# Mabee v. Board of Environmental Protection

> Superior Court of Maine · November 18, 2021

URL: https://www.frixlaw.com/law-library/cases/10812220

## Case

- **Court:** Superior Court of Maine
- **Decided:** November 18, 2021
- **Precedential status:** Unpublished
- **Opinion:** Opinion
- **Judges:** M. Michaela Murphy
- **Cited by:** 0 later opinions in the Frix Law Library

## Citator (automated)

- No negative treatment found by the automated citator. That is not the same as a confirmation that the case is good law; read the citing cases.
- Full citator and citing cases: https://www.frixlaw.com/law-library/cases/10812220

## How later opinions describe it (automated extraction)

- finding five individual plaintiffs, regular users of Baxter State Park, had standing to seek an injunction preventing the use of heavy machinery to clear blowdown because such activity’s effect on their use and enjoyment of the park constitutes a “direct and personal injury”

## Opinion text

STATE OF MAINE BUSINESS & CONSUMER COURT
CUMBERLAND, ss. LOCATION: PORTLAND
DOCKET NO. BCD-APP-2021-00009

JEFFREY MABEE, et al., )
)
Petitioners, )
)
v. )
)
BOARD OF ENVIRONMENTAL )
PROTECTION, )
)
Respondent. )
)
__________________________________ ) COMBINED ORDER ON PENDING
) MOTIONS
UPSTREAM WATCH, )
)
Petitioner, )
)
v. )
)
BOARD OF ENVIRONMENTAL )
PROTECTION, )
)
Respondent. )
)

INTRODUCTION

In this consolidated action, Petitioners Jeffrey Mabee, Judith Grace, Friends of Harriet L.

Hartley Conservation Area (“Friends”), the Maine Lobstering Union (“IMLU”), Wayne Canning,

and David Black (together, the “Petitioners”) appeal the November 19, 2020 Decision of the Board

of Environmental Protection (“BEP”) that approved Nordic Aquafarm, Inc.’s (“Nordic”)

application for permits related to its proposed salmon farm, including three pipelines to be laid

across upland and intertidal land and into the Penobscot Bay. The Petitioners are joined by

Intervenors Upstream Watch, The Fish Are Okay, Northpoint Village Corporation, Eleanor

Daniels, Donna Broderick, Lawrence Richard, The Gulf of Maine Research Institute, and The

1
University of New England (together, the “Intervenors”). The Petitioners and Intervenors have

raised several legal challenges to BEP’s decision regarding Nordic’s permits. The Court heard oral

arguments on the parties’ merits briefs on December 17, 2021 in which both parties appeared

through counsel. Upstream on January 14, 2022 filed a Motion to Stay, which BEP and Nordic

have opposed. For the reasons discussed below, the Court DENIES Petitioners’ Motion to Stay

and AFFIRMS BEP’s Decision approving Nordic’s permits.

FACTUAL AND PROCEDURAL BACKGROUND

In the spring of 2018, Nordic publicly announced its plans to build a $500-million land-

based salmon farm and processing plant in Belfast, Maine. Nordic chose Belfast for its site after

considering options along the northeast seaboard and finding that Belfast and the adjacent waters

of the Penobscot Bay are optimal for the undertaking. The farm requires access to the ocean over

upland and intertidal land to allow for the installation of pipes into the sea. The compound will

primarily be located on land owned by the Belfast Water District on the west side of Route 1 near

the southern town line between Belfast and Northport. Adjacent land to the east of Route 1 for

laying the pipes is to be leased and/or acquired from local property owners.

The salmon farm is expected to produce and process approximately 33,000 tons of Atlantic

salmon each year. It comprises two components: a primary facility and a seawater access system.

The primary facility includes fish tanks and a plant to treat incoming fresh and seawater as well as

wastewater discharge. Eight 2-MW generators supplement electricity for the plant by up to 14 MW

of capacity, serving as emergency backup and for peak shaving as needed. The use of these

generators is restricted to a combined annual fuel limit of 900,000 gallons. The seawater access

system consists of two seawater intake pipes and one discharge outfall pipe. The latter will cross

2
Route 1, extend into intertidal and subtidal areas of coastal wetland, and discharge 7.7 million

gallons of treated freshwater per day into Belfast Bay.

On August 6, 2018, Richard and Janet Eckrote (the “Eckrotes”) entered into an agreement

with Nordic, granting the latter an option to obtain an easement along the border of their lot (“Lot

36”) for laying these pipes subject to Nordic’s acquisition of the requisite environmental permits

and its decision to carry out its plans for the salmon farm (the “2018 Easement Option”).

Nordic applied for a Water Permit 1 on October 19, 2018 relating to its wastewater

discharge pipes. On November 11, 2018 DEP accepted the Water Permit application as complete

for processing and on November 21, 2018 Nordic submitted a second proposed route for the pipes,

as shown during a public hearing on December 17, 2018. On January 7, 2019 Mabee, Grace,

Upstream Watch, and IMLU filed a written objection to the pipeline route based on allegations

that Nordic did not possess sufficient TRI in the property to obtain a permit. On January 30, 2019,

the DEP referred the Water Permit to the BEP, a seven-member board appointed by the Governor

and confirmed by the Legislature which provides independent decisions on the interpretation,

administration, and enforcement of environmental protection regulations and laws. 2 The Water

Permit was put on hold until it could be consolidated with forthcoming applications for other,

related environmental permits. On April 29, 2019 experts commissioned by Mabee, Grace and

Upstream Watch advised Mabee and Grace that they, not the Eckrotes, owned the intertidal land

1
Filed under 38 M.R.S. §§ 414-A(1)(D), 414-A(1)(C), and 464(4)(F) and regulations of Maine’s Department of
Environmental Protection (“DEP”), 06-096 C.M.R. chs. 520-25, 579, 581, and 587. Required as part of the Maine
Pollutant Discharge Elimination System (“MEPDES”), established to comply with the federal Clean Water Act, 33
U.S.A. § 1251 et seq.
2
Most applications for environmental licenses and permits are processed by DEP staff and decided by the DEP
Commissioner but under 38 M.R.S. § 341-D(2), certain applications must be decided by BEP, which has
independent decision-making authority in its areas of responsibility. These include licenses which meet at least three
of four criteria: (i) those which will have an environmental or economic impact in more than one municipality,
territory, or county; (ii) those which involve an activity not previously permitted or licensed in the State; (iii) those
which are likely to come under significant public scrutiny; and (iv) those which are located in more than one
municipality, territory, or county. Nordic’s applications were found to fall under BEP’s jurisdiction.

