# Mission Energy Founders LLC v. 64 Solar LLC

> New York Supreme Court, Westchester County · September 19, 2024

URL: https://www.frixlaw.com/law-library/cases/11471015

## Case

- **Court:** New York Supreme Court, Westchester County
- **Decided:** September 19, 2024
- **Precedential status:** Unpublished
- **Opinion:** Opinion
- **Cited by:** 0 later opinions in the Frix Law Library

## Citator (automated)

- No negative treatment found by the automated citator. That is not the same as a confirmation that the case is good law; read the citing cases.
- Full citator and citing cases: https://www.frixlaw.com/law-library/cases/11471015

## Opinion text

Mission Energy Founders LLC v 64 Solar LLC
2024 NY Slip Op 35502(U)
September 19, 2024
Supreme Court, Westchester County
Docket Number: Index No. 61484/2024
Judge: Gretchen Walsh
Cases posted with a "30000" identifier, i.e., 2013 NY Slip
Op 30001(U), are republished from various New York
State and local government sources, including the New
York State Unified Court System's eCourts Service.
This opinion is uncorrected and not selected for official
publication.

file:///LRB-ALB-FS1/Vol1/ecourts/Process/covers/NYSUP.00614842024.WESTCHESTER.001.LBLX000_TO.html[06/25/2026 3:49:03 PM]
FILED: WESTCHESTER COUNTY CLERK 09/19/2024 03:32 PM INDEX NO. 61484/2024
NYSCEF DOC. NO. 28 RECEIVED NYSCEF: 09/19/2024

To commence the statutory time
period for appeals as of right (CPLR
5513[a]), you are advised to serve a
copy of this order, with notice of
entry, upon all parties.

SUPREME COURT OF NEW YORK
COUNTY OF WESTCHESTER: COMMERCIAL DIVI IO
----------------------------------------------------------------------------X
MISSION ENERGY FOUNDERS LLC Index No . 61484/2024
f/k/a MISSION ENERGY LLC , Motion Seq. No. 1
Plaintiff Motion Date: 7/26/24
- against -

64 SOLAR LLC,
Defendant.
-----------------------------------------------------------------------------X
WALSH, J.

The following e-filed documents listed in NYSCEF under document numbers 4-25 and 27
were read on this motion (' Motion Seq. o. I ') by Mission Energy Founders LLC f/k/a Mission
Energy LLC (" Mission ' or " Plaintiff') for an order pursuant to CPLR 3215 granting a default
judgment against 64 Solar LLC (" 64 Solar' or " Defendant ').

Defendant has failed to submit opposition to the motion despite having been served with
same. Upon the foregoing papers and for the reasons stated herein, Plaintiffs motion shall be
granted.

FACTS AND PROCEDURAL HISTORY

The following facts are taken from Plaintiffs Verified Complaint, which was verified by
Dan Last (" Last' ), in his position as Plaintiffs co-chief executive officer (NYSCEF Doc. No. l
[the "Complaint ']). Plaintiff explains that it is a limited liability company, organized and existing
under the laws of the State of Delaware which is authorized to do business in ew York and
maintains its offices at 42020 Village Center Plaza Suite 120 #650 , Stone Ridge, Virginia 20105
(Complaint at il 2) . Plaintiff asserts that Defendant is a corporation, organized and existing under
the laws of the State of ew York, with a principal place of business at 181 Westchester A venue,
uite 407c, Pott Chester, Westche ter County , ew York l 0573 (id at il 3).

This action arises from Plaintiffs claims of breach of contract based on Defendant' s
alleged breach of: (l) an Engineering, Procurement and Construction Agreement dated March 3,
2022 entered into between Plaintiff and Defendant for the design, installation, operation and
maintenance of a solar photovoltaic system at 174 Filers Lane Stony Point New York (the " Stony
Point Site") (see NYSCEF Doc. No. 12 [the " Stony Brook EPCA"]); and (2) an Engineering,

[* 1] 1 of 13
FILED: WESTCHESTER COUNTY CLERK 09/19/2024 03:32 PM INDEX NO. 61484/2024
NYSCEF DOC. NO. 28 RECEIVED NYSCEF: 09/19/2024

2

Procurement and Construction Agreement between Plaintiff and Defendant dated March 3, 2022
entered into between Plaintiff and Defendant for the design, installation, operation and
maintenance of a solar photovoltaic system at 148 Main Street, ew Rochelle, ew York (the
"New Rochelle Site' ) (see NYSCEF Doc. No. 18 [the "New Rochelle EPCA"]) (id. at ~~ 6, 27).
The Complaint asserts: (I) a First Cause of Action for breach of contract, regarding the Stony
Brook EPCA; and (2) a Second Cause of Action for breach of contract, regarding the New Rochelle
EPCA (id. at ~~ 46-57). To date, Defendant has not filed an answer to the Complaint, or otherwise
appeared in this action.

A. The Stony Point Project

Plaintiff alleges that CE Solar SRP ("CE Solar ') and Salesian Society ("Salesian")
entered into a solar power purchase agreement on or about December l 5 2021 , "pursuant to which
CE Solar promised to design, install , own, operate and maintain a solar photovoltaic system" at
the Stony Point Site owned by Salesian (id. at~ 4). Plaintiff states that it and 'CE Solar entered
into an Engineering, Procurement and Construction Agreement for the Stony Point Project [on
February 17, 2022] pursuant to which Plaintiff promised to deliver a complete and operating solar
photovoltaic system ' (id. at ~ 5). Plaintiff states that it entered into the Stony Point EPCA with
Defendant on March 3, 2022, and that

Section 1.1.1 of the Stony Point EPCA provides among other things that 64 Solar
shall obtain and pay " the expense for all necessary Host Utility and other required
permits and authorizations regardless of the name of the entity under which such
authorizations or permit must be obtained;" "apply for and fulfill requirements for
the System to qualify for any rebate, incentive or SREC programs," and be
responsible for "all other acts necessary to deliver a complete and operating
System.' ( 'System" as defined in Stony Point EPCA shall mean a complete and
operating solar photovoltaic system (which may be comprised of a series of Sub-
Systems if set forth as such in the Recitals) that meets all of the terms and conditions
of the Agreement. (id. at~~ 6-7 [quoting the Stony Point EPCA]).

