# Frederick Olson v. Town of Yarmouth

> Supreme Judicial Court of Maine · February 22, 2018 · 2018 ME 27

URL: https://www.frixlaw.com/law-library/cases/4247279

## Case

- **Court:** Supreme Judicial Court of Maine
- **Decided:** February 22, 2018
- **Citations:** 2018 ME 27
- **Precedential status:** Published
- **Opinion:** Opinion
- **Cited by:** 8 later opinions in the Frix Law Library

## Citator (automated)

- No negative treatment found by the automated citator. That is not the same as a confirmation that the case is good law; read the citing cases.
- Full citator and citing cases: https://www.frixlaw.com/law-library/cases/4247279

## Opinion text

MAINE	SUPREME	JUDICIAL	COURT Reporter	of	Decisions
Decision: 2018	ME	27
Docket: Cum-17-274
Argued: December	13,	2017
Decided: February	22,	2018

Panel: SAUFLEY,	C.J.,	and	ALEXANDER,	MEAD,	GORMAN,	JABAR,	HJELM,	and	HUMPHREY,	JJ.

FREDERICK	OLSON	et	al.

v.

TOWN	OF	YARMOUTH	et	al.

HUMPHREY,	J.

[¶1] Frederick Olson and Leora Rabin appeal from a judgment of the

Superior Court (Cumberland County, Warren, J.) affirming, pursuant to M.R.

Civ.	P. 80B, the Town of Yarmouth Planning Board’s approval of a site plan

application	by	Portland	Cellular	Partnership,	d/b/a	Verizon	Wireless	(Verizon),

to	install	wireless	communication	equipment	on	a	tower	and	site	owned	by	the

Yarmouth	Water	District. Olson	and	Rabin	argue	that	Verizon’s	application	did

not comply with Yarmouth’s Zoning Ordinance because (1) the Yarmouth

Water	District	site	was	subject	to	a	presumption	of	unsuitability	that	Verizon

failed	to	overcome,	and	(2)	Verizon	did	not	present	sufficient	evidence	that	it

investigated	other	technically	feasible	sites. Because	the	Board	did	not	err	by
2

concluding	that	Verizon’s	application	complied	with	the	relevant	provisions	of

the	Zoning	Ordinance,	we	affirm	the	judgment.

I. BACKGROUND

[¶2] In 2001, Sprint Spectrum L.P. (Sprint) submitted a site plan

application	to	the Town	of	Yarmouth	in	which	it	applied	to	install	a	wireless

communication	antenna	array	on	a	water	tower	owned	by	the	Yarmouth	Water

District	and	to	install	equipment	cabinets	on	the	ground	near	the	tower. The

Planning	Board	denied	the	application	because	it	did	not	meet	zoning	and	site

plan	ordinance	standards. In	April	2016,	Verizon	applied	to	the	Planning	Board

for	a	similar	use	at	the	same	site.

[¶3] At	a	public	meeting	on	May	25,	2016,	the	Planning	Board	reviewed

Verizon’s	plan. The	Planning	Board	and	neighboring	residents,	including	Olson

and	Rabin,	questioned	the	location	of	the	equipment	enclosure	and	the	related

visual,	noise,	and	health	effects	on	the	neighborhood. Olson’s	property	abuts

the	Yarmouth	Water	District	site,	and	Rabin	resides	within	500	feet	of	the	site.

Verizon	represented	that	it	would	examine	other	sites	and	look	at	the	gaps	in
3

coverage	that	led	to	the	selection	of	this	location. The	Planning	Board	did	a	site

walk	on	June	15,	2016.

[¶4] On	July	20,	2016,	Verizon	submitted	its	final	site	plan	application	to

install	equipment	on	the	Yarmouth	Water	District	site. Verizon	asserted	in	its

application	that,	by	installing	the	equipment	on	the	Yarmouth Water District

site, Verizon would “be able to fill the substantial coverage gap that it now

experiences, and provide improved coverage and capacity to residents,

businesses,	and	traffic	corridors	within	sections	of	Yarmouth	that	are	currently

located	within	deficient	service	areas	of	Verizon	Wireless’[s]	network.”

