# THORN FLATS, LLC v. BUILDPRO CONSTRUCTION LLC

> District Court, E.D. Pennsylvania · May 26, 2022

URL: https://www.frixlaw.com/law-library/cases/10403405

## Case

- **Court:** District Court, E.D. Pennsylvania
- **Decided:** May 26, 2022
- **Opinion:** 100trialcourt
- **Cited by:** 0 later opinions in the Frix Law Library

## Citator (automated)

- No negative treatment found by the automated citator. That is not the same as a confirmation that the case is good law; read the citing cases.
- Full citator and citing cases: https://www.frixlaw.com/law-library/cases/10403405

## Opinion text

IN THE UNITED STATES DISTRICT COURT
FOR THE EASTERN DISTRICT OF PENNSYLVANIA

THORN FLATS, LLC, CIVIL ACTION

Plaintiff,
NO. 21-5412-KSM
v.

BUILDPRO CONSTRUCTION LLC,

Defendant.

MEMORANDUM
MARSTON, J. May 26, 2022
This case involves a straightforward claim for breach of contract. For the reasons
discussed below, we grant Plaintiff Thorn Flats, LLC’s motion for default judgment.
BACKGROUND
Thorn Flats is a Delaware company that develops and leases luxury apartments. (Doc.
No. 1 at ¶ 1.) Between September 2020 and May 2021, Thorn Flats entered five work
authorization agreements with Defendant BuildPro Construction LLC, which named BuildPro as
general contractor for substantial renovation work at eight apartment buildings owned by Thorn
Flats. (Id. at ¶¶ 7–13.) In each work authorization, BuildPro agreed to “pay promptly all sums
due for labor, services, materials, tools, and equipment supplied in connection with the
performance of the Work.” (Id. at ¶ 14.) If BuildPro breached this or any other provision of the
agreement, Article 11 of each agreement authorized Thorn Flats, after adequate notice to
BuildPro, to “terminate this Agreement and take possession of all materials, tools and equipment
at the project.” (Id. at ¶ 16.) In addition, if the cost of completing the project exceeded any
unpaid balance to BuildPro, BuildPro would be obligated to “pay the difference . . . plus
damages, including attorneys’ fees.” (Id.)
On June 22, 2021, Thorn Flats notified BuildPro that it had breached the work
authorizations by “failing to pay its subcontractors and suppliers for work they had performed
and/or materials which they had supplied and for which BuildPro had received compensation

from Thorn Flats.” (Id. at ¶ 17.) When BuildPro failed to cure its breach, Thorn Flats pursued
its Article 11 rights and terminated the agreements. (Id. at ¶ 18.) Thorn Flats hired a new
contractor, and as a result “incur[red] additional costs, including the costs of completing
BuildPro’s work and paying subcontractors and suppliers directly for the work that Thorn Flats
had already paid BuildPro for, in an amount in excess of $100,000.” (Id. at ¶ 20.)
On December 10, 2021, Thorn Flats filed this action against BuildPro, asserting one
claim for breach of contract and one for breach of fiduciary duty/misappropriation of trust funds.
(See generally Doc. No. 1.) Thorn Flats timely served copies of the complaint and summons on
BuildPro’s agent. (Doc. No. 2.) When BuildPro failed to respond to the complaint, Thorn Flats

