# Evolution Construction, LLC v. Finomus Orange Re Holdings, LLC

> New Jersey Superior Court Appellate Division · July 16, 2025

URL: https://www.frixlaw.com/law-library/cases/11100189

## Case

- **Court:** New Jersey Superior Court Appellate Division
- **Decided:** July 16, 2025
- **Precedential status:** Unpublished
- **Opinion:** Opinion
- **Cited by:** 0 later opinions in the Frix Law Library

## Citator (automated)

- No negative treatment found by the automated citator. That is not the same as a confirmation that the case is good law; read the citing cases.
- Full citator and citing cases: https://www.frixlaw.com/law-library/cases/11100189

## How later opinions describe it (automated extraction)

- stating "[r]aising an issue for the first time in a reply brief is improper"
- explaining "a third party is deemed to be a beneficiary of a contract only if the contracting parties so intended when they entered into their agreement"

## Opinion text

NOT FOR PUBLICATION WITHOUT THE
APPROVAL OF THE APPELLATE DIVISION
This opinion shall not "constitute precedent or be binding upon any court ." Although it is posted on the
internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.

SUPERIOR COURT OF NEW JERSEY
APPELLATE DIVISION
DOCKET NO. A-1405-23

EVOLUTION CONSTRUCTION,
LLC,

Plaintiff-Respondent,

v.

FINOMUS ORANGE RE HOLDINGS,
LLC, FINOMUS EAST BRUNSWICK
RE HOLDINGS, LLC, YUM & CHILL
ORANGE TB, LLC, YUM & CHILL
MANAGEMENT, LLC, and YUM &
CHILL EAST BRUNSWICK, TB, LLC,

Defendants-Appellants.
__________________________________

Submitted May 15, 2025 – Decided July 16, 2025

Before Judges Mawla and Natali.

On appeal from the Superior Court of New Jersey, Law
Division, Somerset County, Docket No. L-0522-18.

Scarinci & Hollenbeck, LLC, attorneys for appellants
(Joel N. Kreizman, of counsel and on the brief).

McHugh and Brancato, LLP, attorneys for respondent
(Mark J. Brancato, on the brief).
PER CURIAM

On December 14, 2023, after an eight-day bench trial, the court entered

judgment in favor of plaintiff Evolution Construction, LLC, after it determined

defendants Finomus Orange RE Holdings, LLC (Finomus Orange), and Finomus

East Brunswick RE Holdings, LLC (Finomus East Brunswick), breached two

contracts for the construction of fast-food restaurants. It also rejected and

accordingly dismissed defendants Finomus Orange's, Finomus East

Brunswick's, Yum and Chill Orange TB, LLC's, Yum and Chill Management,

LLC's, and Yum and Chill East Brunswick, TB, LLC's (collectively Yum and

Chill Entities) counterclaims sounding in breach of contract. Based upon our

review of the record and applicable legal principles, we affirm in part, reverse

in part, and remand for further proceedings.

I.

This matter concerns a dispute between the parties regarding the delayed

construction of two Taco Bell restaurants in Orange and East Brunswick. In

October 2015, plaintiff entered into two construction contracts with Finomus

Orange and Finomus East Brunswick to build the restaurants. Under both

contracts, plaintiff had ninety days to complete construction and turn the

A-1405-23
2
properties over to defendants. Plaintiff was to be paid $800,000 to construct the

Orange restaurant, and $780,000 for the East Brunswick location.

With respect to the Orange contract, two blank lines appeared where the

date of commencement and "outside date for substantial completion and

turnover" were supposed to be completed. As to the East Brunswick contract,

the date of commencement was designated as October 12, 2015, and "the outside

date for substantial completion and turnover" was January 9, 2016. Save for

these differences and the project locations, the two contracts were otherwise

identical.

As relevant here, Article 9 addressed issues pertaining to timing and

delays. Article 9.1 provided "time [was] of the essence" and stated plaintiff

would be liable to defendants "for all damages resulting from [plaintiff's] failure

to commence or complete the [w]ork in accordance with the" ninety-day

timeframe. Article 9.2 defined certain circumstances that would toll the ninety-

day requirement and grant plaintiff an extension of the contract time:

In the event construction of the [p]roject or completion
of any portion of the [w]ork is unavoidably delayed by
(i) extraordinary conditions of weather for the area and
time of year, in excess of that normally encountered,
(ii) war or national conflicts or the arising there from,
(iii) strikes or other labor disruptions beyond the
control of [plaintiff] (except the first five . . . working
days of any strike or labor disruption), (iv) fires,

