# Florida Gas Transmission Company, LLC v. 0.401 Acres of Land in Putnam County, Florida

> District Court, M.D. Florida · July 1, 2021

URL: https://www.frixlaw.com/law-library/cases/10107846

## Case

- **Court:** District Court, M.D. Florida
- **Decided:** July 1, 2021
- **Opinion:** 100trialcourt
- **Cited by:** 0 later opinions in the Frix Law Library

## Citator (automated)

- No negative treatment found by the automated citator. That is not the same as a confirmation that the case is good law; read the citing cases.
- Full citator and citing cases: https://www.frixlaw.com/law-library/cases/10107846

## How later opinions describe it (automated extraction)

- finding that a security bond equal to twice the appraised value of the easements was adequate security under Rule 65(c)
- finding pipeline project served public interest because it would make gas available to consumers and electric power plants, as well as help local communities to attract new business
- observing the financial strength of the gas company and its parent corporation would enable payment if the security fell short

## Opinion text

UNITED STATES DISTRICT COURT
MIDDLE DISTRICT OF FLORIDA
JACKSONVILLE DIVISION

FLORIDA GAS TRANSMISSION
COMPANY, LLC,

Plaintiff, Case No.
3:21-cv-00230-MMH-JRK
vs.
Tract Nos:
+/- 0.401 ACRES OF LAND IN PUTNAM FLMED-PUTN-011.00
COUNTY, FLORIDA, UNKNOWN HEIRS
AND BENEFICIARIES OF THE ESTATE OF
AARON L. DAVIS, et al.,

Defendants.
_____________________________________/

ORDER

This cause is before the Court on Plaintiff’s Motion for Partial Summary
Judgment (Doc. 4) and Motion for Preliminary Injunction for Immediate
Possession (Doc. 5). As it pertains to Defendants, UNKNOWN HEIRS AND
BENEFICIARIES OF THE ESTATE OF AARON L. DAVIS, ROSE DAVIS,
CORENNE BROWN, TOMMIE L. DAVIS, AARON DAVIS, JR., CARL DAVIS,
CHARLES DAVIS, CARRIE O’NEAL, ANNIE SIMMONS, RUTH WORTHEN,
ALENE BRYANT, ALZETA DUGGAN a/k/a ALZETA LUCAS, JANET
HAMPTON a/k/a JANET RAMOS, JANICE MORTIMER, CYNTHIA BERRY,
PEARLIE MAE WHITE DAVIS, TIMOTHY DAVIS, and UNKNOWN
OWNERS, IF ANY (collectively, the “Defendants”), for the reasons discussed
herein, the Court grants both Motions.
I. Background

On March 19, 2020, the Federal Energy Regulatory Commission
(“FERC”) issued an order which, among other things, granted Plaintiff, Florida
Gas Transmission Company, LLC (“FGT”) a Certificate of Public Convenience
and Necessity (“FERC Certificate”) under the Natural Gas Act (“NGA”), 15

U.S.C. § 717f. The FERC Certificate authorizes FGT to construct and operate
the Putnam Expansion Project (“Project”), which is an interstate natural gas
pipeline. FGT filed this condemnation action against these Defendants and
others to acquire the Subject Easements necessary to complete the Project.

FGT personally served the following Defendants pursuant to Rule
71.1(d)(3)(A) and Rule 4, Federal Rules of Civil Procedure (“Rule(s)”): Rose
Davis, on March 11, 2021 (Doc. 15); Carrie O’Neal, on March 22, 2021 (Doc.
17); Corenne Brown, on March 16, 2021 (Doc. 14); Charles Davis, on March 16,

2021 (Doc. 19); Ruth Worthen, on March 17, 2021 (Doc. 16); Alzeta Duggan
a/k/a Alzeta Lucas, on March 17, 2021 (Doc. 13); and Janet Hampton a/k/a
Janet Ramos, on March 16, 2021 (Doc. 20). Additionally, on April 1, 2021, April
8, 2021, and April 15, 2021, FGT effectuated service by publication, pursuant

to Rule 71.1(d)(3)(B), on the following Defendants: Unknown Heirs and
Beneficiaries of The Estate of Aaron L. Davis, Tommie L. Davis, Aaron Davis,
Jr., Carl Davis, Annie Simmons, Alene Bryant, Janice Mortimer, Cynthia
Berry, Pearlie Mae White Davis, Timothy Davis, and Unknown Owners, if any.
(Doc. 36).