requested entry of default (Doc. No. 3), which the Clerk of Court entered on January 24, 2022.
Thorn Flats then moved for default judgment (Doc. No. 4), and the Court held a hearing on the
motion on May 2, 2022 (Doc. No. 5). BuildPro did not appear at the hearing.
DEFAULT JUDGMENT
“After a clerk enters default pursuant to Federal Rule of Civil Procedure 55(a) against a
party that has ‘failed to plead or otherwise defend’ an actison, the party may be subject to entry
of a default judgment.” Serv. Emps. Int’l Union v. ShamrockClean Inc., 325 F. Supp. 3d 631,
634 (E.D. Pa 2018) (quoting Fed. R. Civ. P. 55(a)). The clerk may enter default judgment in a
plaintiff’s favor if “the plaintiff’s claim is for a sum certain or a sum that can be made certain by
computation.” Fed. R. Civ. P. 55(b)(1). “In all other cases, the party must apply to the court for
a default judgment.” Fed. R. Civ. P. 55(b)(2).
Where a party moves for default judgment, the court evaluates the following three
factors: “(1) prejudice to the plaintiff if default is denied, (2) whether the defendant appears to
have a litigable defense, and (3) whether defendant’s delay is due to culpable conduct.”

Chamberlain v. Giampapa, 210 F.3d 154, 164 (3d Cir. 2000); see also, e.g., Int’l Union of
Operating Eng’rs v. N. Abbonizio Contractors, 134 F. Supp. 3d 862, 865 (E.D. Pa. 2015). In
evaluating these factors, the court accepts as true all factual allegations in the complaint, except
those related to damages. Serv. Emps. Int’l Union, 325 F. Supp. 3d at 635. However, “a party in
default does not admit mere conclusions of law,” so before considering the Chamberlain factors,
we begin by considering “whether the unchallenged facts constitute a legitimate cause of action.”
Id. (quotation marks omitted).
A. Cause of Action
Thorn Flats has stated a claim for breach of contract.1 “‘Breach of contract is a claim
with three elements: [1] a contractual obligation; [2] a breach of that obligation by the

defendant; and [3] a resulting damage to the plaintiff.’” Humanigen, Inc. v. Savant Neglected
Diseases, LLC, 238 A.3d 194, 202 (Del. Super. Ct. 2020) (quoting Connelly v. State Farm Mut.
Auto Ins. Co., 135 A.3d 1271, 1279 n.28 (Del. 2016)).2 Each element is satisfied here. Thorn

1 Because Thorn Flats seeks the same damages under Count I and Count II, and we find it has
stated a claim for breach of contract, we need not analyze whether Thorn Flats has also stated a claim for
breach of fiduciary duty.
2 Each work authorization includes a jurisdiction and venue provision, which states that the
“Agreement shall be governed by the laws of the jurisdiction in which the Project is located.” (See, e.g.,
Doc. No. 1-1 at p. 7, Article 18; Doc. No. 1-2 at p. 6, Article 18; Doc. No. 1-3 at p. 6, Article 18; Doc.
No. 1-4 at p. 7, Article 18; Doc. No. 1-5 at p. 6, Article 18.) Each project was located in Newark,
Delaware, so Delaware law controls. (See, e.g., Doc. No. 1-1 at p. 2; Doc. No. 1-2 at p. 2; Doc. No. 1-3 at
p. 2; Doc. No. 1-4 at p. 2; Doc. No. 1-5 at p. 2.)
Flats submitted copies of the five work authorizations, which outline BuildPro’s obligation to
pay subcontractors and suppliers. (Doc. No. 1-1 at p. 6, Article 10; Doc. No. 1-2 at p. 5, Article
10; Doc. No. 1-3 at p. 5, Article 10; Doc. No. 1-4 at p. 6, Article 10; Doc. No. 1-5 at p. 5, Article
10.) BuildPro breached the agreements in June 2021 when it failed to pay its subcontractors and
suppliers. (Doc. No. 1 at ¶ 17.) As a result, Thorn Flats incurred costs hiring another contractor

to complete the projects and “paying subcontractors and suppliers directly for work that Thorn
Flats had already paid BuildPro for.” (Id. at ¶ 19.)
B. Chamberlain Factors
Having found that Thorn Flats states a legitimate cause of action for breach of contract,
we turn to the Chamberlain factors and find that they weigh in favor of granting default
judgment in this case. First, Thorn Flats will be prejudiced if default judgment is denied because
Thorn Flats paid $100,000 to the subcontractor that BuildPro failed to pay—an amount Thorn
Flats had already paid once to BuildPro. Denying default judgment would leave Thorn Flats on
the hook twice. See Serv. Emps. Int’l Union, 325 F. Supp. 3d at 637 (“First, Plaintiffs will
certainly be prejudiced if default judgment is denied, as Plaintiffs have not yet received the