Plaintiff explains that " Section 1.3.1 of the Stony Point EPA provides among other things that 64
Solar ' shall obtain all necessary permits and authorizations that may be required by the federal
state, county, municipal or other governing entity with jurisdiction concerning the installation of
the System " and the section further requires "64 Solar to ' supply [Plaintiff] with a list of permits
and authorizations to be obtained and the corresponding dates when submittals for such permits
and authorizations shall be submitted to the governing entity having jurisdiction thereof'
immediately upon installation of the system and to 'simultaneously submit to [Plaintiff] copies of
the submittals made by [64 Solar] to the governing entity, and of the final permits and
authorizations issued by the governing entity"' (id. at~ 9, quoting the Stony Point EPCA). Plaintiff
states the section further provides that "' [a]ll expenses and fees associated with the permits and
authorizations shall be the responsibility of [64 Solar] ' (id. , quoting the Stony Point EPCA).
Section 3.3 "requires 64 Solar to prepare, maintain, and perform the tasks necessary to comply
with the schedule for execution of the contracted for services," while Section 11.1 "requires 64

[* 2] 2 of 13
FILED: WESTCHESTER COUNTY CLERK 09/19/2024 03:32 PM INDEX NO. 61484/2024
NYSCEF DOC. NO. 28 RECEIVED NYSCEF: 09/19/2024

3

Solar to provide notice to Plainti ff of any sub-contractor it hires to perform the contracted for
services together with proof of insurance for such subcontractors" (id. at~~ I 0- 11 ).

According to Plaintiff Section 10.1 .3 of the Stony Point EPCA states:

If (64 Solar] a) should be adjudged bankrupt, or if [64 Solar] should make a general
assignment for the benefit of his creditors, or if a receiver should be appointed on
account of [64 Solar's] insolvency; b) disregards any applicable law including
federal , commonwealth, municipal law, by-law, ordinance, permit, regulation,
order or decree in executing the Agreement; c) disregards the material instructions
of [Plaintiff] under the Agreement; or, d) violates any material provision of the
Agreement, then [Plaintiff] may, subject to the provisions of Agreement Section
10.1.4 below and without prejudice to any other right or remedy may have under
the Agreement and/or the law, and after giving [64 Solar] seven (7) calendar days
written notice: ( 1) terminate [64 Solar]'s ri ght to proceed with the remaining
Services; (2) take pos ession of the Site and all materials and equipment that will
comprise the System · and (3) finish the remaining Services by whatever method
[Plaintiff] may reasonably deem expedient. In such case, [64 Solar] agrees to a sign
to [Plaintiff] all material contracts, all Second-Tier Contractor contracts to the
extent requested by [Plaintiff] and to assign to System Owner a ll Second-Tier
Contractors and manufacturer warranties related to the Services and the System
and [64 Solar] shall not be entitled to receive any further payment under the
Agreement. [64 Solar] shall pay [Plaintiff] (i) all costs and expenses expended by
[Plaintiff] (inclusi ve of the additional reasonable cost of [Plaintiff] ' s employees and
consultants) to obtain and mobilize a replacement contractor to complete the
Services; (ii) all costs incurred by [Plaintiff] to complete the terminated Services
less the amount [Plaintiff] would have paid [64 So lar] to complete such terminated
Services in accordance with the Agreement; (i ii) liquidated damages pursuant to
Agreement Section 8.1 if the date of Beneficial se achieved by the replacement
contractor occurs after the Beneficial Use Target Date· and (iv) liquidated damages
pursuant to Agreement Section 8. 2 (id. at 1 12 quoting the Stony Point EPCA).

Plaintiff tates that Section 10.1.4 of the Stony Point EPCA states :

If [Plainti ff] believes that [64 Solar] is in default of the Agreement pursuant to
Agreement Section 10.1.3 b), c), or d) above then [Plaintiff] before being entitled
to terminate [64 Solar]'s right to provide Services, will provide [64 Solar] with a
written notice giving [64 Solar] a thirty (30) calendar day period from the receipt
of the written notice to correct such default condition or such longer cure period as
[Plaintiff] reasonably determines. If [64 Solar] fails to correct the default condition
within such time period, then [Plaintiff] shall be entitled to terminate [64 Solar]'s
right to proceed with the Services as specified in Agreement Section 10.1.3 above
(id. at 13, quoting the Stony Point EPCA) .

