# Fox Islands Wind Neighbors v. Department of Environmental Protection

> Supreme Judicial Court of Maine · May 7, 2015 · 116 A.3d 940

URL: https://www.frixlaw.com/law-library/cases/2799297

## Case

- **Full name:** FOX ISLANDS WIND NEIGHBORS, Et Al. v. DEPARTMENT OF ENVIRONMENTAL PROTECTION, Et Al.
- **Court:** Supreme Judicial Court of Maine
- **Decided:** May 7, 2015
- **Citations:** 116 A.3d 940; 2015 ME 53; 2015 Me. LEXIS 55; 2015 WL 2114342
- **Precedential status:** Published
- **Opinion:** Opinion by Jabar
- **Judges:** Saufley, Mead, Gorman, Jabar, Clifford
- **Cited by:** 12 later opinions in the Frix Law Library

## Citator (automated)

- No negative treatment found by the automated citator. That is not the same as a confirmation that the case is good law; read the citing cases.
- Full citator and citing cases: https://www.frixlaw.com/law-library/cases/2799297

## How later opinions describe it (automated extraction)

- concluding that an agency’s compliance conclusion was a reviewable aspect of an enforcement action

## Opinion text

MAINE SUPREME JUDICIAL COURT Reporter of Decisions
Decision: 2015 ME 53
Docket: Ken-14-137
Argued: December 9, 2014
Decided: May 7, 2015

Panel: SAUFLEY, C.J., and MEAD, GORMAN, JABAR, and CLIFFORD, JJ.

FOX ISLANDS WIND NEIGHBORS et al.

v.

DEPARTMENT OF ENVIRONMENTAL PROTECTION et al.

JABAR, J.

[¶1] The Department of Environmental Protection (DEP), Fox Islands Wind

Neighbors (FIWN), and Fox Islands Wind (Fox Island) all appeal from a judgment

entered by the Superior Court (Kennebec County, Murphy, J.) on FIWN’s

Rule 80C petition, reversing DEP’s condition compliance order (CCO), remanding

to DEP, and dismissing FIWN’s First Amendment retaliation claim.1 We vacate

the judgment.

I. BACKGROUND

[¶2] On March 24, 2009, Fox Island applied to DEP for certification

pursuant to 35-A M.R.S. § 3456 (2014) to build and operate a small-scale wind

energy development project in Vinalhaven. DEP approved the application on

June 5, 2009, and issued a section 3456 certification to Fox Island. As part of the
1
Rule 80C permits judicial review of final agency action or the failure or refusal of an agency to act,
brought pursuant to the Maine Administrative Procedure Act. See M.R. Civ. P. 80C.
2

certification, “condition #8” required Fox Island to implement a noise-reduction

operation plan using a “revised operation protocol” if the wind turbines produced

noise in excess of applicable standards. Having received certification for its

project, Fox Island began construction.

[¶3] Some neighbors, organized as FIWN, began complaining about the

noise from the turbines soon after the project began operating. FIWN hired an

attorney and an acoustical consultant who collected sound data. Beginning in

April 2010, FIWN submitted numerous noise complaints to DEP and requested

that DEP take action against Fox Island requiring it to comply with the

certification’s conditions. DEP contacted the Town of Vinalhaven to inquire

whether it wished to take enforcement action against Fox Island.2 By letter dated

November 22, 2010, the Town declined to pursue enforcement action and

instructed DEP to “continue with enforcement.”

[¶4] On November 23, 2010, DEP began the enforcement process by

issuing a formal noncompliance letter to Fox Island. DEP found that on July 17

and 18, 2010, Fox Island exceeded the 45 dBA nighttime sound limit specified in

the certification and instructed Fox Island to submit a “revised operation protocol”

2
Title 35-A M.R.S. § 3456(3) (2014), provides, “Following certification . . . and during construction
and operation,” certification standards “may be enforced by the municipality in which the generating
facilities are located at the municipality’s discretion . . . .” That subsection further provides “The [DEP]
is not responsible for enforcement of this section.” Though the Town has express enforcement authority
pursuant to subsection 3, this subsection plainly does not deprive DEP of its enforcement authority.
Indeed, DEP concedes that it has the discretionary authority to enforce its certifications.
3

within 60 days as required by condition #8. After numerous exchanges between

DEP and Fox Island, including several data requests by DEP and Fox Island’s

submission of a proposed operation protocol that DEP rejected, DEP demanded

that Fox Island submit a revised operation protocol for approval.

