# Cole, C. v. DEP, Aplt.

> Supreme Court of Pennsylvania · January 22, 2025

URL: https://www.frixlaw.com/law-library/cases/10784968

## Case

- **Court:** Supreme Court of Pennsylvania
- **Decided:** January 22, 2025
- **Precedential status:** Published
- **Opinion:** Opinion
- **Judges:** Dougherty, Kevin M.
- **Cited by:** 0 later opinions in the Frix Law Library

## Citator (automated)

- No negative treatment found by the automated citator. That is not the same as a confirmation that the case is good law; read the citing cases.
- Full citator and citing cases: https://www.frixlaw.com/law-library/cases/10784968

## Opinion text

[J-13A-2024, J-13B-2024, J-13C-2024 and J-13D-2024] [MO: Wecht, J.]
IN THE SUPREME COURT OF PENNSYLVANIA
EASTERN DISTRICT

CLIFFORD COLE, PAMELA WEST, : No. 21 EAP 2023
BRIAN,WEIRBACK, KATHY WEIRBACK, :
TODD SHELLY AND CHRISTINE SHELLY, : Appeal from the Order of the
: Commonwealth Court dated June
Appellees : 15, 2021 at No. 1577 CD 2019,
: Reversing and Remanding the
: Order of the Pennsylvania
v. : Environmental Hearing Board dated
: October 9, 2019 at No. 2019-046-L.
:
PENNSYLVANIA DEPARTMENT OF : ARGUED: March 5, 2024
ENVIRONMENTAL PROTECTION, :
:
Appellant :

WEST ROCKHILL TOWNSHIP, : No. 22 EAP 2023
:
Appellee : Appeal from the Order of the
: Commonwealth Court dated June
: 15, 2021 at No. 1595 CD 2019,
v. : Reversing and Remanding the
: Order of the Pennsylvania
: Environmental Hearing Board dated
DEPARTMENT OF ENVIRONMENTAL : September 25, 2019, at No. 2019-
PROTECTION, : 039-L.
:
Appellant : ARGUED: March 5, 2024

CLIFFORD COLE, PAMELA WEST, BRIAN : No. 77 MAP 2023
WEIRBACK, KATHY WEIRBACK, TODD :
SHELLY AND CHRISTINE SHELLY : Appeal from the Order of the
: Commonwealth Court dated June
: 15, 2021 at No. 1577 CD 2019,
v. : Reversing and Remanding the
: Order of the Pennsylvania
: Environmental Hearing Board dated
PENNSYLVANIA DEPARTMENT OF : October 9, 2019 at No. 2019-046-L
ENVIRONMENTAL PROTECTION :
: ARGUED: March 5, 2024
:
APPEAL OF: ADELPHIA GATEWAY, LLC :
WEST ROCKHILL TOWNSHIP : No. 78 MAP 2023
:
: Appeal from the Order of the
v. : Commonwealth Court dated June
: 15, 2021 at No. 1595 CD 2019,
: Reversing and Remanding the
DEPARTMENT OF ENVIRONMENTAL : Order of the Pennsylvania
PROTECTION : Environmental Hearing Board dated
: September 25, 2019, at No. 2019-
: 039-L
APPEAL OF: ADELPHIA GATEWAY, LLC :
: ARGUED: March 5, 2024

CONCURRING OPINION

JUSTICE DOUGHERTY DECIDED January 22, 2025
I join the well-reasoned majority opinion in full.1 I write separately, however, to

explain additional reasons to reject Adelphia’s assertion “[t]he EHB has no role in

