# Grass v. Bangor

> Superior Court of Maine · December 9, 2010

URL: https://www.frixlaw.com/law-library/cases/10809497

## Case

- **Court:** Superior Court of Maine
- **Decided:** December 9, 2010
- **Precedential status:** Unpublished
- **Opinion:** Opinion
- **Judges:** William R. Anderson
- **Cited by:** 0 later opinions in the Frix Law Library

## Citator (automated)

- No negative treatment found by the automated citator. That is not the same as a confirmation that the case is good law; read the citing cases.
- Full citator and citing cases: https://www.frixlaw.com/law-library/cases/10809497

## Opinion text

STATE OF MAINE SUPERIOR COURT
PENOBSCOT, ss CIVIL ACTION
DOCKET NO. RE-Or~4
WRf1~ f'~ tJ - Ic;Y~1 ,)010
JEFFREY B. GRASS, d/b/a
J.B. GRASS EXCAVATING

Plaintiff,

v. ORDER ON DEFENDANT
PM CONSTRUCTION'S
RICHMOND BANGOR MOTION IN LIMINE
DEVELOPMENT, LLC,
PM CONSTRUCTION CO., INC.,
EASTERN BANK and
KATAHDIN TRUST COMPANY

Defendants.

Before the Court is Defendant PM Construction Co., Inc. ("PM")'s motion in

limine requesting that Article 9 ("Article 9") of the contract ("Contract") between PM

and Plaintiff Jeffrey B. Grass, d/b/a J.B. Grass Excavating ("Grass") be found

unambiguous, therefore excluding any parol evidence relating to Article 9. Additionally,

PM asks that the Court "rule that Article 9 did not require PM Construction and Grass to

agree upon and execute change orders as a condition precedent to Grass being obligated

to perfonn changes to the scope of work as originally set forth in the Contract." (Def.' s

M. Limine 1.). In response, Grass has filed in opposition to PM's motion, requesting

that the Court rule that the Contract was unambiguous but required written change orders

between Grass and PM before any additional work was to be performed. In the

alternative, Grass requests that the Court find that the relevant Contract provisions are

ambiguous. Finally, Grass asks that if PM's interpretation of the Contract is adopted,

Article 9 be found unconscionable, invalid and unenforceable. (PI.' s Opp. M. Limine 1.).

1
1. FACTUAL BACKGROUND

Grass and PM agree about little in the factual record. Points of disagreement

between the parties regarding the facts will be noted. In or about September 2007, PM

and Grass entered into the Contract with PM serving as the contractor and Grass a

subcontractor on a project building a Walgreen's Pharmacy in Bangor. The Contract,

which both parties acknowledge as accurate, is attached as Exhibit 1 to Defendant's

Motion in Limine. The parties also both acknowledge that Exhibit 2 to Defendant's

Motion in Limine, entitled "AlA Document A 101™ - 1997" ("Owner's Contract") is the

controlling agreement between PM and the site's owner The Richmond Company, Inc.

("Richmond").

At some point during the project, a dispute arose between Grass and PM

regarding the scope of the excavation work Grass was obligated to perform under the

Contract. Grass contends that after beginning work on the project, it was discovered that

serious differences existed between the elevations identified in the site plans and

documents provided by PM and the actual elevations at the site. (PI.' s Opp. M. Limine

3.). Further, Grass alleges that PM instructed Grass to alter the proscribed method for

excavating trenches after Grass had began performing the work, creating a significant

increase in work. (PI.' s Opp. M. Limine 4.). Finally, Grass claims that the initial plans

and specifications indicated that the soils excavated on site would be used for fill and

backfill, but after commencing work PM directed him to remove the excavated soil and

obtain backfill from off site, which caused Grass added work and expenses. ld.

2
PM, while not addressing specific incidents, generally denies that Grass was

instructed to complete any work outside the scope of their agreement, but accepts the

contention solely for the purposes of this motion. (Def.' sM. Limine 2.).

At the time the dispute arose, Grass refused to continue work on the project until

Grass and PM agreed on written change orders delineating the scope of the new work as

well as Grass's compensation for performing. (Pl.'s Opp. M. Limine 4-5.). Grass claims

that PM's project manager issued assurances that change orders would be executed, but

that instead of providing change orders, PM hired another excavation company to

perform the additional work and the remaining work under the Contract. (Pl.' s Opp. M.

Limine 5.). PM disagrees that change orders were necessary, and alleges that Grass left

the project. (Def.' s M. Limine 1-2.).

