# Transource Pennsylvania, LLC v. DeFrank

> District Court, M.D. Pennsylvania · August 26, 2021

URL: https://www.frixlaw.com/law-library/cases/10410637

## Case

- **Court:** District Court, M.D. Pennsylvania
- **Decided:** August 26, 2021
- **Opinion:** 100trialcourt
- **Cited by:** 0 later opinions in the Frix Law Library

## Citator (automated)

- No negative treatment found by the automated citator. That is not the same as a confirmation that the case is good law; read the citing cases.
- Full citator and citing cases: https://www.frixlaw.com/law-library/cases/10410637

## How later opinions describe it (automated extraction)

- observing that “[s]tate courts are fully competent to adjudicate constitutional challenges to local land-use decisions”

## Opinion text

IN THE UNITED STATES DISTRICT COURT
FOR THE MIDDLE DISTRICT OF PENNSYLVANIA
TRANSOURCE PENNSYLVANIA, : Civil No. 1:21-CV-01101
LLC, :
:
Plaintiff, :
:
v. :
:
GLADYS BROWN DUTRIEUILLE, et :
al., :
:
Defendants. : Judge Jennifer P. Wilson
MEMORANDUM
This is a declaratory judgment action filed by Plaintiff Transource
Pennsylvania, LLC (“Transource”) against the Pennsylvania Public Utility
Commission (“PUC”) and its Commissioners (collectively, “Defendants”). Before
the court is a motion to dismiss the complaint filed by Defendants. (Doc. 57.) For
the reasons that follow, the motion will be denied in part with respect to
Defendants’ contention that Transource lacks standing. Because the court finds
that abstention is appropriate in this case, the court will defer ruling on the
remainder of the motion.
FACTUAL BACKGROUND AND PROCEDURAL HISTORY
According to the complaint, Transource is a limited liability company
“formed to construct, own, operate, and maintain electric transmission facilities
and equipment within the Commonwealth of Pennsylvania.” (Doc. 1, ¶ 7.) The
Commonwealth of Pennsylvania participates in an “inter-state regional electric grid
covering all or part of 13 states and the District of Columbia.” (Id. ¶ 1.) As part of
this system, the Federal Energy Regulatory Commission (“FERC”) has a planning

process to ensure “efficient and reliable operation of the . . . system[,]” which may
include planning for and construction of additional electric transmission lines.
(Id.) The complaint identifies PJM Interconnection, LLC (“PJM”) as a “federally-

regulated regional transmission organization” responsible for, inter alia, identifying
“new electric transmission lines necessary for efficient and reliable operation of the
regional electric system.” (Id.) Participating in FERC’s planning process, PJM
identified a need for two new transmission lines from southern Pennsylvania into

Maryland to alleviate congestion within the existing electric transmission
framework. (Id. ¶ 2.) In October 2014, PJM began soliciting proposals “to
address, among other things, transmission congestion constraints in Pennsylvania,

Maryland, Virginia, and West Virginia.” (Id. ¶ 36.)
To meet this need and construct these additional transmission lines,
Transource submitted a proposal, which was approved by PJM on August 2, 2016.
(Id. ¶ 21.) Transource then entered into a “Designated Entity Agreement” with

PJM authorizing it to construct “two new electric transmission lines and associated
facilities” in Pennsylvania, which was approved by FERC in January 2017. (Doc.
1, ¶¶ 3, 41.) In order to proceed with its projects, Transource applied to the PUC

for a “Certificate of Public Convenience granting public utility status, which would
allow Transource . . . to enter upon land in order to make studies, surveys, tests,
soundings and appraisals related to siting the transmission lines[,]” which was

granted on January 23, 2018. (Id. ¶¶ 3, 43, 63.)
Thereafter, Transource alleges that it sought PUC approval in order to site
the transmission lines, which the PUC denied on May 24, 2021 after it determined

that the “lines were not needed because eliminating the bottleneck would primarily
help out-of-state customers,” rather than Pennsylvania customers. (Id. ¶ 4.) As
part of its decision, the PUC also “revoked Transource’s provisional certificate
granting it status as a Pennsylvania public utility.” (Id. ¶ 63.) Transource then

filed a direct appeal to the Pennsylvania Commonwealth Court on June 23, 2021,
which remains pending.1 Pa. Commw. Ct. Docket No. 689 CD 2021.
Transource filed the instant complaint on June 22, 2021, seeking declaratory

relief on the ground that the PUC’s decision is preempted under federal law and
violates the dormant commerce clause. (Id. at 40.)2 In addition, Transource seeks
injunctive relief preventing enforcement of the PUC’s decision, including its
revocation of Transource’s Certificate of Public Convenience. (Id. at 41.)

Transource has requested resolution of this case on an expedited basis, noting that

1 As of August 17, 2021, the parties indicated that the certified list had been filed and they were
awaiting a briefing schedule from the Commonwealth Court. (Doc. 76, p. 8.)

2 For ease of reference, the court utilizes the page numbers from the CM/ECF header.
it must obtain all required state permits by September 30, 2021, under its
Designated Entity Agreement with PJM. (Id. at 41.) To date, Transource has filed

a motion for summary judgment and a motion to expedite, Docs. 20, 21; PJM has
filed a motion for leave to file an amicus brief, Doc. 40; and Defendants have filed
a motion to dismiss, Doc. 57. On July 12, 2021, the court issued an order setting

an expedited briefing schedule for these motions and scheduling oral argument.
(Doc. 30.) All motions were all ripe for review as of August 13, 2021. (Docs. 23,
24, 41, 58, 61, 63, 66, 68, 70, 72.)
On August 17, 2021, the court held oral argument limited to the issues raised

by the motion to dismiss. In addition to these issues, the court requested that
counsel be prepared to discuss the applicability of the Younger3 abstention
doctrine, which the court raised sua sponte. (Doc. 71.) Following oral argument,

the court allowed counsel to submit supplemental briefs addressing the
Wilton/Brillhart4 abstention doctrine. (Doc. 75.) These briefs were timely filed on
August 24, 2021. (Docs. 78, 80, 81.)

