# Board of Mgrs. of 87-89 Leonard St. Condominium v. Leonard St. Owner

> New York Supreme Court, New York County · October 15, 2024 · 2024 NY Slip Op 33659(U)

URL: https://www.frixlaw.com/law-library/cases/10612405

## Case

- **Court:** New York Supreme Court, New York County
- **Decided:** October 15, 2024
- **Citations:** 2024 NY Slip Op 33659(U)
- **Precedential status:** Unpublished
- **Opinion:** Opinion by Margaret A. Chan
- **Cited by:** 0 later opinions in the Frix Law Library

## Citator (automated)

- No negative treatment found by the automated citator. That is not the same as a confirmation that the case is good law; read the citing cases.
- Full citator and citing cases: https://www.frixlaw.com/law-library/cases/10612405

## Opinion text

Board of Mgrs. of 87-89 Leonard St. Condominium v
Leonard St. Owner
2024 NY Slip Op 33659(U)
October 15, 2024
Supreme Court, New York County
Docket Number: Index No. 151532/2019
Judge: Margaret A. Chan
Cases posted with a "30000" identifier, i.e., 2013 NY Slip
Op 30001(U), are republished from various New York
State and local government sources, including the New
York State Unified Court System's eCourts Service.
This opinion is uncorrected and not selected for official
publication.
FILED: NEW YORK COUNTY CLERK 10/16/2024 04:26 PM INDEX NO. 151532/2019
NYSCEF DOC. NO. 275 RECEIVED NYSCEF: 10/16/2024

SUPREME COURT OF THE STATE OF NEW YORK
COUNTY OF NEW YORK: COMMERCIAL DIVISION PART 49M

-------------------X
BOARD OF MANAGERS OF 87-89 LEONARD STREET INDEX NO. 151532/2019
CONDOMINIUM, SUING ON BEHALF OF ITS UNIT
OWNERS,
MOTION DATE 10/30/2023
Plaintiff,
MOTION SEQ. NO. MS 003
-v-
LEONARD STREET OWNER, LLC,MARC RAVNER, DECISION+ ORDER ON
BENJAMIN SHAOUL, and GRASSOMENZIUSO MOTION
ARCHITECTS,

Defendants.

-------------------X
LEONARD STREET OWNER, LLC, MARC RAVNER, and Third-Party
BENJAMIN SHAOUL Index No. 595968/2023

Plaintiffs,

-against-

GRASSO-MENZIUSO ARCHITECTS, P.C., JACK GREEN
ASSOCIATES, LMW ENGINEERING, GROUP, LLC, CANIDO
BASONAS CONSTRUCTION, CORP., BAY RESTORATION
CORP., DONATO, INC., FNA ASSOCIATES, INC., FRANK
SETA & ASSOCIATES, LLC,, POLAR AIR CONDITIONING,
INC.,, CAPITOL FIRE SPRINKLER, CO. INC., SERVICE ALL
WINDOW & DOOR CORP., KD ONE CONSTRUCTION, INC.,
DUFFYS FLOOR SERVICES INC., TWIN PEAKS, INC., DAX
STUDIO ARCHITECTURE, PLLC, GMI MECHANICAL, INC.,
J.D. WILSON CONSTRUCTION CORPORATION, POURED
FLOORS OF NEW YORK & NEW JERSEY, NY WIRING, and
THE IRON SHOP, LLC

Defendants.
-------------------X

HON. MARGARET A. CHAN:

The following e-filed documents, listed by NYSCEF document number (Motion 003) 105, 106, 107, 108,
119,176,177,178,179,180,181,182,183,184,185,186,187,188,189,190,191,192
were read on this motion to/for DISMISS

The underlying dispute relates to the conversion of a 150-year-old cast-iron
building into what was promised to be a beautifully restored and one·of·a·kind
seven-unit condominium that was not as beautiful as promised (NYSCEF # 15,
151532/2019 BOARD OF MANAGERS OF 87-89 LEONARD STREET CONDOMINIUM, SUING ON Page 1 of 10
BEHALF OF ITS UNIT OWNERS vs. LEONARD STREET OWNER, LLC ET AL
Motion No. 003

