# Lummus Global Amazonas, S.A. v. Aguaytia Energy Del Peru, S.R. Ltda.

> District Court, S.D. Texas · June 14, 2002 · 256 F. Supp. 2d 594

URL: https://www.frixlaw.com/law-library/cases/2390877

## Case

- **Full name:** LUMMUS GLOBAL AMAZONAS, S.A., Plaintiff, v. AGUAYTIA ENERGY DEL PERU, S.R. LTDA., Defendant
- **Court:** District Court, S.D. Texas
- **Decided:** June 14, 2002
- **Citations:** 256 F. Supp. 2d 594; 2002 WL 31401996
- **Precedential status:** Published
- **Opinion:** Opinion by Rosenthal
- **Judges:** Rosenthal
- **Cited by:** 26 later opinions in the Frix Law Library

## Citator (automated)

- No negative treatment found by the automated citator. That is not the same as a confirmation that the case is good law; read the citing cases.
- Full citator and citing cases: https://www.frixlaw.com/law-library/cases/2390877

## Opinion text

MEMORANDUM AND ORDER
ROSENTHAL, District Judge.
Lummus Global Amazonas, S.A. (“LGA”) designed and built natural gas pipeline, gathering, and processing facilities in Peru for the project owner, Aguay-tia Energy Del Peru S.R. Ltda. (“Aguay-tia”). The contract between LGA and Aguaytia contained a broad arbitration provision, providing for “final and binding arbitration” under the Rules of Arbitration of the International Chamber of Commerce. In September 1998, the parties began arbitration proceedings to resolve a number of claims and counterclaims under the contract. The proceedings, conducted in two phases, ended in June 2001. The arbitration panel issued three detailed written decisions and an addendum, resolving LGA’s claims for unpaid bonuses, change orders, and contract price adjustments, and Aguaytia’s counterclaims for liquidated damages for delays, the cost of remedying alleged defects in the construction, payment for pipe paid for but not purchased or installed, and a number of other disputed items. The panel concluded that LGA was required to pay Aguaytia a net amount of $13.4 million, exclusive of interest.
*600
In this lawsuit, LGA moves to vacate, modify, or amend the final and interim arbitration awards, asserting a number of defects in the arbitration process and result. Aguaytia asks this court to confirm and enforce the award, but to enter judgment that reduces the award by an offset of approximately $5.2 million that the parties have stipulated is owed to LGA.
The parties have presented starkly different characterizations of the claims and of the arbitration itself. LGA asserts that it delivered “a working, viable and commercially profitable facility” by the agreed-upon date, that has exceeded the parties’ projections of profit. Aguaytia contends that “LGA failed to complete, test and deliver the facilities at the times specified in the Agreement” and delivered the facilities months late, with material defects. LGA asserts that the arbitration represents a “mockery of justice,” in which the three-member panel, dominated by one arbitrator LGA challenges as biased, acted in “manifest disregard” of the governing law. Aguaytia asserts that the panel of recognized experts in construction law assembled and painstakingly analyzed a thorough and exhaustive record involving a number of very technical issues; correctly stated and applied the law; and based the specific findings that LGA challenges on the detailed technical facts disclosed in the record and the parties’ contract provisions. Aguaytia denies any arbitrator bias and emphasizes that LGA did not raise this claim until after the panel issued its award in favor of Aguaytia.
This court applies the standard for reviewing arbitration awards under the Federal Arbitration Act, 9 U.S.C. §§ 10 , 11, and 12, to the extensive record, the arbitration panel’s detailed findings, and the parties’ contentions. LGA also invokes the Inter-American Convention on International Commercial Arbitration (the “Inter-American Convention”), 9 U.S.C. § 301
et seq.,
and the Convention on the Recognition and Enforcement of Foreign Arbitral Awards (the “New York Convention”), 9 U.S.C. §§ 201
et seq.
Most of the arguments LGA makes for vacating or modifying the awards challenge specific aspects of the awards. Two arguments, arbitrator bias and the panel’s refusal to grant the parties’ joint request to incorporate the stipulation as to credits and payments owing to LGA, are alleged as a basis for vacating the entire award. Each of the grounds LGA asserts, with Aguaytia’s response, raises the same set of issues: does LGA assert a sufficient basis to permit this court, under the narrow and deferential standard of review mandated by statute, to vacate the results of the already prolonged process that the parties agreed would be final and binding upon them?
Based on the pleadings, the motions and responses, the evidence, the arguments of counsel, and the applicable law, this court concludes that LGA has met the burden that the law imposes to vacate the results of contractually binding arbitration only as to two discrete aspects of the award. One is the award for certain IGV, or Peruvian value-added, taxes. This court vacates the portion of the award addressing LGA’s liability for certain IGV taxes and remands that issue to arbitration for a determination as to the amount of taxes owed. The second aspect is the status of the joint stipulation of certain payments and credits owed to LGA. The narrow scope of review does not permit this court to include the stipulation in the final judgment. This court remands the narrow issue of the effect of the stipulation as to payments and credits on the arbitration award to be resolved in arbitration. This court confirms all other aspects of the arbitration award. Specifically, this court DENIES LGA’s motion for discovery on the issue of evi
*601
dent partiality or bias; DENIES LGA’s motions to vacate the award in its entirety; GRANTS, in part, and DENIES, in part, LGA’s motion to vacate specific aspects of the award; DENIES LGA’s supplemental petition and motion to vacate the award; GRANTS, in part, and DENIES, in part, Aguaytia’s motion to confirm and enforce the arbitration award; DENIES, without prejudice, Aguaytia’s motion for final judgment; and DENIES Aguaytia’s request for bond. This court also ORDERS the parties to appear for a status conference on April 12, 2002, at 9:00 a.m., to discuss the most efficient method of proceeding.
The reasons for these rulings are set out below.
I. Background
Aguaytia is organized and has its principal place of business in Peru. (Docket Entry No. 9). LGA is a Peruvian corporation with its principal place of business in Houston, Texas. (Docket Entry No. 1). LGA is a subsidiary of ABB Lummus Global, Inc., a Delaware corporation with its principal place of business in Houston, Texas.
(Id.).
In February 1995, Aguaytia issued an invitation to bid for the design and construction of natural gas and natural gas liquid gathering, processing, and pipeline facilities in what the parties both describe as a “jungle” area in Peru. LGA submitted its bid in May 1995. Effective May 31, 1996, Aguaytia and LGA entered into an Agreement to design and construct a gas processing facility, a fractionation facility, and pipelines from wellheads to the gas plant and from the gas plant to other facilities. The pipelines connected the fractionation facility and a newly constructed power plant that was not part of the Agreement.
Clause 24.02(a) of the Agreement required the parties to submit “all disputes arising in connection with or relating to this Agreement” to “final and binding arbitration,” “pursuant to the rules of Arbitration of the International Chamber of Commerce.” (Docket Entry No. 9, Ex. 7). The Agreement provided that “[t]he substantive law applied in such arbitration shall be the law of New York.”
(Id.).
LGA initiated arbitration proceedings in September 1998. Under the ICC Rules, LGA appointed one of the arbitrators, Robert Rubin, a recognized authority in New York construction law. Aguaytia appointed Michael Jaffe as the second arbitrator. Jaffe is a practicing lawyer with a recognized expertise in construction litigation and experience as an arbitrator. The parties agreed to Allen Overcash as the third, presiding, arbitrator. Overcash teaches and practices construction law and also had experience as an arbitrator.
The parties negotiated and reached an agreement, approved by the panel and the ICC, for a two-phase arbitration. Phase 1 addressed “delay issues, associated damages claims, completion bonus claims, certain pipeline credit issues, a discreet number of defective construction issues and certain claims for extra work (‘variances’) -” (Docket Entry No. 36, Ex. A, p. 2). Phase 2 addressed “warranty issues and claims of defective work.”
(Id.).
Although the Agreement specified Miami, Florida as the place for arbitration, the Terms of Reference the parties and the arbitrators signed specified Houston, Texas as the place for arbitration and stated that the award “shall be considered as having been made at the place of the arbitration, namely Houston, Texas.” (Docket Entry No. 12, Ex. E(A)).
The panel began by issuing a set of rulings on legal and contractual issues that did not turn on factual disputes and did not require the presentation of evidence. In the Interim Award on Issues Proposed for Summary Disposition (the “Summary
*602
Disposition”), issued on January 21, 2000, the panel held that under New York law, extrinsic evidence of the parties’ intent was not admissible to interpret unambiguous contract provisions; interpreted provisions of the Agreement addressing delays by Aguaytia that could provide LGA a right to extend contractual deadlines and preclude liquidated delay damages for the additional time; and ruled that the Agreement did not impose a $500,000 limit to Aguaytia’s right to recover money it had paid LGA for pipe that was not used in the project (the “pipe credit”). The panel deferred consideration of other issues for factual development. (Docket Entry No. 45, p. 2; Aguaytia Ex. 6).
The Phase 1 hearing record included over fifty witness statements, three hundred exhibits, extensive briefs, live testimony from fourteen witnesses taken in nine days of hearings, and post-hearing briefs and exhibits. (Docket Entry No. 19, p. 1). On June 14, 2000, the panel circulated a draft written opinion on the Phase 1 issues. The panel denied most of LGA’s claims that Aguaytia’s own delays made the liquidated damages provisions inapplicable, finding that Aguaytia was entitled to liquidated damages for LGA’s delays, in the amount of $6.7 million. The panel denied LGA’s claims for $6.1 million in contract price adjustments; denied LGA’s claims for $720,000 in proposed change orders; denied LGA’s claims for an early completion bonus; granted Aguaytia a pipe and pipe installation credit of $1.5 million; and found that Aguaytia was entitled to recover from LGA amounts necessary to remedy pipeline corrosion caused by carbon dioxide.
On July 10, 2000, LGA filed a motion to vacate the arbitration panel’s draft award. The ICC denied LGA’s motion, (Aguaytia Ex. 9), and issued the Phase 1 award (the “Interim Award”) on August 16, 2000. The Interim Award addressed each of the parties’ arguments in a lengthy and detailed opinion. (Docket Entry No. 36, Ex. A). The Interim Award granted Aguaytia $8,394,678.40 and LGA $600,713.00, for a net award to Aguaytia in Phase 1 of $7,793,765.40. The panel also found LGA liable for certain design and construction defects, deferring determination of the damage amounts to Phase 2.
On October 30, 2000, LGA filed this petition to vacate, modify, or amend the Interim Award. (Docket Entry No. 1). As legal grounds for vacating the award, LGA alleged that the arbitration panel “manifestly disregarded” the applicable law; the panel failed to allow LGA to present evidence; and one member of the panel was biased as a result of an undisclosed conflict of interest, which “tainted” the “entire proceedings.” (Docket Entry No. 1, p. 2). Aguaytia challenged the timeliness and effectiveness of service and moved to dismiss or transfer venue; this court denied those motions. (Docket Entry No. 9,16).
Shortly after entering the Interim Award, the panel began the proceedings related to the Phase 2 issues. After receiving legal memoranda, numerous documents, over thirty witness statements, and expert reports, the panel held seven days of evidentiary hearings, which included oral examination of witnesses. The panel met with each party’s counsel to review that party’s argument as to each Phase 2 claim and received additional submissions. On April 23, 2001, the panel issued its Final Award, (Docket Entry No. 36, Ex. B), which incorporated the Interim Award.
In the Final Award, the panel granted additional awards of $5,786,738.00 to Aguaytia and $383,419.00 to LGA, resulting in a net Phase 2 award to Aguaytia of $5,403,319.00. The panel also awarded Aguaytia $2,691,088.00 in attorney fees and $525,000.00 in costs. The panel held that
*603
Aguaytia was entitled to be reimbursed for IGV taxes that it had paid or would pay in connection with remedying LGA’s defective design and work and with employing attorneys and consultants for the arbitration. The panel could not determine the total amount of IGV taxes that Aguaytia would be entitled to seek from LGA. In the award, the panel established a procedure for Aguaytia to claim reimbursement from LGA if, and when, it paid those taxes. The panel held that Aguaytia was entitled to receive preaward and postaward interest and determined the dates from which interest would accrue.
On June 1, 2001, the parties submitted a Joint Application for Correction of Final Award to the panel under Article 29(2) of the ICC Rules of Arbitration. In the Joint Application, the parties asked the panel to amend the Final Award by incorporating a stipulation that Aguaytia owed LGA $5.2 million in credits. The parties signed the stipulation in May 2001 and notified the panel before the panel entered the Final Award. On June 4, 2001, Aguaytia also filed a separate application for Correction and Interpretation of the Final Award under Article 29(2).
On September 4, 2001, the panel issued an Addendum to the Final Award (the “Addendum”). (Aguaytia Ex. 60). In the Addendum, the panel denied the parties’ Joint Application to incorporate the stipulation and reduce the Final Award, stating that “[a]s matters contained in the May 2001 Stipulation were resolved by the parties and are not subject to resolution by the Tribunal, there is no proper basis for ‘correcting’ or ‘interpreting’ the Final Award.”
(Id.).
The panel granted, in part, and denied, in part, Aguaytia’s separate request for interpretation and correction.
LGA filed a First Amended Petition and Motion to Vacate, Modify or Amend Arbitration Awards in this court.
1
(Docket Entry No. 36). LGA challenges the following specific aspects of the award:
(1) The award of liquidated damages to Aguaytia for LGA’s failure to achieve interim deadlines under the Agreement.