To date, none of the Defendants have responded to the Complaint or the
Motions, nor did any appear at the hearing on the Motions held by this Court
on June 2, 2021, despite due notice.
Having reviewed the record, the Court makes the following findings of

fact and conclusions of law:
II. Partial Summary Judgment – Federal Power to Condemn

A. Findings of Fact

1. FGT requests that this Court enter an order of partial summary
judgment establishing FGT’s right to condemn the Subject Easements.
2. On March 19, 2020, FERC issued an Order granting FGT a
FERC Certificate that authorizes FGT to construct and operate the Project
(Doc. 1-5; Doc. 6, ¶ 9; Doc. 6-2; Doc. 7, ¶ 9; Doc. 7-2).
3. To construct and operate the Project in accordance with the
FERC Certificate, FGT must acquire the Subject Easements described in
Exhibit 2 to the Complaint (Doc. 1-3), and attached as Exhibit A to this Order,
which are located within the jurisdiction of this Court.

4. As part of the certification process, FGT submitted, and FERC
approved, “alignment sheets” showing the final alignment of the Project and
that the Subject Easements are necessary for the construction of the Putnam
Expansion Project.
5. FGT prepared the Subject Easements, a copy of which is

attached to this Order and to Exhibit 2 to the Complaint, to conform with the
FERC-approved alignment sheets. (Doc. 1-3 & Doc. 8, ¶ 10).
6. FGT has communicated with known owners and made offers in
an attempt to purchase the Subject Easements. (Doc. 8, ¶ 11).

7. FGT was unable to acquire the Subject Easements by contract.
(Doc. 8, ¶ 13).
B. Conclusions of Law

8. A district court “shall grant summary judgment if the movant
shows that there is no genuine dispute as to any material fact and the movant
is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a).
9. Congress enacted the NGA to regulate the interstate
transportation and sale of natural gas for resale to the public for domestic,

commercial, industrial or any other use. As such, the NGA governs the Project.
The pertinent section of the NGA provides as follows:
When any holder of a certificate of public convenience and necessity
cannot acquire by contract, or is unable to agree with the owner of
property to the compensation to be paid for, the necessary right-of-way
to construct, operate, and maintain a pipe line or pipe lines for the
transportation of natural gas, and the necessary land or other property,
in addition to right-of-way, for the location of compressor stations,
pressure apparatus, or other stations or equipment necessary to the
proper operation of such pipe line or pipe lines, it may acquire the same
by the exercise of the right of eminent domain in the district court of the
United States for the district in which such property may be located. . .
Provided, That the United States district courts shall only have
jurisdiction of cases when the amount claimed by the owner of the
property to be condemned exceeds $3,000.

15 U.S.C. § 717f(h) (2016).1
10. The NGA authorizes a party to exercise the federal power of
eminent domain to acquire property necessary for an interstate natural gas
pipeline project when: (1) the plaintiff holds a FERC Certificate authorizing a
project; (2) FERC has determined that the property is necessary for the project;
and (3) the plaintiff is unable to acquire the property by contract.
Transcontinental Gas Pipe Line Co., LLC v. 6.04 Acres of Land, 910 F.3d 1130,
1154 (11th Cir. 2018); see also Sabal Trail Trans., LLC v. 9.669 Acres of Land

in Polk County, Fla., No. 8:16-cv-640-T-33AEP, 2016 WL 2745082, at *3 (M.D.
Fla. May 11, 2016) (citing Columbia Gas Trans., LLC v. 1.01 Acres, More or
Less, in Penn Twp., York City, Pa., 768 F.3d 300, 304 (3d Cir. 2014)).
11. The undisputed record establishes that FGT has satisfied each

condition precedent necessary to condemn the Subject Easements under the
pertinent section of the NGA: (1) FGT holds a FERC Certificate authorizing
the Project; (2) FERC has determined that the Subject Easements are
necessary for the Project; and (3) FGT has been unable to acquire the Subject

Easements by contract.