[* 1] 1 of 10
FILED: NEW YORK COUNTY CLERK 10/16/2024 04:26 PM INDEX NO. 151532/2019
NYSCEF DOC. NO. 275 RECEIVED NYSCEF: 10/16/2024

Complaint ,r 1; NYSCEF # 63, Third-Party Complaint ,r,r 29, 57, 60, 64, 67, 70, 74).
Plaintiff Board of Managers of 87-89 Leonard Street Condominium ("plaintiff') now
sues defendants/third-party plaintiffs Leonard Street Owner, LLC, Marc Ravner,
and Benjamin Shaoul (together "Sponsors"), as well as defendant/third-party
defendant Grasso·Menziuso Architects, P.C. (GMA), for failure to construct the
condominium as promised, resulting in a multitude of defects discovered upon
moving in (NYSCEF # 15 ,r 2). Plaintiff alleges that the building suffered from
material defects, including defects in the mechanical equipment, plumbing
equipment, and electrical system (id ,r,r 51-106). The building also exhibited poor
workmanship, shoddy construction practices, and failed to abide by the Offering
Plan and building codes (id ,r 35). Plaintiff brings claims of fraudulent inducement
against both GMA and the Sponsors; and against only the Sponsors claims of breach
of contract, breach of fiduciary.duty, "constructive fraudulent conveyances while
insolvent," and "constructive fraudulent conveyances causing unreasonably small
capitaf' (NYSCEF # 15).

Sponsors subsequently brought a third ·party action against GMA and other
construction companies for damages Sponsors may incur from the underlying first·
party action (NYSCEF # 63, Third-Party Complaint ,r,r 57, 60, 64, 67, 70, 74). Most
relevant here, the Sponsors allege that GMA's carelessness and recklessness
created the defects alleged in the first-party complaint, and as such GMA should be
responsible for any resulting liability (NYSCEF # 63 ,r 75).

Background
The following facts are drawn from GMA's Motion to Dismiss, the
accompanying exhibits, the Third· Party complaint, and the underlying First· Party
complaint.

How It Started: The Proposal Architect's Certifications. Insurance Procurement
Obligation. and IndemnitvAgreement
GMA's involvement in this project started on February 28, 2014, when they
entered into a proposal agreement ("the Proposal") with non-party MB Leonard St,
LLC (NYSCEF # 107, Menziuso Aff. & Exhibits, at *68-*71 [2/28/2014 Proposal
Letter from Menziuso to Shaoul]).1 According to the Proposal, GMA was to provide
architectural working drawings for the conversion of a new residential building,
.based on designs approved by the Sponsors and plans approved by the Department
of Buildings in 2012 (id at *68). GMA was also responsible for visiting the job site,
verifying field conditions for the preparation of drawings, filing and acquiring

1 The court frowns on parties filing combined affidavits/affirmations and exhibits as a single
document on NYSCEF. Parties are advised to file the affirmations/affidavits and each individual
exhibit separately.
151532/2019 BOARD OF MANAGERS OF 87-89 LEONARD STREET CONDOMINIUM, SUING ON Page 2 of 10
BEHALF OF ITS UNIT OWNERS vs. LEONARD STREET OWNER, LLC ET AL
Motion No. 003

[* 2] 2 of 10
FILED: NEW YORK COUNTY CLERK 10/16/2024 04:26 PM INDEX NO. 151532/2019
NYSCEF DOC. NO. 275 RECEIVED NYSCEF: 10/16/2024

approvals from the Department of Buildings and assisting with the acquisition of
the Certificate of Occupancy (id).