1 I do, however, question the impact of the majority’s determination that the Third Circuit

incorrectly held DEP’s permit decisions are final for purposes of federal law in Del.
Riverkeeper Network v. Sec’y Pa. DEP, 903 F.3d 65 (3d Cir. 2018) (Riverkeeper III), even
if this Court is technically not bound by that determination. See Majority Opinion Section
III.B. While I agree with the majority’s analysis, including its approval of the First Circuit’s
reasoning in Berkshire Environmental Action Team, Inc. v. Tenn. Gas Pipeline Co., 851
F.3d 105 (1st Cir. 2017), I feel compelled to point out that the Third Circuit’s decision in
Riverkeeper III specifically addressed finality in the context of Pennsylvania’s
administrative scheme, while Berkshire Environmental discussed Massachusetts’s
scheme. Additionally, in the normal course, these appeals originating in Pennsylvania
should not make their way to this Court, but instead will go to the Third Circuit. See 15
U.S.C. §717r(d)(1). Thus, although I agree with the majority’s full-throated defense of
EHB’s role in our administrative scheme, as explicitly stated by the plain text of 35 P.S.
§7514(c) (the EHB Act), in this legal landscape, I expect Natural Gas Act permit decisions
originating in Pennsylvania will be subject to the Third Circuit’s federal finality holding in
Riverkeeper III. I would hope that, upon considering the majority’s persuasive analysis
here, the Third Circuit will reconsider its reasoning in Riverkeeper III and ameliorate the
“dual” jurisdiction of which appellants complain. See, e.g., Adelphia’s Brief at 42; DEP’s
Brief at 8. At the very least, the majority’s apt opinion might provide good reason for the
federal court to abstain from exercising its jurisdiction until the conclusion of
Pennsylvania’s administrative processes, in which EHB plays a pivotal role, rather than
enter the fray when the permit decision is still incomplete.

[J-13A-2024, J-13B-2024, J-13C-2024 and J-13D-2024] [MO: Wecht, J.] - 2
implementing, enforcing, or administering the Chapter 127 regulations” incorporated into

Pennsylvania’s State Implementation Plan (SIP) under the Clean Air Act (CAA), which

further justify our conclusion the Natural Gas Act (NGA) does not preempt EHB review.

Adelphia’s Reply Brief at 8.

Preliminarily, I recognize appellants are correct that in Schneidewind v. ANR

Pipeline Co., the Supreme Court of the United States held the NGA occupies the field of

wholesales of natural gas in interstate commerce to the exclusion of state law. See 485

U.S. 293, 300-04 (1988). Crucially, however, the NGA has a savings clause: “Except as

specifically provided in this chapter, nothing in this chapter affects the rights of States

under – (1) the Coastal Zone Management Act of 1972 (16 U.S.C. 1451 et seq.); (2) the

Clean Air Act (42 U.S.C. 7401 et seq.); or (3) the Federal Water Pollution Control Act

(33 U.S.C. 1251 et seq.).” 15 U.S.C. §717b(d) (emphasis added).

Like the majority, I believe Pennsylvania’s “rights . . . under” the CAA allow for EHB

review of DEP permit decisions made pursuant to the CAA. Id.; see Majority Opinion at

30-32 (explaining Pennsylvania’s SIP incorporates a regulation titled “Notice of basis for

certain plan approval decisions” which provides “[t]he action in [DEP’s] notice shall be

final and not subject to review unless, within 30 days of the service of the notice, a person

affected thereby appeals to the EHB setting forth the grounds relied upon.”), citing 25 Pa.

Code §127.13c(d). Adelphia correctly notes the regulation the majority cites is specific to

circumstances where DEP “denies a plan approval application or terminates, modifies,

suspends or revokes a plan approval already issued[,]” 25 Pa. Code §127.13c(a), and

here, DEP approved the application. Nevertheless, this provision “documents the EHB’s

federally approved role as a reviewing body of CAA decisionmaking.” Majority Opinion

at 31.

[J-13A-2024, J-13B-2024, J-13C-2024 and J-13D-2024] [MO: Wecht, J.] - 3
Of course, that SIP provision is not the only indication of EHB’s role in enforcing

the CAA. The regulation codified at 25 Pa. Code §127.12b, entitled “Plan Approval Terms

and Conditions,” is incorporated as part of Pennsylvania’s SIP. Subsection (b) of that

regulation provides: “[a]t a minimum, each plan approval must incorporate by reference

the emission and performance standards and other requirements of the act, the Clean

Air Act or the regulations adopted under the act or the Clean Air Act.” 25 Pa. Code

§127.12b(b). The term “act” as used in that particular article of the Code2 refers to “[t]he

Air Pollution Control Act (35 P.S. §§4001–4015)[,]” (APCA). Id. §121.1. Thus, for plan

approvals to comply with Pennsylvania’s SIP, they “must incorporate by reference the . .