withdrawal liability that they are owed.”); Trustees of the Nat’l. Elevator Indus. Pension Plan v.
Universal Elevator Corp., Civil Action No. 11–3381, 2011 WL 5341008 at *3 (E.D. Pa. Nov. 3,
2011) (“Clearly, Plaintiffs will suffer prejudice if this Court denies their motion for default
judgment; Plaintiffs are not receiving payments owed them.”). In addition, “declining to enter
default judgment would prejudice [Thorn Flats] because [BuildPro’s] default has prevented [it]
from litigating this matter and [it] will not be able to recover the delinquent contributions and
other liabilities [it is] due absent the entry of default judgment.” Trustees of Nat’l Electrical
Benefit Fund v. Mirarchi Bros., CIVIL ACTION NO. 21-4399-KSM, 2022 WL 221610, at *4
(E.D. Pa. Jan. 24, 2022).
Second, BuildPro does not appear to have a litigable defense. As discussed above, Thorn
Flats’s allegations establish a cause of action for breach of contract. Because BuildPro has not
filed an answer, there are no facts to suggest that Thorn Flats is not entitled to reimbursement for
the amounts it was forced to pay BuildPro’s subcontractors and suppliers. (Id. at p. 2 ¶ 8.) See
Acosta v. Schwab, No. 5:18-CV-3544, 2019 WL 7046916 at *8 (E.D. Pa. Dec. 20, 2019)

(citations omitted) (explaining that the court may “presume that an absent defendant who has
failed to answer has no meritorious defense . . . because [i]t is not the court’s responsibility to
research the law and construct the parties’ arguments for them” (cleaned up)); cf. Stevens v.
Wiggins, Civ. A. No. 90-7038, 1991 WL 152960, at *2 (E.D. Pa. Aug. 6, 1991) (“A defendant
establishes a meritorious defense when the defendant’s answer, if established at trial, would
constitute a complete defense to the action.” (quotation marks omitted)).
Third, the Court finds that BuildPro’s delay is due to its own culpable conduct.
BuildPro’s authorized agent received the complaint and summons as well as the motion for
default judgment, but the company has knowingly decided not to enter an appearance or

otherwise defend itself in this case. See Kelly M. v. Luzerne Intermediate Unit, 71 F. App’x 116,
118 (3d Cir. 2003) (“Jerrytone’s conduct in failing to respond to the several personal notices he
received from plaintiffs’ counsel or to appear at several hearings was culpable.”); Serv. Emps.
Int’l Union, 325 F. Supp. 3d at 637 (explaining that “culpable conduct” refers to conduct “taken
willfully or in bad faith,” and finding that “Defendant’s failure to respond to the complaint and
failure to attend the hearing were both ‘willful,’ in the sense that Defendant accepted service of
the complaint and the order setting the hearing and therefore was aware of the complaint and the
hearing” but still failed to appear or otherwise respond to the complaint); cf. Spurio, 880 F. Supp.
at 405 (finding no culpable conduct where the record “contain[ed] no evidence that defendant’s
two-day delay was intentionally dilatory or otherwise in bad faith”). Indeed, during the hearing,
Plaintiffs’ counsel confirmed that BuildPro has refused to answer her telephone calls and one
time, BuildPro’s representative actually hung up on her and a representative for Thorn Flats once
BuildPro’s representative realized who was calling. (See H’rg. Tr.; see also Doc. No. 9
(Plaintiffs’ counsel confirming that the subcontractor’s counsel has likewise been unable to reach

