# J.P. Wescott v. Delaware County IU

> Commonwealth Court of Pennsylvania · November 28, 2017

URL: https://www.frixlaw.com/law-library/cases/4224416

## Case

- **Court:** Commonwealth Court of Pennsylvania
- **Decided:** November 28, 2017
- **Precedential status:** Unpublished
- **Opinion:** Opinion
- **Judges:** McCullough, J.
- **Cited by:** 0 later opinions in the Frix Law Library

## Citator (automated)

- No negative treatment found by the automated citator. That is not the same as a confirmation that the case is good law; read the citing cases.
- Full citator and citing cases: https://www.frixlaw.com/law-library/cases/4224416

## Opinion text

IN THE COMMONWEALTH COURT OF PENNSYLVANIA

James P. Wescott, :
Appellant :
: No. 781 C.D. 2017
v. :
: Argued: October 19, 2017
Delaware County Intermediate Unit :

BEFORE: HONORABLE PATRICIA A. McCULLOUGH, Judge
HONORABLE ANNE E. COVEY, Judge
HONORABLE J. WESLEY OLER, JR., Senior Judge

OPINION NOT REPORTED

MEMORANDUM OPINION
BY JUDGE McCULLOUGH FILED: November 28, 2017

James P. Wescott appeals from the June 5, 2017 order of the Court of
Common Pleas of Delaware County (trial court) denying his petition for preliminary
injunction.

Facts and Procedural History
Wescott is an electrical contractor and a resident of Delaware County and
the applicable school district. On May 23, 2017, Wescott filed a complaint in equity
and petition for injunctive relief with the trial court. Wescott sought to enjoin the
Delaware County Intermediate Unit (IU) from awarding public construction work at
the IU’s Aston Campus based on the IU’s failure to conduct an appropriate bidding
process, i.e., failing to solicit separate bids for plumbing, HVAC, and electrical work.
The work included the construction of two new additions that would be connected to
an existing structure, the removal of a boiler system in that structure, and a new
centralized HVAC system that would serve all three connected structures. The
approximate cost of the project was $38,000,000.00. Wescott alleged that separate bids
were required under section 1 of what is commonly referred to as the Separations Act,1
which provides, in pertinent part, as follows:

Hereafter in the preparation of specifications for the erection,
construction, and alteration of any public building, when the
entire cost of such work shall exceed four thousand dollars,
it shall be the duty of the architect, engineer, or other person
preparing such specifications, to prepare separate
specifications for the plumbing, heating, ventilating, and
electrical work; and it shall be the duty of the person or
persons authorized to enter into contracts for the erection,
construction, or alteration of such public buildings to receive
separate bids upon each of the said branches of work, and to
award the contract for the same to the lowest responsible
bidder for each of said branches.

71 P.S. §1618.
Wescott noted a similar provision at section 751(a.2) of the Public School
Code (Code) of 1949,2 which provides, in pertinent part, as follows:

All construction, reconstruction, repairs, maintenance or
work of any nature, including the introduction of plumbing,
heating and ventilating, or lighting systems, upon any school
building or upon any school property, or upon any building
or portion of a building leased under the provisions of section
703.1, made by any school district where the entire cost,
value or amount of such construction, reconstruction, repairs,
maintenance or work, including labor and material, shall
exceed a base amount of eighteen thousand five hundred

1
Act of May 1, 1913, P.L. 155, as amended, 71 P.S. §1618.

2
Act of March 10, 1949, P.L. 30, as amended, 24 P.S. §7-751(a.2).

2
dollars ($18,500), subject to adjustment under section 120,
shall be done under separate contracts to be entered into by
such school district with the lowest responsible bidder, upon
proper terms, after due public notice has been given asking
for competitive bids.

24 P.S. §7-751(a.2).
Wescott asserted that the IU was attempting to avoid the requirements of
the Separations Act and section 751(a.2) of the Code by awarding a single public
construction contract for new public works by use of the process allowed under the
Guaranteed Energy Savings Act (GESA), 62 Pa.C.S. §§3751-3758. The IU filed an
answer to Wescott’s complaint and petition, asserting that its actions were justified
under GESA.