On April 14, 2014, GMA issued an architect's certification that described the
building if built in accordance with the plans and report prepared on April 9, 2014
(NYSCEF # 187, GMA's Architect Certifications, at *3-*4 [4/14/2014 Certification]).
The report and architect's certification were intended to be incorporated into the
offering plan and given to the prospective purchasers, with the idea that they would
rely on it for the physical condition of the property upon completion (id at *3). The
certification guaranteed that GMA, among other things, did not omit any material
fact, and the report did not contain any untrue statements of material fact, fraud,
deception, concealment, or suppression (id at *3-*4).

A month later, on May 27, 2014, GMA and non·party MB Leonard St, LLC
entered into an Insurance Rider Agreement ("Rider" or "Insurance Rider")
(NYSCEF # 183, Insurance Rider). Pursuant to the Rider, GMA agreed to indemnify
MB Leonard St, LLC, their officers and agents "from and against any claims ... that
may be made: (i) by anyone for injuries to persons or damage to property ... and, (ii)
by persons furnished by" GMA or its "subcontractors under the Workers
Compensation or similar acts." (id at§ 2 [b]).

A year later on, May 29, 2015, GMA then issued another architect's
certification after the building plans and report were updated on February 2, 2015,
and May 27, 2015 (NYSCEF # 187 at *6·*7 [5/29/2015 Certification]). This new
architect's certification, like the past one, was also intended to be incorporated into
the offering plan and given to prospective purchasers for the same purpose and with
the same disclaimers (id).

Then on February 4, 2016, GMA signed an Indemnity Agreement with
defendant/third-party plaintiff Marc Ravner, pursuant to which Ravner agreed to
"indemnify, defend, and hold harmless [GMA] from and against any liability,
obligation .. .loss, claim, cause of action, damage ... that GMA may sustain or incur in
connection with the Permanent Certificate of Occupancy Certification" (NYSCEF #
107 at *73 [Indemnity Agreement ,-r,-r 1, 3]).

Certificate ofOccupancvand Defects Leading to the Complaint

On February 14, 2018, a Final Certificate of Occupancy was issued by the
Department of Buildings (DOB) for the DOB Job Number 120751677 ("Job #1"),
assigned to the conversion project (id at *75 [Job #1 Certificate of Occupancy]).
Plaintiff alleges that by May 2018, the Sponsors had sold all the condominium units
in the building (NYSCEF # 15 ,-r 41). Plaintiff further alleges that as the
condominium owners began occupying their units, they encountered multiple
construction defects that indicated the Sponsor's representations of the physical
conditions of the building were false (id ,-i 45). Therefore, plaintiff brought the
151532/2019 BOARD OF MANAGERS OF 87-89 LEONARD STREET CONDOMINIUM, SUING ON Page 3 of 10
BEHALF OF ITS UNIT OWNERS vs. LEONARD STREET OWNER, LLC ET AL
Motion No. 003

[* 3] 3 of 10
FILED: NEW YORK COUNTY CLERK 10/16/2024 04:26 PM INDEX NO. 151532/2019
NYSCEF DOC. NO. 275 RECEIVED NYSCEF: 10/16/2024

underlying action against the Sponsors and GMA on February 12, 2019 (NYSCEF #
15, Complaint).

More than four years later, the Sponsors began this third-party action
against GMA and many others for the damages the Sponsors may incur as a result
of the underlying action (NYSCEF # 63 at WHEREFORE paragraph). The Sponsors
bring six causes of action against GMA and the other third-party defendants: (1)
breach of contract, (2) contractual indemnification, (3) breach of contractual
insurance procurement obligations, (4) contribution, (5) common law
indemnification, and (6) negligence (id ,r,r 32, 56-57, 59-60, 63, 66, 70, 73).

GMA now brings the current motion to dismiss all of the third ·party claims
as alleged against it pursuant to CPLR 3211(a)(l), (a)(3), and (a)(7) (NYSCEF # 105,
Notice of Motion [MS 003]). 2 GMA argues as follows: (a) Counts I and III for breach
of contract and breach of contractual insurance procurement obligations are time·
barred under the statute of limitations because the project was finished on
February 14, 2018; (b) Counts II and III for contractual indemnity and breach of
contractual insurance procurement obligations should be dismissed because the
May 27, 2014 Insurance Rider did not create an obligation for GMA to indemnify
Sponsors; (c) Count V for common law indemnity is precluded because plaintiff in
the underlying action is seeking to hold Sponsors actively negligent; and (d) there is
no privity of contract between GMA and Sponsors, thus defeating the contract and
tort claims (see generally NYSCEF # 108, GMA's MOL).