3 Younger v. Harris, 401 U.S. 37 (1971).

4 Wilton v. Seven Falls Co., 515 U.S. 277, 290 (1995); Brillhart v. Excess Ins. Co., 316 U.S. 491,
495 (1942).
STANDARD OF REVIEW
Defendants seek dismissal of the complaint pursuant to Federal Rule of Civil

Procedure 12(b)(1) for lack of subject-matter jurisdiction.5 The court, in
determining whether it has subject-matter jurisdiction, must decide “whether the
allegations on the face of the complaint, taken as true, allege facts sufficient to

invoke the jurisdiction of the district court.” Taliaferro v. Darby Twp. Zoning Bd.,
458 F.3d 181, 188 (3d Cir. 2006) (quoting Licata v. U.S. Postal Serv., 33 F.3d 259,
260 (3d Cir. 1994)). Rule 12(b)(1) challenges may be “facial” or “factual.” See
Mortensen v. First Fed. Sav. & Loan Ass’n, 549 F.2d 884, 891 (3d Cir. 1977). A

facial attack challenges whether jurisdiction has been properly pled and requires
the court to “only consider the allegations of the complaint and documents
referenced therein and attached thereto, in the light most favorable to the plaintiff.”

Gould Elecs., Inc. v. United States, 220 F.3d 169, 176 (3d Cir. 2000) (citing
Mortensen, 549 F.2d at 891). Conversely, when a defendant sets forth a factual
attack on subject-matter jurisdiction, “the Court is free to weigh the evidence and
satisfy itself whether it has power to hear the case. . . . ‘no presumptive truthfulness

attaches to plaintiff’s allegations, and the existence of disputed material facts will
not preclude the trial court from evaluating for itself the merits of jurisdictional

5 Defendants also move to dismiss on Rule 12(b)(6) grounds. However, for purposes of this
decision, the court only addresses the jurisdictional challenge under Rule 12(b)(1).
claims.’” Carpet Group Int’l v. Oriental Rug Importers Ass’n, Inc., 227 F.3d 62,
69 (3d Cir. 2000) (quoting Mortensen, 549 F.2d at 891).

In this case, Defendants challenge Transource’s alleged failure to establish
Article III standing, thus presenting a facial attack on subject-matter jurisdiction.
As a result, the court will “only consider the allegations of the complaint and

documents referenced therein and attached thereto, in the light most favorable to
the plaintiff.” Gould Elecs., Inc., 220 F.3d at 176 (citing Mortensen, 549 F.2d at
891).
DISCUSSION

Defendants first argue that Transource lacks standing to bring this lawsuit.
Specifically, Defendants claim that Transource has not suffered an injury in fact
because all economic injuries that Transource claims to have sustained “are

predicated on future contingent events that have not happened yet and may not
happen at all.”6 (Doc. 58, p. 19.) In addition, Defendants assert that Transource’s
purported injuries are not redressable because Transource could face the “same
prospective economic harm [that] it does now even if the [c]ourt were to provide

Transource with the relief it is seeking in this case.” (Id. at 24.) In other words,

6 As a corollary to this argument, Defendants claim that even if Transource sustains economic
injuries in the future, it may be able to recover most, if not all, of these costs. (Doc. 72, p. 9.)
Specifically, Defendants assert that Transource “received a commitment from FERC that it will
recover ‘100 percent’ of its ‘prudently-incurred’ expenditures on the [Projects] as well as a 9.9
percent return on its investment.” (Id.) Therefore, Defendants argue that any economic loss
alleged by Transource is speculative. (Id.)
Transource could obtain a remand of its case to the PUC from this court, but would
then have to establish that its siting applications should be granted under all four

factors listed in 52 PA. CODE § 57.76, which it may not be able to do. (Id.)
Finally, Defendants argue that Transource lacks standing to seek declaratory relief
because such relief is unavailable to remedy an injury that was sustained in the

past. (Doc. 72, pp. 10−11.)
Transource counters that it has been injured because the PUC has denied its
siting permit applications and revoked its certificate of public convenience. (Doc.

68, p. 13.) These actions have prevented Transource from moving forward with its
construction projects, and, without remedy, will put Transource “out of business.”
(Id.; Doc. 76, p. 24.) Likewise, Transource asserts that its injuries are redressable
because “[i]f a reviewing court agrees that [an] agency misinterpreted the law, it

will set aside the agency’s action and remand the case—even though the agency
. . . might later, in the exercise of its lawful discretion, reach the same result.”7 (Id.
at 14−15 (quoting FEC v. Akins, 524 U.S. 11, 25 (1998)).)

The court addresses these arguments below.

7 Transource does not dispute Defendants’ contention that it may be able to recover its economic
losses through FERC if and when they occur. However, Transource argues that the FERC
process will be a “litigated proceeding” in which there is no guarantee that Transource would
“recover every penny of” its investment costs associated with the projects. (Doc. 76, p. 27.)
A. Transource has Standing to Bring this Lawsuit.
Because Article III of the United States Constitution only allows federal

courts to decide cases and controversies, a plaintiff must have standing to bring a
claim in federal court. Dep’t of Comm. v. New York, 588 U.S. __, 139 S. Ct. 2551,
2565 (2019). Article III standing requires that a plaintiff show “(1) a concrete and

particularized injury, that (2) is fairly traceable to the challenged conduct, and (3)
is likely to be redressed by a favorable decision.” Virginia House of Delegates v.
Bethune-Hill, 587 U.S. __, 139 S. Ct. 1945, 1950 (2019) (citing Hollingsworth v.
Perry, 570 U.S. 693, 704 (2013)).

