# Entergy Texas, Inc. v. Public Utility Commission of Texas, Office of Public Utility Counsel, and State of Texas Agencies and Institutions of Higher Education

> Texas Court of Appeals, 3rd District (Austin) · March 6, 2015

URL: https://www.frixlaw.com/law-library/cases/4052560

## Case

- **Court:** Texas Court of Appeals, 3rd District (Austin)
- **Decided:** March 6, 2015
- **Precedential status:** Published
- **Opinion:** Opinion
- **Cited by:** 0 later opinions in the Frix Law Library

## Citator (automated)

- No negative treatment found by the automated citator. That is not the same as a confirmation that the case is good law; read the citing cases.
- Full citator and citing cases: https://www.frixlaw.com/law-library/cases/4052560

## Opinion text

ACCEPTED
03-14-00706-CV
4407712
THIRD COURT OF APPEALS
AUSTIN, TEXAS
3/6/2015 4:11:28 PM
JEFFREY D. KYLE
CLERK

NO. 03-14-00706-CV FILED IN
3rd COURT OF APPEALS
AUSTIN, TEXAS
3/6/2015 4:11:28 PM
JEFFREY D. KYLE
ENTERGY TEXAS, INC., Clerk
Appellant,

v.

PUBLIC UTILITY COMMISSION OF TEXAS, ET AL.,
Appellees.

B RIEF OF A PPELLEE

Filed by: Public Utility Commission of Texas

KEN PAXTON ELIZABETH R. B. STERLING
Attorney General of Texas Assistant Attorney General
State Bar No. 19171100
CHARLES E. ROY Elizabeth.Sterling@texasattorneyg
First Assistant Attorney General eneral.gov

JAMES E. DAVIS MEGAN M. NEAL
Deputy Attorney General for Assistant Attorney General
Civil Litigation State Bar No. 24043797

JON NIERMANN Environmental Protection
Chief, Environmental Protection Division
Division P.O. Box 12548, MC-066
Austin, Texas 78711-2548
512.463.2012
512.457.4616 (fax)

March 6, 2015

Oral Argument Requested
Identity of Parties and Counsel

Party Counsel
Entergy Texas, Inc., Plaintiff in the Marnie A. McCormick
district court, Appellant and John F. Williams
Appellee before this Court Duggins Wren Mann & Romero,
LLP
P. O. Box 1149
Austin, Texas 78767-1149
512.744.9300
512.744.9399 (fax)
mmccormick@dwmrlaw.com
jwilliams@dwmrlaw.com
(in district court, also Patrick J.
Pearsall)

Public Utility Commission of Texas, Ken Paxton
Defendant in the district court, Attorney General of Texas
Appellee before this Court (in district court, Greg Abbott)

Charles E. Roy
First Assistant Attorney General
(in district court, Daniel Hodge)

James E. Davis
Deputy Attorney General for Civil
Litigation
(in district court, John B. Scott)

Jon Niermann
Chief, Environmental Protection
Division

i
Assistant Attorneys General:
Elizabeth R. B. Sterling
Elizabeth.Sterling@texasattorneyge
neral.gov
Megan Neal
Megan.Neal@texasattorneygeneral.
gov
Environmental Protection Division
Office of the Attorney General
P.O. Box 12548, MC-066
Austin, Texas 78711-2548
512.463.2012
512.457.4616 (fax)
Office of Public Utility Counsel, Ross Wyatt Henderson
Intervenor in the district court and Assistant Public Counsel
Appellee before this Court Office of Public Utility Counsel
P.O. Box 12397
1701 N. Congress Avenue, Ste 9-180
Austin, Texas 78711-2397
512.936.7500
512.936.7520 (fax)
Ross.Henderson@opuc.texas.gov
(in district court, Sara J. Ferris)

ii
State Agencies, Intervenors in the Katherine H. Farrell
district court and Appellees before Assistant Attorney General
this Court Administrative Law Division
Energy Rates Section
Office of the Attorney General

P.O. Box 12548 MC 018-12
Austin, Texas 78711-2548
512.475.4237
512.320.0167 (fax)
katherine.farrell@texasattorneygen
eral.gov
(in district court, Susan M. Kelley
and Bryan L. Baker)
Texas Industrial Energy Rex VanMiddlesworth
Consumers, Intervenors in the Benjamin Hallmark
district court and Interested Parties Thompson & Knight LLP
before this Court 98 San Jacinto Blvd., Ste. 1900
Austin, Texas 78701
512.469.6100
512.469.6180 (fax)
rex.vanm@tklaw.com
benjamin.hallmark@tklaw.com
(in district court, Meghan Griffiths
at Andrews Kurth, LLP)

iii
Table of Contents

Identity of Parties and Counsel. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . i

Table of Contents. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . iv

Index of Authorities. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . viii

Glossary.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . xi

Statement of the Case. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . xii

Statement Regarding Oral Argument. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . xii

Issues Presented.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . xii

Statement of Facts. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1

A. The Commission decided Entergy’s rate case, Docket 39896.. . . . . . . 1

B. The Commission addressed the question of Entergy’s rate-case
expenses in this case. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8

1. The ALJ considered ratepayers’ arguments against some of
Entergy’s requested rate-case expenses. . . . . . . . . . . . . . . . . . . . . . 8

a. Depreciation expenses of Entergy’s affiliated company. . . . . . 9

b. Rate-case expenses to advocate for abandoning the two-
bucket policy for including incentive compensation in rates.
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10

c. Excessive rate-case expenses. . . . . . . . . . . . . . . . . . . . . . . . . . . . 13

d. Adjustments to rate-case expenses. . . . . . . . . . . . . . . . . . . . . . . 15

2. The Commission issued its Order in this case. . . . . . . . . . . . . . . . . 18

C. Entergy appealed. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20

iv
Summary of the Argument. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20

Argument. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22

I. Standard of Review. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22

A. Substantial-evidence Standard. . . . . . . . . . . . . . . . . . . . . . . . . . . . 22

B. Arbitrary-and-capricious Standard . . . . . . . . . . . . . . . . . . . . . . . . 23

II. The Commission has discretion to decide that expenses Entergy
incurred making a long-shot argument for overturning a well-
established Commission policy were unreasonable expenses for
ratepayers to reimburse. (Responds to Entergy Issue 1). . . . . . . 24

A. The Commission may allow the utility to recover only
reasonable expenses. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24

B. The Commission applied the law to the evidence and
determined that it was unreasonable for Entergy to recover
rate-case expenses incurred to argue that the Commission
should abandon its two-bucket policy concerning incentive
compensation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26

III. The lack of a Commission rule about rate-case expenses for
incentive-compensation arguments did not relieve the
Commission of its statutory duty to allow the utility to recover
only reasonable rate-case expenses. (Responds to Entergy
Issue 2) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33

A. Entergy’s arguments that the Commission departed from
earlier policy in this case are unavailing . . . . . . . . . . . . . . . . . . . . 33

B. The Commission was merely applying the statutes to the
evidence and argument in this case, not promulgating a new
rule. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34

C. Entergy’s arguments that the Commission engaged in ad hoc
rulemaking are unavailing. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35

v
1. This case is distinguishable from Witcher . . . . . . . . . . . . . . . . 35

2. Entergy improperly relies on the irrelevant thought
processes of individual commissioners in the course of the
case . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 36

3. A rule was adopted when the Commission subsequently
conducted formal rulemaking proceedings . . . . . . . . . . . . . . . 38

IV. The Commission’s decision about the amount of rate-case
expenses to exclude should be affirmed. (Responds to Entergy
Issue 3) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39

A. Entergy—the party with the burden to prove rate-case
expenses—failed to provide the information needed to show
exactly how much of its rate-case expenses were incurred to
make the unreasonable long-shot argument. . . . . . . . . . . . . . . . . 39

B. Substantial evidence supports the Commission’s decision about
the amount of rate-case expenses attributable to the
unreasonable argument in the rate case . . . . . . . . . . . . . . . . . . . . 43

C. The Commission’s decision is reasonable—neither arbitrary and
capricious nor an abuse of discretion .. . . . . . . . . . . . . . . . . . . . . . 44

V. Entergy failed to meet its burden under Utilities Code § 36.058 to
prove depreciation charged by its affiliate for rate-case expenses
was reasonable and necessary and no higher than the costs
charged to other affiliates. (Responds to Entergy Issue 4). . . . . . . . 47

A. The Utilities Code imposes additional requirements to show
that amounts paid to affiliates are reasonable expenses . . . . . . . 47

B. Entergy’s evidence is insufficient to meet its burden of proof. . . 48

1. Entergy failed to explain what depreciation expenses of
Service Company were included . . . . . . . . . . . . . . . . . . . . . . . . 49

vi
2. Entergy failed to provide evidence that including Service
Company’s depreciation expense made the expenses
comparable. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52

Prayer. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 53

Certificate of Compliance. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55

Certificate of Service. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 56

APPENDICES

Order. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A

Proposal for Decision.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . B

Chart of PUC Dockets Addressing the Two-Bucket Incentive
Compensation Policy Statutes. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . C

Statutes and Rules. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . D

Certified Copy of ETI Ex. 41 from Docket 398961. . . . . . . . . . . . . . . . . . . . E

1
ETI Exhibit 41 from Docket 39896 includes an appendix of supporting
information on a CD. That CD is too voluminous to be filed electronically. Therefore,
the Commission has copied only those parts of the CD that it has cited, changed them to
PFD format, and attached them to the body of Exhibit 41. The Commission stands ready
to provide the Court or any other party a copy of the entire CD on request.

vii
Index of Authorities

Cases Pages

Anderson v. R.R. Comm’n,
963 S.W.2d 217 (Tex. App.—Austin 1998, pet. denied). . . . . . . . . . . . 22

Cent. Power and Light Co. v. Pub. Util. Comm’n,
36 S.W.3d 547 (Tex. App.—Austin 2000, pet. denied). . . . . . . . . . . . . 48

Cities of Abilene v. Pub. Util. Comm’n,
146 S.W.3d 742 (Tex. App.—Austin 2004, no pet.).. . . . . . . . . . . . . . . 23

City of El Paso v. Pub. Util. Comm’n,
883 S.W.2d 179 (Tex. 1994). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23

City of El Paso v. Pub. Util. Comm’n,
916 S.W.2d 515 (Tex. App.—Austin 1995, writ dism’d).. . . . . . . . . . . . . 16

City of Frisco v. Tex. Water Rights Comm’n,
579 S.W.2d 66 (Tex. Civ. App.—Austin 1979, writ ref’d n.r.e.). . . 29, 37

Indust. Utils. Serv., Inc. v. Tex. Natural Res. Conservation Comm’n,
947 S.W.2d 712 (Tex. App.—Austin 1997, writ denied).. . . . . . . . . . . . 35

McHaney v. Tex. Comm’n on Envtl. Quality,
No. 03-13-00280-CV, 2015 WL 869197 (Tex. App.—Austin February 27,
2015, no pet. h.).. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38

Oncor Elec. Delivery Co. LLC v. Pub. Util. Comm’n,
406 S.W.3d 253 (Tex. App.—Austin 2013, no pet.).. . . . . . . . . . . . . . . 24

Pedernales Elec. Coop., Inc. v. Pub. Util. Comm’n,
809 S.W.2d 332 (Tex. App.—Austin 1991, no writ).. . . . . . . . . . . . . . . . 37

Pub. Util. Comm’n v. Gulf States Utils. Co.,
809 S.W.2d 201 (Tex. 1991). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22

viii
Index of Authorities (Cont’d)

Cases (Cont’d) Pages

State of Tex. Agencies and Insts. Of Higher Learning v. Pub. Util. Comm’n,
450 S.W.3d 615 (Tex. App.—Austin 2014, pet. filed). . . . . . . . . . . 31, 32

Tex. Health Facilities Comm’n v. Charter Med.-Dallas, Inc.,
665 S.W.2d 446 (Tex. 1984).. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23

Tex. State Bd. Of Pharmacy v. Witcher,
447 S.W.3d 520 Tex. App.—Austin 2014, pet. filed). . . . . . . . . . . . . . . 35

Statutes

Tex. Gov’t Code
§ 2001.174. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
§ 2001.175(e). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37

Tex. Util. Code
§ 15.001. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
§ 31.001. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
§ 33.023(b). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
§ 36.002. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
§ 36.051. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
§ 36.058. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21, 47, 48, 49, 53
§ 36.058(c)(2). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52
§ 36.061(b)(2). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3, 24
§ 36.062. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 36
§ 36.062(4). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
§ 39.451. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
§ 39.452(a).. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1

Rules

16 Tex. Admin. Code
§ 25.231(a). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2

ix
Index of Authorities (Cont’d)

Rules (Cont’d) Pages

§ 25.231(b)(2)(J). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 36
§ 25.245(b)(6). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 47

Other

39 Tex. Reg. 571 (2014), adopted 39 Tex. Reg. 6434 (2014)
(to be codified at 16 Tex. Admin. Code § 25.245). . . . . . . . . . . . . . . . . 38

x
Glossary

ALJ Administrative Law Judge

APA Administrative Procedure Act. Tex. Gov’t Code
§§ 2001.001–.902

Commission or PUC Public Utility Commission of Texas

Docket 39896 Application of Entergy Texas for Authority to Change
Rates, Reconcile Fuel Costs, and Obtain Deferred
Accounting Treatment, P.U.C. Docket 39896, the rate
case that generated the rate-case expenses that
Entergy sought to recover in this case

Entergy Entergy Texas, Inc., the utility that asked the
Commission for rate-case expenses in this case

ERCOT Electric Reliability Council of Texas

OPUC Office of Public Utility Counsel, intervenor at the
Commission, intervenor-defendant at district court,
appellee in this Court

Order The Commission’s order on rehearing that is the
subject of this lawsuit

PFD Proposal for Decision prepared by the ALJ in this case

Service Company Entergy Services, Inc., an affiliate of Entergy that
services the entire family of related companies

State Agencies State Agencies of Texas that are customers of Entergy,
an intervenor at the Commission, intervenor-
defendant in the district court, and appellee before
this Court

TIEC Texas Industrial Electric Consumers, intervenor at the
Commission

xi
Statement of the Case

Entergy challenges the district court’s judgment in an administrative

appeal that affirmed the Public Utility Commission’s order. The

Commission set the rate-case expenses that Entergy is entitled to recover

from ratepayers for reasonable expenses incurred in a prior rate case.