The Sponsors oppose except as to Count IV for contribution and Count VI for
negligence (NYSCEF # 176, Sponsors' Response Aff., ,r 2 [opposing dismissal only
against Counts 1, 2, 3, and 5]). The Sponsors argue that (a) Counts I and III for
breach of contract and breach of contractual insurance procurement obligations are
nottime·barred because work did not finish until at least April 8, 2022; (b) Counts
II and III for contractual indemnity and breach of contractual insurance
procurement obligations should not be dismissed because there is an Indemnity and
Insurance Procurement Agreement that does create an obligation for GMA to
indemnify; (c) Count V for common law indemnity should not be dismissed because
the Sponsors fully delegated duties to GMA; and (d) there is privity of contract (id).

GMA replies that (a) the work that was completed on April 8, 2022 related to
a different project and different DOB job number, and therefore does not affect the
statute of limitations for Counts I and III; (b) Counts II and III fail because
Sponsors conceded their negligence claim, and thus there is no issue of fact
regarding the Indemnity and Insurance Procurement Agreement; and (c) Count V
common law indemnity should be dismissed because the Architect's Certifications

2 Because the Sponsors do not oppose dismissal of Counts IV and VI, arguments relating to these
claims ha,ve been excluded below.
151532/2019 BOARD OF MANAGERS OF 87-89 LEONARD STREET CONDOMINIUM, SUING ON Page 4 of 10
BEHALF OF ITS UNIT OWNERS vs. LEONARD STREET OWNER, LLC ET AL
Motion No. 003

[* 4] 4 of 10
FILED: NEW YORK COUNTY CLERK 10/16/2024 04:26 PM INDEX NO. 151532/2019
NYSCEF DOC. NO. 275 RECEIVED NYSCEF: 10/16/2024

delegating work to GMA do not absolve Sponsors of liability (see generally NYSCEF
# 192, GMA's Reply). .

Discussion

LegaIStandard

On a motion to dismiss under CPLR 3211(a)(l), a party may move for
judgment dismissing one or more causes of action asserted against him on the
ground that a defense to the asserted claim is founded upon documentary evidence.
(Carlson v American Intl. Group, Inc., 30 NY3d 288, 301 [2017]).

For a motion to dismiss under CPLR 3211(a)(3), the moving party has the
burden to prove via prima facie evidence that plaintiffs have no standing to sue.
(Brunner v Estate ofLax, 137 AD3d 553, 553 [1st Dept 2016]).

While on a motion to dismiss under CPLR 3211(a)(7), the court must accept
the facts alleged in the complaint as true and accord plaintiffs the benefit of every
possible favorable inference, determining only whether the facts as alleged "fit
within any cognizable legal theory" ( Tax Equity Now N. Y. LLC v City ofNew York,
42 NY3d 1, 6 [2024], quoting Leon v Martinez, 84 NY2d 83, 87·88 [1994]). However,
if the allegations consist of bare legal conclusions and factual claims that are either
inherently incredible or flatly contradicted by documentary evidence, such benefit is
not warranted (M & B Joint Venture, Inc. v Laurus Master Fund, Ltd, 49 AD3d
258, 260 [1st Dept 2008]).

Threshold Matter: Conceded Claims (Counts IV & lfl)

The Sponsors do not oppose GMA's Motion to Dismiss their Contribution
(Count IV) and Negligence (Count VI) claims (NYSCEF # 176 ,r 2). Therefore, these
claims are dismissed.

Statute ofLimitations: (Counts I & III)

"An action to recover damages for malpractice, other than medical, dental or
podiatric malpractice, regardless of whether the underlying theory is based in
contract or tort, must be commenced within three years" (CPLR § 214 [6]).