[¶5] The Town of Yarmouth Director of Planning and Development

(Director)	submitted	a	report	to	the	Planning	Board	on	September 23,	2016.

The	Director	detailed	how	Verizon’s	application	complied	with	individual	site

plan and zoning standards and concluded that the project conformed to the

Town’s comprehensive plan and submission requirements. As to the

Ordinance’s requirement that Verizon investigate other technically feasible

sites,	he	concluded	that	Verizon	had	“described	[its]	site	selection	process,”	and

the Yarmouth Water District site allows “the antenna to be located on an

existing water tower which avoids the need to construct a new tower.” The
4

Director recommended that the Planning Board approve the application if

Verizon	accepted	the	conditions	that	he	proposed	in	his	report.

[¶6] The	Director’s	report	included	the	2001	letter	denying	Sprint’s	site

plan	application	and	the	Planning	Board’s	findings	on	Sprint’s	application. The

2001	Planning	Board	report	stated	that	“[t]he	size	and	configuration	of	the	lot

on	which	the	water	tower	is	located	and	upon	which	equipment	is	located	is	too

small in area and too narrow in width and therefore too constrained for

‘adverse	impacts’	of	the	proposed	equipment	installation	on	the	ground	to	be

adequately	minimized,	per	[Yarmouth,	Me.,	Zoning	Ordinance,	art.	II(Z)(1)],	in

the	residential	context	and	close	proximity	to	adjacent	and	nearby	residences

involved.”1

[¶7] On	September	28,	2016,	the	Planning	Board	considered	Verizon’s

final	site	plan	application	at	a	public	meeting. The	Planning	Board	asked	about

alternative sites that Verizon had considered, and a Verizon representative

explained	that	it	looked	at	the	gaps	in	its	area	of	coverage	and	then	looked	for

sites	that	could	fill	the	gaps	with	a	minimal	impact	on	the	Town. The	Verizon

1 The	2001	Planning	Board’s	written	findings	included	a	section	entitled	“Presumption	of	inability

to accommodate similar equipment” that was stricken by hand. Because the record is devoid of
evidence concerning the rationale for removing this language and we review the Ordinance’s
provision	creating	a	presumption	of	unsuitability	de	novo,	see	Osprey	Family	Tr.	v.	Town	of	Owls	Head,
2016	ME	89,	¶	9,	141	A.3d	1114,	we	accord	no	weight	to	this	section	of	the	Planning	Board’s	findings.
5

representative told the Planning Board that Verizon’s “[g]oal at this site has

been	to	.	.	.	comply	with	the	primary	goal	of	the	Town’s	wireless	ordinance,	and

that	is	to	avoid	the	need	for	new	towers.” Verizon’s	search	revealed	that	the

Yarmouth	Water	District	site	was	the	only	appropriate	location	because	other

buildings in the area were not tall enough and a Central Maine Power pole

would	not	fill	the	coverage	gap	and	posed	administrative	hurdles. The	Planning

Board unanimously gave conditional approval to Verizon’s application after

finding that the plan conformed to the Site Plan Review Ordinance. The

Planning	Board	issued	a	written	approval	letter	on	October	7,	2016.

[¶8] On November 8, 2016, Olson and Rabin, who both appeared and

commented	at	the	Planning	Board	meetings,	filed	a	complaint	and	petition	for

review of final municipal action pursuant to M.R. Civ. P. 80B in the Superior

Court.2 Verizon intervened in the action. The court affirmed the Planning

Board’s	decision	on	June	1,	2017.

[¶9] Olson	and	Rabin	filed	a	timely	appeal. See	M.R.	Civ.	P.	80B(n);	M.R.

App.	P.	2(b)(3)	(Tower	2016).3

2 Pursuant to Yarmouth, Me., Site Plan Review Ordinance, art. I(F)(3) (June 2017), site plan

decisions	of	the	Planning	Board	are	appealed	to	the	Superior	Court	in	Cumberland	County.
3 This	appeal	was	commenced	before	September	1,	2017,	and	therefore	the	restyled	Maine	Rules

of	Appellate	Procedure	do	not	apply. See	M.R.	App.	P.	1.
6

II. DISCUSSION

[¶10] Olson	and	Rabin	raise	two	issues	on	appeal. First,	they	argue	that

the Planning Board erred in its approval of Verizon’s site plan application

because,	pursuant	to	article	II(Z)(4)(a)(3)	(Sept.	2016)	of	the	Yarmouth	Zoning

Ordinance, the Yarmouth Water District site was presumed to be unsuitable

and	Verizon	failed	to	overcome	that	presumption. Second,	they	contend	that

there	was	not	substantial	evidence	in	the	record	to	support	the	Board’s	finding

that Verizon investigated other technically feasible sites, as required by

Yarmouth,	Me.,	Zoning	Ordinance,	art.	II(Z)(9)(c)	(Sept.	2016).