1 FGT offered to purchase the Subject Easements from known owners for at least $3,000
and the known owners rejected such offers, supporting the inference that the owners claim
the Subject Easements to be worth more than $3,000.
12. District courts have limited jurisdiction in NGA condemnation
actions. “[T]he role of the district court in Natural Gas Act eminent domain

cases extends solely to examining the scope of the certificate and ordering the
condemnation of property as authorized in that certificate.” Columbia Gas
Trans. Corp. v. An Easement to Construct, Operate & Maintain a 24-Inch
Pipeline, No. 5:07CV04009, 2008 WL 2439889, at *2 (W.D. Va. June 9, 2008).

The condemnation action “does not provide challengers with an additional
forum to attack the substance and validity of a FERC order. The district court’s
function under the statute is not appellate but, rather, to provide for
enforcement.” Sabal Trail, 2016 WL 2745082, at *3 (quoting Williams Natural

Gas Co. v. City of Oklahoma City, 890 F.2d 255, 264 (10th Cir. 1989), cert.
denied, 497 U.S. 1003 (1990)).2
“The District Court’s sole charge and authority is to evaluate the scope
of the FERC Certificate, and order the condemnation of property in
accordance with that scope.” Steckman Ridge GP, LLC, v. An Exclusive
Nat. Gas Storage Easement Beneath 11.078 Acres, More or Less, in
Monroe Twp., et al., Nos. 08-168, et al., 2008 WL 4346405, at *3 (W.D.
Pa. Sept. 19, 2008) (citations omitted).

Sabal Trail, 2016 WL 2745082, at *3.

13. Thus, this Court finds that the NGA authorizes FGT to exercise

2 As the Eleventh Circuit stated in Transcontinental Gas, to defeat the “right to condemn
property that was depicted on FERC-approved alignment sheets,” “Defendants would have
had to make its [sic] challenge to FERC’s chosen right-of-way before FERC in the first
instance, subject to review by this Court or the D.C. Circuit on a party’s petition for review.”
910 F.3d at 1156.
the power of eminent domain. FGT has the right to condemn the Subject
Easements identified in the Complaint (Doc. 1-3) and the Notice of

Condemnation (Doc. 2-1). The Subject Easements are described in Exhibit A to
this Order.
III. Preliminary Injunction and Possession

A. Findings of Fact

14. FGT also requests that the Court issue a preliminary injunction
granting it immediate possession of the Subject Easements in order to begin
pre-construction and construction activities.
15. The FERC Certificate authorizes the construction and operation
of the Project on its specified terms and conditions. (Doc. 1-5, ¶ 36(B)). FERC
found that the “…Putnam Expansion Project will not adversely affect FGT’s
existing customers as the project is designed to provide the new service while
maintaining existing services. Further, there will be no adverse impact on

other pipelines in the region or their captive customers; the proposal is
designed to meet the new incremental demand from Seminole Electric and is
not designed to replace existing service on other pipelines.” (Doc. 1-5, ¶ 13).
16. The purpose of the Project is to provide additional supplies of

natural gas to Seminole Electric for its new gas-fired, combined-cycle
generating unit and its power generation needs. Upon completion, the Project
will enable FGT to transport 169,000 dekatherms of natural gas per day for
Seminole Electric to the new FGT/SeaCoast Gas Transmission, LLC
(SeaCoast) delivery point in Putnam County. (Id., ¶ 5).

17. In connection with the Project, on April 5, 2018, FGT and
Seminole Electric entered into a Precedent Agreement whereby FGT has
agreed to provide 169,000 dekatherms per day of firm transportation service
for Seminole Electric to the new FGT/SeaCoast Gas Transmission, LLC

delivery point in Putnam County. FGT and Seminole Electric have agreed to
an in-service date of April 1, 2022. (Id., ¶ 5).
18. For the Project, FGT will be (i) constructing approximately 13.7
miles of 30-inch diameter pipeline loop (the “West Loop”) from approximately