For cases brought under the Declaratory Judgment Act, the Supreme Court
has held that “[b]asically, the question in each case is whether the facts alleged,
under all the circumstances, show that there is a substantial controversy, between

parties having adverse legal interests, of sufficient immediacy and reality to
warrant the issuance of a declaratory judgment.” MedImmune, Inc. v. Genentech,
Inc., 549 U.S. 118, 127 (2007). In addition, the Third Circuit has held that “[t]o
satisfy the standing and ‘case or controversy’ requirements of Article III, a party

seeking a declaratory judgment ‘must allege facts from which it appears there is a
substantial likelihood that he will suffer injury in the future.’” Blakeney v.
Marsico, 340 F. App’x 778, 780 (3d Cir. 2009) (quoting Bauer v. Texas, 341 F.3d

352, 358 (5th Cir. 2003)); see also Wenzig v. SEIU Local 668, 426 F. Supp. 3d 88,
100 (M.D. Pa. 2019) (“Declaratory judgment is not meant to adjudicate alleged
past unlawful activity.”).

In this case, the court finds that the PUC’s denial of Transource’s siting
applications and the rescission of its certificate of public convenience are sufficient
grounds to establish standing.8 It is evident that this case presents a substantial

controversy between adverse parties. Indeed, Transource has been litigating its
ability to construct these transmission lines for almost four years. (Doc. 76, p. 4.)
Transource’s interest is clearly adverse to the PUC because the PUC denied its
siting applications and is actively contesting Transource’s appeal in the

Commonwealth Court and the instant lawsuit. This controversy is also immediate
and real. Transource has alleged that it is required, under its contract with PJM, to
obtain all necessary state permits, including approval of the siting applications

before the PUC, by September 30, 2021—a deadline which is quickly
approaching.9

8 Defendants admitted during oral argument that, to the extent Transource claims that the denial
of its applications and revocation of its certificate of public convenience are sufficient to
establish standing, it would not contest that the traceability prong of Article III standing is met.
(Doc. 76, p. 24.)

9 Transource has not denied that it may seek an extension of this deadline from PJM in order to
obtain its required permits, and Defendants assert that an extension of this deadline has occurred
in the past. However, at this juncture, the court has not been advised that an extension has been
requested and does not know whether such request, if made, will be granted. In any event, it is
also not clear, based on the record before the court at present, that a failure to meet this deadline
would result in a cancellation of Transource’s contract with PJM. However, the court notes that
this possibility has been alleged to exist.
Moreover, without obtaining the relief requested in this action, there is a
substantial likelihood that Transource will suffer future harm. If Transource is

unable to obtain the required permits for construction in Pennsylvania to proceed at
all, regardless of whether it is able to meet its contract deadline, its project would
effectively end before it could begin. Transource is an entity created for the sole

purpose of constructing and overseeing the transmission facilities. If this project is
terminated, Transource’s existence as an entity will follow suit. Thus, not only has
Transource been harmed by the PUC’s decision to deny its applications, it also
faces the future harm of ceasing to exist as an entity—i.e., being forced “out of

business.” (Doc. 76, p. 24.) Absent the relief sought in this action, Transource has
no chance of returning to the PUC to pursue the application process and construct
these transmission lines.10 Therefore, the court finds that Transource has standing

to bring this lawsuit.11

10 While Transource essentially has two avenues by which it could return to the PUC, through
relief granted either by this court or the Commonwealth Court, this reality does not impact the
finding that Transource has standing to pursue its claims in this court.

11 The court will not discuss the arguments raised regarding issue or claim preclusion at this
juncture, as these issues do not serve as a jurisdictional bar that would prevent the court from
hearing this case. See, e.g., Holton v. Henon, 832 F. App’x 781, 785 (3d Cir. 2020) (noting that
“issue preclusion is not a jurisdictional bar”); Pagano v. Ventures Trust, No. 3:15-cv-1489, 2016
U.S. Dist. LEXIS 8341, at *18 n.5 (M.D. Pa. Jan. 22, 2016) (same), report and recommendation
adopted at 2016 U.S. Dist. LEXIS 22584 (Feb. 24, 2016); Briar Meadows Dev., Inc. v. South
Ctr. Twp. Bd. of Supervisors, No. , 2010 U.S. Dist. LEXIS 108995, at *18−19 (M.D. Pa. Oct. 13,
2010) (noting that claim preclusion “is not a jurisdictional bar, but rather is an affirmative
defense”).
B. Abstention
Having determined that the court has jurisdiction to preside over this

dispute, see Kelly v. Maxum Specialty Ins. Group, 868 F.3d 274, 281 n.4 (3d Cir.
2017) (citing Skelly Oil Co. v. Phillips Petroleum Co., 339 U.S. 667, 671 (1950)),
the court next turns to the question of whether to exercise this jurisdiction over the

claims presented in this litigation.
The Supreme Court has held that, as a general rule, “federal courts are
obliged to decide cases within the scope of federal jurisdiction; abstention is not in
order simply because a pending state-court proceeding involves the same subject

matter.” Sprint Communs., Inc. v. Jacobs, 571 U.S. 69, 72 (2013) (cleaned up)
(citing New Orleans Public Service, Inc. v. Council of City of New Orleans, 491
U.S. 350, 373 (1989) (“NOPSI”) (“[T]here is no doctrine that . . . pendency of state

judicial proceedings excludes the federal courts.”)). In other words, “the pendency
of an action in state court is no bar to proceedings concerning the same matter in
the Federal court having jurisdiction.” Colorado River Water Conservation Dist.
v. United States, 424 U.S. 800, 817 (1976).

The Younger abstention doctrine was formed as an exception to this general
rule, holding that federal courts must abstain from exercising their jurisdiction in
cases with a parallel pending state criminal proceeding. Younger v. Harris, 401

U.S. 37 (1971). Younger has since been extended by the Supreme Court to cases
involving “state criminal prosecutions, civil enforcement proceedings, and civil
proceedings involving certain orders that are uniquely in furtherance of the state

courts’ ability to perform their judicial functions.” Sprint Communs. Inc., 571 U.S.
at 73 (cleaned up) (citing NOPSI, 491 U.S. at 367−68). However, the Supreme
Court has emphasized that “[c]ircumstances fitting within the Younger doctrine . . .

are ‘exceptional[.]’” Sprint Communs., Inc., 571 U.S. at 73.
In an apparent effort to restrict federal courts from abstaining in cases over
which they could otherwise exercise jurisdiction, but recognizing that abstention

may nevertheless be appropriate in certain circumstances, the Supreme Court has
created several narrow categories of abstention in addition to the three categories
outlined in Sprint.12 Brillhart/Wilton abstention is one such category arising in the
context of the Declaratory Judgment Act, which confers discretionary jurisdiction

on the federal courts. Wilton v. Seven Falls Co., 515 U.S. 277, 290 (1995);
Brillhart v. Excess Ins. Co., 316 U.S. 491, 495 (1942). Under this category of the
abstention doctrine, “[r]ather than being subject to the ‘normal principle that

federal courts should adjudicate claims within their jurisdiction,’ district courts
exercising [their] discretion [under the Declaratory Judgment Act] are governed by
‘considerations of practicality and wise judicial administration.’” Reifer v.