3
subject to the 2018 Easement Option. Mabee and Grace placed that land under a Conservation

easement with Upstream Watch as the holder. On May 17, 2019 Nordic filed applications for

permits under Maine’s Site Location of Development Act (“SLODA”) 3 and the Natural Resources

Protection Agency (“NRPA”) 4 as well as an Air Emissions License (“AEL”) 5.

On May 29, 2019 DEP requested additional information to support Nordic’s TRI claim.

Nordic filed a 144-page PDF on June 10, 2019 detailing its TRI claim and on June 12, 2019 Mabee,

Grace, and Upstream Watch submitted contrary evidence. On June 13, 2019, DEP determined that

Nordic had demonstrated sufficient evidence of TRI and had submitted sufficient supporting

material to accept the consolidated permit applications as complete for processing. On June 20,

2019 BEP voted to assume original jurisdiction over the consolidated applications and to hold a

public hearing pursuant to the Maine Administrative Procedures Act, 5 M.R.S. §§ 8001-11008

(“MAPA”), and 06-096 C.M.R. ch. 3 (“Ch. 3”). BEP at this time granted intervenor status to

Upstream Watch and the other Intervenors.

Throughout the application processing period, the Petitioners’ and Intervenors’ challenges

to TRI were rejected by BEP and its Presiding Officer. The Water Permit was premised on

sufficient TRI based on the 2018 Easement Option granted by the Eckrotes; Mabee, Grace, and

Upstream Watch disputed the Eckrotes’ right to grant such an interest, claiming that the intertidal

land in question was rather subject to a conservation easement 6 Mabee and Grace had granted to

Upstream Watch and which was then assigned to Friends. This intertidal land was the subject of a

quiet title suit (the “Lot 36 Litigation”) in the Superior Court (Waldo County, R. Murray, J.). 7

3
Issued pursuant to 38 M.R.S. §§ 481-489-E.
4
Issued pursuant to 38 M.R.S. §§ 411-424-B; not subject to this appeal.
5
Issued pursuant to 38 M.R.S. § 590 and DEP regulations in 06-096 C.M.R. ch. 115.
6
Mabee and Grace placed all the intertidal land they claimed under the protection of a conservation easement in
perpetuity, pursuant to 33 M.R.S. § 477-A et seq., on April 29, 2019 to underscore their intent to stop Nordic from
laying its wastewater pipes there.
7
Mabee v. Nordic, No. RE-2019-18 (Me. Super. Ct., Wal. Cnty., Oct. 28, 2021).

4
On October 24, 2019 BEP visited the proposed salmon farm site in Belfast and from

February 11 to 14, 2020 it held a public hearing on the matter. At the close of the hearing, the

Presiding Officer held the record open for limited evidence and comments or evaluation from the

parties. Written comments were accepted through February 18, 2020. The parties submitted post-

hearing briefs and BEP staff submitted a briefing memo to BEP between April 27 and May 4,

2020.

On May 20, 2020 BEP held a deliberative session to discuss the consolidated applications,

the record, and statutory licensing criteria with its staff. Staff drafted recommended decisions on

the applications and posted them for public comment pursuant to Ch. 3, § 28(B). In November

2020, BEP considered the draft decisions in two meetings and voted in both to approve, thereby

granting Nordic’s applications for the Water, NRPA, and SLODA Permits and the AEL. BEP

issued its final findings and decisions on the applications on November 19, 2020. The Petitioners

timely appealed BEP’s decisions under Rule 80C in the instant action.

On June 23, 2021 the Eckrotes conveyed all their interest, if any, in Lot 36 and its intertidal

land to the City of Belfast and on July 10, 2021, Nordic conveyed all its interest, if any, in Lot 36

and its intertidal land to the same. The City of Belfast exercised eminent domain on August 12,

2021 to take the interests, if any, of Mabee, Grace, and Friends in the intertidal land on which Lot

36 fronts for the stated purpose of allowing Nordic to use it for its pipes. Mabee, Grace, Upstream

Watch, and Friends filed an action with the Superior Court (Waldo County, R. Murray, J.)

contesting the taking on August 16, 2021. 8 The State of Maine Office of the Attorney General has

intervened in that action, which is currently pending.

8
Mabee v. City of Belfast, No. RE-2021-07 (Me. Super. Ct., Wal. Cnty).

5
The decision in the Lot 36 Litigation, issued on October 28, 2021, determined that it was

the Eckrotes, not Mabee and Grace, who had owned the intertidal land. Mabee, Grace, and

Upstream Watch filed motions to amend the judgment and motions for amended and/or additional

findings of facts and law as to the Lot 36 Litigation under Rules 52 and 59 of the Maine Rules of

Civil Procedure which were denied by the Superior Court (Waldo County, R. Murray, J.) on

January 10, 2022. 9 The matter was appealed to the Law Court on January 20, 2022.

Upstream Watch has also challenged, under Rule 80B, certain permits granted to Nordic

by the Belfast Planning Board, and this matter is also pending in the Superior Court (Waldo

County, R. Murray, J.). 10

STANDARD OF REVIEW

Administrative standing, i.e., the standing required for an administrative agency to consider

a permit or license application as complete for processing, is based on an applicant’s demonstration

of sufficient title, rights, or interest (“TRI”) in the property subject to the application. 06-096

C.M.R. ch. 2, § 11(D); Southridge Corp. v. Bd. of Envtl. Prot., 655 A.2d 345, 348 (Me. 1995).

