# Marine Steel Transport Line, LLCet al v. Eastern Metal Recycling, LLC

> District Court, E.D. New York · July 31, 2024

URL: https://www.frixlaw.com/law-library/cases/10659100

## Case

- **Court:** District Court, E.D. New York
- **Decided:** July 31, 2024
- **Opinion:** 100trialcourt
- **Cited by:** 0 later opinions in the Frix Law Library

## Citator (automated)

- No negative treatment found by the automated citator. That is not the same as a confirmation that the case is good law; read the citing cases.
- Full citator and citing cases: https://www.frixlaw.com/law-library/cases/10659100

## How later opinions describe it (automated extraction)

- applying the rule to contractual liability
- explaining that damages are reduced by “any value of the wreck as salvage” and increased by “interest on the net amount from the date of the collision”
- noting that fair market value can be shown by “a capitalization of earning capacity”

## Opinion text

UNITED STATES DISTRICT COURT
EASTERN DISTRICT OF NEW YORK
------------------------------------------------x
MARINE STEEL TRANSPORT LINE,
LLC, THORNTON TRANSPORTATION
& TOWING, LLC, MEMORANDUM AND ORDER
Case No. 19-CV-2275-FB-SJB
Plaintiffs,

-against-

EASTERN METAL RECYCLING,
LLC, CAMDEN IRON & METAL,
INC., T&T SCRAP, LLC, SAL’S
METAL CORP.,

Defendants.
------------------------------------------------x

Appearances:
For the Plaintiffs: For Defendants Eastern Metal
DERRICK STORMS Recycling, LLC, and Camden Iron &
Solomos & Storms Metal, Inc.:
33-08 Broadway FRANK P. DEGUILIO
Astoria, New York 11106 CHARLES P. NEELY
Palmer Biezup & Henderson, LLP
140 Broadway, 46th Floor
New York, New York 10005

BLOCK, Senior District Judge:
In this admiralty action, the plaintiffs, Marine Steel Transport Line, LLC, and
Thornton Transportation & Towing, LLC (collectively, “Marine Steel”), allege that
their barges were damaged by the loading and unloading of scrap metal during a
charter. Their claims against two defendants—T&T Scrap, LLC (“T&T”), and
Sal’s Metal Corp. (“Sal’s”), were settled; the claims against the remaining
defendants—Eastern Metal Recycling, LLC, and Camden Iron & Metal, Inc.
(collectively, “EMR”)—proceeded to a bench trial, which was held on January 9,

January 10, February 26, February 28, and April 2, 2024. The following represent
the Court’s findings of fact and conclusions of law pursuant to Federal Rule of Civil
Procedure 52.

BACKGROUND
Formed in 2006, Marine Steel began as a marine towing business.
Beginning in 2011, it expanded its operations to include barge transportation
services. To that end, it acquired the three barges at issue in this case: Barge

2000, a 63-year-old vessel acquired in 2011 for $105,000; Marine Steel 1, a 27-
year-old vessel acquired in 2015 for $54,000; and Marine Steel 2, a 27-year-old
vessel acquired in 2015 for $54,000.

EMR, a UK-based company, purchases scrap metal from third parties,
including T&T and Sal’s. Because U.S law requires goods to be transported
between domestic ports only by U.S.-owned vessels, see Merchant Marine Act of
1920, § 27, Pub. L 66-261, 41 Stat. 988 (1920), EMR required an American

company to transport the scrap to its facility at Port Newark, New Jersey. Thus,
in December 2011, EMR engaged the services of Marine Steel. Marine Steel
agreed to make the three barges available for EMR’s exclusive use and to provide

2
a tugboat captained by one of its employees. Over the next several years, the
tugboat would tow the barges to T&T and Sal’s scrapyards, where employees of

those companies would load the barges with scrap metal. Marine Steel’s tugboat
would then tow the barges to EMR’s facility, where EMR employees would
offload the scrap.