12 For purposes of this case, the court discusses only the Brillhart/Wilton and Colorado River
abstention doctrines. Wilton, 515 U.S. at 290; Colorado River, 424 U.S. at 817; Brillhart, 316
U.S. at 495.
Westport Ins. Corp., 751 F.3d 129, 139 (3d Cir. 2014) (quoting Wilton, 515 U.S. at
288).

In addition, Brillhart is implicated in cases “where ‘another proceeding [i]s
pending in a state court in which all the matters in controversy between the parties
could be fully adjudicated.’” Id. (quoting Brillhart, 316 U.S. at 495). The

Brillhart Court reasoned that:
[o]rdinarily it would be uneconomical as well as vexatious for a federal
court to proceed in a declaratory judgment suit where another suit is
pending in a state court presenting the same issues, not governed by
federal law, between the same parties. Gratuitous interference with the
orderly and comprehensive disposition of a state court litigation should
be avoided.

316 U.S. at 495.
In determining whether to exercise discretion to entertain litigation seeking
declaratory relief where a pending parallel state court proceeding exists, Brillhart
provided a non-exhaustive list of factors for courts to consider.13 Brillhart’s
relevance was re-affirmed in Wilton, which emphasized the non-exhaustive nature

13 The court should consider: “whether the questions in controversy between the parties to the
federal suit, and which are not foreclosed under the applicable substantive law, can better be
settled in the proceeding pending in the state court.” Brillhart, 316 U.S. at 495. Answering this
question may require inquiring

into the scope of the pending state court proceeding . . . the nature of the defenses
open there. . . . whether the claims of all parties in interest can satisfactorily be
adjudicated in that proceeding, whether necessary parties have been joined, whether
such parties are amenable to process in that proceeding, etc.

Id.
of Brillhart’s factors. Wilton, 515 U.S. at 282, 289−90. The Third Circuit has

explained that:
Brillhart and Wilton stand for at least two broad principles: (1) that
federal courts have substantial discretion to decide whether to exercise
[Declaratory Judgment Act] jurisdiction, and (2) that this discretion is
bounded and reviewable. Accordingly, this Circuit has acknowledged
the [Declaratory Judgment Act]’s grant of discretion while cautioning
that “what is granted is an opportunity to exercise a reasoned
discretion.” Bituminous Coal Operators’ Ass’n v. Int’l Union, United
Mine Workers of Am., 585 F.2d 586, 596 (3d Cir. 1978), abrogated on
other grounds by Carbon Fuel Co. v. United Mine Workers of Am., 444
U.S. 212 (1979). Thus, over the years we have enumerated factors for
district courts to consider when exercising [Declaratory Judgment Act]
discretion. We have required district courts to consider four general
factors:

(1) the likelihood that a federal court declaration will resolve the
uncertainty of obligation which gave rise to the controversy;

(2) the convenience of the parties;

(3) the public interest in settlement of the uncertainty of
obligation; and

(4) the availability and relative convenience of other remedies.

Pa. Dep’t of Envtl. Res., 923 F.2d at 1075 (citing Terra Nova Ins. Co.
v. 900 Bar, Inc., 887 F.2d 1213, 1224 (3d Cir. 1989); Bituminous Coal
Operators’ Ass’n, 585 F.2d at 596). We have also suggested that courts
“seek to prevent the use of the declaratory action as a method of
procedural fencing, or as a means to provide another forum in a race for
res judicata.” Terra Nova, 887 F.2d at 1225 (quoting 6A J. Moore, J.
Lucas & G. Girtheer, Jr., Moore’s Federal Practice ¶ 57.08[5], at 57-50
(2d ed. 1987)).

Reifer, 751 F.3d at 140. In addition to the factors listed above, the Third Circuit in
Reifer held that courts should consider: “a general policy of restraint when the
same issues are pending in a state court;” “avoidance of duplicative litigation;” and
“prevention of the use of the declaratory action as a method of procedural fencing

or as a means to provide another forum in a race for res judicata[,]” emphasizing
again that these factors are not exhaustive.14 Id. at 146. Despite this seemingly
broad grant of discretion, the Third Circuit has re-emphasized that “‘the mere

existence of a related state court proceeding’ does not require a district court to
decline to exercise jurisdiction” under the Declaratory Judgment Act. Pa. Dep’t of
Envtl. Res., 923 F.2d at 1075 (citing Brillhart, 316 U.S. at 495).
Similarly, Colorado River abstention “allows a federal court to abstain,

either by staying or dismissing a pending federal action, when there is a parallel
ongoing state court proceeding.” Nationwide Mut. Fire Ins. Co. v. George V.
Hamilton, Inc., 571 F.3d 299, 307 (3d Cir. 2009). However, this theory of

abstention is significantly narrower, and may be applied to claims brought outside
the Declaratory Judgment Act. See id. (“The doctrine is to be narrowly applied in
light of the general principle that ‘federal courts have a strict duty to exercise the
jurisdiction that is conferred upon them by Congress.’” (quoting Quackenbush v.

Allstate Ins. Co., 517 U.S. 706, 716 (1996))).