A-1405-23
3
earthquakes, floods or other natural disasters, the
damage from which was beyond the control of
[plaintiff], or (v) the acts (including [c]hanges) or
omission of [Finomus Orange or Finomus East
Brunswick] or its designated representatives, [plaintiff]
shall continue to advance the [w]ork as expeditiously
as possible. To the extent such unavoidable delays
cause a critical delay to the overall completion of the
[w]ork, [plaintiff] by [c]hange [o]rder shall be entitled
to an extension of the [c]ontract [t]ime in an amount
equal to the number of calendar days completion of the
[w]ork was actually delayed. However, no extension of
the [c]ontract [t]ime shall be granted unless [plaintiff]
has delivered to [Finomus Orange or Finomus East
Brunswick] a written notice of the cause of the delay
with[in] ten . . . days after the commencement of the
delay and has demonstrated that such delay was on the
critical path of the [c]onstruction [p]rogress [s]chedule.

The contract also provided plaintiff was responsible for obtaining "all

licenses, permits, approvals, and certificates," and Finomus Orange and

Finomus East Brunswick would not be liable to plaintiff "for any delays

in . . . obtaining the building permit." As to payments, Article 17.6.1 required

Finomus Orange and Finomus East Brunswick to "make payment to [plaintiff]

of all undisputed amounts due and owing [plaintiff] not later than twenty[ -]one

. . . days following [Finomus Orange's and Finomus East Brunswick's] receipt

and acceptance of [plaintiff's] application for payment."

To achieve substantial completion, Article 19.1.1 required plaintiff turn

the property over such that it may be fully occupied and "use[d] for the purpose

A-1405-23
4
that the [p]roject was intended." In order to attain final completion, Articles

20.1 and 20.2 required the parties to generate a punch list of work which plaintiff

would have ten calendar days to complete. With respect to final payment, the

contract provided "the release of the ten percent . . . retainage amount . . . shall

be made by [Finomus Orange and Finomus East Brunswick] to [plaintiff] when

the [c]ontract and [w]ork required thereunder have been fully performed."

Additionally, under the contract, Finomus Orange and Finomus East Brunswick

were permitted to "withhold any amounts due [by it] as provided for in th[e

c]ontract or which [they] dispute[d were] due [plaintiff]."

Almost immediately after the parties executed the contracts, as we discuss

in greater detail below, plaintiff encountered numerous delays with both

projects. These delays included, among other things, weather-related issues,

prolonged permit-approval processes, and unanticipated issues with the local

utility company. As a result, plaintiff did not finish construction of either

restaurant within the original ninety-day timeframes.

Due to the delayed construction processes, Finomus Orange and Finomus

East Brunswick withheld multiple progress payments and final payments due

plaintiff. Because it had not received these payments, plaintiff repudiated its

A-1405-23
5
obligation to complete all punch list items and supply defendant with a list of

its subcontractors as well as their contact information.

As a result, on April 23, 2018, plaintiff filed a six-count complaint against

Finomus Orange and Finomus East Brunswick, alleging breach of contract,

unjust enrichment, and money due under a book account. With respect to the

Orange contract, plaintiff alleged Finomus Orange owed $124,852.96, plus

interest. With respect to the East Brunswick contract, plaintiff claimed Finomus

East Brunswick owed $113,916.07, plus interest.

Finomus Orange and Finomus East Brunswick answered, asserted various

affirmative defenses, and filed a counterclaim. They alleged plaintiff breached

the contracts by failing to complete the projects within ninety-days, and plaintiff

failed to "adequately address the punch list items necessary to obtain

[certificates] of [o]ccupancy and to ultimately open for business." As a result

of these purported breaches, Finomus Orange and Finomus East Brunswick

alleged they "incurr[ed] damages in the form of unnecessary carrying charges

for mortgage and taxes, payroll expenses[,] and operating expenses in order to

complete the project[,] which would not have been incurred but for [p]laintiff's

breach of contract."

A-1405-23
6
At trial, plaintiff called as its only witness Vice President of Evolution

Construction Georges Chalemin, who first provided testimony with respect to

the East Brunswick restaurant. According to Chalemin, plaintiff filed for a

demolition permit with East Brunswick on August 3, 2015, approximately two

months before the parties executed the contract. East Brunswick approved the

permit and, according to Chalemin, demolition began on October 12, 2015.

With respect to the building permit, Chalemin testified plaintiff also applied for

that permit on August 3, and East Brunswick approved it on November 19, 2015.