Mile Post (“MP”) 521.3 in Columbia County to approximately MP 535.0 in
Union County, which will parallel FGT’s existing 30-inch and 24-inch diameter
mainlines; (ii) constructing approximately 7.0 miles of 30-inch diameter
pipeline loop (the “East Loop”) from approximately MP 574.8 in Clay County

to approximately MP 581.8 in Putnam County, paralleling FGT’s existing 26-
inch and 24-inch diameter mainlines; (iii) relocating two pig receiver stations,
one from Columbia County to Union County and the other from Clay County
to Putnam County; and (iv) modifying existing Compressor Station 18 in

Orange County, Florida to allow for one unit at the station to have bi-
directional gas flow capability into the existing mainline. (Doc. 6, ¶ 11; Doc. 7,
¶ 11).
19. The nature of the Project requires extensive construction along
several segments of the Project in a specified order. (Id., ¶¶ 14-15). A delay in

the acquisition of the easements for one property will delay the entire project
as a result of the linear construction method used for pipeline construction,
and will result in significant unrecoverable costs to FGT. (Id. ¶¶ 21-23). The
process is comparable to an assembly line, with specialized teams following

each other down the right of way, successively performing tasks such as
staking and fencing, clearing and grading, pipe stringing, welding, trenching,
lowering-in and backfilling, hydrostatic testing, clean-up and restoration, and
commissioning. (Id. ¶ 15).

20. On February 2, 2021, FERC issued the Notice to Proceed with
Construction for the Putnam Expansion Project, authorizing FGT to begin
construction activities. (Id., ¶ 10, Exh. C).
21. FGT must begin pre-construction activities as soon as possible.

This Project requires a complex and coordinated construction process, with
work activities being performed in sequential phases. To mitigate construction
risks that threaten FGT’s ability to meet the in-service date of April 1, 2022
(including, but not limited to, potential construction risks associated with

installation methods, possible unexpected groundwater conditions, weather
delays, and force majeure events such as tropical storms and hurricanes), FGT
needs to begin construction on the Project in Clay, Columbia, Putnam, and
Union Counties by August 1, 2021. (Id., ¶ 13-14).
22. FGT must take immediate possession to perform pre-

construction activities in order to start construction on August 1, 2021, and to
meet the in-service date of April 1, 2022. To timely commence and complete
the Project, it is critical that FGT provide its contractors with immediate access
to all properties within the spread. Construction has been planned so that

there will not be conflicting activities occurring at any location along the
FERC-authorized route. Thus, FGT’s inability to enter even a single parcel as
soon as possible could have a domino effect and delay completion of the entire
Project. (Id., ¶ 19). In addition to the pre-construction activities, FGT’s

contractors need access to the authorized construction areas to mobilize
equipment and resources in order to begin the construction and installation
activities by August 1, 2021. (Id., ¶ 20).
23. If FGT’s contractors cannot begin construction by August 1, 2021,

the unrecoverable delay costs that FGT will incur on a daily basis are
significant, and the cumulative effect could be exorbitant. (Id., ¶ 21).
Specifically, if construction of the pipeline facilities in Florida is delayed just
one week beyond August 1, 2021, FGT would incur $1,896,000.00 in delay costs

per week. (Id.).
24. Once construction begins, FGT will be liable to its contractor
for any delays that occur if a contractor cannot access a property in sequential
order. Neither delaying the start of the Project nor halting construction upon
reaching an unresolved parcel are tenable options, as either event would delay

completion of the Project indefinitely, and involve significant costs as detailed
in the Declaration of Adam Broad and the Declaration of Diego Aponte. (Id.,
¶¶ 21-23). The “move around” option would disrupt the efficient, linear
workflow previously described and delay completion of the Project for at least

as long as it takes to acquire the necessary easement interests. Moreover, each
such “move around” is costly. (Id., ¶ 23). In that event, FGT will incur delay
costs that are estimated to range between $20,000.00 and $316,000.00 per day.
(Id., ¶ 22).