[¶5] Fox Island submitted a revised operation protocol on April 11, 2011,

and DEP issued a CCO on June 30. The CCO accepted Fox Island’s revised

protocol, finding that it “satisfactorily addresses the requirement of Special

Condition #8 of [the certification] with respect to the conditions present during the

July 2010 complaint period.” The CCO also required Fox Island to implement

certain noise reduction mechanisms when wind conditions matched those present

on July 17 and 18, 2010.3

[¶6] On July 28, 2011, FIWN filed a Rule 80C petition in the Superior

Court, asserting that the CCO was a product of political intervention; violated

statutory provisions; exceeded DEP’s statutory authority; was unsupported by

substantial evidence; was arbitrary and capricious; and constituted an abuse of

DEP’s discretion. After numerous motions and orders, the court denied a motion

to dismiss brought by Fox Island and DEP, which asserted that judicial review of

3
The CCO initially contained an “Appendix A,” which included two sections: one regarding
additional compliance testing and data submission by Fox Island, and one entitled “complaint response
and resolution protocol,” which required Fox Island to manage complaints in a specific way including
maintaining a 24-hour telephone hotline and posting data to their website. Fox Island objected to the
inclusion of Appendix A, and on June 30, 2011, DEP’s Acting Commissioner issued the CCO without it.
4

the CCO was barred by 35-A M.R.S. § 3456(2). The court found that the CCO

was an enforcement action by DEP subject to judicial review, and that therefore

section 3456(2) did not apply.

[¶7] Nine days later, DEP filed a motion to reconsider and raised a new

issue claiming that FIWN lacked standing to challenge DEP’s enforcement of

violations. The court denied the motion to reconsider and found that FIWN had

standing. FIWN then filed an amended petition adding two additional claims for

relief under the United States Constitution and 42 U.S.C. § 1983 (2014).4 The

court dismissed the independent claims, but granted FIWN permission to argue the

constitutional claims as part of the Rule 80C proceeding.

[¶8] On March 10, 2014, the court issued its order on the Rule 80C petition,

in which it restated its finding that the CCO was an enforcement action subject to

judicial review. The court then reversed the CCO and remanded the matter to DEP

with instructions that DEP “require an operational protocol which would prevent

further violations of the noise rules,” and issue a CCO that would address

“significant vertical and directional wind shear,” rather than wind direction, as the

4
Count III of the amended petition alleged that the CCO violated FIWN’s right to petition DEP as
protected by the First Amendment, and Count IV alleged that the CCO discriminated against FIWN in
violation of the Fourteenth Amendment’s Equal Protection Clause by depriving its members of the right
to be protected from excessive noise, which, FIWN claimed, is available to any other Maine resident
living near a wind project.
5

main causative factor of Fox Island’s noise infractions.5 The court denied FIWN’s

constitutional claims. DEP and Fox Island appealed, and FIWN cross-appealed.

II. DISCUSSION

[¶9] Generally, in Rule 80C appeals, a remand from the Superior Court to

an executive agency for additional decision-making is not a final judgment.

Forest Ecology Network v. LURC, 2012 ME 36, ¶ 16, 39 A.3d 74. Nonetheless, in

circumstances where “denial of appellate review could result in judicial

interference with apparently legitimate executive department activity,” we have

recognized a narrowly construed separation of powers exception to the final

judgment rule in extraordinary circumstances.6 Id. ¶ 18 (quotation marks omitted).

This separation of powers exception applies “when prompt appellate review is

required to prevent judicial interference with apparently legitimate executive

department activity and thereby safeguard the separation of powers, and in order to

avoid undue [judicial] disruption of administrative process.” Id. (quotation marks

5
The court also instructed DEP to issue further findings of fact or “otherwise articulate its rationale”
for eliminating Appendix A.
6
The judicial economy exception to the final judgment rule has two requirements: (1) “that our
review of a non-final order can establish a final, or practically final, disposition of the entire litigation”
and (2) “that the interests of justice require that immediate review be undertaken.” Forest Ecology
Network v. LURC, 2012 ME 36, ¶ 17, 39 A.3d 74 (quotation marks omitted). The separation of powers
exception is an exception to the first requirement. Id. ¶ 18.
6

omitted). Such an extraordinary circumstance exists here,7 and we reach the merits

of this interlocutory appeal under the judicial economy exception to the final

judgment rule.