The parties’ agreement was not reduced to writing. However, their court of
dealings reflects that Marine Steel would, from time to time, bill EMR for damages
to the barges during loading and unloading operations, and that EMR would pay
those bills. In addition, with respect to Marine Steel 2, it agreed in writing to pay

for “debris removal and steel repairs other than those considered to be normal wear
and tear.” Am. Compl., Ex. 5. Based on this course of dealing, there is no
serious dispute that EMR assumed a contractual duty to pay for repairs to the

barges beyond normal wear and tear.
On September 25, 2018, EMR informed Marine Steel that it was terminating
their at-will arrangement. Later surveys of the barges (known as “off-hire”
surveys in the industry) revealed extensive damages, mostly caused by employees

of T&T and Sal’s using a grapple to move the barges during their loading
operations. Quotes from local shipyards estimated that it would cost around
$150,000 to return the barges to “serviceable” condition, or around $300,000 to

3
return them to “as built” condition. EMR refused to pay for any repairs.
Lacking the funds to do so itself, Marine Steel sold the barges for scrap and ceased

operations. This lawsuit followed.
CONCLUSIONS OF LAW
Normally, the Court would begin by making the findings necessary to

resolve any disputed issues of fact. In this case, however, there are several
disputed issues of law that it must address first.
A. Measure of Damages
The parties’ principal dispute concerns the proper measure of Marine Steel’s

damages. As the Court has previously noted, “[t]he concept that a contractual
obligation to repair does not extend beyond the fair market value of the repaired
vessel is well-established in maritime law.” Marine Steel Transp. Line, LLC v.

Eastern Metal Recycling, LLC, 2023 WL 3603489, at *3 (E.D.N.Y. May 23, 2023)
(citing Asphalt Int’l, Inc. v. Enterprise Shipping Corp., 514 F. Supp. 1111, 1113
(S.D.N.Y. 1981), for the proposition that “when a ship is a constructive total loss,
one would not expect there to be a persisting duty to repair, unless the charter

contained an explicit agreement to the contrary. This rule of maritime law
reflects the longstanding rule generally applicable in cases of property damage,
regardless of whether the action sounds in tort or contract:

4
The damages sustained by an automobile in a collision may be
established by showing the reasonable cost of the repairs necessary to
restore it to its former condition, although the general rule is that the
measure of damages to personal property is the difference between its
market value immediately before and immediately after the injury.
This rule is subject to the limitation, first, that the cost of repairs must
be less than the diminution in market value due to the injury, and,
secondly, that the repairs must never exceed the value of the
automobile itself as it was before the injury. The plaintiff should not
benefit by the loss. Where the automobile is totally destroyed, the
measure of damages is its reasonable market value immediately
before destruction. There can be no recovery beyond such value for
mere repairs.

Gass v. Agate Ice Cream, 264 N.Y. 141, 143-44 (1934) (citations omitted); see
also Kanematsu-Gosho Ltd. v. M/T Messiniaki Aigli, 814 F.2d 115, 118 (2d Cir.
1987) (“Generally, the measure of damages is the difference between the fair
market value of the goods at their destination in the condition in which they should
have arrived and the fair market value in the condition in which they actually did
arrive.”). As the Second Circuit has noted, these rules are “equally applicable to
vessels injured through collision on maritime waters.” O’Brien Bros. v. The
Helen B. Moran, 160 F.2d 502, 505 (2d Cir. 1947).
One might reasonably question—as the Court did during the trial—whether
a plaintiff who receives the amount of money necessary to restore his property to
its previous condition truly “benefit[s] by the loss” if the diminution in its fair
market value is less than the cost of obtaining a comparable replacement. But the

5
law in this regard is too settled for the Court to revisit its previous holding. In
any event, the parties have essentially accepted that holding, although—as will be

seen—they sharply dispute the evidence regarding the barges’ fair market value
prior to the damage. In that regard, it is important to note that the vessel owner
“establishe[s] its prima facie case by proof of the extent of the damage and the cost

of repairs.” The Ruthie M., 4 F. Supp. 317, 318 (E.D.N.Y. 1933). The burden
then shifts to the defendant “to show that such damages exceeded the fair market
value of the . . . barges.” Id.
B. Duty to Mitigate Damages

In connection with the parties’ motions for summary judgment, EMR argued
that Marine Steel had a duty to protect its barges from damage because it had
knowledge that T&T and Sal’s were improperly using a grapple to move them.