Statement Regarding Oral Argument

Oral argument would be helpful to allow the Court to ask any questions

it may have about the ratemaking or rate-case-expense cases.

Issues Presented

1. Did the Commission have discretion to decide that expenses Entergy
incurred to make an argument in the rate case that it had almost no
chance to win were unreasonable expenses for ratepayers to reimburse?

2. Does the Commission’s statutory duty “not to consider for ratemaking
purposes … any other expenditure … the regulatory authority finds to be
unreasonable, unnecessary, or not in the public interest” authorize it to
exclude Entergy’s unreasonable expenses even though the Commission
had no rule about Entergy making this particular argument?

3. The administrative record shows that, in addition to obtaining expert
testimony to support the unreasonable argument, Entergy included the
argument in its rate-filing package, responded to discovery about the
argument, and filed briefs about the argument. Entergy knew what it
paid expert witnesses but did not track work by its staff and outside
attorneys on an issue-by-issue basis. Was the Commission reasonable to
decide that some of Entergy’s expenses for staff and outside attorneys
were for making the unreasonable argument? Was the Commission
reasonable to estimate the amount of Entergy’s total unreasonable
expenses using a method supported by testimony in the record?

xii
4. Did the Commission reasonably find that Entergy failed to meet its
burden to show that depreciation expenses for unspecified capital assets
of its affiliated Service Company should be included in recoverable rate-
case expenses?

xiii
Statement of Facts

Entergy Texas, Inc. (Entergy) appeals an order of the Public Utility

Commission of Texas (Commission) setting the amount that the utility may

recover from ratepayers for expenses that Entergy incurred in connection

with its rate case, P.U.C. Docket 39896.

A. The Commission decided Entergy’s rate case, Docket
39896.

Entergy initiated a rate case at the Commission. Entergy, an electric

utility that provides service to parts of southeast Texas, is situated outside

the Electric Reliability Council of Texas (ERCOT) and remains a fully

integrated utility—it generates electricity, transmits and distributes

electricity, and sells electricity to retail customers in its service area. That

business remains fully regulated by the Commission, which sets the rates

Entergy can charge.2 So, in 2011 Entergy filed a rate case with the

2
As Entergy explained in its brief, it was initially included among utilities that
were to transition to competition, but is currently subject to regulation under Chapter
36 of the Utilities Code. See Tex. Util. Code §§ 39.451, .452(a). Thus, Entergy’s rates
remain regulated by the Commission. See Tex. Util. Code § 36.002.

1
Commission, Docket 39896.3 Entergy asked to increase rates by over $100

million; the Commission’s order in Docket 39896 allowed the utility to

increase rates by approximately $27.7 million.4

The basic statutory formula the Commission uses to set rates is

(rate of return × invested capital) + reasonable and necessary expenses =

revenue requirement.5

The Commission then designs rates to give the utility a reasonable

opportunity to recover its revenue requirement.6 Although the utility’s

reasonable and necessary expenses included in rates are based on the

utility’s actual expenses over a twelve-month period called the “test year,”7

3
Tex. Pub. Util. Comm’n, Application of Entergy Texas, Inc. for Authority to
Change Rates, Reconcile Fuel Costs, and Obtain Deferred Accounting Treatment,
Docket 39896, (November 28, 2011)(Entergy’s Application of Entergy Texas, Inc. for
Authority to Change Rates, Reconcile Fuel Costs Application of Entergy Texas, Inc. for
Authority to Change Rates, Reconcile Fuel Costs) available at
http://interchange.puc.texas.gov/WebApp/Interchange/application/dbapps/filings/pg
Search_Results.asp?TXT_CNTR_NO=39896&TXT_ITEM_NO=2. (Subsequent
citations to this docket will be listed as “Docket 39896.”)
4
AR Item 32 at 3. Item 32 is the proposal for decision, which will be cited as
“AR, PFD” hereinafter. The administrative record (AR) in this case (Docket 40295) was
admitted into evidence as Joint Exhibits 1 and 2. R.R. at 6:11–6:20. It consists of two
volumes of filings, which are referenced as “item”; one volume of exhibits; and one
transcript that are all contained in one box. Citations to the Administrative Record will
be in the form “AR, Item(s) ___,” for filings, “AR, ___ Ex(s). ___,” for exhibits, and
“AR, Tr. at ___” for transcripts. In the Order, findings of fact will be cited as “FF__”
and conclusions of law will be cited as “CL __.”
5
See Tex. Util. Code § 36.051.
6
Id.
7
See 16 Tex. Admin. Code § 25.231(a).

2
which is used as a predictor of expense that will occur in the future, one

significant expense does not occur every year—the expense of bringing a

rate case. So that amount is usually separately calculated and recovered

from ratepayers through amortization so that the utility will stop recovering

once rate-case expenses are fully recovered. Utilities Code Section

36.061(b)(2) specifically authorizes the Commission to allow a utility to

recover rate-case expenses.8

Originally, Entergy’s request to recover rate-case expenses was part of

the Docket 39896 rate case but the Commission granted the parties’

request to sever it into a separate docket, P.U.C. Docket 40295, the

contested case on appeal in this lawsuit.9 The Commission did not

incorporate the entire record of Docket 39896 into the record of this case,

but, at the hearing on this case, the administrative law judge took official

notice of the Docket 39896 record.10

8
“(b) The regulatory authority may allow as a cost or expense … (2) reasonable
costs of participating in a proceeding under this title not to exceed the amount approved
by the regulatory authority.” Tex. Util. Code § 36.061(b)(2).
9
Docket 39896, (April 4, 2012) (SOAH Order No. 13: Granting Unopposed
Motion to Sever Rate Case Expense Issues) available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_591_7227
42.PDF.
10
AR, Tr. at 16.

3
One issue in the Docket 39896 rate case—whether incentive

compensation for financially based goals should be recovered through rates

as a reasonable and necessary expense—is relevant to the amount of rate-

case expenses awarded in this case. An amount for payroll costs is usually

included among the utility’s reasonable and necessary expenses. Although

some utilities had included incentive compensation for top executives

before, in AEP Texas Central Company’s rate case filed in 2003 (Docket

28840),11 for the first time, a utility asked to include incentive

compensation as part of the payroll costs for all its employees. Most of the

utility’s incentives in that case were paid according to two sets of

performance measures, financial and operational. In that case the

Commission found:

169. The financial measures are of more immediate benefit to
shareholders, and the operating measures are of more
immediate benefit to ratepayers.

11
Tex. Pub. Util. Comm’n, Application of AEP Texas Central Company for
Authority to Change Rates, Docket 28840 available at
http://interchange.puc.texas.gov/WebApp/Interchange/application/dbapps/filings/pg
Control.asp?TXT_UTILITY_TYPE=A&TXT_CNTRL_NO=28840&TXT_ITEM_MATC
H=1&TXT_ITEM_NO=&TXT_N_UTILITY=&TXT_N_FILE_PARTY=&TXT_DOC_TY
PE=ALL&TXT_D_FROM=&TXT_D_TO=&TXT_NEW=true (Subsequent citations to
this PUC Docket will be listed as “Docket 28840.”)

4
170. Incentives to achieve operational measures are necessary and
reasonable to provide T&D utility services, but those to achieve
financial measures are not.12

Thus, the Commission held that AEP proved that incentive compensation

should be included in rates only for operational measures.13 In its brief to

this Court, Entergy refers to this as two buckets of incentive

compensation.14

Evidently, using incentive compensation to pay all employees had

become fashionable, because the Commission was presented with similar

requests by other utilities in subsequent rate cases. The Commission

consistently maintained the distinction between operational-goal and

financial-goal buckets for incentive compensation. Incentive compensation

that belongs in the operational-goal bucket is recoverable, but incentive

compensation that belongs in the financial-goal bucket is not included as a

reasonable and necessary expense in rates because it is of more immediate

benefit to shareholders. Because different utilities can structure incentive

compensation differently, there is always a fact question about whether a

12
Docket 28840(August 15, 2005)(PUC’s Final Order) available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/28840_878_487
259.PDF.
13
Docket 28840 (August 15, 2005)(PUC’s Final Order) CL 45 available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/28840_878_487
260.PDF.
14
Entergy Appellant’s Br. at 14.

5
particular type incentive compensation goes in the operational-goal bucket

or the financial-goal bucket. But the basic policy that only incentive

compensation to meet operational goals can be included in rates remains.

In Docket 39896, Entergy asked the Commission to abandon the

distinction between buckets and allow not only the incentive compensation

in the operational-goal bucket, but also any incentive compensation in the

financial-goal bucket. Entergy’s rate-filing package included testimony by

two different witnesses supporting that argument.15 The issue was hotly

contested; Entergy responded to discovery concerning that argument, and

it filed five separate briefs at the Commission supporting that argument.16

15
See Entergy Appellant’s Br. at 29 (discussing testimony of Mr. Gardner and
Dr. Hartzell about the issue).
16
Docket 39896 (December 20, 2011)(TIEC’s RFIs to Entergy Texas, Inc.)
available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_46_71373
7.PDF; (January 3, 2012) (Cities’ 7th RFI)) available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_62_71465
2.PDF; (January 13, 2012)(Cities’ 10th RFI) available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_141_7155
98.PDF; (January 17, 2012)(Cities’ 12th RFI to Entergy Texas, Inc.) available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_150_7157
44.PDF; (February 1, 2012) (Cities’ 18th RFI to Entergy Texas, Inc.) available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_266_7170
69.PDF; (February 2, 2012) (Commission Staff's 10th RFI to Entergy Texas, Inc.
Question Nos. 10-1 Through 10-8) available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_280_7171
45.PDF; (February 9, 2012) (OPUC’s 10th RFI to Entergy Texas, Inc.) available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_322_7177
21.PDF; (February 21, 2012 (Texas Energy Consumers’ 9th RFI)available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_373_7187
54.PDF; (March 5, 2012)(Cities’ 23rd RFI)available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_415_7199

6
All the other parties opposed eliminating the distinction between the two

buckets.17

The Commission did not agree with Entergy’s argument to eliminate the

two buckets but did find that some of the types of incentive compensation

that other parties claimed were for financial goals really fit in the

operational-goal bucket. The Commission stated in Finding of Fact 129

that “[i]ncentive compensation that is based on financial measures is of

more immediate and predominant benefit to shareholders, whereas

incentive compensation based on operational measures is of more

immediate and predominant benefit to ratepayers.”18 In rate-case Docket

39896, the Commission did not allow Entergy to include $6,196,037 (as

42.PDF; (April 16, 2012) (State’s 11th RFI to Entergy Texas, Inc.) available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_655_723
481.PDF; Docket 39896, (May 18, 2012) (Entergy’s Initial Brief) available at
http://interchange.puc.state.tx.us/WebApp/Interchange/application/dbapps/filings/pg
Search_Results.asp?TXT_CNTR_NO=39896&TXT_ITEM_NO=719; (May 30,
2012)(Entergy’s Reply Brief) available at
http://interchange.puc.state.tx.us/WebApp/Interchange/application/dbapps/filings/pg
Search_Results.asp?TXT_CNTR_NO=39896&TXT_ITEM_NO=754; (July 23,
2012)(Entergy’s Exceptions to Proposal for Decision) available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_775_7318
38.PDF; (October 4, 2012)(Entergy’s Motion for Rehearing)available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_816_738
263.PDF; (November 21, 2012)(Entergy’s 2nd Motion for Rehearing) available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_828_742
851.PDF.
17
AR, PFD at 22.
18
AR, Item 55 (Order) at FF 129.

7
well as the FICA taxes Entergy would have paid on the payroll) in rates

“because it was related to financial measures that are not reasonable and

necessary for the provision of electric service.”19 Entergy did not appeal the

Commission’s order in rate-case Docket 39896 on that issue.

B. The Commission addressed the question of Entergy’s rate-
case expenses in this case.

After it was severed from the rate case, the Commission sent this rate-

case-expense proceeding to the State Office of Administrative Hearings. In

addition to Entergy and the Cities20 that were seeking to recover rate-case

expenses, parties included Commission Staff; the Office of Public Utility

Counsel, which, by statute, represents residential and small commercial

utility customers; Texas Industrial Energy Consumers; and State Agencies.

1. The ALJ considered ratepayers’ arguments against some of
Entergy’s requested rate-case expenses.

Each of the ratepayer groups other than the Cities raised challenges to

some of the rate-case expenses requested by Entergy and the Cities.