[* 3] 3 of 13
FILED: WESTCHESTER COUNTY CLERK 09/19/2024 03:32 PM INDEX NO. 61484/2024
NYSCEF DOC. NO. 28 RECEIVED NYSCEF: 09/19/2024

4

Plaintiff asserts that Defendant breached the Stony Point EPCA in several ways: (I)
Defendant " breached Section 1. 1 . . . by failing to deliver a complete and operating System to
Plaintiff and failing to obtain all required permits and authorizations in connection with the
System'; (2) Defendant breached 'Section 1.3. l of the Stony Point EPCA because it unofficially
designated project manager has failed to properly use available resources in connection with the
contracted for services, and it failed to replace its project manager after being notified by Plaintiff
that its designated project manager was not competent"; (3) Defendant breached Section 1.4 of
the Stony Point EPCA by failing to supply Plaintiff with a list of permits and authorizations to be
obtained and the corresponding dates when submittals for such permits and authorizations shall be
submitted to the governing entity having jurisdiction thereof'; (4) Defendant breached "Section
3.3 of the Stony Point EPCA by failing to properly track and obtain permits in a timely manner;
and otherwise failed to maintain the schedule in accordance with Section 3.3 and 3.4 of the Stony
Point EPCA" · (5) Defendant ' breached Section 11.1 of the Stony Point EPCA by engaging
Second-Tier Contractors who have been in direct contact with the engineer and failing to provide
Plaintiff with the applicable prior written notice required for such contractors"; and (6) Defendant
generally breached the Stony Point EPCA "by failing to meet equipment ordering dates, or permit
filing dates, as set forth in the Agreement; and by further providing Plaintiff with proof of purchase
or refusing to purchase the equipment, set forth in Exhibit A to the Stony Point EPCA" (id. at~~
14-20). Plaintiff asserts that Defendant ' s breaches of the Stony Point EPCA "are material and
continuing" and that " [o ]n October 14, 2022 , Plaintiff provided [Defendant] with a notice of
default pursuant to the terms of Section 10.1 of the Stony Point EPCA ('Notice of Default ' )" (id.
at ~ 21 ). Plaintiff states this Notice of Default "clearly set forth the nature and extent of
[Defendant ' s] defaults under the Stony Point EPCA and further itemized the actions [Defendant]
needed to perform to cure the defaults,' and that Plaintiff, through the Notice of Default, gave
Defendant the requisite 30 day period to cure the default, and " advised that if the cure period
expired without the defaults being cured, Plaintiff would terminate the Stony Point EPCA" (id. at
~ 22). Plaintiff asserts that, by way of the otice of Default, it advised Defendant that, following
termination of the Stony Point EPCA, Defendant "would be obligated to pay Plaintiff: (i) all costs
and expenses expended by Plaintiff (inclusive of the additional reasonable cost of Plaintiff's
employees and consultants) to obtain and mobilize a replacement contractor to complete the
Services; (ii) all costs incurred by Plaintiff to complete the terminated Services, less the amount
Plaintiff would have paid 64 Solar to complete such terminated Services in accordance with the
Stony Point EPCA ; (iii) liquidated damages pursuant to Sections 8.1 and 8.2 of the EPCA" (id at
1 23). Plaintiff asserts that this cure period expired without any curation by Defendant, and thus
"on ovember 16, 2022, Plaintiff sent 64 Solar a notice of termination(' otice of Termination')"
(id. at~ 24).

B. The New Rochelle Project
Plaintiff alleges that CE Solar and Salesian entered into a solar power purchase agreement
on or about December 15, 2021 wherein CE Solar "promised to design, install, own, operate and
maintain a solar photovoltaic system at a site owned by Salesian ('New Rochelle Project ' ) and
located at 148 Main Street, New Rochelle, New York ( New Rochelle Site ' )" (id. at~ 25). Plaintiff
states that it entered into an Engineering, Procurement and Construction Agreement with CE Solar

[* 4] 4 of 13
FILED: WESTCHESTER COUNTY CLERK 09/19/2024 03:32 PM INDEX NO. 61484/2024
NYSCEF DOC. NO. 28 RECEIVED NYSCEF: 09/19/2024

5

for the ew Rochelle Project, " pursuant to which Plaintiff promised to deliver a complete and
operating solar photovoltaic system to CE Solar' (id. at ~ 26). Plaintiff states that it entered into
the New Rochelle EPCA with 64 Solar on March 3 2022, and that

Section 1.1.1 of the New Rochelle EPCA provides that 64 Solar shall obtain and
pay "the expense for all neces ary Host tility and other required permits and
authorizations regardless of the name of the entity under which such authorizations
or permits must be obtained, "apply for and fulfill requirements for the System to
qualify for any rebate, incentive or SREC programs," and be responsible for "all
other acts necessary to deliver a complete and operating System." ("System' as
defined in the New Rochelle EPCA shall mean a complete and operating solar
photovoltaic system (which may be comprised of a series of Sub-Systems if set
forth as such in the Recitals) that meets all of the terms and conditions of the
Agreement. See, Art. 2 'Definitions.") (id at~~ 27-28 , quoting the New Rochelle
EPCA).

Plaintiff explains that " Section 1.3 .1 of the New Rochelle EPCA provides that 64 Solar ' shall
designate a competent project manager ... satisfactory to [Plaintiff] .' Such project manager is
required ' to possess the expertise and employ whatever resources necessary to efficiently and
professionally perform ' the contracted for services" (id. at~ 29 quoting the New Rochel le EPCA).
Plaintiff explains that

Section 1.4 of the ew Rochelle EPCA provides that 64 Solar "shall obtain all
necessary permits and authorizations that may be required by the federal , state,
county, municipal or other governing entity with jurisdiction concerning the
installation of the System." It also requires 64 Solar to "supply [Plaintiff] with a list
of permits and authorizations to be obtained and the corresponding dates when
submittals for such permits and authorizations shall be submitted to the governing
entity having jurisdiction thereof' immediately upon installation of the System and
to "simultaneously submit to [Plaintiff] copies of the submittals made by (64 Solar]
to the governing entity, and of the final permits and authorizations issued by the
governing entity." It also provides that "[a]ll expense and fees associated with the
permits and authorizations shall be the responsibility of (64 Solar]" (id. at~ 30,
quoting the New Rochelle EPCA)
Plaintiff states that "Section 3 .3 of the ew Rochelle EPCA requires 64 Solar to prepare, maintain
and perform the tasks necessary to comply with the schedule for execution of the contracted for
services" while "Section 11. l ... requires 64 Solar to provide notice to Plaintiff of any sub-
contractor it hires to perform the contracted for services together with proof of insurance for such
subcontractors" (id. at ~~ 31-32, quoting the New Rochelle EPCA). Section 10.1.3 states, in
pertinent part:

If [64 Solar] a) should be adjudged bankrupt or if[64 Solar] should make a general
assignment for the benefit of his creditors, or if a receiver should be appointed on
account of (64 Solar' s] insolvency ; b) disregards any applicable law including

[* 5] 5 of 13
FILED: WESTCHESTER COUNTY CLERK 09/19/2024 03:32 PM INDEX NO. 61484/2024
NYSCEF DOC. NO. 28 RECEIVED NYSCEF: 09/19/2024

6

federal , commonwealth, municipal law, by-law, ordinance, permit, regulation,
order or decree in executing the Agreement; c) disregards the material instructions
of [Plaintiff] under the Agreement; or d) violates any material provision of the
Agreement, then [Plaintiff] may, subject to the provisions of Agreement Section
10.1.4 below and without prejudice to any other right or remedy may have under
the Agreement and/or the law and after giving [64 Solar] seven (7) calendar days
written notice: (1) terminate [64 Solar]'s right to proceed with the remaining
Services; (2) take possession of the Site and all materials and equipment that will
comprise the System ; and (3) finish the remaining Services by whatever method
[Plaintiff] may reasonably deem expedient. In such case, [64 Solar] agrees to assign
to [Plaintiff] alI material contracts all Second-Tier Contractor contracts to the
extent requested by [Plaintiff] and to assign to System Owner all Second-Tier
Contractors and manufacturer warranties related to the Services and the System,
and [64 olar] shall not be entitled to receive any further payment under the
Agreement. [64 Solar] shall pay [Plaintiff] (i) all costs and expenses expended by
[Plaintiff] (inclusive of the additional reasonable cost of [Plaintiff]'s employees and
consultants) to obtain and mobilize a replacement contractor to complete the
Services; (ii) all costs incurred by [Plaintiff] to comp lete the terminated Services,
less the amount [Plaintiff] would have paid [64 Solar] to complete such terminated
Services in accordance with the Agreement; (iii) liquidated damages pursuant to
Agreement Section 8.1 if the date of Beneficial Use achieved by the replacement
contractor occurs after the Beneficial Use Target Date; and, (iv) liqu idated damages
pursuant to Agreement Section 8.2. (id. at 1 33 , quoting the New Rochelle EPCA).

Section I 0.1 .4 states in pertinent part:

If [Plaintiff] believes that [64 Solar] is in default of the Agreement pursuant to
Agreement Section 10.1.3 b), c), or d) above , then [Plai nti ff] , before being entitled
to terminate [64 Solar]'s right to provide Services, wi ll provide [64 So lar] with a
written notice giving [64 Solar] a thirty (30) calendar day period from the receipt
of the written notice to correct such default condition or such longer cure period as
[Plaintiff] reasonably determines. If [64 Solar] fai ls to correct the default condition
within such time period, then [Plaintiff] shall be entitled to terminate [64 Solar]'s
right to proceed with the Services as specified in Agreement Section 10.1.3 above.
(id. at 134, quoting the ew Rochelle EPCA).

Plaintiff states that "64 Solar breached the New Rochelle EPCA in many ways", including:
( 1) breaching Section 1.1 " by fai ling to deliver a complete and operating System to Plaintiff and
failing to obtain all required permits and authorizations in connection with the System" · (2)
breaching 1.3.1 of the New Rochelle EPCA through the failure of its unofficia lly designated
project manager " to properly use available resources in connection with the contracted for ervices,
and it fa iled to replace its project manager after being notified by Plaintiff that its designated
project manager was not competent"; (3) breaching Section 1.4 of the ew Rochelle EPCA " by
failing to supply Plaintiff with a list of permits and authorizations to be obtained and the

[* 6] 6 of 13
FILED: WESTCHESTER COUNTY CLERK 09/19/2024 03:32 PM INDEX NO. 61484/2024
NYSCEF DOC. NO. 28 RECEIVED NYSCEF: 09/19/2024

7

corresponding dates when submittals for such permits and authorizations shall be submitted to the
governing entity having juri diction thereof'; (4) breaching Section 3.3 of the ew Rochelle
EPCA 'by failing to properly track and obtain permits in a timely manner; failed to provide an
updated schedule identifying all key contractual dates and permit and grant program requirements,
and otherwise fai led to maintain the schedule in accordance with Section 3.3 and 3.4 of the New
RocheUe EPCA"; (5) breaching Section 11.1 of the New Rochelle EPCA "by engaging Second-
Tier Contractors who have been in direct contact with the engineer, and failing to provide Plaintiff
with the applicable prior written notice required for such contractors" ; and (6) breaching the New
Rochelle EPCA "by failing to meet equipment ordering dates, or permit filing dates, as set forth
in the Agreement; and by further providing Plaintiff with proof of purchase or refusing to purchase
the equipment, set forth in xhibit A to the New Rochelle EPCA" (id. at~~ 35-41 ). Plaintiff asserts
that Defendant' s breaches "are material and continuing" and that "Plaintiff provided 64 Solar with
a notice of default pursuant to the terms of Section 10.1 of the New Rochelle EPCA" (the "NR
Notice of Default") on October 14, 2022 (id. at~· 42). Plaintiff states that, through the R Notice
of Default, it "clearly et forth the nature and extent of 64 Solar' s defaults under the ew Rochelle
EPCA and further itemi zed the actions that 64 Solar needed to perform in order to cure the
defaults" and that it gave Defendant thirty days to cure the default and advised Defendant that
should the defaults remain uncured, it would terminate the ew Rochelle EPCA (id. at ~ 43).
Plaintiff states that, through the R Notice of Default, it further advised Plaintiff that, should it
elect to terminate the New Rochelle EPCA, Defendant would be obligated to pay Plaintiff: '(i) all
costs and expenses expended by Plaintiff (inclusive of the additional reasonable cost of Plaintiff's
employees and consultant ) to obtain and mobi lize a replacement contractor to complete the
Services; (ii) all costs incurred by Plaintiff to complete the terminated Services, less the amount
Plaintiff would have paid 64 Solar to complete such terminated Services in accordance with the
New Rochelle EPCA; and (iii) liquidated damages pursuant to Sections 8.1 and 8.2 of the ew
Rochelle EPCA' (id at ~ 44). Plaintiff as erts that the cure period ha expired without Defendant
curing any of the aforementioned defaults, and thus, "Plaintiff sent 64 Solar a notice of termination
of the New Rochelle EPCA (' R Notice of Termination ' )" on November 16, 2022 (id. at ~ 45).