[¶10] DEP and Fox Island argue that the CCO is not judicially reviewable

and that the court violated separation of powers principles by remanding the CCO

to DEP with further instructions. FIWN argues that the court should not have

dismissed its First Amendment retaliation claim. We examine these claims in turn.

A. Judicial Reviewability

[¶11] We review issues of statutory interpretation de novo. Carrier v. Sec’y

of State, 2012 ME 142, ¶ 12, 60 A.3d 1241. Section 3456(2), which governs siting

considerations for small-scale wind projects, provides: “Notwithstanding any other

provision of law, [DEP’s] certification pursuant to this section . . . is not itself

subject to judicial review as final agency action or otherwise.” The language is

clear: DEP-issued certifications for small-scale wind projects are not judicially

reviewable. Therefore, the first question we must resolve is whether the

challenged DEP action, the CCO, was part of DEP’s certification process, or a

post-certification enforcement action subject to judicial review. See 5 M.R.S.

§ 11001 (2014); 38 M.R.S. § 347-A (2014).
7
In addition to the Superior Court’s mandate that an executive branch agency explain why it has not
undertaken a specific course of action in an enforcement matter, the remand with specific instructions to
the DEP to institute an operational protocol may leave the DEP without recourse to judicial review
because it cannot seek appellate review of its own action.
7

[¶12] The statutory scheme for approving small-scale wind projects

differentiates between the certification process itself and post-certification

enforcement action. Title 35-A M.R.S. § 3456(1) sets out the certification process,

stating: “A person may not construct or operate a wind energy

development . . . without first obtaining a certification from [DEP]” that the project

meets certain noise, shadow, and setback requirements. The last sentence of this

subsection states, “A person proposing a wind energy development subject to

certification under this section . . . may not begin construction until the

certification is received.” Id. Subsection 3 specifies that enforcement is

undertaken “[f]ollowing certification . . . and during construction and operation.”

Id. § 3456(3).

[¶13] In June 2009, DEP completed its certification process when it notified

Fox Island that its project had been reviewed and approved. Section 3456(2)

provides that DEP “shall issue its certification within 185 days of its acceptance of

a request for certification . . . .” Fox Island submitted its application on March 24,

2009, and DEP’s approval on June 5, 2009, was well within the 185-day limit.

[¶14] Pursuant to its certification-granting authority, DEP imposed certain

conditions on Fox Island’s project. One of those conditions—condition

#8—required Fox Island, within sixty days of a DEP noncompliance

determination, to “submit, for [DEP] review and approval, a revised operation
8

protocol that demonstrates that the project will be in compliance . . . .” That the

certification came with strings attached is not uncommon, and such practice is

expressly authorized by section 3456.8

[¶15] Following certification of its project in June 2009, Fox Island began

construction. A plain reading of section 3456 indicates that, at this point, the

certification process that is a prerequisite to initiating construction had concluded.

Fox Island completed construction and began operations in October 2009.

[¶16] Then, on November 23, 2010, DEP issued a formal noncompliance

letter to Fox Island related to the noise infractions on July 17 and 18, 2010, and

demanded that Fox Island submit a revised operation protocol pursuant to

condition #8 of the certification. See 38 M.R.S. § 347-A(1)(B) (“Before initiating

a civil enforcement action . . . [DEP] shall issue a notice of violation . . . cit[ing]

the applicable law, rule and term or condition of the license, permit or order

alleged to have been violated; and provide time periods for the alleged violator to

take necessary corrective action and to respond to the notice.”). DEP’s letter

concluded, “Provided that [Fox Island implements the revised protocol] in a

manner that ensures compliance with [DEP] noise standards and permit conditions,

[DEP] can resolve this matter without further action.” See id. (“[T]he notice may

8
Title 35-A M.R.S. § 3456(2) (2014), provides that “Certification may be conditioned on specific
requirements.”
9

state that further enforcement action will not be pursued if compliance is achieved

within the time period specified in the notice or under other appropriate

circumstances.”) (emphasis added).