Among those challenges, State Agencies claimed that Entergy was not

entitled to recover for the depreciation of assets recorded by its affiliate,

Entergy Services, Inc. (Service Company). OPUC claimed that Entergy

19
Id. at FF 133.
20
Generally, cities that participate in rate cases at the Commission can require
the utility to reimburse their costs. See Tex. Util. Code § 33.023(b).

8
should not recover the expenses it incurred in the rate case arguing that the

Commission should abandon the two-bucket approach to incentive

compensation.

a. Depreciation expenses of Entergy’s affiliated company

State Agencies argued that the Commission should deny Entergy’s

request to include depreciation of assets owned by Entergy’s affiliated

Service Company. Entergy contended that the costs at issue were “a loader

to [Entergy] labor costs covering depreciation on office expenses and

capital.”21 Entergy conceded that such costs would typically be embedded

in a vendor’s labor costs billed to the Company.22

The ALJ recommended that Entergy not be allowed to recover the

depreciation expenses. He not only stated that Entergy had not cited to any

precedent which would justify the recovery of these apparently unusual

rate- case expenses, but also found that Entergy failed to prove the

reasonableness of the expenses under the more stringent standards that are

applicable to affiliate expenses.23

21
AR, Item 25 at 12.
22
Id.
23
Id.

9
b. Rate-case expenses to advocate for abandoning the two-
bucket policy for including incentive compensation in
rates.

Commission Staff, State Agencies, and OPUC argued that Entergy

should not recover any rate-case expenses it incurred in attempting to

eliminate the distinction between operational-goal and financial-goal

buckets of incentive compensation. Commission Staff argued that by

challenging “overwhelming Commission precedent,” Entergy did not act

reasonably.24 Commission Staff contended that the Commission has such

an unequivocal history of denying recovery for financially based incentive-

compensation payments that “[Entergy] should have known that litigating

a position opposed to [it] was not a reasonable use of resources.”25 State

Agencies pointed out that Docket 39896 was merely the latest of three

recent cases in which Entergy sought, but failed to obtain, authority to

charge ratepayers for its financially based incentive costs (the others being

Dockets 34800 and 37744).26

The ALJ, who had also been an ALJ in the Docket 39896 rate case,

agreed with Commission Staff, State Agencies, and OPUC. He noted that

24
AR, Item 30 at 5.
25
AR, Item 24 at 8.
26
AR, Item 23 at 7.

10
throughout the rate case, Entergy took an aggressive position and made a

long-shot argument seeking to eliminate the two-bucket approach to

including incentive compensation in rates.27

The ALJ opined that Entergy’s citation to the cases over the years, where

other utilities requested recovery of financially based incentive

compensation, hurt Entergy’s cause more than it helped because all of the

requests were unanimously denied by the Commission. The ALJ thought

those cases disproved Entergy’s claim that the two-bucket approach was

undergoing continuing clarification.28

The ALJ also found that Entergy overstated and distorted the facts when

it suggested that commissioners have expressed some concern with the

Commission precedent.29 The ALJ noted that the statements Entergy relied

upon all came from a single commissioner, not multiple commissioners.30

Moreover, the comments that Entergy put in evidence show that the

commissioner considered the Commission’s two-bucket precedent binding;

27
AR, PFD at 23.
28
Id.
29
Id.
30
Id. at 23–24.

11
he thought that any change should be accomplished by rulemaking, not an

ad hoc change in a particular rate case.31

The ALJ also found Entergy’s reliance on the recent order at the State

Office of Administrative Hearings in a rate case for SWEPCO to be

misplaced. In the SWEPCO case, the ALJs stated that the utility was not

legally precluded from seeking recovery for its financially based incentive

compensation. The ALJ in this case stated: “It is one thing to acknowledge

that a utility has a legal right to pursue a long-shot theory. It is another

thing entirely, however, to hold that the ratepayers must pay the costs of

the utility’s pursuit of that long-shot.”32

In this case, the Commission did not decide that a utility could never

argue in a contested case that the Commission should change its policy.33

But the Commission did decide that when Entergy argued that the agency

should change such a well-established policy, the argument was such a long

31
Id. at 24.
32
Id.
33
AR, PFD at 24

12
shot—so unlikely to persuade—that it was unreasonable for ratepayers to

bear the expense.34

c. Excessive rate-case expenses

Several parties also claimed that Entergy’s rate-case expenses were

generally too high and that rate-case expenses were high in relationship to

the amount by which Entergy’s rates were raised. Ratepayers also

complained that Entergy had filed three rate cases in the last four years.

Ratepayers were then required to pay rate-case expenses that Entergy

incurred in each of those cases.35

State Agencies expressed concern that, as a general matter, expenses

from rate cases before the Commission appear to be “getting out of hand.”36

Commission Staff “firmly agree[d]” with that concern.37 State Agencies

worried that utilities have no incentive to minimize the number of rate-case

proceedings or the efficiency of rate-case presentation because they assume

their costs will simply be passed on to ratepayers.38 State Agencies urged

34
AR, Order at FF 18f; AR, PFD at 24 (“Simply put, the ALJ concludes that
[Entergy] did not act reasonably when it incurred expenses litigating for recovery of its
financially-based incentive costs in the face of clear and consistent precedent to the
contrary on the issue.”)
35
AR, PFD at 28.
36
AR, Item 23 at 1-2.
37
AR, Item 30 at 13.
38
AR, Item 23 at 1-2.

13
the Commission to allocate rate-case expenses so that the utility was

incentivized to more productively and efficiently use its time in rate cases.39

OPUC agreed that the standard for evaluating the amount of rate-case

expenses to recover from ratepayers ought to give a utility pause before

deciding to pursue overly aggressive or novel arguments.40 Similarly,

Commission Staff and OPUC were concerned about the frequency of

Entergy rate cases over recent years. Docket 39896 was the third Entergy

rate case in four years. Each case resulted in a rate increase and an

obligation for the ratepayers to pay Entergy’s rate-case expenses.41

Staff and OPUC also expressed concern about the overall size of the rate-

case expenses in this case in relation to the outcome of the underlying rate

case. Total rate case expenses ($8.8 million) equal roughly one-third of the

total approved rate increase in Docket 39896 ($27.7 million).42

Commission Staff, State Agencies, and OPUC all expressed the concern that

Entergy was unreasonable because it did not provide good stewardship in

incurring rate-case expenses.43

39
Id. at 5.
40
AR, Item 22 at 8.
41
AR, Item 24 at 3; AR, Item 22 at 2-3, 7-8.
42
AR, Item 24 at 4; AR, Item 22 at 7.
43
See, e.g., AR Item 30 at 13.

14
d. Adjustments to rate-case expenses

The ratepayer parties suggested three ways to adjust Entergy’s rate-

case-expense request to account for problems with Entergy’s request:

• The 50/50 approach. State Agencies’ primary recommendation was to

charge ratepayers for only 50% of total rate case-expenses, arguing that

shareholders, who reap benefits from a rate increase, ought to also share

in the cost of obtaining that rate increase.44

• The Results-Obtained Approach. Alternatively, State Agencies argued

that Entergy should recover only 26.4% of its rate-case expenses—the

ratio between the increase in rates that the Commission authorized in

Docket 39896 ($27.7 million) and the rate increase Entergy asked for in

that case ($104.8 million). OPUC also advocated that approach.45

• The Issue-Specific Reduction Approach. Alternatively, OPUC and

Commission Staff advocated reducing the amount Entergy requested in

rate-case expenses by the ratio between the amounts Entergy sought in

rates for unreasonable, overly aggressive issues and the total rate

increase sought by Entergy. They wanted to include both financially

44
AR, Item 23 at 3.
45
AR, Item 22 at 11.

15
based incentive payments of $6.5 million, and transmission-equalization

payments of $9 million as the numerator of the ratio.

The ALJ agreed with the general concerns raised by Commission Staff,

State Agencies, and OPUC; he believed that a substantial cut to Entergy’s

rate-case expenses was warranted, but only considered the issue-specific

reduction appropriate.46

The ALJ recognized that Section 36.061(b) of the Utilities Code gives the

Commission discretion. He also recognized a number of factors—such as

the time and labor required; the nature of the case; the size of the interest at

stake; and the benefits to the client—that have been deemed relevant to

determining the reasonableness of rate-case expenses. See City of El Paso v.

Pub. Util. Comm’n, 916 S.W.2d 515, 522 (Tex. App.—Austin 1995, writ

dism’d). The ALJ also noted that the parties agreed that Rule 1.04(b) of the

Texas Disciplinary Rules of Professional Conduct provides factors that can

be considered when determining reasonableness of rate case expenses.47

The ALJ rejected the 50/50 approach on the basis that it is contrary to

Commission precedent. He also rejected the results-obtained approach

although he did not find it contrary to Commission precedent. He

46
AR, PFD at 30–32.
47
AR, ETI Ex. 8 at 18-19.

16
considered it a punitive and hindsight-driven approach to cost recovery,

rather than basing cost recovery on whether a utility acted reasonably at the

time it incurred such costs.48

The ALJ found the issue-specific approach entirely consistent with

Commission precedent because the disallowance is a result of specific,

unreasonable actions by Entergy.49

The ALJ found that Entergy bore the burden of proving its reasonable

expenses, and that burden necessarily requires that it separate out any

unreasonable expenses. Having failed to do so with respect to financially

based incentives and transmission equalization payments, he found that it

was reasonable for the Commission to use the issue-specific reduction

approach to calculate those expenses.50

The ALJ proposed that most of the rate-case expenses requested by

Entergy—$7,344,113—be found reasonable and necessary and allowed as a

cost or expense by Entergy. That proposal reduced Entergy’s requested

amount of rate-case expenses for several small specific charges, for

$207,683 in depreciation of office equipment owned by Entergy’s affiliated

48
AR, PFD at 31–32.
49
Id. at 32.
50
AR, Item 24 at 15.

17
company, and for $1,275,738 attributable to “unreasonable and overly

aggressive arguments pursued by [Entergy] in Docket 39896 related to both

financially-based incentive compensation and transmission equalization

payments.”51 The ALJ also proposed a fact finding:

17. The amount of rate case expenses sought by ETI ($8.8 million)
is high, both in absolute terms, and in relation to the rate
increase ultimately obtained by ETI in Docket 39896 ($27.7
million).52

2. The Commission issued its Order in this case.

The Commission considered the ALJ’s proposal for decision and

“adopt[ed] in part and revers[ed] in part.”53 The Commission adopted Fact

Finding 17 about Entergy’s rate-case expenses being excessive. And the

Commission agreed with the proposal to exclude the Service Company’s

depreciation expenses. But the Commission allowed Entergy to recover

expenses incurred for arguments related to transmission-equalization

payments, contrary to the ALJ’s proposal. The Commission did not allow

Entergy to recoup from ratepayers those expenses incurred to argue that

the Commission should abandon its two-bucket policy concerning incentive

compensation included in rates. The Commission stated: “Specifically, the

51
AR, PFD FF 18f.
52
AR, PFD FF 17.
53
AR, Order at 1.

18
Commission agrees with the ALJ that reductions should be made to

Entergy’s recoverable rate-case expenses for Entergy attempting to recover

financially-based incentive compensation in base rates.”54

The Commission further stated that it “has repeatedly ruled that a utility

cannot recover the cost of financially-based incentive compensation because

financial measures are of more immediate benefit to shareholders and

financial measures are not necessary or reasonable to provide utility

services.”55 The Commission concluded “that it should follow its

well-established policy here.”56 The Commission cited four cases

concerning three different utilities from 2005 through 2011 where the

agency refused to allow recovery of incentive compensation based on

financial goals.57

The Commission also adopted the ALJ’s the use of the issue-specific

reduction approach to determine how to calculate an appropriate reduction

in rate-case expenses because the utility took a long-shot position trying to

54
AR, Order at 2.
55
Id.
56
Id.
57
Id.

19
convince the Commission to abandon its well established two-bucket policy

about including incentive compensation in rates.58

C. Entergy appealed.

Entergy filed this suit for judicial review of the Commission’s order to

challenge the amount of rate-case expenses that the Commission ordered.

OPUC, TIEC, and State Agencies intervened in the case. After reviewing the

briefs of the parties and considering their arguments at the hearing on the

merits, the district court, the Honorable Amy Clark Meachum presiding,

affirmed the Commission’s order.59 Entergy appealed to this Court.

Summary of the Argument

In this rate-case-expense proceeding, the Commission reasonably

decided that one of Entergy’s arguments in its related rate case was so

unlikely to prevail that any cost to make the argument was unreasonable.

Thus, the associated expenses were not included in rate-case expenses that

the utility could recover from ratepayers. This decision is reasonable

because the Utilities Code allows only reasonable rate-case expenses to be

recovered, includes a policy of protecting the interests of both the utility and

its customers, and prohibits the Commission from including unreasonable

58
Id.
59
C.R. 232-34.

20
expenses in rates. Moreover, those statutes give the Commission enough

authority to find the expenses unreasonable without first adopting a rule.

And the fact that the Commission subsequently adopted a comprehensive

rule about rate-case expenses shows even more clearly that this contested-

case decision was not improper rulemaking.