Chalemin further explained some work on the property, specifically the

front area which required work on the curb and sidewalk, was under the

jurisdiction of the New Jersey Department of Transportation (DOT). According

to Chalemin, despite initial plans to replace the curb to comply with DOT

requirements, Finomus East Brunswick did not want to spend additional money

on replacing the curb and asked plaintiff to meet with the DOT and urge them

to keep the existing curbing and sidewalks. Chalemin further explained the DOT

had a cold weather prohibition period from January 5 to March 15, 2016, where

no work was permitted on DOT controlled areas. 1

1
Chalemin testified work during this cold weather prohibition period was
further delayed by a snowstorm, which made work impossible between January
25 to February 11, 2016.
A-1405-23
7
Because of the requested deviation from the original plans, the DOT did

not issue a permit to complete the work until April 19, 2016, which plaintiff

completed the next day. Another deviation from the original plans occurred

when the township of East Brunswick required the existing four-inch sewer line

be replaced with a six-inch line, resulting in a delay of "a couple of weeks."

According to Chalemin, East Brunswick completed final inspections of the

property on April 29, 2016, and the certificate of occupancy was issued on May

3.

As to communications between plaintiff and Finomus East Brunswick,

Chalemin testified he communicated with Finomus East Brunswick's

representative, Nirav Mehta, daily. Chalemin explained plaintiff ultimately did

not complete the punch list items associated with the East Brunswick project

because defendants were two months behind on their progress payments.

With respect to the Orange location, Chalemin stated plaintiff applied for

building and demolition permits in August 2015. While the township approved

the demolition permit on February 10, 2016, it did not issue the building permit

until March 23.

Chalemin further testified demolition did not commence until March 10,

2016, because a telephone pole had to be removed, and it was unclear to whom

A-1405-23
8
it belonged. According to Chalemin, work on the property's footings was further

delayed by twenty-three days due to "unsuitable soil," which Finomus Orange's

soil engineers did not identify in their general recommendations. After

remedying the soil issues, 2 and losing another day due to rain, Chalemin

explained plaintiff finished the building's footings and had them inspected and

approved on April 27, 2016.

Another eight-day delay resulted when an inspector required damp

proofing to be installed on the property's foundation, which Finomus Orange did

not include in the original plans. Completion of the project was further delayed

when Public Service Electric and Gas Company (PSE&G) determined the

electrical plans were not suitable, resulting in another six-day delay. PSE&G's

failure to install permanent power, which it did not accomplish until September

2016, constituted the final significant delay.

After obtaining a temporary certificate of occupancy on September 19,

2016, Chalemin testified plaintiff turned the property over to Finomus Orange

after a final certificate of occupancy was issued by the township on October 7,

2016. Again, Chalemin explained plaintiff did not complete the punch list work

because Finomus Orange owed progress payments from August and September

2
Chalemin clarified plaintiff discovered the soil issue on March 30, 2016.
A-1405-23
9
2016, and plaintiff "needed to be paid the final retention before [Chalemin]

could get the contractors to go back."

With respect to the East Brunswick location, Chalemin acknowledged that

contrary to Article 9.2, plaintiff did not submit any change orders specifically

requesting an extension of the contract time. He did, however, state plaintiff

provided defendants with written notices of the delays. As to the delayed

construction schedules, Chalemin explained plaintiff regularly communicated

with Mehta regarding why the projects were behind the ninety-day timeframe

set out in the contracts. He further testified neither Finomus East Brunswick

nor Finomus Orange ever communicated that plaintiff was in breach of the

ninety-day requirement.

Defendants called Mehta as their only witness, who was "one of the

[principals] for Finomus." With respect to the East Brunswick project, Mehta

claimed no work was done outside the initial scope of approval from the DOT.

He did concede, however, Finomus East Brunswick requested a modification to

the original plans for the curb under the DOT's control. Further, although Mehta

acknowledged he was communicating with Chalemin on a daily basis with

respect to the project and associated delays, he testified he expressed his

displeasure with the speed of the construction in various communications.

A-1405-23
10
With respect to the Orange location, Mehta clarified Finomus Orange

obtained title to the property on October 27, 2015. Additionally, Mehta testified

the only notice of delay he received from plaintiff was for one day due to rain.

As to payments to plaintiff, Mehta explained Finomus Orange and

Finomus East Brunswick received two construction loans from Valley National

Bank and, before any payment could be issued, the bank "would have to come

out and inspect th[e] work before they would agree to release" the funds. With

respect to payroll expenses incurred as a result of plaintiff's alleged delay, Mehta

testified "managers are hired under Yum [and] Chill Management, LLC, and all

the hourlies are hired under the operating company for East Brunswick, which

is Yum [and] Chill East Brunswick, TB, LLC."

Mehta clarified he and his wife owned both Finomus defendants as well

as the Yum and Chill Entities. Because the Yum and Chill Entities had not been

made parties to the matter, and neither Finomus Orange nor Finomus East

Brunswick were responsible for any payroll expenses, the court held Mehta

could not be questioned as to their alleged damages.