Judicial standing related to an agency’s decision is based on a party’s demonstration of a

particularized injury resulting from said decision. Ricci v. Superintendent of Banking, 485 A.2d

645 (Me. 1984).

Review of agency decisions is “deferential and limited.” Champlain Wind, LLC v. Dep’t

of Envtl. Prot., 205 ME 156, ¶¶ 13, 15, 129 A.3d 279. This standard is based on MAPA. 5

M.R.S. § 11007(d) (“The court may not substitute its judgment for that of the agency on

questions of fact.”). The court “[will] not vacate an agency’s decision unless it: violates the

Constitution or statutes; exceeds the agency’s authority; is procedurally unlawful, is arbitrary or

9
Mabee, No. RE-2019-18 (Me. Super. Ct., Wal. Cnty.).
10
Upstream Watch v. City of Belfast, No. AP-2021-03 (Me. Super. Ct., Wal. Cnty.).

6
capricious; constitutes an abuse of discretion; is affected by bias or an error of law; or is

unsupported by the evidence in the record.” Kroeger v. Dep’t of Envtl. Prot., 2005 ME 50, ¶ 7,

870 A.2d 566; accord § 11007(4)(C); Forest Ecology Network v. Land Use Planning Comm’n,

2012 ME 36, ¶ 26, 39 A.3d 74. The court may only vacate findings of fact “if the record contains

no competent evidence to support them.” Mulready v. Bd. of Real Estate Appraisers, 2009 ME

135, ¶ 13, 984 A.2d 1285. Competent, or substantial, evidence “exists when a reasonable mind

would rely on that evidence as sufficient support for a conclusion.” Osprey Family Trust v. Town

of Owls Head, 2016 ME 89, ¶ 9, 141 A.3d 1114. The Business & Consumer Court’s review of

evidence in the record on appeal is identical to the Law Court’s review of trial court factual

findings for “clear error.” See Gulick v. Bd. of Envtl. Prot., 452 A.2d 1202, 1208 (Me. 1982).

“[T]he fact that the record contains inconsistent evidence or that inconsistent conclusions could

be drawn from the record does not prevent the agency’s findings from being sustained if there is

substantial evidence to support them.” Seven Islands Land Co. v. Maine Land Use Regul.

Comm’n, 450 A.2d 475, 479 (Me. 1982).

Conversely, the court is not bound by agency interpretations of statutes which that agency

administers. However, the court will still give great deference to that interpretation “unless the

statute plainly compels a contrary result.” Passadumkeag Mountain Friends v. Bd. of Envt. Prot.,

2014 ME 116, ¶ 12, 102 A.3d 1181. The same standard applies to an agency’s interpretation of

its own internal rules, regulations, and procedures. Becker v. Bureau of Parks & Lands, 2005 ME

120, ¶ 2, 886 A.2d 1280.

Under 5 M.R.S. § 11007(4), this Court is empowered to affirm BEP’s decisions, remand

for further proceedings by the agency, or reverse or modify the decision. Because they are

seeking to overturn the BEP decisions, Petitioners bear the burden of persuasion on appeal and

7
must overcome the deference this Court is bound to give BEP’s interpretations and decisions.

Somerset Cty. V. Dep’t of Corr., 2016 ME 33, ¶ 14, 133 A.3d 1006.

DISCUSSION

I. Upstream’s Motion to Stay

Upstream Watch has moved for this Court to stay the instant proceedings until the Law

Court issues mandates on the Lot 36 Litigation appeal and the appeal, if any, of the eminent domain

action currently before the Waldo County Superior Court. This Court is limited in its Rule 80C

appeal review to determining whether the BEP abused its discretion, made errors of law, or made

factual findings not supported by the record in its approval of the Water Permit, SLODA Permit,

NRPA Permit, and AEL. 5 M.R.S. § 11007. The grant of these permits was, as discussed below,

based on the BEP’s finding that Nordic had demonstrated sufficient TRI in the relevant property

for the purposes of processing Nordic’s permit applications. It was not an adjudication of the actual

ownership of the intertidal land in question, which is the issue in the Lot 36 Litigation currently

on appeal before the Law Court. The ultimate outcome of the Lot 36 Litigation appeal is therefore

inapposite to this Court’s review of BEP’s permit grants. Likewise, the outcome of Petitioners’

action before the Waldo County Superior Court as to the City of Belfast’s use of eminent domain

to take Mabee, Grace, and Friends’ interest in the intertidal land will not affect this Court’s review

of the BEP permit grants under Rule 80C. Moreover, this Court is unwilling to delay these

proceedings until the Law Court has decided the potential appeal of a case which is still pending

before the Superior Court. Consequently, a stay is not warranted and Upstream’s motion is denied.

II. Appeal Merits

8
The questions relevant to reviewing this appeal pursuant to Rule 80C are (i) whether the

DEP erred on 6/13/2019 in determining Nordic had shown sufficient TRI for the purposes of

reviewing its permit applications; (ii) whether the BEP Presiding Officer erred on 7/20/2020 in

refusing to stay or dismiss the Nordic applications based on the Law Court’s 7/7/2020 holding in

Tomasino v. Casco, 2020 ME 96, 237 A.3d 175; and (iii) whether there was substantial evidence

in the record to support the grant of the permits.

A. The DEP’s June 13, 2019 Determination of Sufficient TRI Was Not in Error

Petitioners argue the 2018 Easement Option did not establish sufficient TRI such that

Nordic could use it as the basis for the administrative standing needed to apply for environmental

permits related to Lot 36, meaning the DEP erred in accepting the permit application as complete

for processing. In light of the finding in the Lot 36 Litigation, a more foundational question of

judicial standing arises, because that suit establishes that Petitioners Mabee, Grace, and Upstream

Watch themselves do not possess any interest in Lot 36’s intertidal land and would therefore lack

standing to bring the instant appeal on grounds relating to that property.