(2) The “pipe credit” awarded to Aguay-tia for unused labor and materials for pipeline that LGA did not purchase or install on the project.
(3) The award of damages to Aguaytia for remedying pipeline corrosion from carbon dioxide.
(4) The award to Aguaytia for a defect in the “as built” drawings.
2
(5) The establishment of a procedure for Aguaytia to claim reimbursement for IGV taxes.
(6) The award of attorney fees and costs to Aguaytia.
LGA does not specifically challenge the many other rulings and findings that the panel made. LGA does not specifically challenge the Interim Award rulings granting and denying LGA’s claims for unpaid bonuses and contract adjustments. The Final Award not only incorporated the Interim Award, but specifically addressed twenty-nine separate items, of which LGA challenges only six. LGA challenges the other points only to the extent LGA asserts that arbitrator bias requires the entire award to be vacated and resubmitted to a new panel.
*604
LGA’s specific challenges are based on the following grounds:
(1) Certain aspects of the award are arbitrary and capricious.
(2) In awarding certain damages to Aguaytia, the panel abused and exceeded its authority in the Agreement, issues submitted, and Terms of Reference.
(3) Aspects of the award failed to draw their essence from the contract.
(4) Certain aspects of the award show manifest disregard for New York law.
(5) The panel failed to hear and consider evidence pertinent and material to certain aspects of the case.
(6) The panel failed to issue a final and definite award.
LGA challenges the entire award on the ground that one of the panel members, Jaffe, was partial and engaged in misconduct. (Docket Entry No. 48, pp. 5-6; Docket Entry No. 36). After the panel issued the Addendum, LGA filed a Supplemental Petition and Motion to Vacate Arbitration Awards, asserting that the panel’s refusal to incorporate the parties’ stipulation as to credits and payments owed LGA, reducing the amount of the award, was, in itself, a sufficient ground for vacating the entire award. (Docket Entry No. 48). LGA asserted that in refusing to incorporate the stipulation, the panel “deliberately engaged in acts of misconduct and violated their duties — all to the prejudice of LGA.” (I'd, p. 2).
Aguaytia has filed a Motion to Confirm and Enforce International Arbitration Awards, for Judgment and for Posting of Bond. (Docket Entry No. 45). Aguaytia asks this court to enter judgment that includes the $5.2 million the parties stipulate is owing to LGA as an offset. Aguay-tia asks this court to confirm the $13.4 million award but
enter
judgment in the amount of $7,821,539.00, exclusive of interest. Aguaytia also asks this court to order LGA to post a bond for $9,100,000.00, representing the principal and interest due. Aguaytia asserts that this court has authority to require a bond under Article 6 of the Inter-American Convention and Article VI of the New York Convention.
LGA opposes the motion to confirm and the bond request. LGA argues that this court lacks authority to modify the Final Award by reducing it to reflect the parties’ Stipulation. (Docket Entry No. 49). LGA also argues that this court lacks authority to order a bond and, in the alternative, that a bond is unnecessary. (Docket Entry No. 50).
The parties have submitted a voluminous record, including the evidence submitted -to the arbitration panel, motions and correspondence filed with the ICC, the panel’s awards, and excerpts of the transcripts from the arbitration proceedings. This court has carefully read each of the parties’ briefs and responses, as well as the evidence submitted, and has analyzed the parties’ arguments in light of the relevant law. This court addresses each of the issues presented below.
II. The Applicable Legal Standard
A court considering an arbitration award under the FAA applies a deferential standard of review.
Gulf Coast Indus. Workers Union v. Exxon Co.,
991 F.2d 244, 248 (5th Cir.1993);
Psarianos v. Standard Marine, Ltd.,
790 F.Supp. 134, 135 (E.D.Tex.1992),
aff'd,
12 F.3d 461 (5th Cir.),
cert. denied,
511 U.S. 1142 , 114 S.Ct. 2164 , 128 L.Ed.2d 887 (1994). The party moving to vacate an arbitration award has the burden of proof.
Spector v. Torenberg,
852 F.Supp. 201, 206 (S.D.N.Y.1994). Judicial review of arbitrators’ decisions is “extraordinarily narrow” under the Federal Arbitration Act.
In the Matter of the Arbitration Between Trans Chem. Ltd. & China Nat’l Mach. Import & Exp. Corp.,
*605
978 F.Supp. 266, 303 (S.D.Tex.1997)(citing
Gulf Coast Indus. Workers Union v. Exxon Co.,
70 F.3d 847, 850 (5th Cir.1995), and
Forsythe Int’l. S.A. v. Gibbs Oil Co. of Texas,
915 F.2d 1017, 1020 (5th Cir.1990));
see also Executone Info. Sys., Inc. v. Davis
26 F.3d 1314, 1320 (5th Cir.1994).
The Federal Arbitration Act provides four grounds for vacating an award:
(1) Where the award was procured by corruption, fraud, or undue means.
(2) Where there was evident partiality or corruption in the arbitrators, or either of them.
(3) Where the arbitrators were guilty of misconduct in refusing to postpone the hearing, upon sufficient cause shown, or in refusing to hear evidence pertinent and material to the controversy; or of any other misbehavior by which the rights of any party have been prejudiced.
(4) Where the arbitrators exceeded their powers, or so imperfectly executed them that a mutual, final, and definite award upon the subject matter submitted was not made.
9 U.S.C. § 10 (a).
The Fifth Circuit has held that an arbitration award may be vacated if (1) the award is contrary to public policy; (2) the award is arbitrary and capricious; (3) the award fails to draw its essence from the underlying contract; or (4) the award displays manifest disregard of the law.
Williams v. Cigna Fin. Advisors Inc.,
197 F.3d 752, 758-61 (5th Cir.1999). Review on these grounds is necessarily narrow, limited to determining whether the arbitration proceeding was fundamentally unfair.
Id.
Courts repeatedly admonish that “severely limited” judicial review is an essential, and inherent, feature of contractually agreed binding arbitration, necessary to avoid undermining the “twin goals of arbitration ... settling disputes efficiently and avoiding long and expensive litigation.”
In the Matter of the Arbitration Between Trans Chemical Limited and China Nat’l Machinery Import and Export Corp.,
978 F.Supp. 266, 303 (S.D.Tex.1997), aff
'd,
161 F.3d 314 (5th Cir.1998).
A district court should “interpret the arbitrator’s award and the contract broadly so as to uphold the award.”
Manville Forest Prods. Corp. v. United Paperworkers Intern. Union AFL-CIO,
831 F.2d 72, 74 (5th Cir.1987)(citing
United Steelworkers of America v. Enterprise Wheel & Car Corp.,
363 U.S. 593, 598 , 80 S.Ct. 1358 , 4 L.Ed.2d 1424 ). A district court must accept the arbitrator’s factual findings and the arbitrator’s interpretation of the contract even if it disagrees with the arbitrator’s interpretation of the underlying contract, as long as the arbitrator’s decision “draws its essence” from the contract.
Executone,
26 F.3d at 1320 (citing
United Paperworkers Int’l Union v. Misco, Inc.,
484 U.S. 29, 36 , 108 S.Ct. 364 , 98 L.Ed.2d 286 (1987)). A district court “must affirm the arbitrator’s decision if it is rationally inferable from the letter or the purpose of the underlying agreement.”
Id.
(citing
Anderman/Smith Operating Co. v. Tennessee Gas Pipeline Co.,
918 F.2d 1215, 1218 (5th Cir.1990)).
An award is “arbitrary and capricious” only if “a ground for the arbitrator’s decision cannot be inferred from the facts of the case.”
Ainsworth v. Skurnick,
960 F.2d 939, 941 (11th Cir.1992)(vacating award where, despite district court’s instruction that Florida law required award of statutory damages, arbitration panel failed to award such damages without explanation). In
First Options of Chicago, Inc. v. Kaplan,
514 U.S. 938 , 115 S.Ct. 1920 , 131 L.Ed.2d 985 (1995), the Supreme Court stated that a court may set aside an arbitration award “only in very unusual circumstances,” and that “parties [are] bound by [an] arbitrator’s decision not in
*606
‘manifest disregard’ of the law.”
Id.
at 942 , 115 S.Ct. 1920 (citing
Wilko v. Swan,
346 U.S. 427, 436-37 , 74 S.Ct. 182 , 98 L.Ed. 168 (1953),
overruled on other grounds, Rodriguez de Quijas v. Shearson/American Express, Inc.,
490 U.S. 477 , 109 S.Ct. 1917 , 104 L.Ed.2d 526 (1989)). The Fifth Circuit has described
First Options
as the Supreme Court’s “clear approval of the ‘manifest disregard’ of the law standard in the review of arbitration awards under the FAA.”
Williams v. Cigna Fin. Advisors Inc.,
197 F.3d 752, 759 (5th Cir.1999)(citing,
accord, Montes v. Shearson Lehman Bros., Inc.,
128 F.3d 1456, 1459 (11th Cir.1997);
Barnes v. Logan,
122 F.3d 820 (9th Cir.1997),
cert denied,
523 U.S. 1059 , 118 S.Ct. 1385 , 140 L.Ed.2d 645 (1998);
Cole v. Burns Int’l Sec. Servs.,
105 F.3d 1465, 1486 (D.C.Cir.1997);
M & C Corp. v. Erwin Behr GmbH & Co., KG,
87 F.3d 844 (6th Cir.1996)).
A party asserting “manifest disregard” of the law must meet a heavy standard. The Fifth Circuit applies a two-step test:
First, where on the basis of the information available to the court it is not manifest that the arbitrators acted contrary to the applicable law, the award should be upheld. Second, where on the basis of the information available to the court it is manifest that the arbitrators acted contrary to the applicable law, the award should be upheld unless it would result in significant injustice, taking into account all the circumstances of the case, including power of arbitrators to judge norms appropriate to the relations between the parties.
Williams,
197 F.3d at 762 (quoting Ian R. Macneil et al., 4 Federal Arbitration Law § 20.7.2.6, 40:95 (Supp.1999)(footnote omitted)). The Second Circuit has described the reach of the “manifest disregard” doctrine as “severely limited.”
3
Halligan v. Piper Jaffray, Inc.,
148 F.3d 197, 202 (2d Cir.1998)(quoting
Government of India v. Cargill, Inc.,
867 F.2d 130, 133 (2d Cir.1989)). That court stated, “[Un-deed, we have cautioned that manifest disregard ‘clearly means more than error or misunderstanding with respect to the law.’ ”
Id.
(quoting
Merrill Lynch, Pierce, Fenner & Smith, Inc. v. Bobker,
808 F.2d 930, 933 (2d Cir.1986)). To modify or vacate an award on this ground, “a court must find both that (1) the arbitrators knew of a governing legal principle yet refused to apply it or ignored it altogether, and (2) the law ignored by the arbitrators was well defined, explicit, and clearly applicable to the case.”
Id.
(citing
DiRussa v. Dean Witter Reynolds, Inc.,
121 F.3d 818, 821 (2d Cir.1997)).
In deciding whether an arbitration panel exceeded its authority, the district court resolves all doubts in favor of arbitration.
Executone,
26 F.3d at 1320 -21 (citing
Valentine Sugars, Inc. v. Donau Corp.,
981 F.2d 210, 213 (5th Cir.1993)). In reviewing an award, a court is not limited to the panel’s explanation of the award.
Id.
at 1325. A district court “looks only to the result reached. The single question is whether the award, however arrived at, is rationally inferable from the contract.”
Id.
(quoting
Anderman/Smith Operating Co.,
918 F.2d at 1219 n. 3).
This standard of review must be applied to each argument LGA makes to vacate or modify the award.
*607
III. The Award of Liquidated Damages for LGA’s Failure to Meet Interim Deadlines
The arbitration panel awarded Aguaytia $6.8 mill inn in liquidated damages for LGA’s failure to meet “interim milestones” set in the Agreement. These “interim milestones” are dates by which LGA had to achieve particular “intermediate construction progress.” (Docket Entry No. 36, p. 21). The Agreement defined criteria for three “milestones”: (1) “First Completion” (Section 1.01 at p. 5); (2) “Second Completion” (Section 1.01 at p. 12); and (3) “Commercial Operation” (Section 1.01 at p. 2). The panel awarded Aguaytia liquidated damages for LGA’s failure to meet requirements for the First and Second Completions. (Docket Entry No. 36, Ex. A, p. 3).
The Agreement provided that if LGA faded to achieve First Completion by the Guaranteed First Completion Date of December 30, 1997, LGA would pay liquidated damages of $43,000 per day until it achieved First Completion. If LGA failed to achieve Second Completion by the Guaranteed Second Completion Date of January 30, 1998, LGA would pay liquidated damages of $20,000 for each day of delay, subject to a maximum. The Agreement also provided that LGA would be paid a bonus for each day it saved on these contractual deadlines.
LGA does not dispute that delays occurred. Instead, LGA argues that under the New York law governing “concurrent delay,” Aguaytia’s own delays entitled LGA to an extension of time and abrogated Aguaytia’s right to obtain contractual liquidated damages. In arbitration, LGA asserted that it was entitled to an extension of the contractual deadlines; delay damages; and an early completion bonus. Aguaytia contended that none of the acts or omissions LGA asserted met the contractual requirements for a delay that could extend the contract deadlines and preclude liquidated damages for that period. The arbitration panel considered each of Aguaytia’s acts and omissions that LGA claimed caused its own delay in achieving the First and Second Completions. The panel found that as to one area, LGA was entitled to an extension of time for Aguay-tia’s concurrent delay. As to the remaining areas, the panel concluded that LGA had not proven the elements necessary to show a “Company Delay” as defined by section 13.01(a) of the Agreement. LGA asserts that the panel acted in “manifest disregard” of New York law governing “concurrent delay” and indefinite contract terms, which resulted in an “arbitrary and capricious” liquidated damages award. (Docket Entry No. 36, p. 10).