With respect to the Orange project, Mehta claimed Finomus Orange

sustained $89,678.41 in damages due to real estate taxes and loan interest. As

A-1405-23
11
to the East Brunswick location, Mehta asserted Finomus East Brunswick

sustained $29,650.71 in damages for the same costs.

At the close of the trial day on October 27, 2020, defendants' counsel made

a motion to amend the counterclaim to add the Yum and Chill Entities, and the

court reserved its decision. The next day, the court granted defendants' motion

to amend the complaint.

After defendants amended their complaint, trial resumed and Mehta

testified the Yum and Chill Entities, with respect to the East Brunswick location,

sustained $57,571.02 in payroll damages ($41,192.89 in payroll expenses to

hourly employees, and $16,378.14 in payroll expenses to management

employees). As to the Orange location, Mehta explained the Yum and Chill

Entities incurred $85,476.50 in payroll damages ($49,292.35 in payroll expenses

to hourly employees, and $36,083.45 in payroll expenses to management

employees).

After considering the trial testimony and documentary evidence, on

October 6, 2023, the court issued a written opinion in which it found Finomus

Orange and Finomus East Brunswick liable for breach of contract, awarded

plaintiff attorney's fees, dismissed all parties' counterclaims, and issued a

corresponding order of judgment on December 14, 2023. With respect to

A-1405-23
12
plaintiff's claims regarding the East Brunswick project, the court initially

addressed the issue of whether plaintiff was entitled to extensions for the various

delays. Although plaintiff did not submit into evidence any written notices of

the delays, as required by Article 9.2, the court noted Mehta "received daily

written updates from plaintiff regarding the construction schedule in the [d]aily

[j]ob [r]eports." The court found these written reports met the delay requirement

such that plaintiff was entitled to extend the contract time under Article 9.2.

As to these delays, the court found plaintiff was entitled to the following

extensions of the contract time: (1) twenty-one days for the building permit that

East Brunswick did not issue until November 19, 2015; (2) fourteen days due to

the sewer line issue; (3) eight days for the damp proofing work; and (4) 103 days

for the DOT delay. In light of these extensions, the court concluded substantial

completion of the East Brunswick restaurant was required by June 12, 2016.

Because East Brunswick issued the certificate of occupancy on May 3, 2016, the

court found plaintiff achieved substantial completion on that date.

Therefore, the court found "there was no breach of contract time by

plaintiff in the construction of the East Brunswick . . . restaurant." Although it

found plaintiff committed a "minor breach" when it failed to complete the punch

list items, the court concluded "there was a major breach of contract by

A-1405-23
13
defendant Finomus East Brunswick . . . when it failed to pay plaintiff after

[twenty-one] days of receipt of the bill for the contract and change orders less

the [ten percent] retainage."

The court further found Finomus East Brunswick violated N.J.S.A.

2A:30A-2(a) "for failing to pay plaintiff within [thirty] days of receipt of the

bill" because Finomus "did not provide any writing to . . . plaintiff indicating

why it was not paying the bill less retainage." Accordingly, the court found

plaintiff was "entitled to interest at a rate of prime plus [one percent] from May

3, 2016[,] until the bill is paid," in addition to attorney's fees and costs under

N.J.S.A. 2A:30A-2(e). It further concluded Finomus East Brunswick was not

entitled to a credit for plaintiff's failure to complete the punch list because it

"provided no proof of the cost of completing" the work.

With respect to the change orders at the East Brunswick location, the court

found plaintiff was entitled to compensation as to all the change orders because

they were either requested by Finomus East Brunswick or required by East

Brunswick itself. Accordingly, the court "enter[ed] judgment on behalf of

[plaintiff], for the East Brunswick Taco Bell restaurant contract against Finomus

East Brunswick RE [H]oldings[,] LLC[,] in the amount of $113,916.07," plus

A-1405-23
14
interest, as well as "reasonable counsel fees plus costs." The court further

dismissed with prejudice Finomus East Brunswick's counterclaim.

As to plaintiff's claims concerning the Orange location, the court began

by noting the original ninety-day contract time for substantial completion was

January 26, 2016. It found plaintiff was entitled to the following extensions of

the contract time: (1) an extension to March 23, 2016, when Orange issued the

building permit; (2) a twenty-three-day extension due to the soil issue; (3) an

eight-day extension due to the damp proofing work; and (4) an unspecified

extension due to the issues with PSE&G. Accordingly, the court found plaintiff

was required to achieve substantial completion by September 19, 2016. Because

Orange issued a temporary certificate of occupancy on that date, the court found

plaintiff had achieved substantial completion and "there was no breach of the

[ninety-]day time is of the essence clause in [Article] 9.1 by plaintiff."