At issue is the interpretation of Article 9 of the Contract, reprinted here in full:

Contractor may unilaterally make changes in the work
covered by this Subcontract. Upon receipt of Contractor's
written authorization to proceed with changed work,
Subcontractor shall perform the changed work without
delay. Extra compensation for such changed work will
only be allowed when the amount has been agreed to prior
to the execution of the changed work or when Contractor
has been paid extra compensation by the Owner for said
changed work. No compensation for changes or any other
claims whatsoever shall be allowed unless Contractor is
entitled to payment for Owner and the claim is submitted to
Contractor in a timely fashion allowing Contractor to
process the claim under the terms of the Contract
Documents. The failure to so submit claims in a timely
manner shall be deemed a waiver of the claim by the
Subcontractor. All changes must be authorized by
Contractor's form before payment will be made. (Def. Exh.
1,2).

ll. APPLICABLE LAW

3
"The issue of whether contract language is ambiguous is a question of law for the

court." Portland Valve, Inc. v. Rockwood Systems Corp., 460 A.2d 1383, 1387 (Me.

1983). See also Beal v. Allstate Insurance Company, 2010 ME 20, ~ 26,989 A.2d 733,

741. If the contract language is unambiguous, its interpretation is also a question oflaw

for the Court. Portland Valve, 460 A.2d at 1387. "A contract provision is considered

ambiguous if it is reasonably possible to give that provision at least two different

meanings." Villas by the Sea Owners Ass 'n v. Garrity, 2000 ME 48, ~ 9, 748 A.2d 457,

461. "The parol evidence rule operates to exclude from judicial consideration extrinsic

evidence offered to alter, augment or contradict the unambiguous language of an

integrated written agreement." Handy Boat Servo v. Proffessional Servs., 1998 ME 134, ~

11, 711 A.2d 1306, 1308-09.

III DISCUSSION

a. Ambiguity and the Parol Evidence Rule

PM argues that Article 9 is an unambiguous statement that PM could unilaterally

make changes to Grass's scheduled work, which Grass was obligated to perform upon

receipt of written authorization. Regarding payment, PM points out that there are two

possible methods for payment in Article 9: upon an agreement for extra compensation in

advance of the work being done, or if the Owner compensated PM for the extra work.

PM classifies the payment provisions as a condition precedent to Grass obtaining extra

payment and not a pre-condition to the obligation to perform extra work.

Grass counters by arguing that Article 9 is ambiguous because "[i]t makes no

sense that within the same paragraph, one can first force someone to do work without

receiving compensation and then state that no extra compensation will be allowed for the

4
work if it is not agreed to prior to execution ofthe work." (PI.' s Opp. M. Limine 10.)

(emphasis added). The plain language of Article 9 speaks against this argument.

Article 9 states that "[e]xtra compensation for such changed work will only be

allowed when the amount has been agreed to prior to the execution of the changed work

or when Contractor has been paid extra compensation by the Owner for said changed

work." (Def. Exh. 1,2). This statement, while serving the interests of PM, is not

ambiguous. It simply means that if there is not an agreement for payment prior to PM

providing Grass with a work authorization, PM will pay Grass upon receiving

compensation for the extra work from Richmond. There is no provision in Article 9

saying that a claim for compensation for extra work must be provided prior to the work

being completed, as Grass argues. The Contract provision simply requires the claim to be

made "in a timely fashion" (alternatively, it is also referred to as "in a timely manner").

(Def. Exh. 1, 2). Thus, a plain reading of Article 9 shows a single method for PM to

direct Grass to complete extra work and two non-conflicting, unambiguous pathways for

Grass to be compensated for performing.

Grass alternatively argues that Article 9 is ambiguous based upon conflicts with

other portions of the Contract. (PI.'s Opp. M. Limine 11.). Grass first points to

paragraph 2 of page 1 of the Contract, which states "Contractor agrees that it will pay to

Subcontractor in accordance with the provisions of Section 7, and subject to and [sic]

increases and decreases resulting from changes that may be agreed upon." (Def. Exh. 1,

1). Grass argues that this section states that there will be no increases or decreases in

compensation unless they are agreed upon.

5
This reading does not conflict with Article 9 to create any ambiguity. Not only

would an agreement upon changed compensation prior to completing the work be an

agreement upon changes, but so would an agreement based upon the alternative fonn of

payment specified in Article 9: a submitted claim to PM, which is in turn compensated by

Richmond, resulting in PM agreeing to compensate Grass. I

Article 9 must therefore be determined to be unambiguous, and because Article 9

is unambiguous, the parol evidence rule works to exclude extrinsic evidence offered

regarding the language of the Contract.

b. Interpretation of Unambiguous Language

Having determined the language of Article 9 to be unambiguous, the Court then

turns to interpreting Article 9. Grass argues that Article 4 of the Contract incorporates

the Owner's Contract's use ofthe phrase "NO CHANGES WITHOUT WRITTEN

CHANGE ORDER/ADDITIONAL WORK AUTHORIZATION IN ADVANCE OF

THE WORK" to require written change orders before proceeding. (Pl.'s Opp. M. Limine

6, quoting Owner's Contract §4.2, 7.6.). However, Article 4 ofthe Contract states:

Also incorporated herein by reference are the General
Conditions of the Contract between the General Contractor
and the Owner of said Project, and Subcontractor hereby
agrees to be bound to Contractor by said General
Conditions in the same manner and to the same extent as
the General Contractor is bound to the owner, except as the
same may be modified herein. (Def. Exh. 1,2).