Trial Court Order and Subsequent Opinion
By order dated June 5, 2017, the trial court denied Wescott’s petition for
injunctive relief, concluding that Wescott did not have a clear right to relief. Because
Wescott did not request a hearing with respect to his petition and the trial court
considered the only issue to be resolved to be a purely legal question which did not
require a hearing, the trial court based its order on the pleadings filed by the parties. In
its order, the trial court explained that section 3752 of GESA, 62 Pa.C.S. §3752, which
it found controlled the matter, defines the term “[e]nergy conservation measure”
(hereafter, ECM) as:

A program, facility alteration or technology upgrade
designed to reduce energy, water, wastewater or other
consumption or operating costs. The term may include,
without limitation:
...

3
(4) [h]eating, ventilating or air conditioning system
modifications, extension of systems to new or renovated
areas or system replacements.
(Trial court order at 2) (emphasis in original). Additionally, the trial court noted that
this definition also includes “[w]ater and sewer conservation measures, including,
without limitation, plumbing fixtures and infrastructure.” Id. The trial court described
the project as including a centralized HVAC system for all three structures “put in
space created by first demolishing a boiler system in an existing structure and replaced
with a centralized system centered in the existing structure which will then be
extended” to the new structures via “a labyrinth of pipes, coils, electrical wiring and
all the other attendant equipment and electrical supplies and hook-ups necessary for
the unified system.” Id. at 2-3. The trial court concluded that such a project fit squarely
within the provisions of GESA. Wescott did not request reconsideration of this order,
but instead filed a notice of appeal with the trial court.
In a subsequent opinion in support of its order, the trial court, relying on
the Statutory Construction Act of 1972, 1 Pa.C.S. §§1501-1991, concluded that GESA
was the controlling statute and acted as an exception to the requirements of the
Separations Act. In this regard, the trial court noted that GESA was enacted after the
Separations Act and described GESA’s provisions as more specific than the general
provisions of the Separations Act. The trial court reiterated that the current project
qualifies as an ECM under subsection (4) of its definition as set forth in section 3752
of GESA. Thus, the trial court held that “the activity which [Wescott] sought to restrain
was not actionable and his right to relief was not clear thereby leading to the conclusion
that he was not likely to prevail on the merits,” a necessary element for preliminary
injunctive relief. (Trial court op. at 5-6.)

4
Discussion
Wescott thereafter filed a notice of appeal to this Court.3 On appeal,4
Wescott argues that the trial court erred in denying his request for a preliminary
injunction. More specifically, Wescott argues that the trial court erred in: failing to
require the IU to publicly bid and award the HVAC, electrical, and plumbing contracts
in accordance with the Separations Act; holding that the Separations Act was
superseded by GESA; and holding that the requirements for implementation of GESA
were met.5

Preliminary Injunction
In order to obtain a preliminary injunction, a petitioner must establish: (1)
relief is necessary to prevent immediate and irreparable harm that cannot be adequately
compensated by money damages; (2) greater injury will occur from refusing to grant
the injunction than from granting it; (3) the injunction will restore the parties to their
status quo as it existed before the alleged wrongful conduct; (4) the petitioner is likely

3
Shortly after filing his notice of appeal, Wescott filed an application for injunctive relief
pending our review under Pa.R.A.P. 1732. However, by single-Judge memorandum opinion and
order dated August 1, 2017, this author denied said application.

4
We note that on appeal from the grant or denial of a preliminary injunction, a reviewing
court does not inquire into the merits of the controversy, but only examines the record to determine
if there were any apparent reasonable grounds for the action of the court below. Roberts v. Board of
Directors of the School District of Scranton, 341 A.2d 475, 478 (Pa. 1975). Only if it is apparent that
no grounds exist to support the decree, or that the rule of law relied upon was palpably erroneous or
misapplied, will the court interfere with the decision of the common pleas court sitting in equity. Id.

5
Contrary to Wescott’s argument, the trial court never held that the Separations Act was
superseded by GESA. Rather, the trial court noted that the Separations Act was applicable to the IU
and that GESA acted merely as an exception to that Act.