14 The Third Circuit also noted that there may be additional factors relevant for consideration in
the insurance context, which are inapplicable to this case and are therefore not mentioned here.
In determining whether Colorado River abstention is appropriate, courts
apply a two-part inquiry: (1) “whether there is a parallel state proceeding that

‘involve[s] the same parties and substantially identical claims, raising nearly
identical allegations and issues[;]’” and (2) “[i]f the proceedings are parallel, courts
then look to a multi-factor test to determine whether ‘extraordinary circumstances’

meriting abstention are present.” Nationwide Mut. Fire Ins. Co., 571 F.3d at
307−08 (quoting Yang v. Tsui, 416 F.3d 199, 204 n.5 (3d Cir. 2005); Spring City
Corp. v. American Bldgs. Co., 193 F.3d 165, 171 (3d Cir. 1999)). This multifactor

test calls for consideration of six factors: “(1) [in an in rem case,] which court first
assumed jurisdiction over [the] property; (2) the inconvenience of the federal
forum; (3) the desirability of avoiding piecemeal litigation; (4) the order in which
jurisdiction was obtained; (5) whether federal or state law controls; and (6)

whether the state court will adequately protect the interests of the parties.” Id.
(quoting Spring City, 193 F.3d at 171). “No one factor is determinative[.]”
Colorado River, 424 U.S. at 818−19. Rather, courts should utilize “carefully

considered judgment taking into account both the obligation to exercise
jurisdiction and the combination of factors counseling against that exercise . . . .”
Id. “The balancing of factors is ‘heavily weighted in favor of the exercise of
jurisdiction.’” Nationwide Mut. Fire Ins. Co., 571 F.3d at 308 (quoting Moses H.

Cone Memorial Hosp. v. Mercury Constr. Corp., 460 U.S. 1, 16 (1983)).
In cases such as this, where the complaint seeks both declaratory and
injunctive relief, courts were previously split regarding whether the restrained

Colorado River approach or the more liberal Brillhart/Wilton approach is
appropriate. See Sumner v. Tompkins Ins. Agencies, Inc., No. 16-2218, 2016 U.S.
Dist. LEXIS 78379, at *17 (E.D. Pa. June 15, 2016) (noting that the Third Circuit

has not clarified the issue and that other circuits are “sharply divided”). The Third
Circuit has since resolved this split for our purposes and has determined that the
independent claim test is applicable to a complaint containing claims for both legal
and declaratory relief. Rarick v. Federated Serv. Ins. Co., 852 F.3d 223, 229 (3d

Cir. 2017). In order to apply this test, the Third Circuit has explained that:
a district court must determine whether the legal claims are independent
of the declaratory claims. If the legal claims are independent, the court
has a “virtually unflagging obligation” to hear those claims, subject of
course to Colorado River’s exceptional circumstances. Colo. River,
424 U.S. at 817−19. If the legal claims are dependent on the declaratory
claims, however, the court retains discretion to decline jurisdiction of
the entire action, consistent with our decision in Reifer, 751 F.3d at
144−46.

Id. The instant complaint requests both declaratory and injunctive relief.
Therefore, the complaint contains mixed claims to which the independent claim
test is applicable. See Hartford Ins. Co. v. Stead, 848 F. Supp. 2d 506, 511 n.1
(M.D. Pa. 2012) (“Coercive” claims refer to those “seeking compensatory damages
or injunctive relief.”) (quoting Perelman v. Perelman, 688 F. Supp. 2d 367, 372
(E.D. Pa. 2010)).
In the request for injunctive relief, Transource asks the court to enjoin the
PUC from bringing an enforcement action against Transource in the event that it

enters upon land in Pennsylvania to conduct environmental studies, surveys, and
exercise other rights held by Pennsylvania public utilities. (Doc. 76, pp. 29−34.)
In essence, Transource requests that the court restore the status quo before the PUC

issued its opinion and order denying Transource’s siting applications and revoking
its certificate of public convenience. (Id.) This claim for relief is inextricable from
the declaratory relief in this case because the court could not reasonably award the

injunctive relief sought without examining the merits of the declaratory judgment
claim for relief. In other words, without determining whether the PUC’s actions
violated constitutional law, the court could not order injunctive relief preventing
enforcement of the PUC’s order.

Thus, the court finds that the claims for declaratory and injunctive relief are
not independent from one another, and will proceed to apply the factors identified
in Reifer to determine whether it is appropriate to exercise discretion to decide all

of the claims in this case.
1. First Factor: The likelihood that a federal court declaration
will resolve the uncertainty of obligation which gave rise to the
controversy

With respect to the first factor for the court’s consideration, the Third Circuit
has recently explained that: “[t]he first Reifer factor is not intended to be a vehicle
for considering the effect of a declaratory judgment on the development of state
law.” DiAnoia’s Eatery, LLC v. Motorists Mut. Ins. Co., __ F.4th __, 2021 U.S.

App. LEXIS 24644, at *26 (3d Cir. Aug. 18, 2021). Rather, “the first Reifer factor
captures whether a declaration would bring about a ‘complete termination of the
controversy’ between the parties and thereby avoid duplicative, piecemeal

litigation.” Id. at *26−27. The Third Circuit has stated that a declaration from a
federal court will be unlikely to prevent further litigation “(1) when one or more
persons have not been joined, but have an interest in the outcome of the action, and

(2) when one or more issues have not been raised, but are a part of the controversy
or uncertainty.” Id. at *27.
In this case, a declaration from this court will not completely terminate the
litigation between the parties. This is because Transource has opted to raise legal

issues with this court, but also raise legal and factual issues with the
Commonwealth Court. While a declaration from this court would resolve the legal
issues presented for this court’s review, the issues raised on direct appeal with the

Commonwealth Court would remain pending. Transource has not expressed an
intent to abandon its appeal in the event that this court issues a favorable decision
before the Commonwealth Court issues its decision. Thus, the court finds that
“one or more issues have not been raised, but are a part of the controversy” that
will need to be resolved in the state court proceeding before this litigation can
conclude. Therefore, the first factor weighs in favor of abstention.

2. Second Factor: The convenience of the parties
The court finds that the second factor, the convenience of the parties, does
not weigh heavily in favor of exercising jurisdiction versus abstention in this case.