The court further found "a major breach of contract by [Finomus Orange]

in not paying plaintiff for the remainder of the contract plus change orders."

Again, the court found Finomus Orange was responsible for all the change

orders and violated N.J.S.A. 2A:30A-2(a). Consequently, it "enter[ed] judgment

on behalf of [plaintiff] for the Orange Taco Bell restaurant contract against

Finomus Orange RE Holdings, LLC., in the amount of $124,852.96," plus

A-1405-23
15
interest, as well as "reasonable counsel fees plus costs." Additionally, the court

dismissed with prejudice Finomus Orange's counterclaim.

Lastly, the court addressed the Yum and Chill Entities' counterclaim for

payroll damages. Because they were not parties to the contracts, the court

explained their right to damages hinged on whether they were third-party

beneficiaries.

Although the Finomus defendants were aware of the Yum and Chill

Entities' existence, the court found "plaintiff . . . was totally unaware that some

other entity would be paying payroll and would be claiming damages as a result

of its failure to meet the time element of the contracts." The court found it could

not "conclude that both parties intended the Yum and Chill defendants to be

third[-]party beneficiaries of the contract . . . . You [cannot] intend someone to

have a benefit from a contract you make with someone else when you are totally

unaware of that third party." It accordingly dismissed with prejudice the Yum

and Chill Entities' counterclaims.

II.

Defendants contend the court erred in making a better contract for plaintiff

than it made for itself. Specifically, defendants maintain "the [c]ourt overlooked

[plaintiff's] failure to follow the requirements of the subject contracts as well as

A-1405-23
16
the provisions of the contracts and statute upon which the [c]ourt purportedly

based its draconian award." With respect to the contracts and N.J.S.A. 2A:30A-

2, defendants argue prompt payment was not required because "there was ample

evidence that the [w]ork was not going to be completed within the [c]ontract

[t]ime." Further, defendants assert they "had a right to withhold a [ten percent]

retainage until all work, including the remedying of [punch list] work, was

completed."

Additionally, defendants maintain the court erred in granting plaintiff

multiple delay extensions. First, they contend plaintiff was not entitled to any

extensions because it did not submit any written requests pursuant to Article 9.2.

Second, defendants argue none of Article 9.2's bases for an extension "concern

delays by a municipal building department, a public utility[,] or an agency of

the State of New Jersey." Further, because the contracts imposed upon plaintiff

the obligation to obtain all licenses and permits, defendants argue the court

should not "have relieved [plaintiff] of its responsibilities." They maintain "the

[c]ourt had no business, on its own, to essentially render the time of the essence

provision in the contracts, which was not only negotiated but was quite

obviously of prime importance to [defendants], a nullity."

A-1405-23
17
Defendants further argue plaintiff breached two additional provisions of

the contract: completing the punch list work and providing defendants with

information regarding its subcontractors. Defendants contend the court erred in

finding "that the [punch list] work was a minor provision and that the

[defendants'] failure to pay [plaintiff's] last invoice for East Brunswick excused

[plaintiff] from its [punch list] obligations." In so finding, they maintain the

court failed to consider that defendants "paid all previous pay requests, had a

right to dispute change order requests, had a right to retainage, and had a right

to withhold funds based on [plaintiff's] utter failure to abide by the contracts '

time of the essence requirements and the concomitant right to reduce payments

to [plaintiff]."

When reviewing a decision in a non-jury trial matter, we "give deference

to the trial court that heard the witnesses, sifted the competing evidence, and

made reasoned conclusions." Griepenburg v. Twp. of Ocean, 220 N.J. 239, 254

(2015) (citing Rova Farms Resort, Inc. v. Investors Ins. Co. of Am., 65 N.J. 474,

483-84 (1974)). "[W]e do not disturb the factual findings and legal conclusions

of the trial judge unless we are convinced that they are so manifestly

unsupported by or inconsistent with the competent, relevant[,] and reasonably

credible evidence as to offend the interests of justice." Seidman v. Clifton Sav.

A-1405-23
18
Bank, SLA, 205 N.J. 150, 169 (2011) (second alteration in original) (quoting In

re Trust Created by Agreement Dated Dec. 20, 1961, ex rel. Johnson, 194 N.J.

276, 284 (2008)). In reviewing the judge's findings, this court "do[es] not weigh

the evidence, assess the credibility of witnesses, or make conclusions about the

evidence." Mountain Hill, LLC v. Twp. of Middletown, 399 N.J. Super. 486,

498 (App. Div. 2008) (quoting State v. Barone, 147 N.J. 599, 615 (1997)). We

owe no deference, however, to the judge's interpretation of the law and the legal

consequences that flow from established facts. Manalapan Realty, LP v. Twp.