Entergy’s expenses to make the argument were not limited to the fees of

expert witnesses on the issue because the issue was included in the utility’s

rate-filing package, the utility responded to numerous discovery requests on

the issue, and the utility filed five briefs addressing the issue at the

Commission. All of that necessarily involved work by Entergy’s staff and

outside attorneys. But Entergy, the party with the burden to prove the

expenses, did not track its expenses for staff and outside attorneys on an

issue-by-issue basis. Thus, the Commission reasonably used a method

proposed by expert testimony in the case to estimate the amount of rate-

case expenses incurred to make the unreasonable long-shot argument.

The Commission properly excluded depreciation expenses of Service

Company, an affiliate of Entergy, from rate-case expenses because Entergy

failed to show that they met the requirements in Utilities Code 36.058.

Entergy did not clearly explain what was being depreciated and why it was a

legitimate rate-case expense nor did Entergy show that the charges were not

21
higher than the charges to other affiliates or third parties for the same type

of services.

Argument

I. Standard of Review

As in any lawsuit, the plaintiff has the burden of proof in a suit for

judicial review of an agency’s order in a contested case. For an

administrative appeal of the Commission’s order in a contested case, that

means that the plaintiff must show reversible error in the Commission’s

order; the substantial-evidence rule described in Section 2001.174 of the

Administrative Procedure Act controls.60 That rule is very deferential to the

agency, but the deference is described differently depending on the type of

error alleged. Complaints in this case invoke the substantial-evidence

standard, and the arbitrary-and-capricious standard.

A. Substantial-evidence Standard

When reviewing an agency’s fact finding, a court uses the deferential

substantial-evidence standard. It prohibits a court from substituting its

judgment for the agency’s as to the weight of evidence.61 “A court that is

reviewing purely factual administrative findings … may determine only

60
See Anderson v. R.R. Comm’n, 963 S.W.2d 217, 219 (Tex. App.—Austin 1998,
pet. denied); Tex. Util. Code § 15.001; Tex. Gov’t Code § 2001.174.
61
Pub. Util. Comm’n v. Gulf States Utils. Co., 809 S.W.2d 201, 211 (Tex. 1991).

22
whether substantial evidence supports those findings.”62 The true test is not

whether the agency reached the correct conclusion, but whether some

reasonable basis exists in the record for the agency’s action.63 “At its core,

the substantial evidence rule is a reasonableness test or a rational basis

test.”64

B. Arbitrary-and-capricious Standard

The Texas Supreme Court has recognized the limits of the arbitrary-and-

capricious standard of review when applied to agency decisions: “The

arbitrary and capricious standard of review historically has been construed

narrowly, and we do not think that the legislature intended it to be

interpreted as a broad, all-encompassing standard for reviewing the

rationale of agency actions.”65 Courts must uphold a Commission decision

if “some reasonable basis exists in the record for the action taken by the

agency.”66

62
Cities of Abilene v. Pub. Util. Comm’n, 146 S.W.3d 742, 748 (Tex.
App.—Austin 2004, no pet.).
63
Tex. Health Facilities Comm’n v. Charter Med.-Dallas, Inc., 665 S.W.2d 446,
452 (Tex. 1984).
64
City of El Paso v. Pub. Util. Comm’n, 883 S.W.2d 179, 185 (Tex. 1994).
65
Charter Med., 665 S.W.2d at 454.
66
City of El Paso, 883 S.W.2d at 185.

23
II. The Commission has discretion to decide that expenses
Entergy incurred making a long-shot argument for
overturning a well-established Commission policy were
unreasonable expenses for ratepayers to reimburse.
(Responds to Entergy Issue 1)

A. The Commission may allow the utility to recover only
reasonable expenses.

The Commission performed its statutory duty to determine whether rate-

case expenses are reasonable, to balance interests of both the utility and its

ratepayers when determining reasonableness, and to allow the utility to

recover only reasonable rate-case expenses.

The Utilities Code gives the Commission discretion when deciding how

much to award a utility in rate-case expenses. In a 2013 appeal of rate-case

expenses for Oncor Electric Delivery Co., LLC, this Court recognized that

“section 36.061(b)(2) gives the Commission the discretion to disallow

improper expenses.”67 And that statute only allows a utility to recover

reasonable rate-case expenses.68 The express purpose of the section of the

Public Utilities Code that applies to electric utilities is “to establish a

comprehensive and adequate regulatory system for electric utilities to

67
Oncor Elec. Delivery Co. LLC v. Pub. Util. Comm’n, 406 S.W.3d 253, 264
(Tex. App.—Austin 2013, no pet.).
68
Tex. Util. Code § 36.061(b)(2) (“The regulatory authority may allow as a cost
or expense … (2) reasonable costs of participating in a proceeding under this title not to
exceed the amount approved by the regulatory authority.” (emphasis added).).

24
assure rates, operations, and services that are just and reasonable to the

consumers and to the electric utilities.”69 Thus, when regulating electric

utilities, the Commission must weigh the interests of both the utilities and

consumers. In addition, the Utilities Code prohibits the Commission from

considering for ratemaking purposes, “any other expenditure … the

regulatory authority finds to be unreasonable, unnecessary, or not in the

public interest.”70

Thus, the Commission may not simply allow a utility to recover expenses

because the utility incurred them to bring a rate case. Instead, the

Commission must determine whether the expenses are reasonable, and the

Commission is prohibited from allowing the utility to recover expenses that

the Commission finds unreasonable. And in deciding what is reasonable,

the Commission must weigh the interests of both the utilities and its

ratepayers. That is exactly what the Commission reasonably did in this case.

69
Tex. Util. Code § 31.001 (emphasis added).
70
Tex. Util. Code § 36.062(4).

25
B. The Commission applied the law to the evidence and
determined that it was unreasonable for Entergy to
recover rate-case expenses incurred to argue that the
Commission should abandon its two-bucket policy
concerning incentive compensation.

Although Entergy incurred expenses to bring the Docket 39896 rate case

and claimed that they were all reasonable, various ratepayer groups

challenged some of those expenses. Commission Staff, State Agencies, and

OPUC all argued that Entergy was unreasonable to incur expenses to argue

in the rate case that the Commission should abandon its two-bucket

approach to incentive compensation.71 They argued that it was so unlikely

that Entergy could prevail on that argument that it was not reasonable for

Entergy to have expended time and expenses to make the argument.72 They

argued that was unreasonable for ratepayers to bear the cost of Entergy

making such a long-shot argument.

The ALJ who heard this rate-case-expense case noted that he had also

heard the Entergy Docket 39896 rate case73 when he called Entergy’s rate-

case argument to abandon the two-bucket approach not only a long shot,

but also overly aggressive.74 He may have been considering both the fervor

71
AR, PFD at 22.
72
Id. at 22–23.
73
Id. at n.87.
74
Id. at 23.

26
of the argument and the amount of time and energy devoted to making the

argument. The record of Docket 39896 reveals

• that in its rate-filing package, the filing that initiated the rate case,

Entergy included testimony of two witnesses arguing that the

Commission should abandon the two-bucket approach, one an outside

expert;75

• Entergy had to respond to nine different discovery requests about the

argument from TIEC (industrial ratepayers), Cities, Commission Staff,

OPUC (representing residential ratepayers), and State Agencies;76 and

75
See Entergy Appellant’s Br. at 29 (listing both Mr. Gardner and Dr. Hartzell as
witnesses on the issue).
76
Docket 39896 (December 20, 2011)(TIEC’s RFIs to Entergy Texas, Inc.)
available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_46_71373
7.PDF; (January 3, 2012) (Cities’ 7th RFI)) available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_62_71465
2.PDF; (January 13, 2012)(Cities’ 10th RFI) available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_141_7155
98.PDF; (January 17, 2012)(Cities’ 12th RFI to Entergy Texas, Inc.) available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_150_7157
44.PDF; (February 1, 2012) (Cities’ 18th RFI to Entergy Texas, Inc.) available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_266_7170
69.PDF; (February 2, 2012) (Commission Staff's 10th RFI to Entergy Texas, Inc.
Question Nos. 10-1 Through 10-8) available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_280_7171
45.PDF; (February 9, 2012) (OPUC’s 10th RFI to Entergy Texas, Inc.) available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_322_7177
21.PDF; (February 21, 2012 (Texas Energy Consumers’ 9th RFI)available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_373_7187
54.PDF; (March 5, 2012)(Cities’ 23rd RFI)available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_415_7199
42.PDF; (April 16, 2012) (State’s 11th RFI to Entergy Texas, Inc.) available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_655_723

27
• Entergy included briefing arguing that the Commission should abandon

its two-bucket approach in five different briefs filed with the

Commission.77

The ALJ and the Commission justly used the term “long shot” to describe

Entergy’s argument that the Commission should abandon its two-bucket

approach to including incentive compensation in rates. Since AEP Texas

Central Company tried to recover incentive compensation for all its

employees in 2004, the Commission has steadfastly maintained a two-

bucket approach—allowing recovery of incentive compensation that fits

within the operational-goal bucket and disallowing recovery of incentive

compensation that fits within the financial-goal bucket.78 Moreover, the

statements from a Commission open meeting that an Entergy witness

481.PDF.
77
Docket 39896, (May 18, 2012) (Entergy’s Initial Brief) available at
http://interchange.puc.state.tx.us/WebApp/Interchange/application/dbapps/filings/pg
Search_Results.asp?TXT_CNTR_NO=39896&TXT_ITEM_NO=719; (May 24,
2012)(Entergy’s Reply Brief) available at
http://interchange.puc.state.tx.us/WebApp/Interchange/application/dbapps/filings/pg
Search_Results.asp?TXT_CNTR_NO=39896&TXT_ITEM_NO=754; (July 23,
2012)(Entergy’s Exceptions to Proposal for Decision) available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_775_7318
38.PDF; (October 4, 2012)(Entergy’s Motion for Rehearing)available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_816_738
263.PDF; (November 21, 2012)(Entergy’s 2nd Motion for Rehearing) available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_828_742
851.PDF.
78
See Appendix C to this brief listing various Commission rate cases from
Docket 28840 forward and the Commission’s treatment of incentive compensation.

28
attached to his testimony do not support Entergy’s position; they were 1)

only the statements of a single commissioner79 and 2) included a statement

that the two-bucket policy was so firmly in place that any change would

need to be done through a rulemaking proceeding.80 Entergy had no

reasonable basis to think it likely that the Commission would abandon the

two-bucket approach to incentive compensation in Docket 39896. Thus, it

was unreasonable for Entergy to have expended so much time and expense

on the argument and unreasonable to require ratepayers to bear the

expense.

Entergy tries to make the Commission’s decision that Entergy’s

argument to abandon the two- bucket approach was such a long shot that

ratepayers should not bear the expenses appear less reasonable by

mischaracterizing the facts. But what Entergy did was to argue that the

well-established policy of dividing incentive compensation into two

buckets—one for operational goals and the other for financial goals—should

79
Such statements are generally irrelevant. “It is immaterial what a
commissioner may have said or thought in the process of arriving at his decision.” City
of Frisco v. Tex. Water Rights Comm’n, 579 S.W.2d 66, 72 (Tex. Civ. App.—Austin 1979,
writ ref’d n.r.e.).
80
AR, ETI Ex. 12, Ex. SFM-R-1, p. 8 of 9 (statements of Commissioner Anderson
at the Commission’s July 30, 2009 open meeting) (“But it seems to be a long and
accepted precedent, and unless we were to open up a separate rulemaking or a project to
change that, to put the—everybody on notice, I’m hesitant to do it in a particular case.”).

29
be abandoned.81 It did not merely argue whether its incentive-

compensation plans fit in the operational-goal bucket or the financial-goal

bucket.

Although Entergy is correct that the question whether a particular form

of incentive compensation belongs in the operational-goal or financial-goal

bucket is a question of fact, that does not change the well-established policy

that there are two buckets: incentive compensation that belongs in the

operational-goal bucket may be recovered in rates and incentive

compensation that belongs in the financial-goal bucket may not. But in its

81
In its initial brief in the rate-case-expense proceeding at the Commission,
Entergy stated:

The Company requests that it be allowed to recover its test year costs of
incentive compensation. The Company recognizes that costs of incentive
compensation tied to financial goals have been disallowed in several prior
rate cases in Texas. The market prevalence of using financial goals as a
part of incentive compensation programs has not been disputed. Rather,
the Commission has previously denied recovery of such costs because of a
lack of evidence showing sufficient customer benefits. In this case,
however, the Company has assembled evidence not previously considered
by the Commission that shows the benefits to customers of using financial
measures in incentive compensation programs. The evidence includes the
testimonies of Company witness Gardner, Vice President of HR Programs
for the Entergy Companies, and Dr. Jay C. Hartzell, who is Chair of the
Finance Department, Professor of Finance, and the Allied Bancshares
Centennial Fellow at the McCombs School of Business at the University of
Texas at Austin. The new evidence also includes empirical studies that
support the Company’s position that customers benefit from incentive
compensation programs that use financial measures and goals that
encourage the financial health of the company.
Docket 39896 (May 18. 2012) (Entergy’s Initial Br.) available at
http://interchange.puc.texas.gov/WebApp/Interchange/application/dbapps/filings/pg
Search_Results.asp?TXT_CNTR_NO=39896&TXT_ITEM_NO=719 at 129–30.