[¶11] “We review the Planning Board’s approval of the [site plan

application] directly for error of law, abuse of discretion or findings not

supported	by	substantial	evidence	in	the	record.” Osprey	Family	Tr.	v.	Town	of

Owls Head, 2016 ME 89, ¶ 9, 141 A.3d 1114 (quotation marks omitted).

“Substantial evidence exists when a reasonable mind would rely on that

evidence	as	sufficient	support	for	a	conclusion.” Id.	(quotation	marks	omitted).

“Although interpretation of an ordinance is a question of law, we accord

substantial deference to the Planning Board’s characterizations and

fact-findings	as	to	what	meets	ordinance	standards.” Bizier	v.	Town	of	Turner,

2011	ME	116,	¶	8,	32	A.3d	1048	(quotation	marks	omitted). When	interpreting
7

an ordinance de novo, “we first evaluate the plain meaning of the Ordinance

and,	if	the	meaning	is	clear,	[we]	need	not	look	beyond	the	words	themselves.

We construe the terms of an ordinance reasonably, considering its purposes

and	structure	and	to	avoid	absurd	or	illogical	results.” Fryeburg	Tr.	v.	Town	of

Fryeburg,	2016	ME	174,	¶	5,	151	A.3d	933	(citation	omitted)	(quotation	marks

omitted). Olson	and	Rabin	bear	the	burden	of	persuasion	on	appeal	because

they	seek	to	vacate	the	Planning	Board’s	decision. See	Bizier,	2011	ME	116,	¶	8,

32	A.3d	1048.

A. Application	of	the	Presumption	of	Unsuitability

[¶12] We first consider Olson and Rabin’s argument that, pursuant to

article II(Z)(4)(a)(3) of the Ordinance, the Planning Board’s 2001 denial of

Sprint’s application to install a wireless communication antenna array and

associated	equipment	cabinets	on	the	Yarmouth	Water	District	site	created	a

rebuttable	presumption	that	the	site	was	unsuitable	to	accommodate	Verizon’s

proposal.

[¶13] Article	II(Z)(4)(a)(3)	states:

Once the Planning Board has determined that
telecommunications	equipment	proposed	by	the	applicant	cannot
be	accommodated	on	an	existing	or	approved	tower	or	Alternative
Tower Structure, each tower or Alternative Tower Structure so
found	is	presumed	unable	to	accommodate	similar	equipment	that
may	be	proposed	in	the	future	unless	the	Board	determines,	after
8

additional information is provided, that new technology or other
considerations enables the existing or approved tower or
Alternative	Tower	Structure	to	accommodate	the	equipment.

Yarmouth,	Me.,	Zoning	Ordinance,	art.	II(Z)(4)(a)(3).

[¶14] Olson and Rabin argue that Yarmouth, Me., Zoning Ordinance,

art.	II(Z)(4) (Sept. 2016)4 broadly addresses co-location requirements and is

4 Article	II(Z)(4)	provides:

4. Co-location	requirements

a. On	existing	towers:

(1) Applicants	for	site	plan	review	for	a	new	wireless	communication	tower
must	send	written	notice	by	pre-paid	first	class	United	States	mail	to	all
other	such	tower	and	Alternative	Tower	Structure	owners	and	licensed
wireless	communication	providers	in	the	Town	utilizing	exi[s]ting	towers
and Alternative Tower Structures and to owners of such towers and
Alternative Tower Structures within a 1 mile search radius of the
proposed	tower,	stating	their	siting	needs	and/or	colocation	capabilities.
Evidence that this notice requirement has been fulfilled shall be
submitted to the Planning Board	and	shall	include	a name and address
list,	copy	of	the	notice	which	was	sent,	and	a	statement,	under	oath,	that
the	notices	were	sent	as	required.	An	application	for	a	new	tower	must
include evidence that existing or previously approved towers and
Alternative Tower Structures within the Town and search area cannot
accommodate the communications equipment (antennas, cables, etc.)
planned	for	the	proposed	tower.	Such	evidence	would	be	documentation
from	a	qualified	and	licensed	professional	engineer	that:

(a.) Planned	necessary	equipment	would	exceed	the	structural	capacity
of	existing	and	approved	towers	and	Alternative	Tower	Structures,
considering the existing and planned use of those towers and
Alternative	Tower	Structures,	and	the	existing	and	approved	towers
cannot be reinforced to accommodate planned or equivalent
equipment	at	a	reasonable	cost;

(b.) Planned equipment will cause electromagnetic frequency
interference with other existing or planned equipment for that
tower	or	Alternative	Tower	Structure,	and	the	interference	cannot
be	prevented	at	a	reasonable	cost;
9

not	limited	to	applicants	seeking	to	construct	a	new	tower. They	contend	that

although article II(Z)(4)(a)(1) applies only to new-tower-construction

applicants, article II(Z)(4)(a)(3) applies both to new-tower-construction

(c.) Existing	or	approved	towers	and	Alternative	Tower	Structures	do
not	have	space	on	which	planned	equipment	can	be	placed	so	it	can
function effectively and at least in parity with other similar
equipment	in	place	or	approved;	or

(d.) Other documented reasons that make it technically or financially
unfeasible to place the equipment planned by the applicant on
existing	and	approved	towers	and	Alternative	Tower	Structures.

(2) Shared use shall be conditioned on the applicant’s agreement to pay a
reasonable	fee	and	costs	of	adapting	existing	facilities	to	the	proposed	use.

(3) Once the Planning Board has determined that telecommunications
equipment proposed by the applicant cannot be accommodated on an
existing	or	approved	tower	or	Alternative	Tower	Structure,	each	tower	or
Alternative Tower Structure so found is presumed unable to
accommodate similar equipment that may be proposed in the future
unless the Board determines, after additional information is provided,
that new technology or other considerations enables the existing or
approved tower or Alternative Tower Structure to accommodate the
equipment.

(4) The Planning Department will maintain a list of existing and approved
towers	and	Alternative	Tower	Structures,	including	name	and	address	of
owner(s),	within	the	Town	of	Yarmouth.

b. Construction	of	new	towers
A	proposal	to	construct	a	new	co-located	communication	tower	taller	than	the
maximum	height	permitted	for	a	single	wireless	communication	service	must
include	evidence	that	the	tower	can	structurally	support	a	minimum	of	three
(3)	antenna	arrays	for	each	anticipated	co-locating	entity.	(See	Section	II.Z.3.a
Tower	Height,	above.)

Prior	to	the	issuance	of	any	Building	permits	for	a	co-located	tower	in	excess	of
the height of a single user tower, the applicant will submit to the Code
Enforcement Officer executed agreements documenting commitments to
co-locate	from	the	number	of	co-locators	approved	by	the	Planning	Board.

Yarmouth,	Me.,	Zoning	Ordinance,	art.	II(Z)(4)	(Sept.	2016).
10

applicants	and	to	co-location	applicants	seeking	to	install	similar	equipment	on

an	existing	structure. Based	on	this	reading	of	the	Ordinance,	Olson	and	Rabin

assert that the presumption of unsuitability attaches to a site whenever the

Planning	Board	has	determined	that	the	site	is	unsuitable	for	co-location. Olson

and Rabin contend that the Planning Board’s 2001 determination that the

Yarmouth	Water	District	site	was	“too	small	in	area	and	too	narrow	in	width”

to	accommodate	Sprint’s	proposal	made	the	site	presumptively	unsuitable	for

any	later	application	to	install	similar	equipment	at	that	site,	and	that	Verizon

needed	to	rebut	that	presumption	before	its	application	could	be	approved.