Comm. of Manalapan, 140 N.J. 366, 378 (1995).

At the appellate level, "[i]nterpretation and construction of a contract is a

matter of law for the court subject to de novo review." Fastenberg v. Prudential

Ins. Co., 309 N.J. Super. 415, 420 (App. Div. 1998) (citing Bradford v. Kupper

Assocs., 283 N.J. Super. 556, 583 (App. Div. 1995)). We decide such purely

legal questions without deferring to a lower court's "interpretation of the law

and the legal consequences that flow from established facts." Manalapan Realty,

140 N.J. at 378 (citing State v. Brown, 118 N.J. 595, 604 (1990)); see also

Zaman v. Felton, 219 N.J. 199, 216 (2014).

When interpreting a contract, the court should consider the plain language

of the contract, the circumstances surrounding the contract, and the contract's

A-1405-23
19
purpose. Highland Lakes Country Club & Cmty. Ass'n v. Franzino, 186 N.J.

99, 115-16 (2006). "[W]here the terms of a contract are clear and

unambiguous[,] there is no room for interpretation or construction[,] and the

courts must enforce those terms as written." Karl's Sales & Serv., Inc. v. Gimbel

Bros., 249 N.J. Super. 487, 493 (App. Div. 1991) (citing Kampf v. Franklin Life

Ins. Co., 33 N.J. 36, 43 (1960)). Courts should not "rewrite a contract for the

parties better than or different from the one they wrote for themselves." Kieffer

v. Best Buy, 205 N.J. 213, 223 (2011) (citing Sacarias v. Allstate Ins. Co., 168

N.J. 590, 595 (2001)).

To establish a claim for breach of contract, a plaintiff must prove (1) they

had a valid contract; (2) they did what the contract required them to do; (3) the

defendant failed to perform a defined obligation under the contract; and (4)

defendant's breach caused a loss to plaintiff. Goldfarb v. Solimine, 245 N.J.

326, 338 (2021). Pursuant to general contract principles, if one party commits

a "breach of a material term of an agreement, the non-breaching party is relieved

of its obligations under the agreement. . . . [A] breach is material if it 'goes to

the essence of the contract.'" Roach v. BM Motoring, LLC, 228 N.J. 163, 174

(2017) (first quoting Nolan v. Lee Ho, 120 N.J. 465, 472 (1990); and then

quoting Ross Sys. v. Linden Dari-Delite, Inc., 35 N.J. 329, 341 (1961)).

A-1405-23
20
Whether a breach is material is a question of fact. Chance v. McCann, 405 N.J.

Super. 547, 566 (App. Div. 2009).

At the outset, defendants have not specifically challenged the court's

determination that the Yum and Chill Entities were not third-party beneficiaries

to the contracts, and we therefore consider any appeal of that finding waived.

See Telebright Corp., Inc. v. Dir., N.J. Div. of Tax'n, 424 N.J. Super. 384, 393

(App. Div. 2012) (deeming a contention waived when the party failed to include

any arguments supporting the contention in its brief). Regardless, the court

correctly concluded the Yum and Chill Entities could not have been third-party

beneficiaries of either contract because there was no evidence plaintiff was

aware of their existence when entering the agreements. See Ross v. Lowitz, 222

N.J. 494, 514 (2015) (explaining "a third party is deemed to be a beneficiary of

a contract only if the contracting parties so intended when they entered into their

agreement").

Additionally, in the preliminary statement to defendants' merits brief and

in their reply brief which the Appellate Clerk rejected, defendants summarily

challenge the court's decision to award plaintiff attorney's fees under N.J.S.A.

2A:30A-2. We decline to consider defendants' argument on both procedural and

substantive grounds. Procedurally, we decline to address the issue because we

A-1405-23
21
only consider legal arguments set forth in the argument portion of a brief and

raised in point headings. Almog v. Israel Travel Advisory Serv., Inc., 298 N.J.

Super. 145, 155 (App. Div. 1997) ("[W]e confine our address of the issues to

those arguments properly made under appropriate point headings."). Further,

even if defendants' reply brief was not rejected, we would not have considered

their argument on this point because, as noted, they did not properly raise the

issue in their merits brief and it is also not proper to raise the issue for the first

time in a reply brief. See Borough of Berlin v. Remington & Vernick Eng'rs,

337 N.J. Super. 590, 596 (App. Div. 2001) (stating "[r]aising an issue for the

first time in a reply brief is improper"). Substantively, defendants' argument is

without sufficient merit to warrant discussion in a written opinion. R. 2:11-

3(e)(1)(E).