30
brief to this Court, Entergy, after arguing the factual question about which

bucket should hold a particular type of incentive compensation, pivots to the

statement: “The findings that Commission policy was cemented long ago,

and that it was unreasonable for ETI to seek recovery of financially-based

incentives, simply cannot withstand scrutiny.”82 Entergy is wrong. The

Commission can reasonably hold that its policy about two buckets for

incentive compensation is so well-established that it was unreasonable to

ask ratepayers to foot the bill for Entergy challenging the well established

policy even while the Commission entertains fact questions about which

bucket holds individual incentive compensation plans.

This Court has recently acknowledged both the Commission’s long-

standing policy and the fact question that applies to individual types of

incentive compensation. In the Oncor rate case, this Court recognized both

“Commission precedent disallowing compensation payments that are tied to

financial-performance measures rather than those tied to strictly

operational measures”83 and that “the question of whether [a utility’s]

82
Entergy Appellant’s Br. at 16.
83
State of Tex. Agencies and Insts. of Higher Learning v. Pub. Util. Comm’n,
450 S.W.3d 615, 659-60 (Tex. App.—Austin 2014, pet. filed).

31
incentive-compensation payments were ‘financial’ rather than ‘operational’

in nature is one of fact.”84

But the Commission is not saying that a utility cannot recover its

expenses in connection with arguments about incentive compensation. Nor

did the Commission say that the rate-case expenses were unreasonable

merely because Entergy argued against agency precedent. It characterized

Entergy’s arguments as a long shot and overly aggressive. These are

important qualifiers. The two-bucket precedent for including incentive

compensation in rates was well established. Even Entergy in its first issue

in its brief says that the Commission has “historically stated a policy of

disallowing incentive compensation that is tied to “financial” as opposed to

“operational” measures … .”85 Thus, although Entergy does not use the

phrase “well established,” it accepts the premise. Entergy knew that the

Commission had a well-established policy of allowing incentive

compensation in rates only for operational goals, not for financial goals.

Nonetheless, Entergy argued that the two-bucket policy should be

abandoned. The utility should have known that was too much of a long shot

to have any reasonable likelihood of prevailing. The Commission

84
Id. at 660.
85
Entergy Appellant’s Br. at x.

32
reasonably refused to make ratepayers pay the utility to make such a long-

shot argument.

III. The lack of a Commission rule about rate-case expenses for
incentive-compensation arguments did not relieve the
Commission of its statutory duty to allow the utility to
recover only reasonable rate-case expenses. (Responds to
Entergy Issue 2)

Neither Entergy’s arguments that the Commission changed its policy

about rate-case expenses in this case nor its arguments that the Commission

could not decide this case without first adopting a rule stand up to scrutiny.

A. Entergy’s arguments that the Commission departed from
earlier policy in this case are unavailing.

Entergy’s argument that the Commission’s decision to deny the utility’s

expenses to make an unreasonable argument is a change in policy are based

on a mischaracterization of the Commission’s decision. Entergy’s

arguments rely on the Commission previously allowing utilities to argue

about which incentive-compensation expenses belong in the operational-

goal bucket. But that is not the long-shot argument that Entergy made.

Instead, Entergy argued that the Commission should abandon its two-

bucket policy. Entergy shows no examples of allowing rate-case expenses

for arguments to change the two-bucket policy since it became well-

established policy.

33
B. The Commission was merely applying the statutes to the
evidence and argument in this case, not promulgating a
new rule.

The Utilities Code by itself authorizes and requires the Commission to

exclude unreasonable expenses from the rate-case expenses a utility may

collect from ratepayers and put Entergy on notice that unreasonable

expenses could not be recovered.

There was no need for the Commission to adopt a rule before deciding

this case. The Commission cannot avoid its duty to apply the statutes just

because it has not yet adopted a rule to cover every situation that may arise.

The Commission could not dodge the issue and neglect its statutory duty by

noting that it had no rule about how to treat rate-case expenses and

certainly no rule about the very particularized question of how to treat rate-

case expenses incurred to argue about including incentive compensation in

rates. The Commission had to decide the issue based on statutes, the

evidence, and the argument presented in this case.

Applying the statutes to the evidence and arguments in this case, the

Commission recognized that a utility can make arguments in a rate case that

are so unlikely to prevail that it is unreasonable for ratepayers to bear the

burden of the expenses the utility incurred to make those arguments. This

34
is not a new policy of general application; it is merely an outcome from the

statute.

This Court upheld that same outcome in a 1997 water utility case. The

Court upheld denying any rate-case expenses to a utility that brought a rate

case that it wanted to lose. “[T]he Commission could have determined that

any expenses incurred in seeking a surcharge [the utility] did not want were

unreasonable, unnecessary or not in the public interest and that the utility’s

customers should never have to pay them.”86

C. Entergy’s arguments that the Commission engaged in ad
hoc rulemaking are unavailing.

1. This case is distinguishable from Witcher.

Entergy’s reliance on Texas State Board of Pharmacy v. Witcher,87 is

misplaced because the actions of the Commission are entirely different from

the actions of the Texas State Board of Pharmacy. Unlike Witcher, the

Commission had no unstated policy for all cases that it applied to determine

whether Entergy should recover rate-case expenses. Instead, the

Commission had both a statute and a rule that prohibited including

86
Indust. Utils. Serv., Inc. v. Tex. Natural Res. Conservation Comm’n, 947
S.W.2d 712, 718 (Tex. App.—Austin 1997, writ denied).
87
447 S.W.3d 520 (Tex. App.—Austin 2014, pet. filed).

35
unreasonable expenses in rates.88 Once the Commission decided that the

expenses Entergy incurred to make the argument were unreasonable, the

published rule and statute prohibited the Commission from including those

expenses in rates.

The “rule” that the court found to be impermissible ad hoc rulemaking in

Witcher was an unpublished rule, was applied in contravention of the

agency’s published rule as applied to the facts, and was announced in the

order as a policy of general application; in this case, the only rule is a

published rule prohibiting recovery of unreasonable expenses, it was

applied in harmony with the fact findings, and the Commission did not

announce any new policy of general application.

2. Entergy improperly relies on the irrelevant thought
processes of individual commissioners in the course of
the case.

To support its argument that the Commission should have adopted a

rule, Entergy improperly cites the comment of one of the commissioners

during the Commission’s open meeting in this contested case.89 That

quoted language is not part of the administrative record in this case and

therefore not part of the record that the Court should consider. In an

88
Tex. Util. Code § 36.062; 16 Tex. Admin. Code § 25.231(b)(2)(J).
89
Entergy Appellant’s Br. at 18; 21–22.

36
administrative appeal, “[the] court shall conduct the review sitting without a

jury and is confined to the agency record … .”90 And this Court has

explained, “[t]he thought processes or motivations of an administrator are

irrelevant in the judicial determination whether the agency order is

reasonably sustained by appropriate findings and conclusions that have

support in the evidence.”91 The fact that the Commission’s final order does

not reach the same conclusion as the statement of Commissioner Nelson

that Entergy quoted, shows that through the process of deliberation, she

reached a different conclusion. That demonstrates the inappropriateness of

citing to thought processes of an administrator as evidence of what the

Commission actually decided.

And just last week, this Court noted that a statement similar to

Commisisoner Nelson’s request for a rulemaking showed that the agency

was not adopting a rule in its order. In McHaney v. Texas Commission on

Environmental Quality, this Court stated: “The comment made by a TCEQ

commissioner at a hearing that ‘if there is need for clarity in our rules, I

would encourage our staff to look at that and see if we need to go through

90
Tex. Gov’t Code § 2001.175(e).
91
Pedernales Elec. Coop., Inc. v. Pub. Util. Comm’n, 809 S.W.2d 332, 342 (Tex.
App.—Austin 1991, no writ) (quoting City of Frisco v. Tex. Water Rights Comm'n, 579
S.W.2d 66, 72 (Tex. Civ. App.—Austin 1979, writ ref’d n.r.e.)).

37
the rule making or provide some other guidance” (emphasis in original)

strongly implies that rulemaking is not occurring at that hearing.92

3. A rule was adopted when the Commission subsequently
conducted formal rulemaking proceedings.

Although the Commission did not adopt a rule in this case, the

Commission did adopt a rate-case-expense rule through the formal

rulemaking process in 2014.93 That further indicates that the Commission

was not adopting a rule in this case. The actual rulemaking, deciding a rule

of general application for all cases, was done in formal rulemaking. In this

case the Commission merely decided the issues required to determine what

Entergy should receive in rate-case expenses. The Commission utilized both

formal rulemaking and its authority to decide matters that arise in a single

contested case in the proper context.

Entergy’s curious argument—that because it argues that the exceptions to

ad hoc rulemaking do not apply in this case, the Commission adopted a

rule—is illogical. The logical question is whether the Commission actually

adopted a rule in this contested case. It did not; it adopted a rule in a formal

92
McHaney v. Texas Comm’n on Envtl. Quality, No. 03-13-00280-CV, 2015 WL
869197 at *8 (Tex. App.—Austin Feb. 27, 2015, no. pet. h.).
93
39 Tex. Reg. 571 (2014), adopted 39 Tex. Reg. 6434 (2014) (to be codified at
16 Tex. Admin. Code § 25.245).

38
rulemaking. Here the Commission decided only the questions necessary to

resolve this contested case.

IV. The Commission’s decision about the amount of rate-case
expenses to exclude should be affirmed. (Responds to
Entergy Issue 3)

A. Entergy—the party with the burden to prove rate-case
expenses—failed to provide the information needed to
show exactly how much of its rate-case expenses were
incurred to make the unreasonable long-shot argument.

Because Entergy did not track its expenses on an issue-by-issue basis, the

Commission used a proxy to identify the unreasonable expenses Entergy

incurred to make its overly aggressive, long-shot argument that the

Commission should abandon the two-bucket approach to incentive

compensation. Entergy complains that the Commission did not use its

actual expenses, but, because Entergy did not keep track of its expenses on

an issue-by-issue basis, Entergy fails to identify the actual expenses Entergy

incurred in staff and outside counsel expenses to make the unreasonable

argument. Therefore, based on the evidence in the case, the Commission

used a proxy to determine the amount of issue-specific rate-case expenses

that were attributable to the argument. The Commission applied a ratio to

the total amount of rate-case expenses Entergy requested. The ratio

compared disallowed financial-goal bucket incentive-compensation

expenses Entergy requested but did not receive to the total increase in rates

39
that Entergy sought in the Docket 39896 rate case. That resulted in a

$522,244.66 decrease in requested rate-case expenses. The Commission

described that amount as “the amount of rate-case expenses related to

financially-based incentive compensation using the issue-specific reduction

approach.”94

Once the Commission decided that Entergy’s financially based incentive-

compensation arguments were unreasonable and overly aggressive, it

needed to decide how much of the rate-case expenses were attributable to

that argument. The expenses to employ outside expert witnesses in Docket

39896 to support the unreasonable argument could be identified, but the

Commission found that those were not the only expenses. Entergy’s rate-

case expenses included the cost of its staff, the staff of its affiliate Service

Company, and its outside counsel. They decided to make the unreasonable

argument, hired the experts, and included the arguments in the rate-filing

package that initiated the rate case. In addition, they had to respond to

discovery on the issue.95 Finally, Entergy briefed the issue at the State

94
AR, Order at 3.
95
Tex. Pub. Util. Comm’n, Application of Entergy Texas, Inc. for Authority to
Change Rates, Reconcile Fuel Costs, and Obtain Deferred Accounting Treatment,
Docket 39896 (December 20, 2011)(TIEC’s RFIs to Entergy Texas, Inc.) available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_46_71373
7.PDF; (January 3, 2012) (Cities’ 7th RFI)) available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_62_71465
2.PDF; (January 13, 2012)(Cities’ 10th RFI) available at

40
Office of Administrative Hearings and before the Commission.96 To

accomplish all this, some of the time of Entergy and Service Company

employees as well as the time of outside counsel had to have been devoted

to the issue. The fees of the expert witnesses did not capture all these

additional expenses.

http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_141_7155
98.PDF; (January 17, 2012)(Cities’ 12th RFI to Entergy Texas, Inc.) available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_150_7157
44.PDF; (February 1, 2012) (Cities’ 18th RFI to Entergy Texas, Inc.) available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_266_7170
69.PDF; (February 2, 2012) (Commission Staff's 10th RFI to Entergy Texas, Inc.
Question Nos. 10-1 Through 10-8) available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_280_7171
45.PDF; (February 9, 2012) (OPUC’s 10th RFI to Entergy Texas, Inc.) available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_322_7177
21.PDF; (February 21, 2012 (Texas Energy Consumers’ 9th RFI)available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_373_7187
54.PDF; (March 5, 2012)(Cities’ 23rd RFI)available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_415_7199
42.PDF; (April 16, 2012) (State’s 11th RFI to Entergy Texas, Inc.) available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_655_723
481.PDF.
96
Tex. Pub. Util. Comm’n, Application of Entergy Texas, Inc. for Authority to
Change Rates, Reconcile Fuel Costs, and Obtain Deferred Accounting Treatment,
Docket 39896, (May 18, 2012) (Entergy’s Initial Brief) available at
http://interchange.puc.state.tx.us/WebApp/Interchange/application/dbapps/filings/pg
Search_Results.asp?TXT_CNTR_NO=39896&TXT_ITEM_NO=719; (May 24,
2012)(Entergy’s Reply Brief) available at
http://interchange.puc.state.tx.us/WebApp/Interchange/application/dbapps/filings/pg
Search_Results.asp?TXT_CNTR_NO=39896&TXT_ITEM_NO=754; (July 23,
2012)(Entergy’s Exceptions to Proposal for Decision) available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_775_7318
38.PDF; (October 4, 2012)(Entergy’s Motion for Rehearing)available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_816_738
263.PDF; (November 21, 2012)(Entergy’s 2nd Motion for Rehearing) available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/39896_828_742
851.PDF.