C. Plaintiff's Causes of Action

Plaintiff ends its Complaint a serting two causes of action . The First Cause of Action is for
Breach of the Stony Point ECPA, and the Second Cause of Action is for Breach of the ew
Rochelle EPCA. Plaintiff states that it fully performed its obligations under both the Stony Point
EPCA and the ew Rochelle EPCA which require "64 Solar to , among other things, to deliver a
complete and operating System, to manage the schedu le for completion effectively, to obtain and
provide all approvals and permits in connection with the Syst m installation and maintenance,
obtain all equipment to be used in conn ction with the System and notify Plaintiff of its use of any
subcontractors in connection with the [Stony Point Project and New Rochelle Project] ' (id. at~~
47-48, 53 -54). Plaintiff states that Defendant "has willfully, and in bad faith failed to do any of the
above, despite being given notice and opportunity to cure as required by the [Stony Point ECPA
and ew Rochelle ECP A] , and accordingly has repeatedly and materially breached the [Stony
Point EPCA and New Rochelle ECPA]' (id at~~ 49 , 55). Plaintiff states it was forced to hire a
new contractor to complete the services Defendant was obligated and fai led, to perform, as a direct

[* 7] 7 of 13
FILED: WESTCHESTER COUNTY CLERK 09/19/2024 03:32 PM INDEX NO. 61484/2024
NYSCEF DOC. NO. 28 RECEIVED NYSCEF: 09/19/2024

8

and proximate result of Defendant's breaches of the EPCAs, and, " [m]oreover, [Defendant' s]
numerous material breaches of the [Stony Point EPCA and ew Rochelle EPCA] caused delays
and put Plaintiff in jeopardy of being in breach of its obligations to CE Solar" (id. at~~ 50, 56).
Plaintiff asserts that, " [a ]ccordingly, Plaintiff is entitled to compensatory and Iiquidated damages
in an amount to be determined at trial, but not less than $100,000, together with pre-judgment
interest" (id. at ~~ 51, 57).

PLAINTIFF'S CONENTIONS IN SUPPORT OF ITS MOTION
In support of its motion, Plaintiff submits: (1) an affirmation of James K. Landau, Esq.
dated June 25 , 2024 (NYSCEF Doc. No. 5 [the "Landau Aff. "]) and attached exhibits (NYSCEF
Doc. Nos. 6-1 0; (2) an affidavit of Dan Last, sworn to on June 24, 2024 (NYSCEF Doc. o 11
[' Last Aff. "]; and (3) a memorandum of law (NYSCEF Doc. o 24 ["Plf s Mem. "]).

In his affirmation Landau asserts that Plaintiff commenced this action by filing its
Summons and Complaint on May l , 2024 (Laundau Aff. at~ 2). Landau states that Plaintiff served
the Summons and Complaint thro ugh personal delivery to the office of ew York's Secretary of
State pursuant to New York 's Limi ted Liabil ity Company Law ("LLCL") § 303 , and that,
accordingly, "the deadline for Defendant ' s time to respond to the summons and complaint was
June 7, 2024' (id. at 113-4). Landau states that deadline has since passed "and Defendant has not
responded in any way to the summons an.d complaint nor has it requested any additional time to
respond. Accordingly, Defendant is in default in this action" (id. at 1 5). Landau states that " [o] n
June 11, 2024, [P]laintiff served additional notice of the action on Defendant in the manner
prescribed by CPLR § 3215(g)(4)" (id. at 16).

In his affidavi t, Dan Last asserts that he is Plaintiffs co-chief executi ve officer and has
personal knowledge of the facts set forth therein (Last Aff. at ~ I ). Last explains the factual
background of the Stony Point Project as et forth in the Complaint (Last Aff. at ~1 2-23). Last
asserts that following the otice of Termination effective ovember 25, 2022, "Plaintiff was
forced to hire and pay another contractor to comp! te the Services that 64 Solar had contract d to
perform in connection wi th the Stony Point Project. Plaintiffs costs and expenses incurred to
obtain and mobilize a replacement contract to complete the Services is $17 250. Plaintiff paid an
additional $332,041.98 to complete the Services on the Stony Point Project (id at ir~ 23-24). Last
states, with regard to the Stony Po int project, that Plaintiff achieved the Beneficial Use mil estone
on August 29, 2023 and achieved the Final Completion milestone on Nove mber 9, 2023 (id. at ~~
25 -26). I ast asserts that, due to the Defendant s defaults, failure to cure those defaults after notice,
Plaintiff terminated the Stony Point PCA before Beneficial Use and Final Completion were
reached, and "[t]hus under the Stony Point EPCA, Plaintiff is entitled to: (i) all costs and expenses
expended by Plaintiff (inclusive of the additional reasonable cost of Plaintiffs employees and
consultants) to obtain and mobilize a rep lacement contractor to complete the Services; (ii) all costs
incurred by Plaintiff to complete the terminated Services, less the amount Plaintiff would have
paid 64 So lar to complete such terminated Services in accordance with the Agreement; (iii)
liquidated damages pursuant to Agreement Section 8.1 of the Stony Point EPCA" (id. at 11 27-
28). Last asserts that " Plaintiff is entitled to $357,253.58 in damages pursuant to Stony Point
EPCA Section 10.1.3, and pre-judgment interest of an additional $34 917.73 through and