Transource appears to believe that it would be more convenient to litigate these
issues in this court based on its expressed preference to litigate its legal claims in a
federal forum and the perception that this court may provide a faster resolution
than the Commonwealth Court.15 (See Doc. 76, p. 10 (noting that Transource does

not wish to place its questions of federal law before the Commonwealth Court);
Doc. 80, p. 5 (noting that “the state court will not provide timely relief”)); see also
Pa. Commw. Ct. Docket No. 689 CD 2021 (denying expedited review). For their

part, Defendants argue that abstention would allow the parties to devote their full
attention to one case at a time. In other words, it would be more convenient for the
parties to only have to brief, argue, and generally manage one case in one court in

15 While the Commonwealth Court has denied Transource’s request for expedited relief, this
court has not yet ruled on Transource’s motion to expedite. (Doc. 21.) Therefore, there has been
no commitment from this court to resolve Transource’s weighty constitutional claims by
September 30, 2021, as requested by Transource. But, even if this court were to make a final
decision on the merits of Transource’s claims in its favor before September 30, 2021, it is
virtually impossible for Transource to meet its September 30, 2021 deadline to obtain all
required state permits. This is because Transource would be required to return to the PUC for
the agency to reconsider Transource’s siting applications and issue a new determination. The
court concludes that it is practically impossible to complete both steps by September 30, 2021.
a consolidated proceeding in which “all active parties in the proceedings before the
PUC have an opportunity as of right to intervene and fully participate in the state

proceeding,” rather than balancing two cases in two separate courts
simultaneously.16 (Doc. 78, p. 3.)
In addition to these arguments, the court notes that both the Commonwealth

Court and this court are located in Harrisburg, Pennsylvania. Therefore, there is
not a more convenient forum for either party based on the location of the tribunal.
On balance, considering the parties’ competing arguments, the court finds that this
factor is neutral with respect to the court’s abstention analysis.

3. Third Factor: The public interest in settlement of the
uncertainty of obligation

With respect to the third Reifer factor, the Third Circuit has stated that
“[w]here state law is uncertain or undetermined, the proper relationship between
federal and state courts requires district courts to ‘step back’ and be ‘particularly
reluctant’ to exercise [Declaratory Judgment Act] jurisdiction.” Reifer, 751 F.3d at
148 (quoting State Auto Ins. Cos. v. Summy, 234 F.3d 131, 135−36 (3d Cir. 2000)
(“[T]he state’s interest in resolving its own law must not be given short shrift
simply because one party or, indeed, both parties, perceive some advantage in the

16 Defendants also note that “[t]here is no equal right to intervene in this [c]ourt’s proceeding; in
fact, this [c]ourt has denied intervention to at least one party.” (Doc. 78, p. 3.) The court notes
that there is a pending appeal regarding this court’s order denying intervention to Franklin
County and Stop Transource Franklin County. (Doc. 77.)
federal forum.”)). Thus, the Third Circuit has expressed a preference for district
courts to “squarely address the alleged novelty” of the state law claims at issue, if

any. Id. at 149.
In this case, the court perceives novel questions of state law regarding the
following issues: (1) whether the PUC may question or reevaluate PJM’s regional

planning “need” determination when making a “need” determination under 52 PA.
CODE § 57.76(a)(1);17 and (2) whether the PUC’s “need” determination under 52
PA. CODE § 57.76 may conflict with PJM’s determination of “need” at the regional
planning level.18 The court recognizes that there is some degree of interplay

17 52 PA. CODE § 57.76 provides, in pertinent part, that:

The Commission will not grant the application, either as proposed or as modified,
unless it finds and determines as to the proposed [high voltage] line:

(1) That there is a need for it.

(2) That it will not create an unreasonable risk of danger to the health and
safety of the public.

(3) That it is in compliance with applicable statutes and regulations
providing for the protection of the natural resources of this Commonwealth.

(4) That it will have minimum adverse environmental impact, considering
the electric power needs of the public, the state of available technology and
the available alternatives.

52 PA. CODE § 57.76(a)(1)−(4).

18 The court notes that in its notice of appeal to the Commonwealth Court, Transource presents
substantially the same questions in its short statement of the relief sought: (1) whether “[t]he
PUC erred as a matter of law when it applied the incorrect legal standard under 66 Pa. C.S.
§ 1501 for determining whether the Project is needed;” and (2) whether “[t]he PUC erred as a
matter of law when it rejected the results of PJM’s FERC-approved process for evaluating
between state and federal law with respect to these questions. Indeed, Transource
would have this court phrase these questions differently: i.e., (1) whether the

PUC’s reevaluation of PJM’s determination of “need” at the regional planning
level when making a “need” determination under Pennsylvania law is preempted
by the Supremacy Clause and otherwise violates federal law; and (2) whether the

PUC’s “need” determination under 52 PA. CODE § 57.76 impermissibly conflicts
with PJM’s predetermined “need” finding under the regional planning process in
violation of federal law.
Regardless of how these questions are phrased, both federal and state law are

implicated. What is most important for purposes of the immediate issue under
discussion is that, on balance, Pennsylvania has the greater interest in resolving
this question under state law before this court is asked to apply federal

constitutional law. Specifically, the court observes that if the Commonwealth
Court determines, as a matter of state law, that the PUC is not permitted to
question or reevaluate PJM’s regional planning “need” determination when making
a “need” determination under section 57.76 of the Pennsylvania Code, the

Supremacy and Dormant Commerce Clause issues will be rendered moot.