41
But when Entergy was asked to calculate the amount of rate-case

expenses devoted to any particular issue, the utility’s witnesses repeatedly

testified that Entergy did not keep track of rate-case expenses on an issue-

by-issue basis. At the hearing, Entergy witness Considine testified:

“Employees charge their time and expenses to a rate case project code that’s

set up specifically for Docket 39896.” In response to the question, “But not

issue specific?” Considine replied, “No, ma’am.”97 Again, Considine

testified, “The Company tracks time on a project level basis, and the entire

project related to the rate case as a whole.”98 In response to a question

about separating rate-case expenses concerning another issue in the rate

case, Considine indicated that he would not estimate how much time was

devoted to a particular issue because it would be a guess.99

In response to a request for information about the rate-case expenses

related to a different issue in the rate case, Entergy responded: “Costs

related to the preparation and presentation of testimony are not accounted

for in the manner requested. Costs are accumulated on a project level basis

and related to the rate case as a whole.”100

97
AR, Tr. at 35.
98
Id. at 45.
99
Id. at 45-46.
100
AR, State’s Ex. 4.

42
B. Substantial evidence supports the Commission’s decision
about the amount of rate-case expenses attributable to
the unreasonable argument in the rate case.

Lacking any evidence from Entergy—the party with the burden to prove

that its rate-case expenses were reasonable—that identified the exact

amount of rate-case expenses that Entergy incurred to argue for abandoning

the two-bucket policy, the Commission had to find a way to measure the

rate-case expenses associated with that argument. The Commission looked

to evidence in the administrative record and applied a method supported by

OPUC witness Benedict. He proposed using a percentage; he compared the

amount of disallowed financial-goal bucket incentive compensation that

Entergy sought in the rate case to the total amount by which Entergy wanted

to increase rates in Docket 38986. That ratio was applied to the total

amount of rate-case expenses Entergy requested to find the percentage of

rate-case expenses attributable to Entergy’s unreasonable long-shot

arguments.101 The ALJ and the Commission used this method to determine

how much of Entergy’s rate-case expenses were for the unreasonable and

overly aggressive rate-case expenses.

101
AR, OPUC Ex. 1 at 10.

43
Thus, the way the Commission determined the amount of requested rate-

case expenses attributable to the unreasonable and overly aggressive

argument is supported by substantial evidence in the record.

C. The Commission’s decision is reasonable—neither
arbitrary and capricious nor an abuse of discretion.

Entergy unsuccessfully argues that the Commission’s computation of

unreasonable rate-case expenses is different from the Commission’s usual

practice. But the Commission followed its practice of excluding only that

portion of the expenses that were unreasonable and its method to determine

that amount is similar to that used in an earlier Commission decision, its

2004, Docket 28840 Order.102

Contrary to Entergy’s claims, the Commission’s actions were consistent

with other rate-case-expense cases: The Commission denied the utility’s

rate-case-expense request to the extent it concerned a single, unreasonable

expense—the expense associated with the argument that the Commission

should abandon the two-bucket approach to determining incentive

compensation included in rates. The Commission refused to generally cut

rate-case expenses in half, based on the assumption that half of the costs

benefitted the shareholders or to cut rate-case expenses based on the

102
Docket 28840 (July 2, 2004) (Proposal for Decision) at 125 available at
http://interchange.puc.texas.gov/WebApp/Interchange/application/dbapps/filings/pg
Search_Results.asp?TXT_CNTR_NO=28840&TXT_ITEM_NO=636.

44
utility’s success in raising rates.103 The Commission’s issue-specific

approach is consistent with only denying unreasonable rate-case expenses.

Moreover, the Commission’s decision in this case is remarkably similar

to the way it decided how much of the cities’ requested rate-case expenses

should not be allowed in the earlier case. Although the Commission did not

use the term “proxy” in Docket 28840, the Commission went through an

analysis similar to the one here to determine how much of the rate-case

expenses were reasonable and should be recovered. In Docket 28840, the

Commission decided that a survey that the cities’ expert used was “seriously

flawed and that conclusions drawn from the data cannot reasonably be

supported under current legal standards”104 Without any analysis of the

amount the expert spent on each part of her study or testimony, the ALJs in

that case stated: “Although Dr. Goodfriend’s survey and the portion of her

testimony upon which it is based may be flawed, that criticism does not fit

the remainder of her testimony. Therefore, the ALJs recommend a

disallowance of one-half of Dr. Goodfriend’s expenses … .”105 The

103
AR, PFD at 31.
104
Docket 28840 (July 2, 2004) (Proposal for Decision) at 125 available at
http://interchange.puc.texas.gov/WebApp/Interchange/application/dbapps/filings/pg
Search_Results.asp?TXT_CNTR_NO=28840&TXT_ITEM_NO=636.
105
Id. at 121-22.

45
Commission adopted that decision in its final order.106 Obviously, the

Commission went to less effort in that case than here to identify the amount

of expense to allocate to a single part of rate-case expenses.

And the Commission did not in this case mandate that every utility keep

track of its rate-case expenses on an issue-by-issue basis. It noted that

Entergy could not complain that exact rate-case expenses attributable to the

unreasonable argument were not used because Entergy, the party with the

burden to prove all the reasonable rate-case expenses it seeks to recover

from ratepayers, did not account for its expenses in a way that would allow

the Commission to determine the exact amount.107 But the computation the

Commission makes—using an issue-specific method to determine those

costs that is based on evidence in the record—was reasonable.

Finally, the Commission did not adopt a rule: it made no general

statement in this case that all utilities must keep track of their rate-case

106
Docket 28840 (Mar. 3, 2006) (Order) FF 29, available at
http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/31433_32_50489
0.PDF.
107
The PFD that the Commission adopted states:
Staff counters (and the ALJ agrees)that [Entergy] bore the burden of
proving its reasonable expenses, and that burden necessarily requires that
it separate out any unreasonable expenses. Having failed to do so with
respect to financially-based incentives …, it is reasonable for the
Commission to use the Issue-Specific Reduction Approach as a proxy for
calculating those expenses.
AR, PFD at 32-33.

46
expenses on an issue-by-issue basis. The Commission did address that

question when it formally adopted a new rule.108 Thus, the Commission

properly decided only the case before it and properly went through formal

rulemaking to adopt a rule.

Because the Commission was not making any new policy decision of

general application, it did not adopt a rule in its order in this case. It was

simply using the evidence presented to determine facts in this case.

V. Entergy failed to meet its burden under Utilities Code
§ 36.058 to prove depreciation charged by its affiliate for
rate-case expenses was reasonable and necessary and no
higher than the costs charged to other affiliates. (Responds
to Entergy Issue 4)

A. The Utilities Code imposes additional requirements to
show that amounts paid to affiliates are reasonable
expenses.

Expenses paid to a utility’s affiliate are subject to increased scrutiny to

ensure that no expenses are included that would not be similarly recovered

in an arms-length transaction. Entergy failed to meet the heightened

standard imposed under Utilities Code § 36.058 when it sought

108
16 Tex. Admin. Code § 25.245(b)(6).

47
depreciation of the assets of the Service Company.109 For each item or class

of items, Entergy had the burden to prove that the expenses were

reasonable and necessary, and that the price was not higher than the prices

charged by the supplying affiliate to its other affiliates, or to a nonaffiliated

person within the same market area or under the same market conditions.110

The Commission must presume that affiliate expenses should not be

included in rates unless these conditions are met.111 Thus, Entergy had to

overcome the presumption against affiliate expenses to recover depreciation

expenses for Service Company in rate-case expenses. It failed to do so.

B. Entergy’s evidence is insufficient to meet its burden of
proof.

Regarding depreciation of Service Company’s assets, the Court should

uphold the Commission’s factual determination that Entergy failed to

provide evidence sufficient to meet the level of scrutiny that applies to

109
Tex. Util. Code § 36.058; Cent. Power & Light Co. v. Pub. Util. Comm’n, 36
S.W.3d 547, 564 (Tex. App.—Austin 2000, pet. denied) (“Because of the possibility for
self-dealing between affiliated companies, however, expenses paid to an affiliated entity
are presumptively not included in the rate base. A utility can overcome this
presumption against affiliate expenses only if it demonstrates that its payments are
‘reasonable and necessary for each item or class of items as determined by the
commission.’”).
110
Tex. Util. Code § 36.058.
111
Tex. Util. Code § 36.058; Cent. Power & Light Co., 36 S.W.3d at 564.

48
expenses paid to affiliates, and Entergy’s reliance on the rate case for

support is misplaced.

1. Entergy failed to explain what depreciation expenses of
Service Company were included.

The quality and character of proof of depreciation expenses that Entergy

provided is not the same in both the rate case and the rate-case-expense

docket. The Commission has explained that “independent evidence must be

provided in order to meet the statutory requirement to develop findings of

fact based on an item or class of items basis.”112 Entergy did not provide

sufficient independent evidence to include Service Company’s depreciation

as part of the utility’s rate-case expenses. Entergy failed to include studies,

comparison to affiliates, comparison to alternative providers, and evidence

of costs to Service Company on a stand-alone basis.113 Utility Code § 36.058

requires strict compliance, and Entergy did not meet the statutory standard.

The Commission found: “$207,683 in depreciation of office equipment

owned by [Service Company] (an affiliated company of [Entergy]) and used

112
Tex. Pub. Util. Comm’n, Application of Entergy Gulf States, Inc. For
Approval of its Transition to Competition Plan and the Tariffs Implementing the Plan,
and for the Authority to Reconcile Fuel Costs, to Set Revised Fuel Factors, and to
Recover a Surcharge for Under-Recovered Fuel Costs, Docket No. 16705,(Oct. 13, 1998)
(Second Order on Rehearing) at 85, FF 150. available at
http://interchange.puc.texas.gov/WebApp/Interchange/application/dbapps/filings/pg
Search_Results.asp?TXT_CNTR_NO=16705&TXT_ITEM_NO=5006 . (Subsequent
citations to this PUC Docket will be cited “Docket 16705.”)
113
Id.

49
by [Service Company] employees for their work in Docket 39896 is not

reasonable and is properly disallowed.”114

In this case, Entergy’s witness Considine testified in response to State

Agencies’ challenge to $207,683 in depreciation expense for Entergy’s

affiliate as rate-case expenses.115 State Agencies claimed that the utility

failed to support the amounts with detail. In response, Mr. Considine

attached detail that was supposed to respond to State Agencies’ concern.116

That detail lists many items for depreciation, but the plethora of data still

fails to explain what is being depreciated. Although the spreadsheets

include project code, year, month, resource code, resource description,

monthly amount, and journal ID number, all that data fails to explain why

those depreciation amounts are relevant to Entergy’s participation in the

rate case. The resource code is a number without any key, and the resource

description simply states “Depreciation & Amort Expenses.”117 There is no

way to know whether Entergy’s affiliate is depreciating only property used

to do work necessary for Entergy’s rate case or whether it is depreciating

every asset it owns.

114
AR, Order at FF 18a.
115
AR, Entergy Ex. 7 at 9 of 11.
116
AR, Entergy Ex. 7 at Ex. MPC-R-1.
117
See id.

50
Entergy attempts to support the expenses by relying on Stephanie

Tumminello’s testimony in Docket No. 39896 where she stated that the

depreciable assets “consist primarily of computer equipment, computer

software systems, communications equipment, furniture, fixtures, leasehold

improvements, and aircraft.”118 Entergy’s reliance on this testimony fails

because it refers to expenses during the test year rather than rate-case

expenses, many of which occurred after the test year, during the rate case.119

The rate-case expenses are subject to entirely different project codes and

billing methods.120 And it is not clear that the same assets are being

depreciated in the rate-case expense proceedings as were depreciated in the

test year. For example, Ms. Tumminello testified that test-year expenses

were adjusted to remove depreciation of aircraft,121 but whether it was also

removed from rate-case expenses is a mystery. This borrowed testimony

118
Docket No. 39896, ETI Ex. 41 (Tuminello Direct at 79 of 98)(emphasis
added). (A certified copy is attached as Appendix E.)
119
Id. at 77 of 98.
120
Id. at 8, 45.
121
Id. at 79 of 98.

51
from the rate case fails to meet the standard requiring independent

evidence to support the item or class of items.122

2. Entergy failed to provide evidence that including Service
Company’s depreciation expense made the expenses
comparable.