BuildPro).)
Because Thorn Flats has stated a cause of action for breach of contract and the
Chamberlain factors weigh in its favor, default judgment is appropriate.
DAMAGES
“Having determined that [Thorn Flats is] entitled to entry of default judgment, the Court
must calculate the proper amount of damages . . . .” Serv. Emps. Int’l Union, 325 F. Supp. 3d at
637. Thorn Flats seeks to recover $100,000, along with pre- and post-judgment interest,
attorneys’ fees, and costs. (See Doc. No. 4 at ¶ 6.). We address each amount in turn.
A. Compensatory Damages
First, Thorn Flats seeks $100,000 as compensation for the breach of contract. (Doc. No.
4 at ¶ 6.) At default judgment, the court must “calculate the appropriate amount of damages[ ]

and need not accept the plaintiff’s representations on damages as true.” Tristrata Tech, Inc. v.
Med. Skin Therapy Research, Inc., 270 F.R.D. 161, 165 (D. Del. 2010) (quoting Christ v.
Cormick, C.A., Nos. 06-275-GMS, 07-060-GMS, 2008 WL 4889127, at *1 (D. Del. Nov. 10,
2008)). “In a breach of contract case, the amount of damages a plaintiff is entitled to is measured
by what is necessary to place the plaintiff in the same position that he would have been in if the
contract had been performed.” U.S. for Use of Endicott Enters. Inc. v. Star Brite Const. Co., 848
F. Supp. 1161, 1169 (D. Del. 1994).
Here, Thorn Flats claims in its complaint that it incurred damages in “an amount well in
excess of $100,000” when it had to hire another contractor to finish the projects and paid
“subcontractors and suppliers directly for work,” for which “Thorn Flats had already paid
BuildPro.” (Doc. No. 1 at ¶ 19.) Consistent with this allegation, Thorn Flats seeks
compensatory damages of $100,000. (Doc. No. 4 at ¶ 6.) During the default judgment hearing

and in supplemental filings, Plaintiffs’ counsel confirmed that “the $100,00 sought in the
complaint is for monies paid to [the subcontractor] through a negotiated settlement.” (Doc.
No. 9 at p. 2.) This is sufficient. See Levitation Arts, Inc. v. Plox, Inc., C.A. No. 17-1476-MN,
2020 WL 2730905, at *2–3 (D. Del. May 26, 2020) (finding that “Plaintiff’s request for
$289,575.00 is appropriate and supported by the record”); Ascendia USA, Inc. v. AdvancePost,
Inc., No. 1:12–cv–2169, 2013 WL 877132, at *2 (M.D. Pa. Mar. 8, 2013) (“Plaintiff has
supported the requested amount of damages, save for the amount of attorney’s fees, with exhibits
and an affidavit.”).
We grant Thorn Flats’s request for an award of $100,000 in compensatory damages.

B. Interest
Next, we analyze Thorn Flats’s request for pre- and post-judgment interest.
“Under Delaware law, a party is entitled to prejudgment interest when the amount of
damage is calculable, and such interest has been awarded in breach of contract cases.” U.S. for
Use of Endicott Enters. Inc., 848 F. Supp. at 1169; cf. Brandywine Smyrna, Inc. v. Millennium
Builders, LLC, 34 A.3d 482, 487 (Del. 2011) (“[P]rejudgment interest in Delaware cases is
awarded as a matter of right[.]”). “[P]re-judgment interest ‘accumulates from the date payment
was due to the plaintiff, because full compensation requires an allowance for the detention of the
compensation awarded and interest is used as a basis for measuring that allowance.’” Jewell v.
Miller, Civil Action No. 21-324-MN, 2021 WL 3510771, at *3 (D. Del. July 2, 2021) (quoting
Brandywine Smyrna, Inc. v. Millenium Builders, LLC, 34 A.3d 482, 486 (Del. 2011)). When, as
here, the contract does not provide an interest rate, a statutory interest rate applies, Enzo Life
Sciences, Inc. v. Adipogen Corp., 82 F. Supp. 3d 568, 607 (D. Del. 2015) (citing 6 Del. Code
§ 2301(a)); U.S. for Use of Endicott Enters. Inc., 848 F. Supp. at 1169 (same), and it sets “the
legal rate of interest” at “5% over the Federal Reserve discount rate including any surcharge as