Both parties agree that the applicable statute of limitations accrues on the
date of completion of the job and runs for three years (NYSCEF # 108 at 5; NYSCEF
# 176 ,r 14 [implicitly accepting three-year statute of limitations]). Where they
disagree is on when that date of completion actually was. GMA argues that the
statute of limitations accrued on February 14, 2018, when the Project received its
Final Certificate of Occupancy for Job #1 and expired three years later on February

151532/2019 BOARD OF MANAGERS OF 87-89 LEONARD STREET CONDOMINIUM, SUING ON Page 5 of 10
BEHALF OF ITS UNIT OWNERS vs. LEONARD STREET OWNER, LLC ET AL
Motion No. 003

[* 5] 5 of 10
FILED: NEW YORK COUNTY CLERK 10/16/2024 04:26 PM INDEX NO. 151532/2019
NYSCEF DOC. NO. 275 RECEIVED NYSCEF: 10/16/2024

14, 2021 (NYSCEF # 108 at 6). 3 Since the third-party complaint was filed on
September 5, 2023, GMA argues that the breach of contract and breach of insurance
procurement obligation were time barred upon filing (id).

The Sponsors respond that the date of completion was actually April 8, 2022,
at the earliest, and submit multiple documents in an attempt to prove their point
(NYSCEF # 176 ,r 14). They first submit a "snapshot of the [DO B's] Job Overview
page," which they argue shows that in addition to Job #1, GMA was also working at
the building pursuant to Job Number 123409338 ("Job #2") until at least April 8,
2022 (id ,r 15; NYSCEF # 177, DOB Job Overview Page). Sponsors claim this
snapshot shows that at the time of their opposition, there was still no final
certificate of occupancy for Job #2 (NYSCEF # 176 ,r,r 14·17). Sponsors next submit
a "PWI: Plan/Work Application" form for Job #2 in which GMA described the job as
"converting an existing duplex apartment at cellar & 1st floor back into a
commercial (B occupancy) use" (id ,r 15; NYSCEF # 179, PWl Application for Job
· #2, at 2, 4). Sponsors also submit GMA's April 7, 2022 application for a Post·
Approval Amendment, to reflect the continued conversion work pursuant to Job #2
(id ,r16; NYSCEF # 180, GMA's Application for Post-Approval Amendment).
Sponsors argue that these documents together show that GMA continued to work
on the Project through at least April 8, 2022, extending the statute of limitations
long past the date of this third ·party complaint.

GMA replies that Job #2 is a separate job from Job #1, and therefore the
statute of limitations accrued with the Final Certificate of Occupancy for Job #1
(NYSCEF # 192 at 3). GMA points out that Sponsors do not dispute any of GMA's
arguments. GMA argues that the third-party complaint itself defines "the Project"
as the conversion of the "150-year-old landmarked cast-iron building," implicitly
conceding that the Project and underlying complaint relate to Job #1 and not Job #2
(id at 4·5, quoting NYSCEF # 63 ,r 29). Moreover, GMA argues that "[n]one of the
services provided by GMA for [Job #2] have any relation to the claims in [p]laintiffs
complaint," because the complaint only discusses defects related to the overall
conversion of the building (NYSCEF # 192 at 5). GMA also points out that the
underlying complaint was filed before Job #2 even had a Temporary Certificate of
Occupancy (id at 6). GMA also argues that for Job #2 "was not a continuation" of
Job #1, because Job #2 was pursuant to "a separate written agreement, separate
application with the DOB, separate designs, separate scope and fee, and separate
performance" (id at 7).