With respect to the East Brunswick contract, we are convinced the court

appropriately found plaintiff did not breach the time of the essence clause and

that Finomus East Brunswick committed "a major breach of contract . . . when

it failed to pay plaintiff after [twenty-one] days of receipt of the bill for the

contract and change orders less the [ten percent] retainage." We are

unpersuaded by defendants' argument plaintiff was not entitled to any extensions

of the contract time because it failed to submit written notices pursuant to Article

A-1405-23
22
9.2. As noted, to be entitled to an extension of the contract time due to an

unavoidable delay, plaintiff was required to deliver to Finomus East Brunswick

"a written notice of the cause of the delay with[in] ten . . . days after the

commencement of the delay and . . . demonstrate[] that such delay was on the

critical path of the [c]onstruction [p]rogress [s]chedule."

Here, we discern no error in the court's decision plaintiff satisfied this

requirement by submitting written daily job reports. These written daily job

reports clearly satisfy Article 9.2's requirement that plaintiff submit "a written

notice of the cause of the delay with[in] ten . . . days." Additionally, because

defendants have failed to include these reports in the appellate record, we have

no reason to question the court's conclusion they also satisfied Article 9.2's

requirement that plaintiff demonstrate the delays were "on the critical path of

the [c]onstruction [p]rogress [s]chedule." See R. 2:6-1(a)(1)(I) (explaining an

appellant must include in the appendix "such other parts of the record . . . as are

essential to the proper consideration of the issues"); see also State v. Robertson,

438 N.J. Super. 47, 56 n.4 (App. Div. 2014) ("We obviously cannot address

documents not included in the record.").

We are similarly unconvinced by defendants' argument plaintiff was not

entitled to any extensions of the contract time because none of Article 9.2's bases

A-1405-23
23
for an extension "concern delays by a municipal building department, a public

utility[,] or an agency of the State of New Jersey." As noted, the court found

plaintiff was entitled to the following extensions with respect to the East

Brunswick contract: (1) twenty-one days for the delayed building permit; (2)

fourteen days due to the sewer line issue; (3) eight days for the damp proofing

work; and (4) 103 days for the DOT delay.

Although the court did not explain which provisions in Article 9.2 excused

these delays, we are satisfied all the delays, save for the building permit issue,

are excused as they were occasioned by "the acts (including [c]hanges) or

omission[s]" of Finomus East Brunswick. As noted, the fourteen-day delay due

to the sewer line issue and the eight-day delay for damp proofing work were

caused by Finomus East Brunswick's "omission" to include this work in the

original plans. Additionally, Finomus East Brunswick created the DOT delay

by requesting that plaintiff urge the DOT to keep the existing sidewalks and

curbing. Because the contract required plaintiff to obtain all permits, however,

we are convinced it was not entitled to this twenty-one-day extension.

Therefore, plaintiff was entitled to extend the contract time by 125 days.

Because the effective date of the East Brunswick contract was October 16, 2015,

without any delays plaintiff was required to complete the work by January 14,

A-1405-23
24
2016. With the 125-day extension, the revised completion date was May 18,

2016. As the court found plaintiff achieved substantial completion on May 3,

2016, it correctly concluded plaintiff did not breach the contract's time of the

essence clause.

Additionally, the court did not, as defendants contend, "err[] in failing to

require [plaintiff] to abide by its contractual obligations." Here, the court found

Finomus East Brunswick committed "a major breach of contract . . . when it

failed to pay plaintiff after [twenty-one] days of receipt of the bill for the

contract and change orders less the [ten percent] retainage." As noted, it also

concluded plaintiff committed "a minor breach of contract when [it] failed to

complete the punch list." Because the court found as fact that Finomus East

Brunswick breached a material term of the contracts, see Chance, 405 N.J.

Super. at 566, plaintiff was entitled to suspend performance and was not

obligated to correct the punch list items or provide information regarding its

subcontractors, see Roach, 228 N.J. 163 at 174.

Lastly, we reject defendants' argument prompt payment was not required

because "there was ample evidence that the [w]ork was not going to be

completed within the [c]ontract [t]ime." Although the contracts do permit

defendants to withhold payments based upon "[r]easonable evidence that the

A-1405-23
25
[w]ork will not be completed within the [c]ontract [t]ime," as noted above,

plaintiff did complete the work within the extended timeframe. As such,

defendants had no basis to withhold payments based upon their belief plaintiff

would not complete the work within the contract's original timeframe. We

therefore affirm the court's December 14, 2023 order of judgment to the extent

it found Finomus East Brunswick liable for breach of contract and dismissed its

counterclaim.

We reach a different conclusion, however, with respect to the court's

findings regarding the Orange project. As noted, the court found plaintiff was

entitled to the following extensions of the contract time: (1) an extension to

March 23, 2016, when Orange issued the building permit; (2) a twenty -three-

day extension due to the soil issue; (3) an eight day extension due to the damp

proofing work; and (4) an unspecified extension due to the issues with PSE&G.