5
to prevail on the merits; (5) the injunction is reasonably suited to abate the offending
activity; and, (6) the public interest will not be harmed if the injunction is granted.
Berwick Township v. O’Brien, 148 A.3d 872, 890 (Pa. Cmwlth. 2016), appeal denied,
___ A.3d ___ (Pa., No. 923 MAL 2016, filed May 17, 2017). To establish a likelihood
of prevailing on the merits, a petitioner must show that the activity which he seeks to
restrain is actionable and that his right to relief is clear. Firearm Owners Against Crime
v. Lower Merion Township, 151 A.3d 1172, 1175 (Pa. Cmwlth. 2016).

Public Bidding of HVAC, Electrical, and Plumbing Contracts
Wescott first argues that the trial court erred in failing to require the IU to
separately and publicly bid the HVAC, electrical, and plumbing contracts in
accordance with the Separations Act.
The parties agree that the provisions of the Separations Act, and similar
provisions later incorporated into the Code, generally apply to the IU. See Trial court
op. at 2. These provisions clearly require separate specifications/bids for plumbing,
heating, ventilating, and electrical work in relation to a school building or school
property and mandate awards of contracts for such services to the lowest responsible
bidder. However, a question remains as to whether GESA acts as an exception to these
bidding requirements, as the trial court found. Section 3753 of GESA addresses
contracting procedures under GESA, and provides, in pertinent part, as follows:

(a) General rule. — Notwithstanding any other contrary or
inconsistent provision of law, a governmental unit may enter
into a guaranteed energy savings contract with a qualified
provider in accordance with the provisions of this subchapter
or in accordance with another statutorily authorized
procurement process.

6
(b) Guaranteed energy savings contract. — If in
accordance with applicable law the award of a contract by a
governmental unit requires action at a public meeting, a
governmental unit may award a guaranteed energy savings
contract at a public meeting if it has provided public notice
in the manner prescribed under 65 Pa.C.S. Ch. 7 (relating to
open meetings), the notice including the names of the parties
to the contract and the purpose of the contract. For
governmental units that are not required to take actions on
contracts at public meetings, the governmental unit may
award a guaranteed energy savings contract in accordance
with the procedures adopted by the governmental unit and
the requirements of all applicable laws.

(c) Competitive sealed proposals. — For the purpose of
entering into a guaranteed energy savings contract, all
governmental units are authorized to utilize the competitive
sealed proposal method of procurement. The governmental
unit shall evaluate any proposal that meets the requirements
of the governmental unit and is timely submitted by a
qualified provider. The request for proposals shall be
announced through a public notice from the governmental
unit which will administer the program. The request for
proposals shall provide all interested parties with sufficient
information necessary to submit a timely and responsive
proposal.

(d) Selection and notice. — The governmental unit shall
select the qualified provider that best meets the needs of the
governmental unit in accordance with criteria established by
the governmental unit. . . After reviewing the proposals . . .
a governmental unit may enter into a guaranteed energy
savings contract with a qualified provider if it finds that the
amount it would spend on the energy conservation measures
recommended in the proposal would not exceed the amount
of energy, water or wastewater cost savings, operational cost
savings or revenue increases resulting from the energy
conservation measures within a period not to exceed 20 years
from the date of final installation. . . .

7
62 Pa.C.S. §3753(a)-(d).6
Generally, if two statutes are in dispute, we turn to the Pennsylvania rules
of statutory construction to resolve the dispute. In such cases, section 1933 of the
Statutory Construction Act of 1972 states that:

Whenever a general provision in a statute shall be in conflict
with a special provision in the same or another statute, the
two shall be construed, if possible, so that effect may be
given to both. If the conflict between the two provisions is
irreconcilable, the special provisions shall prevail and shall
be construed as an exception to the general provision, unless
the general provision shall be enacted later and it shall be the
manifest intention of the General Assembly that such general
provision shall prevail.
1 Pa.C.S. §1933; see also In re Downingtown, 161 A.3d 844, 871 (Pa. 2017) (when
two statutes are irreconcilable, the statute which is more specific prevails).
The trial court in this case concluded that the Separations Act and GESA
were in conflict, applied section 1933 of the Statutory Construction Act of 1972, and
held that the later enacted and more specific GESA provisions trump the general
provisions of the Separations Act. Because the project qualified as an ECM under
section 3752 of GESA, the trial court concluded that Wescott’s claim was not
actionable and his right to relief was not clear, and, therefore, Wescott was not likely