[* 8] 8 of 13
FILED: WESTCHESTER COUNTY CLERK 09/19/2024 03:32 PM INDEX NO. 61484/2024
NYSCEF DOC. NO. 28 RECEIVED NYSCEF: 09/19/2024

9

including July l, 2024, for a total due of $392,225.31 as of July 1, 2024", and he attaches a copy
of his damage and pre-interest calcu lations for the Stony Point EPCA as Exhibit F (id. at ,i 29).

Last next explains the factual background of the New Rochelle Project as set forth in the
Comp laint (Last Aff. at ,i 30-50). Last asserts that, following the Notice of Termination effective
November 25 2022, ' Plaintiff was forced to hire and pay another contractor to complete the
Services that 64 Solar had contracted to perform in connection with the New Rochelle Project.
Plaintiffs costs and expenses incurred to obtain and mobilize a replacement contract to comp.lete
the Services is $ I 7,250. Plaintiff paid an additional $ 499,921.23 to complete the Services on the
New Rochelle Project" (id. at ,i,i 50-51 ). Last states with regard to the New Rochelle project, that
Plaintiff achieved the Beneficial Use milestone on September 27 2023 and ach ieved the Final
Completion milestone on December 8, 2023 (id. at ,i,i 52-53). Last asserts that due to the
Defendant' s defaults, and their failure to cure those defaults after notice Plaintiff terminated the
New Rochelle EPCA before Beneficial Use and Final Comp letion were reached , and "[t]hus under
the New Rochelle EPCA, Plaintiff is entitled to: (i) all costs and expense expended by [Plaintiff]
(inclusive of the additional reasonable cost of (Plaintiff] ' s employees and consultants) to obtain
and mobilize a replacement contractor to complete the Services; (ii) all costs incurred by [Plaintiff]
to complete the terminated Services, less the amount [Plaintiff] would have paid [64 Solar] to
complete such term inated Services in accordance with the Agreement; (iii) liquidated damages
pursuant to Agreement Section 8.1 of the Stony Point EPCA" (id. at 1~154-55). Last asserts that
"Plainti ff is entitled to $509,547.23 in damages pursuant to New Rochelle EPCA, Section 10.1.3
and pre-judgment interest of an additional $49 879.08 through and including July 1, 2024, for a
total due of $559 426.31 a of July 1 2024", and he attaches a copy of hi s damage and pre-interest
calculations for the New Rochelle EPCA as Exhibit L (id. at ,i 56).

Based on the foregoing, Last requests 'that this Court enter judgment in favor of Plaintiff
and against 64 Solar in the total amount of $392,225 .31 (through July l , 2024) as a direct result of
64 Solar's defaults and failures to cure such defaults under the Stony Point EPCA and it is further
requested that this Court enter judgment in favor of Plaintiff and against 64 Solar in the total
amount of $559,426.31 (through July 1 2024) as a direct result of 64 Solar' defaults and failures
to cure such defaults under the . ew Rochelle EPCA" (id. at ,i 57).

In its memorandum of law, Plaintiff asserts that " under the Stony Point EPCA, Plaintiff is
entitled to: (i) all costs and expenses expended by [Plaintiff] (inclusive of the additional reasonable
cost of [Plaintiff] ' s employees and consultants) to obtain and mobilize a replacement contractor to
complete the Services· (ii) all costs incurred by [P lainti ff] to complete the terminated Services
less the amount [Plaintiff] would have paid [64 Solar] to complete such terminated Services in
accordance with the Agreement; (iii) liquidated damages pursuant to Agreement Section 8.1 of the
Stony Point PCA ... Plaintiff is entitled to $357,253 .58 in damages pursuant to Stony Point
EPCA, Section 10.1.3 , and pre-judgment interest of an additional $3 4,917.73 through and
including July 1 2024, for a total due of $392 225.31 a of July 1, 2024" (id. at 7). Plaintiff asserts
that " [u]nder the ew Rochelle EPCA , Plaintiff is entitled to: (i) all costs and expenses expended
by [Plaintiff] (inclusive of the additional reasonable cost of [Plainti ff]'s employees and
consultants) to obtain and mobilize a replacement contractor to complete the Services; (ii ) all costs

[* 9] 9 of 13
FILED: WESTCHESTER COUNTY CLERK 09/19/2024 03:32 PM INDEX NO. 61484/2024
NYSCEF DOC. NO. 28 RECEIVED NYSCEF: 09/19/2024

10

incurred by [Plaintiff] to complete the terminated Services, less the amount [Plaintiff! would have
paid (64 Solar] to complete such terminated Services in accordance with the Agreement; (ii i)
liquidated damages pursuant to Agreement Section 8 .1 of the New Rochelle EPCA . .. Plaintiff is
entitled to $509,547.23 in damages pursuant to New Rochelle EPCA, Section 10.1.3 , and pre-
judgment interest of an additional 49,879.08 through and including July 1, 2024 for a total due
of $559,426.31 as of July I 2024" (id. at 12-13). Plaintiff asserts that "[a]ccordingly, [it] is entitled
to judgment against 64 Solar in the amount of $392,225.3 1 (through July 1, 2024) as a direct result
of 64 olar's defaults and failures to cure such defaults under the Stony Point EPCA and in the
amount of $559,426.31 (through July l, 2024) as a direct result of 64 Solar's defaults and failures
to cure such defaults under the ew Rochelle EPCA" (id. at 13).