25. If FGT is delayed in its construction of the Project and is unable
to meet the in-service date, FGT will suffer damage to its reputation and
business goodwill that cannot be reasonably calculated. (Id. at ¶ 24).
B. Conclusions of Law

26. It is well established that granting immediate possession of
property through a preliminary injunction is appropriate where a pipeline
company holds a valid FERC Certificate, a court has entered an order
establishing the pipeline company’s right to condemn the necessary easements,

and the pipeline company has satisfied the standard for injunctive relief. See,
e.g., Transcon. Gas Pipe Line, 910 F.3d at 1153; E. Tenn. Nat. Gas Co. v. Sage,
361 F.3d 808, 828 (4th Cir. 2004) (“Sage”), cert. denied, 543 U.S. 978 (2004);
Alliance Pipeline, LP, v. 4.360 Acres, 746 F.3d 362, 368-69 (8th Cir. 2014), cert.
denied, 135 S. Ct. 245 (2014); Columbia Gas Trans., 768 F.3d at 315-16.

27. In the Eleventh Circuit, as in other circuits, a party satisfies the
standard for injunctive relief and is “entitled to a preliminary injunction if it
show[s]: ‘(1) a substantial likelihood of success on the merits; (2) that
irreparable injury will be suffered unless the injunction is issued; (3) the

threatened injury to the moving party outweighs whatever damage the
proposed injunction might cause the non-moving party; and (4) if issued, the
injunction would not be adverse to the public interest.’” Jysk Bed’N Linen v.
Dutta-Roy, 810 F.3d 767, 774 (11th Cir. 2015) (citations omitted).

28. By granting FGT’s Motion for Partial Summary Judgment as to
these Defendants, this Court has determined FGT has the right to condemn
the Subject Easements. Accordingly, there is a substantial likelihood that FGT
will prevail on the merits.

29. FGT will suffer irreparable injury if the requested preliminary
injunction is not granted. Economic harm is considered irreparable where, as
here, there is no adequate remedy at law to recover damages for the harm
suffered. Transcon. Gas, 910 F.3d at 1165–66. The Eleventh Circuit has found

such irreparable harm based on the declarations of pipeline representatives
attesting that the pipeline company would incur unrecoverable costs for each
day that construction was delayed, as well as harm to its reputation and
business goodwill. Id. at 1163–66.
30. Any delay in granting FGT possession of the Subject Easements

will impede its ability to provide the needed energy delivery services that
FERC has already conclusively determined to be in the best interest of the
public.
31. The irreparable injury at stake for FGT outweighs any damage

the proposed injunction may cause these Defendants, which damage is entirely
reparable by the payment of compensation. The right to compensation under
the NGA is not harmed by immediate possession of the Subject Easements,
and “[t]he damages that a preliminary injunction would cause [these]

Defendants, on the other hand, comes down only to any damages that might
result from a defendant losing possession of the property in question sooner,
rather than later, after compensation for the taking has been finally
determined.” Transcon. Gas, 910 F.3d at 1166. The Defendants are guaranteed

the right to just compensation for the condemned property interests, and any
damages suffered based on the timing of the taking are “capable of
determination at the compensation stage of the litigation.” Id. Weighing the
balance of harms supports an award of preliminary relief, where, as in

Transcontinental Gas, the harm to FGT outweighs the harm to these
Defendants from FGT “accessing their properties sooner rather than later,
especially because Defendants should be able to recover all recoverable
damages in full at the compensation stage of the litigation, while [FGT’s]
damages would be irrecoverable.” Id. The relief that FGT seeks in the form of

immediate possession will not harm Defendants’ right to compensation. Any
such damages must and will be remedied with money. Upon the grant of
injunctive relief, there will remain the proceeding to determine just
compensation.

32. Granting FGT immediate possession of the Subject Easements
to construct the Project in a timely manner would serve the public interest.
This conclusion is supported by the NGA and the FERC Certificate. “Congress
passed the Natural Gas Act and gave gas companies condemnation power to

ensure that consumers would have access to an adequate supply of natural gas
at reasonable prices.” Sage, 361 F.3d at 830. Congress did so because supplying
natural gas for the generation of electricity and other energy needs advances
the public interest. Id. (finding pipeline project served public interest because

it would make gas available to consumers and electric power plants, as well as
help local communities to attract new business). This Court, along with other
federal courts in the Eleventh Circuit, have held that supplying natural gas to
generate electricity and to fulfill other energy needs is in the best interest of

the public. Indeed, in affirming the award of a preliminary injunction in a
pipeline condemnation case, the Eleventh Circuit noted that “[a]ny delays in
construction would delay the realization of these public benefits.” Transcon.
Gas, 910 F.3d at 1167 & n.21; see also, e.g., Sabal Trail Transmission, LLC v.
+/– 0.4 Acres of Land in Marion County Florida, 5:16-cv-210-Oc-30PRL, 2016