Unlike the delays associated with the East Brunswick location, the most

significant delays plaintiff encountered at the Orange project were not excusable

under Article 9.2. Specifically, neither the delays associated with PSE&G nor

Orange's protracted delay in issuing the building permit qualify as "acts

(including [c]hanges) or omission[s]" of Finomus Orange, nor do those delays

fall within any of the other four circumstances in which a delay would toll the

A-1405-23
26
contract time under Article 9.2.3 The only delays that are excusable under

Article 9.2 are the twenty-three and eight-day delays caused by work Finomus

Orange omitted in the original plans. As a result, plaintiff was entitled to extend

the contract time by thirty-one days.

Here, the court found the contract time began on October 27, 2015, when

Finomus Orange obtained title to the property. Accordingly, the original date

for substantial completion was January 26, 2016. With the thirty-one-day

extension, plaintiff was required to achieve substantial completion by February

26, 2016. Because the court found plaintiff achieved substantial completion on

September 19, 2016, plaintiff did not complete the project within the extended

ninety-day timeframe.

Our analysis, however, does not end there. It is well-established

[w]here time of performance is of the essence of the
contract, a party who does any act inconsistent with the
supposition that [they] continue[] to hold the other
party to [their] part of the agreement will be taken to
have waived it altogether. When a specific time is fixed
for the performance of a contract and is of the essence
of the contract and it is not performed by that time, but

3
We recognize the Orange contract incorporated a letter of intent which stated,
in part, the "construction timeline would be [ninety] days from the date of receipt
of building permits or date of [plaintiff's] mobilization, whichever is earlier."
Even assuming this letter delayed the beginning of the ninety-day construction
timeline to March 23, 2016, plaintiff still would have been required to complete
the work by June 21.
A-1405-23
27
the parties proceed with the performance of it after that
time, the right to suddenly insist upon a forfeiture for
failure to perform within the specified time will be
deemed to have been waived[,] and the time for
performance will be deemed to have been extended for
a reasonable time.

[Marioni v. 94 Broadway, Inc., 374 N.J. Super. 588,
608 (App. Div. 2005) (quoting 15 Williston on
Contracts § 46:14 (Lord ed. 2002)).]

Here, it appears evidence in the record may support finding Finomus

Orange waived the time of the essence clause and, therefore, waived any right

they may have had to insist upon the consequences of plaintiff's failure to abide

by the time of the essence clause. By way of example only, the ninety-day

timeframe originally contemplated in the Orange contract lapsed on January 26,

2016. Aside from Mehta's testimony he communicated to Chalemin his

displeasure with the speed of the project, there is no evidence Finomus Orange

advised plaintiff it was in breach of the time of the essence clause. Further,

Finomus Orange allowed plaintiff to complete the project and obtain a certificate

of occupancy before it ever raised the issue.

Neither the court nor the parties, however, addressed the issue of waiver.

Because the record would benefit from more specific factual and legal findings ,

we decline to exercise original jurisdiction on this point and conclude the court

should address the issue in the first instance and, if necessary, provide the parties

A-1405-23
28
with an opportunity to brief and be heard on the matter. See Price v. Himeji,

LLC, 214 N.J. 263, 294 (2013).

If on remand the court concludes Finomus Orange waived the time of the

essence clause, the court may reinstate plaintiff's damages award, including the

attorney's fee award under N.J.S.A. 2A:30A-2. To the extent the court does not

find waiver, however, it shall examine the proofs in light of plaintiff's alternative

claims for relief and determine whether or not defendants are entitled to damages

with respect to Finomus Orange's claim they incurred unnecessary carrying

charges as a result of plaintiff's breach of the time of the essence clause, and

determine the amount of damages associated with that breach. We therefore

remand for the court to make findings consistent with Rule 1:7-4 as to whether

Finomus Orange waived the time of the essence clause.

In sum, we affirm the December 14, 2023 order of judgment as to Finomus

East Brunswick. We reverse the December 14 order to the extent the court found

Finomus Orange liable and remand for further proceedings to address the issue

of waiver. Nothing in our opinion should be construed as suggesting our view

on the outcome of the remanded proceedings. To the extent we have not

addressed specifically any of defendants' remaining arguments, it is because we

A-1405-23
29
have concluded they are without sufficient merit to warrant discussion in a

written opinion. R. 2:11-3(e)(1)(E).

Affirmed in part, reversed in part, and remanded for further proceedings.

We do not retain jurisdiction.

A-1405-23
30

---

Source: Frix Law Library, https://www.frixlaw.com/law-library/cases/11100189. Public record. Not legal advice.