# TOWN OF KINGSTON & Another v. HIGH PINES CORPORATION.

> Massachusetts Appeals Court · January 9, 2025

URL: https://www.frixlaw.com/law-library/cases/10777684

## Case

- **Court:** Massachusetts Appeals Court
- **Decided:** January 9, 2025
- **Precedential status:** Unpublished
- **Opinion:** Opinion
- **Cited by:** 0 later opinions in the Frix Law Library

## Citator (automated)

- No negative treatment found by the automated citator. That is not the same as a confirmation that the case is good law; read the citing cases.
- Full citator and citing cases: https://www.frixlaw.com/law-library/cases/10777684

## Opinion text

NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule
23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28,
as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties
and, therefore, may not fully address the facts of the case or the panel's
decisional rationale. Moreover, such decisions are not circulated to the entire
court and, therefore, represent only the views of the panel that decided the case.
A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25,
2008, may be cited for its persuasive value but, because of the limitations noted
above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260
n.4 (2008).

COMMONWEALTH OF MASSACHUSETTS

APPEALS COURT

23-P-1155

TOWN OF KINGSTON & another1

vs.

HIGH PINES CORPORATION.

MEMORANDUM AND ORDER PURSUANT TO RULE 23.0

High Pines Corporation (High Pines) appeals from a summary

judgment granted in the Superior Court to the town of Kingston

and its planning board (together, town) on the town's breach of

contract claims against High Pines.2 We conclude that the

parties' 2014 settlement agreement was an enforceable contract,

and summary judgment was properly granted in favor of the town.

We likewise discern no abuse of discretion or other error in the

1 Planning Board of Kingston.

2High Pines also challenges the judge's denial of its cross
motion for summary judgment on the same claims. As we note
below, however, its argument does not meet the requirements of
Mass. R. A. P. 16 (a) (9) (A), as appearing in 481 Mass. 1628
(2019).
judge's choice of limited specific performance as the remedy for

High Pines's breach. Accordingly, we affirm.

Background. The following facts are not disputed. In

1997, the town granted a special permit to High Pines, allowing

High Pines to develop a subdivision in Kingston. In 2008,

dissatisfied with High Pines's failure to complete the

subdivision's roadways and drainage systems, the town sued High

Pines in the Land Court (Land Court action) seeking injunctive

relief compelling High Pines to complete the infrastructure. In

an attempt to resolve the Land Court action, High Pines and the

town executed a settlement agreement in September 2014. That

agreement provided, in relevant part, the following:

"1. Upon the execution hereof, High Pines, by and through
its qualified engineer shall prepare a comprehensive list
of infrastructure work that is required to be completed in
the . . . subdivision (the 'Work'). Such Work shall relate
to completion of roadway and drainage infrastructure in [a
given phase of the subdivision]. Such list of Work shall
be subject to the peer review and approval by the Planning
Board's designated engineer/inspector who may edit or amend
such list of Work accordingly. The Planning Board's
designed inspector/engineer shall be Webby Engineering or
such other peer review engineer as may be approved by High
Pines, such approval not to be unreasonably withheld. The
Planning Board may utilize such funds from the Security as
may be necessary to fund such peer review. High Pines'
engineer and the Board's engineer shall cooperate with each
other in arriving at a final list of Work which, when
complete, shall describe all of the infrastructure Work
that forms the basis of the parties' dispute.

"2. All of such Work shall be completed by no later than
December 1, 2014, unless a request for extension of such
deadline is approved, in writing, by the Kingston Planning
Board[.]

2
. . . .

"6. If all the Work or any portion of the Work is not
completed by December 1, 2014, the Security [$144,006.52]
shall be available and discharged to the Town to complete
the Work. . . . In the event that, upon December 14, 2014,
the remaining Security is insufficient to complete the
remaining Work, the Town may resume the Suit or bring a
separate action in Contract in a Massachusetts court of
competent jurisdiction to compel the completion of any
remaining Work. . . .

"7. Upon the execution of this Agreement, the parties
shall submit a Joint Motion to Stay the [Land Court action]
so as to permit the Work to be completed in the manner set
forth [in the settlement agreement].

"8. This Agreement is a Massachusetts Contract."

High Pines did not prepare the list of work or take any

other steps required under the terms of the agreement, and the

parties did not submit a joint motion to stay the Land Court

action. On the eve of trial, the town did dismiss the action,

however. Shortly thereafter, the town filed this breach of

contract action in the Superior Court.