I Grass also points to the merger clause of the Contract (Article 21), and the clause of the Contract
incorporating the Owner's Contract as far as it is unmodified by the Contract (Article 4) as supporting his
argument that the agreement is ambiguous. Neither clause affects the reading of Article 9 or the procedures
it establishes.

6
A full reading of Article 4 thus shows that despite what may be contained in the Owner's

Contract regarding authorization for changed work, Article 9 of the Contract modifies

that provision.

The plain language of Article 9 states that in order to begin extra work, PM may

unilaterally provide Grass with written authorization to perform, which Grass shall

undertake without delay. There is no requirement for a mutually agreed upon change

order contained in the Contract, as Grass contends.

c. Unconscionability

Grass finally argues that, failing a finding of ambiguity or that a plain reading of

unambiguous language requires a written change order, Article 9 is unconscionable and

therefore unenforceable. Grass makes three arguments for procedural unconscionability:

(1) the take-it-or-leave-it nature of the offer; (2) the use of a broad range of contract

documents including fine print and convoluted language; and (3) PM's enhanced

bargaining power. Grass also claims substantive unconscionability because the terms of

Article 9 are "so one-sided as to shock the conscience." (Pl.'s Opp. M. Limine, 15, citing

Barrett v. McDonald Investments, Inc., 2005 ME 43, ~ 36, 870 A.2d 146, 156 (1.

Alexander concurring)(citations and quotation marks omitted).).

No evidence has been provided regarding the negotiation of the Contract, so it is

impossible to rule on the procedural unconscionability of the Contract. Regarding the

substantive unconscionability claims, Article 9 does not state that Grass will not be paid

if compensation is not decided upon prior to starting work. A process for submitting

claims for extra work already performed is provided, in which PM would compensate

Grass upon receipt of compensation from Richmond.

7
The entry is:

1. The Contract between Grass and PM was not
ambiguous.
2. Parol Evidence will not be considered to construe
the meaning of the Contract.
3. The Contract required only Grass's receipt of
"written authorization" from PM to proceed with
changed work.
4. Article 9 of the Contract was not unconscionable.

The Clerk may make this entry on the docket by reference.

Date: December 1,2010
William R. Anderson
Justice, Superior Court

8
JEFFREY B GRASS DBA J B GRASS EXCA - PLAINTIFF SUPERIOR COURT
3000 BROADWAY PENOBSCOT, 55.
GLENBURN ME 04401 Docket No BANSC-RE-200B-00014
Attorney for: JEFFREY B GRASS DBA J B GRASS EXCA
DONALD F BROWN - RETAINED 10/27/2009
DON BROWN LAW OFFICE DOCKET RECORD
424 SOUTH MAIN ST
PO BOX 3370
BREWER ME 04412

Attorney for: JEFFREY B GRASS DBA J B GRASS EXCA
JOHN BUNKER - WITHDRAWN 11/03/2009
PAINE LYNCH & HARRIS
PO BOX 1451
BANGOR ME 04402-1451

V5
EASTERN BANK - DEFENDANT
C/O TERENCE A. MCGINNIS ONE EASTERN PLACE EP5-10
LYNN MA 01901
Attorney for: EASTERN BANK
THEODORE SMALL - RETAINED 05/30/200B
BERNSTEIN SHUR SAWYER & NELSON
100 MIDDLE ST
PO BOX 9729
PORTLAND ME 04104-5029

Attorney for: EASTERN BANK
MICHAEL BOSSE - RETAINED 05/30/200B
BERNSTEIN SHUR SAWYER & NELSON
100 MIDDLE ST
PO BOX 9729
PORTLAND ME 04104-5029

KATAHDIN TRUST COMPANY - DEFENDANT
C/O MARY BONNIE LONDON POBOX 36
HOULTON ME 04730
Attorney for: KATAHDIN TRUST COMPANY
THEODORE SMALL - RETAINED 05/30/200B
BERNSTEIN SHUR SAWYER & NELSON
100 MIDDLE ST
PO BOX 9729
PORTLAND ME 04104-5029

Attorney for: KATAHDIN TRUST COMPANY
MICHAEL BOSSE - RETAINED 05/30/200B
BERNSTEIN SHUR SAWYER & NELSON
100 MIDDLE ST
PO BOX 9729
PORTLAND ME 04104-5029

Attorney for: KATAHDIN TRUST COMPANY
DANIEL R NELSON - RETAINED
SEVERSON HAND & NELSON PA
355 MARKET SQUARE
Page 1 of 14 Printed on: 12/10/2010

---