As the Court explained, that duty arises “for claims of negligence, not breach of
contract.” Marine Steel, 2023 WL 3603489, at *2. It then acknowledged that
“[t]here are similar duties in contract cases, such as the injured party’s ‘obligation
to make reasonable efforts to mitigate its damages.’” Id. (quoting APL Co. PTE

v. Blue Water Shipping U.S. Inc., 592 F.3d 108, 111 (2d Cir. 2010)). But the
injured party need not take steps to mitigate damages “where the breaching party
had the same opportunity to prevent damages.” Travelers Indem. Co. v. Maho

6
Mach. Tool Corp., 952 F.2d 26, 31 (2d Cir. 1991). Moreover, “if plaintiff takes
such mitigating action within the range of reason, the breaching party remains

liable if such reasonable attempts at mitigation fail.” APL Co., 592 F.3d at 111
(internal quotation marks and alteration omitted).
C. Consequential Damages

As the Court has previously explained, consequential damages are “not
recoverable in an action to recover damages for breach of contract in the absence
of the plaintiff's showing that such damages were foreseeable and within the
contemplation of the parties at the time the contract was made.” Marine Steel,

2023 WL 3603489, at *1.
D. Apportionment of Damages
EMR argues that the Supreme Court’s decision in McDermott, Inc. v.

AmClyde, 511 U.S. 202 (1994), requires the Court to allocate fault among all the
defendants, including the settling defendants and then apportion Marine Steel’s
total damages according to that allocation. The Court disagrees.
AmClyde holds that, in an admiralty case involving multiple defendants,

some of whom settle with the plaintiff before trial, “the liability of the nonsettling
defendants should be calculated with reference to the jury’s allocation of
proportionate responsibility.” 511 U.S. at 204. That approach is essentially a

7
specific application of the general rule of contribution in tort cases. Since
“[c]ontribution rests upon a finding of concurrent fault,” it does not apply in cases

of strict liability. Cooper Stevedoring Co. v. Fritz Kopke, Inc., 417 U.S. 106, 115
(1974). “Contract liability is strict liability.” CITGO Asphalt Refining Co. v.
Frescati Shipping Co., 589 U.S. 348, 358 (2020) (quoting Restatement (Second) of

Contracts); accord Board of Educ. of Hudson City Sch. Dist. v. Sargent, Webster,
Crenshaw & Folley, 71 N.Y.2d 21, 29 (1987) (“Nor are we persuaded that we
should create a common-law right of contribution in contract actions.”).
AmClyde does not change that result. The non-settling defendant discussed

in that case had been found 38% liable in tort. While EMR points out that
another non-settling defendant had been sued based on a contract, the Supreme
Court explicitly “ignore[d]” that defendant because the court of appeals had held

that the contract rendered it immune from damages and “[n]o party appeal[ed] that
holding.” 511 U.S. at 210 n.11 (citing McDermott, Inc. v. Clyde Iron, 979 F.2d
1068, 1075-76 (5th Cir. 1992)).
Thus, the Court rejects the application of the “proportionate share approach”

in this contract case. Instead, it will apply the “one satisfaction” rule that
settlements received for the same injury “reduce a plaintiff's recovery from the
nonsettling defendant to prevent the plaintiff from recovering twice from the same

8
assessment of liability.” Chisholm v. UHP Projects, Inc., 205 F.3d 731, 737 (4th
Cir. 2000); see also Mathias v. Jacobs, 238 F. Supp. 2d 556, 572 (S.D.N.Y. 2002)

(applying the rule to contractual liability).
E. Prejudgment Interest
The Second Circuit has instructed that prejudgment interest be granted in

admiralty cases “in the absence of exceptional circumstances.” Mitsui & Co. v.
Am. Export Lines, Inc., 636 F.2d 807,823 (2d Cir. 1981). The rate to be used
rests “firmly within the sound discretion of the of the trial court,” but “should be
measured by interest on short-term, risk-free obligations.” Ingersoll Milling

Mach. Co. v. M/V Bodena, 829 F.2d 293, 311 (2d Cir. 1987) (citation, internal
quotation marks, and alteration omitted).
Having established the relevant legal rules, the Court now turns to resolving

the disputed issues of fact.
FINDINGS OF FACT
The breach of a valid contract is not in serious dispute. For the sake of
completeness, the Court finds that EMR undertook a contractual duty to pay for

any repairs, beyond normal wear and tear, necessitated by its use of the barges, and
that it breached that duty upon the termination of its hire.
EMR preliminarily argues that Marine Steel failed to prove that any