Further, Entergy failed to provide evidence required by the statute:

Entergy did not demonstrate that the depreciation price Service Company

charged Entergy is no higher than the prices charged to other affiliates.123

For the test-year expenses, Ms. Tumminello’s testimony regarding

depreciation was supported with numerous reports, benchmarks, and

comparisons.124 But there is no such support for the rate-case-expense

depreciation. Although Mr. Considine testified that Service Company

charges Entergy its actual costs, this is insufficient without supporting

evidence showing that the prices charged to Entergy were not higher than

122
Docket 16705(Oct. 14, 1998) (Second Order on Rehearing) at 85, FF 150.
available at
http://interchange.puc.texas.gov/WebApp/Interchange/application/dbapps/filings/pg
Search_Results.asp?TXT_CNTR_NO=16705&TXT_ITEM_NO=5006.
123
Tex. Util. Code § 36.058(c)(2).
124
See Docket No. 39896 ETI Ex. 41 (Tumminello Direct), Ex. SBT-20 Entergy
Arkansas Test Year Billing to Affiliates; Ex. SBT-21 Entergy Gulf States Louisiana Test
Year Billings to Affiliates; SBT-22 Entergy Louisiana Test Year Billings to Affiliates;
SBT-23 Entergy Mississippi Test Year Billings to Affiliates; Ex. SBT-24Entergy New
Orleans Test Year Billings to Affiliates; SBT-25 Non-regulated Test Year Billings to
Regulated Affiliates. (A certified copy is attached as Appendix F.)

52
those charged to its other affiliates.125 There is no information that enables

the Commission to independently evaluate the costs that Service Company

charged to Entergy compared to its other affiliates. Entergy failed to meet

its burden.

The only evidentiary support Entergy offered to prove that depreciation

should be included in its rate-case expenses is a meaningless spreadsheet

and a Service Company employee’s conclusory statement that the

depreciation expense is reasonable and necessary. The Commission

reasonably decided that the evidence failed to meet the heightened standard

for allowing affiliate expenses under Utilities Code § 36.058. The

Commission properly excluded Service Company’s depreciation from rate-

case expenses, and the Commission’s order should be affirmed.

Prayer

The Commission asks the Court to affirm the district court’s judgment,

which affirmed the Commission’s order. The Commission also asks for all

other relief to which it is entitled.

125
Tex. Util. Code § 36.058; see also Docket 16705 (Oct. 14, 1998) (Second Order
on Rehearing) at 85, FF 153. available at
http://interchange.puc.texas.gov/WebApp/Interchange/application/dbapps/filings/pg
Search_Results.asp?TXT_CNTR_NO=16705&TXT_ITEM_NO=5006.

53
Respectfully submitted,

KEN PAXTON
Attorney General of Texas

CHARLES E. ROY
First Assistant Attorney General

JAMES E. DAVIS
Deputy Attorney General for
Civil Litigation

JON NIERMANN
Division Chief
Environmental Protection Division

/s/ Elizabeth R. B. Sterling
Elizabeth R. B. Sterling
Assistant Attorney General
State Bar No. 19171100

MEGAN M. NEAL
Assistant Attorney General
State Bar No. 24043797

Environmental Protection Division
Office of the Attorney General
P.O. Box 12548, MC-066
Austin, Texas 78711-2548
512.463.2012
512.457.4616 (fax)
Elizabeth.Sterling@texasattorneygeneral.gov

COUNSEL FOR PUBLIC UTILITY
COMMISSION OF TEXAS

54
Certificate of Compliance

I certify that the foregoing computer-generated document has 11,080
words, calculated using the computer program WordPerfect 12, pursuant to
Texas Rule of Appellate Procedure 9.4.

/s/ Elizabeth R. B. Sterling
Elizabeth R. B. Sterling

55
Certificate of Service

I hereby certify that on this the 6th day of March 2015, a true and
correct copy of the foregoing document was served on the following counsel
electronically, through an electronic filing service and by email.

/s/ Elizabeth R. B. Sterling
Elizabeth R. B. Sterling

Counsel for Appellant Entergy Texas, Inc.:

Marnie A. McCormick
John F. Williams
Duggins Wren Mann & Romero, LLP
P. O. Box 1149
Austin, Texas 78767-1149
512.744.9300
512.744.9399 (fax)
mmccormick@dwmrlaw.com
jwilliams@dwmrlaw.com

Counsel for Appellant Office of Public Utility Counsel:

Ross Wyatt Henderson
Assistant Public Counsel
Office of Public Utility Counsel
P.O. Box 12397
Austin, Texas 78711-2397
512.936.7500
512.936.7520 (fax)
Ross.Henderson@opuc.texas.gov

56
Counsel for State Agencies:

Katherine H. Farrell
Assistant Attorney General
Administrative Law Division
Energy Rates Section
Office of the Attorney General
P.O. Box 12548 MC 018-12
Austin, Texas 78711-2548
512.475.4237
512.320.0167 (fax)
Katherine.Farrell@texasattorneygeneral.gov

Counsel for Texas Industrial Energy Consumers:

Rex VanMiddlesworth
Benjamin Hallmark
Thompson & Knight LLP
98 San Jacinto Blvd., Ste. 1900
Austin, Texas 78701
512.469.6100
512.469.6180 (fax)
rex.vanm@tklaw.com
benjamin.hallmark@tklaw.com

57
APPENDIX A

Order
^ k+qn m
"R N

*` , 4 d !.il!

1©!^
PUC DOCKET NO. 40295 VVV

SOAEI DOCKET NO. XXX-XX-XXXX pt/8,t1c Plf 3:
CL4^ `

APPLICATION OF ENTER(^Y § PUBLIC UTILITY COMMISSI(^N
TEXAS, INC. FOR RATE CASE §
EXPENSES PERTAINING TO PUC § OFTEXAS
DOCKET NO. 39896 §

ORDER

This Order addresses the rate-case expenses pertaining to Docket No. 39896,1 Entergy
Texas, Inc.'s last rate case. Entergy requested $8.8 million in rate-case expenses associated with
Docket No. 39896-$7.6 million for Entergy's own rate-case expenses and $1.2 million for
Cities' rate-case expenses. The proposal for decision in this docket was issued on February 19,
2013. In the proposal for decision, the ALJ recommended allowing Cities' rate-case expenses
incurred through August 31, 2012, plus up to $75,800 in rate-case expenses as they are incurred
after August 31, 2012. The ALJ also recommended that Entergy's rate-case expenses be reduced
to account for Entergy taking certain positions in the rate case regarding financially-based
incentive compensation and transmission equalization expenses. The Commission considered
the proposal for decision at the April 11 and April 25, 2013 open meetings. The Commission
adopts in part and reverses in part the proposal for decision, including findings of fact and

conclusions of law.

1. Estimated Rate-Case Expenses
The Commission reverses the proposal for decision regarding Cities' $75,800 in
estimated rate-case expenses to be incurred after August 31, 2012.2 In Docket No. 37772, the
Commission found that approving estimated rate-case expenses for two different parties

representing Cities is not in the public interest and disallowed their recovery in the rate-case
expense surcharge, but did not prohibit the Cities from seeking recovery of actual rate-case

pplication oJ'Entergy Texas, Inc. for A uthority to Change Rates, Reconcile Fuel Costs, and Obtain
1 Application
Deferred Accounting Treatment, Order on Rehearing, Docket No. 39896 (Nov. 2, 2012).
2 Proposal for Decision at 4-8 ( Feb. 19, 2013).

90
PUC Docket No. 40295 Order Page 2 of 8
SOAH Docket No. XXX-XX-XXXX

expenses in the utility's next rate case.3 The Commission affirms that holding here: Cities
cannot recover for estimated rate-case expenses in this docket, but may seek recovery in
Entergy's next rate case. To reflect its determination on this issue, the Commission adds new
finding of fact 16A, modifies conclusion of law 7, and adds new conclusion of law 10.

II. Proportional Reduction
The Commission affirms the proposal for decision regarding the need to reduce Entergy's
recoverable expenses due to an unreasonable position pursued by Entergy in the rate case4 and
also affirms the use of the "issue-specific reduction approach" to determine how to calculate an
appropriate reduction in rate-case expenses when the utility takes positions that are in conflict
with Commission precedent.5

Specifically, the Commission agrees with the AU that reductions should be made to
Entergy's recoverable rate-case expenses for Entergy attempting to recover financially-based
incentive compensation in base rates. The Commission has repeatedly ruled that a utility cannot
recover the cost of financially-based incentive compensation because financial measures are of
more immediate benefit to shareholders and financial measures are not necessary or reasonable
to provide utility services.6 The Commission concludes that it should follow its well-established
policy here.

However, the AU did not include all of the impacts attendant to the disallowance for
incentive compensation.7 To calculate the amount of the reduction in rate-case expenses related
to financially-based incentive compensation, the Commission starts with Entergy's initial rate-

3 Application qf Southwestern Electric Power Company for Rate Case Expenses Pertaining to Docket No.
37364, Order at 1-2, Docket No. 37772 (Oct. 21, 2010).
4 Proposal for Decision at 29-30.
5 Id. at 32-34.
b Application of AEP Texas Central Company for Authority to Change Rates, Docket No. 28840, Proposal
for Decision at 92-97, Findings of Fact Nos. 164-170, Order at 35 (Aug. 15, 2005); Application of AEP Texas
Central Company for Authority to Change Rates, Docket No. 33309, Proposal for Decision at 116-12 1, Finding of
Fact No. 82, Order on Rehearing at 12 (March 4, 2008); Application of Oncor Electric Delivery Company, LLC, for
Authority to Change Rates, Docket No. 35717, Proposal for Decision at 96-100, Finding of Fact No. 93, Order on
Rehearing at 22 (Nov. 30, 2009); and Application of'CenterPoint Electric Delivery Company, LLC, for Authority to
Change Rates, Docket No. 38339, Proposal for Decision at 66-67, Findings of Fact Nos. 81-83, Order on Rehearing
at 22 (June 23, 2011).
7
Docket No. 39896, Order on Rehearing at 5-6, 7-8 (Nov. 2, 2012).
PUC Docket No. 40295 Order Page 3 of 8
Sf)AH Docket No. XXX-XX-XXXX

case expense request, reduced by $208,494 in disallowances made by the ALJ' and affirmed by
the Commission. The Commission further reduces this amount by an additional $522,244.66,

which is the amount of rate-case expenses related to financially-based incentive compensation
using the issue-specific reduction approach.

The Commission disagrees with the AU that Entergy's rate-case expenses should be

reduced due to Entergy's request for transmission equalization (MSS-2 expenses).`' Even though
Entergy did not meet the burden of proof that the requested expenses were known and
measureable changes to test-year expenses, the request for the MSS-2 expenses did not conflict
with clear Commission precedent.

Accounting for these reductions, the Commission finds that rate-case expenses for ETI in
the amount of $6,896,037.73 are reasonable and necessary. Consequently, the Commission is
approving a total amount of $8,021,806.34 in allowable rate-case expenses in this docket.

To reflect its determinations on the proportional reduction issue, the Commission
modifies finding of fact 18 and conclusion of law 9.

1[I. Affiliate Payments
The Commission also finds that the price for Entergy's affiliate payments is not higher
than the prices charged by the supplying affiliate for the same item or class of items to its other
affiliates or divisions or a nonaffiliated person within the same market area or having the same
market conditions. The Commission adds new finding of fact 19 and new conclusion of law 11
to reflect that Entergy met the requirements in PURA § 36.058 regarding payments to its
affiliates for its rate-case expenses.

The Commission also makes minor corrections to conclusions of law 6 and 8 to
incorporate the statutory reference into the language of the conclusion of law. Consistent with
the discussion above, the Commission adopts the following findings of fact and conclusions of
law:

Proposal for Decision at 33-34.
' /ct at 25-27.
PUC Docket No. 40295 Order Page 4 of 8
SOAII Docket No. XXX-XX-XXXX

IV. Findings of Fact
I. Entergy Texas, Inc. (ETI or the Company) is an investor-owned electric utility with a
retail service area located in southeastern "I'exas.

2. On November 28, 2011, ETI filed an application (the ETI Application) requesting,
among other things, approval of a proposed increase in annual base rate revenues of
approximately $111.8 million over adjusted test year revenues, and a new rider for
recovery of costs related to purchased power capacity.

3. On November 29, 2011, the Public Utility Commission of Texas (Commission or PUC)
referred the ETI Application to the State Office of Administrative Hearings (SOAH) for a
hearing and the matter was assigned docket number 39896 (Docket 39896).

4. On April 4, 2012, in Docket 39896, the ALJs issued SOAH Order No. 13 severing rate-
case expense issues into a new docket, the case at issue here, Application of Entergy
Texas, Inc. for Rate Case Expenses Severed from PUC Docket No. 39896, Docket
No. 40295.

5. The hearing on the merits in Docket 39896 was held in April-May 2012.

6. The Proposal for Decision (PFD) in Docket 39896 was issued July 6, 2012.

7. The Commission issued its final order in Docket 39896 on November 2, 2012.

8. The hearing on the merits in the present docket, Docket 40295, was held on
November 28, 2012. The record closed on December 21, 2012, following the filing of
post-hearing briefs.

9. The following parties were granted intervenor status in this docket: Office of Public
Utility Counsel (OPUC); the cities of Anahuac, Beaumont, Bridge City, Cleveland,
Conroe, Dayton, Groves, Houston, Huntsville, Montgomery, Navasota, Nederland, Oak
Ridge North, Orange, Pine Forest, Rose City, Pinehurst, Port Arthur, Port Neches,
Shenandoah, Silsbee, Sour Lake, Splendora, Vidor, and West Orange (Cities); State
Agencies; and Texas Industrial Energy Consumers (TIEC). The staff (Staff) of the
Commission was also a participant in this docket.
PUC Docket No. 40295 Order Page 5 of'8
SOAH Docket No. XXX-XX-XXXX

10. In Docket 39896, ETI adjusted its request for a proposed increase in annual base rate

revenues to approximately $104.8 million over adjusted Test Year revenues.