A. Concurrent Delay
During Phase 1 of the arbitration, both LGA and Aguaytia presented witness statements, cross-examined witnesses, presented experts, and argued about whether Aguaytia’s own acts and omissions contributed to LGA’s failure to meet the interim construction deadlines, so as to relieve LGA of the liquidated damages provided under the Agreement. LGA asserted that Aguaytia’s “Company Delays” caused LGA to be delayed in achieving both the First and Second Completions.
Section 13.01(a) of the Agreement defines a “Company Delay,” as follows:
If (i) Contractor is delayed in performing any aspect of the Work due to a delay of Company in performing its obligations under this Agreement, (ii) the cause of such delay does not arise from Force Majeure, and (iii) Contractor is unable to proceed with other portions of the Work so as not to cause a delay in the First Completion Date, the Second Completion Date, and/or the Commercial Operation Date, the Contractor shall
*608
give Company notice of the occurrence of such condition as soon as it becomes aware thereof (a
“Company Delay”).
Section 16.02 of the Agreement provided that the contract deadlines could be adjusted as:
a result of Company Delay ... that will cause a delay in the Project Schedule such that there will be a corresponding delay in Contractor achieving the First Completion Date, the Second Completion Date, ... in which event Contractor shall be entitled to a one day extension ... for each such day of delay ....
In the Interim Award, the panel explained why it concluded that there was one “Company Delay” on the part of Aguaytia that, under the doctrine of concurrent delay, extended the First Completion Date by almost one month, in LGA’s favor. The panel also explained why it concluded that the other acts and omissions LGA asserted were not “Company Delays” by Aguaytia and did not warrant extensions of the completion dates or preclude liquidated damages for the days LGA failed to meet the deadlines. (Docket Entry No. 43). LGA asserts that the panel “manifestly disregarded” New York law on concurrent delay in reaching these conclusions. LGA argues that the panel applied a more rigorous “total time” standard, set out in federal Court of Claims cases addressing the burden on a party seeking to recover liquidated damages on government contracts.
The panel recognized in both the Summary Disposition and the Interim Award that New York law on concurrent delay applied. In the Summary Disposition, the panel stated that in order to receive an extension under the parties’ Agreement, LGA had to demonstrate: (1) the existence of a “Company Delay” by Aguaytia, as defined in Section 13.01(a) of the Agreement, and (2) that the Company Delay actually impaired LGA’s ability to meet the deadlines under Section 16.02(a)(ii) of the Agreement. (Aguaytia Ex. 6, p. 3). The panel stated that “[ljiquidated damages will not be recovered by [Aguaytia] for LGA’s delays where, and to the extent, there are concurrent Company Delays that impaired LGA’s achieving the relevant contract milestone.”
(Id.,
p. 13). LGA does not dispute this statement of the concurrent delay rule.
The panel noted that LGA had conceded that it had to “[establish a causal link between the claimed Company Delay and its inability to progress the work necessary to achieve the particular contract milestone for which it seeks a Target Schedule Adjustment.” (Aguaytia Ex. 6, p. 4). The panel cited to New York law and rules.
(Id.,
p. 12)(citing Cushman & MEYERS, CONSTRUCTION LAW HANDBOOK, § 23.01[D], p. 825 (Aspen Law 1999)). LGA agrees that the panel correctly stated the applicable New York law on concurrent delay and that the panel correctly applied the law when it granted LGA a twenty-seven day extension of the First Completion Date based on a shared responsibility for a pressure control valve that was not timely installed. LGA argues that except as to as to this one area, the panel failed to apply New York law on concurrent delay and instead applied a more stringent federal law standard that uses a “total time” analysis.
Under a “total time” analysis, LGA had to prove the following elements: a causal connection between Aguaytia’s improper conduct and a specific amount of delay; that other methods (other than the one prohibited by Aguaytia) to achieve the same result were not available; or that such methods, if used, would have been unavailing. (Docket Entry No. 36, Ex. A, p. 8)(citing
WRB Corp. et al. v. United States,
183 Ct.Cl. 409, 427 (Ct.Cl.1968)).
*609
The panel specifically addressed five areas that LGA asserted as “Company Delays”: Aguaytia’s denial of right of way access to LGA; Aguaytia’s announced plan to shut down two wells; Aguaytia’s inspectors’ refusal to allow LGA to use tack welds to close pipe ends, resulting in dirty pipes that slowed LGA’s pipe cleaning; Aguaytia’s failure to control inlet pressure of gas into the plant; and Aguaytia’s rejection of LGA’s pipeline tests. The record reveals that the arbitration panel considered each of these arguments and found that LGA had failed to show a Company Delay by the project owner, Aguaytia, as defined in Section 13.01(a) of the Agreement. The record supports these findings.
As to the claim of failure to provide access to the right of way, the panel found that Aguaytia had not breached any obligation under the parties’ “early start agreement” or under the Agreement itself to make right-of-way access available before a certain date. The panel also concluded that LGA did not show that its inability to have right of way access before that date was a “critical path delay.” The panel did not, as LGA contends, apply federal law to this issue. Instead, the panel examined the Agreement provisions on access; heard the disputed evidence as to the effect of obstructed right of way access; and concluded that LGA had not met the contractual criteria for a “Company Delay” that would trigger the application of the concurrent delay rule. (Docket Entry No. 36, Ex. A, pp. 5). Federal case law involving a “total time” analysis played no role in the panel’s decision on this issue.
The panel cited federal case law, and referred to a “total time” analysis, as to only two of the “Company Delay” claims. The panel did not cite federal law, or refer to a “total time” analysis, in analyzing the right of way access delay claim; the claim of delay from Aguaytia’s planned shutdown of two wells; or the claim of delay from the failure to control inlet pressure of gas into the plant. The panel did cite federal cases and law, and refer to a “total time” analysis, in its decision on LGA’s claim that Aguaytia’s refusal to allow tack welded end caps on open sections of pipeline caused dirt and debris to gather in the pipelines and delayed the pipeline cleaning work. The panel also referred to a “total time” analysis in discussing LGA’s claim of delay arising from Aguaytia’s rejection of certain tests LGA performed. A review of the record reveals that in neither section of the award did the panel manifestly disregard controlling New York law.
In its discussion of the impact of Aguay-tia’s refusal to allow LGA to tack weld end caps on pipes during construction, the panel first examined whether the refusal amounted to a “Company Delay” under the Agreement. The panel concluded that the evidence showed that LGA had a number of alternatives available to mitigate the effect of Aguaytia’s refusal to allow tack welds and that LGA had failed to show that there was a causal connection between Aguaytia’s “improper refusal ... and a specific amount of delay later in the cleaning and testing process.” The panel found no Company Delay as defined in section 13.01 of the Agreement. The panel went on to note that, in addition to the inability to show a “Company Delay,” LGA had not shown the prerequisites to a total time claim, citing federal cases. However, the panel did not deny this delay claim by manifestly disregarding the New York law of concurrent delay. Rather, the panel based its denial on the conclusion that LGA had not made the necessary showing under the contractual definition of “Company Delay.”
LGA also challenges the panel’s rejection of the claim that Aguaytia had improperly rejected test results as based on a “total time” theory. The panel’s dis
*610
cussion states that “LGA approached the issue as a total time claim”; the panel concluded that LGA had not met the requirements. (Docket Entry No. 36, Ex. A, p. 11). In one of its briefs in support of its petition, LGA stated that “[assuming without conceding that LGA employed a ‘total time analysis’, New York courts permit the use of the ‘total cost method’ where it is ‘prohibitively difficult or speculative to follow the ordinary measures of damages.’” (Docket Entry No. 25, p. 20). The panel rejected LGA’s total time basis for claiming that Aguaytia’s test result rejection had delayed LGA’s work by fifty-one days. The panel went on to analyze the evidence showing problems with LGA’s testing and with its work on the pipeline, which caused problematic test results. The panel concluded, again relying on the contractual definition of “Company Delay” in section 13.01 and the evidence in the record, that LGA had not shown a Company Delay that would trigger application of the concurrent delay rule. The panel did not apply a federal law “total time” standard, in manifest disregard of New York law on concurrent delay.
LGA’s citation to New York cases applying the doctrine of concurrent delay do not support its argument that the panel manifestly disregarded New York law. In
Mosler Safe Co. v. Maiden Lane Safe Deposit Co.,
199 N.Y. 479 , 93 N.E. 81 (1910), the court held that if an owner or the architect acts so as to delay a contractor’s work, the contractual provision for liquidated damages for delay is waived and cannot be renewed. The court relied on the general rule that damages for delays caused by mutual fault cannot be apportioned unless the contract permits substitution of another date for completion.
Id.
at 83-84. The court explained that while a liquidated damages clause does not have “the harshness of a penalty, it is, nevertheless, in its nature, such that its enforcement, where the party claiming the right to enforce has, in part, been the cause of delay, would be unjust.”
Id.
at 83. In
XLO Concrete Corp. v. John T. Brady & Co.,
104 A.D.2d 181 , 482 N.Y.S.2d 476 (N.Y.App.Div.1984), the court described
Mosler Safe
as “clearly addressing a situation where the liquidated damages clause sought by the owner exceeded its actual delay damages and the court was concerned with the injustice of permitting the owner to reap the benefit of the liquidated damage clause.”
Id.
at 480. This case does not present such a situation.
In
Halligan ,
the court vacated an award based on manifest disregard of the law. The plaintiff had presented “overwhelming” and “strong” evidence of age discrimination, but the arbitrator denied the claim without explanation. 148 F.3d at 203-04 . The court acknowledged that arbitrators are not required to explain their awards, but stated that when a court is already inclined to hold that a panel manifestly disregarded the law, the failure to explain may be taken into account to support that result, especially if all imaginable explanations would “strain credulity.”
Id.
at 204 . In this case, unlike
Halligan ,
the arbitration panel painstakingly explained its reasons for its decisions in awarding liquidated damages for the delays. The record in this case presents neither overwhelming evidence against the result reached nor an absence of explanation for that result.
An award does not result from “manifest disregard” of the law merely because of error in understanding or applying the law. An award may not be vacated on this basis unless the arbitrators manifestly acted contrary to the applicable law, resulting in significant injustice.
Williams,
197 F.3d at 762 . This court finds that LGA has failed to carry its burden to show that the panel’s decisions granting liquidated damages and rejecting
*611
LGA’s claims of Company Delays resulted from “manifest disregard” of New York law on concurrent delay, under either the Fifth or Second Circuit standard. For the same reasons, this court finds that LGA failed to allege or present facts showing that the panel’s award was arbitrary and capricious.
4
This court DENIES LGA’s motion to vacate, modify, or amend the liquidated damages award on the basis of manifest disregard of the law of concurrent delay.
B. Indefiniteness of Contract Terms
LGA argues that it should not be held liable for liquidated damages for its delay in obtaining the First and Second Completion Deadlines because the contract terms used to measure compliance with the Deadlines were so indefinite as to be unenforceable. LGA argues that the panel manifestly disregarded New York law making vague and indefinite contract terms unenforceable.
Section 1.10 of the Agreement required LGA to perform certain tests “in accordance with Section 4.05” in order to achieve the First Completion and Second Completion Dates.
5
Section 4.05 of the Agreement states that all performance tests must be “conducted and measured as provided in Schedule 4.05,” which, in turn, sets out the conditions for the initial performance tests required to achieve the First and Second Completion Dates. The panel imposed liquidated damages for LGA’s delay in achieving these dates, due to problems with the initial performance tests. The panel found that although LGA conducted initial performance tests on the gas plant in late December 1997, in March 1998, and in early May 1998, “[p]rior to the tests that were run on May 20-22, 1998, the requirements of the Agreement regarding First Completion were not met.” The panel found that before that date, LGA did not do some of the tests and did others improperly. The panel held LGA responsible for liquidated damages for delays to May 22, 1998 for First Completion and May 22, 1998 for Second Completion.
LGA first argues that under the Agreement, it was not obligated to meet “performance guarantees” required for “complete
*612
operation” in order to meet the First and Second Completion requirements. The panel’s decision is consistent with LGA’s position. In its decision, the panel acknowledged that LGA did not have to meet the performance guarantees contained in Section 2.06 of the Agreement to meet the First and Second Completion requirements. However, according to the panel, LGA did have to meet the protocols set out in Schedule 4.05 of the Agreement. (Docket Entry No. 86, Ex. A, p. 9). The panel concluded that LGA had failed to perform some of the tests necessary to achieve the First and Second Completions and had performed others improperly by failing to comply with the protocols described in Schedule 4.05.
LGA argues that the Section 4.05 protocols it failed to satisfy are too indefinite to be enforceable under New York law. LGA focuses on the provision in Schedule 4.05, requiring the contractor to establish inlet stream rates and conditions “as nearly as possible” to the design conditions and to adjust plant operation conditions to conform “as nearly as possible” to the design conditions. (Docket Entry No. 25, p. 30; Section 4.05(i)). LGA argues that these provisions are analogous to contract clauses “purporting to obligate a party to use its ‘best efforts’ in achieving an end,” which New York courts have found unenforceable for indefiniteness.