Plaintiff states that it commenced the action through purchasing an index numb rand filing
th summons and complaint on May 1, 2024, and that it served the summons and complaint in this
action through personal del ivery of such to the office of the Secretary of State, State ofNew York,
pursuan t to LLCL § 303 on May 8, 2024 (id.). Accordingly, Plaintiff asserts that " the deadline for
Defendant time to respond to the summons and complaint was June 7, 2024," but that Defendant
has not appeared in this action in any manner nor requested addi tional time to respond, and as
such is in default (id.). Plaintiff asserts it served the additional notice of the action, pursuant to
CPLR 3215(g)(4) on June 11 , 2024 (id.) .

For its legal argument, following a recap of the relevant procedural and factual history of
thi s case, Plaintiff explains that CPLR 3215 "provides that ' [w]hen a defendant has failed to
appear, plead or proceed to trial of an action reached and called for trial, the plaintiff may seek a
default judgment against him ' and that "[i]n order to prevail on a motion for the entry of a default
judgment a plaintiff must "'submit proof of service of the summons and complaint, proof of the
facts constituting [his] claim and proof of [Defendan t '] default in answering or appearing"' (id.
at 14, quoting CPLR 321 S[fJ) . Plaintiff asserts it has demonstrated service of the Summons and
Complaint on Defendant and submitted proof of such service, as well as the additional notice of
the action and that Defendant 's time to re pond to the Complaint has expired (id. al 15). Plaintiff
asserts it has demonstrated the requisite showing to prevail on a cause of action for breach of
contract for both the First and Second Causes of action, namely "( l) fo m1ation of a contract
between plaintiff and defenda_nt (2) performance by plaintiff (3) defendant's failure to perform
and (4) resulti.ng damage" (id. at 14- 15). Plaintiff states it has: (1) demonstrated the contracts (the
Stony Point EPCA and New Rochelle EPCA), entered into between it and Defendant; (2) .its
performance under the Stony Point EPCA and New Rochelle EPCA; (3) Defendant's "numerous
breaches" of the Stony Point EPCA and New Rochelle EPCA; and (4) the damages and
prejudgment interest it is ntitled to recover from Defendant as a result of its breaches (id).

DISCUSSION

A. Standard of Review Pursuant to CPLR 3215

Pursuant to CPLR 321 S(f), '" [a]n applicant for a default j udgment against a defendant must
submit proof of service of the summons and complaint, proof of the facts constituting the claim,
and proof of the defaulting defendant s failure to answer or appear " (Lancer Ins. Co. v Fishkin,

[* 10] 10 of 13
FILED: WESTCHESTER COUNTY CLERK 09/19/2024 03:32 PM INDEX NO. 61484/2024
NYSCEF DOC. NO. 28 RECEIVED NYSCEF: 09/19/2024

11

211 AD3d 719, 720 [2d Dept 2022], quoting Counlfywide Horne Loans Servicing, L.P. v
Vorobyov, 188 AD3d 803, 806 [2d Dept 2020] ; see also Atlantic Cas. Ins. Co. v RJNJ Serv. Inc.,
89 AD3d 649 [2d Dept 2011 ]). "To demonstrate the facts constituting the claim, the movant need
only submit sufficient proof to enable a court to determine if the claim is viable" (Lancer Ins. Co.,
211 AD3d at 721).

However default judgments are not to be rubber-stamped once jurisdiction and failure to
appear are shown. Proof must sti ll be submitted to satisfy the Court, at least prima facie, as to the
viability of the uncontested cause of action (Joosten v Gale , 129 AD2d 531 [I st Dept 1987]; see
CPLR 3215[b] [f]). Even if there appears to be no opposition, the Court should not exercise its
power, whether statutory or inherent, in a manner or under such circumstances where that power
could work an injustice to litigants or to non-parties (Rivera v Laporte, 120 Misc 2d 733 , 735 [Sup
Ct, New York County 1983 ]).

To avoid the entry of a default judgment the defaulting party is required to demonstrate a
reasonable excuse for the default and a meritorious defense to the action (Grinage v City of N. Y ,
45 AD3d 729 [2d Dept 2007]; Zino v Joab Taxi, Inc., 20 D3d 521 [2d Dept 2005] ; Pampa lone v
Giant Bldg. Maintenance, Inc. , 17 AD3d 556 [2d Dept 2005]; Ennis v Lema, 305 AD2d 632 [2d
Dept 2003]). The determination of what constitutes a reasonable excuse for a default lies within
the sound discretion of the court (Grinage, 45 AD3d 729; Ennis, 305 AD2d 632).

B. Service of Process and Merits of the Claim

Plaintiff has established its entitlement to a default judgment against Defendant ba ed on
its submission of evidence of its service of the Summons and Complaint on Defendant and its
compliance with the additional notice requirement under CPLR 3215(g)(4) and Defendant ' s
default in failing to timely respond to the Complaint (see TCIF REO GCM, LLC v Walker 139
AD3d 704 [2d Dept 2016) ; U.S. Bank Nat. Assn. v Poku, 118 AD3d 980 [2d Dept 2014]). It has
also established the merits of its claim through the Last Affidavit (see CPLR 3215[t] ; HSBC Bank
USA, NA . v Thorne , 189 AD3d 1193 [2d Dept 2020) [affirming a default judgment where the
plaintiff submitted an ' affidavit of merit" based upon personal knowledge in compliance with
CPLR 3215(±)]; Deutsche Bank Natl. Trust Co. v Silverman, 178 AD3d 898, 900 [2d Dept 2019]
[holding that " [t]he affidavit of merit from a representative of the plaintiffs ... was competent
evidence to establish the plaintiff's entitlement to a default judgment against [the defendant]"]).
Thus, Plaintiff established entitlement to default judgment "by providing proof of service of the
summons and complaint, proof of the facts constituting the claim, and proof of the defendants'
failure to . . . appear" (Deutsche Bank at. Tr. Co. v Otano , 129 AD3d 770, 771 [2d Dept 2015]).