11. In the PFD in Docket 39896, the ALJs recommended an overall rate increase of
$28.3 million.

12. In its final order in Docket 39896, the Commission largely followed the
recommendations contained in the PFD, but reduced ETI's overall rate increase to $27.7
million.

13. In this docket, ETI seeks to recover $8.8 million in rate-case expenses associated with
Docket 39896.

14. Of that total, $7.6 million was incurred by ETI and $1.2 million was incurred by Cities.

15. Cities proved that, through August 31, 2012, they reasonably incurred rate-case expenses
of $1,125,768.61 in Docket 39896 and this docket.

16. Cities reasonably estimated that their total rate-case expenses in Docket 39896 and this
docket after August 31, 2012 will total $75,800.

16A. The Commission finds that Cities' estimated expenses are not recoverable as rate-case
expenses in this docket.

17. The amount of rate-case expenses sought by ETI ($8.8 million) is high, both in absolute
terms, and in relation to the rate increase ultimately obtained by ETI in Docket 39896
($27.7 million).

18. Rate-case expenses for ETI in the amount of $6,896,037.73 are reasonable and necessary
and should be allowed as a cost or expense by the Company. This amount is calculated
by reducing the requested amount by the amounts listed and for the reasons stated below:

a. $207,683 in depreciation of office equipment owned by Entergy Services, Inc.
(ESI) (an affiliated company of ETI) and used by ESI employees for their work in
Docket 39896 is not reasonable and is properly disallowed.
b. $281 for meals over $25 was erroneously sought by ETI, is not reasonable, and is
properly disallowed.
PUC Docket No. 40295 Order Page 6 of 8
SOAN Docket No. XXX-XX-XXXX

c. $10 for clothing purchased by an attorney for ETl is not reasonable and is
properly disallowed.
d. $40 for laundry charges by an attorney for ETI is not reasonable and is properly
disallowed.
e. $480 for a lodging charge unsupported by receipts is not reasonable and is
properly disallowed.
f. $522,244.66 attributable to unreasonable and overly aggressive arguments
pursued by ETI in Docket 39896 related to tinancially-based incentive
compensation is properly disallowed.
19. The price for Entergy's affiliate payments is not higher than the prices charged by the
supplying affiliate for the same item or class of items to its other affiliates or divisions or
a nonaffiliated person within the same market area or having the same market conditions.

V. Conclusions of Law
1 ETI is a "public utility" as that term is defined in the Public Utility Regulatory Act
(PURA) § 11.004(1) and an "electric utility" as that term is defined in PURA
§ 31.002(6).

2. The Commission exercises regulatory authority over ETI and jurisdiction over the subject
matter of this application pursuant to PURA §§ 32.001, 32.101, 33.002, 33.051, and
36.101-111.

3. SOAH has jurisdiction over matters related to the conduct of the hearing and the
preparation of a proposal for decision in this docket, pursuant to PURA § 14.053 and
Tex. Gov't Code § 2003.049.

4. This docket was processed in accordance with the requirements of PURA and the Texas
Administrative Procedure Act, Tex. Gov't Code Chapter 2001.

5. Pursuant to PURA § 33.051, the Commission has jurisdiction over an appeal from a
municipality's rate proceeding.

6. Pursuant to PURA § 33.023, Cities bore the burden to prove that the rate-case expenses
they incurred were reasonable.
PUC Docket No. 40295 Order Page 7 of 8
SOAH Docket No. XXX-XX-XXXX

7. Cities are entitled to reimbursement by ETI for rate-case expenses of $1,125,768.61
incurred in Docket 39896 and this docket through August 31, 2012.

8. Pursuant to PURA § 36.061(b), ETI bore the burden of proving that the rate-case
expenses it incurred in Docket No. 39896 were reasonable.

9. ET I proved the reasonableness of its rate-case expenses in the amount of $6,896,037.73,
and is entitled to claim that amount as a cost.

10. Consistent with Commission precedent, it is not in the public interest to permit recovery
of estimated rate-case expenses.

11. Entergy met the requirements of PURA § 36.058 regarding payments to its affiliate for its
rate-case expenses.

VI. Ordering Paragraphs
In accordance with these findings of fact and conclusions of law, the Commission issues
the following orders:

l. The Proposal for Decision prepared by the SOAH ALJs is adopted to the extent
consistent with this Order.

2. All other motions, requests for entry of specific findings of fact and conclusions of law,
and any other requests for general or specific relief, if not expressly granted, are denied.

3. Cities' and ETI's requests to recover rate-case expenses are granted to the extent
consistent with this Order.
PUC Docket No. 40295 Order Page 8 of 8
SOAFi Docket No. XXX-XX-XXXX

S"1
SIGNED AT AUSTIN, TEXAS the % day of May 2013

PUBLIC UTILITY COMMISSION OF TEXAS

DONNA L. NELSON, CHAIRMAN

KENNETH W. ANDER,40+; J"lT, COMMISSIONER

y-\cadm\orders\tinal\40000\402951'o.docz
APPENDIX B

Proposal for Decision
State Office of Administrative Hearings

2DI3 FEB 19 PH 3: 24

Cathleen Parsley
Chief Administrative Law Judge

February 19, 2013

TO: Stephen Journeay, Director Courier Pick-up
Commission Advising and Docket Management
William B. Travis State Office Building
1701 N. Congress, 7th Floor
Austin, Texas 78701

RE: SOAH Docket No. XXX-XX-XXXX
PUC Docket No. 40295

Application of Entergy Texas, Inc. for Rate Case Expenses Pertaining to PUC
Docket No. 39896

Enclosed is the Proposal for Decision (PFD) in the above-referenced case. By
copy of this letter, the parties to this proceeding are being served with the PFD.

Please place this case on an open meeting agenda for the Commissioners'
consideration. There is no deadline in this case. Please notify me and the parties of the
open meeting date, as well as the deadlines for filing exceptions to the PFD, replies to the
exceptions, and requests for oral argument.

Sincerely,

unt
Administrative Law Judge

HB/mle
Enclosure
xc: All Parties of Record

300 W. 15th Street, Suite 502, Austin, Texas 78701/ P.O. Box 13025, Austin, Texas 78711-3025
512.475.4993 (Main) 512.475.3445 (Docketing) 512.322.2061 (Fax)
6o7
www.soah.state.tx.us
SOAH DOCKET NO. XXX-XX-XXXX
PUC DOCKET NO. 40295
2 I1 F E B 19 P P', 3: 24

APPLICATION OF ENTERGY §§ BEFORE THt STATE OFFICE tf F ti
TEXAS, INC. FOR RATE CASE
EXPENSES PERTAINING TO PUC § OF
DOCKET NO. 39896 §
§ ADMINISTRATIVE HEARINGS

TABLE OF CONTENTS

I. BACKGROUND ....................................................................................................................... 1

II. JURISDICTION, NOTICE, AND PROCEDURAL HISTORY ........................................ 2

III. PARTIES ............................................................................................................................... 2

IV. DISCUSSION ........................................................................................................................ 3

A. Overview .................................................................................................................... 3

B. Cities' Rate Case Expenses ....................................................................................... 4

C. ETI's Rate Case Expenses ........................................................................................ 8

1. Challenges to Specific ETI Rate Case Expenses That are
Relatively Quantifiable ... .............................................................................. 8

a. Costs Associated with Gerald Tucker, ETI's
Consulting Expert ............................................................................ 8
b. Costs Associated with "Lessons Learned" .................................. 10
c. ESI Depreciation Costs .................................................................. 11
d. Miscellaneous Internal Rate Case Expenses ............................... 13
e. Costs Associated with the Calpine-Carville PPA ........................ 13
f. Specific Items That State Agencies Contend Cast Doubt on
ETI's Overall Scrutiny of Its Expenses ....................................... 15

(1) External Legal Fees .......................................................... 16
(2) Meals and Snacks ............................................................. 17
(3) Courier and Taxi Services ............................................... 18
(4) Meals Over $25 ................................................................. 19
(5) Clothing and Laundry Service ........................................ 20
(6) Airfare and Lodging ........................................................ 20
SOAH DOCKET NO. XXX-XX-XXXX TABLE OF CONTENTS PAGE 2
PUC DOCKET NO. 40295

2. Challenges to Specific ETI Rate Case Expenses That are Difficult to
Quantify ....................................................................................................... 21

a. Financially-Based Incentive Compensation ................................ 21
b. Transmission Equalization (MSS-2) Expenses ........................... 25
c. Purchased Power Capacity Rider ................................................. 27

3. Proportional Reduction .............................................................................. 28

D. Recovery Method ..................................................................................................... 34

1. Rate Case Expense Allocation and the Recovery Mechanism ................ 34
2. ETI's Request to Earn a Return on the Unpaid Balance of Rate
Case Expenses .............................................................................................. 35

V. CONCLUSION ..................................................................................................................... 36

VI. PROPOSED FINDINGS OF FACT, CONCLUSIONS OF LAW, AND
ORDERING PARAGRAPHS .. .......................................................................................... 36

A. Findings of Fact ....................................................................................................... 36

B. Conclusions of Law ................................................................................................. 38

C. Proposed Ordering Paragraphs ............................................................................. 39
SOAH DOCKET NO. XXX-XX-XXXX
PUC DOCKET NO. 40295

APPLICATION OF ENTERGY § BEFORE THE STATE OFFICE
TEXAS, INC. FOR RATE CASE §
EXPENSES PERTAINING TO PUC § OF
DOCKET NO. 39896 §
§ ADMINISTRATIVE HEARINGS

PROPOSAL FOR DECISION

1. BACKGROUND

Entergy Texas, Inc. (ETI) is an investor-owned electric utility with a retail service area
located in southeastern Texas. ETI serves retail and wholesale electric customers in Texas. On
November 28, 2011, ETI filed an application requesting approval of an increase in annual base rate
revenues, a reconciliation of fuel costs, and authority to defer costs for the transition to the Midwest
Independent System Operator (the ETI Application). On November 29, 2011, the Commission
referred the ETI Application, PUC Docket No. 39896, to SOAH (Docket 39896). On April 4, 2012,
the Administrative Law Judges (ALJs) presiding over pocket 39896 issued an order severing from
Docket 39896 the issues relating to ETI's request to recover its rate case expenses and creating this
docket, Docket 40295, for consideration of the rate case expenses.

In this Proposal for Decision (PFD), the ALJ recommends as follows:

That Cities' be allowed to recover from ETI a total of $1,201,569 in rate case expenses
(representing $1,125,769 in rate case expenses incurred through August 31, 2012, plus up to
$75,800 in rate case expenses as they are incurred after August 31, 2012); and

• That ETI be allowed to recover a total of $7,344,113 in rate case expenses.

` The Cities are: the Cities of Anahuac, Beaumont, Bridge City, Cleveland, Conroe, Dayton, Groves, Houston,
Huntsville, Montgomery, Navasota, Nederland, Oak Ridge North, Orange, Pine Forest, Rose City, Pinehurst, Port Arthur,
Port Neches, Shenandoah, Silsbee, Sour Lake, Splendora, Vidor, and West Orange.
SOAH DOCKET NO. XXX-XX-XXXX PROPOSAL FOR DECISION PAGE 2
PUC DOCKET NO. 40295

II. JURISDICTION, NOTICE, AND PROCEDURAL HISTORY

The Public Utility Commission of Texas (Commission or PUC) has jurisdiction over ETI and
this rate case expenses hearing pursuant to Texas Utility Code, Public Utility Regulatory Act
(PURA) §§ 32.001, 33.002, and 35.004. The State Office of Administrative Hearings (SOAH) has
jurisdiction over the contested case hearing, including the preparation of the proposal for decision
(PFD) pursuant to PURA § 14.053 and Texas Government Code § 2003.049(b). ETI's notice of its
application and notice of the hearing were not contested and, therefore, do not require further
discussion here but will be addressed in the proposed findings of fact and conclusions of law.

The hearing on the merits in Docket 39896 was held in April-May, 2012. The PFD was
issued on July 6, 2012. A Final Order in Docket 39896 was issued by the Commission on September
14, 2012. In response to motions for rehearing submitted by multiple parties, the Commission issued
an Order on Rehearing on November 2, 2012, in Docket 39896.2

The hearing on the merits in the present docket, Docket 40295, was held on
November 28, 2012. The record remained open for the filing of post-hearing briefs. The record
closed on December 21, 2012.

III. PARTIES

In addition to ETI, the following entities were granted party status in this case: Texas
Industrial Energy Consumers (TIEC); State of Texas agencies and institutions of higher education
(State Agencies); Office of Public Utility Counsel (OPUC); Cities; and the staff of the Public Utility
Commission (Staff).

2 Multiple second motions for rehearing were denied by the Commission on December 4, 2012.
SOAH DOCKET NO. XXX-XX-XXXX PROPOSAL FOR DECISION PAGE 3
PUC DOCKET NO. 40295

The following is a list of the parties who participated in the hearing and their counsel:

PARTIES REPRESENTATIVES
ETI Steven H. Neinast, Wajiha Rizvi, and George Hoyt
Cities Stephen Mack
TIEC Meghan Griffiths
State Agencies Susan Kelley
OPC Sarah Ferris
Staff Brennan Foley

IV. DISCUSSION

A. Overview

In the ETI Application, ETI requested, among other things, approval of an increase in annual
revenues of approximately $10