(Id.,
p. 31)(citing
Strauss Paper Co., Inc. v. RSA Exec. Search, Inc.,
260 A.D.2d 570 , 688 N.Y.S.2d 641, 642-43 (N.Y.App.Div.1999)).
LGA’s argument is not supported by the record before the arbitration panel or . the basis of its decision. Even assuming that the phrase “as nearly as possible” is similar to the phrases in the cases cited, the panel’s decision did not turn on LGA’s failure to conduct tests “as nearly as possible” to the design conditions.
6
The panel found that LGA failed to perform a Propane Recovery Test, which section 1.01 of the Agreement specifically required for First Completion. The panel also found that LGA had failed to run the tests for forty-eight hours, a definite part of the Schedule 4.05 protocols that LGA had to satisfy. The panel found that under the contract, LGA could not attain Second Completion until it completed the tests for the Fractionation Plant, as required in Section 1.01 of the Agreement. Again, the panel did not rest its conclusion on LGA’s failure to comply with criteria LGA faults as vague and indefinite.
LGA’s final challenge to this aspect of the award is that the panel’s findings are contrary to the “essence” of the parties’ agreement. LGA argues that the forty-eight hour requirement was part of a performance guarantee set out in Section 2.06 of the Agreement, not a required protocol under Section and Schedule 4.05. LGA points to deposition testimony from an Aguaytia witness, who explained that the business purpose for the First Completion Date in the Agreement was that Aguaytia “needed to have a facility that was capable of running and supplying gas to our power plant.” (Docket Entry No. 25, p. 32). LGA argues that it provided usable gas to the plant by the First Completion deadline, meeting the purpose of the contractual requirement.
The award must be sustained if the arbitrator’s decision “draws its essence” from the Agreement.
Executone,
26 F.3d at 1320 (quoting
United Paper-
*613
workers Int’l Union v. Misco, Inc.,
484 U.S. 29, 36 , 108 S.Ct. 364 , 98 L.Ed.2d 286 (1987)). The Fifth Circuit has stated that an award fails the “essence” test only when it is “so unfounded in reason and fact, so unconnected with the wording and purpose of the [agreement] as to ‘manifest an infidelity to the obligation of an arbitrator.’ ”
Id
at 1325 (quoting
Brotherhood of R.R. Trainmen v. Central
Co.
Ry.,
415 F.2d 403, 412 (5th Cir.1969), quoting
United Steelworkers v. Enterprise Wheel & Car Corp.,
363 U.S. 593, 597 , 80 S.Ct. 1358 , 4 L.Ed.2d 1424 (1960)). LGA is correct that Section 2.06 of the Agreement, pertaining to performance guarantees, states that LGA must run the tests for two consecutive twenty-four hour periods. Section 1.01 states that LGA did not have to satisfy the performance guarantees in the performance tests necessary to achieve the First and Second Completion Dates. However, LGA did have to conduct the tests under Section 4.05 and the Schedule 4.05 protocols. Schedule 4.05 also refers to the “48 hour performance test” and the “48 hours test period.” (Agreement, Section 4.05(h) and (j)). Aguaytia notes that LGA’s start-up supervisor, Ed Munoz, “conceded at the Phase 1 hearing the necessity that LGA run the performance test for 48 hours.” (Docket Entry No. 19, p. 24).
7
Section 4.05 could reasonably be interpreted to impose a forty-eight hour testing requirement for the tests that were clearly necessary to achieve the First and Second Completion Dates. LGA has not shown that the panel’s interpretation was so unreasonable as to be contrary to the “essence” of the parties’ agreement.
8
The panel members interpreted the Agreement and the evidence and unanimously determined that LGA did not meet the requirements for either the First or Second Completion Dates until May 22, 1998. The panel used that date in assessing liquidated damages for delay under the Agreement. LGA has failed to allege or present facts showing that the panel’s interpretation of the contract requirements for achieving the First or Second Completion Dates manifestly disregarded New York law, that upholding that interpretation would result in significant injustice, or that the result fails to draw its essence from the contract.
Williams,
197 F.3d at 762 . LGA also has failed to show that the panel’s interpretation of the Agreement
*614
was not “rationally inferable from the letter or the purpose of the underlying agreement,” so as to be arbitrary and capricious.
Executone,
26 F.3d at 1320 .
This court DENIES LGA’s motion to vacate, modify, or amend the liquidated damages award on the basis of indefinite contract terms or the panel’s interpretation of the contractual requirements for the First and Second Completion Dates.
IV. The Award of Carbon Dioxide Corrosion Damages and New York Law on the Basis of Design
LGA asserts that the panel acted in manifest disregard of New York law when it awarded almost $1.6 million to Aguaytia for work necessary to remedy carbon dioxide corrosion in the project pipes and plants. (Docket Entry No. 36, p. 25). The corrosion was caused by the combination of free water in the production facility and carbon dioxide in the produced gas.
9
LGA argues that it designed and constructed the pipes on the “Basis of Design” Aguaytia furnished in Schedule 2.06 of the Agreement. LGA relies on the following description of the water content in the pipes: “Sat... LB/MMSCF.” LGA argues that this description “effectively caused LGA to design pipelines ... for saturated natural gas with no free water consistent with industry standards.” (Docket Entry No. 36, p. 26). LGA argues that the panel manifestly disregarded New York law that entitled LGA to design and construct facilities consistent with Aguaytia’s “Basis of Design.”
LGA cites
Young Fehlhaber Pile Co. v. State,
265 A.D. 61 , 37 N.Y.S.2d 928 (N.Y.App. Div.—3d Dept.1942) for the general rule that a contract bidder may “properly rely upon the clear and unequivocal information contained in the plans, otherwise they would serve no useful purpose.”
Id.
at 929. In
Young Fehlhaber,
the court stated that plans “should reasonably depict the work to be done and where they are definite and plain the contractor is entitled to rely upon them.”
Id.
at 930. In
Young Fehlhaber,
the court held that the State could not recover damages for the costs of reconstructing a bridge because the State had provided the contractor with plans showing the river depth to be four feet shallower than the actual depth. The court found that the State knew its plans to be inaccurate and that the State had committed fraud in its representations to the project bidders.
Id.
at 929.
In this case, the panel did not disregard New York law on the basis of design. The panel analyzed the parties’ contentions and evidence as to whether Aguaytia’s statements in Schedule 2.06 of the Agreement were “sufficient to alert [LGA] to the possibility of corrosion within the pipelines that it was designing.” (Docket Entry No. 36, Ex. A, p. 17). The parties agree that “Sat... LB/MMSCF” indicated that the gas would be saturated. (Docket Entry No. 21, Ex. 18, p. 8). During the arbitration, both parties presented evidence as to the meaning of “saturated” in Schedule 2.06 and whether that description necessarily implied the absence of free water in the system.
LGA asserts that it presented “competent, unrebutted expert testimony” to the
*615
panel that the specification in the Agreement allowed LGA to assume the absence of free water in the pipe system. LGA presented testimony from its expert, William Krause, that Schedule 2.06’s specification of the gas stream at the Gas Plant inlet as “Sat.” necessarily meant that there would be no “free water” at the plant fence. However, Aguaytia presented evidence disputing Krause’s testimony. Aguaytia’s witnesses, including James McHaney and Tony Hines, presented evidence that the term “Sat.” did not address or exclude the probability of free water in the gas stream. (Docket Entry No. 21, Ex. 18, p. 8). These witnesses testified that the information available to LGA, including the information as to the composition of the gas stream, was sufficient to inform LGA that there was a likelihood of carbon dioxide corrosion in the pipes; that LGA had conducted a corrosion analysis that was inadequate for the gas plant piping and equipment; and that LGA had not included corrosion allowance or inhibitors for the gather lines, resulting in serious damage from corrosion.
The panel considered the conflicting expert testimony and the exhibits. The panel concluded that the statements and information in Schedule 2.06 of the Agreement, with other information available to LGA, told LGA that both carbon dioxide and water were present in the gas stream and that changes would occur in the temperature of the gas and in the gas pressure in the pipeline from the wellhead to the Gas Plant that would likely result in water condensation. The panel concluded that LGA had information from Aguaytia to disclose that carbon dioxide could be present and could cause corrosion in the pipelines LGA was designing. (Docket Entry No. 36, Ex. A, p. 17). The panel rejected LGA’s argument that the statement that the gas would be “Sat.” necessarily meant that there would be no free water in the pipes.
10
That decision is supported by evidence in the record.
The record supports the panel’s finding that applying New York law on the basis of design to the Agreement specification at issue did not permit LGA to assume the absence of free water in the system. The panel concluded that the information Aguaytia provided was sufficient to notify LGA of the possibility of corrosion if it did not take steps to address the presence of carbon dioxide and water in the system. (Docket Entry No. 36, Ex. A, p. 17).
During Phase 2, LGA argued that the measure of corrosion damages should be limited to $432,000.00, the cost of repairing the corrosion in the pipes according to LGA’s proposed method. The panel again heard expert testimony from both sides and determined that Aguaytia’s proposed method for addressing the corrosion damage, while more costly, “can be considered prudent for the safe operation of the plant” and was “appropriate, prudent, and reasonable from a cost perspective.” (Docket Entry No. 36, Ex. B, p. 33, p. 34). In the Final Award, the panel reiterated that it had determined that, contrary to LGA’s argument, “Schedule 2.06 did not relieve LGA of responsibility for addressing the presence of C02 in the gas.”
{Id.,
p. 34 n. 7).
The panel explained its conclusion as based on its interpretation of the Agreement, the expert testimony, and the other
*616
evidence submitted. This court finds that the panel’s conclusions did not manifestly disregard New York law on the basis of design. Instead, the panel based its conclusion on an analysis of the record evidence as to the design information Aguay-tia provided to LGA to use in designing and constructing the plant and pipelines. This court DENIES LGA’s request to vacate, modify, or amend the portion of the award relating to damages for carbon dioxide corrosion.
Y. The Panel’s Evidentiary Ruling: The Award for Pipe Credit
LGA asserts that the panel wrongfully excluded evidence of what the parties intended Section 5.05(b) of the Agreement to mean, “in violation of the Inter-American Convention, Article 5(l)(b), the New York Convention, the FAA, 9 U.S.C. § 10 (a)(3), and in violation of LGA’s due process rights.” (Docket Entry No. 36, p. 32). LGA argues that the panel’s exclusion of this evidence resulted in a wrongful award of $1,014,000.00.
(Id.).
Aguaytia responds that the panel properly excluded the evidence and that its ruling cannot form a basis for vacating or modifying the award. (Docket Entry No. 19, pp. 25-29).
Section 5.05(b) of the Agreement states: The maximum amount of adjustment to the Contract Price that shall occur as a result of differences in pipe length is an upward or downward adjustment of U.S. $500,000, regardless of the actual required length of pipe installed.
In the arbitration, and in this court, LGA asserted that Section 5.05(b) imposed a $500,000.00 limit on the amount that Aguaytia could receive as credit for the cost of pipe and for pipe installation services that LGA had never purchased or performed. In the Summary Disposition, the panel concluded that the $500,000 cap applied only to credit for amounts Aguay-tia had paid for installing pipe that was not used. The panel concluded that the $500,000 cap did not apply to limit the credit Aguaytia could receive for amounts it had paid LGA for pipe material that LGA had not purchased. The panel stated as follows:
LGA’s argument is plausible only if read in isolation. Rather, Section 5.05(b) and Schedule 5.05(b)
11
, which is specifically referenced in Section 5.05(b) make it plain that the cost of the pipe material itself and the cost of the installation are treated separately. Section 5.05(b) focuses on the cost of installation, leaving the matter of material cost adjustment to the text at the top of Schedule 5.05(B), namely: if the extra pipe was ordered, it is to be delivered to [Aguay-tia] and LGA is to be paid for the pipe; if the pipe length is adjusted before the pipe was ordered, the price for the pipe material will be “the actual invoice and amount of the pipe, coating and freight.” LGA’s isolated reading of the last sentence of Section 5.5(b) [sic] is not only askew from New York law, which requires that the provisions of an agreement are to be read in the context of the entire agreement,
12
but makes no practical sense. Imagine, for example, LGA being required to absorb the material cost associated with a huge increase in the length of the pipeline. That result would be as inequitable as a result that
*617
pays LGA for pipe that it never ordered or for which it never paid. Yet, that is precisely the result that would obtain if we were to read the last sentence of Section 5.05(b) as LGA now urges.
Based on the entirety of Section 5.05(b) and Schedule 5.05(B), the Arbitral Tribunal declares:
The $500,000 limitation in Section 5.05(b) of the Agreement does not preclude [Aguaytia’s] claim for a price adjustment for the pipe material as a result of a reduction in the quantity of pipe required for the Project.
(Docket Entry No. 21, Aguaytia Ex. 6, pp. 13-14).
LGA submitted affidavits from one of its employees who had negotiated the Agreement with Aguaytia. In the affidavits, the witness stated that during negotiations, the parties discussed the $500,000 cap as applying to the cost of both procuring pipe material and installing the pipe. The panel struck these portions of the affidavits in procedural rulings issued in February 2000. The panel excluded the evidence under rulings applying New York law included in the Summary Disposition: “before a tribunal may receive extrinsic evidence as an aid to the interpretation of an agreement, the tribunal must conclude that the provision at issue is ambiguous. And, under New York law, a provision is ambiguous if it is susceptible to at least two reasonable, competing constructions.” (Docket Entry No. 21, Ex. 6, p. 3). At the hearing, the panel followed this approach and precluded LGA from cross-examining one of Aguaytia’s witnesses on the $500,000 cap.