WL 2997672, at *5 (M.D. Fla. May 25, 2016) (stating that “supplying natural
gas for the generation of electricity and other energy needs advances the public
interest”); Sabal Trail Transmission, LLC v. Estate, 1:16-cv-100, 2016 WL
8919397, at *8 (N.D. Fla. May 23, 2016) (same).

33. Here, FERC determined that the “…Putnam Expansion Project
will not adversely affect FGT’s existing customers as the project is designed to
provide the new service while maintaining existing services. Moreover, there
will be no adverse impact on other pipelines in the region or their captive

customers; the proposal is designed to meet the new incremental demand from
Seminole Electric and is not designed to replace existing service on other
pipelines.” (Doc. 1-5, ¶ 13).
34. Supplying natural gas for the generation of electricity and other

energy needs advances the public interest. Sage, 361 F.3d at 830 (finding
pipeline project served public interest because it would make gas available to
consumers and electric power plants, as well as help local communities to
attract new business); E. Tenn. Nat. Gas, 2006 WL 1133874, at *14 (“[T]here

is a substantial public interest at stake in this case – the need to capture and
supply as much natural gas to the market as soon as possible.”). The Florida
Gas Putnam Expansion Project allows FGT to expand its system to deliver
169,000 dekatherms per day of firm transportation service for Seminole
Electric’s new gas-fired, combined-cycle generating unit, which will replace

and retire an existing coal-fired generating unit. (Doc. 1-5, ¶ 5).
35. To satisfy the requirement under Rule 65(c) of the Federal Rules
of Civil Procedure that a movant give security upon issuance of a preliminary
injunction, FGT proposes to deposit into the Court Registry twice the appraised

value of the parcel.3 This Court finds such security to be sufficient. See
Transcon. Gas, 910 F.3d at 1174 (finding that a security bond equal to twice
the appraised value of the easements was adequate security under Rule 65(c));
Sage, 361 F.3d at 824 (observing the financial strength of the gas company and

its parent corporation would enable payment if the security fell short).
36. In consideration of the foregoing factors, this Court finds that
FGT’s request for a preliminary injunction as to these Defendants should be
granted. The Court conditions the entry of preliminary injunction on FGT

making a cash deposit into the Registry of the Court in the amount of $2,200,
which is twice FGT’s most recent appraisal of the compensation owed for Tract
FLMED-PUTN-011.00. The cash deposit will “blunt” or negate any potential
claim of irreparable harm to Defendants. Sage, 361 F.3d at 829.

Accordingly, it is

3 This appraised value has been reached by Florida Gas’s expert(s) and has not been
tested. It is subject to challenge at the valuation phase of the proceeding.
ORDERED, ADJUDGED, and DECREED:
1. Plaintiff's Motion for Partial Summary Judgment (Doc. 4) is
GRANTED, and FGT has the right to condemn the Subject Easements.
2. Plaintiffs Motion for Preliminary Injunction and Immediate
Possession (Doc. 5) is GRANTED.
3. Upon FGT’s deposit of $2,200 into the Registry of the Court, the
following shall occur:

a. FGT shall have immediate access to, and possession of, the
Subject Easements described in Exhibit A to this Order; and
b. FGT may immediately begin pre-installation activities so
that construction-related activities can commence by August 1, 2021, for
the purposes of constructing the Project.
4, All pre-installation and construction-related activities must be
consistent with the FERC Certificate and all other applicable regulatory
permits.
DONE and ORDERED in Jacksonville, Florida, this Ist day of July
2021.

United States District Judge

Copies furnished to:
Counsel/Parties of Record
17

---

Source: Frix Law Library, https://www.frixlaw.com/law-library/cases/10107846. Public record. Not legal advice.