. requirements of [APCA].” Id. at §127.12b(b).3 Critically, APCA includes a provision

mandating:

2 Title 25 (Environmental Protection), Part I (Department of Environmental Protection),

Subpart C (Protection of Natural Resources), Article III (Air Resources).
3 Pennsylvania’s SIP includes an “additional explanation” regarding the incorporation of

25 Pa. Code §127.12b that states: “[r]evised; limited approval.” 40 C.F.R. §52.2020; EPA,
EPA Approved Regulations in the Pennsylvania SIP, https://www.epa.gov/air-quality-
implementation-plans/epa-approved-regulations-pennsylvania-sip (last visited
September 17, 2024). The SIP also lists an EPA approval date of October 5, 2012 for
section 127.12b and cites to the associated Federal Register publication from that date.
See 77 F.R. 60910. In 77 F.R. 60910, the EPA simply responded to a comment
challenging an expansion to “shakedown period” extensions provided in section
127.12b(c). See id. EPA approved the revisions to 25 Pa. Code §127.12b, and in doing
so, noted it “requires each plan approval to contain all applicable CAA requirements[,]”
which is a requirement found in section 127.12b(b). Moreover, the SIP does not specify
subsections included or excluded from section 127.12b (as it does for other Code
sections) and the PDF available on EPA’s website listing the relevant Code Provisions in
Chapter 127 includes section 127.12b(b). See EPA, Pennsylvania SIP, Construction,
Modification, Reactivation, and Operation of Sources- Plan Approval Requirements,
https://www.epa.gov/air-quality-implementation-plans/pennsylvania-sip-construction-
modification-reactivation-and-1, (linking https://www.epa.gov/sites/default/files/2017-
08/documents/chapter_127_subchapter_b_comprehensive_11_5_12_15_pgs.pdf). We
have no reason to believe subsection (b) is excluded from Pennsylvania’s SIP. Indeed,
even Adelphia cites an EHB decision for the proposition that “Pennsylvania’s SIP
‘includes the Air Pollution Control Act and the Department’s regulations’ in order to
demonstrate ‘how [the Department] intends to achieve EPA’s [NAAQS].’” Adelphia’s
(continued…)

[J-13A-2024, J-13B-2024, J-13C-2024 and J-13D-2024] [MO: Wecht, J.] - 4
The [environmental] hearing board shall have the power and its duty
shall be to hear and determine all appeals from appealable actions of the
department as defined in the act of July 13, 1988 (P.L. 530, No. 94), known
as the “Environmental Hearing Board Act,” in accordance with the
provisions of this act. Any and all action taken by the hearing board with
reference to any such appeal shall be in the form of an adjudication, and all
such action shall be subject to the provisions of 2 Pa.C.S. (relating to
administrative law and procedure).
35 P.S. §4006 (footnote omitted) (emphasis added). APCA further provides:
Any person aggrieved by an order or other administrative action of [DEP]
issued pursuant to this act or any person who participated in the public
comment process for a plan approval or permit shall have the right, within
thirty (30) days from actual or constructive notice of the action, to appeal
the action to [EHB] in accordance with the [EHB Act], and 2 Pa.C.S. Ch. 5
Subch. A . . . .
35 P.S. §4010.2. Thus, EHB’s reviewing authority does not derive solely from the EHB

Act but is also embedded in APCA itself.

In my view, the availability of EHB review is likely a “requirement[]” of APCA for

purposes of 25 Pa. Code §127.12b(b), though I acknowledge we have not received full

advocacy on this point. Regardless, it appears DEP complied with such a plan approval

content requirement in this case; the plan approval stated DEP was authorized to issue it

“in accordance with the provisions of [APCA],” Plan Approval at 1 (emphasis added),

and the accompanying letter stated “[a]ny person aggrieved by this action may appeal the

action to [EHB],” while providing information on how to file an appeal with EHB. Plan

Approval Letter (Apr. 19, 2019).

But more importantly, even if one does not believe section 127.12b(b) incorporates

EHB review via APCA explicitly, it is still undeniable APCA provides for EHB review. See

35 P.S. §§4006, 4010.2. Thus, all the provisions of APCA were adopted in the context of

an administrative scheme that presumed the availability of EHB review. We cannot

Reply Brief at 7, quoting N. Am. Refractories Co. v. DEP, 2000 EHB 707, 715 (emphasis
added).

[J-13A-2024, J-13B-2024, J-13C-2024 and J-13D-2024] [MO: Wecht, J.] - 5
extricate EHB review without impacting the way the other provisions of APCA operate.4

And where APCA is incorporated into Pennsylvania’s SIP so extensively, I join the

majority’s “assum[ption] that the EPA approved Pennsylvania’s SIP with the

understanding that an independent administrative body had review authority over the

DEP’s initial decisionmaking under the CAA.” Majority Opinion at 31. Indeed, it appears