Once a design professional has completed their contractual duties, the
statute of limitation's expiration date will not be extended for an incidental matter
arising out of the subsequent relationship with the owner (see Sendar Dev. Co.,
LLC v CAM Design Studio P. C., 68 AD3d 500, 503 [1st Dept 2009]; see also Cabrini

3 The Statute of Limitations could have alternatively expired on September 30, 2021, if a 228-day

pandemic related toll is considered, but this does not affect the analysis.
151532/2019 BOARD OF MANAGERS OF 87-89 LEONARD STREET CONDOMINIUM, SUING ON Page 6 of 10
BEHALF OF ITS UNIT OWNERS vs. LEONARD STREET OWNER, LLC ET AL
Motion No. 003

[* 6] 6 of 10
FILED: NEW YORK COUNTY CLERK 10/16/2024 04:26 PM INDEX NO. 151532/2019
NYSCEF DOC. NO. 275 RECEIVED NYSCEF: 10/16/2024

Med Ctr. v Desina, 64 NY2d 1059, 1061 [1985]; State ofNew York v Lundin, 60
NY2d 987, 989 [1983]). For example, in Mutual Redevelopment Houses, Inc. v
Skyline Engineering, LLC, the First Department tolled the Statute of Limitations
accrual date only because the second project consisted of remediating defects in the
original project (178 AD3d 575, 576 [1st Dept. 2019]).

Here, Job #2 is an incidental matter, and therefore the statute oflimitations
accrued with the Final Certificate of Occupancy issued in Job #1. Unlike Mutual
Redevelopment Houses, GMA's subsequent services in Job #2 were not in
remediation of defects in Job #1 but were a completely separate job with an entirely
different goal. Namely, Job # 1 involved converting and restoring a 150-year-old
cast-iron building into a condominium, while Job #2 involved converting a single
existing duplex apartment into a Commercial (B Occupancy) Use (NYSCEF # 107 at
*68; NYSCEF # 179 at 2, 4). In other words, Job #1 converted the building from one
type of residential use to another, while Job #2 converted a single unit from
residential to commercial-completely separate goals.

Additionally, the documents submitted by Sponsors do not imply any
connection between the two jobs. For example, the "snapshot of the [DO B's] Job
Overview" page shows that Job #2 started two months afterthe DOB issued the
Final Certificate of Occupancy for Job #1, strongly suggesting the two projects are
unrelated (see NYSCEF # 177). As for the PWl and Post-Approval Amendment
forms for Job #2, both forms have a section for the applicant to add "Related DOB
Job Numbers" (see NYSCEF # 179 at 4 [§ IIA]). GMA (the applicant) left that box
empty, indicating that GMA did not believe there was any relation between Job #2
and Job #1.

Thus, Job #2 is at best incidental to Job #1 and does not extend the job
completion date. The Statute of Limitations therefore accrued on February 14, 2018,
the date of Job #l's Final Certificate of Occupancy and expired three years later on
February 14, 2021. 4 Sponsors filed the Third-Party Complaint on September 5, 2023
(NYSCEF # 63), meaning that the claims for breach of contract (Count I) and breach
of insurance procurement obligation (Count III) were already time-barred. Counts I
and III are therefore dismissed. 5

Contractual Indemnification (Count II)

When a party is under no legal duty to indemnify, a contract assuming that
obligation "must be strictly construed to avoid reading into it a duty which the
parties did not intend to be assumed" (Cordeiro v. TS Midtown Holdings, LLC, 87
AD3d 904, 907 [1st Dept 2011]).

4 Or September 30, 2021, if a 228·pandemic related toll is applied as per Governor Cuomo's
Executive Order 202.8.
5 Given this conclusion, the court does not reach the arguments about privity.
151532/2019 BOARD OF MANAGERS OF 87-89 LEONARD STREET CONDOMINIUM, SUING ON Page 7 of 10
BEHALF OF ITS UNIT OWNERS vs. LEONARD STREET OWNER, LLC ET AL
Motion No. 003

[* 7] 7 of 10
FILED: NEW YORK COUNTY CLERK 10/16/2024 04:26 PM INDEX NO. 151532/2019
NYSCEF DOC. NO. 275 RECEIVED NYSCEF: 10/16/2024