In Maine, standing to sue exists where the complaining party has “sufficient personal stake

in a justiciable controversy to assure the existence of that concrete adverseness that facilitates

diligent development of the legal issues presented.” Halfway House, Inc. v. City of Portland, 670

A.2d 1377, 1381 (Me. 1996). Standing may exist, for example, where the party makes a reasonable

allegation of a potential particularized injury, Christy’s Realty Ltd. Partnership v. Town of Kittery,

663 A.2d 59, 61 (Me. 1995); the party has a sufficiently substantial interest in the subject of a

declaratory judgment, Smith v. Allstate Ins. Co., 483 A.2d 344, 346 (Me. 1984); or the party

demonstrates actual deprivation, Brann v. State, 424 A.2d 699, 702 (Me. 1981).

9
In administrative appeals, standing to seek judicial review is governed by statute and

“depends on the wording of the specific statute involved.” Nelson v. Bayroot, LLC, 2008 ME 91,

¶ 9, 953 A.2d 378. MAPA governs judicial review of state agency actions and provides a right to

review to any person “aggrieved by final agency action.” 5 M.R.S. § 11001(1). “Aggrieved” has

been interpreted to mean having suffered a particularized injury, i.e., the final agency action

operates “prejudicially and directly upon the party’s property, pecuniary or personal rights.”

Nelson, 2008 ME 91, ¶ 10, 953 A.2d 378. This particularized injury must be “distinct from any

injury experienced by the public at large.” Lindemann v. Comm’n on Governmental Ethics &

Election Practices, 2008 ME 187, ¶ 14, 961 A.2d 538. In narrow circumstances, individuals have

been found to have standing to sue based on public rights. See Fitzgerald v. Baxter State Park

Auth., 385 A.2d 189, 197 (Me. 1978) (finding five individual plaintiffs, regular users of Baxter

State Park, had standing to seek an injunction preventing the use of heavy machinery to clear

blowdown because such activity’s effect on their use and enjoyment of the park constitutes a

“direct and personal injury”). Standing must exist both at the outset of litigation and throughout

its existence; if a litigant becomes deprived of his or her ongoing stake in the controversy, the case

becomes moot and hence not justiciable Halfway House, 670 A.2d at 1379-80.

The Petitioners and Intervenors base their standing on the enforcement of a conservation

easement granted by Mabee and Grace to Upstream Watch, purportedly including the intertidal

land subject to the 2018 Easement Option between Nordic and the Eckrotes. The Water Permit

issued by BEP to Nordic authorizes Nordic to run wastewater pipes along the border of Lot 36 and

out into the Penobscot Bay through this intertidal land. The Lot 36 Litigation determined that the

land in question at all relevant times belonged to the Eckrotes, not to Mabee and Grace, meaning

the attempted conservation easement is void as to the intertidal land which belonged to the

10
Eckrotes and which has since been conveyed to the City of Belfast. As such, Petitioners have not

and will not suffer any particularized injury distinct from the public at large from the grant of the

Water Permit or the installation of the wastewater pipes. They lack standing to sue on these

grounds and their complaints in relation to Nordic’s TRI in the land are thus moot. Intervenors

have been granted standing to seek review of the permit application process pursuant to MAPA.

Even if Petitioners did have standing, as do Intervenors, their appeal must fail. “An

applicant for a license or permit to use property in certain ways must have ‘the kind of relationship

to the . . . site,’ that gives him a legally cognizable expectation of having the power to use that site

in the ways that would be authorized by the permit or license he seeks.” Murray v. Town of

Lincolnville, 462 A.2d 40, 43 (Me. 1983) (quoting Walsh v. City of Brewer, 315 A.2d 200, 207

(Me. 1974)). In Murray, a purchase and sale agreement conditioned on necessary subdivision

approval provided sufficient TRI to invoke administrative standing to petition BEP for approval

to develop the property. Murray, 462 A.2d at 43. The fact that a purchaser in this situation “could

opt out of the purchase under certain circumstances does not deprive [him or her] of standing, any

more than the owner of property in fee simple could be said to lack standing because he has the

right to sell his land at any time.” Id. The court in Southridge Corp. extended this principle to find

that a party claiming title to a disputed parcel by adverse possession in an unresolved action

nevertheless demonstrates sufficient TRI in the parcel for DEP to consider that party’s permit

application as complete for processing. 655 A.2d at 348. The instant case falls between these two,

as Nordic held an option to purchase an easement but had not yet entered into a purchase and sale

agreement with the Eckrotes. The DEP considered and, at the request of Petitioners, reconsidered

several times record evidence on Nordic’s claim of TRI and finally determined on June 13, 2019

that it was satisfied by the 2018 Easement Option. Given that even an unresolved adverse

11
possession claim to property provides sufficient TRI for permit applications, this Court agrees that

an option arrangement must suffice as well. Once the BEP voted to assume original jurisdiction

over the application, this threshold determination of TRI was no longer appealable. The Petitioners

were within their rights to request the BEP revisit the issue but the BEP was not obliged to do so.

That Nordic ultimately did not exercise its rights under the 2018 Easement Option

Agreement is inapposite to TRI for permit purposes. As BEP correctly notes in its opposition brief,

a showing of TRI is only relevant as far as processing of the permit was concerned. The TRI

determination was not an adjudication of property rights or a grant of legal ownership; TRI is a

threshold question to ensure State resources are not squandered investigating permit applications

which the applicant clearly has no legal capacity to utilize if granted. Murray, 462 A.2d at 43. The

Water Permit does not give Nordic the right to build its pipes on the land in question, it is merely

the fulfillment of a prerequisite to building its pipes. Nordic must separately acquire the right to

lay its pipes, whether by grant or easement. The right to use the land for pipes or otherwise is a

matter for Nordic to resolve; BEP’s permitting process simply ensures that environmental

regulatory standards are met.