9
damages occurred during EMR’s hire of the three barges. This argument is based
on the type of surveys conducted prior to EMR’s hire. As explained by the trial

testimony of Marine Steel’s expert, Richard Meyerrose, an “on-hire” survey
extensively details the condition of and damage to a vessel at a particular point in
time; he conducted such surveys after EMR terminated its relationship with EMR

and used them to form the bases of his opinions regarding the nature and extent of
the damage to the barges. By contrast, the only surveys predating EMR’s hire
were “condition and valuation,” or “off-hire” surveys, which describes the
condition of a vessel in more general terms. EMR posits that the lack of pre-

damage “on-hire” surveys raises the possibility that some or all of the damage
predated the hire.
The Court agrees that inadequate descriptions of a vessel’s pre-accident

condition can support a factual finding of no causation. See, e.g., B.W. King, Inc.
v. Consol. Iron & Metal Co., 310 F. Supp. 471, 473-75 (S.D.N.Y. 1970). But the
Court declines to make that finding here. It credits the ample testimony that
almost all of the damage observed in the on-hire surveys was caused by improper

use of a grapple to move the barges, as well as Meyerrose’s testimony that the
damage was so extensive and obvious that it would have been included in the pre-
accident off-hire surveys if it had existed at the time those surveys were conducted.

10
Thus, the Court finds that the damages sought by Marine Steel were caused during
EMR’s hire.1

The Court now turns to the principal dispute in this case: the amount of
Marine Steel’s damages. Marine Steel’s valuation expert, Michael Collyer,
opined that Barge 2000 had a fair market value of approximately $170,000, while

Marine Steel 1 and Marine Steel 2 each had a fair market value of $195,000. By
contrast, EMR’s expert, Kenneth Hendrix, opined that Barge 2000 had a fair
market value of approximately $68,000, while Marine Steel 1 and Marine Steel 2
each had a fair market value of $58,000.

Neither expert’s opinion satisfies the Court. This is not a criticism of their
expertise. Indeed, both candidly acknowledged that assessing the barges’ fair
market value was fraught with difficulty because there is virtually no market—let

alone a robust market—for barges of comparable age and condition.
Nevertheless, the Court must reject both of their methodologies. Collyer
estimated fair market value based on the few listings he could find for barges of a
similar “vintage.” Tr. at 231. The Court has previously explained why it finds

1EMR briefly argues that Marine Steel cannot recover for damages to Barge
2000 because it was sold to Gem Line, LLC, in 2013. Marine Steel’s principal,
Gerard Thornton, testified that Gem Line was an “affiliated” company, Tr. at 94,
and it is undisputed that Marine Steel continued to treat the barge as its own until
selling it after EMR’s hire ended. The Court infers from this that, whatever the
legal niceties, Marine Steel was Barge 2000’s beneficial owner.

11
that approach unconvincing. See Garpo Marine Servs., 2017 WL 4157284, at *4
(“[The expert’s] valuation was based on the advertised ‘asking’ price of vessels

selected from random journals and a database . . . ; he never sought to determine if
the vessels listed were actually sold for the prices sought.”).2
Hendricks, meanwhile, based his estimates on the barges’ scrap value. The

relevant metric is the fair market value “at the time of loss,” or more precisely, just
prior to the loss. See id. He did so based on the premise that all three barges
were past their useful life and, therefore, would fetch the same price with or
without damage. But he also acknowledged that repairs could extend their

lifespan. That is apparently how Marine Steel operated; the Court finds both that
it would have made the repairs had it had the resources to do so, and that it would
have been economically reasonable to do so. Cf. The Helen B. Moran, 160 F.2d

at 505 (noting that fair market value can be shown by “a capitalization of earning
capacity”).
Because of the burden of proof, see The Ruthie M., 4 F. Supp. at 318, the
impact of the lack of sufficient evidence of the barges’ fair market value falls on

EMR. Accordingly, the Court falls back on repair cost as a measure of damages.

2Collyer also considered the significant cost of transporting a barge to New
York. But Marine Steel is entitled only to the barge’s fair market value, not the
cost of actually replacing it.