LGA requested the panel to reconsider its ruling on the meaning of Section 5.05(b). In the Interim Award, the panel denied the motion for reconsideration, stating that “[w]hile the textual argument made by LGA is consistent with a literal reading of the particular sentence in Section 5.05(b), the result is at odds with the structure and intent of the Agreement read in its entirety, as New York law requires.” (Docket Entry No. 36, Ex. A, p. 18). LGA argues that the panel’s two rulings are inconsistent: by stating that LGA’s interpretation was consistent with a “literal reading” of Section 5.05(b), the panel acknowledged that Section 5.05(b) could be given two different interpretations, making it ambiguous and making external evidence of the drafters’ intent admissible. LGA alleges that the panel’s evidentiary rulings excluding the affidavits and the cross-examination are a refusal to hear evidence “pertinent and material to the controversy,” a statutory ground for vacating the arbitration award.
The Federal Arbitration Act permits a court to vacate an award if “the arbitrators were guilty of misconduct in ... refusing to hear evidence pertinent and material to the controversy[,] or of any other misbehavior by which the rights of the party have been prejudiced.” 9 U.S.C. § 10 (a)(3). The New York Convention provides that an award is unenforceable if “[t]he party against whom the award is invoked was not given proper notice of the appointment of the arbitrator or the arbitration proceedings or was otherwise unable to present his case.” New York Convention, Art. V(l)(b). The provision as to the inability to present the case applies to an arbitrator’s evidentiary rulings.
See Iran Aircraft Indus. v. Avco Corp.,
980 F.2d 141, 146 (2d Cir.1992).
The arbitrator is the judge of the relevance and admissibility of the evidence presented in an arbitration proceeding.
Cordis Corp. v. C.R. Bard, Inc.,
1993 WL 723844 , * 3 (S.D.Tex. Mar.11, 1993)(citing
Hoteles Condado Beach, La Concha & Convention Ctr. v. Union De Tronquistas Local 901,
763 F.2d 34, 39 (1st Cir.1985));
see also Fairchild & Co., Inc.
*618
v. Richmond, Fredericksburg & Potomac R.R. Co.,
516 F.Supp. 1305, 1314 (D.D.C.1981)(“[I]t should be remembered that arbitrators are charged with the duty of determining what evidence is relevant and what is irrelevant.”)(citing
Petroleum Transport, Ltd. v. Yacimientos Petroliferos Fiscales,
419 F.Supp. 1233, 1235 (S.D.N.Y.1976),
aff'd,
556 F.2d 558 (2d Cir.1977)). An arbitration award will be set aside only if the exclusion of the contested evidence prevented the parties from receiving a fundamentally fair hearing.
Gulf Coast Indus. Workers Union v. Exxon Co., USA,
70 F.3d 847, 850 (5th Cir.1995);
see also Tempo Shain Corp. v. Bertek, Inc.,
120 F.3d 16 (2d Cir.1997)(“Our review is restricted to determining whether the procedure was fundamentally fair.”) (citation omitted);
Cordis,
1993 WL 723844 at * 3 (citing
Totem Marine Tug & Barge, Inc. v. N. Am. Towing, Inc.,
607 F.2d 649, 651 (5th Cir.1979));
Fairchild & Co.,
516 F.Supp. at 1314 (“The error which would constitute misconduct must not simply be an error of law, but one which so affects the rights of a party that it may be said to deprive him of a fair hearing.”)(citing
Newark Stereotypers’ Union No. 18 v. Newark Morning Ledger Co.,
397 F.2d 594, 599 (3d Cir.1968)).
In
Cordis ,
the plaintiff moved to yacate an arbitrator’s award for patent infringement. The plaintiff argued that by refusing to admit evidence of tests on the allegedly infringing equipment, the arbitrator had refused to hear material evidence. Before ruling on admissibility of the evidence, the arbitrator heard arguments from both parties as to the relevance of the tests. The arbitrator concluded that the testing evidence was, in part, irrelevant to the issues presented in the arbitration and, in part, cumulative of other evidence. The district court rejected the plaintiffs challenge to these rulings, holding that “neither the arbitrator’s refusal to admit irrelevant evidence, nor his refusal to admit cumulative evidence prevented [plaintiff] from receiving a fundamentally fair hearing.”
Cordis,
1993 WL 723844 at *3.
In this case, as in
Cordis ,
the panel heard the parties’ arguments as to the meaning of the contract terms and the admissibility of evidence describing the parties’ understanding of the contract terms during the negotiation. The panel considered LGA’s arguments a second time in ruling on the affidavits and a third time in ruling on the motion for reconsideration. The panel consistently concluded that Section 5.05(b) of the Agreement unambiguously permitted Aguaytia to seek credit for a reduction in pipe material used in the project, but limited any claim for credit for undelivered pipe installation services to $500,000.00. An unambiguous contract provision may not be contradicted or varied by external evidence of the parties’ contrary or different intent when the agreement was entered.
Wayland Inv. Fund LLC v. Millenium Seacarriers, Inc.,
111 F.Supp.2d 450, 454 (S.D.N.Y.2000)(citing
W.W.W. Assocs., Inc. v. Giancontieri,
77 N.Y.2d 157 , 565 N.Y.S.2d 440 , 566 N.E.2d 639, 642 (1990)).
LGA cites cases in which courts vacated arbitration awards because evidentiary rulings deprived a party of a fair hearing. In
Gulf Coast,
the Fifth Circuit held that an award against an employer should be vacated because the arbitrator had refused to consider a test that showed that a substance found in the discharged employee’s ear was marijuana. 70 F.3d at 850 . The court found that the panel had misled the employer’s counsel so that he did not submit the testing evidence as a business record.
Id.
at 849 . Unlike
Gulf Coast,
there is no allegation in this case that the panel “tricked” LGA.
See also Iran Aircraft,
980 F.2d at 146 (vacating award under the New York Convention where one arbitra
*619
tor had advised plaintiff to submit audit listing individual invoices rather than the invoices themselves and panel later ruled against plaintiff because it had not submitted individual invoices).
Unlike in
Gulf Coast,
in the present case, the panel’s ruling that Section 5.05(b) of the Agreement was unambiguous did not turn on the presence or absence of the excluded evidence. Contrary to LGA’s argument, the panel’s decisions consistently read Section 5.05(b), together with Schedule 5.05(B), as having one meaning. The panel’s decisions recognize that if read in isolation, the sentence LGA cited in Section 5.05(b) could support the result LGA advocated, but that if read with Schedule 5.05(B), the provision was susceptible to only one reasonable construction. The panel consistently concluded that the provision was unambiguous, without referring to the parties’ subjective intent or understandings in entering the Agreement, but rather to the objective intent revealed by the terms and structure of the Agreement itself. The panel did not reach the question of the parties’ subjective intent, which was the subject of the evidence LGA sought to introduce.
In
Tempo Shain,
another case LGA cites, the court vacated an award under section 10(a)(3) of the Federal Arbitration Act because the panel did not continue the proceeding to hear the testimony of a key witness who was temporarily unavailable. The arbitration panel implied in its ruling that it believed his testimony would be cumulative.
Tempo Shain,
120 F.3d at 19-20 . The district court confirmed the award, concluding that the panel correctly understood that it was required to decide whether the testimony would “add to” the panel’s knowledge or would be merely cumulative.
Id.
at 19 . The Second Circuit reversed, finding that there was no reasonable basis for the panel to find the evidence cumulative and noting that the panel had not explained the basis for concluding that the evidence would be merely cumulative. The Second Circuit held that the award should be vacated because the panel’s refusal to continue the arbitration hearing amounted to fundamental unfairness and misconduct under section 10(a)(3).
Id.
at 20 .
Tempo Shain
teaches that an arbitration panel’s understanding of the evidentiary question it must decide is not sufficient to uphold the panel’s decision; the panel’s answer to the question must find support in the record.
Id.
at 20 . In the present case, the panel found that Section 5.05(b) of the Agreement could reasonably be given only one interpretation, when read in the context of the entire Agreement, rather than by isolating a single sentence. The panel explained how the single sentence LGA relied upon fit into the rest of Section 5.05(b) and into the Agreement as a whole. The record offers support for the panel’s interpretation of the Agreement as unambiguous and its conclusion that external evidence of the parties’ intent was inadmissible to contradict the language of the Agreement.
LGA has faded to show that the panel’s exclusion of the evidence as to the parties’ intent in agreeing to Section 5.05(b) prevented LGA from receiving a fundamentally fair hearing. This court DENIES LGA’s motion to vacate, modify, or amend the section of the award relating to the pipe credit under 9 U.S.C. § 10 (a)(3).
VI. The Claim of Arbitrator Partiality, Nondisclosure, and Misconduct
The arbitration panel consisted of three arbitrators, one appointed by each party, and a chairman, appointed by the International Chamber of Commerce. The Federal Arbitration Act permits a district court to vacate an award for “evident partiality or corruption in the arbitrators.” 9 U.S.C.
*620
§ 10(a)(2). LGA asserts “evident partiality” as grounds for vacating the award, including inadequate disclosure of potential conflicts of interest; actual bias; and misconduct by Michael Jaffe, the arbitrator Aguaytia appointed. (Docket Entry No. 30, p. 3).
Jaffe is a partner in the law firm of Arent Fox Kintner Plotkin & Kahn, PLLC (“Arent Fox”). When appointed to the panel in late 1998, Jaffe made the following disclosure to the parties under Article 7 of the ICC Rules of Arbitration:
While I have never done any work for Aguaytia Energy del Peru or any company associated with it, I am advised that a former partner of mine at Arent Fox, Ms. Coralyn Goode, may have done work for the entity or may have supervised an associate at Arent Fox in doing some work for that entity. So far as I am aware, there has been no work done at Arent Fox for Aguaytia Energy del Peru since Ms. Goode resigned from the firm to relocate to Squire Sanders & Dempsey, LLP. I am advised that El Paso Energy has a minority interest in Aguaytia Energy del Peru and that Ms. Goode did substantial work for El Paso Energy while at Arent Fox. Lastly, I am advised by my partners, Carl Valenstein and Hendrik Gordenker, that since Ms. Goode’s departure a limited representation of El Paso Energy has continued with respect to matters wholly unrelated to Aguaytia Energy del Peru or its operations or El Paso Energy’s investment in Aguaytia Energy del Peru.
(Docket Entry No. 21, Ex. 3).
LGA did not request further information from Jaffe after receiving this disclosure. During the Phase 1 hearings, LGA did not object to Jaffe or to his conduct in the proceedings. After the panel issued its draft interim award on July 11, 2000, LGA filed a motion with the ICC to challenge and replace Jaffe, to stay the proceedings, and to vacate the award. (Docket Entry No. 21, Ex. 9). LGA asserted that Jaffe had acted inappropriately during the proceedings by interrupting witnesses, interjecting his own opinions, advocating Aguaytia’s position, and influencing other members of the panel.
(Id.).
In response, the arbitration panel sent a letter to the ICC opposing LGA’s challenge to the draft interim award. (Docket Entry No. 21, Ex. 14). The arbitrators noted that LGA had made no objection to the conduct of any arbitrator during the proceedings.
(Id.,
p. 1). The arbitrators stated that “[a]ll three members of the Tribunal participated in every aspect of the proceedings.”
(Id.,
p. 2). The arbitrators denied that Jaffe had exerted any improper influence. The arbitrators stated that each member of the panel considered the evidence and that the panel’s decision as to every issue was unanimous. The letter described the award as based on “extensive independent consideration by all three members of the Tribunal as well as lengthy discussions among the Tribunal.”
(Id.).
Finally, the arbitrators denied that Jaffe had acted improperly in the proceedings. The arbitrators stated that Jaffe had asked questions and made comments solely to help himself and the other panel members understand the evidence and issues.
(Id.,
pp. 3-4).
On July 20, 2000, LGA sent a, letter to the ICC, asserting that Jaffe had failed to disclose the relationship between his law firm, Arent Fox, and one of the parties to the arbitration. The letter concluded that “[Mr. Jaffe’s disclosure] did not reveal that he and his law firm actually worked on this project.” (Docket Entry No. 21, Ex. 26, quoting July 20, 2000 letter at p. 5).
Jaffe sent a letter to the ICC in response. In the letter, Jaffe explained that before his nomination to the panel by Aguaytia in November 1998, he “had no involvement whatsoever with the Project
*621
and, indeed, had done no work of any kind for [Aguaytia] or El Paso Energy, the entity for which Arent Fox, through my former partner, Ms. Coralyn Goode, had in the past provided legal counsel.”
(Id.,
p. 1). Jaffe stated that since his appointment, his “only involvement with the Project has been in my service as an arbitrator.”
(Id.).
Jaffe stated that while at Arent Fox, Goode, who had left the firm prior to Jaffe’s appointment in 1998, “had acted for El Paso Energy, an investor in the Project ...” and “had been invited to a Management Committee meeting in March 1996 in her capacity as counsel for El Paso Energy.”
(Id.,
p. 2). On July 26, 2000, the ICC informed the parties that it had rejected LGA’s challenge and decided not to replace the panel. (Docket Entry No. 21, Ex. 9).
In this court, LGA asserts that after the ICC ruled, LGA discovered “new evidence” of the relationship between Arent Fox and El Paso Energy. In 1995, John Hushon, who had been a partner at Arent Fox, became president of El Paso Energy. Hushon had retained Goode, then at Arent Fox, in early 1996. Some of the work Goode did or supervised while at Arent Fox included work on the financing for the project, on behalf of El Paso Energy. Some of the Arent Fox work included lobbying for legislation to reauthorize the Overseas Private Investment Corp., which later provided certain insurance to the project. (Docket Entry No. 30, pp. 5-6). LGA submits clips of news articles and items appearing on Arent Fox’s web page.