B. The 7/20/2020 Refusal to Apply Tomasino Was Not in Error

Petitioners and Intervenors contend that BEP’s Presiding Officer erred and abused his

discretion when he refused to apply the Law Court’s holding in Tomasino, issued two weeks prior

to Petitioners’ request the holding be considered in this case. 2020 ME 96, 237 A.3d 175. They

argue that under the standard established in Tomasino, Presiding Officer should have stayed or

revoked Nordic’s applications pending the outcome of the Lot 36 Litigation over title to the

intertidal land.

12
Tomasino involves neighboring properties owned by the Tomasinos and the Trust,

respectively, which share mirror easements along part of the property border for use as a road. The

Tomasinos obtained a permit from the Town of Casco Code Enforcement Office to cut several

trees located wholly or partially on Trust land burdened by the Tomasinos’ easement to build a

gravel driveway. The Trust appealed to the Casco Zoning Board of Appeals, which vacated the

permit for lack of administrative standing because it was not clear whether the easement included

the right to remove trees. Tomasino, 2020 ME 96, ¶ 7, 237 A.3d 175. That decision was affirmed

by both the Superior Court, reviewing in its intermediate appellate capacity, and the Law Court.

The Law Court distinguished Tomasino from its earlier decisions in Walsh, Murray, and

Southridge, noting that the latter three cases all

involved the question of whether the applicants had sufficient connections to the
title to the properties to seek municipal or agency permits on those properties, and
in each case, there was no question but that the title owner of the property, once its
identity was established, would be able to make use of the property as permitted
according to applicable ordinances and statutes.
Tomasino, 2020 ME 96, ¶ 14, 237 A.3d 175; see also Southridge Corp., 655 A.2d t 348; Murray,

462 A.2d at 43; Walsh, 315 A.2d at 205, 207-08. The Court continued that in the face of a dispute

between private property owners, the requirement that an easement allows the type of activity a

permit is sought for “is not met by an easement whose parameters have not been factually

determined by a court with jurisdiction to do so.” Tomasino, 2020 ME 96, ¶ 15, 237 A.3d 175.

The instant case aligns with Southridge, Murray, and Walsh, not with Tomasino. There is

no dispute about the scope of the 2018 Easement Option, either in its location or what it allows.

The quiet title suit between Mabee and Nordic was a dispute about ownership, not easement

parameters. The only question, as in the earlier cases, was who owns the land burdened by the

easement and thus who was able to grant an easement interest, and as such no involvement of a

13
court with the jurisdiction to determine the easement’s parameters was necessary. The Presiding

Officer did not err by refusing to stay or revoke Nordic’s permit pending the outcome of the Lot

36 Litigation, nor did the BEP err by not conditioning the permit on a judgment that Mabee and

Grace did not possess an interest in the intertidal land because such a condition is unnecessary.

Logically, Nordic can only utilize the permit on land in which it has an interest allowing it to use

the land for the permitted purpose. Though it is under appeal, the Lot 36 Litigation is the current

law of the case and because it was resolved in Nordic’s favor, this point is now moot.

C. Substantial Record Evidence Exists to Support Grant of Permits

Petitioners and Intervenors contest many of BEP’s findings made during Nordic’s

permitting process. Specifically, they assert BEP’s findings regarding NRPA dredging rules;

Water Permit requirements regarding the use of zero-waste technology, water quality standards,

and State antidegradation statutes; air emissions rules; and SLODA requirements were erroneous

as not based on substantial record evidence. 38 M.R.S. § 414-A requires BEP to affirmatively find

an applicant has met requisite standards prior to issuing a permit or license. As such, Upstream

Watch seeks the invalidation of Nordic’s NRPA Permit, Water Permit, AEL, and SLODA Permit

under MAPA for failure to make such affirmative findings. Upstream Watch overstates this

Court’s capacity to overturn administrative decisions; review of BEP decisions on appeal is

“deferential and limited,” Champlain Wind, 2015 ME 156, ¶ 13, 129 A.3d 279, and the standard

for substantial record evidence is very low, Osprey Family Trust v. Town of Owls Head, 2016 ME

89, ¶ 9, 984 A.2d 1285.

14
a. NRPA Permit

NRPA requires under 38 M.R.S. § 480-D(9) that proposed activities involving dredging,

dredge spoils or transporting dredge spoils by water demonstrate, with sufficient public

involvement, “the transportation route minimizes adverse impacts on the fishing industry and that

the disposal site is geologically suitable.” The DEP found the installation of seawater and

wastewater pipes for the salmon farm qualifies as dredging and applied this statute, which requires

the Commissioner of the Department of Marine Resources (“DMR”) to provide an assessment of

potential impacts on the area to be dredged and on local fishing operations. § 480-D(9). The DMR

held a public hearing, submitted comments to the BEP, and requested sediment testing along the

pipes’ route. It recommended measures, which were added to the permit conditions, to prevent

siltation when transporting excess dredge material by barge to Mack Point in Searsport, where it

will by transported by truck to an upland disposal site. On the basis of the DMR’s comments, the

sediment testing results, predictions of contaminant dispersion, and public comments, the BEP

found that the dredging connected to Nordic’s project would not cause an unreasonable adverse

effect under § 480-D(9).

Petitioners argue the BEP improperly refused to admit evidence in the form of a map of

the dredge spoils disposal route presented at the DMR hearing into its own record. Petitioners

wanted a hearing to determine whether Nordic had materially changed its dredge spoils disposal

plan, though Nordic denies any deviation from the permitted plan. Given the lack of good cause

shown by the Petitioners to reopen the BEP record and admit this additional evidence, this Court

may infer it was proper for the BEP to deny their motion on the disposal plan details.