GMA argues it has no contractual duty to indemnify because there are no
agreements creating such an obligation. Notably, GMA claims in an affidavit that
the only agreements it entered relating to the Project were the Proposal and the
February 4, 2016 Indemnity Agreement in which Ravner agreed to indemnify GMA
(NYSCEF # 107 at *3 [GMA Principal's Affidavit ,r 5]). Since both of those
agreements were between GMA and nonpartyMB Leonard St. LLC, GMA argues
that the documents conclusively establish that Sponsors do not have any
contractual right to indemnity (NYSCEF # 108 at 7-9; see also Acquista v N. Y. Life
Ins. Co., 285 AD2d 73, 76 [1st Dept 2001] [dismissal based on documentary evidence
under CPLR 3211(a)(l) appropriate where documents prove "a material fact as
claimed by the pleader is not a fact at all and no significant dispute exists regarding
it"]).

But as Sponsors show, GMA did enter into other agreements with respect to
the Project. Specifically, Sponsors submit an Insurance Rider dated May 27, 2014,
under which GMA agreed to indemnify MB Leonard St., LLC, and its "officers,
agents, employees, authorized representatives and customers" (NYSCEF # 183 § 2
[b]). Sponsors assert that Sponsors Ravner and Shaoul are the principals of both
Sponsor Leonard Street Owner, LLC and non-party MB Leonard St., LLC, and are
therefore beneficiaries of the indemnification provision (NYSCEF # 176 ,r 20).

Yet even if the Insurance Rider's indemnity clause applies to Sponsors, GMA
persuasively argues that the clause is nonetheless too narrow to apply here.
Specifically, the indemnity clause is limitedto "injuries to persons or damage to
property," and/or claims for Worker's Compensation (NYSCEF # 192 at 12, quoting
NYSCEF # 183 § 2 [b]). The underlying complaint alleges only breach of contract,
breach of fidµciary duty, and fraud, none of which relate to injuries to person,
property, or Worker's Compensation (see generallyNYSCEF # 15). Therefore, the
Insurance Rider does not contractually mandate indemnification for cases like the
underlying one.

Nevertheless, the court will deny the motion to dismiss the contractual
indemnity claim. As Sponsors point out, the third-party complaint alleged
indemnity obligations pursuant to "written agreement or agreement§" (see NYSCEF
#176 ,r 20 [emphasis added]), and they are entitled to discovery to determine
whether any additional indemnification agreements exist. This is especially true
because GMA's assertion that no other agreements exist is directly contradicted by
the existence of the Insurance Rider. Therefore, the court cannot infer that no other
indemnification agreements exist, and that the three known agreements
conclusively establish that there is no contractual indemnification claim (see
Morgenthow& Latham v BankofN.Y. Co., Inc., 305 AD2d 74, 78 [1st Dept 2003]
[allegations in complaint presumed true except where "flatly contradicted by
documentary evidence"]).

151532/2019 BOARD OF MANAGERS OF 87-89 LEONARD STREET CONDOMINIUM, SUING ON Page 8 of 10
BEHALF OF ITS UNIT OWNERS vs. LEONARD STREET OWNER, LLC ET AL
Motion No. 003

[* 8] 8 of 10
FILED: NEW YORK COUNTY CLERK 10/16/2024 04:26 PM INDEX NO. 151532/2019
NYSCEF DOC. NO. 275 RECEIVED NYSCEF: 10/16/2024

As a result, there is still a question of fact, and GMA's Motion to Dismiss the
Contractual Indemnification claim (Count II) is denied.

Common Law Indemnification (Count v,)
Common-law indemnification may be pursued by parties who have been held
vicariously liable for negligence that injured the plaintiff (Chatham Towers, Inc. v
Castle Restoration & Constr., Inc., 151 AD3d 419,420 [1st Dept 2017]). Therefore, a
party who has itself actually participated to some degree in the wrongdoing cannot
receive the benefit of common law indemnity (17 Wsta Fee Assocs. v Teachers Ins.
& Annuity Assn ofAm., 259 AD2d 75, 80 [1st Dept 1999]). The only exception is if
the alleged negligence has resulted from a duty that they were compelled to
discharge but that had been fully delegated to, and should have been discharged by,
the party whose negligence was the actual cause ofloss (Bd ofManagers of the
Porter House Condo. v Delshah 60 Mnth LLC, 192 AD3d 415, 415 [1st Dept 2021],
quoting 17 Wsta Fee, 259 AD2d at 80).