13
LGA asserts that Jaffe failed to make a full disclosure of his firm’s connection with the project and with John Hushon at El Paso Energy International Company. (Docket Entry No. 30). LGA asserts that Jaffe’s inadequate initial disclosure of the connections among Jaffe, his law firm, his law firm’s clients, and the project provide a sufficient basis for vacating the entire award. Alternatively, LGA asks for discovery directed to “Arent Fox, Aguaytia, and Aguaytia’s investor El Paso Energy International Company (or its parent or affiliates)” to obtain “documentation of the full extent of Mr. Jaffe’s firm’s involvement with Aguaytia’s investors and with the Aguaytia Project itself.”
(Id.).
Aguaytia opposes LGA’s motion for discovery and argues that as a matter of law, no basis to vacate for arbitrator bias, partiality, or misconduct is present. (Docket Entry No. 34). Aguaytia emphasizes that
*622
the undisputed facts show that Jaffe “has never worked for Aguaytia or any associated company such as El Paso” and that Arent Fox “has had no undisclosed contact with either Aguaytia or El Paso since one of its partners left the firm, prior to Mr. Jaffe’s appointment as an arbitrator.” Aguaytia argues that LGA has not met its burden to show a basis for vacating the award due to Jaffe’s failure to make an adequate disclosure or his partiality, or to show a need for discovery. In the alternative, Aguaytia asserts that LGA waived any objection by failing to challenge Jaffe when he made the initial disclosure of the connection between Arent Fox, El Paso Energy, and Aguaytia, and by waiting until after the award to raise the issue for the first time.
Each of these contentions is considered below.
A. The Standards for Disclosure and Evident Partiality
The Second Circuit has described the balance that must be struck between encouraging disclosure and vacating awards for nondisclosure:
There is an obvious possibility, alluded to by Justice White in
Commonwealth Coatings
that ‘a suspicious or disgruntled party can seize’ upon an undisclosed relationship ‘as a pretext for invalidating the award.’ 393 U.S. at 151, 89 S.Ct. 337 . Courts are usually reluctant to impugn the decisions of a jury because of claims of subsequently discovered bias ... and challenges to a judge’s impartiality are typically ruled untimely when the complaining party delays an objection past the point at which he is deemed on notice of potentially disqualifying circumstances. Surely, even greater caution is justified when the decision to be set aside is the product of the theoretically informal, speedy, and inexpensive process of arbitration, freely chosen by the parties. Moreover, a principal attraction of arbitration is the expertise of those who decide the controversy. Expertise in an industry is accompanied by exposure, in ways large and small, to those engaged in it, and the dividing line between innocuous and suspect relationships is not always easy to draw. But as Justice White recognized, an arbitrator ‘cannot be expected to provide the parties with his complete and unexpurgated business biography.’ 393 U.S. at 151 , 89 S.Ct. 337 . The very intimacy of the group from which specialized arbitrators are chosen suggests that the parties can justifiably be held to know at least some kinds of basic information about an arbitrator’s personal and business connections.
Andros Compania Maritima, S.A. v. Marc Rich & Co., A.G.,
579 F.2d 691, 700-01 (2d Cir.1978)(other internal citations omitted).
In
Commonwealth Coatings Corp. v. Continental Cas. Co.,
393 U.S. 145 , 89 S.Ct. 337 , 21 L.Ed.2d 301 (1968), the Supreme Court vacated an award because of the arbitrator’s failure to disclose his prior connections with one of the parties. The arbitrator had not disclosed that he had served as a consultant for the party opposing the award and had received approximately $12,000 in fees over four to five years from that representation.
Id.
at 146, 89 S.Ct. 337 . The court described the dealings between the arbitrator and the party as “sporadic in that the arbitrator’s services were used only from time to time at irregular intervals, and there had been no dealings between them for about a year” but nonetheless “repeated and significant.” Some of the arbitrator’s undisclosed services were on the projects involved in the arbitration.
Id.
at 146, 89 S.Ct. 337 .
In
Andros Compania Maritima, S.A. v. Marc Rich & Co., A.G.,
579 F.2d 691, 702 (2d Cir.1978), the Second Circuit distinguished
Commonwealth Coatings, Andros
*623
involved an arbitration between a vessel charterer and owner. The charterer challenged the arbitration award, alleging that the arbitrator had failed to disclose his “close personal and professional relationship” with one of the principals of the firm that actually operated the vessel. The charterer did not accuse the arbitrator of bias or improper conduct, but only nondisclosure.
Andros,
579 F.2d at 696 . Documents submitted in the arbitration showed that the arbitrator had participated in arbitration panels with the principal. The principal submitted an affidavit stating that his relationship with the arbitrator was solely professional and not of a financial, business, or social nature.
Id.
The court noted that the record showed a very limited relationship between the arbitrator and the principal. The charterer had failed to allege or present facts showing that the principal had a direct financial stake in the outcome of the arbitration.
Id.
at 701 . The court denied the charterer’s request for discovery into the nature and extent of the arbitrator’s relationship with the principal and held that the charterer had failed to present “clear evidence of impropriety.”
Id.
B. The Claim of Inadequate Disclosure
In this case, in contrast to both
Commonwealth Coatings
and
Andros,
Jaffe himself did not perform any legal or other work for Aguaytia or for El Paso Energy, an investor in Aguaytia. Jaffe did disclose that his former partner, Coralyn Goode, had done legal work for El Paso Energy and for Aguaytia. Jaffe stated that Arent Fox had not done work for Aguaytia after Goode left the law firm, and while it had continued to do some limited work for El Paso Energy, the matters were unrelated to Aguaytia. The information that LGA subsequently either discovered or appreciated revealed that a former Arent Fox partner was the president of El Paso Energy; Goode’s representation of El Paso’s interest in Aguaytia included some involvement in the management committee on El Paso’s behalf; and Arent Fox had been involved in representing El Paso in issues relating to the Aguaytia project financing and insurance.
A timeline of the relevant events is helpful.
• 1969-present Jaffe worked at Arent Fox in Washington, D.C.
• 1995 John Hushon, a partner in the Arent Fox Washington, D.C. office, leaves Arent Fox and becomes president of El Paso Energy International Corporation.
• 1996 Hushon retains Arent Fox to represent El Paso on work relating to the Aguaytia project. Coralyn Goode is the partner who performs most of the work.
• March 1996 Goode is invited to attend meeting of the Aguaytia management committee in her capacity as counsel for El Paso Energy.
• July 1996 Project financing complete.
• November 1996 Arent Fox involved in lobbying for legislation to reauthorize OPIC, which later provides certain project insurance.
• After Fall 1996 and before November 1998
Coralyn Goode leaves Arent Fox to become a partner in Squire Sanders, LLP. Arent Fox ceases work on the Aguaytia project.
*624
Arent Fox continues limited representation of El Paso Energy, unrelated to Aguaytia or El Paso’s investment in the project.
• September 1998 Lummus files request for arbitration.
• November 1998 Jaffe submits initial disclosure.
• December 1998 Jaffe confirmed as arbitrator.
Jaffe disclosed that his former law partner, Coralyn Goode, had done and supervised “substantial work” for El Paso Energy while at Arent Fox, and that El Paso Energy had a “minority interest” in Aguaytia. Jaffe did not disclose the substance of Goode’s or Arent Fox’s work relating to the project. Jaffe did not disclose that a former partner of Arent Fox, Hushon, had become president of El Paso Energy in 1995. Jaffe did disclose that after Goode moved to a different law firm, Arent Fox continued to do some work for El Paso Energy, but unrelated to the Aguaytia or El Paso’s investment in it.
14
LGA challenges Jaffe’s failure to disclose the substance of the work Goode had done relating to the Aguaytia project or El Paso’s investment in the project, over two years before Jaffe was appointed as an arbitrator, and to disclose that Hushon had been a partner at Arent Fox until 1995, when he became president of El Paso Energy. Jaffe did disclose that Goode and Arent Fox may have performed legal work for Aguaytia and had performed “substantial work” for El Paso, which had an interest in Aguaytia. Jaffe investigated the firm’s involvement with El Paso after Goode’s departure, stating “I am advised by my partners, Carl Valenstein and Hen-drik Gordenker, that since Ms. Goode’s departure a limited representation of El Paso Energy has continued with respect to matters wholly unrelated to Aguaytia Energy del Peru or its operations or El Paso
*625
Energy’s investment in Aguaytia Energy del Peru.” (Docket Entry No. 4, Ex. 4).
Neither Hushon nor El Paso was a party to the arbitration. LGA has not alleged or presented facts showing that Hushon, Goode, or Jaffe had any relationship extending beyond having overlapping periods as partners in a law firm.
See Andros,
579 F.2d at 701 (noting that allegedly undisclosed relationship was purely professional, not financial or social). Jaffe stated that he “had done no work of any kind for [Aguaytia] or El Paso Energy .... ” (Docket Entry No. 21, Ex. No. 26, p. 1). Jaffe specifically disclosed that his law firm may have performed legal work for Aguaytia and had performed “substantial work” for an investor in Aguaytia. Although Jaffe did not disclose that the work had involved project financing ánd insurance, there is no suggestion that the arbitration concerned either of these areas. LGA’s allegations of nondisclosure, in light of the information that Jaffe did reveal, are insufficient to warrant vacatur on the basis that the undisclosed facts clearly evidence impropriety, a reasonable impression of bias, or evident partiality.
The Fourth Circuit faced somewhat analogous facts in
Peoples Sec. Life Ins. Co. v. Monumental Life Ins. Co.,
991 F.2d 141 (4th Cir.1993), and denied a challenge based on evident partiality or bias. In
Peoples,
the arbitrator had failed to disclose his law partner’s representation of one of the parties to the arbitration.
Id.
at 145 . The partner had signed and filed the complaint while working for a different firm; he had not brought the client with him to the arbitrator’s firm. In the present case, while Goode was at Arent Fox, she did “substantial work” representing El Paso Energy, including work relating to its interest in Aguaytia. Arent Fox had ceased to represent El Paso on matters related to Aguaytia years before Jaffe’s appointment. Like the arbitrator in
Peoples,
Jaffe himself had no involvement in any of the legal work relating to entities involved in the arbitration. Unlike the arbitrator in
Peoples,
Jaffe did disclose that his law firm and former partner had represented an investor in the entity involved in the arbitration and may have done work for the entity itself, ending approximately two years earlier. LGA has failed to allege that either the disclosed or undisclosed facts reveal partiality that is “ ‘direct, definite and capable of demonstration rather than remote, uncertain and speculative.’ ”
Peoples Sec. Life Ins. Co.,
991 F.2d at 146 (citing
Health Servs. Mgmt. Corp. v. Hughes,
975 F.2d 1253, 1264 (7th Cir.1992)(quoting
Florasynth v. Pickholz,
750 F.2d 171, 173-74 (2d Cir.1984))).
LGA did not object or request further Information when Jaffe made his disclosure.
See Bernstein Seawell & Kove v. W.E. Bosarge,
813 F.2d 726, 732 (5th Cir.1987)(rejecting evident partiality challenge and noting that the party “had the obligation to make his objection to the composition of the arbitration panel at the time of the hearing. By not doing so, [the party] waived his right to challenge the selection of the arbitrators.”). Aguaytia asserts waiver. LGA argues that it had insufficient information until just before the hearing on Phase 1 to realize that Goode had attended a management committee meeting at the project in March 1996 and did not learn until later that Arent Fox had been involved in lobbying for OPIC. This argument is problematic. Jaffe’s disclosure in November 1998 made it clear that Arent Fox and Goode had done work for an investor in Aguaytia, and may have done or supervised work for Aguaytia itself, but provided no details as to the specific substance of that work. The disclosure put LGA “on notice” of the circumstances they now allege are potentially disqualifying — that one of Jaffe’s law
*626
partners had done work for Aguaytia itself and “substantial work” for an investor in Aguaytia.
See Bosarge,
813 F.2d at 732 . However, even assuming that LGA did not waive its right to challenge the composition of the panel, this court finds that Jaffe’s alleged nondisclosure does not require vacatur.
C. The Request for Discovery
The parties dispute what standard governs LGA’s request for discovery. LGA asserts that it need only show that the requested discovery is “relevant and necessary ... to the determination of Mr. Jaffe’s bias and misconduct.” (Docket Entry No. 30, p. 7). Aguaytia responds that LGA must demonstrate “clear evidence of impropriety” before discovery is appropriate. (Docket Entry No. 34, p. 1).
LGA cites
Frere v. Orthofix, Inc.,
2000 WL 1789641 (S.D.N.Y. Dec.6, 2000). In
Frere ,
the district court stated that discovery in a post-arbitration judicial proceeding is available “only in limited circumstances, where relevant and necessary to the determination of an issue raised by [a motion to confirm or vacate an award].”
Id.
at *4 (citations omitted). In
Frere ,
however, the court was not confronted with an allegation of arbitrator bias. The court recognized that the more demanding “clear evidence of impropriety” standard applies specifically “to discovery inquiries directed at the arbitrator and only when the goal is to impugn the validity of the arbitrator’s decision.”