[¶17] By way of the June 30, 2011, CCO, DEP accepted Fox Island’s

revised protocol as compliant with condition #8 of the certification, and also

required Fox Island to implement noise reduction mechanisms under certain wind

conditions. That DEP was able to reach an agreement with Fox Island and did not

have to go to court to enforce Fox Island’s revised operations protocol does not

render the CCO any less an enforcement action by DEP. Indeed, the CCO was

very similar to a consent decree, which is a common DEP enforcement

mechanism. See id. § 347-A(4). Further, DEP’s action here was based on

complaints regarding Fox Island’s operations, and not on DEP’s own initiative to

modify or renew the certification.

[¶18] DEP and Fox Island argue that because the revised operation protocol

was referenced in the original certification in special condition #8, the CCO

approving it was merely an “amendment” of the initial certification and was

therefore part of the certification process as well. We disagree. This

characterization is contrary to a plain reading of the statute, pursuant to which the

certification process was over when DEP granted Fox Island’s application on

June 5, 2009. That the certification contained conditions with which Fox Island
10

had to comply does not give DEP authority to “amend” the certification process

many months or even years later. Nor does the initial attachment of conditions

mean that any subsequent DEP action to bring a project into compliance with those

conditions is not “enforcement.” Section 3456 clearly sets an end date for the

certification process because it provides that Fox Island could not have

constructed, much less operated, its wind energy project until the certification

process had been completed.

[¶19] Requiring Fox Island to comply with the certification’s original stated

conditions is an enforcement action, not an amendment to the certification. The

“certification amendment” view posited by DEP and Fox Island would result in the

imposition of new “enforceable standards” pursuant to DEP’s certification

authority. However, this view would render the “enforceability” of these new

standards meaningless, because they could never be enforced, only amended

through the imposition of further standards. If we were to accept this argument,

the certification process would never have an end point as long as there were

conditions initially imposed upon the project.

[¶20] For these reasons, the CCO was a judicially reviewable enforcement

action commenced many months after certification was complete.
11

B. The Condition Compliance Order

[¶21] Because we conclude that DEP’s CCO was an agency enforcement

action, we review its merits.9 The CCO was issued following Fox Island’s noise

infractions on July 17 and 18, 2010, and it requires Fox Island to implement certain

noise reduction mechanisms when the wind conditions match those present during

those noncompliance periods. Specifically, the CCO requires Fox Island to

implement a particular operational plan between 7:00 p.m. and 7:00 a.m. whenever

the wind direction is between 200 and 250 degrees, or south-southwest, and the

wind shear falls within a specific range.

[¶22] DEP’s formal determination of noncompliance noted that Fox Island

“is likely to exceed the required sound compliance level . . . when there is a

significant vertical and directional shear.” The record on which the CCO was

issued included evidence that wind shear is “most possible” with a south-southwest

wind in the Gulf of Maine, as was the case on July 17 and 18, 2010. The record

also contained evidence that wind shear is possible with other wind directions as

well, that not all wind shear would result in a noise violation, and that the level of

shear should be measured by the “wind shear coefficient.” However, DEP

9
FIWN has standing to challenge the CCO because it has demonstrated a particularized injury,
namely the claim of negative impact from excessive noise emanating from the wind energy development.
See Great Hill Fill & Gravel, Inc. v. Bd. of Envtl. Prot., 641 A.2d 184, 184 (Me. 1994). Further, there is
no separation-of-powers issue because this is an enforcement action, a final agency action for which
judicial review is expressly authorized by statute. See 5 M.R.S. §§ 11001, 11007 (2014); Heckler v.
Chaney, 470 U.S. 821, 832-33 (1985).
12

concluded that, other than wind direction, there was no clear evidence of what

factors affect this coefficient.

[¶23] FIWN argues that DEP could not, based on this record evidence, have

rationally adopted a CCO that addresses only the speculative factor of wind

direction to the exclusion of what FIWN contends is the one clear causative factor:

wind shear of a certain coefficient. Essentially, FIWN contends that the CCO did

not go far enough to address potential noise violations because its terms were

limited to the wind direction present on July 17 and 18, 2010, when winds blowing

from other directions might be just as harmful.

[¶24] However, the possibility of noise violations under meteorological

conditions other than those present during the July violations does not negate the

substantial record evidence supporting the CCO. See 5 M.R.S. § 11007(4)(C)(5)

(2014) (providing that the court may reverse an administrative decision if it is

“[u]nsupported by substantial evidence on the whole record”). The CCO

addressed Fox Island’s operations under weather conditions that DEP knew to have

resulted in the only formal instances of noncompliance in the record. While these

may not be the only conditions under which Fox Island’s operations result in noise

violations, DEP rationally focused on wind direction in issuing the CCO.