DEP shared that understanding when it issued the present plan approval. 5

4 For example, a requirement listed in the Plan Approval stated: “The issuance of this plan

approval does not prevent the future adoption by the Department of any rules, regulations
or standards, or the issuance of orders necessary to comply with the requirements of the
Federal Clean Air Act or the Pennsylvania Air Pollution Control Act, or to achieve or
maintain ambient air quality standards.” Plan Approval at 7 (citing 25 Pa. Code
§127.12b(a), (b) for authority). But as mentioned above, such “order[s] or other
administrative actions of [DEP]” are “[a]ppealable actions” subject to review by EHB under
35 P.S. §4010.2. In fact, even the APCA provision detailing DEP’s powers and duties
contemplates EHB review. See id. at §4004(9)(ii) (“Within thirty (30) days after service of
any [DEP] order the person to whom the order is issued or any other person aggrieved
by such order may file with the hearing board an appeal setting forth with particularity the
grounds relied upon.”). Eliminating EHB’s role would disturb the balance of other APCA
provisions implicated in Pennsylvania’s SIP (and the present plan approval).
5 What’s more, I question appellants’ position that for a State to act pursuant to its rights

under the CAA (and therefore fall within the NGA’s savings clause), the State’s action
must be expressly provided for in its SIP. The NGA’s savings clause provides: “[e]xcept
as specifically provided in this chapter, nothing in this chapter affects the rights of States
under . . . the Clean Air Act[.]” 15 U.S.C. §717b(d)(2) (emphasis added). And, the CAA
has a savings clause of its own, specifically preserving certain enforcement rights of the
States. See 42 U.S.C. §7416 (entitled “Retention of State authority,” provides “[e]xcept
as otherwise provided in [various other sections], nothing in this chapter shall preclude or
deny the right of any State or political subdivision thereof to adopt or enforce (1) any
standard or limitation respecting emissions of air pollutants or (2) any requirement
respecting control or abatement of air pollution . . . .”); see also id. at §7401(a) (“The
Congress finds . . . that air pollution prevention (that is, the reduction or elimination,
through any measures, of the amount of pollutants produced or created at the source)
and air pollution control at its source is the primary responsibility of States and local
governments”) (emphasis added); cf. id. at §7604(e) (“Nothing in this [citizen suits]
section shall restrict any right which any person (or class of persons) may have under any
statute or common law to seek enforcement of any emission standard or limitation or to
seek any other relief (including relief against the Administrator or a State agency)”). If the
CAA preserves Pennsylvania’s right to use EHB appeals, I do not see why that right would
not also fall under the NGA’s savings clause, absent a specific provision to the contrary.
(continued…)

[J-13A-2024, J-13B-2024, J-13C-2024 and J-13D-2024] [MO: Wecht, J.] - 6
I add that the majority’s opinion harmonizes with the Third Circuit’s recent

precedential opinion in Transcontinental Gas Pipe Line Co. v. Pa. EHB, 108 F.4th 144

(3d. Cir. 2024) (Transco). In Transco, the Third Circuit affirmed the district court’s denial

of a motion to preliminarily enjoin an administrative appeal to EHB of a DEP permit

decision regarding Transco’s pipeline. See Transco, 108 F.4th at 148. Like appellants

in this case, Transco argued that under Section 717r(d)(1) of the NGA, EHB lacked

jurisdiction to hear a challenge to DEP’s issuance of a permit pursuant to the Clean Water

Act (CWA), which is exempt (like the CAA) from preemption under the NGA’s savings

clause. The Third Circuit held Transco was not entitled to injunctive relief because it could

not demonstrate a reasonable probability of success on the merits, explaining Transco’s

entire case was premised on preemption, but as a matter of law, none of the methods of

preemption applied. See id. at 151.

First, as the majority does here, the Transco court held Section 717r(d)(1) does

not expressly preempt EHB’s review because it applies to “civil actions” only and not to

administrative appeals. See id. at 152-56 (relying on Bordentown v. FERC, 903 F.3d 234,

267 (3d Cir. 2018), for the proposition “civil action” in Section 717r(d)(1) “refers only to

civil cases brought in courts of law or equity and does not refer to hearings or other quasi-

judicial proceedings before administrative agencies[,]” as well as the Commonwealth

Court’s determination in this case that EHB proceedings are administrative proceedings

and not civil actions). Thus, the Third Circuit held Section 717r(d)(1) does not expressly

preclude EHB review.

Next, the Third Circuit held the NGA did not field preempt EHB’s role, explaining

that notwithstanding Schneidewind, the savings provision in NGA Section 717b(d)

Nevertheless, even accepting appellants’ premise that EHB’s role must be included in
Pennsylvania’s SIP for the NGA’s savings clause to apply, for the reasons outlined above,
EHB’s role is so preserved.