6
While these provisions of GESA are found in Title 62 of Purdon’s Consolidated Statutes,
generally known as the Commonwealth Procurement Code, Wescott notes that another statute of the
same name is found in Title 73 of Purdon’s, relating to Trade and Commerce. See Act of May 10,
1996, P.L. 153, 73 P.S. §§1646.1-1646.8. The provisions of both statutes are nearly identical, but
there is some variation in the definition sections of each statute. While Wescott argued before the
trial court that the latter provisions were applicable to the IU in the present case, he concedes in his
brief that the IU would fit within the definition of a “government unit” under section 3752 of GESA,
62 Pa.C.S. §3752. Indeed, the trial court found the Commonwealth Procurement Code provisions of
GESA to be applicable to the IU herein.

8
to succeed on the merits. As a result, the trial court concluded that Wescott could not
meet all of the elements necessary for preliminary injunctive relief.
However, contrary to the trial court, we are not persuaded that the
Separations Act and GESA are in conflict. Instead, we believe that a compelling
argument can be made that these statutes can function together such that effect could
be given to both, thereby obviating the need for any statutory construction analysis.
The Separations Act generally requires separate bidding and award of contracts to the
lowest responsible bidder for any construction or alteration of a public building that
exceeds $4,000.00. GESA’s application is very narrow and limited to specific
situations involving energy, water, or wastewater projects which would result in a cost
savings that would effectively pay for the projects themselves. The fact that a project
may include an element of energy, water, or wastewater savings does not make the
entire project subject to GESA. Indeed, in this case, the IU could have bid out the
construction of the additions separately in accordance with the Separations Act and
limited the GESA project to demolition of the existing boiler system and replacement
with a centralized HVAC system.
Nevertheless, while we disagree with the trial court’s conclusions in this
regard, we are constrained to affirm the trial court’s denial of the preliminary injunction
on other grounds, i.e., Wescott failed to establish that greater injury will occur from
refusing to grant the injunction and that the public interest will not be harmed if an
injunction were to be granted. Our Supreme Court has stressed that “For a preliminary
injunction to issue, every one of these prerequisites must be established; if the
petitioner fails to establish any one of them, there is no need to address the others,”
County of Allegheny v. Commonwealth, 544 A.2d 1305, 1307 (Pa. 1988), and that the
“burden is on the party who requested preliminary injunctive relief,” Warehime v.

9
Warehime, 860 A.2d 41, 47 (Pa. 2004). Here, Wescott failed to meet at least two of
the required elements.
More specifically, the project here involves the upfront expenditure of a
significant amount of public funds, with an estimated cost of $38,000,000. The grant
of an injunction will result in significant delays in the completion of the project, which,
in turn, will undoubtedly result in increased costs to the IU, including, inter alia, costs
for new specifications for bids, mobilization costs, and material costs. Moreover, any
delay in the completion of the project would require the IU to sustain additional and
substantial facility costs to house and teach its students. Indeed, during previous
argument with respect to Wescott’s application for injunctive relief pending our
review, the IU noted that it currently leases outside facilities, that said leases are set to
expire as of July 1, 2018, the project’s expected completion date, and that it would cost
approximately $2 million to extend these leases for an additional year. Wescott did
not dispute these costs.
Accordingly, the trial court’s order is affirmed, on the other grounds set
forth above.7

________________________________
PATRICIA A. McCULLOUGH, Judge

7
Based upon our determination above, we need not reach Wescott’s remaining argument that
the project did not meet the requirements for implementation under GESA.

10
IN THE COMMONWEALTH COURT OF PENNSYLVANIA

James P. Wescott, :
Appellant :
: No. 781 C.D. 2017
v. :
:
Delaware County Intermediate Unit :

ORDER

AND NOW, this 28th day of November, 2017, the order of the Court of
Common Pleas of Delaware County, dated June 5, 2017, is hereby affirmed, albeit on
the other grounds discussed in the opinion.

________________________________
PATRICIA A. McCULLOUGH, Judge

---

Source: Frix Law Library, https://www.frixlaw.com/law-library/cases/4224416. Public record. Not legal advice.
