeding	between	the	same parties. Town of	N.	Berwick	v.	Jones,	534

A.2d 667, 669 (Me.	1987). That form of res judicata known as “collateral

estoppel” or “issue preclusion” prevents the relitigation of issues already

decided	“if	the	identical	issue	was	determined	by	a prior	final	judgment,	and

the	party	estopped	had	a	fair	opportunity	and	incentive	to	litigate	the	issue	in

a	prior	proceeding.” Macomber	v.	MacQuinn-Tweedie,	2003	ME	121,	¶	22,	834

A.2d	131	(alteration	omitted)	(quotation	marks	omitted). The	doctrine	of	res
9

judicata	applies	to	decisions	made	by	municipal	bodies	as	well	as	to	judgments

issued	by	the	court. See	30-A	M.R.S.	§	2691(4)	(“Any	such	decision	that	is	not

timely	appealed	is	subject	to	the	same	preclusive	effect	as	otherwise	provided

by	law.”);	Jones,	534	A.2d	at	670	(establishing	that	res	judicata	applies	to	“a	final

adjudication	in	an	administrative	proceeding	before	a	quasi-judicial	municipal

body”).

[¶16] Each of	the elements of issue preclusion was established in this

case. See	Macomber,	2003	ME	121,	¶	22,	834	A.2d	131. First,	the	landowners

had a fair opportunity and incentive to litigate the issue of whether their

generator was a “structure” before the Board of Appeals. A review of the

minutes	of	the	public	hearing	reveals	that	they	had	notice	and	an	opportunity

to	be	heard. They	did,	in	fact,	advocate	assertively	for	their	position. Second,

after	the	Board	of	Appeals	issued	its	decision	and	the	period	for	filing	a	Rule

80B appeal expired without an appeal, the Board’s decision became a valid,

final	judgment. See	30-A	M.R.S.	§	2691(3)(G),	(4). Third,	the	issue	before	the

Board of Appeals—whether the landowners’ generator is a “structure” as

defined by the Town’s Ordinance—is the identical issue that they sought to

litigate in the District Court in the land use violation trial. Based on these

facts—which	the	landowners	do	not	dispute—and	for	these	reasons,	the	court
10

did	not	err	by	concluding	that	they	were	precluded	from	relitigating	the	issue

of	the	generator	as	a	structure	pursuant	to	the	Ordinance.3

[¶17] Finally, the landowners’ argument that the application of the

principles	of	res	judicata	in	these	circumstances	will	make	municipal	land	use

compliance more difficult and more expensive for landowners is not

persuasive. To the contrary, knowing the Town’s interpretation of the

Ordinance before the initiation of a land use violation complaint pursuant to

Rule 80K allows a landowner to take corrective action before risking the

potentially	draconian	penalties	flowing	from	the	filing	of	a	land	use	violation

complaint,	if	the	landowner	is	willing	to	work	with	the	Town	toward	a	solution.

See 30-A M.R.S. § 4452(3) (allowing penalties to be assessed “on a per-day

basis”).

[¶18] Pursuant to the final decision of the Mount Vernon Board of

Appeals, the generator on Landherr and Center’s property is a structure. It

must	meet	the	requirements	of	Mount	Vernon’s	Land	Use	Ordinance	regarding

structures. It	does	not. The	court	did	not	err	in	finding	that	the	landowners

were	in	violation	of	the	Ordinance	and	assessing	a	modest	penalty.

3 The	landowners	also	argue	that	the	court	erred	by	finding	that	they	had	failed	to	carry	their

burden	of	proof	in	establishing	their	equitable	defenses. We	are	not	persuaded	by	their	argument
and	do	not	address	it	further.
11

The	entry	is:

Judgment	affirmed.

Robert	E.	Sandy,	Jr.,	Esq.	(orally),	Sherman	&	Sandy,	Waterville,	for	appellants
James	Landherr	and	Valerie	Center

David	M.	Sanders,	Esq.	(orally),	Sanders	&	Hanstein,	Farmington,	for	appellee
Town	of	Mount	Vernon

Waterville	District	Court	docket	number	CV-2016-11
FOR	CLERK	REFERENCE	ONLY

---

Source: Frix Law Library, https://www.frixlaw.com/law-library/cases/4296983. Public record. Not legal advice.