Other arguments put forth by Petitioners on the NRPA Permit are inapplicable. They say

the BEP should have conditioned this and other permits on Nordic’s obtaining of other, related

15
stated and federal permits. However, a successful permit applicant must still comply with all other

applicable regulations and acquire all other relevant licenses; there is generally no need to

condition one permit on the acquisition of another. Moreover, the permits Petitioners believe

should have been made prerequisite to the NRPA Permit are inapplicable to Nordic’s proposed

activities. For example, Petitioner argues the BEP erred by not requiring an additional type of

Water Permit, related to solid waste disposal at Mack Point, to grant the NRPA Permit. But Nordic

does not propose disposing of any solid waste at Mack Point. That is only the point at which the

dredge spoils will be unloaded from barges onto trucks for disposal elsewhere, and the BEP found,

based on record evidence, that the ultimate disposal site is properly licensed. NRPA also sets forth

requirements for projects involving “dredge spoils disposal in a coastal wetland,” including (i)

collecting and testing the dredge spoils; (ii) publishing notice of the proposed route for transporting

the dredge spoils to a disposal site; and (iii) submitting the application to each municipality

adjacent to any proposed marine and estuarine disposal site and route, 38 M.R.S. § 480-E(3), and

Petitioners contend the BEP’s decision violated testing and notice requirements. However,

Nordic’s project does not envision disposing dredge spoils in the costal wetland and the NRPA

permit as granted does not provide for such disposal, rendering § 480-E(3) irrelevant.

b. Water Permit

i. The BEP Did Not Abuse Its Discretion in Finding Nordic’s Proposal is the

Best Practicable Treatment

Upstream Watch contends that the Water Permit should have been denied because Nordic’s

proposed water treatment system is not the “best practicable treatment” for its discharge and that

the BEP abused its discretion by failing to consider zero-discharge systems. Under § 414-A(1)(D),

where pollutants will be discharged, a Water Permit is only available if “[t]he discharge will be

16
subject to effluent limitations that require application of the best practicable treatment.” The best

practicable treatment is that which applies the “best conventional pollutant control technology or

best available technology economically achievable” for a given type of discharge source which the

DEP determines to be best calculated to protect and improve the quality of the receiving water and

which is consistent with the federal Clean Water Act and other federal regulations. § 414-A(1)(D).

According to Upstream Watch, only a “zero-discharge” system would fulfill these requirements.

Nordic counters that the CWA expressly allows for non-zero-discharge systems that otherwise

comply with the Act and that zero discharge is a stated goal, not a requirement. “Best practicable

treatment” is a distinct standard from “best available treatment.” The best available technology

may not be economically or pragmatically feasible in a given project, making it non-practicable,

and the statutory language recognizes this. In the case of the salmon farm, BEP made findings,

based on evidence presented by Nordic, that Upstream Watch’s proposed zero-discharge

technology is not scalable to the size of the project.

A lack of an explicit, written finding that the zero-discharge technology is not practicable

in the context of the proposed salmon farm does not equate to a lack of a finding on the matter.

This Court may infer BEP considered and rejected the zero-discharge proposal because “the

subsidiary facts may be obvious or easily inferred from the record and the general factual findings.”

Fair Elections Portland, Inc. v. City of Portland, 2021 ME 32, n. 11, 252 A.3d 504. BEP heard

and considered conflicting oral and written testimony about the implementation of zero-discharge

processes and Upstream Watch submitted written filings, including examples of this technology.

Consequently, this Court infers BEP, in its judgment, rejected this technology as not being the

“best practicable treatment” because BEP issued a permit for a different sort of treatment process

after reviewing such evidence. Moreover, the language of § 414-A(1) states that the agency “shall”

17
issue wastewater discharge permits where it makes the enumerated findings. The agency may not

require redesigns or a “best available treatment” even if a better process is available so long as the

criteria of § 414-A are met. The BEP both applied the narrative National Effluent Guidelines, 40

C.F.R. § 451.1, and, in its best professional judgment, set numeric standards for pollutants from

this type of discharge, ultimately finding that Nordic’s proposal complies with § 414-A as the best

practicable treatment.

ii. The BEP Did Not Abuse Its Discretion in Finding Proposed Discharge Does

Not Violate Maine’s Antidegradation Statutes Nor Temperature Standards

Discharging pollutants into State waters requires a permit under 38 M.R.S. §§ 361-A(7) &

413. § 414-A(1)(C) generally prohibits discharge permits where the discharge will lower the

existing quality of a body of water below its current grade. Where discharges would lower water

quality, the BEP must find the discharge “is necessary to achieve important economic or social

benefits to the State and when the action is in conformance with subparagraph (3) [requiring

periodic reporting on water quality to the Legislature].” 38 M.R.S. § 464(4)(F)(5). Similarly, Ch.

582 of the DEP Rules states discharge of pollutants may not change the monthly mean ambient

temperature of a tidal body of water by more than a set amount. 06-096 C.M.R. ch. 582 § 5.

Minimum standards for State bodies of water are set out in a water quality classification system

under §§ 464(1) and 469. Upstream Watch’s arguments as to BEP’s findings regarding the effect

Nordic’s wastewater discharge will have on the water quality and ambient temperature of Belfast

Bay are not persuasive. It is beyond the scope of this appeal for this Court to second-guess BEP’s

factual findings “on matters falling within its realm of expertise.” Mulready, 2009 ME 135, ¶ 13,

984 A.2d 1285 (quoting Wood v. Superintendent of Ins., 638 A.2d 67, 71 (Me. 1994)).

18
Upstream Watch claims the BEP improperly made its findings on water quality in the

context of nitrogen absorption levels based on evidence admitted after the close of the record. To

the contrary, the BEP used data already in the record to reassess its findings after Nordic noted

that BEP staff had incorrectly calculated nitrogen levels using a worst-case scenario in lieu of the

standard, long-term tidally averaged valuation. The Presiding Officer reopened the record to allow

all parties to comment on the new calculations and use of the exiting data and provided Intervenors

with the emails on the subject between Nordic and BEP staff for their review. After recalculating,

BEP staff concluded in a revised memorandum that the proposed discharge would still slightly

lower water quality due to nitrogen levels, thus requiring the BEP to specifically approve the

discharge under § 464(4)(F)(5), which it did. The BEP also requires Nordic to conduct post-permit

studies to monitor dilution factors to ensure compliance with the Water Permit. This is an open

and fair deliberative process.