On the parties' cross motions for summary judgment, the

judge ruled in favor of the town and against High Pines.

Judgment entered, ordering High Pines to fulfill its obligations

"under Paragraph 1 of [the] Agreement to engage in the process

of defining the subdivision work to be completed thereunder."

This appeal followed.

Discussion. 1. Summary judgment on town's contract claim.

a. Standard of review. "We review a grant of summary judgment

3
de novo," Deutsche Bank Nat'l Trust Co. v. Fitchburg Capital,

LLC, 471 Mass. 248, 252-253 (2015), to determine "whether,

viewing the evidence in the light most favorable to the

nonmoving party, all material facts have been established and

the moving party is entitled to judgment as a matter of law"

(citation omitted). Molina v. State Garden, Inc., 88 Mass. App.

Ct. 173, 177 (2015).

b. Settlement agreement as enforceable contract. The

settlement agreement at issue set forth all material terms of

the parties' agreement, and so was enforceable. See Situation

Mgt. Sys., Inc. v. Malouf, Inc., 430 Mass. 875, 878 (2000) ("to

create an enforceable contract, there must be agreement between

the parties on the material terms of that contract, and the

parties must have a present intention to be bound by that

agreement"). Significantly, the agreement described the nature

of the work to be done (completion of roadway and drainage

infrastructure in a defined phase of the subdivision), the

method by which the details of that work would be decided, the

timing for the work's completion, and how the parties could

address disputes about any costs that exceeded the security High

Pines had already posted. This was not "merely an

[unenforceable] agreement to agree." Hunneman Real Estate Corp.

v. Norwood Realty, Inc., 54 Mass. App. Ct. 416, 419 (2002).

4
High Pines contends that the agreement was unenforceable

because it "has no provision to determine the rights or

obligations of the parties if the engineers cannot agree on the

work." That the agreement did not detail how potential good-

faith disagreements between the parties' experts should be

resolved does not alter our conclusion that the agreement was

enforceable, however. See Situation Mgt. Sys., Inc., 430 Mass.

at 878 ("It is not required that all terms of the agreement be

precisely specified, and the presence of undefined or

unspecified terms will not necessarily preclude the formation of

a binding contract"). Contrast Bell v. B.F. Goodrich Co., 359

Mass. 763, 763 (1971) (no contract where defendant agreed to

negotiate "until an agreement was consummated or until both

parties mutually agreed to terminate their negotiations").

We are likewise unpersuaded that High Pines's completion of

the list of work described in the first paragraph of the

agreement was a condition precedent to a contract, rather than a

contractual provision. The agreement does not include the

"'[e]mphatic words' . . . generally considered necessary to

create a condition precedent that will limit or forfeit rights

under an agreement," Massachusetts Mun. Wholesale Elec. Co. v.

Danvers, 411 Mass. 39, 46 (1991), quoting Commerce Ins. Co. v.

Koch, 25 Mass. App. Ct. 383, 385 (1988), and no such intention

is otherwise "clearly manifested in the contract as a whole."

5
Massachusetts Mun. Wholesale Elec. Co., supra. Indeed, the

parties themselves characterized the settlement as "a . . .

[c]ontract." See Hunneman Real Estate Corp., 54 Mass. App. Ct.

at 421 (parties' stated intention to be bound is significant to

determination of contract's enforceability). Even viewing the

facts in the light most favorable to High Pines, we discern no

genuine issue of material fact that would suggest the agreement

is less than it says.

c. Judge's remedy of limited specific performance. High

Pines challenges the judge's order for specific performance of

the contract insofar as it orders specific performance of the

"work" under the settlement agreement. The judge's order,

however, was narrowly tailored, and only ordered High Pines "to

engage in the process of defining the subdivision work to be

completed [under paragraph 1 of the agreement]." Because we

conclude that the order for specific performance does not extend

to the "work," we do not address further High Pines's challenge

to the relief specified in the judgment.3

3 Nothing in our decision should be read to suggest that
High Pines is excused from its other contract obligations,
however. So far as the record reflects, the settlement
agreement remains an enforceable contract. There is no dispute
that High Pines failed to take any steps to complete its
obligations under the settlement agreement; thus, its breach was
material. See Duff v. McKay, 89 Mass. App. Ct. 538, 547 (2016)
("material breach" is "a breach of an essential and inducing
feature of the contract" [quotation omitted]). That material