market efficiency projects as insufficient evidence of need under Pennsylvania law[.]” (Doc.
78-1, p. 15.)
In addition, Transource has filed a direct appeal from the PUC to the
Commonwealth Court. Pennsylvania has a strong interest in maintaining the

uninterrupted progression of its administrative appeals process to resolve potential
constitutional violations, among other issues. Similarly, Pennsylvania has a strong
interest in siting concerns for high voltage transmission facilities. This interest is

represented and codified in federal regulations, which explicitly reserve siting
considerations to the states. See FERC Order 1000, 18 CFR Part 35, ¶ 107 (July
21, 2011) (“We acknowledge that there is longstanding state authority over certain
matters that are relevant to transmission planning and expansion, such as matters

relevant to siting, permitting, and construction. However, nothing in this Final
Rule involves an exercise of siting, permitting, and construction authority.”).
Indeed, Transource has not contested the fact that siting authority is within the

exclusive jurisdiction of the states. (Doc. 76, pp. 65−66.)
Finally, the court notes that the “Supreme Court has frequently counselled
that federal courts should presume ‘that the [state] statute will be construed in such

a way as to avoid the constitutional question presented,’ Baggett v. Bullitt, 377
U.S. 360, 375 (1964); see Siler v. Louisville & Nashville R. R. Co., 213 U.S. 175,
193 (1909), and that ‘state courts may be reluctant to attribute to their legislature
an intention to pass a statute raising constitutional problems, unless such legislative

intent is particularly clear[.]’” Finberg v. Sullivan, 634 F.2d 50, 69−70 (3d Cir.
1980) (citing Boehning v. Indiana State Employees Assn., Inc., 423 U.S. 6, 7 n.*
(1975) (per curiam)). Thus, the court finds that Pennsylvania has a strong and

significant interest in being the first to resolve any potential constitutional
violations before this court intervenes.
To be clear, the court is not foreclosing Transource’s ability to present its

federal constitutional questions before this court indefinitely. Rather, the court
finds that Pennsylvania Courts should be given the first opportunity to consider the
scope of its own law (52 PA. CODE § 57.76) in light of the interplay with federal
law before this court determines whether the PUC’s application of this particular

state law violates the federal constitution.
In light of these considerations, the court finds that the third Reifer factor
weighs in favor of abstention.

4. Fourth Factor: The availability and relative convenience of
other remedies

The court finds that the fourth factor, the availability and relative
convenience of other remedies, weighs slightly in favor of abstention in this case.
As explained above, Transource appears to believe that it would be more
convenient to litigate these issues in this court based on its expressed preference to
litigate its legal claims in a federal forum and the perception that this court may
provide a faster resolution than the Commonwealth Court.19 (See Doc. 76, p. 10
(noting that Transource does not wish to place its questions of federal law before

the Commonwealth Court)); see also Pa. Commw. Ct. Docket No. 689 CD 2021
(denying expedited review). However, Transource has conceded that the
Commonwealth Court has jurisdiction to hear its federal claims and Transource is

not precluded from litigating its federal claims in state court. (Doc. 76, pp. 10−11.)
Thus, Transource has another avenue available for pursuing its constitutional
issues. As acknowledged by Transource, the Commonwealth Court is perfectly

capable of applying the Supremacy and Dormant Commerce Clauses to this case.
(See id.)
The court also finds that the Commonwealth Court may be a more
convenient forum for the parties since, as explained above, they could consolidate

their litigation efforts before one court, rather than litigating two separate sets of
claims before two separate courts. Moreover, the Commonwealth Court is
“statutorily empowered” to review actions by Pennsylvania agencies and, as such,

is a specialty court uniquely suited to resolve appeals from PUC decisions. (Doc.
78, p. 4.) Therefore, based on these considerations, the court finds that this factor
weighs slightly in favor of abstention.

19 See footnote 15, supra.
5. Fifth Factor: The general policy of restraint when the same
issues are pending in a state court

The Third Circuit has clarified that the fifth Reifer factor’s “‘policy of
restraint’ is applicable only when the ‘same issues’ are pending in state court
between the same parties, not when the ‘same issues’ are merely the same legal
questions pending in any state proceeding.” DiAnoia’s Eatery, LLC, 2021 U.S.
App. LEXIS 24644, at *29−30 (citing Kelly, 868 F.3d at 289 (holding fifth factor

inapplicable where “issue of [insurer’s] obligations under its insurance policy with
[insured] is not pending in a state court” and “[insurer] is not even a party in the
pending state court action and the insurance coverage dispute cannot be fully
resolved without [insurer]”); Brillhart, 316 U.S. at 495 (“Ordinarily it would be

uneconomical as well as vexatious for a federal court to proceed in a declaratory
judgment suit where another suit is pending in a state court presenting the same
issues, not governed by federal law, between the same parties.”)).

In this case, Transource has indicated that it intends to “protectively brief”
the same issues raised in this court in its direct appeal to the Commonwealth Court
once a briefing schedule is set and it has the opportunity to file a brief. (Doc. 76,
p. 10.) Specifically, Plaintiff’s counsel indicated at oral argument that:

I want to be candid with the court, we haven’t filed our brief in that case
yet. I want to be candid with the court that we may sort of protectively
brief those issues in the state court given the arguments that the
commission has made about preclusion and this court’s inability to
decide the merits of them. We don’t want to be unable to present them
to any court. That wouldn’t be an appropriate outcome.

But right now they are not before the Pennsylvania court. We don’t
want to place them before the Pennsylvania court. We’ve reserved
them for this court’s adjudication pursuant to the England doctrine[.]

(Id.)20
The court finds the question of whether the “same issues” are pending in
both proceedings to be somewhat opaque. Transource has indicated its intent to
“protectively brief” the issues presented to this court before the Commonwealth
Court, but also notes that “right now[,] they are not before the Pennsylvania court.”
(Id.) In its notice of appeal to the Commonwealth Court, Transource indicated that
it seeks a determination from the Commonwealth Court that “[t]he PUC erred as a
matter of law when it applied the incorrect legal standard under 66 Pa. C.S. § 1501
for determining whether the Project is needed;” and “whether “[t]he PUC erred as
a matter of law when it rejected the results of PJM’s FERC-approved process for