Upstream Watch also contends the BEP was wrong to use surface water temperature

measurements when calculating the impact Nordic’s wastewater discharge will have on the mean

ambient temperature of Belfast Bay. This is an improper argument in this appeal. Moreover, the

BEP has provided a reasonable rationale for its methods, noting that the warmed water will

naturally rise to the surface from the deeper point at which the discharge pipes enter the bay, and

points to 38 M.R.S. § 451, which specifically allows for a reasonable mixing of effluent and

receiving water. The BEP heard extensive testimony on thermal discharge and considered models

demonstrating the thermal impact and buoyancy of Nordic’s effluent and concluded that the

discharge will meet the criteria of Ch. 582, conditioning the permit on regular monitoring of

receiving water temperature. The record shows the BEP considered substantial, competent

evidence. This Court cannot question either the BEP’s findings or its choice of methodology in

19
reaching these findings, only whether it abused its discretion; Upstream Watch has not

demonstrated any such abuse.

c. Air Emissions License

Under 38 M.R.S. § 590 and the federal Clean Air Act, the DEP licenses sources of pollutant

air emissions, implemented by 06-096 C.M.R. ch. 115. Section 4(C)(6) of Ch. 115 sets out the

requisite criteria an applicant must demonstrate for new minor sources of air emissions, and the

DEP must grant a license if these criteria are met. A “minor source” is defined as any source which

emits or has the potential to emit regulated pollutants excluding greenhouse gases at rates less than

significant emissions 11 and is not defined as a Part 70 source. 06-096 C.M.R. ch. 100 § 89. These

criteria comprise (i) providing the DEP a complete application; (ii) showing the emissions will

receive the Best Available Control Technology (“BACT”) 12 as described in subsection 4(A)(4)(d);

(iii) showing the emissions will not violate state standards adopted by the DEP under 38 M.R.S. §

585 or can be controlled so as not to violate them; (iv) showing the emissions will not violate or

can be controlled not to violate specified ambient air quality standards; (v) showing the conditions

of the license provide for compliance with all relevant State and Chapter requirements; showing

the DEP and applicant complied with public participation and review under subsection 4(C)(3);

and (vi) in the case of an AEL amendment, installing additional emissions controls or mitigating

measures, if necessary, within twenty-four months of the issuance of the amendment. 06-096

C.M.R. ch. 115, § 4(C)(6). Upstream Watch argues the BEP misinterpreted § 590 and Ch. 115

11
Defined as any rate of emissions which would equal or exceed one hundred tons per year of any regulated
pollutant excluding greenhouse gases or fifty tons per year of volatile organic compounds in the ozone transport
region. 06-096 C.M.R. ch. 100 § 156.
12
The statutory standard is “best practical treatment,” which is lower than BACT. For the purposes of this appeal,
the Court will assume the stricter standard controls. Compare 38 M.R.S. § 590(2)(A) with 06-096 C.M.R. ch. 115 §
4(C)(6)(b).

20
when it categorized Nordic’s facility as a “minor” source because Nordic did not disclose its full

power demand and because Upstream Watch is uncertain that Nordic will operate within the annual

limit of 900,000 gallons of fuel for its backup generators imposed by the BEP in the AEL.

Upstream Watch’s opposition to the grant of the AEL revolves around these generators and the

emissions they will produce.

These are questions of fact. The record shows the BEP found Nordic qualifies as a “minor

source” because of the fuel limit imposed in the AEL. Nordic intends to use the generators for

backup power and peak shaving while primarily using electricity from the local grid, so the issue

of the total power draw by the facility is inapposite. Only the expected use of the generators is

relevant, the BEP found usage within the fuel limit will meet permit requirements, and Nordic

testified it believes the limit is several times higher than what it will actually need. In the event of

a power outage, the generators will provide necessary, short-term emergency electricity, not power

full-scale facility operations. The record also shows peak-shaving usage of generators will be

limited and will not use more fuel than conditioned by the license. Should Nordic be forced to

exceed the AEL fuel limit for any reason, it will have to apply for an amendment to the AEL.

Under § 590(2)(C), an AEL applicant’s emissions must not violate or must be controlled

so as not to violate applicable ambient air quality standards “[e]ither alone or in conjunction with

existing sources.” Judicial interpretation of this statute is de novo but great deference is given to

the BEP’s reading, which will not be refuted unless the statute “plainly compels a contrary result.”

Passadumkeag Mountain Friends, 2014 ME 116, ¶ 12, 102 A.3d 1181. Upstream Watch argues

that “other existing sources” should be interpreted as including all other emission sources from the

salmon farm. The BEP, however, considers “other existing sources” to mean only sources which

are not exempt or insignificant, and thus not subject to licensing, under Ch. 115 App. B. The other

21
emission sources from the salmon farm include the fish processing plant, the wastewater treatment

plant, the office building, and fish grow-out buildings, among others. It is reasonable based on

evidence in the record for the BEP to have considered these other sources as exempt or

insignificant and thus did not consider them when calculating the generator emissions’ effect on

air quality. See generally Ch. 115 App. B § A. The record also shows that the BEP considered the

effect of generator emissions under a conservative assumption that the generators were in constant

use despite the fuel limit and stated intentions of Nordic to use them a fraction of that amount.