Here, Sponsors cannot sustain a claim for common law indemnification
because they have actually participated in the alleged wrongdoing (see 17 Wsta Fee,
259 AD2d at 80). In the underlying complaint, plaintiff sues Sponsors for breaches
of contract, fiduciary duty, and fraud (NYSCEF # 15). All three causes of action seek
to hold Sponsors directly liable for Sponsors' own conduct because, among other
things, they were obligated to convert the building in accordance with the terms of
the Offering Plan and made numerous affirmative misrepresentations through its
promotion (id).

The Sponsors nevertheless argue that they meet the exception to the general
rule because they delegated the preparation of the plans and specifications to GMA,
from which the plaintiff is now alleging defects and fraud (id at ,r 25). However, the
Sponsors are still not entitled to common law indemnification for three reasons:

First, the Sponsors cannot rely on the exception because it only applies when
the person seeking indemnity was forced to discharge the duties they had delegated
to someone else (Porter House Condo, 192 AD3d at 415). Here, Sponsors admit that
GMA completed every task delegated to them (NYSCEF # 176 ,r,r 24-26). Sponsors
did not complete any of the work delegated to GMA. Thus, the exception does not
apply.

Second, even if the exception did apply, GMA's Architect's Certifications
contained a disclaimer that they were "not intended as a guarantee or warranty of
the physical condition of the property" and only certified the "conditions of the
entire property as it should exist upon completion of the construction, provided
construction is in accordance with the plans that we examined, and information
supplied by the Sponsor." (NYSCEF # 187 at *4, *7). Therefore, relying on these

151532/2019 BOARD OF MANAGERS OF 87-89 LEONARD STREET CONDOMINIUM, SUING ON Page 9 of 10
BEHALF OF ITS UNIT OWNERS vs. LEONARD STREET OWNER, LLC ET AL
Motion No. 003

[* 9] 9 of 10
FILED: NEW YORK COUNTY CLERK 10/16/2024 04:26 PM INDEX NO. 151532/2019
NYSCEF DOC. NO. 275 RECEIVED NYSCEF: 10/16/2024

certifications to depict how the building was actually constructed, is, at best, a
result of the Sponsors' own malpractice.

Third, a claim for common law indemnification requires an underlying
negligence cause of action (Sendar, 68 AD3d at 504), but Sponsors have conceded
their negligence claim. Therefore, the common law indemnification claim does not
have the predicate cause to survive.

Conclusion
Pursuant to the above, it is hereby

ORDERED that GMA's Motion to Dismiss Cross-Claims and Third-Party
Claims (MS 003) is denied in part with respect to Count II of the Third Party
Claims for Contractual Indemnification, and granted with respect to the remaining
claims; and it is further

ORDERED that within 30 days of the e·filing of this order, GMA shall file an
answer to the third-party complaint.

This constitutes the Decision and Order of the court.

10/15/2024
DATE MARGARET A. CHAN, J.S.C.

~
CHECK ONE: CASE DISPOSED NON-FINAL DISPOSITION

GRANTED □ DENIED GRANTED IN PART □ OTHER
APPLICATION: SETTLE ORDER SUBMIT ORDER

CHECK IF APPROPRIATE: INCLUDES TRANSFER/REASSIGN FIDUCIARY APPOINTMENT □ REFERENCE

151532/2019 BOARD OF MANAGERS OF 87-89 LEONARD STREET CONDOMINIUM, SUING ON Page 10 of 10
BEHALF OF ITS UNIT OWNERS vs. LEONARD STREET OWNER, LLC ET AL
Motion No. 003

[* 10] 10 of 10

---