Id.
at * 5 (citing
Andros Compania Maritima, S.A. v. Marc Rich & Co., A.G.,
579 F.2d 691, 702 (2d Cir.1978)). The
Frere
court explained the standards for discovery, as follows:
“[I]n view of the narrowness of the grounds on which an arbitral award may be challenged, the need for discovery is typically not nearly as acute as in other civil lawsuits. Necessarily, then, the liberality that normally attends discovery in civil litigation is not appropriate in this context. In addition, any inquiry that is targeted at the arbitrator is particularly suspect, since the arbitrator’s coerced involvement in post-award litigation will inevitably intrude upon the arbitrator’s quasi-judicial function and discourage qualified individuals from offering their services as arbitrators.”
Id.
(providing examples)(internal citations omitted). The court continued:
In judging discovery requests in this context, the court must weigh the asserted need for hitherto undisclosed information and assess the impact of granting such discovery on the arbitral process. The inquiry is an entirely practical one, and is necessarily keyed to the specific issues raised by the party challenging the award and the degree to which those issues implicated factual questions that cannot be reliably resolved without some further disclosure.
Id.
at * 5 (citing
Sanko S.S. Co. v. Cook Indus.,
495 F.2d 1260, 1263 (2d Cir.1973);
National Hockey League Players Ass’n v. Bettman,
1994 WL 38130 , *2-7 (S.D.N.Y. Feb. 4, 1994)).
In applying this analytical framework, this court examines the specific issues LGA raises and the degree to which they implicate “factual questions that cannot be reliably resolved without some further disclosure,” to weigh the need for the additional information sought in discovery.
Id.
This approach applies whether the standard for discovery is “relevant and necessary” to a showing of bias, or predicated on a higher threshold showing of “clear evidence of impropriety.”
LGA cites cases in which courts have allowed discovery before evaluating a claim of arbitrator bias. In
Sanko S.S. Co., Ltd.,
495 F.2d at 1262-63 , one party alleged that an arbitrator had failed to disclose his company’s previous business
*627
connections to the opposing party and its counsel. The Second Circuit noted that the record was unclear as to the nature of the relationship and permitted an eviden-tiary hearing. In
National Hockey League Players’ Ass’n,
1994 WL 38130 at *5, two hockey players presented disputes under a collective bargaining agreement. The league president resolved the disputes. The players’ association sued to set aside the president’s decisions, alleging that under the collective bargaining agreement, the disputes should have been settled by an independent arbitrator. The association contended that the league president was biased against players. The court permitted discovery because the record did not explain the league president’s responsibilities and duties, his employment history, his
ex parte
contacts with interested parties, or the extent to which any of these would have made him biased against the players.
Id.
at *2 .
In this case, by contrast, the record is adequate to permit this court to decide the issues presented. The disclosures Jaffe did make, his letters to the ICC, the documents LGA obtained, and the information LGA has presented, present a sufficient record to permit this court to determine the allegations and issues.
LGA does not suggest that Jaffe had any personal involvement with El Paso or Aguaytia. The record does not suggest that Arent Fox’s work on the Aguaytia project related to any issue involved in the arbitration. The record does not suggest that Arent Fox had any recent or continuing involvement with Aguaytia or El Paso’s interest in Aguaytia. The record does not suggest that Arent Fox had any substantial ongoing representation of El Paso on matters related to the project at the time Jaffe was selected as an arbitrator and made his disclosure to the parties.
See Lyeth v. Chrysler Corp.,
929 F.2d 891, 899 (2d Cir.1991)(affirming denial of discovery where party had failed to show that arbitrator had any financial or personal stake in outcome);
Andros, 579
F.2d at 701 (affirming denial of discovery into relationship between arbitrator and principal where record showed extent of relationship was purely professional);
Hunt v. Mobil Oil Corp.,
654 F.Supp. 1487, 1496 (S.D.N.Y.1987)(denying discovery where record provided adequate factual basis to decide motion).
15
Unlike the arbitrators in the cases LGA cited, Jaffe was not personally involved with any party to the arbitration and had no identifiable interest in the outcome.
*628
Jaffe had specifically disclosed that a former partner in his law firm did “substantial work” for an investor in one of the parties. Jaffe’s firm had ceased representing the nonparty investor in matters related to the investment long before Jaffe was appointed. This court finds that LGA has failed to allege facts showing a reasonable possibility of bias, much less “clear evidence of impropriety,” so as to permit discovery, particularly, when, as here, LGA was on notice of the relationship between Arent Fox, El Paso, and Aguaytia before the arbitration began and sought no other information at the time. This court DENIES LGA’s request for discovery and DENIES LGA’s challenges for nondisclosure and actual bias.
D. The Claim of Arbitrator Misconduct
LGA also alleges that Jaffe engaged in “partisan behavior” during the arbitration proceedings by interrupting LGA’s witnesses, “usurping” the role of chair of the panel, influencing other members of the panel, and advocating Aguaytia’s position. (Docket Entry No. 36, pp. 35-36). LGA submitted to the ICC excerpts of the arbitration transcript that LGA identified as examples of Jaffe’s partisan behavior. (Docket Entry No. 21, Ex. 8). In a letter to the ICC, the arbitrators denied LGA’s allegations and disputed its characterizations of the proceedings. (Docket Entry No. 21, Ex. 14). The arbitrators asserted that they each, independently, evaluated the issues. The arbitrators stated that while Jaffe had played an active role in the proceedings, his questions and comments were solely to assist the panel in understanding the issues and were appropriate to reaching an efficient and fair resolution of those issues.
(Id.,
pp. 3-4). The ICC rejected LGA’s challenge. (Docket Entry No. 21, Ex. 9).
In
Fort Hill Builders, Inc. v. Nat'l Grange Mut. Ins. Co.,
866 F.2d 11 (1st Cir.1989), the court held that an arbitrator’s “alleged interruptions and interjections of comments or explanations favorable to [one party] or hostile to [the other party] to the point where [that party’s] lawyer felt he was facing an adversary” were insufficient to show evident partiality.
Id.
at 13 . The plaintiff argued that the arbitrator’s comments were “so strong and frequent that they must have influenced the other arbitrators.”
Id.
The court emphasized that the plaintiff did not argue that he “lacked an opportunity to oppose or correct [the arbitrator’s] statements or to argue his own views.”
Id.
The court held that the complaint should have been raised at the proceeding itself.
Id.
at 13 . The court did not rely only on waiver, but also rested on the fact that the arbitrators’ decision was unanimous, stating “[t]hat the other panel members were ultimately persuaded by [the arbitrator’s] reasoning rather than [the plaintiffs counsel] does not constitute bias.”
Id.
In the present case, as in
Fort Hill Builders,
LGA did not raise any complaint during the hearings as to Jaffe’s interruptions, questions, or comments. Instead, LGA waited until it received the adverse draft interim award. (Docket Entry No. 21, Ex. 14, p. 1). LGA should have objected earlier had it felt prejudiced during the proceeding itself. LGA’s failure to do so is not, however, the sole basis for this court’s rejection of this argument as grounds to vacate the award. As in
Fort Hill Builders,
LGA has not alleged any wrongdoing by the other two members of the panel.
See Fort Hill Builders,
866 F.2d at 14 . LGA has not shown that it lacked the opportunity to respond to Jaffe’s comments and questions. A review of the transcript reveals that each of the panel members asked questions of the witnesses, often vigorously. The hearings involved highly technical and detailed subjects, about which the arbitrators had acknowl
*629
edged substantive expertise and experience, as well as experience as arbitrators. There were a number of sharp disputes and disagreements. The transcript shows that a number of participants interrupted, questioned, and commented. The record does not support LGA’s characterization of Jaffe’s behavior as improper or as prejudicial.
LGA specifically faults Jaffe for “usurping the role of chair,” claiming that Jaffe wrote the draft award. The record does not support this claim. The panel’s letter to the ICC clarified that, contrary to LGA’s assertion, the chair of the panel did write the draft award. Jaffe merely faxed the copies from his office. (Docket Entry No. 21, Ex. 14). LGA has failed to allege or present facts showing that Jaffe “usurped” the role of chair.
In
Ballantine Books Inc. v. Capital Distrib. Co.,
302 F.2d 17 (2d Cir.1962), the court rejected a challenge based on misconduct where the arbitrator indicated his tentative views to counsel and encouraged settlement; favored one party’s position; and “in effect ‘usurped the office of counsel [for that party].”’
Id.
at 20 . The court rejected the challenge, noting that by the time the arbitrator expressed his views, he had seen many documents, evidence, and testimony, and the defense had nearly rested.
Id.
Similarly, in this case, the panel received and reviewed volumes of evidence from the parties before the hearings began. (Aguaytia Ex. 14).
The panel characterized Jaffe’s questions and comments as being aimed, appropriately, at understanding the issues and affecting an efficient and fair resolution. “A fortiori an arbitrator should act affirmatively to simplify and expedite the proceedings before him, since among the virtues of arbitration which presumable have moved the parties to agree upon it are speed and informality.”
Ballantine,
302 F.2d. at 21 (citations omitted). “It is to be expected that after a judge or an arbitrator has heard considerable testimony, he will have some view of the case. As long as that view is one which arises from the evidence and the conduct of the parties it cannot be fairly claimed that some expression of that view amounts to bias.”
Id.; see also Fairchild & Co., Inc. v. Richmond, Fredericksburg & Potomac R.R. Co.,
516 F.Supp. 1305, 1313 (D.D.C.1981)(stating that arbitrators are expected to develop opinions during course of arbitration, and to “act affirmatively to simplify and expedite the proceedings” before them)(citing
Ballantine,
302 F.2d at 21 ). “[A]n arbitrator’s legitimate efforts to move the proceedings along expeditiously may be viewed as abrasive or disruptive to a disappointed party. Nevertheless, such displeasure does not constitute grounds for vacating an arbitration award.”
Fairchild & Co.,
516 F.Supp. at 1313 .
The panel reached a unanimous decision. When challenged, Rubin and Overcash, the other panel members, experienced arbitrators and experienced and knowledgeable lawyers in the area of construction contracts, defended the process and the results reached. The transcript supports their description of the process and of Jaffe’s role in it. This court finds that LGA has failed to allege or present facts showing that Jaffe’s conduct rose to the level of evident partiality or provides a basis for vacating the award.
This court DENIES LGA’s motion to vacate the award based on arbitrator misconduct and evident partiality.
VII. The Panel’s Refusal to Incorporate the Parties’ Stipulation
On December 11, 2000, the parties signed a stipulation reflecting their agreement that Aguaytia owed LGA specific payments and credits. The stipulation it
*630
self was not then submitted to the panel. The panel issued its Final Award on April 28, 2001. In May 2001, the parties entered a stipulation under which they agreed that “the following agreed Items and credited party, Amounts and Payment Due Dates should be made a part of the Final Award, and should be used for purposes of establishing a Project Account Balance and calculating preaward and pos-taward interest.” (Docket Entry No. 36, Ex. C). The net effect of the stipulation was that Aguaytia owed LGA $5.2 million. In June 2001, the parties filed a Joint Application for Correction of Final Award, asking the panel “to approve the Stipulation or its substantive provisions as an addendum to the Final Award,” under Article 29 of the ICC Rules of Arbitration.
16
(Docket Entry No. 36, Ex. C). In the Joint Application, the parties stated that some, but not all, of the stipulated items were listed in the Terms of Reference as “issues the Tribunal was to resolve.” The parties did not identify which were inelud-ed and which were not.
17
The parties stated that they had reached an agreement as to all the items addressed in the stipulation.
On September 4, 2001, the panel issued an addendum to the Final Award, denying the parties’ Joint Application to correct the award. (Docket Entry No. 52, Ex. 73). The panel stated as follows:
In their Joint Application the parties ask the Tribunal to supplement the Final Award by including in it the contents of a Stipulation executed by the parties in May 2001. As the matters contained in the May 2001 Stipulation were resolved by the parties and not subject to resolution by the Tribunal, there is no proper basis for “correcting” or “interpreting” the Final Award. Accordingly, no revision to the Final Award will be made on the Joint Application.
(Id.,
p. 2).
LGA asserts that the entire award must be vacated because the panel refused to
*631
incorporate the parties’ joint stipulation. LGA argues that the panel’s refusal violates the FAA and that vacatur is the exclusive remedy. Aguaytia responds that its motion to enforce the award effectively recognizes the stipulated amounts as an offset reducing the judgment and that the panel’s ruling is not a ground for vacating the entire award.
The procedural posture this issue presents is unusual. Both sides agree that a judgment enforcing the award, without including the stipulated amounts as a setoff or credit, would be excessive. Both sides agreed to have the arbitration panel make the adjustment, in an agreed amount. The panel declined to do so. The first issue before this court is whether the panel’s refusal exceeded its authority, requiring this court to vacate the entire award, as LGA asserts.
LGA cites ICC Rule 26 to support its argument that the panel exceeded its authority and engaged in “deliberate misconduct” by refusing to incorporate the parties’ settlement as to the issues addressed in the stipulation.
18
However, as Aguaytia notes, the parties did not request entry of a settlement under Rule 26. Instead, the parties requested a correction under Rule 29. LGA does not identify authority under which the panel could have recorded the stipulation as a settlement under Rule 26, absent a specific request from the parties to do so. This court finds that the panel did not exceed its authority or engage in misconduct by refusing to record the stipulation as a settlement.