[¶15] The question to be answered is whether the presumption of

unsuitability attaches to a co-location site only when an applicant initially

proposes to construct a new tower, or whether it also attaches when the

applicant’s	initial	proposal	is	to	co-locate	by	installing	equipment	on	that	site.

If	the	latter,	a	rebuttable	presumption	of	unsuitability	attached	to	the	Yarmouth

Water	District	site	after	the	Planning	Board	denied	Sprint’s	application	in	2001.

[¶16] As is the case with statutes, our single goal in interpreting an

ordinance	is	to	give	effect	to	the	Town’s	intent	in	enacting	the	ordinance. See

Dickau	v.	Vt.	Mut.	Ins.	Co.,	2014	ME	158,	¶	19,	107	A.3d	621. We	first	determine

if the language of the ordinance is plain and unambiguous. See id. Our
11

interpretation of the plain language is guided by “taking into account the

subject	matter	and	purposes	of	the	statute,	and	the	consequences	of	a	particular

interpretation.” Id. ¶ 21. We must construe the terms of article II(Z)(4)

reasonably, by considering the purposes and structure of the Ordinance to

avoid	absurd	or	illogical	results. See	Fryeburg	Tr.,	2016	ME	174,	¶	5,	151	A.3d

933. After	examining	the	entirety	of	the	Ordinance,	we	conclude	that	the	plain

and unambiguous language	of	the	Ordinance makes clear that article II(Z)(4)

applies	only	to	new-tower-construction	applicants.

[¶17] At	the	outset,	article	II(Z)	announces	that	one	of	the	purposes	of

the	Ordinance	is	to	encourage	co-location	and	“[p]ermit	the	construction	of	new

towers only where all other reasonable opportunities have been exhausted.”

See	Yarmouth,	Me.,	Zoning	Ordinance,	art.	II(Z)(1). Accordingly,	article	II(Z)(4)

describes the process that new-tower-construction applicants must use to

exhaust their opportunities for co-location before they can obtain Planning

Board	approval	of	their	new-tower-construction	application.

[¶18] No	language	in	article	II(Z)(4)	states	that	the	provisions	apply	to

co-location applicants. Instead, article II(Z)(4)(a)(1) expressly requires

new-tower-construction applicants to undertake a search for existing and

previously approved co-location sites that can accommodate the applicant’s
12

proposed	communications	equipment;	article	II(Z)(4)(a)(2)	requires	payment

of fees if a co-location site is found in that search; and article II(Z)(4)(a)(3)

creates a presumption of unsuitability if the Planning Board agrees with the

new-tower-construction	applicant	that	a	co-location	site	is	unsuitable,	and	the

effect	of	the	presumption	is	that,	unless	additional	information	is	provided	to

the	Planning	Board,	and	the	Board	determines	“that	new	technology	or	other

considerations enables the existing or approved tower or Alternative Tower

Structure to accommodate the equipment,” later new-tower-construction

applicants proposing	to	install	“similar	[communications]	equipment”	do not

have	to	submit	any	evidence	to	the	Planning	Board	about	the	unsuitability	of

that particular co-location site when attempting to comply with article

II(Z)(4)(a)(1). Finally, article	II(Z)(4)(a)(4) requires the Town to maintain a

list of existing and approved co-location sites. We reject Olson and Rabin’s

interpretation	of	the	Ordinance	because	it	would	increase	the	burden	for	co-

location applicants, produce the illogical result of decreasing the number of

sites available to co-location applicants, and ultimately result in the

construction	of	more	new	towers.5 See	Desfosses	v.	City	of	Saco,	2015	ME	151,

5 The Superior Court affirmed the Planning Board’s decision by concluding that

article	II(Z)(4)(a)(3) applies only “when there has been a Planning Board determination that
‘telecommunications	equipment	.	.	.	cannot	be	accommodated	on	an	existing	or	approved	tower	or
Alternative	Tower	Structure’”	and	because	the	2001	denial	of	Sprint’s	application	expressly	found
13

¶	16, 128 A.3d 648 (“[W]e must interpret [the Ordinance] to avoid absurd,

illogical, unreasonable, inconsistent, or anomalous results if an alternative

interpretation	avoids	such	results.”	(quotation	marks	omitted)).

[¶19] The	Planning	Board	did	not	err	in	declining	to	require	Verizon	to

rebut	a	presumption	of	unsuitability.

