# Huhn

> District Court, E.D. California · December 22, 2025

URL: https://www.frixlaw.com/law-library/cases/11232355

## Case

- **Full name:** Robert Huhn, dba Huhn Electric v. City of Red Bluff, et al.
- **Court:** District Court, E.D. California
- **Decided:** December 22, 2025
- **Opinion:** 100trialcourt
- **Cited by:** 0 later opinions in the Frix Law Library

## Citator (automated)

- No negative treatment found by the automated citator. That is not the same as a confirmation that the case is good law; read the citing cases.
- Full citator and citing cases: https://www.frixlaw.com/law-library/cases/11232355

## Opinion text

1
2
3
4
5
6
7
8 IN THE UNITED STATES DISTRICT COURT
9 FOR THE EASTERN DISTRICT OF CALIFORNIA
10
11 ROBERT HUHN, dba Huhn Electric, No. 2:25-CV-1777-DMC
12 Plaintiff,
13 v. ORDER
14 CITY OF RED BLUFF, et al.,
15 Defendants.
16
17 Plaintiff, who is proceeding with retained counsel, brings this civil action. The
18 parties have consented to Magistrate Judge jurisdiction and the case has been reassigned. See
19 ECF No. 18. Pending before the Court is Defendants’ motion to dismiss. See ECF Nos. 9 (initial
20 motion) and 11 (amended points and authorities). Plaintiff has filed an opposition, see ECF No.
21 20, and Defendants have filed a reply, see ECF No. 21. The parties appeared for a hearing before
22 the undersigned and, following oral arguments, the Court granted Defendants’ motion and
23 dismissed the complaint with leave to amend. Plaintiff has since filed his first amended
24 complaint. See ECF No. 23. This order will formally confirm the Court’s oral ruling from the
25 bench and direct Defendants to file a response to Plaintiff’s first amended complaint.
26 / / /
27 / / /
28 / / /
1 In considering a motion to dismiss, the Court must accept all allegations of
2 material fact in the complaint as true. See Erickson v. Pardus, 551 U.S. 89, 93-94 (2007). The
3 Court must also construe the alleged facts in the light most favorable to the plaintiff. See Scheuer
4 v. Rhodes, 416 U.S. 232, 236 (1974); see also Hosp. Bldg. Co. v. Rex Hosp. Trustees, 425 U.S.
5 738, 740 (1976); Barnett v. Centoni, 31 F.3d 813, 816 (9th Cir. 1994) (per curiam). All
6 ambiguities or doubts must also be resolved in the plaintiff's favor. See Jenkins v. McKeithen,
7 395 U.S. 411, 421 (1969). However, legally conclusory statements, not supported by actual
8 factual allegations, need not be accepted. See Ashcroft v. Iqbal, 129 S. Ct. 1937, 1949-50 (2009).
9 In addition, pro se pleadings are held to a less stringent standard than those drafted by lawyers.
10 See Haines v. Kerner, 404 U.S. 519, 520 (1972).
11 Federal Rule of Civil Procedure 8(a)(2) requires only “a short and plain statement
12 of the claim showing that the pleader is entitled to relief” in order to “give the defendant fair
13 notice of what the . . . claim is and the grounds upon which it rests.” Bell Atl. Corp v. Twombly,
14 550 U.S. 544, 555 (2007) (quoting Conley v. Gibson, 355 U.S. 41, 47 (1957)). However, in order
15 to survive dismissal for failure to state a claim under Rule 12(b)(6), a complaint must contain
16 more than “a formulaic recitation of the elements of a cause of action;” it must contain factual
17 allegations sufficient “to raise a right to relief above the speculative level.” Id. at 555-56. The
18 complaint must contain “enough facts to state a claim to relief that is plausible on its face.” Id. at
19 570. “A claim has facial plausibility when the plaintiff pleads factual content that allows the
20 court to draw the reasonable inference that the defendant is liable for the misconduct alleged.”
21 Iqbal, 129 S. Ct. at 1949. “The plausibility standard is not akin to a ‘probability requirement,’ but
22 it asks for more than a sheer possibility that a defendant has acted unlawfully.” Id. (quoting
23 Twombly, 550 U.S. at 556). “Where a complaint pleads facts that are ‘merely consistent with’ a
24 defendant’s liability, it ‘stops short of the line between possibility and plausibility for entitlement
25 to relief.” Id. (quoting Twombly, 550 U.S. at 557).
26 / / /
27 / / /
28 / / /
1 In deciding a Rule 12(b)(6) motion, the Court generally may not consider materials
2 outside the complaint and pleadings. See Cooper v. Pickett, 137 F.3d 616, 622 (9th Cir. 1998);