evaluating market efficiency projects as insufficient evidence of need under

20 England v. Louisiana State Bd. of Medical Examiners, 375 U.S. 411 (1964). At a basic level,
the England doctrine is applicable “when a federal court abstains from deciding a federal
constitutional issue to enable the state courts to address an antecedent state-law issue[.]” San
Remo Hotel, L.P. v. City & County of San Francisco, 545 U.S. 323, 339 (2005). “[T]he plaintiff
may [then] reserve his right to return to federal court for the disposition of his federal claims.”
Id. At the time when Transource filed its direct appeal with the Commonwealth Court, the action
before this court had only been pending for a single day. Thus, this court had yet to issue a
determination regarding whether it would abstain from hearing Transource’s claims. The court
accordingly questions whether Transource prematurely raised the England doctrine in the
Commonwealth Court proceeding before this court decided whether to abstain.
Pennsylvania law[.]” (Doc. 78 1, p. 15.) As noted above, the court acknowledges
that the phrasing of the questions before the Commonwealth Court and those

presented to this court is distinct. But the court finds that it is a distinction without
a difference for purposes of this discussion. The same federal and state law
concerns are implicated regardless of how the issues are phrased. That fact, in

combination with Transource’s representation that it may “protectively brief” the
federal issues in the Commonwealth Court appeal, creates a distinct possibility that
both courts may essentially be asked to resolve the same issues (although the
Commonwealth Court is also being asked to resolve additional issues).

Based on this conclusion, the court finds that the general policy of restraint
when the same issues are pending in the state court weighs slightly in favor of
abstention in this case. The court recognizes that the application of this factor is

somewhat unclear in light of Transource’s mixed representations to the court about
whether it intends to argue the federal issues in the Commonwealth Court appeal.
Nevertheless, based on the status of both cases at this time, the court finds that the
same issues have at least been presented before both courts, and the general policy

of restraint tips slightly in favor of abstention.
6. Sixth Factor: Avoidance of duplicative litigation
For many of the same reasons as the fifth factor, the sixth Reifer factor

weighs in favor of abstention in this case. As explained above, Transource has
effectively presented the same issues to the Commonwealth Court in its direct
appeal that it has presented to this court. (See Doc. 76, pp. 7, 10.) Especially in

light of Transource’s potential protective briefing, there is a real concern that two
courts will be asked to decide the same issues of federal constitutional law.
Requesting that two courts perform the work that one could easily accomplish on

its own is “the very definition of vexatious, inefficient, and duplicative litigation.”
Nationwide Agribusiness Ins. Co. v. Sheriff, No. 1:14-cv-2082, 2015 U.S. Dist.
LEXIS 8968, at *13 (M.D. Pa. Jan. 27, 2015). Therefore, the court finds that this
factor weighs in favor of abstention.

7. Seventh Factor: Prevention of the use of the declaratory action
as a method of procedural fencing or as a means to provide
another forum in a race for res judicata

Likewise, the court finds that the seventh factor weighs especially strongly
in favor of abstention in this case. The court has concerns that it has been set up in
a “race” with the Commonwealth Court to determine which forum is able or
willing to provide faster relief to Transource. Indeed, at oral argument, Transource
indicated that “given where [the Commonwealth Court] case is . . . and given this -
- where this case is, . . . we’re hopeful that that eventuality wouldn’t occur where
the state court would reach judgment first.” (Doc. 76, pp. 11−12.) Transource also
expressed its appreciation for this court ordering “a quick schedule for briefing.”

(Id. at 11.) Since this litigation was initiated with this court, Transource has been
interested in obtaining relief as quickly as possible. While this court has not yet
ruled on Transource’s motion to expedite this case, it has set an expedited briefing

schedule and made an effort to resolve the threshold jurisdictional issues as quickly
as possible. The court also infers that Transource is displeased with the
Commonwealth Court’s denial of its request for expedited relief on July 14, 2021.

See Pa. Commw. Ct. Docket No. 689 CD 2021. While the court can understand
Transource’s desire for an expedited resolution of the significant issues that have
been presented to both courts, this court is neither compelled nor inclined to race
another court toward resolution of identical issues.21

Therefore, the seventh Reifer factor weighs heavily in favor of abstention.

21 Moreover, Transource acknowledged that although it can argue its constitutional questions
before the Commonwealth Court and the Commonwealth Court would have jurisdiction to hear
them, it would nonetheless prefer to have those issues resolved by a federal district court. (Doc.
76, pp. 10−11.) Indeed, Transource has explicitly stated that it does not want to place its
constitutional issues before the Commonwealth Court. (Id. at 10.) Yet, Transource has given no
explanation of why it does not wish to present its federal constitutional claims to the
Commonwealth Court, nor has Transource provided a convincing explanation of why this court
has a superior interest or ability to resolve these particular constitutional questions, which
implicate the scope of Pennsylvania law governing siting applications for high voltage
transmission lines and the PUC’s application of this law. The Supreme Court has noted that the
state courts are quite capable of adjudicating constitutional challenges to state agency decisions.
See, e.g., San Remo Hotel, 545 U.S. at 347 (observing that “[s]tate courts are fully competent to
adjudicate constitutional challenges to local land-use decisions”). Thus, the court views
Transource’s persistence in attempting to reserve its federal constitutional law claims for federal
court as additional evidence of Transource’s perception that this court will provide faster relief
than the Commonwealth Court. For the reasons listed in footnote 15, supra, the court rejects this
notion and construes it here in favor of abstention to avoid racing this court with the
Commonwealth Court.
8. Balancing
Taking all the Reifer factors together, the court notes that none weigh against

abstention in this case. Instead, the first, third, fourth, fifth, sixth, and seventh
factors weigh in favor of the court’s discretionary decision to abstain pending
resolution of the Commonwealth Court case, and the second factor is neutral.

Therefore, the court will, in the exercise of its discretion, abstain from further
action in this case until there is a final decision on the merits of Transource’s
appeal from the PUC’s adverse decision.
CONCLUSION

For the foregoing reasons, the motion to dismiss filed by Defendants, Doc.
57, will be DENIED in part with respect to Defendants’ arguments that Transource
lacks standing. Having determined that the court has jurisdiction over this lawsuit,

in the exercise of its discretion, the court will abstain from exercising its
jurisdiction until final resolution of the parallel Pennsylvania Commonwealth
Court proceeding at docket number 689 CD 2021. An appropriate order follows.
s/Jennifer P. Wilson
JENNIFER P. WILSON
United States District Court Judge
Middle District of Pennsylvania

Dated: August 26, 2021

---