Plaintiff has also established prima facie, the merits of its claims for breach of contract.
"The essential elements of a cause of action to recover damages for breach of contract are the
existence of a contract, the plaintiffs performance pursuant to the contract, the defendant's breach
of its contractual obligations, and damages resulting from the breach" (Tudor Ins. Co. v Unithree
Inv. orp., 137 AD3d 1259, 1260 [2d Dept 2016]). "To establish the existence of an enforceable
agreement, a plaintiff must establi h an offer, acceptance of the offer, consideration, mutual assent,
and an intent to be bound" (Kowalchuk v. Stroup, 61 AD3d 118 121 [l st Dept 2009]). Here,
Plaintiff has submitted evidence establishing, prima facie , the parties' entry into the Stony Point

11 of 13
[* 11]
FILED: WESTCHESTER COUNTY CLERK 09/19/2024 03:32 PM INDEX NO. 61484/2024
NYSCEF DOC. NO. 28 RECEIVED NYSCEF: 09/19/2024

12

EPCA and the New Rochelle EPCA, Defendant's breach of those agreements and that it has
sustained damages (IP FS Corp. v Mane/ta Enterprises, Inc. 160 AD3d 706, 707 [2d Dept 2018]).

However, Plaintiff has not submitted evidence substantiating various damage figures set
forth in the Last Affidavit, such as the costs Plaintiff incurred to complete the projects and whether
such costs were reasonable (Ben Ciccone, Inc. v Naber Elec. Corp., 2 I 4 AD3d 936 [2d Dept 2023];
Caggianelli v Sontheimer 46 AD3d 1206 [3d Dept 2007]; RBS Citizens, NA. v Dynamic Biz, Inc. ,
80 AD3d 868 [3d Dept 20 11]; Wamco XVII v Chestnut Estates Dev, Corp. , 25 l AD2d 888 [3d
Dept 1998]). A party in default only admits liability and does not adm it to the damages alleged in
the complaint (see McClelland v Climax Hosie,y Mills, 252 Y 347 [1930] ; Commonwealth Land
Title In . Co. v Islam, 220 AD3d 739 [2d Dept 2023]; Boorman v Deut ch, 152 AD2d 48 [1st Dept
1989], Iv dismissed 76 NY2d 889 [1990]; Paulson v Kotsilimbas, 124 AD2d 513 [1st Dept 1986];).
Where a party has defaulted and the amount of damages to award is unclear, the court may order
the parties to appear at an inquest to determine the amount to be awarded for damages (see Paulson,
124 AD2d 513 ; ervino, 91 AD2d 249). Moreover, courts may exercise wide discretion when
assessing the merits of damages alleged in default judgments in order to avoid excessive penalties
(see CPLR 3215[b]; Neuman v Greenblall, 260 AD2d 616 , 617 [2d Dept 1999] ["' [i]t has long
been held that courts have inherent power beyond that which is contained in the CPLR ... to open
defaults . . . and where the amount awarded on a default judgment has been perceived as excessive
the court have exercised their inherent power to modify or reduce th amount' "]). "An
unwarranted and excessive award after inquest will not be sustained as to do otherwise ' would be
tantamount to granting the plaintiffs an "open season" at the expense of a defaulting defendant"'
(Neuman, 260 AD2d at 617 , quoting Brosnan v Behette , 186 AD2d l 65, 167 [2d Dept 1992], lv
denied 81 Y2d 706 [ 1993 ]). Accordingly while the Court shall award Plaintiff a default
judgment against Defendant as to its liability, the amount to be awarded as damages shall be
determined following an inquest.

CONCLUSION
Accordingly for the reasons stated and based upon the papers aforesaid , it is hereby

ORDERED that the motion by Plaintiff Mission Energy Founders LLC f/k/a Mission
Energy L C seeking a default judgment against Defendant 64 Solar LLC on its First and Second
Causes of Action as to liabi lity only is granted; and it is further

ORDERED that the matter is s t down for an inquest to determine damages on October 2 1,
2024 at 2 :00 p.m. ; and it is further
ORDERED that Plaintiff shall pursuant to the provi sions of22 .Y.C.R.R §202.48 submit
a proposed judgment, and a bill of costs on notice to Defendants to the Court for settl ment on
October 21 , 2024 at 2:00 p.m. , with the amount to be awarded for damages and interest and costs
being left blank so that the Court may insert the amounts awarded, if any, at the conclusion of the
inquest ordered herein; an.d it is further
ORDERED that Plaintiff's counsel shall serve upon the Defendant by certified mail , return
receipt requested and by overnight delivery (next day delivery) and file in NYSCEF a copy of this
Decision and Order with otice of Entry, a Notice of Inquest on or before September 23, 2024.

[* 12] 12 of 13
FILED: WESTCHESTER COUNTY CLERK 09/19/2024 03:32 PM INDEX NO. 61484/2024
NYSCEF DOC. NO. 28 RECEIVED NYSCEF: 09/19/2024

13

The foregoing constitutes the Decision and Order of this Court.

Dated: White Plains, New York
September ( j , 2024
ENTER:

~ S H J.S .C.

LACHTMAN COHEN & BELOWICH LLP
By: James K. Landau, Esq.
Attorneys for Plaintiff
256 Main St, Suite 230
White Plains Y 10601