3 Branch v. Tunnell, 14 F.3d 449, 453 (9th Cir. 1994). The Court may, however, consider: (1)
4 documents whose contents are alleged in or attached to the complaint and whose authenticity no
5 party questions, see Branch, 14 F.3d at 454; (2) documents whose authenticity is not in question,
6 and upon which the complaint necessarily relies, but which are not attached to the complaint, see
7 Lee v. City of Los Angeles, 250 F.3d 668, 688 (9th Cir. 2001); and (3) documents and materials
8 of which the court may take judicial notice, see Barron v. Reich, 13 F.3d 1370, 1377 (9th Cir.
9 1994).
10 Finally, leave to amend must be granted “[u]nless it is absolutely clear that no
11 amendment can cure the defects.” Lucas v. Dep’t of Corr., 66 F.3d 245, 248 (9th Cir. 1995) (per
12 curiam); see also Lopez v. Smith, 203 F.3d 1122, 1126 (9th Cir. 2000) (en banc).
13
14 I. PLAINTIFF’S ALLEGATIONS
15 This action proceeds on Plaintiff’s complaint, filed in state court and removed to
16 this Court on June 25, 2025. See ECF No. 1. Plaintiff, a licensed electrical contractor, is an
17 individual doing business as Affordable Solar Energy. See id. at 6. Plaintiff names the
18 following as defendants: (1) City of Red Bluff; (2) Beth Lindauer, the City of Red Bluff’s
19 Community Development Director; (3) Tom Westbrook, the City of Red Bluff’s City Manager;
20 and (4) Anita Rice, the City of Red Bluff’s Deputy City Clerk. See id. at 6-7.
21 Plaintiff states that, in October 2024, he was contracted to install a solar energy
22 system at the First Church of God, a commercial property located in Red Bluff. See id. at 8.
23 Plaintiff submitted to the City of Red Bluff a building plan for a commercial solar installation
24 permit on October 16, 2024. See id. On October 17, 2024, Plaintiff received an invoice for
25 permit application fees in the amount of $1,000.00, which Plaintiff asserts is the maximum
26 amount allowed under the California Solar Rights Act. See id. This fee included a charge of
27 $188.00 for a fire department inspection. See id.
28 / / /
1 Plaintiff was informed that he could not pay the full fees online because the City
2 of Red Bluff’s online payment system only accepted payments up to $550.00. See id. As a
3 result, Plaintiff reported in-person to pay the fees and was told he could make separate
4 payments through the online system. See id. Plaintiff states, however, that the online system
5 would not accept separate payments. See id.
6 Plaintiff began preliminary work on the solar project on October 18, 2024. See
7 id. During this process, Plaintiff discovered significant structural issues on the church roof that
8 required changes to the original building plan and layout. See id. Based on these findings,
9 Plaintiff revised the installation layout. See id. at 9. On October 21, 2024, an inspector for the
10 City of Red Bluff issued a stop-work order on the project because the initial permit process had
11 not been finalized and because the installation layout no longer matched the plans originally
12 submitted. See id. The same day, Plaintiff went to the city’s offices to complete payment and
13 explain the layout changes. See id.
14 When Plaintiff appeared again at the city’s offices to pay the permit fees, he was
15 informed that a permit would not be issued because the current layout plan no longer matched
16 the plan submitted with the original permit application. See id. Plaintiff explained to city
17 officials, including Defendant Lindauer, that the layout changes were required for structural
18 safety and requested that the city issue the permit and allow him to submit an updated plan. See
19 id. Plaintiff alleges that, despite accepting Plaintiff’s payment of $1,000.00, no permit was
20 issued. See id.
21 Plaintiff also states that, during this interaction with city officials, he questioned
22 the legality of the $188.00 fire department inspection fee based on lack of any city ordinance or
23 resolution authorizing such a fee. See id. Plaintiff further argued that the fire department
24 inspection would be duplicative of the inspection which was already required by the Building
25 Department. See id.
26 / / /
27 / / /
28 / / /
1 Plaintiff claims that, in response to his questions about the fire department
2 inspection fee, Defendant Lindauer “issued a retaliatory threat.” Id. Plaintiff claims:

3 . . . She [Defendant Lindauer] stated that if Plaintiff continued to challenge
the commercial solar inspection fees, she would instruct the fire department
4 to reinstate the residential solar permit fees. Those residential fees had
previously been eliminated following Plaintiff’s earlier objections to their
5 legality. This threat directly tied the possibility of adverse government
action to Plaintiff’s constitutionally protected speech. The statement had
6 the clear potential to chill future speech, precisely the type of retaliatory
conduct that is prohibited under the established First Amendment
7 jurisprudence.

8 Id.
9 Plaintiff states that a permit was ultimately issued on October 24, 2024. See id. at 10.
10 Following the incident with Defendant Lindauer, Plaintiff contacted the City
11 Manager, Defendant Westbrook to report the retaliatory threat. See id. Defendant Westbook
12 reported to Plaintiff that he would review surveillance footage of Plaintiff’s encounter with
13 Defendant Lindauer. See id. While Defendant Westbook promised to follow up, Plaintiff
14 contends he never did so. See id.
15 On October 28, 2024, Plaintiff submitted a formal public records request
16 seeking: (1) all ordinances pertaining to residential and commercial solar permit fees; (2) audio
17 and video recordings from the encounter with Defendant Lindauer; and (3) any ordinance or
18 written authorization allowing the fire department to impose inspection fees for solar
19 installations. See id. at 10-11. On November 19, 2024, Plaintiff called city offices to inquire
20 about his records request. See id. at 11. According to Plaintiff, Defendant Rice, who is the
21 Deputy City Clerk, informed Plaintiff that the city believed his request had “gone away”
22 because Plaintiff previously met with city officials. Id. Plaintiff states that he told Defendant
23 Rice that he never withdrew his request. See id. Plaintiff adds that, on November 20, 2024,
24 Defendant Rice sent Plaintiff an email providing some, but not all, of the requested documents.
25 See id. According to the November 20, 2024, email, Defendant Rice stated that surveillance
26 video footage from October 23, 2024, was no longer available. See id. Plaintiff contends that,
27 as of the filing of the complaint, he still had not received all of the requested records. See id.
28 / / /
1 Plaintiff asserts the following claims:

2 FIRST CLAIM Retaliation in violation of the First Amendment
pursuant to 42 U.S.C. § 1983 (against all Defendants).
3
SECOND CLAIM Violation of the California Public Records Act
4 (against Defendant City of Red Bluff).

5 THIRD CLAIM Violation of the California Solar Rights Act
(against Defendant City of Red Bluff).
6
FOURTH CLAIM Unlawful business practices (against Defendant
7 City of Red Bluff).