6
2. Waiver argument. High Pines argues that the language

of the agreement (particularly, paragraph 6) can be interpreted

in more than one way and, as a result, there exists a genuine

issue of material fact whether the town waived its right to

bring the instant action in the Superior Court. Specifically,

High Pines contends that the town waived this right when it

continued to litigate the Land Court action after the settlement

agreement was signed. The question in this case concerns the

interpretation of a contractual provision, however, and is thus

one of law. See James B. Nutter & Co. v. Estate of Murphy, 478

Mass. 664, 667 (2018). Reviewing the relevant language de novo,

see id., we are not persuaded that the settlement agreement

provided for a waiver of rights in the circumstances here. See

David v. Kelly, 100 Mass. App. Ct. 443, 446 (2021), quoting

Balles v. Babcock Power Inc., 476 Mass. 565, 571 (2017) ("[W]hen

the language of a contract is clear, it alone determines the

contract's meaning").

Paragraph 6 of the agreement provided that, in the event

that the outstanding work on the subdivision infrastructure was

not completed by December 1, 2014, and "the remaining Security

breach excused the town from performance "as [a] matter of law,"
Dalrymple v. Winthrop, 97 Mass. App. Ct. 547, 554 (2020),
quoting Hastings Assocs., Inc. v. Local 369 Bldg. Fund, Inc., 42
Mass. App. Ct. 162, 171 (1997), but did not otherwise affect the
contract's enforceability.

7
[was] insufficient to complete the remaining Work, the Town

[could] resume the [Land Court action] or bring a separate

action in Contract in a Massachusetts court of competent

jurisdiction to compel the completion of any remaining Work"

(emphasis added). The use of the word "or" in this context

serves at least two purposes: to provide the town flexibility

if enforcement of the contract was necessary, and to confirm

that, if enforcement was required, High Pines would not have to

defend on more than one front at a time. It is not, however,

"explicit language" indicating a waiver, see David, 100 Mass.

App. Ct. at 447, and it otherwise falls far short of

demonstrating the town's "intentional relinquishment" of its

right to pursue the instant action after it dismissed its Land

Court action. Psychemedics Corp. v. Boston, 486 Mass. 724, 745

(2021), quoting Dynamic Mach. Works, Inc. v. Machine & Elec.

Consultants, Inc., 444 Mass. 768, 771 (2005). Cf. Federal

Deposit Ins. Corp. v. Hill, 13 Mass. App. Ct. 514, 518 (1982)

(where note stated bank "had no duty as to the collection or

protection of collateral held [to secure the note] or any income

thereto nor as to the preservation of any rights pertaining

thereto beyond the safe custody thereof," it included "a clear

and unequivocal waiver by the defendant of any right he may have

had to be discharged . . . by the bank's impairment of

collateral").

8
3. Motion to strike. The judge in this case denied High

Pines's motion to strike the affidavit of Kingston's assistant

town administrator, Gloria Mitchell, and the two Stantec

engineering reports that were attached to it, concluding that

they were business records. We need not reach the correctness

of that determination because, whatever their significance to a

determination of the scope and cost of the remaining

infrastructure work, those documents do not bear on either the

question whether High Pines breached the contract by failing to

perform any part of it, or on the propriety of the relief that

the judge ordered. Accordingly, any abuse of discretion or

other error in the judge's denial of High Pines's motion to

strike portions of the affidavit and the attached reports did

not "injuriously affect[] the substantial rights of [High

Pines]," and so does not require reversal (citation omitted).

David, 100 Mass. App. Ct. at 451.

4. High Pines's motion for summary judgment. High Pines's

challenge to the judge's denial of its cross motion for summary

judgment does not rise to the level of appellate argument. See

9
Mass. R. A. P. 16 (a) (9) (A), as appearing in 481 Mass. 1628

(2019). We do not address it further.

Conclusion. The judgment dated December 22, 2022, is

affirmed.

So ordered.

By the Court (Henry, Hand &
Brennan, JJ.4),

Clerk

Entered: January 9, 2025.

4 The panelists are listed in order of seniority.

10

---

Source: Frix Law Library, https://www.frixlaw.com/law-library/cases/10777684. Public record. Not legal advice.