12
Here, too, the evidence is imperfect. Marine Steel proffered actual repair
quotes from shipyards as well as Collyer’s estimates. The Court finds the quotes

more persuasive and rejects the estimates as speculative.
EMR argues that Marine Steel is entitled only to the cost of repairing the
ship to a serviceable condition. That may be the rule in tort cases, see Zeller

Marine Corp. v. Nessa Corp., 166 F.2d 32, 34 (2d Cir. 1948), but Marine Steel
contracted for any repairs beyond normal wear and tear. It is entitled to the
benefit of that bargain. Cottle v. Gallup, 432 F.3d 43 (1st Cir. 1970), cited by
EMR, is not to the contrary and, indeed, held that the plaintiff was entitled to a new

engine “in perfect, warranted condition” because the damages could not be
repaired to its former status.” Id. at 44. Accordingly, the Court rejects EMR’s
argument that Marine Steel seeks the cost of repairing the barges to “as built”

condition and repeats its previous finding that the damages sought be repaired were
all caused during EMR’s hire.
In sum, the Court finds that the quotes provided by Marine Steel accurately
reflect the cost of restoring the barges to their condition immediately prior to

EMR’s hire. Marine Steel offered two quotes for each barge and choosing
between them is necessarily arbitrary; to give EMR the benefit of the doubt, the
Court will use the lower of the two quotes provided for each barge. Accordingly,

13
the Court finds that the cost of repairing Barge 2000 is $99,508, that the cost of
repairing Marine Steel 1 is $67,655, and that the cost of repairing Marine Steel 2 is

$132,000, for total damages of $299,163.
EMR argues that Marine Steel failed to mitigate those damages because it
was aware that T&T and Sal’s were using a grapple to move the barges. The

Court finds that it would have been unreasonable for Marine Steel to terminate the
hire and potentially incur legal liability to avoid further use of the grapple.
Moreover, the Court finds that Marine Steel reasonably informed EMR of T&T
and Sal’s actions and further, that EMR, once so informed, was in a better position

to avoid the damage because T&T and Sal’s were working on its behalf.
On the other hand, Marine Steel’s damages must be reduced by the amounts
it recovered by selling the barges. See The Helen B. Moran, 160 F.2d at 506

(explaining that damages are reduced by “any value of the wreck as salvage” and
increased by “interest on the net amount from the date of the collision”). Based
on the undisputed facts, the Court finds those amounts to be $76,000 for Barge
2000, $23,132 for Marine Steel 1, and $20,529 for Marine Steel 2, for a total of

$119,661.
With respect to consequential damages, EMR’s explicit promise to repair the
barges does not refer to Marine Steel’s lost profits and nothing else about the

14
arrangement satisfies the Court that such damages were within the parties’
contemplation. Accordingly, the Court does not include lost profits in its award

of damages.
Moreover, the award must be reduced by the $53,500 received from T&T
and Sal’s. Based on the undisputed fact that those amounts secured the dismissal

of the claims against those defendants, the Court finds that they partially
compensated Marine Steel for the same damages sought from EMR. The Court
specifically rejects Marine Steel’s argument that the settlements were de minimis
and intended to cover only attorneys’ fees.

Finally, the Court finds that a one-year Treasury bill issued on November
19, 2018—the date on which Marine Steel sent EMR an invoice for repair costs—
supplies an appropriate prejudgment interest rate 2.66% per year.

CONCLUSION
Based upon the foregoing findings of fact and conclusions of law, the Clerk
is directed to enter judgment in favor of Marine Steel and against EMR in the
principal amount of $126,002, plus $19,063.20 ($126,002 x 0.0266 x 5.6877 years)

in prejudgment interest, for a total of $145,065.20. Post-judgment interest shall
accrue at the statutory rate until the judgment is paid in full. Marine Steel’s
request for attorneys’ fees is denied without prejudice to filing a motion for such

15
fees within 14 days of the entry of judgment. See Fed. R. Civ. P. 54(d)(2). In
addition to demonstrating that EMR’s counterclaim was frivolous, the motion must

provide a legal basis for Marine Steel’s claim that it is entitled to attorneys’ fees
for defending a frivolous counterclaim3 and supporting documentation regarding
the amount and reasonableness of the fees incurred.

SO ORDERED.

_/S/ Frederic Block__________
FREDERIC BLOCK
Senior United States District Judge
Brooklyn, New York
July 31, 2024

3The sole case cited in Marine Steel’s post-trial submissions stands only for
the proposition that 28 U.S.C. § 1988 presumptively entitles prevailing plaintiffs to
attorneys’ fees in civil rights cases. See Raishevich v. Foster, 247 F.3d 337, 344
(2d Cir. 2001).