B. Investigation	of	Other	Technically	Feasible	Sites

[¶20] Olson and	Rabin	next	assert	that	we	should vacate	the	Planning

Board’s	decision	or	remand	for	further	fact-finding	because	the	Board	did	not

receive substantial evidence that Verizon investigated other “technically

feasible	sites,”	as	required	by	article	II(Z)(9)(c)	of	the	zoning	ordinance.

[¶21] The	Board	did	not	make	specific	findings	on	Verizon’s	compliance

with	particular	aspects	of	the	zoning	and	site	plan	ordinances	and	made	only

the	following	finding:	“On	the	basis	of	the	application,	plans,	reports	and	other

information	submitted	by	the	applicant,	information	from	the	public	hearing,

information	and	the	findings	and	recommendations	contained	in	[the]	Planning

that	the	water	tower	itself	was	an	appropriate	structure	and	the	denial	was	because	of	the	equipment
on	the	ground,	the	rebuttable	presumption	did	not	apply. We	agree	with	Olson	and	Rabin	that	this
interpretation	was	incorrect	because	the	term	“telecommunications	equipment”	encompasses	not
only the antennae on the water	tower, but also the equipment on the ground. However, it is the
decision	of	the	Planning	Board	that	we	review,	not	the	decision	of	the	Superior	Court. See	Osprey
Family	Tr.,	2016	ME	89,	¶	9,	141	A.3d	1114.
14

Board	Report	dated	September	23,	2016	.	.	.	the	Planning	Board	finds	that	the

plan	is	in	conformance	with	Chapter	702,	Site	Plan	Review	Ordinance	.	.	.	.”

[¶22] Planning Board findings must be supported by substantial

evidence	in	the	record. See	Osprey	Family	Tr.,	2016	ME	89,	¶	9,	141	A.3d	1114.

The Planning Board had substantial evidence that Verizon had investigated

other technically feasible sites and concluded that none was available.

Although	Verizon’s	written	submissions	to	the	Planning	Board	did	not	contain

information	about	alternative	sites	that	it	had	considered,	Verizon’s	application

included	detailed	information	about	its	site	selection	process,	and,	during	the

May and September meetings, the Planning Board asked the Verizon

representative about alternative sites that Verizon had considered. At the

September	28	Planning	Board	meeting,	a	Verizon	representative	explained	that

its site selection process consisted of looking for gaps in coverage and

identifying sites that would fill those gaps and have a minimal effect on the

Town. Verizon’s representative reported that the only feasible site for

co-location	was	the	Yarmouth	Water	District	site	because	other	sites	were	not

tall enough or would not fill the coverage gap. The Director’s report to the

Planning	Board	referred	to	the	requirement	of	article	II(Z)(9)(c)	and	Verizon’s

description	of	its	site	selection	process,	and	noted	that	“[t]his	site	allow[s]	the
15

antenna	to	be	located	on	an	existing	water	tower[,]	which	avoids	the	need	to

construct	a	new	tower.”

[¶23] Because	the	Planning	Board’s	finding	was	supported	by	substantial

evidence,	we	will	not	disturb	the	Board’s	conclusion	that	the	application	met

ordinance	standards. See	Bizier,	2011	ME	116,	¶¶	8,	12,	32	A.3d	1048	(“[W]e

accord substantial deference to the Planning Board’s characterizations and

fact-findings as to what meets ordinance standards.”) (quotation marks

omitted)).

The	entry	is:

Judgment	affirmed.

Nathaniel	A.	Bessey,	Esq.	(orally),	Brann	&	Isaacson,	Lewiston,	for	appellants
Frederick	Olson	and	Leora	Rabin

Philip	R.	Saucier,	Esq.	(orally),	Bernstein	Shur,	Portland,	for	appellee	Town	of
Yarmouth

Scott D. Anderson, Esq. (orally), Verrill Dana, LLP, Portland, for appellee
Verizon	Wireless

Cumberland	County	Superior	Court	docket	number	AP-2016-48
FOR	CLERK	REFERENCE	ONLY

---

Source: Frix Law Library, https://www.frixlaw.com/law-library/cases/4247279. Public record. Not legal advice.