Even under this assumption, the BEP found no violation of ambient air quality standards. Upstream

Watch has not carried its burden to show the statute plainly compels a result contrary to that which

the BEP reached.

d. Site Location of Development Act Permit

SLODA requires the builder of a development of state or regional significance which

may substantially affect the environment to demonstrate certain licensing criteria. 28 M.R.S. §§

481-490-E; 06-096 C.M.R. ch. 375. These criteria, set out in § 484, address a number of

environmental concerns and require a developer to show, among other things, “that the

development will not adversely affect existing uses, scenic character, air quality, water quality

or other natural resources in the municipality or in neighboring municipalities.” The BEP must

issue a permit to an applicant who meets the stated criteria. Upstream Watch argues the BEP did

not properly find that Nordic met the SLODA permitting requirements.

The BEP considered emissions from both the permanent generators, see supra, and those

produced by equipment during the construction of the facility and found no adverse impact on

air quality. It also analyzed record evidence on how the facility will impact freshwater resources

and determined that Nordic’s strategic use of a variety of groundwater sources will not

22
adversely impact local resources, conditioning the permit on Nordic's monitoring of the Little

River reservoir and other wells for adverse effects. Upstream Watch has not shown a lack of

record evidence in support of the BEP's findings for SLODA permitting purposes.

CONCLUSION

Based on the foregoing, the entry will be: Petitioner Upstream's Motion to Stay is

DENIED. Respondent BEP's decision is AFFIRMED.

SO ORDERED.

The Clerk is requested to enter this Order on the Docket, incorporating it by reference

pursuant to M.R. Civ. P. 79(a).

Date: 2/23/2022
M. Michaela Murphy, Justice
Business & Consumer Court

Entered on the docket: 02/23/2022

23
STATE OF MAINE BUSINESS AND CONSUMER COURT
CUMBERLAND, ss BCD-APP-2021-00009

JEFFREY MABEE, et al., )
)
Petitioners, )
)
v. )
)
BOARD OF ENVIRONMENTAL )
PROTECTION, )
)
Respondent. )
)
__________________________________ ) COMBINED ORDER ON MOTIONS
)
UPSTREAM WATCH, )
)
Petitioner, )
)
v. )
)
BOARD OF ENVIRONMENTAL )
PROTECTION, )
)
Respondent. )

Before the Court are two motions brought by Petitioners that were still pending before the Waldo

County Superior Court when these consolidated cases were transferred to this Court.

The first seeks leave to exceed page limits set by M.R. Civ. P. 7(F). The second is a Motion to

Amend Petition, Permit Discovery and for an Order Specifying the Course of Future Proceedings.

The Court has reviewed the filings of the parties and for the reasons stated, denies both the

Motion to Exceed Page Limits as well as the Motion to Amend, Permit Discovery and to Specify the

Course of Future Proceedings.

With respect to the motion regarding page limits, which is opposed, the Court has reviewed the

motion as well as the many pages of attachments to what is usually presented as an unopposed procedural

motion. Because the many documents attached are directly pertinent to the second, more substantive

1
motion, the outcome of the first motion is controlled by the Court’s analysis and conclusion as to the

second.

The second motion is captioned as Motion to Amend Petition, Permit Discovery and to Specify

the Course of Future Proceedings, and it seeks three things. First, it seeks to clarify that the proper

Respondent in this case should be the Department of Environmental Protection (DEP) and not the Board

of Environmental Protections (BEP). Second, it seeks to add independent claims. Third, the motion seeks

to conduct discovery on those claims.

As to the motion to have the Respondent designated as the DEP instead of the BEP, that request

is denied. As current Respondent BEP points out, it was BEP that issued the permitting decisions that are

under appeal by Petitioners. The BEP is therefore the proper party. The Board acted as fact-finder in this

case and it will be the Board’s findings and conclusions that will be reviewed.

With respect to the motion to add independent claims and conduct discovery, the Petitioners

argue that materials outside the record in the form of email communications made in the first few weeks

of 2019 provide a basis for independent claims. These emails can fairly be described as emails between

members of the Governor’s Office, the DEP Acting Commissioner, Nordic and other third parties

including the Governor’s brother who was also during this time frame working as a member of the

Governor’s Transition Team. All the emails, along with a meeting that took place involving some of these

individuals, pre-date the formal application process before the agency. They do support the proposition

that the project at issue was one that was favored by the Administration. However, these preliminary

discussions are not enough, in the Court’s view, to overcome the presumption of good faith this Court is

obligated to apply to the decision makers at the BEP. See Beal v. Town of Stockton Springs, 2017 ME 6, ¶

19, 153 A.3d 768 (quoting Mr. & Mrs. V. v. York Sch. Dist., 434 F. Supp. 2d 5, 12-13 (D. Me. 2006))

(administrative agency officer “enjoys a presumption of honesty and integrity”). At the time of these

communications, the BEP had not yet asserted jurisdiction over the application at issue here, and no part

of the adjudicatory process had yet begun. And as pointed out by Respondent BEP, there is no indication

2
at all that the BEP was ever made aware of these very preliminary inquiries or communication described

in the emails at issue. The Court is also unpersuaded that because the BEP is permitted to rely upon DEP

staff during the BEP process, the administrative proceeding was somehow defective or was

inappropriately affected by political influence.

For these reasons, the Court will deny the motion to add independent claims or to conduct

discovery on those claims. This decision obviates the need to consider the third part of the motion which

seeks to obtain an Order specifying the course of future proceedings, and it determines the outcome of the

motion seeking to exceed page limits.

The entry will be: The Motion to Exceed Page Limits is DENIED. The Motion to Amend

Petition, Permit Discovery, and for on Order Specifying the Course of Future Proceedings is also

DENIED. The Clerk shall note this Combined Order on the docket by reference pursuant to Rule 79(a) of

the Maine Rules of Civil Procedure.

_____________________________ ______________________________________

DATE M. Michaela Murphy
SUPERIOR COURT JUSTICE

3

---

Source: Frix Law Library, https://www.frixlaw.com/law-library/cases/10812220. Public record. Not legal advice.