LGA simultaneously argues that the panel exceeded its scope of authority by deciding matters as to which the parties had agreed and that the panel exceeded the scope of its authority by refusing to include in their decision matters as to which the parties had agreed. LGA asserts that the parties had discussed their resolution of the issues addressed in the December 2000 and May 2001 stipulations during the arbitration hearings. LGA specifically refers to Hearing Exhibit H-62, “the Project Account Balance,” and asserts that this exhibit reflected the parties’ agreement as to particular issues which the arbitrators should not have decided, but should have incorporated into the arbitral award.
Aguaytia disputes LGA’s characterization of the exhibit and the parties’ presentation to the panel during the proceedings. (Docket Entry No. 43, p. 2). Aguaytia asserts that Exhibit H-62 was an agreed summary of the parties’ respective positions, not a stipulation resolving specific issues to be included in the Final Award.
(Id.,
pp. 3, 5). Aguaytia argues that the parties introduced Exhibit H-62 to identify the disputed issues the panel needed to resolve and the settled issues the parties had already resolved. Aguaytia asserts that Exhibit H-62 included certain amounts and dates that were undisputed, never contested, and never presented to the panel for resolution, as well as vigorously disputed issues that the panel did hear and resolve. (Docket Entry No. 43, p. 2). When the parties submitted Exhibit H-62, the chairman of the panel stated: “[T]his will be a very important document. I want to be exactly sure what the parties agree on and what they disagree on. Obviously we’ll decide what they disagree on.” (Aguaytia Ex. 40, p. 1161, lines 15-18). LGA did not object to this characterization of Exhibit H-62. Aguaytia also points out that in the Terms of Reference,
*632
the parties did not request the arbitration panel to find any of the amounts and terms set out in the stipulation, or to find that Aguaytia owed LGA a net amount of $5.2 million. (Docket Entry No. 43, p. 5).
Aguaytia acknowledges that the panel could have included the stipulated amounts in its Final Award. Aguaytia argues that the parties did not dispute the amounts owed and credits due and did not include issues as to the stipulated amounts in the Terms of Reference. Because the panel’s obligation was to resolve disputed matters, Aguaytia argues that the panel did not err in declining to include stipulated, undisputed amounts in the award. (Docket Entry No. 43, p. 3).
LGA cites
Delta Queen Steamboat v. Dist. 2 Marine Eng’rs Ben. Assoc.,
889 F.2d 599 (5th Cir.1989) and
HMC Mgmt. Corp. v. Carpenters Dist. Council of New Orleans and Vicinity,
750 F.2d 1302 (5th Cir.1985). In both cases, the arbitrator entered an award in favor of an employee, despite a finding that the employment contract justified the employer’s action. The Fifth Circuit vacated the award as contrary to either the express provisions or the essence of the parties’ arbitration contract. The court stated the clear rule that arbitrators are bound to the terms of the parties’ agreement in entering awards and may not displace or replace those terms based on the panel’s own sense of justice or fairness. Those cases, and that rule, do not address the issue this case presents. LGA has not identified a contractual provision that required the panel to include in their award amounts or issues that the parties had already resolved, outside the arbitration process. LGA has not identified a contractual provision that prevented the panel from making an award that did not include terms or amounts that the parties had settled, outside the arbitration process.
See Valentine Sugars, Inc. v. Donau Corp.,
981 F.2d 210, 213 (5th Cir.1993)(distinguishing
Delta Queen
where party had not identified contractual provision that removed the issue decided from the arbitrator’s review).
LGA also cites
Totem Marine Tug & Barge, Inc. v. N. Am. Towing, Inc.,
607 F.2d 649, 651 (5th Cir.1979). In
Totem,
the parties to a vessel charter agreement submitted to arbitration an itemized damages claim. The panel awarded damages that were not requested. 607 F.2d at 652 . The district court confirmed the award; the Fifth Circuit reversed and vacated.
19
In
Totem,
the panel awarded damages beyond those requested. In this case, by contrast, the panel refused to include undisputed payments and credits in its completed resolution of disputed liability issues and damages amounts.
Totem
does not support the result of vacating the award, as LGA requests.
“Arbitration is contractual and arbitrators derive their authority from the scope of the contractual agreement.”
Totem,
607 F.2d at 651 (citing
Enterprise Wheel,
363 U.S. at 597 , 80 S.Ct. 1358 ). “Parties to an arbitration may stipulate the issues they want determined and increase or limit the arbitrator’s contractual authority by their express submission.”
Am. Postal Workers Union v. Runyon,
185 F.3d 832, 835 (7th Cir.1999)(quoting
Hill v. Staten Island Zoological Soc’y, Inc.,
147 F.3d 209, 214 (2d Cir.1998)). In this case, the Terms of Reference did not expressly request the panel to enter findings as to the stipulated amounts.
20
The parties did not submit the
*633
stipulation to the panel before the award issued. While the parties referred to some, but not all, of the amounts and dates included in the stipulation during the arbitration proceedings, the record does not show that the parties expressly requested the panel to include the stipulated amounts in the award before the panel issued the Final Award.
21
It was not until after the Final Award issued that the parties requested the panel to “correct” the award by including the stipulated amounts. The panel addressed the narrow question of its own authority under the ICC rules to correct the award. The panel found that under those rules, it lacked the authority to “correct” or “interpret” the Final Award to include matters that the parties had resolved by agreement, outside the arbitration process, and had not submitted to the panel.
LGA argues that the panel refused to consider evidence by refusing to incorporate the stipulated amounts, warranting vacatur of the entire award. The issue is not, however, one of admissibility of evidence timely submitted during the proceedings. The arbitrators addressed and resolved the disputed issues submitted to them, based on the evidence submitted before the Final Award issued. After the panel issued the Final Award and the parties submitted the stipulation, the panel found that it lacked sufficient information to change the Final Award in the manner and at the time the parties filed their request. LGA has failed to present or allege facts showing that the panel refused to consider evidence during the arbitration proceeding so as to make the proceedings fundamentally unfair.
LGA also argues that the panel’s refusal to incorporate the stipulated amounts to reduce the size of the award results in an award that is not “mutual, final, and definite,” as required by 9 U.S.C. § 10 (a)(4). LGA argues that the panel left open the effect of the stipulated credits on the Final Award. In support, LGA submits the affidavit of William Huth as an expert on ICC arbitration. Huth states that the panel’s refusal to reduce the award by the amounts both parties stipulated was an abuse of the panel’s authority and that vacatur is the proper remedy.
22
(Docket Entry No. 52, Ex. 74).
Aguaytia responds that the panel’s refusal to incorporate the stipulated amounts into the Final Award is not a failure to resolve all issues submitted to the panel. “Aguaytia’s responsibility for these amounts was ‘resolved’ well in advance of the Final Award, when Aguaytia agreed that LGA was entitled to be credited for them.” (Docket Entry No. 54, p. 3). Aguaytia acknowledges that it owes LGA the stipulated amounts.
(Id.).
Aguaytia included the stipulated amounts in its proposed final judgment, as an offset that reduces the amount of the Final Award, noting that LGA has not challenged Aguaytia’s calculation of the net amount LGA owes.
(Id.).
LGA’s argument is not a basis for vacating the entire award, but rather to vacate the panel’s refusal to determine the effect of the stipulation on the Final Award, and to remand for the limit
*634
ed purpose of making that determination. If, as Aguaytia argues, the effect of the stipulation is simply that of an offset in an undisputed amount, the issue on remand is narrow, specific, and simple.
LGA argues that Aguaytia’s position would require this court to modify the award beyond the statutory authority to do so. Aguaytia responds that this court has the authority to confirm the entire award but to enter a final judgment that incorporates the stipulated amount as an offset or to modify the award to include the stipulated amount as an offset.
The FAA provides the following authority for district courts to modify an award:
In either of the following cases the United States court in and for the district wherein the award was made may make an order modifying or correcting the award upon the application of any party to the arbitration—
(a) Where there was an evident material miscalculation of figures or an evident material mistake in the description of any person, thing, or property referred to in the award.
(b) Where the arbitrators have awarded upon a matter not submitted to them, unless it is a matter not affecting the merits of the decision upon the matter submitted.
(c) Where the award is imperfect in matter of form not affecting the merits of the controversy.
The order may modify and correct the award, so as to effect the intent thereof and promote justice between the parties.
9 U.S.C. § 11 .
Aguaytia argues that this court has the authority to modify the Final Award to include the stipulation under 9 U.S.C. § 11 (c), which permits modification of an award that is “imperfect in a matter of form not affecting the merits of the controversy,” and under the general provision stating that “[t]he order may modify and correct the award, so as to effect the intent thereof and promote justice between the parties.” (Docket Entry No. 54, pp. 3-4). Aguaytia asserts that “[crediting LGA for the agreed amounts does not affect the merits of the controversy since these amounts are not contested and all that is required to incorporate them is a mathematical calculation previously agreed to by the parties.”
(Id.
at n. 3).
In
Diapulse Corp. of Am. v. Carba, Ltd.,
626 F.2d 1108 , the district court found that an arbitrator’s award enforcing a noncom-petition agreement violated public policy because the award failed to include geographic or temporal limits. The district court modified the award under section 11(c) to include geographic and temporal limitations. The Second Circuit reversed, holding that the district court’s conversion of a very broad noncompetition injunction into a relatively narrow one affected “matters of substance that were at the heart of the controversy between [the parties].”
Id.
In
Diapulse,
only one party sought a modification to the arbitrator’s award. In this case, by contrast, both parties requested the panel to modify the award and agreed as to how the award should be modified. The stipulated amounts are not “at the heart of the controversy” between the parties, in the sense that the parties agreed as to the amounts and due dates set out in the stipulation, while continuing to dispute issues before the arbitration panel. However, the stipulation obviously will affect the amount of the award. The panel itself noted its uncertainty as to the effect of the stipulation on the final amount owing between the parties. (Docket Entry No. 36, Ex. B, p. 3 n. 2, p. 35 n. 8).
LGA relies on
Katz v. Feinberg,
167 F.Supp.2d 556 (S.D.N.Y.2001), to support its argument that this court lacks authority to offset the award by the stipulated
*635
amounts. In
Katz ,
the plaintiff, the prevailing party in an arbitration, moved to confirm the arbitration award. The party opposing the award had filed a separate arbitration proceeding against the plaintiff, seeking payment of litigation expenses. The party opposing the award argued that under the parties’ agreement, he had a right to offset the amount owed under the award by the amount of the litigation expenses he incurred. However, the separate proceeding to resolve the litigation expenses had not concluded. The dispute as to those litigation expenses had not been submitted as part of the arbitration that resulted in the award. The court confirmed the award without resolving the disputed issues as to the litigation expenses and without including an offset for those expenses.
Katz,
167 F.Supp.2d at 573 .
The circumstances of
Katz
are quite different from those in the present case. In the present case, the parties filed a joint request to the panel to reduce the amount of the Final Award by the stipulated amounts as a net credit from Aguaytia to LGA, offsetting the amount LGA owed Aguaytia under the Final Award. Neither party disputes the amounts or Aguaytia’s obligation to pay LGA the net stipulated amount. LGA has not challenged the method by which Aguaytia calculated the amount of the judgment that would result from modifying the award to include the net stipulated amount. However,
Katz
and other cases emphasize the limited role a court plays in resolving motions to confirm, or modify, arbitration awards:
This case was brought as a petition to confirm an arbitration award. As such, this Court’s role is limited to reviewing the parties’ challenges to the arbitrator’s decision. As [the party opposing modification] points out, “[ajctions to confirm arbitration awards ... are straightforward proceedings in which no other claims are to be adjudicated.”
167 F.Supp.2d at 572 (quoting
Ottley v. Schwartzberg,
819 F.2d 373 (2d Cir.1987), and citing
Florasynth, Inc. v. Pickholz,
750 F.2d 171, 176 (2d Cir.1984)(“[T]he confirmation of an arbitration award is a summary proceeding that merely makes what is already a final arbitration award a judgment of the court.”)).
Aguaytia’s argument that the modification it seeks would not change the award in a manner that affects the merits of the disputed issues between the parties is supported by the lack of dispute over the items and amounts of credits and payments in the stipulation. However, the defect in the award that the parties assert is not merely one of form; it is a $5.2 million net sum, composed of a number of specific payment and credit items. The modification would not effectuate the panel’s intent in issuing the award. The panel was clear that it did not intend to include the stipulated amounts in the award. The panel was clear that it lacked sufficient information to determine the relationship between the stipulated items and the items resolved in the award. The panel did not intend to issue an award that would completely define “the final amount of funds payable from one party to the other since that involves issues not determined in this proceeding.” (Docket Entry No. 36, Ex. B, p. 3 n. 2).
This court concludes that it can neither vacate the entire award because it does not include the stipulation, nor, on the present record, modify the award to incorporate the stipulation. This court DENIES the motion to vacate the award on the basis of the panel’s refusal to include the effect of the parties’ stipulation. This court finds that the panel’s refusal to incorporate the stipulation after the Final Award had already issued is not a basis to vacate the award as a whole or to vacate any specific provision of the award. However, because
*636
the panel did not address the effect of the parties’ stipulation on the amounts established by the award, and because this court cannot do so, this court REMANDS, in part. Specifically, this court remands the issue of the effect on the Final Award of the parties’ stipulation that Aguaytia owes LGA a net amount of $5.2 million. The remand is to the International Chamber of Commerce, to permit resolution consistent with the parties’ broad contractual agreement to submit all disputes to binding arbitration.
23
This court DENIES LGA’

[Text truncated at 120,000 characters. The full text is on the page linked above.]

---

Source: Frix Law Library, https://www.frixlaw.com/law-library/cases/2390877. Public record. Not legal advice.