[J-13A-2024, J-13B-2024, J-13C-2024 and J-13D-2024] [MO: Wecht, J.] - 7
provided anti-preemption protection for States’ rights under the CAA, the CWA, and the

Coastal Zone Management Act, “[e]xcept as specifically provided in [the NGA.]” Id. at

156-57, quoting 15 U.S.C. §717b(d). The court reasoned the “specifically provided”

language leaves open the possibility of express preemption only, foreclosing any form of

implied preemption with regards to those named statutes. See id. at 157 (referring to this

language as an “anti-implied-preemption clause”). The court reiterated the NGA does not

expressly preempt EHB review, and then rejected Transco’s argument (similar to those

raised by appellants here) that the savings clause protects DEP’s permit decisions only,

not EHB’s review of them. See id. at 157-58. It explained “the preservation of state

regulatory authority under an anti-preemption clause also allows states to ‘us[e]

appropriate tools to exercise that authority.’” Id. at 157, quoting Chamber of Com. v.

Whiting, 563 U.S. 582, 601 (2011) (Roberts, C.J., plurality). The Third Circuit concluded

the EHB Act’s authorization of EHB review of DEP permit decisions under the CWA was

“reasonably in furtherance of the [CWA] powers reserved for states[,]” and that an

administrative appeal was therefore an “appropriate tool to implement the powers

reserved to Pennsylvania under the anti-preemption clause of the [NGA.]” Id. at 157-58.

Likewise here, EHB review reasonably furthers the CAA powers reserved to

Pennsylvania, and EHB’s role is preserved under Pennsylvania’s SIP, if not protected by

the CAA savings provision itself.

Finally, the Transco court held obstacle/conflict preemption did not bar

administrative appeals of DEP’s permit decisions to EHB. See id. at 158-63. It rejected

obstacle preemption based on three arguments appellants also raise (and which the

majority also rejects) in this case: (1) EHB’s decision would be unreviewable under NGA

Section 717r(d)(1) because only DEP issues, conditions, or denies permits pursuant to

[J-13A-2024, J-13B-2024, J-13C-2024 and J-13D-2024] [MO: Wecht, J.] - 8
federal law6; (2) EHB’s decision would be unreviewable based on NGA Section 717n

requiring FERC to prepare an administrative record for “Federal authorizations,”

purportedly limiting the scope of the original-and-exclusive jurisdiction clause in Section

717r(d)(1) to review of “federal authorizations”; and (3) dual-track jurisdiction would

undermine the purpose of the NGA to streamline litigation in this context. See id. at 159-

62. After rejecting those arguments on their merits, the Third Circuit held that even if they

supported a finding of conflict preemption, “the [NGA’s] anti-preemption clause prevents

all forms of implied preemption of state regulation within its scope.” Id. at 162. Since

states retain their power under the CWA, the court concluded that even if EHB review

presented an obstacle, “the anti-implied-preemption clause in §717b(d) would prevent

conflict preemption.” Id. at 163. The majority ably performs a similar merits analysis in

the present case, but I would further endorse the Third Circuit’s reasoning that the NGA’s

savings clause prevents implied obstacle/conflict preemption because EHB review of a

DEP permit decision under the CAA is protected by the “anti-implied-preemption” clause

in NGA Section 717b(d). Id.

Justice Donohue and Justice McCaffery join this concurring opinion.

6 Interestingly, the Third Circuit observed that, because the NGA occupies the field of

interstate natural gas pipeline regulation per Schneidewind, “any state regulatory action
on that subject matter occurs only by virtue of the anti-preemption clause, see 15 U.S.C.
§ 717b(d)[, and t]herefore, any such state regulation is pursuant to federal law.” Transco.,
108 F.4th at 160. Since the court held an EHB appeal is within the scope of the anti-
preemption clause, “an EHB disposition of such an administrative appeal would be within
the ‘pursuant to federal law’ requirement and subject to review through a civil action in
th[e Third Circuit], leaving no obstacle to that purpose of the [NGA].” Id. Indeed, this
portion of the Transco court’s analysis underlines my skepticism that EHB’s role must be
explicitly stated in Pennsylvania’s SIP in order to exist within the overlapping statutory
schemes created by the CAA and the NGA. See supra n. 5.

[J-13A-2024, J-13B-2024, J-13C-2024 and J-13D-2024] [MO: Wecht, J.] - 9

---