of the time from which interest is due,” 6 Del. Code § 2301(a). The Federal Reserve discount
rate was 0.25% in June 2021, when BuildPro breached the contract.3 Therefore, Thorn Flats is
entitled to pre-judgment interest at a rate of 5.25%.
As for post-judgment interest, because it will accrue on a federal judgment, we look to
federal law to determine whether Thorn Flats is entitled to interest. Federal law provides that
“[i]nterest shall be allowed on any money judgment in a civil case recovered in a district court.”
28 U.S.C. § 1961(a). Post-judgment interest is “calculated from the date of the entry of the
judgment, at a rate equal to the weekly average 1-year constant maturity Treasury yield, as
published by the Board of Governors of the Federal Reserve System, for the calendar week

preceding[ ] the date of the judgment.” Id. Therefore, Thorn Flats is entitled to post-judgment
interest at a rate of 2.11%.4
C. Attorneys’ Fees and Costs
Last, we turn to Thorn Flats’s request for attorneys’ fees and costs.
Thorn Flats is entitled to attorneys’ fees under Article 11 of each work authorization. As
of May 2, 2022, Thorn Flats had incurred $19,327.56 in attorneys’ fees and $546.80 costs. (Doc.

3 The Federal Reserve publishes current and historical discount rates online at
https://www.frbdiscountwindow.org/pages/discount-rates (last visited Apr. 28, 2022).
4 This rate can be found online at
https://www.federalreserve.gov/datadownload/Preview.aspx?pi=400&rel=H15&preview=H15/H15/RIFL
GFCY01_N.WF (last visited May 26, 2022).
No. 6 at ¶ 7; Doc. No. 4 at ¶ 2; Doc. No. 9 at ¶ 5.) To support its request for fees, Thorn Flats
submitted affidavits by lead attorney, Margaret England, along with copies of all invoices paid
by Thorn Flats to date. (Doc. No. 6-1; Doc. No. 9.) Those invoices show that five individuals at
the law firm Gellert, Scali, Busenkell & Brown worked on the case: Charles J. Brown III
(Partner; hourly rate $425), Margaret F. England (Of Counsel; hourly rate $375), Bradley P.

Lehman (Associate; hourly rate $310), Richard Bennett (Paraprofessional; hourly rate $130),
Ashley P. Gollmann (Paraprofessional; hourly rate $160). (See Doc. No. 6-1; Doc. No. 9 at
¶¶ 6–11.) Collectively, they worked more than 58 billable hours. (See Doc. No. 6-1; Doc. No. 9
at pp. 11–12.) England’s affidavit gives each individual’s position and level of experience and
testifies that the “hourly fee charged for services” is the law firm’s “standard rate for legal work
related to contract and lien law and is competitive in both the State of Delaware and the
Commonwealth of Pennsylvania.” (Doc. No. 9.) During the default judgment hearing, England
also explained that the firm has spent a significant number of hours on this matter because she
and her colleagues not only pursued this case but also negotiated the settlement with the

subcontractor and have repeatedly (and unsuccessfully) tried to contact BuildPro.
The Court finds the proposed award for attorneys’ fees and costs reasonable and grants
Thorn Flats’ request for $19,874.36 in fees and costs.
CONCLUSION
Because Thorn Flats has stated a legitimate cause of action for breach of contract, and the
Chamberlain factors weigh in favor of granting default judgment, Thorn Flats’s motion is
granted, and judgment is entered in favor of Thorn Flats in the amount of $100,000, plus pre- and
post-judgment interest, and $19,874.36 in fees and costs.
An appropriate order follows.

---