8 FIFTH CLAIM Negligence (against all Defendants).

9 SIXTH CLAIM Intentional interference with prospective
economic advantage (against all Defendants).
10
ECF No. 1, pgs. 12-21.
11
12
13 II. DISCUSSION
14 In their motion to dismiss, Defendants argue: (1) the complaint fails to state a
15 claim for violation of the First Amendment as against any defendant; (2) there is no right of
16 action against a public entity under California’s Solar Rights Act; (3) there is no right of action
17 against a public entity under California’s unfair business practices law; and (4) the negligence
18 claim is deficient because Plaintiff fails to allege any duty owed and because the claim is barred
19 by state law immunities. See ECF No. 11. Because this Court declines to exercise
20 supplemental jurisdiction over pendent state law claims in the absence of a cognizable federal
21 law claim, Plaintiff’s First Amendment retaliation claim is discussed first.
22 To state a claim under 42 U.S.C. § 1983 for retaliation, the plaintiff must establish
23 that he was retaliated against for exercising a constitutional right, and that the retaliatory action
24 was not related to a legitimate penological purpose. See Barnett v. Centoni, 31 F.3d 813, 815-16
25 (9th Cir. 1994) (per curiam). In meeting this standard, the plaintiff must demonstrate a specific
26 link between the alleged retaliation and the exercise of a constitutional right. See Pratt v.
27 Rowland, 65 F.3d 802, 807 (9th Cir. 1995); Valandingham v. Bojorquez, 866 F.2d 1135, 1138-39
28 (9th Cir. 1989). The plaintiff must also show that the exercise of First Amendment rights was
1 chilled, though not necessarily silenced, by the alleged retaliatory conduct. See Resnick v. Hayes,
2 213 F.3d 443, 449 (9th Cir. 2000), see also Rhodes v. Robinson, 408 F.3d 559, 569 (9th Cir.
3 2005). Thus, the plaintiff must establish the following in order to state a claim for retaliation: (1)
4 government officials took adverse action against the plaintiff; (2) the adverse action was taken
5 because the plaintiff engaged in protected conduct; (3) the adverse action chilled the plaintiff’s
6 First Amendment rights; and (4) the adverse action did not serve a legitimate governmental
7 purpose. See Rhodes, 408 F.3d at 568.
8 As to Plaintiff’s First Amendment retaliation claims, Defendants argue that the
9 claims, as currently pleaded, fail because Plaintiff has not alleged facts to show that Defendant
10 Lindauer’s comments or Defendant Westbrook’s conduct chilled Plaintiff’s ability to engage in
11 protected activity. See ECF No. 11. Next, Defendants argue that Plaintiff has failed to allege
12 facts to show Defendant Rice’s involvement. See id. Next, Defendants contends that Plaintiff
13 has failed to allege sufficient facts to establish municipal liability against Defendant City of Red
14 Bluff. Finally, Defendants argue that Lindauer and Westbrook are entitled to qualified immunity.
15 See id.
16 For all defendants, Plaintiff needs to allege facts to show that adverse action was
17 taken against him because he complained about fees. Here, Plaintiff has failed to do so.
18 Rather, he asserts facts indicating his speculation that adverse action may be taken if Plaintiff
19 continued to complain. Further, notwithstanding Plaintiff’s complaints and the alleged threats,
20 Plaintiff was issued a permit. On the facts currently alleged, Plaintiff has not shown adverse
21 action sufficient to support a First Amendment retaliation claim.
22 More specifically as to Defendants Westbrook and Rice, Plaintiff has not alleged
23 their involvement in any threats against Plaintiff should he continued to make complaints about
24 fees. Rather, Defendant Westbrook is alleged to have failed to follow up on review of
25 surveillance footage, and Defendant Rice is alleged to have failed to provide all of the public
26 record requested by Plaintiff. These allegations do not indicate that either Defendant
27 Westbrook or Defendant Rice took any adverse action against Plaintiff on account of
28 complaints about fees.
] Finally, Defendants’ argument concerning municipal liability is persuasive.
2 | Municipalities and other local government units are among those “persons” to whom § 1983
3 || liability applies. See Monell v. Dep’t of Soc. Servs., 436 U.S. 658, 690 (1978). Counties and
4 | municipal government officials are also “persons” for purposes of § 1983. See id. at 691; see also
5 || Thompson v. City of Los Angeles, 885 F.2d 1439, 1443 (9th Cir. 1989). A local government
6 || unit, however, may not be held responsible for the acts of its employees or officials under a
7 || respondeat superior theory of liability. See Bd. of County Comm’rs v. Brown, 520 U.S. 397, 403
8 | (1997). Thus, municipal liability must rest on the actions of the municipality, and not of the
9 || actions of its employees or officers. See id. To assert municipal liability, therefore, the plaintiff
10 || must allege that the constitutional deprivation complained of resulted from a policy or custom of
11 | the municipality. See id.
12 Here, even if Plaintiffs First Amendment claims against one of the individual
13 || defendants was viable — and they are not as currently pleaded — Plaintiff would still need to
14 | allege the existence of some kind of municipal policy, custom, or practice which allowed the
15 || individual defendants to retaliate against him. He has failed to do so in the operative complaint.
16
17 Il. CONCLUSION
18 Accordingly, IT IS HEREBY ORDERED as follows:
19 1. Defendants’ motion to dismiss, ECF Nos. 9 and 11, is GRANTED.
20 2. Plaintiff's complaint, ECF No. 1, is dismissed with leave to amend.
21 3. Plaintiff's first amended complaint, ECF No. 23, filed on December 18,
22 || 2025, is deemed timely.
23 4. Defendants shall file a response to Plaintiffs first amended complaint
24 || within 30 days of the date of this order.
25 | Dated: December 19, 2025 Co
26 DENNIS M. COTA
07 UNITED STATES MAGISTRATE JUDGE
28

---