[¶25] This is not a case where DEP refused to undertake any enforcement

action. The CCO, much like a consent decree, was an agreement reached by the
13

parties in lieu of DEP’s pursuing further enforcement action such as sanctions or

greater conditions imposed upon Fox Island. The petitioners do not complain that

DEP refused to take any enforcement action; rather, they complain that DEP’s

action did not go far enough. This goes to the essence of prosecutorial discretion:

agencies have a great deal of discretion when it comes to enforcement of the laws

under their jurisdiction. See, e.g., Lindemann v. Comm’n on Governmental Ethics

& Election Practices, 2008 ME 187, ¶ 17, 961 A.2d 538; Herrle v. Town of

Waterboro, 2001 ME 1, ¶¶ 10-11, 763 A.2d 1159. As a matter of policy, an

agency’s chosen level of enforcement may be more or less than that which is

sought, but our review must give deference to the agency so long as its action is

supported by substantial evidence in the record. Contrary to FIWN’s argument,

DEP’s decision to enter into an agreed upon order rather than push for further

conditions was supported by substantial record evidence and was within the

agency’s discretion.

C. First Amendment Retaliation

[¶26] FIWN claims that the issuance of the CCO was an act of retaliation by

DEP against the neighbors. In order to establish a claim under 42 U.S.C.A.

§ 1983, “the claimant must show a deprivation of a right secured by federal law,

statutory or constitutional, and that the deprivation was achieved under color of

state law.” Wyman v. Sec’y of State, 625 A.2d 307, 310 (Me. 1993). FIWN argues
14

that the court erred by dismissing its First Amendment retaliation claim, pursued as

an independent claim in the Rule 80C proceedings. We review constitutional

issues de novo. Light v. D’Amato, 2014 ME 134, ¶ 17, 105 A.3d 447.

[¶27] To establish a First Amendment retaliation claim, FIWN must show

that: “(1) [it] engaged in constitutionally protected conduct, (2) [it] was subjected

to an adverse action by [DEP], and (3) the protected conduct was a substantial

motivating factor in the adverse action.” D.B. v. Esposito, 675 F.3d 26, 43

(1st Cir. 2012). The parties agree that FIWN engaged in constitutionally protected

conduct when it complained to DEP about the excessive noise. FIWN’s claim

fails, however, because there was no adverse action taken by DEP against FIWN

that would deter the latter from further exercising its constitutional rights. Id.

at 44 n.11. The CCO is binding on Fox Island, not on FIWN. It does not require

FIWN to take or refrain from taking any particular action or otherwise divest

FIWN of any right or privilege established by law. FIWN and the individuals who

make up the group continue to have the unfettered right to petition DEP to respond

to noise violations or any other alleged violation of DEP standards by Fox Island.

The entry is:

Judgment vacated. Remanded to the Superior
Court for dismissal of the complaint.
15

On the briefs:

Janet T. Mills, Attorney General, and Gerald D. Reid, Asst.
Atty. Gen., Office of the Attorney General, Augusta, for
appellants Department of Environmental Protection and Patricia
Aho

Catherine R. Connors, Esq., and Nolan L. Reichl, Esq., Pierce
Atwood LLP, Portland, for appellant Fox Islands Wind, LLC

Rufus E. Brown, Esq., Brown & Burke, Portland, for cross-
appellants Fox Islands Wind Neighbors, et al.

David G. Webbert, Esq., and Roberta L. de Araujo, Esq.,
Johnson, Webbert & Young, LLP, Augusta, for amicus curiae
Maine Employment Lawyers Association

Zachary L. Heiden, Esq., American Civil Liberties Union of
Maine, Portland, for amicus curiae American Civil Liberties
Union of Maine

At oral argument:

Gerald D. Reid, Asst. Atty. Gen., for appellants Department of
Environmental Protection and Patricia Aho

Catherine R. Connors, Esq., for appellant Fox Islands Wind,
LLC

Rufus Brown, Esq., for cross-appellants Fox Islands Wind
Neighbors, et al.

Kennebec County Superior Court docket number AP-2011-42
FOR CLERK REFERENCE ONLY

---

Source: Frix Law Library, https://www.frixlaw.com/law-library/cases/2799297. Public record. Not legal advice.
